csp in south africa - afdb.org in south africa tunisia june 2012 ... typical summer day dni typical...
TRANSCRIPT
AfDB and World Bank Workshop – CSP Scale up program for Middle East and North
Africa Region
CSP in South Africa
Tunisia June 2012
Vikesh Rajpaul Programme Manager – Concentrating Solar Power
Renewables Business Unit, Eskom
E-mail [email protected] Website www.eskom.co.za
Outline
•2
Strategic Drivers
Why develop Concentrating Solar Power in
South Africa
Projects under development
Challenges in CSP project development
Opportunities from CSP project development
Lessons Learnt
•3
Strategic Drivers
South Africa 1994 - 2008 growth
Real GDP
64%
Power capacity
(~5 000 MW)
14% •How do we
keep the
lights on and
move to a
cleaner
future?
•4
Strategic Drivers
South Africa’s renewable energy strategy driven by low-carbon objectives and priorities outlined in:
•South Africa’s Long-Term Mitigation Scenarios (LTMS),
•Renewable Energy White Paper of 2003,
•National Energy Efficiency Strategy of 2009,
•Government’s National Climate Change Response green paper of 2010,
•The New Growth Path Framework (2010),
• The Integrated Resources Plan (IRP) 2010.
•5
Strategic Drivers
Total additional new capacity
(without committed) until 2030 in GW
5
20
15
10
0
Wind
CSP
Solar PV
1,0
Peak -
OCGT
Coal
3,9
8,4
9,6
6,3
8,4
17,8
Renew-ables Nuclear Gas -
CCGT
2,4 2,6
Hydro
25
15% 23% 6% 6% 9% 42%
Share
of total
new GW
65% 20% 5% 1% < 0,1% 9%
90% 5% 5% 0% < 0,1% 0% Energy
share
in 2010
in 2030
= 260 TWh
= 454 TWh
Policy-Adjusted IRP (Capacity)
Source IRP 2010
•6
Why develop Concentrating Solar Power in South Africa
•7
Strategic Drivers - CSP with Storage
24000
26000
28000
30000
32000
34000
36000
38000
0
200
400
600
800
1000
1200
0:30 3:30 6:30 9:30 12:30 15:30 18:30 21:30
typical Summer day DNI typical Summer day demand
24000
26000
28000
30000
32000
34000
36000
38000
0
200
400
600
800
1000
1200
0:30 3:30 6:30 9:30 12:30 15:30 18:30 21:30
typical Winter day DNI typical Winter day demand
•Power available from conversion technologies does not align with the needs of the system operator to meet demand.
•DN
I W
h /
m2
•DN
I W
h /
m2
•Dem
an
d M
W
•De
ma
nd
MW
•8
Projects under development
9
•9
Eskom CSP plant
• Central Receiver with Molten Salt as the heat transfer
and storage medium.
• 100 MWe with a capacity factor in excess of 60 %.
• The plant will be dry cooled or hybrid cooled
designed to optimise water usage.
• All auxiliary power will be sourced from the National
grid and backup will be sourced from diesel
generators.
• Life of plant will be a minimum of 25 years.
• The plant will displace about 9m tons over its
lifetime.
• It can provide electricity to 400 000 standard homes
per annum if 200kW per month is assumed.
• 1000 – 1500 jobs can be created during construction
and approx. 70 during operation
Gemasolar
Solar 2
10
Eskom CSP plant status
• EIA complete – ROD obtained – Revision in progress
• Land Procured.
• Funding obtained from World Bank, African
Development Bank (AfDB), Kredit Anstalt fur
Weideafbau (KfW), European Investment Bank (EIB),
French Development Agency (AFD), Clean
Technology Fund (CTF).
• Five years of Solar data – site and satellite.
• Water Supply – 300 ML / annum secured.
• Owner’s Engineer appointed.
• Construction scheduled to start in 2014 for
completion at the end of 2016.
Analysis of MW allocation and remaining MW
Technology
MW allocation
in accordance
with the
Determination
MW capacity
allocated in
the First Bid
Submission
Phase
MW capacity
allocated in
the Second
Bid
Submission
Phase
MW capacity
for allocation
in future Bid
Submission
Phases
Onshore wind 1 850.0 MW 634.0 MW 562.5 MW 653.5 MW
Solar photovoltaic 1 450.0 MW 631.5 MW 417.1 MW 401.1 MW
Concentrating
solar power 200.0 MW 150.0 MW 50.0 MW 0.0 MW
Small hydro (≤ 10MW) 75.0 MW 0.0 MW 14.3 MW 60.7 MW
Landfill gas 25.0 MW 0.0 MW 0.0 MW 25.0 MW
Biomass 12.5 MW 0.0 MW 0.0 MW 12.5 MW
Biogas 12.5 MW 0.0 MW 0.0 MW 12.5 MW
Total 3 625.0 MW 1 415.5 MW 1 043.9 MW 1 165.6 MW
Source : Dept of Energy
Preferred Bidders Salient Terms CSP
Source : DoE •13
Bid Window 2 Bid Window 1
Price: Fully Indexed (Ave Rand per
MWh) R 2 512 R 2 686
MW allocation 50 MW 150 MW
Total Project Cost (R’million) R 4 483 R 11 365
Local Content Value (R’million) R 1 638 R 2 391
Local Content % 36.5% 21.7%
Job Creation : Construction (People) 662 1 165
Job Creation : Operations (People) 50 70
•14
Challenges in CSP project development
Challenge – Current Cost of CSP in relation to PV
Challenge - Worldwide PV market more than sextupled since 2007
•16
•Source : Boston Consulting Group
Challenge – difficulty in obtaining finance for technically most suitable technology
•17
Site location – Upington
Assumed same financing structure for both technologies.
Costs are reported in January 2012 South African Rand.
EPRI April 2012 Technical update report for IRP of South Africa confirm Central Receiver plant has lower capital costs and lower LCOE when compared to Parabolic Trough plants
•18
Challenge – Level of Maturity of Central Receiver / Power Tower
•Molten Salt
•Proven in demonstration projects, and recently completed. construction of first commercial plant (Gemasolar) – 19.9 MWe.
• Under Construction – Solar Reserve – Tonopah – 565 MW thermal with storage. Planned completion 2015.
•Molten Salt
•Proven in demonstration projects, and recently completed. construction of first commercial plant (Gemasolar) – 19.9 MWe.
• Under Construction – Solar Reserve – Tonopah – 565 MW thermal with storage. Planned completion 2015.
•Direct Steam Generator
• PS 10 (2007) and PS 20 (2009) – saturated steam.
• Siera Sun 5 MW – 2009 -saturated
• Under Construction – Ivanpah – 1-3 with 1 x 123 MWe/ 2 x 133 MWe planned to be in operation by 2013 – superheated steam.
•
•Direct Steam Generator
• PS 10 (2007) and PS 20 (2009) – saturated steam.
• Siera Sun 5 MW – 2009 -saturated
• Under Construction – Ivanpah – 1-3 with 1 x 123 MWe/ 2 x 133 MWe planned to be in operation by 2013 – superheated steam.
•
•PS-20 built by Abengoa
•(Source: RENAC, 2010)
•Gemasolar built by Torresol
CSP Challenges - Summary
•19
CSP Tower technology is in early stages
of development life cycle.
Lacks long term commercial and technical
operating experience.
Achieving balance between cost, risk and
affordability is a challenge.
Local industry involvement non-negotiable.
Local Currency funding limited and foreign
exchange risk a challenge.
Difficulty in financing
projects without
concessional financing
Cost of technology is a barrier to entry.
Often compared to
Wind and PV but should
be compared to gas in
South Africa
Skills constraints for
first projects.
Increased cost of capital
•20
Opportunities from CSP project development
•21
•Source : EA SAC 2011
•Impact of the quality of the solar resource (DNI) on the relative LEC
•EA SAC projected LEC reduction with CSP Growth
Opportunity – Potential for reduction in cost of CSP
•Barrier to entry: Current cost of CSP.
•European Academies Science Advisory Council - Nov 2011 - predicts grid price parity with Fossil between 2020 and 2030 in Europe, and sooner in places with higher DNI.
•Barrier to entry: Current cost of CSP.
•European Academies Science Advisory Council - Nov 2011 - predicts grid price parity with Fossil between 2020 and 2030 in Europe, and sooner in places with higher DNI.
•Eskom anticipates CSP cost reduction through:
• Capacity expansion,
• Research and Development,
• Localisation.
•Eskom anticipates CSP cost reduction through:
• Capacity expansion,
• Research and Development,
• Localisation.
22
Summary of opportunities for CSP in South Africa
Source: Eskom, BCG analysis
Cata
lyst
for
ch
an
ge in
So
uth
Afr
ica
6
Economic growth engine
1
Job creation and skills
development
2
Positive Impact on local
communities
Positive Environmental footprint
4
Enabler of S.A. Development
through electricity for all initiative
5
3
•23
Lessons Learnt
• Government support is imperative in embarking on Sustainable projects.
• Effective diversification not possible without concessional funding.
• Benefits to Local industry must be demonstrated to harness support:
– Job creation
– Poverty alleviation
• Thorough Environmental Impact Assessment with no fatal flaws is key to obtaining local
support.
• Site selection - Should be close to established infrastructure like:
– Water supply, National roads, Transmission connection, Airport etc.
• Since local expertise is limited, consultants may be required initially but with emphasis
on training and development.
• In procuring the plant, emphasis should be placed on local supply, T&D, and technology
transfer.
•24
THANK YOU
Vikesh Rajpaul Programme Manager – Concentrating Solar Power
Renewables Business Unit
Eskom
Tel (ZA) +27 11 516 7414 | Fax +27 086 667 6958 | Mobile +27 73 799 9893
Eskom Holdings SOC Limited (Reg No: 2002/015527/06)
E-mail [email protected] Website www.eskom.co.za