csm-2014 hydraulic fracturing and push-pull isco - pdf
TRANSCRIPT
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
AN INTEGRATED HYDRAULIC
FRACTURING AND PUSH-PULL ISCO
APPROACH FOR CRYSTALLINE
BEDROCK AQUIFER
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PRESENTATION OUTLINE
• Site Background
• Remedial Approach
• Phase I Pilot Test
• Phase II Pilot Test
• ISCO Remedy Design
• ISCO Implementation
• Conclusions
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
SITE BACKGROUND • 98 Acre Former Industrial R&D Facility
• Trichloroethene (TCE) impacts in soil and groundwater
Extent of TCE Plume (1 ppb)
Groundwater
Flow Direction
• Groundwater concentrations of TCE up to 59,000 ppb (PIW-1B, Nov 2011)
• Bulk of TCE impacts in the intermediate bedrock zone
• 155 tons of source area soil removed in 2006
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
• Unstratified Glacial Deposits
• Bedrock (Diorite)
SITE GEOLOGY
Photographer: Siim Sepp, 2005, Source: Wikipedia
Diorite fragments from well drilling
Shallow Bedrock
Intermediate Bedrock
Deep Bedrock
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
REMEDIAL APPROACH Why Permanganate?
• Bedrock matrix had low SOD (0.5 g/kg), enabling chemical oxidation to be more cost effective.
• Known to be effective for removal of chlorinated ethenes
• Relatively short remedial timeframe
• MnO4- Relatively long subsurface
half-life (months to years)
2KMnO4 + C2HCl3 2CO2 + 2MnO2 + 3Cl- + H+ + 2K+
Permanganate MnO4
- + 4H+ + 3e- → MnO2(s) + 2H2O E° = 1.70 V
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PHASE I ISCO PILOT TEST – NOVEMBER 2011
Automated Portable Bulk Feed System (Vironex)
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PILOT TEST ACTIVITIES
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
INJECTION SUMMARY • Three injection wells
• 6,081 gallons of 2.5% potassium permanganate
• 1,260 lbs. of oxidant
• Three day operation
• 97% of solution injected into the Deep Bedrock Zone (Flow rate = 5 to 22 gpm at 60 psi)
• Shallow and Intermediate Bedrock: No measureable flow at injection pressures up to 100 psi
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
RADIUS OF INFLUENCE • Deep zone ROI is at least 25 feet - Observed
pink water at MW-12C.
• Observed groundwater mounding at MW-12C, MW-16B, MW-17B and MW-12D
• 99% reduction in TCE at PIW-1C, where the majority of the solution was injected
• 62% reduction in TCE at MW-12C, the directly downgradient deep monitoring well
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
GEOCHEMICAL PARAMETERS ORP
pH
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PHASE I TESTING RESULTS
• ISCO is a feasible remedial technology for the site.
• Concentrations did not decrease significantly due to the inability to inject in the intermediate bedrock zone.
• Hydraulic fracturing needed to achieve reasonable injection rates in the intermediate bedrock zone
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PHASE II ISCO PILOT TEST – APRIL 2012 Objectives:
• Obtain injection flow-pressure relationships for full-scale remedial design
• Evaluate strategies to increase chemical distribution
• Evaluate effectiveness of hydraulic fracturing to facilitate injection in the intermediate bedrock zone
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
FIELD IMPLEMENTATION Methodology and Operation:
• Installed an additional intermediate injection well (PIW-2B)
• Hydro-fractured PIW-2B
• Injected 2,000 gallons of 2.5% KMnO4 (452 lbs.) in PIW-2B
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
HYDRAULIC FRACTURING
• Fracturing of rock by a pressurized liquid
• Increases connectivity of aquifer and well yield
• Performed at PIW-2B at 100-150 bgs, where highest TCE concentrations were observed, by Northeast Water Production, Inc.
• Direct hydraulic connection was observed, as a function of water level fluctuations, between PIW-2B and PIW-1C, following hydro-fracturing.
OVERBURDEN OVERBURDEN
WEATHERED BEDROCK WEATHERED BEDROCK
DIORITE DIORITE
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
INJECTION OBSERVATIONS • Hydraulic fracturing can achieve flow rates of up to 15
gpm at pressures less than 50 psi.
• Hydraulic influence was observed at distances up to 125 feet during injection.
• Groundwater daylighting was observed at PIW-1C.
Visual evidence of permanganate solution in PIW-1A
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
POST ISCO GROUNDWATER DATA • Oxidant distribution
at distances up to 125 feet downgradient
• Oxidant was present at several wells during the post injection sampling round
• No indication of rebound at PIW-1B
Notes:
‒ -- = Sample not collected
‒ Sampled via passive diffusion bag (PDB) samplers
‒ NJDEP GWQS for TCE = 1 ppb
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PHASE II TESTING RESULTS
• ISCO is feasible for the intermediate bedrock zone.
• Hydro-fracturing can significantly enhance oxidant injection rates and distribution in the subsurface.
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
PUMP/WELL YIELD TESTING – APRIL 2013
• Performed at seven monitoring wells to verify achievable extraction rates that can be sustained during ISCO
• Specific capacity (step-drawdown) aquifer pumping tests - Flow rates at individual wells ranged from 0.15 to 1.5 gpm
• Constant-rate aquifer pumping test - Conducted at seven wells simultaneously at 5 gpm
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
FULL-SCALE ISCO REMEDY DESIGN Remedial Strategy:
• Installation of six additional intermediate bedrock zone injection wells, one extraction well
• Hydraulic fracturing of select injection wells
• ISCO with NaMnO4
• Groundwater extraction at select monitoring wells along the downgradient site boundary while injecting oxidant “Push-Pull ISCO Approach”
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
• Total mass of 40% NaMnO4 = 61,100 lbs.
• Target NaMnO4 injection solution concentration = 10%
• Total injection volume = 27,400 gallons
• Design injection rate = 10 gpm (over 6 hours/day)
• Design extraction rate = 3 gpm (over 8 hours/day)
INJECTION & EXTRACTION STRATEGY
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
INJECTIONS & EXTRACTION WELLS
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
EQUIPMENT LAYOUT
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
FULL-SCALE IMPLEMENTATION: OCTOBER – NOVEMBER 2014
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
INJECTION ACTIVITIES…
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
INJECTION VOLUMES Date Daily Total
PIW-1A PIW-1B PIW-1C PIW-2B IW-3B IW-4B IW-5B IW-6B IW-7B IW-8B (gallons)
10/16/2014 1,000 1,000
10/17/2014 1,200 1,200
10/20/2014 400 600 200 1,200
10/21/2014 1,200 1,200
10/22/2014 803 176 221 1,200
10/23/2014 779 217 296 108 1,400
10/24/2014 60 500 109 178 181 372 1,400
10/27/2014 75 900 160 180 145 140 1,600
10/28/2014 1,000 1,000
10/29/2014 1,600 1,600
10/30/2014 1,400 1,400
10/31/2014 650 200 850
11/3/2014 1,075 125 1,200
11/4/2014 1,300 1,300
11/5/2014 50 300 650 100 1,100
11/6/2014 70 665 665 1,400
11/7/2014 66 567 567 1,200
Well Total (gallons) 321 - 1,400 2,600 2,123 2,603 1,600 5,401 2,925 2,277 21,250
Proposed Volume 700 700 1,400 2,600 1,600 2,600 1,600 5,400 5,400 5,400 6,150
Injection Well
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
ISCO PERFORMANCE SAMPLING
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
GROUNDWATER SAMPLING RESULTS
Well MW-25B-1 MW-25B-2 MW-25B-3 MW-25B-4
Sampling Depth (ft bgs) 122.5 127.5 132.5 137.5
10/1/2014 1,400 440 230 200
10/20/2014 1,400 NS NS NS
10/23/2014 1,100 390 310 270
10/30/2014 850 540 280 270
Sa
mp
lin
g
Da
te
TCE Concentrations, ug/L
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
SIMILAR APPROACH ANOTHER SITE • TCE plume occupies an area of approximately 3 million
ft2.
• Poorly connected fractures form a complex network with low hydraulic connectivity.
• DNAPL Source Zone ISCO Pilot Test - 2003
• 9 blast fracture trenches and 327 blast/injection boreholes totaling approximately 21,400 linear feet installed to facilitate chemical oxidant injections - 2006
• 51,024 GALLONS (31,320 LBS.) OF 2.5% POTASSIUM PERMANGANATE & 10% SODIUM PERMANGANATE SOLUTION INJECTED FROM 2003 TO 2009
• 2011 RA: 43,200 GALLONS (9,151 LBS.) 2.5% POTASSIUM PERMANGANATE SOLUTION INJECTED INTO 32 INTERMEDIATE INJECTION WELLS AND 8 DEEP INJECTION WELLS – SEVERAL WELLS WERE HYDRO-FRACTURED TO FACILITATE CHEMICAL OXIDANT INJECTIONS.
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
BLASTING VIDEO
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
BLAST FRACTURE TRENCH LAYOUT
SOURCE ZONE “A”:
• 6 TRENCHES
• 2 DEEP INJECTION POINTS
• SOURCE ZONE EXCAVATION
SOURCE ZONE “B”:
• 3 TRENCHES
• 3 DEEP INJECTION POINTS
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water
REMEDIAL ACTION RESULTS
Reduction in size of groundwater plume
Reduction in average TCE concentrations by 88%
Technical Impracticability Waiver
Substantial Cost Savings