crisis in shrewsbury

33
Crisis in Crisis in Shrewsbury Shrewsbury Flooding impacts and risk Flooding impacts and risk management management

Upload: nicholas-carroll

Post on 01-Jan-2016

53 views

Category:

Documents


2 download

DESCRIPTION

Crisis in Shrewsbury. Flooding impacts and risk management. Responsibility and management. Under the ‘Water resources act 1991’ the Environment Agency have a duty to... ‘…protect people and resources threatened by river and sea flooding’. Dealing with high risk. Pre-disaster planning - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Crisis in Shrewsbury

Crisis in ShrewsburyCrisis in Shrewsbury

Flooding impacts and risk Flooding impacts and risk managementmanagement

Page 2: Crisis in Shrewsbury

Responsibility and Responsibility and managementmanagement

Under the ‘Water resources act 1991’ the Environment Agency have a duty to...

‘…protect people and resources threatened by river and sea flooding’.

Page 3: Crisis in Shrewsbury

Dealing with high riskDealing with high risk

Pre-disaster planning Preparation Response Recovery and

reconstruction

Page 4: Crisis in Shrewsbury

Flood alleviation in Flood alleviation in ShrewsburyShrewsbury

Flood alleviation strategies have been proposed from 1956 to the present day

1:100 floods cost an estimated £4m The NRA (now Environment Agency)

commissioned the latest study in 1993. 3 options

• Upstream storage• Channel enlargement by dredging• Hard defences (cost effective option -

£3.1m)

Page 5: Crisis in Shrewsbury

Floodwater Containment UpstreamFloodwater Containment Upstream

The River Vyrnwy doubles the River Severn discharge during flood risk periods.

Water encouraged on farmland upstream of Shrewsbury at confluence

Discharge slowed

BUT – rejected on a cost benefit analysis -

Compensation to landowners for loss of land = £18 million.

Page 6: Crisis in Shrewsbury

Channel Enlargement by DredgingChannel Enlargement by DredgingThis would:

• Deepen the river

• Increase the efficiency

Allow the channel to contain more water within its banks during periods of peak flow.

However, the channel would need to be 35 meters deep!

This would be prone to re-silting which would incur even more costs.

Page 7: Crisis in Shrewsbury

Hard defences and drainage Hard defences and drainage modification within the townmodification within the town

Defence walls at key locations in the town to hold back flood water.

One way valves included to stop water backing up and flooding out of the drains.

Cost would be £3.1 million.

This was the only option considered cost effective by the EA.

Page 8: Crisis in Shrewsbury

Planning application was made in 1993 Proposed scheme…

• Include walls, floodgates and ‘one-way’ drain valves in a two phase development…

Phase 1 - Based in Frankwell Phase 2 - Based on English Bridge

Proposal rejected - May 1996• ‘unacceptable impact on the town’s river side

character’ NRA (1996)

Hard defences...Hard defences...

Page 9: Crisis in Shrewsbury

In Oct. 1998 Shrewsbury experienced its largest flood for 30 years (1:60 yr. event)

And in Nov. 2000 Shrewsbury again was devastated by its largest flood for 50 years

(1:50-70 yr. event)

EA have acknowledged a significant increase in the frequency of floods events since 1998

(EA 2001)

And what happened...And what happened...

Page 10: Crisis in Shrewsbury

B4393 Crew Green to Llandrinio Road

Page 11: Crisis in Shrewsbury

Frankwell, Shrewsbury.

Page 12: Crisis in Shrewsbury

Frankwell Car Park, Shrewsbury.

Page 13: Crisis in Shrewsbury

English Bridge, Shrewsbury.

Page 14: Crisis in Shrewsbury

Gay Meadow Football Ground, Shrewsbury.

Page 15: Crisis in Shrewsbury

Linked to the River Severn Strategy (EA)...

...the EA have proposed the latest flood alleviation strategy for Shrewsbury.

Based on…• the work in 1993 • the latest flood protection systems • and full communication with interested parties

Renewed calls for action...Renewed calls for action...

Page 16: Crisis in Shrewsbury

What is happening?What is happening?

The EA split Shrewsbury into “Cells” – each for consideration and Cost Benefit Analysis -

Work is funded by local authorities and grants from Central Government.

Page 17: Crisis in Shrewsbury

FrankwellFrankwell

River Severn

Car park

Housing

Page 18: Crisis in Shrewsbury

Shrewsbury and Atcham Borough Council granted planning permission for Phase 1 on 4th July 2001...

Formal application made to DEFRA (Department for the Environment, Food and Rural Affairs) for funding...

Accepted - construction work started early 2003

Completed Autumn 2003

So what’s the latest?So what’s the latest?

Page 19: Crisis in Shrewsbury

Frankwell – hard defencesFrankwell – hard defencesThe scheme incorporated demountable barriers which are only deployed prior to flooding.

Page 20: Crisis in Shrewsbury

Temporary Flood DefencesTemporary Flood Defences

Two other temporary flood defences will be trialled in Shrewsbury

Mobile Dam – which consists of two tubes fitted together and filled with water to create a dam.

Page 21: Crisis in Shrewsbury

Temporary Flood DefencesTemporary Flood Defences

Pallet Barrier – which is a metal frame on which wooden pallets and plastic sheeting are placed to retain the water

Page 22: Crisis in Shrewsbury

Defences testedDefences tested

Defences were tested Defences were tested during the flooding in during the flooding in Feb 2004Feb 2004

Page 23: Crisis in Shrewsbury

Defences testedDefences tested

Page 24: Crisis in Shrewsbury

Other areas not so protectedOther areas not so protected

Page 25: Crisis in Shrewsbury

Other areas not so protectedOther areas not so protected

Page 26: Crisis in Shrewsbury

Other areas not so protectedOther areas not so protected

Page 27: Crisis in Shrewsbury

They await the success of Phase 1 Phase 2 - English Bridge area - does not

currently meet cost benefit requirements.

R. Severn Management Strategy Continued monitoring...

• R. Severn• Climate• Catchment response

Pre-planning (e.g Flood Warnings) Increase awareness (e.g. Floodline)

Continuing work by the EA...Continuing work by the EA...

Page 28: Crisis in Shrewsbury

Summary of the proposed schemesSummary of the proposed schemes

SchemeScheme CostCost EffectivenessEffectiveness Environmental Environmental ImpactImpact

ContainmentContainmentToo high at over £18 millionToo high at over £18 million Would protect area downstream, including Shrewsbury Would protect area downstream, including Shrewsbury Loss of agricultural land, but creation of new wetlandLoss of agricultural land, but creation of new wetland

DredgingDredgingToo high would require repeat dredgingToo high would require repeat dredging Would only work in channel re-dredgedWould only work in channel re-dredged Destroys aquatic habitats and river would have high Destroys aquatic habitats and river would have high

muddy banks during low dischargemuddy banks during low discharge

Hard Hard DefencesDefences

£3.1 million£3.1 million Would protect Shrewsbury with minimal impact Would protect Shrewsbury with minimal impact elsewhereelsewhere

Minimal impactMinimal impact

Page 29: Crisis in Shrewsbury

Flood defence optionsFlood defence optionsOptionOption Positive Positive NegativeNegative Cost Cost

(£million)(£million)

Do NothingDo Nothing 00

Maintenance onlyMaintenance only 0.10.1

Upstream Upstream Containment/storageContainment/storage

24.324.3

Hard DefencesHard Defences 66

Storage and hard defencesStorage and hard defences 7.97.9

Dredging and re-routing Dredging and re-routing river channelriver channel

30+30+

Page 30: Crisis in Shrewsbury
Page 31: Crisis in Shrewsbury

Why locate in high risk Why locate in high risk areas?areas?

Risk perception• Understanding based on experience• Low frequency of high magnitude events

may induce complacency

Knowledge Benefits outweigh potential costs Necessity

Page 32: Crisis in Shrewsbury

EIA for Phase 1 completed Jan 2001.• Work based in Frankwell, Shrewsbury• Objective analysis of impacts by new developments• Statutory obligation for major projects

Stages…• Problem Identified - national and local relevance • Scoping Report - sets out problems• Consultation, feedback and option evaluation• Planning application with env. action plan

EIAEIA((Environmental Impact Assessment)Environmental Impact Assessment)

Page 33: Crisis in Shrewsbury

Rejected for aesthetic Rejected for aesthetic reasons? or was it reasons? or was it something else…?something else…?

Decades of the C20th Metres above Gauge Datum. 20’s 30’s 40’s 50’s 60’s 70’s 80’s 90’s

Total

3.0-3.25 4 2 3 6 6 21 3.26-3.5 1 4 4 5 7 6 27 3.51-3.75 1 2 1 1 4 1 6 3 19 3.76-4.0 2 2 1 1 6 4.01-4.25 2 1 3 6 4.26-4.5 2 1 2 5 4.51-4.75 2 2 4 4.76-5.0 1 2 2 5 5.01-5.25 1 1 2 5.26-5.5 2 2 4 5.51-5.75 1 1

Total No. Of Floods 7 5 10 13 15 9 20 21