cur recommendation 102_inspection and assessment of concrete structures in which the presence of asr...

Upload: ec02160

Post on 03-Jun-2018

220 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    1/31

    CUR - Recommendation 102

    | 1

    Recommendation 102

    Inspection and assessment ofconcrete structures in which thepresence of ASR is suspectedor has been establishedAn alkali-silica reaction (ASR) is a reaction between the alkalis present in the pore

    water of concrete and certain components of the aggregate that contain reactive silica.

    The reaction leads to the formation of a gel, which expands when it absorbs water. As a

    result of this expansion cracks are formed and the mechanical properties of the concrete

    may change. This may have an adverse effect on the behaviour and the load-bearing

    capacity of the structure. ASR is characterised by a crazed pattern of cracks. Depending

    on the design of the structure and stresses in the material, however, more or less straightcracks may also occur.

    It is important to recognise the presence of ASR in view of its potential consequences

    for the load-bearing capacity and the structural safety of the structure. This

    Recommendation provides a procedure on the basis of which it can be established

    whether cracks that are present are actually caused by an alkali-silica reaction in the

    concrete. To be able to estimate the effect on structural safety a procedure is described

    in this Recommendation for gathering all the material characteristics required of the

    structures in question, including strength properties. In this CUR Recommendation

    guidelines are provided for the structural assessment of a number of specific structures

    on the basis of these material properties. Finally, this Recommendation also discusses

    the maintenance measures that are to be taken when ASR is present.

    At the time this Recommendation was published CUR Research Committee C 106,

    Structural aspects of alkali-silica reaction in concrete structures, had the following

    members:

    ir. J.D. Bakker (chair), ir. C.A. van der Steen (secretary and reporter), ir. G. Chr.

    Bouquet, dr. M.A.T.M. Broekmans (corresponding member), ing. J. Dudar, ir. J.

    Hartogsveld*, ing. N. Kaptijn*, ir. E.J.C. Rademaker, ir. R. van Selst, ir. A.J.M.

    Siemes*, dr. ir. C. van der Veen*, drs.E. Vega (coordinator) en W. Buist (mentor).

    The structural section, chapter 8, of this Recommendation was prepared by a designers

    working group, consisting of the committee members above indicated by an *, together

    with ir.G.G.A. Dieteren, ir.U. Frster, ir.F.B.J. Gijsbers, dr. ir.E. Schlangen and ir.

    J.A. den Uijl. Furthermore, an important contribution to establishing the calculation

    methods in this Recommendation was made by ir.A.J. Wubs.

    CUR Recommendation 102 was approved by the General Regulations Committee

    Concrete and is supported by NEN/CUR Committee 353 039 / RC 12 Concrete and

    NEN/CUR Committee 353 001 09 / RC 20 TGB concrete structures.

    This Recommendation was found to be consistent with NEN 6702, NEN 6720, NEN

    6723, NEN-EN 206-1 and NEN 8005.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    2/31

    CUR - Recommendation 102

    2 |

    content

    1 Subject 4

    2 Area of application 4

    3 Terms and definitions 4

    4 Classification 54.1 Inspection and study classes 54.2 Reporting 84.3 Specification of study and reporting, data 8

    5 Nature and scale of the study 95.1 General information 95.2 Exploratory inspection 95.2.1 Contents of inspection 95.2.2 Performance method 10

    5.3 Technical study 105.3.1 Contents of study 105.3.2 Performance method 105.4 Targeted study 115.4.1 Contents of study 115.4.2 Performance method 115.4.3 Establishing the reinforcement configuration 125.5 Structural study 125.5.1 General information 125.5.2 Contents of study 13

    6 Sample-taking 136.1 General information 136.2 Marking and drilling 146.3 Treatment of drilled cores 146.4 Repairing drilled holes 14

    7 Measuring and assessment methods 14

    7.1 Crack pattern, crazing 147.2 Cumulative crack width 147.3 Assessment of data and structure 167.3.1 Assessment of data 167.3.2 Assessment of structure 17

    7.4 Polarisation and fluorescence microscopy (PFM) 177.4.1 Procedure 177.4.2 Aspects to be established 177.4.3 Microscope requirements 187.5 Uniaxial tensile strength 187.5.1 Determination of the uniaxial tensile strength 187.5.2 Verification of uniaxial tensile strength measured 187.6 Compression strength 19

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    3/31

    CUR - Recommendation 102

    |3

    8 Structural analysis 19

    8.1 Analysis principles 198.2 Deflection verification 198.3 Verification of shear forces 198.3.1 Principles 198.3.2 Design value of shear stress according to NEN 6720, based on average tensile strength 208.3.3 Design value of shear stress based on experimental research 20

    8.3.4 Upper limit of the design value of shear stress 218.3.5 Special load combinations 228.4 Punch and torsion 22

    9 Reporting 22

    9.1 Class A 229.2 Class B 229.3 Class C 229.4 Control strategy and control measures 239.4.1 Data required for control measures 239.4.2 Specification of control measures 23

    Titles of standards and CUR Recommendations stated 25

    Appendix A Preparation of fluorescent epoxy 26Appendix B Preparation Of Thin Sections 28

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    4/31

    CUR - Recommendation 102

    4 |

    1 Subject

    This CUR Recommendation provides procedures and guidelines for:

    establishing whether an alkali-silica reaction (ASR) is present in concrete;

    establishing the relevant material properties;

    assessing a concrete structure for ASR, whereby methods are given for the structural

    assessment of a number of specific structures.

    In addition to this, possible control measures are discussed. These depend on the extent

    of the damage by ASR.

    2 Area of application

    This CUR Recommendation applies to concrete structures in the Netherlands. The

    structural assessment methods in chapter 8 of this Recommendation are only valid for

    certain structures with structurally deleterious ASR. More specifically, the calculation

    methods determined from experimental research (8.3.3) may only be used if:

    it concerns plate-shaped structures (plates, walls) with a thickness of at least 400

    mm;

    a bidirectional reinforcement (in one plane) is used in these plates;

    the damage by ASR has resulted in delamination parallel to the plane of the plate;

    this has resulted in anisotropy of the uniaxial tensile strength.

    3 Terms and definitions

    3.1 Alkali-silica reaction (ASR):the reaction of certain components of aggregate containing

    reactive silica with the alkalis that are present in the pore water of concrete, which leads

    to the formation of gel-like reaction products.

    3.2 Structurally deleterious ASR: the situation whereby the occurrence of ASR results in

    deterioration of the mechanical properties of the concrete to such an extent that this

    affects structural safety and usability.

    3.3 Exploratory inspection: a mainly visual assessment of the structure with the aim to

    establish whether any (deleterious) ASR may be present.

    3.4 Technical study: a study performed on the structure and in a laboratory to establish

    whether ASR is actually present, including exploratory tests to determine whether

    material properties, such as compression and tensile strength, have been adversely

    affected.

    Explanation

    These reaction products may absorb pore water, which makes them swell up and

    exert pressure within the concrete. As a result of this, some of the mechanical

    properties will initially deteriorate, including the tensile strength, and the concrete

    may eventually start to crack. The deterioration of mechanical properties can be

    deleterious to the structure.

    Explanation

    For newly to be built concrete structures, please refer to CUR Recommendation 89

    Measures to prevent damage to concrete by alkali-silica reaction (ASR).

    The limitation to concrete structures in the Netherlands is necessary, as the

    calculation methods were derived from Dutch calculation regulations or as these

    calculation regulations are used for the assessment. The limited applicability of

    calculation methods determined by experimental research stems from the fact that

    only the structure described was studied.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    5/31

    CUR - Recommendation 102

    |5

    3.5 Targeted study: a study with the aim to determine the strength properties of the concrete

    affected by ASR more extensively.

    3.6 Structural study:a study into the structural consequences for the concrete affected by

    ASR.

    3.7 PFM (polarisation and fluorescence microscopy):a microscopic research technique that

    is applied on very thin, impregnated preparations of concrete in order to obtain an imageof the microstructure of the cement paste, the water-cement ratio, the type of cement,

    the lithological composition of the aggregate and any converted substances in it, the

    presence of cracks as well as the spatial distribution and the homogeneity of these

    properties.

    3.8 Reactive silica:the amorphous or low-crystalline silica present in some aggregates that

    reacts faster with alkalis on the basis of its less well-ordered crystal structure and/or its

    greater specific surface area compared to coarse crystalline quartz.

    3.9 Relative cumulative crack width ASR: an indicative measure for the extent to which

    cracks have formed that is determined by adding all the widths of the cracks that

    intersect with a measuring line placed along a cracked area of the structure and then

    dividing it by the length of the measuring line.

    3.10 Structural risk: a measure for the seriousness of the consequences relating to the possible

    presence of ASR.

    3.11 Control strategy: the strategic choice of the period in which and level at which a

    structure will be maintained by performing control measures.

    3.12 Control measure: the package of measures that are to be taken immediately and in the

    future to keep a structure in a prearranged condition or to achieve a predetermined

    situation.

    4 Classification

    4.1 Inspection and study classes

    The class of inspection and/or nature and scale of the study to be performed must be

    agreed upon in advance by reporting a class as stated below. It is possible to agree onseveral different classes at the same time (see table 1).

    Explanation

    Examples of control measures are reinforcing the structure or measures to delay or

    prevent the progress of the damage mechanism, such as limitation of the moisture

    load.

    Explanation

    The structural risk is determined by analysing the reinforcement configuration and

    the consequences of the damage observed for aspects such as safety and functioning.

    Explanation

    Well-known reactive components are opal, chalcedony, moganite, cristobalite,tridymite, cryptocrystalline quartz, (porous) flintstone (silex / chert / flint), impure

    sandstone (grey wacke, siltstone), siliceous limestone and certain types of volcanic

    rock due to the glass that is present in it.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    6/31

    CUR - Recommendation 102

    6 |

    Class I Exploratory inspection

    The purpose of this inspection is to find out whether ASR is present in the structure or

    whether the cracks that were observed are more likely to have a different cause.

    Class II Technical study

    The purpose of this study is to confirm that ASR is indeed present, as well as to obtain

    an initial indication of the seriousness of the damage. Among other things, this is done

    by establishing whether a relatively low uniaxial tensile strength is present.

    Class III Targeted study

    The purpose of this study is to gather more information in a targeted manner, to be able

    to determine reliable material properties on the basis of this, among other things, for the

    structural assessment calculation and the specification of control measures.

    Class IV Structural study

    The purpose of this study is to obtain an insight into the structural safety of the

    structure. The structural study is divided into:

    Class IVA Manual inspection of transverse forces in representative cross-sections,

    either with or without basic calculation software.

    Class IVB Numerical inspection of transverse forces in representative cross-sections.

    Class IVC Structural assessment of the entire structure.

    A representative cross-section is the cross-section in which the modified mechanical

    properties of the concrete have the greatest effect on the load-bearing capacity and the

    structural safety of the entire structure.

    Figure 1 shows the relationship between the various components. The various studies

    are specified in more detail in 5.2 to 5.5.

    The diagram in Figure 1 will only have to be followed if the structural risk is medium

    or high, see 7.3.1.

    Explanation

    To assess the structural safety calculation models are used that are only valid for

    certain structures, see 8. The determination of representative cross-sections requires

    a good structural understanding and can therefore best be left to an experienced

    structural engineer.

    Explanation

    The tests described in this Recommendation serve as a supplement to the inspection

    and test methods in CUR Recommendation 72, Inspection and testing of concrete

    structures, and describe tests that are related to ASR in more detail. In certain cases

    it is recommended to ascertain whether it is desirable to perform an inspection or

    study according to CUR Recommendation 72 at the same time, supplementary to a

    study according to this Recommendation.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    7/31

    CUR - Recommendation 102

    |7

    Figure 1 Flow chart for inspection and studies

    Explanation of flow chart

    In the flow chart used the various study classes are described in a mutual context.

    Generally speaking, an increasing amount of information is obtained from top to

    bottom in the flow chart, whereby the study effort also increases. Please note that a

    step-by-step approach was chosen, whereby different levels of study are performed

    in succession. In some situations the additional costs and nuisance (traffic measures)

    may be such, that it will be better to decide to take all the samples in advance, in

    anticipation of a possible targeted study in the laboratory. With regard to this, it is

    important to have a clear image of the desired results of the study in advance. The

    studies mentioned will only be useful in practice if the structural risk is medium or

    high.

    Y

    Y

    Y

    Y

    Y

    N N

    N

    N

    N

    N

    Class I

    exploratory inspection

    Class II

    technical study

    Class III

    targeted study

    Class IV

    structural study

    ASR

    possible

    ASR

    Indication of low

    tensile strength

    Safety now

    guaranteed

    Report

    Report

    Report

    Report with

    safety

    measures

    Possibly further

    study into cause of

    cracks

    Low tensile

    strength

    Report

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    8/31

    CUR - Recommendation 102

    8 |

    4.2 Reporting

    Based on their contents, reports are divided into:

    Class A Reporting of data.

    Class B Reporting of data and measures to be taken.

    Class C Reporting of data and control measures to be taken.

    For the contents of the reports, please refer to chapter 9.

    4.3 Specification of study and reporting, data

    In order to determine which study is required and which type of report is to be prepared,

    at least the following must be agreed:

    a. the type of inspection or study, based on the classification in 4.1;

    for an exploratory inspection it must also be agreed whether the pattern of cracks

    is to be recorded in accordance with 7.1;

    for a technical study it must also be agreed whether impregnated cores are to be

    assessed;

    for a targeted study it must also be agreed whether the reinforcement

    configuration is to be determined;

    b. the method and contents of the required report, based on the classification in 4.2.

    Prior to an inspection or study of a concrete structure at least the following data must be

    available:

    the definition of the problem relating to the inspection or the study;

    the location of the structure to be studied;

    the nature and type of the structure;

    the shape and size of the structure;

    the age of the structure and, where available, the design life;

    the component or components of the structure to be studied;

    whether any previous studies have been performed on these components or thestructure;

    the accessibility of the structure as a whole and of the most important structural

    components at which the study is aimed;

    the possibilities of closing-off the building site as well as the need to take traffic

    measures.

    If a structural study is prescribed the following must also be agreed:

    whether the (original) design calculations, verification calculations and reinforce-

    ment drawings are available;

    the number of representative cross-sections that must be tested (see 5.5).

    If any control measures are to be specified, the client should provide information about

    the control strategy that applies to the concrete structure in question.

    Explanation

    Please note that a link exists between the type of study and the possible reports. For

    example, an inspection according to class 1 will provide insufficient data to prepare

    a report according to class C.

    This Recommendation is aimed at identifying ASR and the consequences of it. If

    ASR cannot be identified as a cause or the only cause of the cracks observed, it is

    advisable to have these cracks and the consequences of them assessed further by an

    expert. It may also be useful for maintenance purposes to obtain information about

    other defects and shortcomings in the structure. For the recording of a study different

    to one concerning ASR, please refer to the various inspection classes that are statedin CUR Recommendation 72.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    9/31

    CUR - Recommendation 102

    |9

    5 Nature and scale of the study

    5.1 General information

    In this chapter the inspection and studies stated in 4.1, which may either be performed

    separately or together, are described in more detail.

    When prescribing a particular study or a combination of studies the intended objective

    must be clear, for example, merely determining whether ASR is present or, for example,

    answering the question of whether the structural safety is still guaranteed. Table 1indicates which study is required to obtain a particular result.

    Table 1 Overview of relevant questions and studies required

    Scale of study at least

    Exploratory

    inspection

    Technical study Targeted study Structural studyQuestion

    See 5.2 See 5.3 See 5.4 See 5.5

    Could ASR have occurred? To be performed

    Could the mechanical properties

    have been affected in a negative

    manner?

    To be performed To be performed

    Has ASR currently led to a

    structurally unsafe situation?

    To be performed To be performed To be performed

    5.2 Exploratory inspection

    5.2.1 Contents of inspection

    For each component to be studied, an exploratory inspection must at least consist of the

    following:

    Establishing whether a crazed pattern of cracks is present, which is the case if the

    cracks are more or less perpendicular to each other. The crazing may exhibit apreferred direction, for example, due to the forces in the structure.

    Establishing whether the crazing is uniform over the entire surface or whether there

    are areas with limited crazing and areas with a large amount of crazing.

    Identifying other cracks and crack patterns, whereby at least the following is recorded:

    the shape of the cracks, the crack distance, the crack width and an estimate of the

    cumulative crack width.

    If this has been agreed, the crack pattern should also be recorded in accordance with 7.1.

    The following must also be recorded for the structure that contains the component to be

    assessed:

    Any visually identifiable expansion and deformation of the structure, for example,the structure being out of centre at joint interfaces, lopsidedness of bearings as well

    as unusual curvature, lopsidedness or shifting of faces.

    Explanation

    The reliability of statements relating to the damage, the consequences and the

    measures to be taken is determined for a large part by the study. For example, an

    exploratory inspection provides an insufficient basis for specifying control measures.

    Table 1 shows which studies are considered to be required at the least to be able to

    make a particular statement.

    If any previous studies were performed on the structure, either with regard to ASR or

    other types of damage, it will be useful to provide this information as well.

    Depending on the nature and scale of the previous study it may be decided to limit

    the study described in this Recommendation.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    10/31

    CUR - Recommendation 102

    10 |

    Any environmental factors relating to the moisture load, for example, for car decks

    the possibility of loads exerted as a result of de-icing salts and excessive forms of

    moisture load as a result of the design and/or inadequate drainage of the structure.

    Any secretion of alkali-silica gel present or the spalling of pieces of concrete for

    reasons other than reinforcement corrosion.

    The presence of a coating or signs of concrete repairs performed previously. In

    particular, the possibility must be taken into account here that a coating may hide

    previous damage by ASR that was repaired.

    5.2.2 Performance method

    Where agreed, the pattern of cracks must be recorded in accordance with 7.1 in at least

    three locations where the most severe form of crazing is visible.

    5.3 Technical study

    5.3.1 Contents of study

    The technical study must at least consist of:

    Removing drilling cores for polarisation and fluorescence microscopy (PFM test)

    and to determine the mechanical properties.

    Recording the relative cumulative crack width according to 7.2 in at least 3 locationswith a crazed pattern of cracks.

    An analysis of the structure on the basis of information provided, see 7.3.1,

    including any exploratory inspections performed.

    A verification of the tensile strength of the cores measured against the designed

    tensile strength and the low tensile strength criterion according to 7.5.2.

    5.3.2 Performance method

    For the technical study a sufficient number of cores with the correct length must be

    drilled out of the structure or structural components in order to perform the test of the

    mechanical properties and for the presence of ASR. The diameter of the drilling cores

    must be around 75 mm. The length of the drilling cores is derived from the property that

    is to be determined.

    Explanation

    Depending on the size of the object, it may be decided to have the pattern of cracks

    recorded in a greater or smaller number of locations. For possible testing of the

    uniaxial tensile strength perpendicular to the span, in other words, in the plane of the

    element, it is recommended that at least three cores be drilled. To establish thenecessity of a test of the uniaxial tensile strength in the plane of the element, please

    refer to 8.3.1.

    Explanation

    It may be useful to draw and record the pattern of cracks in order to monitor possible

    developments.

    Explanation

    To recognise damage patterns that may be related to ASR, please refer to the ASR

    picture-book, a publication of the Public Works Service of the Directorate-General

    for Public Works and Water Management, which can be accessed via

    www.bouwdienst.nl.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    11/31

    CUR - Recommendation 102

    |11

    The number of cores required and the length of the cores is:

    at least 6 to determine the uniaxial tensile strength according to 7.5, their length

    must be equal to twice the diameter of the core;

    at least 3 to determine the compression strength according to 7.6, their length must

    at least be equal to the diameter of the core.

    The drilling locations of the cores must be spread out over the bad areas, but not on a

    crack and preferably in representative cross-sections in terms of transverse force.

    In addition to the cores stated, it may be necessary to collect additional sample material

    for a PFM test. These cores must have a length of at least 100 mm and should

    preferably be drilled on a crack. The core must also include the outside surface.

    All drilled cores must be assessed visually for signs of ASR. At least one core

    containing material suitable for the PFM test according to 7.4 must be selected from the

    available sample material.

    5.4 Targeted study

    5.4.1 Contents of study

    The targeted mechanical study must at least consist of drilling cores for mechanical

    testing. Where agreed, the reinforcement configuration must also be determined.

    5.4.2 Performance method

    Drilling cores

    The locations where drilling cores are to be removed for the structural test must bedetermined by an experienced concrete maintenance expert with a structural

    understanding, or else in consultation with the structural engineer who is responsible for

    the more detailed structural study. The cores should basically be removed from areas in

    which transverse forces are present.

    Explanation

    Please note that the areas in which the transverse force is normative are particularly

    interesting; more so than areas in which it is at its maximum.

    Explanation

    Additional cores are required for PFM testing, as a sufficient number of cores must

    be available to test the mechanical properties. It cannot be excluded that additionalmaterial is obtained when drilling cores for mechanical testing before the number of

    cores with the correct length stated is collected. This material could be used for PFM

    testing. A drilling core can be used for more than one purpose, provided that its

    length is sufficient.

    Please note that a core with a greater diameter, for example, 100 mm, and a length of

    more than 300 mm may provide more information when this core is fully

    impregnated compared to the minimum dimensions prescribed. This is simply

    because more material will then be available.

    By impregnating cores with a fluorescent resin a greater insight is obtained into the

    cause and the severity of the cracks that are present. The presence of ASR is often

    shown with PFM, but it is difficult to ascertain whether ASR really is the primary

    cause of the cracks that are present due to the limited dimensions of the test piece. Abetter insight is obtained by impregnating entire cores.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    12/31

    CUR - Recommendation 102

    12 |

    A sufficient number of cores must be drilled from each area designated for the test. The

    diameter of the drilling cores must be around 75 mm. The number of cores must be:

    at least 3 to determine the uniaxial tensile strength according to 7.5, their length

    must at least be equal to twice the diameter of the core;

    at least 3 to determine the compression strength according to 7.6, their length must

    at least be equal to the diameter.

    The cores for the uniaxial tensile strength and compression strength test should

    preferably be taken from one and the same location to prevent weakening as much as

    possible, for example, by drilling a core with a length of at least 250 mm and then

    cutting it into sections.

    If cores were already drilled before in the cross-section in question as part of a technical

    study in accordance with 5.3, the compression strength and uniaxial tensile strength of

    these were determined and if these results are available, the number of cores may be

    reduced in accordance with the number of tests performed before.

    5.4.3 Establishing the reinforcement configuration

    It must be ascertained whether the configuration of the (outside) reinforcement matches

    the reinforcement pattern stated on the drawing. In at least two locations per structural

    component the diameter of the reinforcement present and the type of reinforcement

    must be determined by means of destructive testing. If the reinforcement configuration

    differs this must be discussed with a structural engineer.

    If drawings are unavailable the scale of the study into the reinforcement configuration

    must be such that an image is created of the main reinforcement present in the structural

    component to be assessed that is sufficiently reliable to allow a verification calculation

    to be performed on the basis of it.

    5.5 Structural study

    5.5.1 General information

    Regardless of the type of structural study (IVA, IVB or IVC) at least the followingaspects must be considered:

    cracks as a result of ASR;

    deformation of the structure by ASR;

    the compressive and tensile strength present with special attention for uniaxial

    tensile strength;

    the variation in the uniaxial tensile strength and possibly other mechanical properties

    for each cross-section observed and between the various individual cross-sections

    observed.

    Explanation

    To be able to determine the diameter the surrounding reinforcement will have to be

    cleared away sufficiently. The type of reinforcement can be derived from the profileof the rebar. In consultation, the number of locations where destructive testing is to

    be performed may be limited. The purpose of establishing the reinforcement

    configuration is to obtain an impression of whether the structure was built in

    accordance with the drawings. If this is not the case, a structurally unsafe situation

    may also be present even without ASR. It is therefore advisable to assess the

    consequences of a differing reinforcement configuration first.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    13/31

    CUR - Recommendation 102

    |13

    5.5.2 Contents of study

    A structural class IVA study at least includes:

    A verification calculation of the transverse force on the agreed cross-sections,

    performed either manually or with basic computer software. Here the design

    calculation with regard to the distribution of forces in the structure may be used if it

    is available and usable.

    A structural class IVB study at least includes:

    A numerical calculation of the shear stress present in the agreed cross-sections. In

    this case the modelling of the structure must be performed using shell elements.

    A structural class IVC study at least includes:

    An assessment of the transverse force stated under IVA and IVB.

    A test of the entire structure, taking into account the material properties that were

    derived from the test results in accordance with chapter 8.

    A study according to classes IVA, IVB or IVC does not require a test of the bending

    moment capacity.

    For the assessment method, please refer to chapter 8.

    6 Sample-taking

    6.1 General information

    When removing drilling cores the drilling through structural reinforcement present must

    be prevented as much as possible. To achieve this at least the outside reinforcement

    must be located in advance using a concrete cover meter.

    Prestressed reinforcement must not be drilled through.

    The load-bearing capacity of the structure must not be affected substantially by the

    sample-taking. If this is a possibility, the number of drilling cores to be removed mustbe agreed in advance.

    For each core the following must be recorded:

    The location of the core by indicating the position of the centre of the drilling core on a

    drawing or relative to recognisable parts of the structure with an accuracy of 0.1 m.

    Visually recognisable aspects of the removed core that may be a sign of ASR and

    that provide information about the condition of the concrete, for example, the

    presence of reaction edges around coarse aggregate, stained drying, the presence of

    gel, cracks, a layered structure, honeycombing, construction joints, etc.

    Visually recognisable aspects of the concrete surrounding the core, for example,

    extensive cracking, weathering, moist patches, etc.

    Whether anything unusual has occurred while drilling, for example, breakage whiledrilling.

    Explanation

    Practical tests on severely damaged structural parts and theoretical studies have

    shown that the failure moment does not differ from that of a structural part not

    affected by ASR. The tension in the reinforcement must be allowed to build up

    gradually. The ends of the bars must be located in the zero points of the moments or

    the reinforcement must include hooks or bends that can transfer the force in the

    reinforcement to the concrete. The practical tests were performed on beams cut from

    sheets with severe horizontal cracks, whereby the uniaxial tensile strength in a

    direction perpendicular to the sheet plane had dropped to 1/7 of the expected value

    for the tensile strength based on a splitting test.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    14/31

    CUR - Recommendation 102

    14 |

    6.2 Marking and drilling

    The location and orientation of the core in the structural component to be tested must be

    indicated clearly on both the core and in a drawing or sketch of the structure in question.

    The following must be indicated on the core with a permanent marker:

    An orientation cross on the top face, whereby the axes match the span direction of

    the component and the transverse direction of the component, respectively. Both

    directions must be recognisable by different colours or a pattern of lines.

    Which side of the core was in the original structural surface.

    An unambiguous number of the core.

    The drilling core must be drilled and removed with care. The occurrence of undesirable

    effects such as cracks, which may adversely affect both the observations during the

    PFM test and the values measured during the mechanical study, must be prevented.

    6.3 Treatment of drilled cores

    After removing and assessing the core it must be handled and stored as follows:

    Clean the core immediately after removing it using a minimum amount of water to

    remove any attached material.

    A unique sample number must be applied additionally or again.

    Wrap the core in an uncoloured, hand-wrung cloth and wrap it in self-adhesive film

    to prevent drying-out and damage during transport.

    Place each of the cores in one piece with a diameter-length ratio of 1:2 or more

    slender and cores that already consist of various fragments in a tightly fitting,

    durable plastic tube for transport.

    Short, compact whole cores may be transported after wrapping them in cloth and

    film.

    The number of the drilling core must be printed on the wrapping. The cores must be placed in the means of transport or in additional packaging in

    such a way that they cannot be damaged during the journey to the laboratory.

    6.4 Repairing drilled holes

    Unless agreed differently, drilled holes must be sealed using a cement-based low-

    shrinkage mortar in accordance with CUR Recommendation 54, application class RC2,

    environmental class 3.

    Holes in asphalt must be sealed with liquid asphalt.

    Ancillary materials, such as formwork, must be stripped from the mortar after

    hardening. Drilled holes, etc. must be sealed.

    7 Measuring and assessment methods

    7.1 Crack pattern, crazing

    Crazing must be recorded by marking the cracks on a measuring square, preferably with

    edges of 1 metre in length. The orientation of the measuring square should preferably

    match the orientation of the pattern of cracks.

    7.2 Cumulative crack width

    The relative cumulative crack width ASRmust be determined as follows:

    draw two orthogonal lines within the measuring square;

    measure the crack width wiof all the cracks n that cross the line in question. The

    crack width must be measured perpendicularly to the crack;

    measure the angle ibetween crack iand the edge in question;

    Explanation

    It is recommended to attach the drilling installation to the structure in a fixed

    position and prevent wobbling of the core drill.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    15/31

    CUR - Recommendation 102

    |15

    adjust the crack width wito the direction of the measuring edge according to wi/cos

    I (Figure 2);

    for each measuring line add the corrected crack widths and divide them by length l

    of the relevant measuring line, as a result of which the relative cumulative crack

    width ASRis obtained:

    l

    wn

    i i

    i

    ASR

    =

    =1cos

    in which:

    ASR is the relative cumulative crack width in mm/m;

    l is the length of the measuring line when determining ASR, in m;wi is the crack width of crack iin mm;

    i is the angle between measuring line and crack iwhen determining ASR.

    Figure 2 Principle of measuring Figure 3 Detail of measuring the crack

    the relative cumulative width and angular correction

    crack width ASR

    Instead of the previous procedure, it will also be sufficient to estimate the value of ASR

    for the exploratory inspection. This can be done simply by counting the number of

    cracks n that cross a measuring line with length l. Following this the average crack

    width waveragecan be estimated or roughly measured. Then the relative cumulative crack

    width ASRcan be calculated as follows:

    l

    wn averageASR

    =

    in which:

    ASR is the relative cumulative crack width in mm/m

    l is the length of the measuring line when determining ASR, in mn is the number of cracks

    waverageis the average crack width in mm

    The cumulative crack width that is determined must be classified in a class on the basisof table 2.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    16/31

    CUR - Recommendation 102

    16 |

    Table 2 Classification based on relative cumulative crack width

    Relative cumulative crack width Class

    0 mm/m

    < 0.6 mm/m

    0.6 mm/m to 1.0 mm/m

    1.0 mm/m to 1.5 mm/m

    1.5 mm/m to 2.5 mm/m

    2.5 mm/m

    none

    very little

    little

    limited

    significant

    very significant

    7.3 Assessment of data and structure

    7.3.1 Assessment of data

    The assessment of the available data must at least consist of the following, see table 3:

    Determining the high-risk components with regard to ASR based on the

    reinforcement configuration.

    Determining high-risk components with regard to safety and the functioning of the

    concrete structure.

    A classification of the risk of ASR for a structure (structural risk).

    Aspects that must at least be weighed when determining high-risk components with

    regard to safety and functioning are:

    The feeling or perception of safety.

    The risk of significant consequential damage and/or loss of function as a result of

    continued expansion, for example, the jamming of moving parts.

    The (economic) damage, both direct and indirect, as well as the amount of human,

    emotional and/or social suffering if the structure fails entirely or partially.

    Table 3 Structural risk derived from reinforcement configuration and the conse-

    quences for safety and functioning

    Consequences for safety andfunctioning

    Reinforcementconfiguration

    Notes on reinforcement configuration

    Major Minor

    High-quality 3D

    reinforcement, see Figure

    4, for example

    The concrete is enclosed on all sides. ASR expansion is

    slightly tensioning the reinforcement. This limits the

    consequences.

    Watch out for detachment of the prestress and

    delamination in the plane of the prestress.

    Structural risk

    = medium

    Structural risk

    = low

    3D reinforcement with

    moderate anchoring

    Watch out for detachment of lap joints due to the ASR

    expansion.

    Structural risk

    = medium

    Structural risk

    = low

    2D reinforcement with goodor moderate anchoring or

    no reinforcement, Figure 5.

    ASR expansion concentrated in 1 direction. In thisdirection the tensile strength drops. Layers may form in

    the concrete. The ASR may cause transverse force or

    shearing problems.

    Structural risk

    = high

    Structural risk

    = medium

    Figure 4 Cross-section of beam, column Figure 5 Cross-section of plate, wall

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    17/31

    CUR - Recommendation 102

    |17

    7.3.2 Assessment of structure

    When assessing the structure watch out for signs that may indicate ASR. Special

    attention must be paid here to aspects such as:

    (Restrained) deformation of components.

    Indications of possible failure.

    When indications of possible failure are found for critical components of the structure,

    measures must be taken immediately.

    7.4 Polarisation and fluorescence microscopy (PFM)

    7.4.1 Procedure

    For each PFM study the drilling core with a length of at least 100 mm must be

    impregnated as a whole in vacuum with a UV-fluorescent epoxy resin prepared in

    accordance with Appendix A.After the epoxy resin has fully hardened the impregnated core must be cut lengthwise in

    two pieces and both halves must be petrographically tested for cracks and other relevant

    signs (of damage) as stated in 7.4.2.

    An impregnated thin section must be prepared from at least one of the two halves

    according to the method described in Appendix B. The thickness of the thin section

    must be (20 1) m and the surface area must be at least 30 mm x 45 mm.

    7.4.2 Aspects to be established

    The combined data of the assessment of the impregnated core and the thin section must

    at least establish the following:

    whether any cracks are present or not, assessed for various scale sizes, as well as the

    excessive presence of these; whether any potentially reactive components with regard to ASR are present and

    whether these components actually show signs of a reaction;

    the bonding of the cement matrix to the aggregate;

    the number of aggregate grains affected in the overall concrete (level of ASR);

    a qualitative impression of the amount of gel that is present;

    the lithological composition of the entire aggregate, regardless of any ASR-sensitive

    behaviour assumed or observed;

    the possible type of cement, an indication of the water-cement ratio and the level of

    hydration;

    whether, on the basis of observation, ASR could be the primary cause of any cracks

    observed and whether the ASR observed is more than would be expected for a

    material without a reactive aggregate.

    Explanation

    Due to the reinforcement configuration or an irregular moisture load ASR expansion

    may occur irregularly in the concrete. As a result of this deformations may occur,

    resulting in tensions that were not taken into account during the design, for example,

    as a result of eccentricity in columns.

    Deformation by ASR can be prevented by the surroundings of the components

    affected by ASR. As a result of this tensions may occur in the affected component

    and the neighbouring component. These tensions were often not taken into account

    during the design and in some cases they may result in damage to one component or

    both components.

    Indications of possible failure are large cracks and deformation. Other indicationsare: detachment of lap joints, buckling of components or, if cracks are present,

    mutual shifting of the crack planes.

    For the observations mentioned above no generally decisive criterion can be

    defined. Which measures are to be taken depends on the specific structure.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    18/31

    CUR - Recommendation 102

    18 |

    7.4.3 Microscope requirements

    The assessment of the thin sections must be performed using a stereo microscope with a

    magnification factor of around 50 to 80. To assess a thin section the petrographic

    polarisation microscope must have a blue-light fluorescence system.

    7.5 Uniaxial tensile strength

    7.5.1 Determination of the uniaxial tensile strength

    The uniaxial tensile strength must be determined for cylinders with a diameter of 75

    mm and a length of 150 mm. Both ends of the cylinder must be flattened in a plane-parallel fashion, perpendicularly to the axis of the core. The required smoothness is 0.1

    mm per 100 mm.

    Steel tie plates with a diameter equal to the diameter of the core must be attached to the

    ends by glueing them on.

    The test pieces must be conditioned at 20C and 98% R.H. for at least 2 periods of 24

    hours.

    After sufficient hardening the test pieces must be pulled from the glue in a tensile

    testing machine tester. Their capacity must not be more than 5x the expected tensile

    strength. It must be possible to read the load with an accuracy of 1%. The load must be

    increased gradually at a rate of (0.05 0.01) N/mm2per second.

    The tensile strength must be calculated with an accuracy of 0.1 N/mm2using:

    AF

    ctf =

    in which:

    fct is the tensile strength in N/mm2

    F is the force at failure in N

    A is the surface area of the core in mm2

    If failure occurs directly underneath the pulling head the measurement will be invalid.

    7.5.2 Verification of uniaxial tensile strength measured

    It must be determined whether the uniaxial tensile strength measured is much lower

    than the strength assumed during design. This will be the case if the following applies:

    bm,ref< 0,7 (1,00 + 0,05 c,design)

    in which:

    fbm,ref is the average uniaxial tensile strength based on test pieces in accordance

    with 7.5.1, in N/mm2;

    cc,design is the average cube compressive strength used during design, in N/mm2;

    0.7 is the conversion factor to convert the splitting tensile strength into uniaxial

    tensile strength.

    Explanation

    For the best possible results the following characteristics are recommended for the

    fluorescence filters:

    A so-called band-pass excitation filter for blue light with a wavelength range

    of 450 to 490 nm.

    An emission filter for green light for a wavelength of 515 nm or more.

    A frequency splitter (beam splitter) that is centred around a wavelength of 510

    nm.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    19/31

    CUR - Recommendation 102

    |19

    7.6 Compression strength

    The compression strength of cylinders (diameter equal to height) must be determined in

    accordance with CUR Recommendation 74. The lowest value measured, using at least 6

    cylinders, is the value for the characteristic compression strength present.

    8 Structural analysis

    8.1 Analysis principles

    a. Regardless of the type of structural study (IVA, IVB or IVC) it must be established

    whether one of the following may be the case due to the deformation of the

    structure:

    changes to the distribution of internal forces;

    changes to the eccentricity of normal forces;

    additional external loads to the structure due to kinematical restraint of swelling

    deformation, for example, a bridge deck that rubs against abutment.

    If the deflections in the structure are smaller than the allowable deflection according

    to NEN 6702 or if the eccentricities are smaller than 30% of the eccentricity to be

    taken into account according to 7.3.4 of NEN 6720 the changes mentioned above

    will not require further structural consideration.

    b. The structural analysis must be based on NEN 6702, NEN 6720 or NEN-EN 206-1

    with the accompanying NEN 8005 and, for bridges and similar structures, NEN

    6723.

    c. Contrary to the standards and regulations mentioned above, the material strengths

    derived from the test results using the method described in this chapter must be

    used.

    8.2 Deflection verification

    For a structural analysis of the structure in accordance with this Recommendation no

    verification of bending is required, see the explanation of 5.5.2.

    8.3 Verification of shear forces

    8.3.1 Principles

    a. The verification of shear forces and the calculation of the calculation value of the

    resulting shear stress must be performed in accordance with 8.2.1 and 8.2.2 of NEN

    6720:1995, respectively.

    b. To calculate the design value of shear stress the calculation methods in 8.3.2 must be

    used. If c has been met the calculation methods in 8.3.3 may also be used, whereby

    the more favourable result may be used.

    c. The calculation methods in 8.3.3 may only be used if the conditions stated in it are

    met.

    d. For the design value of shear stress 1no value greater than the upper limit accor-

    ding to 8.3.4 may be taken into account, regardless of the value calculated in 8.3.2 or

    8.3.3.

    Explanation:

    For the calculations in this Recommendation it was assumed that ASR causes a

    significant reduction in the uniaxial tensile strength perpendicular to the plane of the

    element, which was also established in the experiments on which the calculation

    methods are based (see explanation 5.5.2).

    It may happen that the uniaxial tensile strength is relatively low, both in the plane of

    the element and perpendicular to it, even without ASR. In that case the calculation

    methods included in 8.3.3 may not be used.

    If a low uniaxial tensile strength is measured compared to the original compressive

    strength, it is strongly recommended to complete the flow chart in figure 1 to

    determine the structural safety or to determine which control measures to take.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    20/31

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    21/31

    CUR - Recommendation 102

    |21

    If these conditions are met the calculation value for the design value of shear stress 1

    may also be calculated from:

    mmld /6,0 ,11 =

    in which:

    0.6 is a coefficient used for determining the characteristic lower limit of thedesign value of shear stress from the average ultimate design value of shear

    stress 1,m;ld is a factor for calculating the long-term tensile strength of the concrete (=

    0.9);

    1,m is the average ultimate design value of shear stress, in N/mm2;

    m is the material factor (= 1.5).

    The effect of any transverse force reinforcement that may be present must not be taken

    into account. If the calculated value is more favourable than the value calculated

    according to 8.3.2, the calculated value may be used, taking into account the maximum

    value stated in 8.3.4.

    The average ultimate value of shear stress 1,mmust be calculated with the formula:

    )'.( 90,,0,,1 bmdctrefctdSI

    m ff +=

    in which:

    I is the second moment of area of the cross-section that is assumed to be

    uncracked, in mm4

    d is the effective depth, in mm

    S is the largest value for the first moment of area of the cross-section, in mm3

    bmd is the average concrete compressive stress in the cross-section due to thenormal force generated by the prestress load and the other loads on the

    structure (+bmdfor pressure; -bmdfor tension), in N/mm2;

    ct,0,ref = bm,ref: the average uniaxial tensile strength of n test pieces. The tensile

    strength must be determined in a direction perpendicular to the axis of the

    structural component, in N/mm2;

    )'05,01( ,,0,90, measuredccrefctct fff += , in N/mm2

    in which:

    cc, measuredis the measured average cube compressive strength, in N/mm2.

    8.3.4 Upper limit of the design value of shear stress

    The maximum value to be used for 1is

    1 030 4= , f k kb h (1not smaller than 0.4 fb)

    Explanation

    The material factor m of 1.5 is a rather safe value due to model uncertainties (as the

    formulas are based on a limited number of experiments). In the formula forfct,spl it is

    tacitly assumed that the value of 1 is a fixed value. This is not actually the case. The

    value is subject to scatter and the formula too is an approximation of reality, based

    on the best line that can be fit through a large number of test results.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    22/31

    CUR - Recommendation 102

    22 |

    For an explanation of k, khand 0and the values to be used for these, please refer to

    8.2.3.1 of NEN 6720. The value for fb must be calculated from the characteristic

    concrete compression strength as stated in 6.1.2 of NEN 6720. However, a value of 0.9

    can be used for the long-term strength.

    8.3.5 Special load combinations

    For special load combinations the factor for the long-term effect (ld= 1.0) is no longer

    used and mcan be reduced to

    - m= 1.1 for a calculation according to 8.3.2;

    - m= 1.25 for a calculation according to 8.3.3;

    - m= 1.0 for the calculation of the upper limit according to 8.3.4.

    8.4 Punch and torsion

    The values calculated for the design value of shear stress may not be used for the

    verification of punch and torsion.

    9 Reporting

    9.1 Class A

    A written report according to class A should at least include:

    the definition of the problem;

    a description of the structure in question;

    a description of the study performed and the measurements, including the test

    method;

    an indication of the measuring locations;

    the results of the visual inspection; a description of the cracks found and the classification of the cumulative crack width

    (crazed pattern, etc.);

    the results of any measurements performed and laboratory testing;

    the results of the calculations performed.

    9.2 Class B

    A written report according to class B should include the points stated in 9.1, with the

    addition of:

    a discussion of the results;

    the consequences of the findings and results for the component assessed or the

    structure;

    any measures or actions to be taken immediately.

    And more specifically for the various studies:

    Technical study: a statement whether ASR is present;

    the classification of the relative cumulative crack width ASR;

    a statement whether a relatively low uniaxial tensile strength

    determined in accordance with 7.5.2 is present.

    Targeted study: a statement whether the results show that a further structural

    study is required.

    Structural study: a statement whether the structure can still be considered safe.

    9.3 Class C

    A report according to class C should at least include the points stated in 9.2, with the

    addition of possible control measures, see 9.4.

    Explanation

    The effects of structurally deleterious ASR on punch and torsion are still not

    sufficiently known.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    23/31

    CUR - Recommendation 102

    |23

    9.4 Control strategy and control measures

    9.4.1 Data required for control measures

    The client must indicate what the control strategy is for the structure in question. At

    least the following must be recorded here:

    the planned period in which the client wishes to continue using the structure;

    the minimally required state of repair of the structure, for example, whether damage

    to preservations on concrete is allowed or not, or the presence of concrete damage; the loads and/or traffic class the structure must be able to absorb.

    For the specification of a control plan at least the following data must be available and

    must have been verified:

    the control strategy;

    the exposure conditions of the various structural components;

    the current damage.

    9.4.2 Specification of control measures

    Which control measures are to be taken depends on many factors and they may

    therefore differ for each structure. As an indication, Table 4 provides an overview of

    possible control measures depending on the risk classification according to Table 3, the

    presence of a relatively low uniaxial tensile strength and the level at which cracks are

    present.

    Explanation of table 4

    V Sealing against moisture; targeted drying of the concrete

    More damage is usually observed in locations where moisture transport is high

    compared to locations where a structure is fully submerged. Where possible,

    one measure may therefore be aimed at limiting moisture transport through

    (ASR) cracks. Puddles must be prevented from remaining directly on the

    concrete.

    Targeted drying of the concrete can be achieved by draining moisture correctly,keeping moisture out of wet faces and allowing drying on dry faces. It is

    pointless to wrap up a structure completely, as any moisture present will not

    be able to get out. Here a role is played by the fact that structures with their

    base in the water easily absorb moisture through the cracked concrete. In this

    case wrapping-up the concrete will increase the wetness of the structure.

    M Monitoring

    Cracks can be monitored in a number of ways:

    The easiest way is to monitor the development of cracks in the structure. In

    some cases it will be sufficient to visit the structure periodically.

    Periodically marking the cracks in the same location (see also 7.1) and

    copying these cracks to a sheet of Perspex, whereby crack widths are

    measured and stated. It is advisable to use the same person for this each

    time, as the width of a crack changes starting at the surface and the edges of

    cracks are not always clear-cut. This means that different people may

    interpret things differently.

    Monitoring the cumulative crack width as described in 7.2.

    Several measuring techniques (wire recorders) are available for monitoring

    expansion in concrete. In this case it must be taken into account that expansion

    is always related to temperature and, to a limited degree, moisture.

    Moisture can be measured in various ways. Moisture can be measured

    indirectly based on the relative humidity of the concrete. The electric

    alternating-current resistance and the electric impedance of the concrete arealso moisture indicators.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    24/31

    CUR - Recommendation 102

    24 |

    Table 4 Selection table for control measures. The table only provides an initial

    indication for possible measures; these require further consideration for

    each situation

    Necessary measure(s) Optional measuresRisk classification

    of the structure

    Relatively low

    tensile strength

    indication *)

    Level of crack

    formation

    (indicative) V M VF C V M VF C

    Low Yes < 1 mm/m 1 2 4

    Yes > 1 mm/m 2 4 5 4 1 1 1

    No < 1 mm/m 2 3

    No > 1 mm/m 1 4 3 4 1 1

    Medium Yes < 1 mm/m 2 6 2 4 1 2

    Yes > 1 mm/m 6 6 2 4 2 1

    No < 1 mm/m 2 4 1 2 2 1 2

    No > 1 mm/m 5 4 2 4 1 2 1

    High Yes < 1 mm/m 5 4 4 2

    Yes > 1 mm/m 6 4 5 4 2

    No < 1 mm/m 6 5 2 2 2

    No > 1 mm/m 6 6 3 4 1 2*) obtained from 7.5.2, as the number of options may be limited based on the results if a structural

    study has already been performed.

    Table 4 indicates the importance of the measures using the numbers 1 to 6. The number 6 indicates

    that the measures are highly recommended, the number 1 indicates that the measures are

    considered to be the least urgent. If a cell is empty this means that the measure will not be useful.

    The ratio of the numbers for necessary and optional measures provides an indication as to whether

    it is better to choose the necessary or optional measure.

    These moisture measurements are often related to temperature. It is therefore

    recommended to determine both parameters at the same time. By measuring the

    moisture content periodically it can be established whether the structure is

    drying up.

    VF Measures for guaranteeing safety and functioning

    When considering measures for guaranteeing safety and functioning, they must

    always be tuned to the specific situation. The Recommendation provides a

    number of guides for this in Table 4. However, these are not exhaustive.

    Examples of measures to guarantee safety / functioning are limiting the load or

    applying a local reinforcement or support. If structural damage is about to

    occur due to jamming of a structure, room for expansion may be created.

    C Limiting the risk of reinforcement corrosion

    If a structure damaged by ASR is cracked, reinforcement corrosion may occur

    by penetration of chlorides and carbonation in these cracks. Depending on the

    local situation, measures may be taken to seal the concrete from chlorides. One

    option is to inject cracks. This will be required especially if a changeable wet-

    dry situation is present with enough moisture.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    25/31

    CUR - Recommendation 102

    |25

    Titles of standards and CUR Recommendations stated

    NEN 6702:2001 Technical principles for engineering structures. TGB

    1990. Loads and deformations.

    NEN 6720:1995 Concrete regulations. Structural requirements and cal-

    culation methods (VBC 1995), incl. amendment A3:2004.

    NEN 6723:1995 Concrete regulations. Bridges. Structural requirements

    and calculation methods (VBB 1995), incl. amendment

    A1:2003

    NEN 8005:2004 Dutch specification of NEN-EN 206-1. Concrete, part 1.

    Specification, performance, production and conformity.

    NEN-EN 206-1:2001 Concrete; part 1. Specification, performance, production

    and conformity.

    CUR Recommendation 54 Concrete repair using manually applied or poured cement-based mortar.

    CUR Recommendation 72 Inspection and testing of concrete structures.

    CUR Recommendation 74 Studying of concrete structures Studying of compres-

    sion strength.

    CUR Recommendation 89 Measures to prevent damage to concrete by alkali-silica

    reaction ASR.

    Dutch standards are publications by Stichting Nederlands Normalisatie-instituut,

    Vlinderweg 6, Postbus 5059, 2600 GB Delft. Orders can be placed at NEN, sales and

    information hotline, tel. +31 (0)15 2690391.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    26/31

    CUR - Recommendation 102

    26 |

    Appendix A Preparation of fluorescent epoxy

    A1 Introduction

    This appendix describes the preparation of fluorescent epoxy for the impregnation of

    sample material.

    A2 Composition

    For the preparation of fluorescent epoxy the following substances and materials arerequired:

    a fluorescent dye, namely finely ground powder of Hudson Yellow, for example,

    EpoDye produced by Struers or equivalent;

    epoxy resin, for example, BY 158 by Ciba Geigy, or equivalent;

    epoxy hardener, for example, HY 2996 by Ciba Geigy, or equivalent;

    materials required: fume cupboard, plastic beaker, wooden spatula, bucket/tray of

    cold water, magnetic stirrer, balances with a variety of weighing ranges.

    A3 Safety

    If the instructions and safety regulations of the manufacturer are not strictly observed

    the handling of epoxy resin may be harmful to a persons health. Epoxy resin must

    therefore only be handled in a fume cupboard.

    A4 Procedures

    A4.1 Adding dye to the resin

    Carefully add one weight percent of dye to a weighed quantity of epoxy resin in asealable container; also add a stirring magnet. Be careful with the dye, as it may even

    contaminate the laboratory if a slight draught is present.

    Seal the container and firmly mix the contents by hand. Place the glass on a magnetic

    stirrer and leave it to stir for at least two days. Firmly shake the glass again by hand at

    least once every 24 hours. Remove the stirring magnet with a steel pin after stirring and

    clean it thoroughly.

    The hardener and the coloured resin must be stored in the dark in a ventilated location

    or in a fume cupboard.

    A4.2 Mixing the two componentsThe coloured resin must be mixed with the hardener according to the instructions of the

    manufacturer. Table A1 provides the current mixing ratio for products by Ciba Geigy.

    Place a plastic beaker on a balance and add the required amount of coloured resin to it

    first, then add the correct amount of hardener.

    Explanation

    Hudson Yellow is also known as Brilliant Yellow and by the trade name Epodye; it

    is a fluorescent dye that lights up as light yellowish green under filtered blue lightwith a wavelength of around 476 nm when viewed through an LWP 515 emission

    filter.

    Explanation

    The final amount of coloured resin in the glass may contain a few lumps of undis-

    solved fluorescent dye. To prevent false-positive fluorescence this contaminated

    amount of resin must not be used for the impregnation of slices.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    27/31

    CUR - Recommendation 102

    |27

    Table A1 Mixing ratio by weight (g) for Ciba Geigy products

    Coloured resin

    BY 158

    Hardener

    HY 2996

    Coloured resin + hardener

    40

    80

    120

    200

    12

    24

    36

    60

    52

    104

    156

    260

    Start stirring the mixture immediately with a wooden spatula; stir in a circular motion

    and in figures of eight in both a horizontal and vertical direction. Regularly scrape the

    sides and bottom of the beaker. Stir vigorously for two whole minutes.

    In addition to other problems, incomplete mixing may result in insufficient hardening.

    The mixed epoxy must be used for impregnation within 30 minutes of mixing.

    The hardening of the epoxy generates heat. Keep any epoxy that has not (yet) been used

    in plastic beakers that are placed in cold water to prevent the epoxy from boiling. Make

    sure that no water is added to the epoxy. After hardening (the next day) the excess

    epoxy can be removed as regular waste.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    28/31

    CUR - Recommendation 102

    28 |

    Appendix B Preparation of thin sections

    B1 Introduction

    These instructions describe the procedure for the preparation of thin sections for the

    PFM test.

    B2 Materials required

    The following materials are required for the preparation of thin sections: diamond cutter with water cooling and a fully straight cutting blade that does not

    vibrate;

    suitable diamond cutting (and lapping) equipment with water cooling;

    support slide matted on one side to be used as a reference for plane-parallel

    treatment when impregnating and also as external glued-on reinforcement for

    fragile samples;

    sample slide with one matted side;

    covering slide;

    UV-hardening glue;

    UV lamp;

    polarisation microscope; micrometer (optional);

    soft brush, or better yet, a clean ultrasonic cleaning bath to clear the sample of

    cutting and grinding sludge;

    soft brush, or better yet, an electrostatic brush to clean the slide and the samples

    before glueing;

    acetone and/or alcohol;

    soft paper, for example, cleaning paper for optical lenses;

    siphon or spray bottle of alcohol (60% V/V).

    B3 Procedures

    B3.1 General informationThe slices are prepared as follows:

    select a location for a slice in the drilling core that was cut in half;

    cut a piece of at least 30 x 40 x 10 mm3from the selected section of the impregnated

    sample;

    never reduce the amount of surface cut off; this will affect the representative

    character of the sample;

    glue the section that was cut off to the support slide using a thin and even layer of

    Loctite 330 or a similar alternative;

    cut off the sample parallel to the support slide so that a thickness of 2 to 5 mm is

    obtained;

    grind the surface parallel to the support slide with a fine-grained diamond so that a

    smooth and even surface is formed;

    glue a sample slide to the final surface;

    cut off any excess material;

    grind the surface further with increasingly fine diamond to a thickness of (20 1)

    m;

    print the sample number on the finished slice.

    A number of procedures are described in more detail below.

    B3.2 Sample number

    It is of essential importance that the unique sample number remains linked to the

    samples at all times. This is why samples must be placed and processed in a logical

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    29/31

    CUR - Recommendation 102

    |29

    order. Any residue that is cut off must be kept with the sample during all practical

    procedures. Reattach the sample code to the treated sample as quickly as possible.

    B3.3 Cutting with a diamond wheel

    The following applies to cutting with a diamond wheel:

    1. Use the thinnest possible diamond wheel.

    2. Cut with the diamond wheel using an even pressure that is as low as possible and

    always use water cooling (for some special applications, for example, for water-soluble substances, cooling with alcohol is recommended). A sharp diamond cutter

    will cut through the material almost without pressure.

    3. If the cutting is too slow the diamond wheel may be worn-out or it may require

    sharpening or needs to be replaced.. It may be that the wrong type of diamond wheel

    is mounted to the cutter.

    4. Diamond wheels require inspection and maintenance, and they must be replaced

    where required:

    Where required, sharpen the wheel by cutting a soft material, for example, a

    brick.

    Use a magnifying glass to check whether the outer layer is still covered in

    diamond grains.

    Replace the diamond wheel if it is worn-out or if any wobbling, vibration or

    shocking occurs, as this may damage the sample.

    B3.4 Grinding

    The grinding procedure largely depends on the equipment used. For good results the

    following general points must be taken into account:

    Grinding is to be performed with a gradually decreasing grain size.

    Grinding with a particular grain size will not be finished until all the scratches from

    the previous, coarser treatment (grinding or cutting) are removed.

    Prevent grains or particles from breaking free from the surface, especially along the

    edges of the sample, by making sure that the sample is fully impregnated.

    After each grinding round, check the surface under an angled beam of light(floodlight) for completely even grinding results, in other words, a flat surface

    without ridges.

    Clear the surface of grinding waste after every treatment and then moisturise the

    surface with alcohol by spraying, then dry it off with soft paper in a single swipe.

    The preparation may never dry up during the entire treatment. Water may leave

    circles of microscopically small crystals, may contribute to artificial carbonation of

    the cement paste and has a negative effect on the UV-hardening glue.

    The final surface quality must be sufficient for an unambiguous identification of

    components and microstructural characteristics.

    B3.5 Glueing-on the sample slide and the covering slide

    It has been shown that the procedure below results in good and even glueing: Apply a diagonal cross of glue to the impregnated and finished sample surface (to

    prevent air bubbles from becoming trapped).

    Place the slide at the centre of the sample.

    Only for the sample slide:

    leave the layer of glue to even out by itself for 5 minutes and recentre the slide;

    hold the sample and the slide together for 10 minutes using a force that is evenly

    distributed over the surface;

    expose the sample to UV light for 20 minutes.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    30/31

    CUR - Recommendation 102

    30 |

    Only for the covering slide:

    leave the glue to even out by itself for 5 minutes;

    remove any excess glue from the edges of the covering slide with a pipe cleaner,

    recentre the slide;

    place the sample under UV light for around 1 minute;

    carefully remove any excess glue with a Stanley knife and acetone or alcohol;

    place the sample under UV light for around 10 minutes;

    clean all surfaces with acetone or alcohol.

    B3.6 Checking the thickness

    The thickness of the thin section is checked with the polarisation microscope. The

    correct thickness of around 20 m is determined based on the white or light-grey

    birefringent colour of quartz For some automatic grinding equipment the thickness can

    also be measured with a micrometer, whereby the thickness of the UV-hardening glue

    must be taken into account.

    B4 Storing impregnated fluorescent thin sections

    The fluorescent power of the thin sections is reduced noticeably if they are exposed to

    strong light for a prolonged period of time. This is why thin sections must be stored in

    the dark.

  • 8/12/2019 CUR Recommendation 102_Inspection and Assessment of Concrete Structures in Which the Presence of ASR is Su

    31/31

    CUR - Recommendation 102

    It should be pointed out that this CUR Recommendation reflects the state of the art at

    the moment of publication. Any suggestions for experiences with the use of this

    Recommendation will be gratefully received by CURNET. CUR Recommendations are

    evaluated three years after publication and are updated if necessary. This will be

    reported in the press.

    Copyright

    All rights reserved. No part of this publication may be reproduced, stored in a retrievalsystem, or transmitted, in any form or by any means, electronic, mechanical, photocopy-

    ing, recording and/or otherwise, without the prior written permission of CURNET.

    It is allowed, in accordance with article 15a Netherlands Copyright Act 1912, to quote

    data from this publication in order to use this in articles, essays and books, provided that

    the source of the quotation, and, insofar as this has been published, the name of the

    author, are clearly mentioned. CUR-Recommendation 102 Inspection and

    assessment of concrete structures in which the presence of ASR is suspected or has been

    established, April 2008, Gouda, The Netherlands.

    Liability

    CURNET and all contributors to this publication have taken every possible care in the

    preparation of this publication. However, it cannot be guaranteed that this publication is

    complete and/or free of errors. The use of this publication and data from this publication

    is entirely at the users own risk and CURNET hereby excludes any and all liability for

    any and all damage which may result from the use of this publication or data from this

    publication, except insofar as this damage is a result of intentional error or gross

    negligence of CURNET and/or the contributors.

    Gouda, April 2008The Board of CURNET

    Stichting CURNET, Groningenweg 10, P.O. Box 420, 2800 AG GOUDA,

    The Netherlands

    tel. +31 (0)182540600