5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
1/7
CTR No: INLET COMPRESSOR FOR GPP CA MAU Rev : 0
Title: TOTAL COST Date 24-Nov-11
ID CTR NO. CTR Title Manhour Cost (USD) REMARKS
1 1 Project Management #REF! #REF!
1.1 Project Management Board #REF! #REF!
1.2 Site Study Survey #REF! #REF!
2 2 FEED Design #REF! #REF!
2.1 Process Design #REF! #REF!
2.2 Electrical System #REF! #REF!
2.3 Mechanical #REF! #REF!
2.4 Civil Works #REF! #REF!
2.5 Piping #REF! #REF!
2.6 Instrument #REF! #REF!
2.7 Fire Fighting #REF! #REF!
2.8 Cost estimation #REF! #REF!
CTR TOTAL (excluding VAT 10%) #REF! #REF!
VAT 10% #REF!
CTR TOTAL (including VAT 10%) #REF!
- Exchange rate USD/VND: 20,834
SCOPE OF WORK FOR SITE SURVEY, FEED DESIGN
CA MAU GAS PROCESSING PLANT PROJECT - PM3 GAS BOOSTER COMPRESSION PACKAGE
Cost Time and Resources (CTR) Sheet - SITE SURVEY, FEED DESIGN
Prepared by Approved by:
-
5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
2/7
BID PRICEPACKAGE: FEED DESIGN
PROJECT: CA MAU GPP PROJECT - PM3 GAS BOOSTER COMPRESSION PACKAGE
TABLE 1 - HOURLY RATE OF EACH POSITION
NO. DESCRIPTIONHOUR RATE
(USD/PERSON/HOUR)NOTE
1 Project Director 33
2 Project Deputy Director
3 Project Manager 32
4 Process Lead Engineer 25
5 Mechanical Lead Engineer 25
6 Piping Lead Engineer 25
7 Instrument Lead Engineer 25
8 Electrical Lead Engineer 25
9 Civil Lead Engineer 25
10 FFT Lead Engineer 25
11 Cost Estimation Lead Engineer 25
12 Document Controller 10
13 Project Engineer 23
14 Project Coodinator 23
15 Senior Engineer 23
16 Engineer 18
17 Draftman10
-
5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
3/7
BID PRICEPACKAGE: FEED DESIGN
PROJECT: CA MAU GPP PROJECT - PM3 GAS BOOSTER COMPRESSION PACKAGE
TABLE 2 - PROPOSAL PRICE FOR CHANGE ORDER /
ADDITIONAL SERVICES
NO. DESCRIPTIONHOUR RATE
(USD/PERSON/HOUR)NOTE
1 Project Director 33
2 Project Deputy Director
3 Project Manager 32
4 Process Lead Engineer 25
5 Mechanical Lead Engineer 25
6 Piping Lead Engineer 25
7 Instrument Lead Engineer 25
8 Electrical Lead Engineer 25
9 Civil Lead Engineer 25
10 FFT Lead Engineer 25
11 Cost Estimation Lead Engineer25
12 Document Controller 10
13 Project Engineer 23
14 Project Coordinator 23
15 Senior Engineer 23
16 Engineer 18
17 Draftman10
-
5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
4/7
CTR No: DUST COLLECTION SYSTEM OF NPK FERTILIZER PLANTTitle: DUST COLLECTION SYSTEM
ACTIVITY DESCRIPTION:
- Input to Basis of Design
- Prepare drawings for Dust Collection system;
- Prepare specification and calculation for Dust Collection system;
DELIVERABLES:
- PFD
- P&IDs
- Equipment datasheet- Calculations & Reports
- Material Take off (MTO)
INPUT REQUIREMENTS:
- SOW
- BOD
- General plot plan
- Design requirement for Dust Collection system;
- Architectural drawings for each building.
WORK, COST AND SCHEDULE
Personnel
Process Lead Engineer 1 15
Senior Engineer 1 30
Engineer 2 30
Draftman 1 30
Personnel Subtotal
OTHERS (software)
Total Value
SCOPE OF WORK FOR FEED
NPK Fertilizer Plant Pro
Cost Time and Resources (CTR) Sheet
-
5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
5/7
-
5/26/2018 CTR-InPK Fertilizer Plant Project-FEED Design
6/7
Rev : ADate 24-Nov-11
Manhours Unit Amount
(hours) (USD/hour) (USD)
120 25 3,000.00
240 23 5,520.00
480 18 8,640.00
240 10 2,400.00
1,080 USD 19,560.00
-
USD 19,560.00
DESIGN
ect
- FEED SERVICES
-