cste
TRANSCRIPT
QUESTION: 1In information technology, we often build products requirements/specifications whichalthough documented not true quality needs of our customers.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 2Our products must be corrected so that they will eventually meet our customers' true qualityneeds.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 3Quality without timeliness and cost consideration is ________________
A. MeaninglessB. BeneficialC. One of product deficienciesD. Cheaper
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 4We can produce products at our convenience and at any cost
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 5Those responsible for quality must include –
CSTE
2
A. Cost considerationB. delivery at required timeC. At required qualityD. 1 & 2E. 2 & 3F. All the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 6Quality is ----------------'s responsibility.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 7Management must create an _______________ and _______________ for quality tohappen.
A. Environment , enthusiasmB. Principles, rewardC. Empowerment, rewards
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 8Management must make quality number one and then reward quality work.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 9Monetary and non monetary rewards can be considered management to make people enjoywhat they are doing.
A. TrueB. False
CSTE
3
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 10Product inspections and testing can be eliminated by building processes to eliminate rootcauses of defects and producing defect free products.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 11The following comprise the processes - Which is correct
A. Policies, standards, proceduresB. standards, procedures, policiesC. Procedures, policies, standardsD. Policies, procedures, standards
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 12Quality is not an attribute of product.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 13Quality is not a binary state
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 14Quality need not be defined in quantitative terms in order to be measurable.
A. True
CSTE
4
B. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 15Quality can be controlled only if it is measured.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 16Judgement is an audit function
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 17AQL means –
A. Audit quality levelB. Audit quantity levelC. Accepted quality level
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 18 Management must support zero defects
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 19
CSTE
5
Deficiencies of AQL are –
A. Undermines the concept of qualityB. Does not aim at eradicating the cause of defects From the processes.C. 1 & 2D. None of the above.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 20Non conformance must be detected as early as possible measured.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 21High defect prone products and processes are identified testing the product after allprocesses are over.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 2280% of all defects are attributable to incorrect ineffective processes.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 23_____________ is responsible for processes and must accept the responsibility fornonconformance at least to 80% attributable to the processes.
A. QA departmentB. QC departmentC. Information technology management
CSTE
6
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 24The concept that is an integral part of information technology function is –
A. Meeting the requirementsB. Producing a quality productC. Customer's view of quality is the correct view quality.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 25Probability of being successful is extremely high, customer's problems are taken ascompany's problems.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 26Quality work can be rewarded.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 27The topics of standards and nonconformance should discussed in every meeting to improvequality.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 28
CSTE
7
Quality is a ______________ Responsibility.
A. StaffB. LineC. Both
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 29Everyone should be involved in quality improvement programs.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 30The responsibility of supervisor –
A. Teach subordinates how to performB. To evaluate subordinate performanceC. Assist and support workers until they become proficientD. 1 &2E. 1 & 3F. 2 & 3G. 1, 2 and 3
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 31Standards, procedures and metrics are to be established workers doing the job.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 32Management can always override standards and procedures established by workersabsolutely when necessary.
CSTE
8
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 33It is better to deal with more number of vendors
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 34Quality pyramid illustrates core processes (building blocks) of quality) and implementationdimension of each process
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 35Baselining is quantitatively determining what you want be.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 36Analysis is performed before baselining is done.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 37Analaysis is done to determine which area is in need improvement.
A. TrueB. False
CSTE
9
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 38Vision provides an umbrella for focusing all the plans in order to achieve constancy ofpurpose.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 39Planning involves agreeing on specific objectives and you hope to get there.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 40Six sigma quality is ___________
A. 1.2 Defects per million lines of codeB. 3.4 Defects per million lines of codeC. 6.1 Defects per million lines of code
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 41Deming's 14 quality principles emphasize the following strategy:1. Management must lead, direct, train, empower and support rather than supervise andcontrol.2. MBP is important rather than MBO3. Long term continual quality improvement must be focus rather than short termprofit/cost.
A. 1 only;B. 1 & 2;C. 1 & 3;D. 2 & 3;E. all the above.
CSTE
10
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 42The three levels of management are -
A. Lower, middle and upperB. Executive, middle, line
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 43Executive is __________ and ____________
A. Directional and tacticalB. Tactical and strategicC. Visionary and strategicD. Visionary and directional
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 44Middle is ___________ and ____________
A. Visionary and tacticalB. Visionary and directionalC. Directional and tactical
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 45Line is ____________
A. DirectionalB. TacticalC. Operational
Answer: Pending. Please send your suggestions to [email protected]
CSTE
11
QUESTION: 46Executive must establish a working relationship with middle management and middlemanagement must establish a working relationship with line management and linemanagement establish a working relationship with executive management
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 47CASE tools can be introduced duly integrating standards and supporting procedures.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 48Tools supporting processes to be ensured rather processes supporting tools.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 49Quality control is the responsibility of people who evolve the processes.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 50Quality defect is non conformance to standards.
A. TrueB. False
CSTE
12
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 51Techniques for identifying deviations from standards Deviations from productspecifications must be integrate into all work processes.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 52Verification activity is a static analysis.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 53Common verification techniques are -
A. Walkthroughs, checkpoint reviews, inspectionsB. Test plan, test execution
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 54Testing is not a verification technique
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 55Types of measurement of performance are –
A. strategic, statical, operational
CSTE
13
B. Strategic, tactical, operational
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 56Match:
A. Strategic - a. Operational managementB. Tactical - b. Executive managementC. Operational - c. Middle management
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 57Management must retain decision making authority identify and resolve problems.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 58Rational, analytical techniques can be used for problem resolution/problem solving.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 59Seven core processes are
A. Baseline, analyse, vision and planB. Establish a TQM processC. Install and improve processesD. Control quality (walkthrough, reviews and inspectionsE. Quality control (validation-test plan/test execution)F. Perform quantitative analysisG. Perform continuous improvement
CSTE
14
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 60Plan - Baseline, plan - approach partDo - Set short term objectives , compare results targets, revise approach if requiredCheck & act - check results, replan and recheckResults - final resultsApproach is repeatable.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 61Quality means
A. conformance to requirementsB. meeting customer needsC. bothD. none
Answer: C
QUESTION: 62AQL stands for
A. Allowable Quality LevelB. Allocated Quality LevelC. Acceptable Quality LevelD. Allowed Quality Level
Answer: C
QUESTION: 63For quality to happen, there must be well-defined standards and procedures which arefollowed.
A. TrueB. False
Answer: A
CSTE
15
QUESTION: 64Many technical personnel believe that standards inhibit their creativity.
A. TrueB. False
Answer: A
QUESTION: 65Achieving quality (defect-free products and services) is easy.
A. TrueB. False
Answer: B
QUESTION: 66The challenge of making quality happen is
A. a miniscule challengeB. a monumental challenge
Answer: B
QUESTION: 67Accomplishing quality requires "a thought revolution by management.". Who stated asabove?
A. Dr. Malcolm BaldrigeB. Dr. Kaoru IshikawaC. Bill Gatesd)William J Clinton
Answer: B
QUESTION: 68Taylor approach refers to
A. Engineers create work standards and specifications. Workers merely follow.
CSTE
16
B. Engineers create work standards and specifications. Both engineers and workers follow.C. Engineers create work standards and specifications and follow them.
Answer: C
QUESTION: 69In Zero defect movement all responsibilities and defects are borne by the workers.
A. TrueB. False
Answer: A
QUESTION: 70The word "kick-off" is used in
A. Zero Defect MovementB. Deming's CircleC. QAI's Quality Improvement Model
Answer: A
QUESTION: 71Dr. W. Edwards Deming has stated that it takes ____________ years to change a culturefrom an emphasis on productivity to an emphasis on quality.(10 years/20 years/2 to 5years/none of these)
Answer:20 years
QUESTION: 72Quality means meeting requirements. This is ____________view. (producer's /customer's )
Answer:producer's view
QUESTION: 73Quality means fit for use. This is ________________view. (producer's /customer's )
CSTE
17
Answer:customer's view
QUESTION: 74Which one of the following definitions of quality is more important.
A. Quality means meeting requirements.B. Quality means fit for use.
Answer: B
QUESTION: 75Quality control is a ______________ function. (line/staff)
Answer:line
QUESTION: 76Quality assurance is a ____________ function. (line/staff)
Answer:staff
QUESTION: 77By what other two names is PDCA process referred to?
Answer:Management Cycle/Deming's wheel
QUESTION: 78What does "Going Around the PDCA Circle" connote?
Answer:The four-step procedure, viz., Plan-Do-Check-Act is referred to as PDCA. Repeatedlygoing through the management cycle is known as "going around the PDCA circle".
CSTE
18
QUESTION: 79The no of principles in Dr. W. Edwards Deming's quality principles is ____________.(8/10/12/14/16)
Answer:14
QUESTION: 80 For quality to happen it is not necessary that all the Deming's principles are usedconcurrently.
A. TrueB. False
Answer: B
QUESTION: 81The award has three eligibility categories which are Manufacturing, Service and Smallbusiness.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 82Manufacturing Companies includes
A. AgricultureB. MiningC. ConstructionD. All the aboveE. b & c
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 83Upto two awards can be given in each category each year.(T/F)
CSTE
19
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 84Please tick which of the following are covered under award criteria.
A. Leadership.B. Strategic Planning.C. Customer & Market Focus.D. Information & Analysis.E. Human Resource Development & Management.F. Process Management.G. Business Results.H. Funds Management.I. Materials Management.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 85The total maximum points for award criteria is
A. 100 pointsB. 500 pointsC. 1000 pointsD. 10000 points
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 86Under strategic planning, we have
A. Strategy planningB. Strategy DevelopmentC. Human resource plansD. Only a & bE. a, b, & c.
CSTE
20
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 87Leadership category includes
A. Leadership systemB. Societal ResponsibilitiesC. Community InvolvementD. a,b & cE. a & b only.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 88Describing how company practices a good citizenship is a part of leadership category.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 89Performance projections forms part of strategic planning.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 90Customer and Market focus examines
A. Customer and Market knowledgeB. Customer satisfaction & relationship enhancementC. Financial & Market results.D. All the aboveE. Only a & b.
CSTE
21
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 91Accessibility and complaint management forms part of customer and market knowledge.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 92Information and Analysis deals with
A. Selection and use of Information and dataB. Selection and use of comparative Information & dataC. Analysis of dataD. Only a & cE. a,b & c.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 93Analysis of data comprises
A. Customer related performanceB. Operational performanceC. Competitive performanceD. Financial & market related performanceE. All the aboveF. b,c & d.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 94HRD Management includes
A. Compensation & RecognitionB. Work and Job design
CSTE
22
C. Employee education, training & developmentD. Work environmentE. All the aboveF. Only a,c & d
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 95Employee support services not forms part of a HRD Management category
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 96Process Management includes
A. Design ProcessB. Management of Support ProcessC. Supplier and Partnering processD. Only a & bE. a,b & c.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 97Company's key support process should be designed, __________ and improved.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 98Business results include
A. Customer satisfaction resultsB. Financial and market resultsC. Human resource principlesD. Supplier and Partner results
CSTE
23
E. Company specific resultsF. All the aboveG. a,b,d & e.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 99Pricing is also important to competitive success and customer satisfaction.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 100Human resource results does not cover work system performance
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 101Organisation at initial level can improve their performance by instituting
A. Project ManagementB. Management OversightC. Quality AssuranceD. Change ControlE. All the aboveF. Only a,b, & d
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 102Establishing project management requires
A. Adequate PreparationB. Clear Responsibility
CSTE
24
C. Dedication to PerformD. All the aboveE. None of the above.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 103Management oversight does not include review and approval of all major developmentplans prior to official commitment.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 104Quality Assurance Dept should not have independent reporting line to senior managementand they should report to middle management for better performance.
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 105Generally the strength of QA dept should be ______________ percent of size oforganisation.
A. 1 to 2B. 3 to 6C. 10 to 20D. 70 to 80
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 106Change control for software is fundamental to ____________ and ______________ controlas well as to _______________ stability.
A. business, finance, technical
CSTE
25
B. finance, technical, businessC. technical, business, financeD. None of the above.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 107In repeatable process, the organisation provides control over its _______________ and___________________.
A. Resources and commitmentsB. Plan & commitmentsC. Resources & quality ControlD. None of the above.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 108The changes that effect organisation at repeatable process are
A. New tools & methods.B. When organisation ventures into new fieldC. Major organisational changesD. All the aboveE. None of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 109To overcome the changes that affect repeatable process the organisation should do
A. Establish process groupB. Establish S/W development process architectureC. Introduces S/W Engg methods & technologiesD. All the above.E. Only a,b & c.
CSTE
26
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 110In defined process, the organisation has
A. achieved foundation for major and continuing progressB. able to face crisisC. BothD. Neither a or b.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 111The Defined process is still only qualitative but not measurable qantatively
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 112Key steps required to be initiated at defined process are
A. Establish quality and cost parametersB. Establish process databaseC. Provide resources to gather & maintain dataD. Establish Total quality planE. All the aboveF. Only a,b & c.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 113The greatest potential problem with the managed process is the cost of gathering data
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
CSTE
27
QUESTION: 114In managed process
A. Data should be definedB. Automate gathering of dataC. Use process data to analyzeD. All the aboveE. Only a & b
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 115In optimising process, process optimising is done to produce major quality & productivitybenefits
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 116The Malcolm Baldridge National Quality Award is an annual award to recognise UScompanies which excel in
A. Quality achievement and quality controlB. Quality assurance and quality controlC. Quality achievement and quality management
Answer: C
QUESTION: 117Which of the following is inaccurate ? The award promotes
A. Awareness of quality as an increasingly important element in competitivenessB. Understanding of the strategies for quality excellenceC. Understanding of the requirements for quality excellenceD. Sharing of information on successful strategies and on the benefits derived fromimplementation of these strategies
CSTE
28
Answer: B
QUESTION: 118The Malcolm Baldridge Award was created by Public Law 100-107, signed into law on20th Aug 1987.
A. TrueB. False
Answer: A
QUESTION: 119Greater emphasis on statistical process control can lead to dramatic improvements in thecost and quality of manufactured products.
A. TrueB. False
Answer: A
QUESTION: 120Quality improvement programs must be management led and customer oriented.
A. TrueB. False
Answer: A
QUESTION: 121The match the three eligibility categories of the awardA Companies or subsidiaries that produce and sell manufactured products or manufacturingprocesses and those companies which produce agricultural, mining or constructionproducts.B Companies or subsidiaries that sell services.C Complete businesses with not more than 500 full time employees. Business activitiesmay include manufacturing and / or service.1. Small business2. Manufacturing3. Service
CSTE
29
A. 1 2 3,B. 3 2 1,C. 2 3 1.
Answer: C
QUESTION: 122The small business must be able to document that it functions through its equity owners.
A. TrueB. False
Answer: B
QUESTION: 123The number of awards given in each category each year is
A. 3B. 1C. 2
Answer: C
QUESTION: 124The National Quality Award model is divided into _______ categories which cover themajor components of a ______________________.
Answer:7, total quality management system
QUESTION: 125Match the followingA Driver 1. Quality resultsB System 2. Customer satisfactionC Measures of Progress 3. Information and analysis
A. Strategic quality planningB. Human resources utilisation
CSTE
30
C. Quality Assurance of product and servicesD. Goal 4. Leadership
Answer:a - 4, b - 3, c - 1, d - 2
QUESTION: 126Leadership category examines the senior executives leadership
A. in creating quality valuesB. building the values into the way the company does businessC. how the executive and company project the quality values outside the companyD. create a quality department and appoint a quality officerE. all the aboveF. a, b & c
Answer: F
QUESTION: 127Leadership evaluations are based upon the appropriateness, effectiveness and extent of theexecutives' and of the company's involvement in relation to the size and type of business.
A. TrueB. False
Answer: A
QUESTION: 128Quality department or officer / regulatory affairs office or officer is a prerequisite foreligibility under leadership criteria.
A. TrueB. False
Answer: B
QUESTION: 129Information and analysis category examines the scope, validity and use of data to determinethe adequacy of the data system to support total quality management.
CSTE
31
A. TrueB. False
Answer: A
QUESTION: 130The scope, management and analysis of data depend upon
A. the type of business, its resourcesB. number and geographical distribution of business unitsC. and other factorsD. all of the above
Answer: D
QUESTION: 131Information and analysis evaluations are based upon
A. the appropriateness and effectiveness of methods for management of dataB. information and analysisC. and of technology in relation to these business factorsD. all of the above.
Answer: D
QUESTION: 132Information and analysis evaluations do not depend on
A. how activities are organised orB. whether or not the company has an information department or an officer orC. uses particular technologies to analyse data orD. to make data available throughout the company E. all of the above.
Answer: E
QUESTION: 133
CSTE
32
Strategic quality and planning category examines the company's approach to planning todetermine its adequacy to achieve or sustain quality leadership.
A. TrueB. False
Answer: A
QUESTION: 134Competitive and benchmark data are essential for planning quality leadership because theymake possible clear and objective quality comparisons.
A. TrueB. False
Answer: A
QUESTION: 135While the planning processes and priority development do not depend appreciably upon thesize and type of business, the scope and type of benchmark may depend upon such businessfactors.
A. TrueB. False
Answer: A
QUESTION: 136The principal considerations in assessing the effectiveness of competitive and benchmarkdata are in relation to
A. the competitive environment and resources of the companyB. the type and size of the companyC. a & bD. b only
Answer: A
QUESTION: 137
CSTE
33
Evaluations of planning are based upon the thoroughness and effectiveness of processesincluding the information used.
A. TrueB. False
Answer: A
QUESTION: 138Evaluations for strategic quality planning do not depend upon
A. how planning activities are organisedB. whether or not the company has a planning department or officerC. a & b
Answer: C
QUESTION: 139Human resources utilisation category examines the company's efforts to develop andinvolve
A. the entire workforce in total qualityB. the management in total qualityC. the line staff in total quality d. all the above
Answer: A
QUESTION: 140The organisation of efforts to develop and involve employees depend upon
A. the number of employeesB. resources of the companyC. geographical distribution of business unitsD. and other factorsE. all the above
Answer: E
QUESTION: 141
CSTE
34
Evaluations depend upon the appropriateness and effectiveness of approaches to humanresource development and do not depend upon whether or not the company has either ahuman resource department or officer, or training and education specialists or facilities
A. TrueB. False
Answer: A
QUESTION: 142Quality assurance of products and services category has a very strong process and systemsorientation throughout.
A. TrueB. False
Answer: A
QUESTION: 143The degree of formality in systems and processes depends upon a number of factors such as
A. size of the businessB. types of products and servicesC. customer and government requirementsD. regulatory requirementsE. number of business locationsF. all the above
Answer: F
QUESTION: 144Quality assurance of products and services evaluations take into account consistency ofexecution of quality operations that incorporate a sound prevention basis accompanied bycontinuous quality improvement activities.
A. TrueB. False
Answer: A
QUESTION: 145
CSTE
35
Consistency of execution is taken to mean the existence of defined and
A. suitably recorded processes with clear delineation of responsibilitiesB. consistently executing operationsC. other factors
Answer: A
QUESTION: 146Evaluations for quality assurance of products and services depend upon
A. how responsibilities are distributed or organised orB. whether or not the company has a quality organisation or officerC. none of the above
Answer: C
QUESTION: 147Quality results category examines the company's quality improvement and quality levels bythemselves and in relation to those of competitors.
A. TrueB. False
Answer: A
QUESTION: 148The number and types of measures for quality results depend upon factors such as
A. the company's sizeB. types of products and servicesC. competitive environmentD. all the above
Answer: A
QUESTION: 149Quality results evaluations consider whether or not the measures are sufficient to supportoverall improvement and to establish clear quality levels and comparisons.
CSTE
36
A. TrueB. False
Answer: A
QUESTION: 150Customer satisfaction category examines
A. the company's knowledge of customer requirementsB. service and responsivenessC. satisfaction results measures through a variety of indicator D. all the above
Answer: D
QUESTION: 151The scope and organisation of activities to gather information to serve and to respond tocustomers depend upon many factors such as
A. company resourceB. types of products and servicesC. geographical distribution of business unitsD. customersE. none of the aboveF. all of the above
Answer: F
QUESTION: 152Customer satisfaction evaluations are based upon the appropriateness and effectiveness ofefforts in relation to these business factors.
A. TrueB. False
Answer: A
QUESTION: 153Customer satisfaction evaluations do not depend upon
CSTE
37
A. how responsibilities are distributed orB. whether or not the company has separate departments for customer service, complaintsor other special purposesC. Both of the above
Answer: C
QUESTION: 154The seven examination categories address all major components of an integrated,prevention - based quality system built around continous quality improvement.
A. TrueB. False
Answer: A
QUESTION: 155The system for scoring examination items is based upon which of thefollowing evaluationdimensions
A. ApproachB. DeploymentC. ResultsD. All of the above
Answer: D
QUESTION: 156Approach refers to the method the company uses to achieve the
A. Evaluation of approachesB. purposes addressed in the examination itemsC. a & b
Answer: B
CSTE
38
QUESTION: 157The scoring criteria used to evaluate approaches
A. the degree to which the approach is prevention basedB. the appropriateness of the tools, techniques, and methods to the requirementsC. the effectiveness of the use of tools, techniques and methodsD. the degree to which the approach is systematic, integrated and consistently appliedE. the degree to which the approach embodies effective self-evaluation, feedback andadaptation cycles to sustain continuous improvementF. the degree to which the approach is based upon quantitative information that is objectiveand reliableG. the indicators of unique and innovative approaches, including significant and effectivenew adaptations of tools and techniques used in other applications or types of businesses.H. all of the aboveI. any one or more of the above
Answer: I
QUESTION: 158Deployment refers to the extent to which the approaches are applied to all relevant areasand activities addressed and implied in the examination items.
A. TrueB. False
Answer: A
QUESTION: 159Scoring criteria used to evaluate deployment include
A. any one or more of the belowB. the appropriate and effective application to all product and service characteristicsC. the appropriate and effective application to all transactions and interactions withcustomers, suppliers of goods and services and the publicD. the appropriate and effective application to all internal processes, activities, facilities andemployees
Answer: A
QUESTION: 160
CSTE
39
Results refers to outcomes and effect in achieving the purposes addressed and implied inthe examination items
A. TrueB. False
Answer: A
QUESTION: 161The scoring criteria used to evaluation results include
A. any one or more of the belowB. the quality levels demonstratedC. the contributions of the outcomes and effects to quality improvementD. the rate of quality improvementE. the breadth of quality improvementF. the demonstration of sustained improvementG. the significance of improvements to the company's businessH. the comparison with industry and world leadersI. the company's ability to show that improvements derive from their quality practices andactions
Answer: A
QUESTION: 162Match the following Initial
A. Initiate rigorous project management of commitments, costs, schedules and changesRepeatableB. At this point advanced technology can be usefully introducedDefinedC. Achieve rudimentary predictability of schedules and costsManagedD. Foundation for continuing improvement and optimisation of processOptimisingE. Most significant quality improvements begin
Answer:
CSTE
40
1 - c, 2 - a, 3 - b, 4 - e, 5 - d
QUESTION: 163The five maturity levels have been selected because they reasonably represent the actualhistorical phases of evolutionary improvement of real software organisation represent ameasure of improvement that is reasonable to achieve from the prior level suggest interimimprovement goals and progress measures make obvious a set of immediate improvementpriorities, once an organization’s status in this framework is known all the above
A. Initiate rigorous project management of commitments, costs, schedules and changesRepeatableB. At this point advanced technology can be usefully introducedDefinedC. Achieve rudimentary predictability of schedules and costsManagedD. Foundation for continuing improvement and optimisation of processOptimisingE. Most significant quality improvements begin
Answer: E
QUESTION: 164The primary objective of the maturity level transitions is to achieve a controlled andmeasured process as the foundation for continuing improvement.
A. TrueB. False
Answer: A
QUESTION: 165Assessment methodology helps an organisation establish a structure for implementing thepriority improvement actions.
A. TrueB. False
Answer: A
QUESTION: 166Management system helps an organisation identify its specific maturity status.
CSTE
41
A. TrueB. False
Answer: A
QUESTION: 167Once its position in the maturity structure is defined the organisation can concentrate onthose items that will help it advance t the next level.
A. TrueB. False
Answer: A
QUESTION: 168Poor project planning generally leads to unrealistic schedules, inadequate resources andfrequent crises.
A. TrueB. False
Answer: A
QUESTION: 169When a software organisation does not have an effective project planning system, it may bedifficult or even impossible to introduce advanced methods and technology.
A. TrueB. False
Answer: A
QUESTION: 170In initial process (level 1) software installation and maintenance often present seriousproblems.
A. TrueB. False
Answer: A
CSTE
42
QUESTION: 171In organisations in level1, there is no mechanism to ensure that formal procedures forplanning and tracking their work are used.
A. TrueB. False
Answer: A
QUESTION: 172In a crisis, if the organisation abandons established procedures and essentially reverts tocoding and testing it is likely to be in at____________________ level
A. repeatable processB. initial processC. both a & bD. none of the above
Answer: B
QUESTION: 173Because many effective software actions (such as design and code inspections or test dataanalysis) do not appear directly to support shipping the product, they are expendable.
A. TrueB. False
Answer: B
QUESTION: 174Organisations at the initial process level can improve their performance by insisting basiccproject controls like
A. project managementB. management oversightC. quality assuranceD. change controlE. all the above
Answer: E
CSTE
43
QUESTION: 175For software, project management starts with an understanding of the job's magnitude.
A. TrueB. False
Answer: A
QUESTION: 176The fundamental role of the project management system is to ensure effective control ofcommitments. This requires adequate preparation, clear responsibility, a public declarationand a dedication to performance.
A. TrueB. False
Answer: A
QUESTION: 177In any but the simplest projects, a plan must be developed to determine the best scheduleand the anticipated resources required.
A. TrueB. False
Answer: A
QUESTION: 178A suitably disciplined software development organisation must have senior managementoversight. This includes review and approval of all major development plans prior to theirofficial commitment.
A. TrueB. False
Answer: A
QUESTION: 179A quarterly review in Initial Process should be conducted of
A. Facility-wide process compliance
CSTE
44
B. Installed quality performanceC. Schedule trackingD. Cost trendsE. Computing serviceF. Quality and productivity goals by projectG. All the above
Answer: G
QUESTION: 180The lack of reviews typically results in uneven and generally inadequate implementation ofthe process as well as frequent over commitments and cost surprises.
A. TrueB. False
Answer: A
QUESTION: 181A quality assurance group is charged with assuring management that software work is donethe way it is supposed to be done.
A. TrueB. False
Answer: A
QUESTION: 182To be effective the assurance organisation must have an independent reporting line tosenior management and sufficient resources to monitor performance of all
A. Key planning, implementation and verification activitiesB. Implementation and verification activitiesC. Change control, verification and planning
Answer: A
QUESTION: 183_____________ for software is fundamental to business and financial control as well as totechnical stability.
CSTE
45
A. Design and code changeB. Change controlC. a & b
Answer: B
QUESTION: 184To develop quality software on a predictable schedule _____________________ andmaintained with reasonable stability throughout the development life cycle.
A. Change control must be establishedB. Requirements must be established
Answer: B
QUESTION: 185While requirement changes are often needed, historical evidence demonstrates that manyhave to be deferred indefinitely.
A. TrueB. False
Answer: B
QUESTION: 186Design and code changes must be made to correct problems found in ________ ____, butthese must be carefully introduced.
A. Development planB. Test planC. Development and test
Answer: C
QUESTION: 187If changes are not controlled, then orderly _________________ is impossible and noquality plan can be effective.
A. Design, implementation and test
CSTE
46
B. Design and testC. Design and code
Answer: A
QUESTION: 188Organisations at the repeatable process level face major risks when they are presented withnew challenges.
A. TrueB. False
Answer: A
QUESTION: 189Repeatable process provides control over the way the organisation establishesits__________.
A. plans and commitmentsB. processes and productsC. both the above
Answer: A
QUESTION: 190Organisations in the _________ process level have achieved a degree of statistical controlthrough learning to make and meet their estimates and plans.
A. definedB. initialC. repeatable
Answer: C
QUESTION: 191New tools and methods will affect the process if they are not introduced with great care inthe repeatable process.
A. TrueB. False
CSTE
47
Answer: A
QUESTION: 192At the repeatable process level, a new manager has orderly basis for understanding theorganisation's operation, and new team members must learn the ropes through documents.
A. TrueB. False
Answer: B
QUESTION: 193The key actions required to advance from the repeatable to the next stage, the definedprocess are
A. to establish a process groupB. establish a development process architectureC. introduce a family of software engineering methods and technologiesD. all the above.
Answer: D
QUESTION: 194The process of establishing a software development process architecture or developmentlife cycle, that describes the technical and management activities required for properexecution of the development process must be attuned to
A. the documentation procedure of the organizationB. the specific needs of the organisation
Answer: B
QUESTION: 195The decomposition of architecture continues until each defined task is performed by anindividual or single management unit.
A. TrueB. False
Answer: A
CSTE
48
QUESTION: 196The architecture is a structural decomposition of the development cycle into tasks each ofwhich has a defined set of prerequisites, functional descriptions, verification proceduresand task completion specifications
A. TrueB. False
Answer: A
QUESTION: 197The family of software engineering methods and technologies that can be introduced inrepeatable process are
A. Design and code inspectionsB. Formal design methodsC. Library control systemsD. comprehensive testing methodsE. all the above
Answer: E
QUESTION: 198With the defined process the organisation has achieved the foundation established forexamining the process and deciding how to improve it.
A. TrueB. False
Answer: A
QUESTION: 199Defined process is quantitative.
A. TrueB. False
Answer: B
CSTE
49
QUESTION: 200With a defined process, we can focus the measurements on specific tasks.
A. TrueB. False
Answer: A
QUESTION: 201The process architecture is an essential prerequisite to effective measurement.
A. TrueB. False
Answer: A
QUESTION: 202The key steps to advance from the defined process to the managed process are establish aminimum basic set of process measurements to identify the quality and cost parameters ofeach process step.
A. establish a process data base and the resources to manage and maintain it.B. provide sufficient process resources to gather and maintain this process data and toadvise project members on its use.C. assess the relative quality of each product and inform management where quality targetsare not being met.D. all the aboveE. a, b ,c only
Answer: E
QUESTION: 203The greatest potential problem with the managed process is the cost of gathering data.
A. TrueB. False
Answer: A
QUESTION: 204
CSTE
50
In managed process approach data gathering with care and precisely define each piece ofdata in advance.
A. TrueB. False
Answer: A
QUESTION: 205Productivity data is essentially meaningless unless explicitly defined.
A. TrueB. False
Answer: A
QUESTION: 206It is rare that two projects are comparable by any simple measures. The variations in taskcomplexity caused by different product types ca exceed five to one.
A. TrueB. False
Answer: A
QUESTION: 207The degree of requirements change can make no difference as can the design status of thebase program in the case of enhancements.
A. TrueB. False
Answer: A
QUESTION: 208Process data must be used to compare projects or individuals.
A. TrueB. False
CSTE
51
Answer: B
QUESTION: 209The purpose of process data is to illuminate the product being developed and to provide aninformal basis for improving the process.
A. TrueB. False
Answer: A
QUESTION: 210When process data is used by the management to evaluate individuals or teams, thereliability of the data itself will deteriorate.
A. TrueB. False
Answer: A
QUESTION: 211The fundamental requirements for advancing from the managed process to optimisingprocess are
A. support automatic gathering of process dataB. use process data both to analyse and to modify the process to prevent problems andimprove the efficiencyC. both the above
Answer: C
QUESTION: 212In varying degrees, process optimisation goes on at all levels of process maturity.
A. TrueB. False
Answer: A
CSTE
52
QUESTION: 213Up to managed process level, software development managers have largely focused ontheir products and will typically gather and analyse only data that directly relates to productimprovement.
A. TrueB. False
Answer: A
QUESTION: 214In the optimising process the data is available to tune the process itself.
A. TrueB. False
Answer: A
QUESTION: 215With a little experience, management can soon see that process optimisation can producemajor quality and productivity benefits.
A. TrueB. False
Answer: A
QUESTION: 216Many types of errors can be identified and fixed far more economically by design and codeinspections than by testing.
A. TrueB. False
Answer: A
QUESTION: 217The data that is available with the optimising process gives us a new perspective on testing.
A. TrueB. False
CSTE
53
Answer: A
QUESTION: 218For most projects, a little analysis shows that there are two distinct activities involved
A. the removal of defectsB. the assessment of program qualityC. application of technology to critical tasksD. a & b
Answer: C
QUESTION: 219To reduce the cost of removing defects, inspections should be emphasised, together withany other cost-effective techniques. The role of functional system testing should then bechanged to one of gathering quality data on the programs
A. TrueB. False
Answer: A
QUESTION: 220With the optimising process, the data is available to justify the application of technology tovarious critical tasks, and numerical evidence is available on the effectiveness with whichthe process has been applied to any given product.
A. TrueB. False
Answer: A
QUESTION: 221With the optimising process, the organisation has the means to identify the weakestelements of the process and to fix them.
A. TrueB. False
CSTE
54
Answer: A
QUESTION: 222Verification is:
A. Checking that we are building the right systemB. Checking that we are building the system rightC. Performed by an independent test teamD. Making sure that it is what the user really wants
Answer: B
QUESTION: 223A regression test:
A. Will always be automatedB. Will help ensure unchanged areas of the software have not been affectedC. Will help ensure changed areas of the software have not been affectedD. Can only be run during user acceptance testing
Answer: B
QUESTION: 224If an expected result is not specified then:
A. We cannot run the testB. It may be difficult to repeat the testC. It may be difficult to determine if the test has passed or failedD. We cannot automate the user inputs
Answer: C
QUESTION: 225Which of the following could be a reason for a failure1) Testing fault2) Software fault3) Design fault4) Environment Fault5) Documentation Fault
CSTE
55
A. 2 is a valid reason; 1,3,4 & 5 are notB. 1,2,3,4 are valid reasons; 5 is notC. 1,2,3 are valid reasons; 4 & 5 are notD. All of them are valid reasons for failure
Answer: D
QUESTION: 226Test are prioritized so that:
A. You shorten the time required for testingB. You do the best testing in the time availableC. You do more effective testingD. You find more faults
Answer: B
QUESTION: 227Which of the following is not a static testing technique
A. Error guessingB. WalkthroughC. Data flow analysisD. Inspections
Answer: A
QUESTION: 228Which of the following statements about component testing is not true?
A. Component testing should be performed by developmentB. Component testing is also know as isolation or module testingC. Component testing should have completion criteria plannedD. Component testing does not involve regression testing
Answer: D
QUESTION: 229During which test activity could faults be found most cost effectively?
A. Execution
CSTE
56
B. DesignC. PlanningD. Check Exit criteria completion
Answer: C
QUESTION: 230Which, in general, is the least required skill of a good tester?
A. Being diplomaticB. Able to write softwareC. Having good attention to detailD. Able to be relied on
Answer: B
QUESTION: 231The purpose of requirement phase is
A. To freeze requirementsB. To understand user needsC. To define the scope of testingD. All of the above
Answer: D
QUESTION: 232The process starting with the terminal modules is called –
A. Top-down integrationB. Bottom-up integrationC. None of the aboveD. Module integration
Answer: B
QUESTION: 233The inputs for developing a test plan are taken from
CSTE
57
A. Project planB. Business planC. Support planD. None of the above
Answer: A
QUESTION: 234Function/Test matrix is a type of
A. Interim Test reportB. Final test reportC. Project status reportD. Management report
Answer: C
QUESTION: 235Defect Management process does not include
A. Defect preventionB. Deliverable base-liningC. Management reportingD. None of the above
Answer: B
QUESTION: 236What is the difference between testing software developed by contractor outside yourcountry, versus testing software developed by a contractor within your country?
A. Does not meet people needsB. Cultural differenceC. Loss of control over reallocation of resourcesD. Relinquishments of control
Answer: B
QUESTION: 237
CSTE
58
Software testing accounts to what percent of software development costs?
A. 10-20B. 40-50C. 70-80D. 5-10
Answer: B
QUESTION: 238A reliable system will be one that:
A. Is unlikely to be completed on scheduleB. Is unlikely to cause a failureC. Is likely to be fault-freeD. Is likely to be liked by the users
Answer: B
QUESTION: 239How much testing is enough
A. This question is impossible to answerB. The answer depends on the risks for your industry, contract and special requirementsC. The answer depends on the maturity of your developersD. The answer should be standardized for the software development industry
Answer: B
QUESTION: 240Which of the following is not a characteristic for Testability?
A. OperabilityB. ObservabilityC. SimplicityD. Robustness
Answer: B
QUESTION: 241Cyclomatic Complexity method comes under which testing method.
CSTE
59
A. White boxB. Black boxC. Green boxD. Yellow box
Answer: A
QUESTION: 242Which of these can be successfully tested using Loop Testing methodology?
A. Simple LoopsB. Nested LoopsC. Concatenated LoopsD. All of the above
Answer: D
QUESTION: 243To test a function, the programmer has to write a ______, which calls the function andpasses it test data.
A. StubB. DriverC. ProxyD. None of the above
Answer: B
QUESTION: 244Equivalence partitioning is:
A. A black box testing technique used only by developersB. A black box testing technique than can only be used during system testingC. A black box testing technique appropriate to all levels of testingD. A white box testing technique appropriate for component testing
Answer: C
QUESTION: 245
CSTE
60
When a new testing tool is purchased, it should be used first by:
A. A small team to establish the best way to use the toolB. Everyone who may eventually have some use for the toolC. The independent testing teamD. The vendor contractor to write the initial scripts
Answer: A
QUESTION: 246Inspections can find all the following except
A. Variables not defined in the codeB. Spelling and grammar faults in the documentsC. Requirements that have been omitted from the design documentsD. How much of the code has been covered
Answer: D
QUESTION: 247Define the following along with examplesA. Boundary Value testingB. Equivalence testingC. Error GuessingD. Desk checkingE. Control Flow analysis
Answer:A. Boundary value Analysis: - A process of selecting test cases/data by identifying theboundaries that separate valid and invalid conditions. Tests are constructed to test the insideand outside edges of these boundaries, in addition to the actual boundary points. or Aselection technique in which test data are chosen to lie along “boundaries” of the inputdomain [or output range] classes, data structures, procedure parameters, etc. Choices ofteninclude maximum, minimum, and trivial values or parameters.E.g. - Input data 1 to 10 (boundary value)Test input data 0, 1, 2 to 9, 10, 11B. Equivalence testing: - The input domain of the system is partitioned into classes ofrepresentative values, so that the no of test cases can be limited to one-per-class, whichrepresents the minimum no. of test cases that must be executed.
CSTE
61
E.g.- valid data range: 1-10Test set:-2; 5; 14C. Error guessing: - Test data selection technique. The selection criterion is to pick valuesthat seem likely to cause errors Error guessing is based mostly upon experience, with someassistance from other techniques such as boundary value analysis. Based on experience, thetest designer guesses the types of errors that could occur in a particular type of software anddesigns test cases to uncover them.E.g. - For example, if any type of resource is allocated dynamically, a good place to lookfor errors is in the de-allocation of resources. Are all resources correctly deallocated, or aresome lost as the software executes?D. Desk checking: - Desk checking is conducted by the developer of the system orprogram. The process involves reviewing the complete product to ensure that it isstructurally sound and that the standards and requirements have been met. This is the mosttraditional means for analyzing a system or program.E. Control Flow Analysis: - It is based upon graphical representation of the programprocess. In control flow analysis; the program graphs has nodes which represent a statementor segment possibly ending in an unresolved branch. The graph illustrates the flow ofprogram control from one segment to another as illustrated through branches .the objectiveof control flow analysis is to determine the potential problems in logic branches that mightresult in a loop condition or improper processing.
QUESTION: 248You find that there is a senior tester who is making more mistakes than the junior testers.You need to communicate this aspect to the senior tester. Also, you don’t want to loose thistester. How should one go about the constructive criticism?
Answer:In the quality approach, it is the responsibility of the supervisor to make His/Hersubordinates successful. The effective use of criticism is a tool for improving subordinateperformance.In giving constructive criticism, you should incorporate the following tactics: -• Do it privately.• Have the facts.• Be prepared to help the worker improve His/Her performance.• Be specific on Expectations.• Follow a specific process in giving the criticism.
QUESTION: 249Your manager has taken you onboard as a test lead for testing a web-based application. Hewants to know what risks you would include in the Test plan. Explain each risk factor thatwould be a part of your test plan.
CSTE
62
Answer:Web-Based Application primary risk factors:-A. Security: anything related to the security of the application.B. Performance:- The amount of computing resources and code required by the system toperform its stated functions.C. Correctness:-Data entered, processed, and outputted in the system is accurate andcompleteD. Access Control:-Assurance that the application system resources will be protectedE. Continuity of processing:-The ability to sustain processing in the event problem occursF. Audit Trail:-The capability to substantiate the processing that has occurred.G. Authorization:-Assurance that the data is processed in accordance with the intents of themanagement.General risk or secondary risk’s:-A. Complex - anything disproportionately large, intricate or convoluted. B. New - anythingthat has no history in the product.C. Changed - anything that has been tampered with or “improved”.D. Upstream Dependency - anything whose failure will cause cascading failure in the restof the system.E. Downstream Dependency - anything that is especially sensitive to failures in the rest ofthe system.F. Critical - anything whose failure could cause substantial damage. G. Precise - anythingthat must meet its requirements exactly.H. Popular - anything that will be used a lot.I. Strategic - anything that has special importance to your business, such as a feature thatsets you apart from the competition.J. Third-party - anything used in the product, but developed outside the project.K. Distributed - anything spread out in time or space, yet whose elements must worktogether.l. Buggy - anything known to have a lot of problems.M. Recent Failure - anything with a recent history of failure.
QUESTION: 250You are in the contract stage of a project and are developing a comprehensive proposal fora safety critical software system. Your director has consulted you for preparing a guidelinedocument what will enlist user’s role during acceptance testing phase. Indicate the keyroles you feel that the user should play during acceptance stage. Also indicate thecategories into which the acceptance requirements should fall.
Answer:1) Ensure user involvement in developing systems requirement and acceptance criteria.2) Identify interim and final products for acceptance their acceptance criteria and schedule.3) Plan how and by whom each acceptance activity will be performed.4) Plan resources for providing information.
CSTE
63
5) Schedule adequate time for buyer staff to receive and examine the products andevaluation prior to acceptance review.6) Prepare the acceptance plan.7) Respond to the analysis of project entitles before accepting and rejecting.8 ) Approve the various interim software products.9) Perform the final acceptance activities, including the formal acceptance testing atdelivery.10) Make an acceptance decision for each product.
QUESTION: 251What is parallel testing and when do we use parallel testing? Explain with example?
Answer:Testing a new or an altered data processing system with the same source data that is used inanother system. The other system is considered as the standard of comparison. OR we cansay that parallel testing requires the same input data be run through two versions of thesame application.Parallel testing should be used when there is uncertainty regarding thecorrectness of processing of the new application. And old and new versions of theapplications are same.E.g.-1) Operate the old and new version of the payroll system to determine that the paychecksfrom both systems are reconcilable.2) Run the old version of the application system to ensure that the operational status of theold system has been maintained in the event that problems are encountered in the newapplication.
QUESTION: 252What is the difference between testing Techniques and tools? Give examples.
Answer:Testing technique: - Is a process for ensuring that some aspects of the application system orunit functions properly there may be few techniques but many tools.Tools: - Is a vehicle for performing a test process. The tool is a resource to the tester, butitself is insufficient to conduct testingE.g.:- The swinging of hammer to drive the nail. The hammer is a tool, and swinging thehammer is a technique. The concept of tools and technique is important in the testingprocess. It is a combination of the two that enables the test process to be performed. Thetester should first understand the testing techniques and then understand the tools that canbe used with each of the technique.
QUESTION: 253Quality control activities are focused on identifying defects in the actual productsproduced; however your boss wants you to identify and define processes that would
CSTE
64
prevent defects. How would you explain to him to distinguish between QA and QCresponsibilities?
Answer:Quality Assurance:1) A planned and systematic set of activities necessary to provide adequate confidence thatrequirements are properly established and products or services conform to specifiedrequirements2) An activity that establishes and evaluates the processes to produce the products.3) Helps establish processes.4) Sets up measurements programs to evaluate processes.5) Identifies weaknesses in processes and improves them.6) QA is the responsibility of the entire team.7) Prevents the introduction of issues or defectsQuality Control:1) The process by which product quality is compared with applicable standards; and theaction taken when nonconformance is detected.2) An activity which verifies if the product meets pre-defined standards.3) Implements the process.4) Verifies if specific attribute(s) are in a specific product or service5) Identifies defects for the primary purpose of correcting defects.6) QC is the responsibility of the tester.7) Detects, reports and corrects defects
QUESTION: 254Differentiate between Transaction flow modeling, Finite state modeling, Data flowmodeling and Timing modeling?
Answer:Transaction Flow modeling: -The nodes represent the steps in transactions. The linksrepresent the logical connection between steps.Finite state modeling:-The nodes represent the different user observable states of thesoftware. The links represent the transitions that occur to move from state to state.Data flow modeling:-The nodes represent the data objects. The links represent thetransformations that occur to translate one data object to another.Timing Modeling:-The nodes are Program Objects. The links are sequential connectionsbetween the program objects. The link weights are used to specify the required executiontimes as program executes.
QUESTION: 255List what you think are the two primary goals of testing
CSTE
65
Answer:1) Determine whether the system meets specifications (producer view)2) determine whether the system meets business and user needs (Customer view)
QUESTION: 256As a general rule, __________ measures are much more important.
A. SubjectiveB. Objective
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 257If the measurement taken by the two people are same refers to the term as
A. ReliabilityB. ValidityC. CalibrationD. Ease of Use and Simplicity
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 258The term __________ refers the degree to which a measure actually measures what it wasintended to measure.
A. ReliabilityB. ValidityC. CalibrationD. Ease of Use and Simplicity
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 259When basic quality aspects have been identified the “standards” should be defined by
A. IT TeamB. Project ManagerC. Quality Assurance personalD. ManagementE. Development Team
CSTE
66
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 260The “standards” for the software developed using new technology should be defined by
A. IT TeamB. Project ManagerC. Quality Assurance personalD. ManagementE. Development Team
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 261If the COTS software developed by the contractor which is from the another country, thenthe following problem arises:
A. Cultural differencesB. Communication barriersC. The two words having the same name in diff. countriesD. All of the aboveE. None of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 262The ‘V’ represents the following term:
A. Verification and ValidationB. Static testing and Dynamic testingC. Black box and White Box testingD. Software development process and Software testing process
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 263Test Readiness Review is conducted by the
A. Project Manager
CSTE
67
B. Test ManagerC. Quality Assurance PersonnelD. User/Customer
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 264Acceptance testing is the ________ type of testing
A. Black box testingB. White box testingC. Shoe box testingD. Structural testing
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 265__________ is not the White box testing technique.
A. Condition CoverageB. Decision CoverageC. Test script coverageD. User specified Data coverageE. All of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 266Event identification, Risk Response are the term defined in the ___internal control model
A. COSO Enterprise Risk Management (ERM. ModelB. COSO Internal Control ModelC. CobiT Model
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 267A statistical technique to assess, monitor and maintain the stability of a process.
CSTE
68
A. Pareto ChartB. Control ChartC. Run ChartD. Cause and Effect DiagramE. Histogram
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 268Determination to continue with the software development or not is determined from the
A. InspectionB. In-process ReviewC. Phase end reviewD. Don’t remember other options
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 269The following is the component for the FIT
A. DataB. StructureC. PeopleD. RuleE. All of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 270A major obstacle for deployment of wireless networks is in the
A. StandardsB. CoverageC. Security
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 271Hand-held and internet enabled devices are example of
CSTE
69
A. Electronic equipmentB. Wireless ApplicationsC. Computer devices
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 272Therapeutic listening is
A. Sympathetic listeningB. Listening to pieces of information…C. Analyzing the listening of the speaker
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 273Function point is a measure of
A. EffortB. ComplexityC. UsabilityD. Size
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 274Acceptance Testing is the responsibility of the:
A. ProgrammerB. Project LeaderC. Independent TesterD. Assistance programmerE. User
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 275While deciding the Test tool the following factors should be considered
CSTE
70
A. Testing for the next builds/releases after making changesB. Testing where large volumes of data is requiredC. Testing based on the UI interfaceD. All of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 276Completeness can be defined as the
A. Customer says the product is readyB. Tester says the testing is completedC. Don’t remember the other options
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 277Auxiliary code which sets up an appropriate environment and calls the module is termed as
A. DriverB. FunctionC. StubD. None of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 278A question on fit components. Which of the following contributes to fit.
A. DataB. StructureC. PeopleD. RuleE. All of the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 279Reliability, timeliness, consistency are included in which component of fit
CSTE
71
A. DataB. StructureC. PeopleD. Rule
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 280Who will develop the test process for software development using new technology?
A. ManagementB. Project teamC. AuditorD. Tester and few more options
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 281Which of the following are relatively complete acceptance criteria? A. Performance shouldincreaseB. Response time should be with in 10 sec Few more statements.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 282Which of the following model has these steps .. event identification , risk assessment, riskresponse
A. ERMB. COSO internal control frameworkC. CobiT model
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 283Utilize the computer resources to perform their work.. belong to which type of activityspecified below
CSTE
72
A. InterfaceB. DevelopmentC. Computer operation
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 284Obligations of both contractual parties should be spelled out in detail in which part of thecontract?
A. WhatB. WhoC. WhenD. How
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 285Test planning activity which includes starting and end time for each test milestone.
A. BudgetingB. SchedulingC. EstimationD. Staffing
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 286Which communication skill will be neglected by most
A. ReadingB. ListeningC. Writing
Answer: Pending. Please send your suggestions to [email protected]
CSTE
73
QUESTION: 287Therapeutic listening is
A. Sympathetic listeningB. Listening to pieces of information…
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 288Which model demonstrates relation between 2 or more parameters of effort, duration orresource?
A. CostB. ConstraintC. Function Point
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 289In which model expertise can be used to estimate cost
A. Top-DownB. Expert JudgmentC. Bottom-Up
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 290Fit for use is
A. TranscendentB. Product BasedC. User BasedD. Value Based
Answer: Pending. Please send your suggestions to [email protected]
CSTE
74
QUESTION: 291Re-Use of data is done in which type of testing (Similar type 2 questions on retesting andregression testing)
A. Capture/Play backB. System TestingC. Regression TestingD. Integration Testing
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 292In Acceptance testing, which data is used.
A. Test CasesB. Use CaseC. Test Plan
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 293In four components of FIT, reliability is included in (Similar type 2 qs)
A. DataB. PeopleC. StructureD. Rules
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 294Obligations of both contractual parties should be spelled out in
A. What is doneB. Who does itC. When it is doneD. How it is done
CSTE
75
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 295Dates on which Obligations need to be filled out should be specified in
A. What is doneB. Who does itC. When it is doneD. How it is done
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 296Who defined the standards?
A. ISOB. QAI
Answer: A
QUESTION: 297Juran is famous for
A. Quality ControlB. Management
Answer: A
QUESTION: 298Which one is not Statistical Tool?
A. Cause & effect GraphingB. StratificationC. Run ChartD. Regression Analysis
Answer: A
CSTE
76
QUESTION: 299Histogram refers to
A. Bar ChartB. Run ChartC. Pareto
Answer: A
QUESTION: 300Who are there in External IT TEAM?
A. Non DeveloperB. Customer/ User
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 301Which one is not Structural Testing?
A. RegressionB. ParallelC. AcceptanceD. Stress
Answer: C
QUESTION: 302Who is not part of Inspection?
A. Prj ManagerB. AuthorC. ModeratorD. ReaderE. Inspetor
Answer: A
CSTE
77
QUESTION: 303Tester job is not to
A. Report DefectB. Who entered the defect in system
Answer: B
QUESTION: 304Which one is not secondary role of tester
A. Raising IssuesB. Instilling ConfidenceC. cts improving processD. InsightE. developer work
Answer: E
QUESTION: 305Acceptance testing is
A. White BoxB. Black boxC. White box & black BoxD. none of the above
Answer: B
QUESTION: 306Deming 14 principle includes
A. mobility of mgmtB. new philosphyC. adobt leadershipD. both b& cE. both a & c
Answer: E
CSTE
78
QUESTION: 307Configuration Management tool used in which phase.
A. Unit tetsingB. IntegrationC. acceptingD. all the phases
Answer: D
QUESTION: 308Max Defects created in which phases
A. reqB. designC. ImplementaionD. Coding
Answer: A
QUESTION: 30950% Defect found in which phase
A. reqB. designC. ImplementaionD. Coding
Answer: A
QUESTION: 310defects are least costly in which phase
A. reqB. designC. ImplementaionD. Coding
CSTE
79
Answer: A
QUESTION: 311Software inspections categorize defects as Wrong, Missing and Extra.
A. TRUEB. FALSE
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 312The purpose of Risk Management in a project is to
A. Eliminate RisksB. Minimize RisksC. Avoid risksD. Anticipate the risks
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 313Testing of the system to demonstrate system compliance with user requirements is:
A. Black box testingB. System testingC. Independent testingD. Acceptance Testing
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 314Function point is a measure of
A. EffortB. ComplexityC. UsabilityD. None of the above
Answer: Pending. Please send your suggestions to [email protected]
CSTE
80
QUESTION: 315An activity that verifies compliance with policies and procedures and ensures thatresources are conserved is
A. an inspectionB. an auditC. a reviewD. an assessment
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 316Which is the application for the process management and quality improvement concepts tosoftware development and maintenance.
A. Malcolm BaldridgeB. ISO 9000C. QAID. QS14000
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 317Software testing accounts for what percent of software development costs?
A. 10-20B. 30-60C. 70-80
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 318Software errors are least costly to correct at what stage of the development cycle?
A. RequirementsB. ConstructionC. Acceptance testD. Design
Answer: Pending. Please send your suggestions to [email protected]
CSTE
81
QUESTION: 319Which of the following test approaches is not a Functional test approach?
A. Control TechniqueB. Stress TechniqueC. Regression TechniqueD. Cause/effect GraphingE. Requirements
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 320Effectiveness is doing things right and efficiency is doing the right things
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 321Juran is famous for
A. Quality ControlB. Quality AssuranceC. Trend Analysis
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 322Top down & Bottom Up are the part of Incremental Testing
A. TrueB. False
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 323
CSTE
82
Achieving quality requires:
A. Understanding the customers expectationsB. Exceeding the customers expectationsC. Meeting all the definitions of qualityD. Focusing on the customerE. All the above
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 324Which is NOT the exit criteria for unit testing:there is a application which is delivered to the customer now customer found bugs andassume each bug cost is $125 and there are 4 bugs found each day and there are 5 workingday. What should be the cost to fix those bugs
A. $300B. $25000C. $ 15000D. $ 13,000E. $ 26,000
Answer: B
QUESTION: 325Which is NOT the exit criteria for unit testing:Tester should know
A. Test planningB. Automation toolC. Defect tracking toolD. programming language
Answer: C
QUESTION: 326Which is NOT the exit criteria for unit testing:Pareto Analysis
A. 80-20 ruleB. Trend analysis
CSTE
83
Answer: A
QUESTION: 327Which is NOT the exit criteria for unit testing:Testing efforts in SDLC
A. 10-20 %B. 30-60%C. 60-80%D. 80-90%
Answer: B
QUESTION: 328Which is NOT the exit criteria for unit testing:Critical Listening is
A. Listen analyses what speaker saidB. Listen what is requiredC. Listen only summary
Answer: A
QUESTION: 329Which is NOT the exit criteria for unit testing:Who finds vulnuralibility in system?
A. ICOB. ISSC. It Manager
Answer: A
QUESTION: 330Which is NOT the exit criteria for unit testing:Which is NOT the exit criteria for unit testing:COQ is not
CSTE
84
A. ProductionB. AppraisalC. PreventionD. Failure
Answer: A
QUESTION: 331Which is NOT the exit criteria for unit testing:Training come under what category cost of quality?
A. AppraisalB. PreventiveC. FailureD. none of the above
Answer: B
QUESTION: 332Which is NOT the exit criteria for unit testing:Why testing is called negative
A. EasyB. delay in implementationC. No training reqd Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 333Which is NOT the exit criteria for unit testing:Incremental testing is Top down & bottom Up testing
A. TrueB. false
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 334Which is NOT the exit criteria for unit testing:Effectiveness is doing right thing & efficiency is doing thing right
CSTE
85
A. TrueB. false
Answer: B
QUESTION: 335Which is NOT the exit criteria for unit testing:Which one is not part of Demind
A. PlanB. doC. checkD. actE. risk analysis
Answer: E
QUESTION: 336Which is NOT the exit criteria for unit testing:Defect fixed in which phase is lease cost
A. same phaseB. productionC. next phaseD. none
Answer: A
QUESTION: 337Which is NOT the exit criteria for unit testing:In White box testing test coverage is
A. DecisionB. StatementC. branchD. modified decisionE. user specified data coverage
CSTE
86
Answer: A
QUESTION: 338Which is NOT the exit criteria for unit testing:Test Plan should not contain
A. ScopeB. ObjectiveC. PolicyD. Risk Analysis
Answer: C
QUESTION: 339Which is NOT the exit criteria for unit testing:Acceptance Testing is the responsibility of the:
A. ProgrammerB. Project LeaderC. Independent TesterD. Assistance programmerE. User/Customer
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 340Which is NOT the exit criteria for unit testing:Cost of Quality is least among
A. PreventionB. AppraisalC. Failure
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 341Which of the following is not a perspective of quality?
A. transcendentB. product-basedC. translucentD. user-based
CSTE
87
E. value-basedF. manufacturing based
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 342Effectiveness is doing things right and efficiency is doing the right things.
A. TrueB. False.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 343Which of the following is not one of Deming's 14 points for management?
A. Adopt a new philosophyB. Eliminate slogans, exhortations, and targets for the work forceC. Mobility of managementD. Create constancy of purpose
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 344The largest cost of quality is from production failure.
A. TrueB. False.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 345Defects are least costly to correct at what stage of the development cycle?
A. RequirementsB. Analysis & DesignC. ConstructionD. Implementation
Answer: Pending. Please send your suggestions to [email protected]
CSTE
88
QUESTION: 346A review is what category of cost of quality?
A. PreventiveB. AppraisalC. Failure
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 347A defect is related to the term fault.
A. TrueB. False.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 348What type of change do you need before you can obtain a behavior change?
A. LifestyleB. VocabularyC. InternalD. Management
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 349Software testing accounts for what percent of software development costs?
A. 10-20B. 40-50C. 70-80D. 5-10
Answer: Pending. Please send your suggestions to [email protected]
CSTE
89
QUESTION: 350The purpose of software testing is to:
A. Demonstrate that the application works properlyB. Detect the existence of defectsC. Validate the logical design
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 351One of the key concepts of a task force is that the leader be an expert in leading groups asopposed to an expert in a topical area.
A. TrueB. False.
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 352Match the following terms with their definitions:
A. Black box testingB. White box testingC. Conversion testingD. Thread testingE. Integration testing
Answer: Pending. Please send your suggestions to [email protected]
QUESTION: 353List what you think are the two primary goals of testing. What is a test strategy?
Answer:A test strategy must address the risks and present a process that can reduce those risks. Thetwo components of Test strategy are:a) Test Factor: The risk of issue that needs to be addressed as a part of the test strategy.Factors that are to be addressed in testing a specific application system will form the test
CSTE
90
factor.b) Test phase: The phase of the systems development life cycle in which testing win occur.)
QUESTION: 354When to stop testing?
Answer:a) When all the requirements are adequately executed successfully through test cases b) Bugreporting rate reaches a particular limitc) The test environment no more exists for conducting testing d) The scheduled time fortesting is overe) The budget allocation for testing is over
CSTE
91