current status of design of solid breeder test blanket ... · blanket development group. fusion...
TRANSCRIPT
1
M. Enoeda, Y. Nomoto, S. Suzuki, D. Tsuru, K. Ezato, T. Hirose, H. Tanigawa, H. Nishi and M. Akiba
Blanket Development GroupFusion Research and Development Directorate
Japan Atomic Energy Agency (JAEA)
Current Status of Design of Solid Breeder Test Blanket Module of Japan
14th International Workshop on CERAMIC BREEDER BLANKET INTERACTIONS6–8 Sept. 2006, Petten, The Netherland
2
Contents
1. Design overview of Japan Solid Breeder TBMs2. Possible neutronics diagnostics of TBMs3. Progress of source term identification for safety evaluation 4. R&D milestones and qualification program prior to ITER TBM tests
3
Design Conditions of JA Solid Breeder TBMs
Unit Water Cooled He CooledStructural Material F82HCoolant Water He gasNeutron Multiplier Be, or Be12 Ti Tritium Breeder Li2 TiO3 , or other Li ceramicsSHF (aver., max.) MW/m2 0.3, 0.5NWL (aver.) MW/m2 0.78FW Area m2 0.484x1.66 1.208x0.71Coolant Pressure MPa 15.5 8Coolant Temp.Inlet/ Bypass/ Outlet
oC 280 /325 300/395/500(472)
Heat Deposition MW 0.944 1.08Tritium Production Rate
g/FPD 0.134 0.157
Coolant Flow Rate kg/s 3.59 1.3 (Bypass =0.34 )Coolant Holdup m3 1.5 2.9
4
Modification of the TBM Dimension
Front view of Common Frame for Vertical Modules
JA Water Cooled Solid Breeder TBM
Module dimension 484 x 1660Radial thickness 600
JA Helium Cooled Solid Breeder TBM
Module dimension 1208 x 710Radial thickness 600
Port 18
Port 16
524
1700
Front view of Common Frame for Horizontal Modules
750
1248
5
Concept of JA Solid Breeder TBM’s
First Wall
Concept of Water Cooled Solid Breeder TBM
Plasma side
Tritium Breeder(Li2 TiO3, or other Li ceramic pebble
single size packing, 0.2 2mmφ
depending on the layer width)
Neutron Multiplier(Be, single size pebble bed, 1mmφ)
1st Multiplier Layer
2ndMultiplier
Layer
2nd Breeder Layer
Sub-module structure for internal pressure durability and structure similarity with DEMO blanket (slit structure for electro-magnetic force reduction in DEMO).
2 sub-modules, 2 breeder layers in the WCSB TBM3 sub-modules, 3 breeder layers in the HCSB TBM
1st Breeding Layer
6
Structure of Water Cooled Solid Breeder TBM
1st Breeder
1st Multiplier
2nd Breeder
2nd Multiplier
Consists of two sub-modules
Horizontal View
Vertical ViewModule structure is integrated by EB welding.
7
Structure of JA He Cooled Solid Breeder RAFM TBM
1st breeder
1st multiplier2nd breeder2nd multiplier3rd breeder3rd multiplier
3 Sub-module Configuration with one set of inlet , outlet and bypass coolant pipes
Horizontal View Vertical ViewEBW at rear wall
Drawings shall be modified.
Coolant pipes are unified to one set for minimizing the pipe penetration through the Back Shield of the Common Frame.
8
Test Plan of JA Solid Breder TBM’s
FuCu
Year 1 2 3 4 5 6 7 9 10
Mile Stone First Plasma Full Field, Current & H/CD Power
Short Burn200 MW
Q=10500 MW
Q=10500 MW 400 s
Non-inductiveCurrent Drive
Operation
Equivalent Number of Burn pulses (500 MW x 400 s)Cumulative Neutron Fluence at Test Port (MWa/m2)
1 750 1000 1500 2500 3000 3000
9.9x10-6 0.0074 0.017 0.032 0.057 0.087 0.12
High Duty DTLow Duty DT
D-Plasma(limited T)H-Plasma
Baking & Conditioning
- Machine com- missioning
- Achieve good vacuum & wall condition
- Machine commissioning with plasma
- Heating & CD experiments- Reference scenarios with H
- Commissioning with neutron
- Reference with D
- Short DT burn
- Development of full DT high Q- Development of non-inductive
operation aimed at Q=5- Improvement of inductive and non-
inductive operation- Demonstration of a high duty operation
Installation &Commissioning
Basic Installation & Commissioning For Activation PhaseFor High Duty Operation
Upgrade
Blanket TestPhase
System Checkout & CharacterizationTBM W-1, TBM H-1 TBM W-2,3, TBM H-2,3
Performance TestTBM W-4, TBM H-4- Overall functions,
instrumentation, flow control, heat loss, etc.
- Integrity to EM & thermal loads
- FW heat removal- Ferritic steel effect on
plasma control
- Remote handling test during shut down
- Neutronics environment measurement
- Indication of tritium production & extraction
- Indication of heat generation
- High grade heat generation and extraction
- Continuous tritium recovery- Electricity generation with TBM w-3
System Checkout &Test EnvironmentMeasurement
NeutronicsMeasurement Thermo-mechanical Test
T and Heat Production (long term)TBRTest
TestKey Words
Refurbishment, Replacement
9
Possible Neutronics Instrumentation1. Energy spectrum and transient trends of neutron flux are favorable
data. For these data, pneumatic systems and micro fission chambers are possible instrumentation.
Neutronics Instrumentations
2. Pneumatic systems may not be available in ITER, from safety point of view
3. Micro-fission chambers (U235 and U238) for thermal and fast neutron are most possible instrumentation.
10
Source Term Evaluation (Tritium and ACP)
11
Tritium Control of WCSB TBM
HT, HTO to T Plant
TBM Cooling System
TBM inside V.V. boundary
Com mon Frame
Port Cell Shaft
TCWS Vault
HX
ITER Heat Rejection System
TBM T Recovery System T BuildingGB
123
4
5
6
7
1: Plasma P. Cool. 4: Purge Gas out 7: TRS to T plant
2: Breeder P. Cool. 5: P. Cool. out 8: Drain water waste storage
3: Breeder P. Cool. 6: P. Cool. 2 Cool.
Drain Tank
HTO waste storage
8
Major source terms: Tritium release in breeder, Permeation to primary coolant
12
Tritium Release & Inventory Characteristics
Please see the presentations of Mr. Kinjo, Prof. Nishikawa, Ms. Sasaki in Session 3.
13
Estimation of Permeation Rate to Primary Coolant
(1) Permeation into the FW cooling water by implantation was estimated using equations by Doyle and Brice*.J2 =φα[(1+W)/{W+α(γ2+ 1 )}] (1)W=(φR/D1 )(k1 /φ)0.5 (2)α=(R/xo )[(xo /δ)/{exp(xo /δ)-1}] (3)γ=exp(xo /xs )(kl /k2 )0.5 (4)1/δ=1/xD +1/xs (5)xD =xo kB To /ED (6)xs =-xo kB To /Q* (7)To = T1 T2 /(T1 -T2 ) (8)D=1.07 10-7exp(-0.145/kB /T)k=9.40 10-26 (500/T)exp(-0.118/kB T)(2) Permeation from purge gas to cooling tubes was estimated by Serra’s paper**.Φ=DKP-0.5S/xo (9)DK=3.18 10-8exp(-0.4219eV/kB T) mol s-1m-1Pa-0.5 (10)(3) Permeation reduction factor (PRF)
Permeation Rate = (Original Permeation Rate) / (PRF)
*B. L. Doyle, D. K. Brice, Radiation Effects, 89 (1985) 21.**E. Serra et al., J. Nucl. Mater., 245 (1997) 108.
14
Currently Available Permeation Data
15
Estimated Permeation Rate to Primary Coolant of TBMs
Tritium partial pressure at outlet of purge gas line
WCSB TBMAFW =0.89m2, TFW =293-550ºC,
ABr =1.47m2, TBr =340ºCFlux=1.56x1019/m2s
HCSB TBMAFW =0.95m2, TFW =370-
550ºC, ABr =1.51m2, TBr =510ºC
Flux =1.56x1019/m2sg/FPD/module g/FPD/module
Breeder Layer (T2 = 1 Pa) 6.3x10-5 2.1x10-4
FW implantation 9.6x10-5 4.6x10-4
16
Estimated Tritium Permeation Amount to Primary Coolant of TBMs in 0.12 MWa/m2
Tritium partial pressure at outlet of purge gas line
WCSB TBM HCSB TBMBq/m3 in 1FPD* Bq/m3 in 1FPD*
Breeder Layer, T=1Pa 1.26 x 1012 1.47 x 1012 ( 9.62 x 1011)**Bare FW implantation 1.3 x 1012 3.23 x 1012 ( 9.62 x 1011)**
Be 5mm FW implantation*** 4.9 x 1010 – 1.2 x 1011 1.2 x 1011 – 3.0 x 1011
* (1) Water holdup of WCSB primary cooling system is 1.5 m3. (2) Helium holdup of HCSB primary cooling system is 2.9 m3.
** 1Pa T2 partial pressure is equivalent to about 9.62 x 1011 Bq/m3. ***Permeation rate in Be is more than 1 or 2 order of magnitude smaller than Fe.Tritium concentration limit of the in-vessel components cooling water is 1.81 x 1012 Bq/m3.
17
Activated Corrosion Products (ACP)
0 500 1000 1500Duration (h)
0
1
2
3
4
Wei
ght g
ain
(mg/
cm2 )
743K
717K
653K
NF616 at 773K
-9Cr1Mo at 839K
108
109
1010
1011
1012
1013
0 10 20 30 40 50 60 70Radial location from FW [cm]
Indu
ced
activ
ity[B
q/cc
]
1 s1 min1 h1 day1 week1 month1 year
FW
Distribution of Total Induced Activation in Water Cooled TBM after 0.3MWa/m2
irradiationMeasured data of corrosion rate of F82H by high pressure and temperature water
From the induced activation analysis and experimental data of corrosion rate, induced activity is estimated to be about 4.1x1013 Bq/kg.
Using corrosion rate data, maximum ACP is estimated 9.64 x 1011 Bq.
18
Source term evaluation
Tritium1. In the case of HCSB, maximum accumulation of tritium permeation
can be limited to 9.6x1011 Bq/m3, which is the equilibrium tritium concentration of He purge gas.
2. In the case of WCSB, by using permeation reduction factor of 100, the maximum accumulation of tritium in coolant water can be limited to 1.4x1012 Bq/m3.
3. Currently available permeation data is limited for the most clean surface and the data include the large uncertainty (one or more orders of magnitude). The realistic data with oxidized surface is not evaluated well. Especially the permeation data of gas to high temperature water through the structural material need to be obtained.
ACP1. ACP of WCSB is estimated to be 9.64 x 1011 Bq.
19
Time Schedule of Solid Breeder TBM’s Development in Japan
ITERProject
FY 2020
BlanketDevelopmentPhase
20102000
Module #1
2005 2015
ElementalTechnol.
R&D
ConstructionEDA
Module #2Start Fabrication
CTA/ITA
Start Fabrication
Fusion Power Demonstration Plant
TBM TestsOperation
•In-pile R&Ds
•Out-pile R&Ds
Test BlanketFabrication
PrototypeDevelop-ment
Out-pile overall Demonstration Tests
Elemental R&Ds on Fabrication Tech.
Engineering R&Ds with large scale mock-ups
Elemental R&Ds on Irradiation Tech.
Elemental R&Ds
Engineering R&Ds on Irradiation Tech., Pebble Fabrication Tech.
Irradiation Tests on Module #2
TPR Evaluation with a full module structure
OverallsystemTests
TPR evaluation with simulated blanket structure
Demonstration Tests for Basic
Option
Out-pile Overall Demonstration Testsof Advanced Module
Irradiation Tests on Advanced Module
TPR Evaluation with a Full Structure of Advanced Module
Overall system Testsfor Advanced Module
Irradiation in Fission ReactorsIFMIF
Basic Research on Blanket Neutronics
Basic Research on Blanket Tritium Recovery Process
•Tritium Recovery System Development
•Neutronics / Tritium Production Tests with 14MeV neutrons
Optimization Verification Qualification/ImprovementStructuralMaterial R&D(RAF/M)
Blanket R&D
DesignDecision of construction
Engineering R&D
20
Major milestones of JA Solid Breeder TBM
OutpileR&D
NeutronicsTest
2009• 1/1 Module Mockup Heat Load Tests (1.3 MW/m2 + simulated internal heating x 3000 cycle)• Be FW HHF test (1.3 MW/m2 x 3000 cycle)
Qualification of TBM integrity
In-pileR&D
2009• Breeder pebble:>0.32%LiBU/1.04 dpa*• Be pebble:320 appmHe/0.8 dpa*• In-situ tritium recovery data by pebble bed mockup >0.12MWa/m2*
Confirmation of tritium recovery and mechanical integrity of beds
2009• Neutronics tests by 14 MeV fusion neutron using simulated TBM mockup
Evaluation of neutronics performance and tritium production rate for TBM structure
*TBM 10 (0.12MWa/m2)
StructuralMaterialR&D
2009• Irradiation data upto 1.2dpa by fission reactor• Extrapolation evaluation to fusion neutron irradiation of 3dpa
Pre-selection of material spec. for DEMO and standard data for TBM structure
2014: Delivery of TBMs to the ITER site2010: Start TBM fabrication2010: Final Design Report/ Safety Report/ Material Specification
21
Qualification ProgramMajor Milestones:– 2008 Material Selection Report
• Chemical Composition• Physical Properties• Mechanical Properties, including bonding parts
– 2008 Fabrication Technology Report• Influence of Component Fabrication Process on Physical/Mechanical
Properties• Neutron Irradiation Effects on Physical Properties, up to 1-2 dpa• Corrosion Behavior
– 2010 Final Design Report, Safety Report, Material Specification Report• Detailed design of TBMs, which includes fabrication procedure and
qualification control, and also includes safety evaluation.• Mock-up qualification tests included:
– Fabrication of scalable mock-ups, ~1/2 ~ full size, which should be the same fabrication procedure of the TBM
– Mechanical tests of representative TBM specimens– HHF tests: 0.5MW/m2, 10,000 cycles
22
Summary
1. DDDs of Water Cooled Solid Breeder TBM and Helium Cooled Solid Breeder TBM were generated. They include structure design of thermo-mechanical TBMs, their performance analyses and R&D achievements and plan.
2. For diagnostic system of TBM, micro fission chamber system is considered. It is necessary to assess the availability of pneumatic system for activation foil measurement.
3. Information for safety assessment of TBMs, for ITER preliminary safety report (RPrS), are being prepared. Interim reports for WCSB and HCSB were submitted.
4. Qualification program has been defined, on the basis of the R&D achievement, toward TBM construction.