customer experience & outcomes · switching and fade-to-lock capabilities enterprise...
TRANSCRIPT
Customer Experience
& Outcomes
Dale Trudeau
Manager of IT Operations
OUR SPEAKERS
Carl Jaspersohn
Associate Director of Infrastructure
Nutanix at Imprivata
Dale Trudeau
Manager of IT Systems
4
Imprivata enables healthcare securely by establishing trust
between people, technology, and information.
v28
5
Imprivata OneSign Imprivata Confirm IDImprivata Identity
GovernanceImprivata
PatientSecureImprivata Cortext
Healthcare’s trusted single sign-on and virtual desktop access platform
• Usernames and passwords
replaced with a single
badge tap or fingerprint
scan
• Integrated clinical workflow
automation for every major
EHR and virtual desktop
infrastructure
• Unattended systems
secured with fast-user
switching and fade-to-lock
capabilities
Enterprise multifactorauthentication purpose-built for healthcare
• Most comprehensive
EPCS solution
• Invisible security via
innovative and convenient
authentication methods
• Improved security via
strong authentication for
remote network access,
cloud applications, medical
devices, and other
workflows
Healthcare’s leading identity governance and compliance management solution
• Automated identity management processes
• Strengthened enforcement
of security policies and
compliance management
• Role-based provisioning
providing clinicians
appropriate system access
on day one
Leading positive patient
identification solution
• Improved patient safety
with 1:1 biometric link
between patients and
their medical records
• Increased revenue
capture through fewer
denied claims
• Prevent duplicate
medical records and
overlays to improve
data integrity
Securecommunications tailored for clinical environments
• Comprehensive pager replacement for robust care team communication
• HIPAA-compliant messaging for secure communication of PHI
• Improved clinical productivity with streamlined, context-rich communications
Imprivata product portfolio
6
Our Challenges
• Typical 3 Tier environment and the management challenges that come with it
• Aging Compellent SAN
• Mix of older Dell and Cisco UCS for compute
• Growing resource demands by the Engineering/QA teams were becoming harder to meet
• It was time for an overall evaluation of our infrastructure
7
The Selection Process
• We performed a small POC of Nutanix (3 Nodes) and had many meetings with VCE about Scale-IO
– vSAN was not an option for us as we needed the potential to run a number of hypervisors.
• The manageability and performance of Nutanix was very impressive in our POC.
– I kept hearing from one of my Engineers “THIS IS SO FAST!”
• Ultimately it came down to cost and the fact we were never given a chance at a true POC of Scale-IO
Why We Chose Nutanix
8
Our Initial Configuration: 3 Clusters Prod, Eng & VDI
9
New Additions since Go Live
New Cluster Currently on order:
3 Nodes
Dell XC640
Running Hyper-V
We have also added
two Acropolis File
System (AFS)
environments.
10
• How WTG and Nutanix helped us achieve a no down-time datacenter move from Boston to Needham
Success Story
Questions?
Carl JaspersohnAssociate Director of
Technical Infrastructure
VxRail Implementation
Who is the BAC?
• Boston Architectural College (BAC)
• Independent design college in Boston’s
Back Bay
• Open admission school with a goal to diversify
the design professions
• 97 percent of all BAC students were employed
in their field at the time of graduation
the-bac.edu
Where Were We?
• Traditional 3-2-1 virtualization
stack
• 1gbe iSCSI Equallogic storage
with 7200rpm drives
• Needed to virtualize our
primary database server
the-bac.edu
What Did We Do?
• 3-node all-flash VxRail cluster
• First VxRail deployment that used Winslow’s Professional Services team (Thanks Nathan and Francis!)
the-bac.edu
How Did It Go?
GREAT!
• No Downtime During VM Migration!
• Ability to virtualize other physical servers as they approach the end of their warranties.
• Awesome deduplication/compression!
the-bac.edu
How Did It Go?
What Could Have Gone Better?
• Problems deploying ESRS
• VxRail Manager ability to pull status information
on physical node hardware stopped working
• One 10g switch port the VxRail cluster utilizes
died after everything else was resolved
the-bac.edu
What’s Next?
• 4th Node
4TH NODE
Questions?