crb failure report (1)

Upload: rashmi-singh

Post on 05-Apr-2018

228 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/31/2019 CRB Failure Report (1)

    1/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Revision: November 2005Herman vd Merwe(Engineering Manager)

  • 7/31/2019 CRB Failure Report (1)

    2/10

    Cause of failure (generic sequence of events):

    Rationale:

    Catastrophic failure on electric motors, e.g. ID fan motor (Eskom, 11kV, 7250kW)

    Inter bar currents cause electrical arcing between core laminations and the broken bar

    Localized heating could be so severe that the bridge portion of the laminations melts away

    Close to break location, current flows through core laminations to adjacent unaffected bars

    Bar of copper type rotor cage breaks __ current continues to flow in the bar

    Lifted bar invariably starts to rub against the overhang of the stator winding

    Broken bar then lifts out of the core slot under influence of centrifugal forces

    This rub leads to an inter turn fault on the stator winding and thereby an earth fault

    Cracked rotor bar research project (2300HP 8 pole motor)

  • 7/31/2019 CRB Failure Report (1)

    3/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Cracked rotor bar lifted out of the core slot (close-up

    Findings:

    & general view)

  • 7/31/2019 CRB Failure Report (1)

    4/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Damage to stator winding overhang (close-up of failed coil

    Findings (continued 1):

    & other damaged coils)

  • 7/31/2019 CRB Failure Report (1)

    5/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Bridge of rotor laminations destroyed Overheated bridge of rotor laminations

    Findings (continued 2):

  • 7/31/2019 CRB Failure Report (1)

    6/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Electrical arcing damage on broken rotor bar (bottom of slot side)

    Findings (continued 3):

  • 7/31/2019 CRB Failure Report (1)

    7/10

    Research project, facilitated by the

    load test plant of M&C and involvingEskom and various industry anduniversity based specialists

    Cracked rotor bar research project (2300HP 8 pole motor)

  • 7/31/2019 CRB Failure Report (1)

    8/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Basic research methodology:

    Use a wide range of test techniques (existing technologies & experimental / new) and

    measuring instruments, operated by a number of test personnel from different companies

    All tests are conducted for a number of progressive test conditions ( 1.as is, 2. half abroken bar & 3. one broken bar; tests with two broken bars required?)

    Tests under load are taken at a number of different load points

    Tests under load

    Monitoring of shaft earthing brush current

    Assembled off-line tests (inductance profile)

    Disassembled off-line tests (bar continuity and growler)

    Other tests:

    Stator current spectral analyses

    Stray flux measurement

    Vibration spectral and time waveform analyses

  • 7/31/2019 CRB Failure Report (1)

    9/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    One rotor bar half broken

    Artificially introduced progressive test conditions:

    One rotor bar fully broken

  • 7/31/2019 CRB Failure Report (1)

    10/10

    Cracked rotor bar research project (2300HP 8 pole motor)

    Test results, analyses and comparison of techniques

    *** TO FOLLOW ***