csm-2014 hydraulic fracturing and push-pull isco - pdf

32
2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water 2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water AN INTEGRATED HYDRAULIC FRACTURING AND PUSH-PULL ISCO APPROACH FOR CRYSTALLINE BEDROCK AQUIFER

Upload: omer-uppal

Post on 09-Aug-2015

33 views

Category:

Documents


0 download

TRANSCRIPT

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

AN INTEGRATED HYDRAULIC

FRACTURING AND PUSH-PULL ISCO

APPROACH FOR CRYSTALLINE

BEDROCK AQUIFER

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PRESENTATION OUTLINE

• Site Background

• Remedial Approach

• Phase I Pilot Test

• Phase II Pilot Test

• ISCO Remedy Design

• ISCO Implementation

• Conclusions

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

SITE BACKGROUND • 98 Acre Former Industrial R&D Facility

• Trichloroethene (TCE) impacts in soil and groundwater

Extent of TCE Plume (1 ppb)

Groundwater

Flow Direction

• Groundwater concentrations of TCE up to 59,000 ppb (PIW-1B, Nov 2011)

• Bulk of TCE impacts in the intermediate bedrock zone

• 155 tons of source area soil removed in 2006

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

• Unstratified Glacial Deposits

• Bedrock (Diorite)

SITE GEOLOGY

Photographer: Siim Sepp, 2005, Source: Wikipedia

Diorite fragments from well drilling

Shallow Bedrock

Intermediate Bedrock

Deep Bedrock

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

REMEDIAL APPROACH Why Permanganate?

• Bedrock matrix had low SOD (0.5 g/kg), enabling chemical oxidation to be more cost effective.

• Known to be effective for removal of chlorinated ethenes

• Relatively short remedial timeframe

• MnO4- Relatively long subsurface

half-life (months to years)

2KMnO4 + C2HCl3 2CO2 + 2MnO2 + 3Cl- + H+ + 2K+

Permanganate MnO4

- + 4H+ + 3e- → MnO2(s) + 2H2O E° = 1.70 V

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PHASE I ISCO PILOT TEST – NOVEMBER 2011

Automated Portable Bulk Feed System (Vironex)

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PILOT TEST ACTIVITIES

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

INJECTION SUMMARY • Three injection wells

• 6,081 gallons of 2.5% potassium permanganate

• 1,260 lbs. of oxidant

• Three day operation

• 97% of solution injected into the Deep Bedrock Zone (Flow rate = 5 to 22 gpm at 60 psi)

• Shallow and Intermediate Bedrock: No measureable flow at injection pressures up to 100 psi

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

RADIUS OF INFLUENCE • Deep zone ROI is at least 25 feet - Observed

pink water at MW-12C.

• Observed groundwater mounding at MW-12C, MW-16B, MW-17B and MW-12D

• 99% reduction in TCE at PIW-1C, where the majority of the solution was injected

• 62% reduction in TCE at MW-12C, the directly downgradient deep monitoring well

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

GEOCHEMICAL PARAMETERS ORP

pH

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PHASE I TESTING RESULTS

• ISCO is a feasible remedial technology for the site.

• Concentrations did not decrease significantly due to the inability to inject in the intermediate bedrock zone.

• Hydraulic fracturing needed to achieve reasonable injection rates in the intermediate bedrock zone

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PHASE II ISCO PILOT TEST – APRIL 2012 Objectives:

• Obtain injection flow-pressure relationships for full-scale remedial design

• Evaluate strategies to increase chemical distribution

• Evaluate effectiveness of hydraulic fracturing to facilitate injection in the intermediate bedrock zone

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

FIELD IMPLEMENTATION Methodology and Operation:

• Installed an additional intermediate injection well (PIW-2B)

• Hydro-fractured PIW-2B

• Injected 2,000 gallons of 2.5% KMnO4 (452 lbs.) in PIW-2B

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

HYDRAULIC FRACTURING

• Fracturing of rock by a pressurized liquid

• Increases connectivity of aquifer and well yield

• Performed at PIW-2B at 100-150 bgs, where highest TCE concentrations were observed, by Northeast Water Production, Inc.

• Direct hydraulic connection was observed, as a function of water level fluctuations, between PIW-2B and PIW-1C, following hydro-fracturing.

OVERBURDEN OVERBURDEN

WEATHERED BEDROCK WEATHERED BEDROCK

DIORITE DIORITE

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

INJECTION OBSERVATIONS • Hydraulic fracturing can achieve flow rates of up to 15

gpm at pressures less than 50 psi.

• Hydraulic influence was observed at distances up to 125 feet during injection.

• Groundwater daylighting was observed at PIW-1C.

Visual evidence of permanganate solution in PIW-1A

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

POST ISCO GROUNDWATER DATA • Oxidant distribution

at distances up to 125 feet downgradient

• Oxidant was present at several wells during the post injection sampling round

• No indication of rebound at PIW-1B

Notes:

‒ -- = Sample not collected

‒ Sampled via passive diffusion bag (PDB) samplers

‒ NJDEP GWQS for TCE = 1 ppb

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PHASE II TESTING RESULTS

• ISCO is feasible for the intermediate bedrock zone.

• Hydro-fracturing can significantly enhance oxidant injection rates and distribution in the subsurface.

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

PUMP/WELL YIELD TESTING – APRIL 2013

• Performed at seven monitoring wells to verify achievable extraction rates that can be sustained during ISCO

• Specific capacity (step-drawdown) aquifer pumping tests - Flow rates at individual wells ranged from 0.15 to 1.5 gpm

• Constant-rate aquifer pumping test - Conducted at seven wells simultaneously at 5 gpm

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

FULL-SCALE ISCO REMEDY DESIGN Remedial Strategy:

• Installation of six additional intermediate bedrock zone injection wells, one extraction well

• Hydraulic fracturing of select injection wells

• ISCO with NaMnO4

• Groundwater extraction at select monitoring wells along the downgradient site boundary while injecting oxidant “Push-Pull ISCO Approach”

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

• Total mass of 40% NaMnO4 = 61,100 lbs.

• Target NaMnO4 injection solution concentration = 10%

• Total injection volume = 27,400 gallons

• Design injection rate = 10 gpm (over 6 hours/day)

• Design extraction rate = 3 gpm (over 8 hours/day)

INJECTION & EXTRACTION STRATEGY

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

INJECTIONS & EXTRACTION WELLS

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

EQUIPMENT LAYOUT

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

FULL-SCALE IMPLEMENTATION: OCTOBER – NOVEMBER 2014

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

INJECTION ACTIVITIES…

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

INJECTION VOLUMES Date Daily Total

PIW-1A PIW-1B PIW-1C PIW-2B IW-3B IW-4B IW-5B IW-6B IW-7B IW-8B (gallons)

10/16/2014 1,000 1,000

10/17/2014 1,200 1,200

10/20/2014 400 600 200 1,200

10/21/2014 1,200 1,200

10/22/2014 803 176 221 1,200

10/23/2014 779 217 296 108 1,400

10/24/2014 60 500 109 178 181 372 1,400

10/27/2014 75 900 160 180 145 140 1,600

10/28/2014 1,000 1,000

10/29/2014 1,600 1,600

10/30/2014 1,400 1,400

10/31/2014 650 200 850

11/3/2014 1,075 125 1,200

11/4/2014 1,300 1,300

11/5/2014 50 300 650 100 1,100

11/6/2014 70 665 665 1,400

11/7/2014 66 567 567 1,200

Well Total (gallons) 321 - 1,400 2,600 2,123 2,603 1,600 5,401 2,925 2,277 21,250

Proposed Volume 700 700 1,400 2,600 1,600 2,600 1,600 5,400 5,400 5,400 6,150

Injection Well

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

ISCO PERFORMANCE SAMPLING

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

GROUNDWATER SAMPLING RESULTS

Well MW-25B-1 MW-25B-2 MW-25B-3 MW-25B-4

Sampling Depth (ft bgs) 122.5 127.5 132.5 137.5

10/1/2014 1,400 440 230 200

10/20/2014 1,400 NS NS NS

10/23/2014 1,100 390 310 270

10/30/2014 850 540 280 270

Sa

mp

lin

g

Da

te

TCE Concentrations, ug/L

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

SIMILAR APPROACH ANOTHER SITE • TCE plume occupies an area of approximately 3 million

ft2.

• Poorly connected fractures form a complex network with low hydraulic connectivity.

• DNAPL Source Zone ISCO Pilot Test - 2003

• 9 blast fracture trenches and 327 blast/injection boreholes totaling approximately 21,400 linear feet installed to facilitate chemical oxidant injections - 2006

• 51,024 GALLONS (31,320 LBS.) OF 2.5% POTASSIUM PERMANGANATE & 10% SODIUM PERMANGANATE SOLUTION INJECTED FROM 2003 TO 2009

• 2011 RA: 43,200 GALLONS (9,151 LBS.) 2.5% POTASSIUM PERMANGANATE SOLUTION INJECTED INTO 32 INTERMEDIATE INJECTION WELLS AND 8 DEEP INJECTION WELLS – SEVERAL WELLS WERE HYDRO-FRACTURED TO FACILITATE CHEMICAL OXIDANT INJECTIONS.

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

BLASTING VIDEO

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

BLAST FRACTURE TRENCH LAYOUT

SOURCE ZONE “A”:

• 6 TRENCHES

• 2 DEEP INJECTION POINTS

• SOURCE ZONE EXCAVATION

SOURCE ZONE “B”:

• 3 TRENCHES

• 3 DEEP INJECTION POINTS

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

REMEDIAL ACTION RESULTS

Reduction in size of groundwater plume

Reduction in average TCE concentrations by 88%

Technical Impracticability Waiver

Substantial Cost Savings

2014 – Contaminated Site Management (CSM-2014) Sustainable Remediation & Management of Soil, Sediment and Water

Source: Google Maps

QUESTIONS?