cranes today april 08
TRANSCRIPT
-
7/29/2019 Cranes Today April 08
1/68April
2008:Ou
r400
thiss
ue
-
7/29/2019 Cranes Today April 08
2/68
[email protected][email protected]
KOBELCO CRANESKOBELCO CRANES
BELCO CRANES MIDDLE EAST FZEbai, U.A.E.
BELCO CRANES Co., Ltd.KYO, JAPAN: 00-81-(0)3-5789-2130x: 00-81-(0)[email protected]
BELCO CRANES MIDDLE EAST FZEbai, U.A.E. 00-971-(0)-4-881-3291
x: 00-971-(0)[email protected]
KOBELCO CRANESNORTH AMERICA INCHouston, Texas,U.S.A.Tel: 00-1-(0)-713-856-5755Fax: 00-1-(0)-713-856-9072
KOBELCO CRANESSOUTH EAST ASIA PTE. LTDSingaporeTel: 00-65-(0)-6268-1308Fax: 00-65-(0)-6268-2490
KOBELCO CRANES CO., Ltd.Shanghai Office for CHINATel: 00-86-(0)-21-5382-0120 or 0811Fax: 00-86-(0)[email protected]
KOBELCO CRANES EUROPE Ltd.FOR U.K. AND IRELAND:Tel: 00-44-(0)-1473-716-302Fax: 00-44-(0)[email protected]
WWW.KOBELCO-CRANES.COM
KOBELCO CRANES EUROPE Ltd.FOR MAINLAND EUROPE AND RUSSIA:Tel: 00-31-(0)-36-549-5510Fax: 00-31-(0)-36-549-5520
-
7/29/2019 Cranes Today April 08
3/68
-
7/29/2019 Cranes Today April 08
4/68
-
7/29/2019 Cranes Today April 08
5/68
-
7/29/2019 Cranes Today April 08
6/68
-
7/29/2019 Cranes Today April 08
7/68
-
7/29/2019 Cranes Today April 08
8/68
-
7/29/2019 Cranes Today April 08
9/68
By all meansThe new Terex Demag AC300/6
What makes this 300-tonne crane so valuable for you:
Total system length 125.7 meter (412 ft)
Superlift attachment for additional increase in lifting capacity
Fast and simple set-up of the jib and the fully automated counter-weight system
Powerful engines delivering 448 kW for the road and 205 kW for crane operation
Terex-Demag GmbH & Co. KG Zweibrcken, Germany 00 49 (0) 63 32 / 830 www.terex-demag.com info@ terex-demag.com
Ready for actionWhatever you're planning, we're there for you.
Terex Corporation 2008 Terex is a registered trademark of Terex Corporation in the United States of America and many other countries
-
7/29/2019 Cranes Today April 08
10/68
News roundup
ConExpo draws 140,000 visitors
TEREX CRANES IS GEARING UPtraining for North American
dealers. Tom Limbach, formerly
Terex Cranes lean manufacturing
manager, has been redeployed
to manage sales training for the
company's North American
distribution network.
"Doug Friesen wanted someone
with excitement, with heartfelt
belief," Limbach told Cranes Today,
referring to Terex Cranes North
America's vice president. "People
don't care what you know until
they know that you care."
The training courses draw on alot of existing information, but the
technique, style and uniformity of
the training is new, Limbach said.
He said that courses are currently
optional, although Terex is
considering making them
mandatory. All Terex distributors
are currently being trained as a
matter of priority.
Formal training programs will
be rolled out to other staby
September, Limbach said.
Regional sales training will take
place in Waverly, Iowa and
Wilmington, North Carolina.
All distributor training
programs will be attended by the
Terex regional business managerresponsible for that individual
distributor. There are currently
four regional business managers
across North America in these
newly-organised positions.
Regional business managers are
supposed to represent the face of
Terex Cranes to distributors and
their customers, and liaise
internally with product managers,
upper management, and the
trac and engineering
departments. They report to new
senior manager Dave Kuhlman.
THE TADANO STRATEGIC PLAN
scheduled to be announced in
Aprilwill last three years, until
31 March2011. It will propose a
new business domain, LE,
Lifting Equipment, president
and chief executive ocer
KoichiTadano told Cranes Today
at ConExpo.
Over the previous four-year
cycle, the company has increased
the export ratio of mobile cranes
from 30% in 2004 to 47% in its
2007 nancial year. At the same
time, the mobile crane business
has grown to 60% of Tadano's
total business in its 2007 year.
Now the company plans to
promote its truck loader cranes
and aerial work platform
businesses to balance the mobile
cranes business. "These last four
years in which we have
concentrated on globalising our
mobile cranes, we have had a
following wind from the market,"
Tadano says. "Our gures have
been getting better, but we don't
say that there has been growth,
just a following wind." Tadano
says that the company is planning
to work on specic geographical
markets, and also expand the
product range.
At theshow, Tadano's 90 US ton
capacity GT 900 truck crane carries
20,000 lbs (9t) more counterweight
than its 80 US tonolder sibling,
which was launched in 2002. The
crane also rests on a newcarrier
made at Faun in Germany.
The 35 US ton capacity Tadano
TM-35100 boom truck mounts a
new rough-terrain formed boom
on a four-axle Kenworth or
Sterling commercial chassis. It is
the company's largest boom
truck, and the manufacturer is
planning to make a 4550 US ton
machine. As exhibited, the crane
had one axle in front and three at
the back. Carrier wheels can be
modied to suit local road
regulations: a three-axle machine,
or a dual axle in front and back.
The boom comes from
Tadano's 25t rough terrain crane,
the GR-250N, a crane launched for
the Japanese export market in
2007, but not yet exported. The
crane has right-hand steering for
the Japan and Korea market; an
export version would have left-
hand steering.
Tadano is planning to launch a
few new mobile cranes later this
year to deal with new emissions
regulations in Japan.
A long, hot week in the Mohave desert translated into lots ofbusiness for crane buyers and sellers. We review the show news.
TheConExpo gold lotfrom abalcony at thenearby Hilton
-
7/29/2019 Cranes Today April 08
11/68
-
7/29/2019 Cranes Today April 08
12/68
Manitowoc: Performing near youThe 200 t (220 USt) Model 14000 joins Manitowocs celebrated line of lattice-boom crawler cranes, offering an 86 m(282 ft) main boom and 113.7 m (373 ft) luffing jib. The Model 14000 features the exclusive EPIC with Can-Buscontrol system enhancing the performance of all crane functions. Crane setup is optimized using FACT connectiontechnology to reduce assembly times.
For more information about the Manitowoc Model 14000, go to: www.mcgads.com/1181.
Manitowoc: Performing near you
-
7/29/2019 Cranes Today April 08
13/68
-
7/29/2019 Cranes Today April 08
14/68
-
7/29/2019 Cranes Today April 08
15/68
PALFINGERAG5101Bergheim/Salzburg
AustriaE-Mailinfo@palfingercom
wwwpalfinge
rcom
More shape, strength and speed:PALFINGER High Performance the best crane range of all times!With the High Performance crane range PALFINGER once again sets a new milestone. The functional
design provides an even higher level of operating comfort. The increased lifting capacity enables even
more power with roughly the same deadweight. Innovative technical details such as a maintenance free
extension boom system allow jobs to be carried out even more efficiently. Quite the best crane range
of all times just as you would expect from the market and technology leader! www.palfinger.com
Making the besteven better!
-
7/29/2019 Cranes Today April 08
16/68
Rising to new heights!
1947 Quincy Court
Glendale Heights, IL 60139
630.893.3888
Wire rope you can trust.
www.alpswirerope.com
-
7/29/2019 Cranes Today April 08
17/68
-
7/29/2019 Cranes Today April 08
18/68
-
7/29/2019 Cranes Today April 08
19/68
-
7/29/2019 Cranes Today April 08
20/68
-
7/29/2019 Cranes Today April 08
21/68
-
7/29/2019 Cranes Today April 08
22/68
-
7/29/2019 Cranes Today April 08
23/68
-
7/29/2019 Cranes Today April 08
24/68
USA
24 CRANES TODAY APRIL 2008 www.cranestodaymagazine.com
is a subsidiary of All Erection & Crane
Rental. "As a crane retailer, All Erection
has seen a decrease in inquiries for both
used and new 40-ton (36t) and lower
capacity cranes and boom trucks."
Boom truck manufacturer National is
also feeling the pinch, says David
Pengelly, Manitowoc Crane Credit
director of global trade finance. National
is owned by Manitowoc. "I can tell you
that the sale of Nationals is down, but
only to the extent that they are tied to
small commercial and residential
construction," he says.
Ray Anthony argues that rental rates
for small hydraulic truck cranes and boom
trucks are affected (but not bigger
cranes), and that as a result his rental
rates are dropping. But not everyone
agrees. Robertson at Manitex admits that
utilisation of its C-series is down, but says
that rental rates are holding their own.
Freckmann argues that he cannot
cut rental rates much, because of
pressure from the supply side. "We as a
company and an industry have had to
absorb enormous cost increases
resulting from rising steel prices and
soaring petroleum (fuel) prices. We're
dealing with the weakness of the US
dollar in overseas markets, where many
cranes are manufactured. Crane
manufacturers have been increasing
their prices in the last few years,
anywhere from 3%10% per year, and
charging even higher p ercentage
increases on crane parts."
On the positive side, the slowdown
has meant that for the first time in a few
years, customers can buy a small boomtruck and receive it very quickly.
Freckmann says that supply is starting to
outpace demand for small equipment.
The situation has filtered back through
the dealer channel to manufacturers. "For
the first time in two or three years I can
deliver a unit or two from stock," says
Manitex's Randy Robertson. "The
[delivery] lead times have gone from 10
months, in mid-2007, to 90 days now."
Impact on towersThe sub-prime mortgage collapse will
delay the introduction of self-erecting
tower cranes in the USA, argues Matthias
Donn, executive vice president of
German tower crane manufacturer
Liebherr Biberach, in an interview at
ConExpo. "The market was starting to
be willing to use self-erectors instead of
boom trucks. Now it will take more time
to convince construction companies." He
says the company will begin a new
marketing approach of roadshows and
seminars to promote the small towercranes, which are popular in Europe, to a
customer base that is largely unfamiliar
with the technology.
The situation has actually helped the
business of Linden-Comansa, according
to North America sales manager K. Matt
Dobbs, who said that fewer people
buying houses meant greater demand for
rental condominium properties, which
tend to be built by Comansa's larger top-
slewing tower cranes.
Robertson at Manitex is hopeful that
the situation will stabilise in late 2008,
and turn around in mid-2009.
Freckmann at Dawes seems less positive.
"The outlook is more of the same for the
residential construction market, with
commercial vulnerable for a while. We
understand that construction is cyclical.
Right now, demand is high for the larger
equipment, but eventually, there will be a
glut of large equipment on the market as
well. Supply and demand will equalise,
or supply could exceed demand."
All the companies interviewed said
that they were dealing with the
slowdown by building up other US crane
markets that continue to need cranes.
"We are moving more to the industrial
and bridge and road work, and some
large commercial work is still going on,"
Ray Anthony says. Freckmann says
Dawes is concentrating on infrastructure
and energy, particularly wind power,
coal-fired power plants and
ethanol/biodiesel construction.
Robertson says that Manitex is turning
partly to mining, particularly copper. He
adds that a couple of models are used
power transmission. He forecasts strong
outlook for the next several years in new
transmission infrastructure construction.
Some large crane projects are created
not by the ebb and flow of the privateconstruction market, but by government
contracts. In January 2008, the US
Association of Equipment Manufacturers
(AEM) praised a report that suggests that
the US needs to invest a minimum of
$225bn over the next 50 years to repair
the USA's highway, transit and passenger
rail systems.
A vital infrastructure is an integral
part of our daily lives at work and leisure.It is clear that we have enormous
infrastructure repair and maintenance
needs, said AEM 2008 chairman Glen
Tellock, chief executive officer of crane
manufacturer Manitowoc.
Fellow US construction equipment
and crane manufacturer Terex Corp
recently supported a conference on US
infrastructure projects. In a statement
supporting the conference, Terex
chairman Ronald DeFeo said, "Around
the world, infrastructure building is
booming, while many feel that the lack
of spending on America's aging
infrastructure is affecting our ability tocompete in the global marketplace."
Everyone in the crane industry
renters, dealers and manufacturers
would benefit if the government
decided to allocate more money to
roadbuilding. "Hopefully, after the 2008
elections, the new administration will
focus and redirect much-needed tax
revenues toward our crumbling
infrastructure, and that would be a
boon to the crane industry," says
Freckmann at Dawes.
A crunch for crane credit?It remains unclear whether buyers will
find it more difficult to find financing for
new cranes because of the credit crunch
in homebuying.
Randy Robertson at Manitex was the
most positive. "A lot of finance
companies are not offering mortgages,
and are now looking elsewhere.
Depending on what you are doing,
credit is available."
Steve Freckmann at Dawes is less
positive. "Some jobs are being cancelled
due to more stringent requirements on
financing," he says. We know that banks
are tightening up on potential equipment
buyers by introducing more stringent
requirements for credit. Buyers now have
to meet more rigorous standards than
ever before. This is seemingly a reaction
to the subprime mortgage crisis."
David Pengelly at Manitowoc admits
that crane credit might become slightly
more difficult in the future. But he says he
has not seen any evidence of that
happening in the USA. Cranes,
particularly large ones, cost a lot, so
buyers are typically sophisticated and
well-financed: the sort of customer banks
want to keep. Secondly, cranes' high
resale valuemakes them a soundinvestment, and good collateral if the
buyer defaults on the loan.
Manitex boomtruck at ConExpo
Now's not the time to go outand pour a bunch of concrete.
Work smart, and manage yourbusiness closely.Randy Robertson, sales director,Manitex
-
7/29/2019 Cranes Today April 08
25/68
:7!'%2-!. -!4%2)%%, "6-IDDENWEG !% .%$%2(/234 $%. "%2' .,
WE HAVE A CHOICE OF 120 CRAWLER CRANES
AVAILABLE FROM 50 TONS TO 250/350 TONS
WE ARE ALSO SEARCHING FOR CRANESFROM 50 TONS TO 250/350 TONS
CALL TODAYMEMBER OF THE ZWAGERMAN GROUP
Tel: +31.(0).294.25.33.77 Fax: +31.(0).294.25.27.57
E-mail: [email protected] WWW.A-BCRANES.COM THE NETHERLANDS
HITACHI
KH-230-3
Y.O.M 1989
65 TON
31 METRE BOOM
SUMITOMOSC 800-PAX S-2Y.O.M 1998-8
80 TON36 METRE BOOMPARK NO. ZW.302
Bigge Equipment Co. has UNMATCHEDAVAILABILITY on 2008 Terex Cranes
-
7/29/2019 Cranes Today April 08
26/68
Cranes Today 400th issue...
26 CRANES TODAY APRIL 2008 www.cranestodaymagazine.com
Readers' lettersOver the last few months we have asked
long-standing readers and crane people to
write in. Here is a selection.
Tom Martin, Sparrows Offshore Services,
Angola, West Africa, writes:
I have been an avid reader of Cranes
Todayfor over 25 years now, I don't
actually have an old copy of your
magazine as I pass them on to my
fellow workers in our crane department.
Over the years Cranes Todayin my eyes
has been the 'Bible' of the crane
industry and I always look forward the
latest copy. Well done with reaching
400 issues ofCranes Todayand look
forward to reading many more issues in
the future.
Steve J Barnett, Managing Director,
Manitowoc Crane Group (UK) Ltd,
Sunderland, UK, writes:
While at Neagron Plant Ltd in the 1970s
and latterly NRC in the 1980s and early
1990s, we advertised in the publication
on a very regular basis.I recall that I also wrote a few editorial
pieces in the early days and actually had
many of my photographs published
including two of my own on front cover,
one was a rebuilt NCK 6052B which we
sold and the other was a Sumitomo
heavy Duty Crane with a diaphragm wall
grab taken at Yokohama harbour.
I also remember the days of Ian
Johnston as publisher and the annual
RugbyVarsity match at Twickenham at
which the magazine hosted a fine day of
corporate hospitality. I believe that
Iattended about eight of these! Other
than that I made a goodfriend in Nick
Ratcliffe who was at one time the ad
manager. His daughter Grace is my
goddaughter.
Other memories include the famous
Cranes TodayLondon Bus, which was first
seen at the Haydock exhibition in the
late 1980s and the other major shows,
Intermat and Bauma, in the 1990s.
Ben Graham, vice president & crane
division manager, Kirby-Smith
Machinery, Oklahoma City, Oklahoma,
USA, writes:
Attached is photo of me re-living
Conexpo 1999 by reviewing issue 293,March 1999. That Conexpo was always
special to me in my crane career as at
the time I worked for the Grove and
Manitowoc dealer in Las Vegas and both
Cranes Todayand International Cranes
featured cranes that I had sold.
Im sure Im not even close to being
the longest-standing reader, but it is
always a must to read.
Several early readers wrote in with the first
issue that they read. They include:
Bill Houlker, general manager, Morrow
Equipment Co. (NZ), Petone, New
Zealand. Earliest issue: April 1973
Bev Hitchcock, Technical rep, West
Country Crane Hire, Plymouth, UK.
Earliest issue: August 1973
Dirk Knoester, Mammoet projectengineer, Schiedam, Netherlands.
Earliest issue: April 1974
Happy 400th to us!
We celebrate
more than 35
years of articles,advertisements,
opinions and lots
of new cranes in
Cranes Today
magazine
Like all good stories, the history ofCranes Today
starts in the middle of something else. Cranes
Todaywas born out of 1960s predecessor called
Cranes. First editor Chris Wilson explains Cranes
Today's early origins.
"It really started with [publisher] Morgan Grampian, when
they decided to merge Cranes with another magazine,
Muckshifter, into Construction Plant and Equipment. It had not
been all that long since they had separated the cranes content
from Muckshifterin the first place."
"I took over as editor ofCranes in May 1970, increasing
publication from six to 12 per year, and we proved that there
was a market for the magazine. When Morgan Grampian killed
it off in 1972, publisher Ian Maclaren and I went into
partnership to start Cranes Todayunder our MW
(MacLaren/Wilson) Publishers company name."
The two-man business carried on until 1984, when they sold
it to United Trade Press.
Cranes Today hasbelonged to the US
transport andrigging association
for 20 years
Reader BenGraham
-
7/29/2019 Cranes Today April 08
27/68
...November 1972 to April 2008
CRANES TODAY APRIL 2008 27www.cranestodaymagazine.com
Former staff reminsceGraham Brent, former editor
When I joined CT in 1979 we were still
printing in black and white, and setting the
type with a hot metal linotype
typesetting machine. Cranes were still
manufactured in the UK by Coles, Jones,
Thos. Smith and Jones (remember the Iron
Fairy?). That seems to date me far more
than it should! GrahamBrent is nowexecutive director of theUS National
Commissionfor the Certification of Crane Operators.
Ian Johnston, former publisher
Once, at a small gig run by French rental companies north of Paris, two
guys from French rail company SNCF asked [ad manager] Nick Ratcliffe
and me (we were known as Monsieur Cranes and Monsieur Today), in
front of a large group of French crane folks why the British did not
have high high-speed trains like theirs. We replied, in French, "Because
French tourists like to look at our pretty countryside." They didn't think
it was that funny and chalked it up to the English sense of humour.
Many great memories.
David Taylor, former editor
Our offices were in Bowling Green Lane, EC1. It was a dump. We wrote on
manual typewriters and the studio on the top floor pasted everything
onto layout sheets. On the other hand, with CT I travelled the world.
About a year after I joined, United Trade Press (the publisher) was
bought by Robert Maxwell and became Maxwell Business
Communications. I met Maxwell in 1987 just before he bought the
company. He'd just bought British International Helicopters and we
had run a feature on aerial lifting the previous year. Maxwell decided
to turn up and we were lined up to shake his paw. At the press
conference later, I was impressed to see that he'd memorised everysingle journalist's name.
Tim Whiteman, former editor
I joined a week before we moved offices to
Dartford, in Kent, a site owned by Maxwell.
But then Maxwell disappeared in
November 1991, and the business was in
turmoil. Out of frustration in the situation
- our foreign travel budget was frozen,
there was no work done on the circulation
- I tried to do a management buy-out of
some of the titles. But the receivers did not want to sell two or three
titles. At that point I had done the calculations, and knew how much
money the magazine was making. I left Cranes Today and joined some
others to launch International Cranes. I wish Cranes Today every
success- it is a great old magazine. TimWhiteman is now themanaging
director of the International PoweredAccess Federation (IPAF).
Mark Aldwinkle, former editor
The sad news in mid-March of a crane collapse in New York reinforces
the message that all those articles that Cranes Today and others sought
to carry over in my time as editor (1992-7) - 'safety begins with you'.
That slogan has been around for many years, of course, but it struck me
with particular resonance during ConExpo 1993 when I was touring
some of the nearby Las Vegas crane hire companies.
Phil Bishop, former editor
Compared to the generally uptight and
cautious civil engineers whose universe I
had specialised in previously, I was happy
to find crane people to be open, warm and
helpful. I saw some amazing machines,
with Van Seumeren's PTC a stand out, and
remarkable projects, including the clear-up
of Ground Zero in September 2001, whichwill always be a vivid memory.
Ian MacLaren, 19182005
Ian MacLaren, who founded Cranes Today in 1972, was a fighter
pilot with Britains Royal Air Force (RAF) throughout World War
II. He served above many of the campaigns overseas and at
home flying mainly Spitfires and Hurricanes and, later on,
Tempests. He used to say the Spitfire was a most forgiving
plane to fly. Late in the war, when the Doodlebug pilotless
bombs threatened England, Ians squadron tried to stop themby tipping their wings underneath the bombs to make them
dive harmlessly into the sea.
After the war, MacLaren, still in the RAF, joined Transport
Command flying cargo and passenger planes on the long routes
to Australia and the Far and Middle East. In 1955 he was awarded
the Queens Commendation for Valuable Service in the Air. A
year later, Ian flew jets as a test pilot until he retired in 1963.
In civilian life, MacLaren aspired to financial journalism but
found it difficult at age 45 to get much of a foothold. However,
he joined the London City Press newspaper where he
interviewed various industrialists and city directors and wrote
articles for the features editor.
Shortly after joining the trade journal Cranes, the publishing
group Morgan Grampian decided to merge it into another
magazine. Ian thought this a mistake and, after speaking tosome of the crane manufacturers, decided to publish it himself.
Hence, in 1972, Cranes Today was born in a tiny two-room
office in Edgeware, North London.
During his 12 years at Cranes Today, the magazine evolved
from a domestic black-and-white publication printed using the
hot metal process, to a colorful international magazine.
In 1993, Ian moved permanently to Suffolk, where he played
golf most days until ill health overtook him in 2004. He died in
August 2005 aged 87, leaving wife Peggy and son Robert.
Cranes Today founders IanMacLaren, left, and Chris
Wilson, in their prime
Graham Brent TimWhiteman
Phil Bishop
The current CranesToday team. Left toright: Kirsty Guest,Will Dalrymple,Mark Bridger, WillNorth and MartinMcCarthy. Missing:Kate Hearn
-
7/29/2019 Cranes Today April 08
28/68
Experience the Progress with Liebherr:The LTM mobile cranes are convincing
by their manoeuvrability, performanceand safety. Advanced Technologies areour Business.
Liebherr-Werk Ehingen GmbHP.O. Box 1361, D-89582 Ehingen
Tel.: +49 7391 502-0Fax: +49 7391 502-3399
www.liebherr.com
-
7/29/2019 Cranes Today April 08
29/68
-
7/29/2019 Cranes Today April 08
30/68
-
7/29/2019 Cranes Today April 08
31/68CRANES TODAY APRIL 2008 31www.cranestodaymagazine.com
Mitsubishi Heavy Industries (MHI) and
Tanenaka Corp had a turnkey contract to
execute its construction. Also included
were Kisho Kurokawa Architects &
Associates,Tokyo, DP Architects Pte Ltd
Singapore,and Rider Levett Bucknall
project management.
Horizontal construction takes gravity
out of the equation, and thus pre-stresses
are equal during assembly. But vertical
construction means gravity-loads act
within theplaneof thewheel causing
tension to vary at different positions in
thecables, making the sequence of cable
stressing much more complicated.
If you have ever tried to tighten the
buckle out of a bicycle wheel rim as a kid
by adjusting the spokes you will know
what I mean,said McNiven.
To find a solution,McNiven at Arup
and Akihiko Nozaka,project manager,
and Kei Itou, structural design manager,
at MHI oversaw a handful of engineers
and designers scattered across offices in
three continents testing dozens of
methods of erection in a virtual CAD
computer environment,analysing the
forces at every stage of construction.
MHI conducted wind tunnel tests at its
labs in Nagasaki.
Eventually, in October 2006, three
years after theSingapore Flyer was a
sketch on an architects pad,and one year
after the groundbreaking on September27, 2005, the time had come for MHI and
Tanekana to build the support structure
Singapore flyer
Ferris wheels keep gettingbigger. The London Eye was
135m tall; the Singapore Flyer
is 165m; the Beijing wheel will
be 208m.
Brendon McNiven, associate director
of construction contractor and engineer
Arup, said that big wheels may get bigger
yet. "The upper limit for these things
comes when the limits of financing are
reached, not the limits of engineering.
You will have noticed a lot of these
projects are around but only a few make
it throughmainly as they are harder to
finance than a typical building. Whereas
office rentals and returns are well known,
the guaranteed number of visitors to a
wheel is not.
Two memorable flops are the 182m
Voyager intended for Las Vegas, Nevada
and the 200m Shanghai Star proposed
for the city of Shanghai, China.
Says McNiven, The main limit is in the
size of the bearings, but everywhere you
come up against limits: requirements that
might not be available off the shelf or
loads that might be too large. Usually an
innovative engineering solution can be
developed.
Arup had to find just such a solution
for the Singapore Flyer. Its 138m rim
stands above a three-storey terminal
building. While Londons 122m Eye could
be fabricated floating on the Thames and
then be pulled upright, the lack of space
on the Singapore site made this
impossible: It had to be built vertically
between two supporting columns.
McNiven recalled doubts expressed
about vertical construction. Early on the
client was approached by quite reputable
engineers saying the erection could not
be done vertically, he said.
MHI and Arup knew differently from
doing the numbers.Arup was involved with the Singapore
Flyer project from its conception, while
and assemble the wheel.
Bulldozers had reformed the
grounds, and the tricorne-
shaped terminal building was a
bare framework of steel girders.
Inside its three-storey
perimeter, open on one side to
allow entry by heavy
machinery, was the platform
that would withstand the
2,200t of the wheel, supporting
columns, cables and capsules.
Beneath it, 38 piles of 1.5m
diameter had been bored to
50m, and steel-cased through
the top 10 meters. Two clusters
of nine piles underlay the
positions where the wheels
two support columns would
stand. Four groups of five piles
sat beneath the four spots
where the cable stays anchors
would sit.
When erected, the Singapore
Flyers two support columns
would measure 85m high, 2.8m
in diameter and weigh a total of
550t. Fabricated offsite, they
were delivered in six sections,
including their end caps.
Since the London Eye was erected in 2000,large, modern, Ferris wheels have captured
the imagination of city planners. Glenn Smith
reports on three recent wheels in China and
Singapore; On page 35, Greg Keane reports
on another in Melbourne.
Alternative lifting
1
2
3
4
5
6
Both sides of Singapore Flyer support columns were built in stagesfrom the ground up, with temporary supports (in orange). Once the
column heads were lifted (Fig 4), a jacking system raised the 180t hub
and spindle in a single 12-hour lift (not shown). Rim sections werefitted in between two temporary spokes, hooked with cables, and
then rotated out of the way. Cars were added one by one at the end.
-
7/29/2019 Cranes Today April 08
32/68
During assembly,the lead machine
was a 600t Demag CC 2800 crawler with a
112m boom. In its shadow, MHI crewsbuilt a temporary structure resembling a
sawhorse,its spine a horizontal strut
spanning the distance between the not
yet erected column bases. Next,the crane
lifted the basal sections into place, first
one then the other,so workers could bolt
them to the foundation, and butt their
tops to the temporary horizontal strut.
Then the second sections were
positioned,spliced to the section below
and braced with another temporary
strut.
This procedure was repeated,
sometimes without the struts, until the
lower five sections of the two support
columns were fully assembled, on
October 27. Two weeks later, on
November 8,the crane lifted the end
caps into place. The next phase of
construction,the lifting of the hub and
spindle, began with the fastening of a
temporary gantry across the end caps.
Months earlier, MHI in Japan had
fabricated the spindle and hub for the
Flyer. With a length of 25m and
weighing 180t,it was unwieldy. From
the docks of Singapore, it was loaded
onto a 120-wheel trailer,and hauled
along a carefully considered route. The
spindle is believed to be the biggest load
ever carried through Singapore.
Lifting the spindle 85m to the top of
the Singapore Flyers two support
columns was not possible by crane.
Instead,MHI mounted two 200t strand
jacks at flanking positions on the
temporary gantry. Early on the morning
of December 13 they began hoisting the
assembly upwards. By evening, the task
was finished,and the assembly was
bolted to the columns end caps. In the
following days,MHI secured the
structure with four groups of six 100mm
locked coil cable stays, lashing the endcaps to the four anchors located beyond
the perimeter of the terminal building,
www.cranestodaymagazine.com32 CRANES TODAY APRIL 2008
Alternative lifting
balancing the forces horizontally at
ground level through the floor of the
building. The Singapore Flyerssupporting structure was complete.
Next MHI tackled the construction of
the wheels rim, that was fabricated in
Malaysia from steel pipe,25.4mm thick
and 864mm in diameter. The complete
rim would be formed out of 28 sections,
weighing 30t each.
The engineers used temporary struts
to divide the wheel into seven equal pie
slices. Only one of these would be
constructed at a time. The method
required building two temporary struts
extending from the hub to the rim
perimeter. Each strut was made of four
lengths, winched into position and
fastened with high-tension bolts. When
two struts were ready, four rim sections
would be attached between them, and
radial cables (the spokes of the wheel)
installed in a slack condition. This
finished pie slice was strengthened with
a lightweight steel chord forming a
bowstring truss around the wheels
perimeter. Fully stabilised, the pie slice
would be rotated out of the way so that
another strut could be added and work
on the rim continued.
MHI worked on the rim and its spokes
from January 2007 to mid-July. The crew
then removed the struts and stressed the
cables in two stages to avoid
overloading the rim.
With the wheel itself complete, a 160t
mobile crane lifted the 10t passenger
capsules one by one to a support
platform erected on top of the terminal
building. A drive unit on an eye deck
near the base of the wheels supporting
columns rotated the wheel into position,
enabling workers to attach the capsules.
By the end of October all that
remained was to run some tests and
prepare the grounds for opening day in
February. On a clear day, visitors will beable to see the borders of Malaysia
and Indonesia 45km away.
Two Chinese wheelsIn 2006, China completed The Star
of Nanchang, which at 160 meters
high cut short the 135-meter
London Eyes tenure as worlds
tallest. But it is a traditional,
compression-braced Ferris wheel
built in themiddle of nowhere.
Nanchang was sleepy backwater
until Ford built an automobile
factory in 1995.The city got rich
overnight and the city fathers
commissioned the project,perhaps
in a fit of civic pride.
In November 2007,construction
crews in Beijing broke groundon
the 208m bicycle-shape Great
Beijing Wheel,now scheduled to
open in 2009. The builder is the
Shanghai Construction (Group)
General Company. Several foreign
veterans of London Eye worked on
the project,including the Dutch
engineers IV Bouw, Poma of France
(observation capsules), and BoschRexroth (hydraulic drives).
The old-fashionedstarof Nanchang
The high-techGreat Beijing
Wheel
-
7/29/2019 Cranes Today April 08
33/68
IKUSI - ngel Iglesias S.A.Tel.: +34 943 44 88 00 [email protected]
TM70 & I-syon fullRadio Remote RangeRadio Remote Control Systems Solutions for:Construction, Tower Cranes & Concrete Pumps
-
7/29/2019 Cranes Today April 08
34/68
ZHSLZ'VPSJVU[YVSJVT r ;LS r -H_
)VZJO 9L_YV[O 6PS *VU[YVS :W(
www.oilcontrol.com
We make what we sell. Only in this way can we live up to the high quality standards
our customers have come to expect and which are also deeply engrained in the
way we have come to see ourselves, as a company that looks back on more than 30
years of history. But also as a subsidiary of Bosch Rexroth AG, which makes us part
of a globally operating technology group which has been successfully in business
for more than 200 years. This is our drive and commitment. Unique. Like Bosch
Rexroth. ;OL +YP]L *VU[YVS *VTWHU`
>L HJ[\HSS`manufacture.
What others
Q\Z[ I\
Hydraulic components and systems for mobile
and industrial applications.
Visit us at
*,4(; /HUUV]LY 4HYJO /HSS :[HUK )
-
7/29/2019 Cranes Today April 08
35/68
-
7/29/2019 Cranes Today April 08
36/68
Alternative lifting
36 CRANES TODAY APRIL 2008 www.cranestodaymagazine.com
Terex-Demag raising the upper end and
the Sumitomo walking the base into
position, where it was connected to the
foundations. The leg was then held in
place using temporary supports.
The last legsThe remaining two legs were erected ina similar manner, although this was
complicated by a drain running through
the work area. The Sumitomo walked the
base of each leg to the edge of the drain,
where it was unhitched from the load
and walked around the drain. It then
picked up the leg again, and walked it to
the foundations. These legs were also
secured in place by temporary props
until the capital was placed.
The second tripod was erected in a
similar manner, but because the radius
was reduced 32.5m, the Superlift
counterweight of the Terex-Demag was
reduced to 100t.The next stage was to pre-assemble the
25m diameter, 8m deep inner hub that
weighing 152t. It wasbuilt on a temporary
assembly stand14m above the ground,
and liftedfrom there to a height of67m,
where it was mounted in bearings on the
capitals.This took 5 hours, and theTerex-
Demagcrane was at 99% capacity for the
lift.The biggest concern was thewind
(gusts of140 km/h had been recordedat a
similar time during theprevious year), and
with the 490m2surface area of thehub,
the safewind speed for the lift was
calculated at 19 km/h.
The final lifts on this project for the
CC2800-1 were the seven triangular
lattice construction spokes, each 33m
long, 10.2m wide at the base, 8m deep
and weighing 24.5t.
The first four spokes were installed at
the three oclock position, and the boom
was then reconfigured from 96m to
114m length for the final three spokes,
which were installed at the one oclock
position. The wheel was rotated
between lifts, so that the lifts were
undertaken at the same orientation.
The first two spokes were installed as
dual lifts using the Terex-Demag and
Sumitomo crawler cranes, and all other
lifts were undertaken with the Terex-
Demag alone, with the Sumitomo
supporting a man basket for the riggers
connecting the spokes to the hub.
Soft slings were attached to the main
chords at the top of each spoke at 4
points, and chain blocks were connected
in two locations at one end, allowing
fine adjustment of the angle of the
spokes to assist with the connection.
Each spoke took six hours to install.
Once all seven spokes were installed,
small sections of the outer rim were
installed to each of the spokes.These rimsections were 12m long and weighed 12t,
and were installed using Alfasis 150t
Sumitomo SCX 1500-2 crawler crane, with
its 70t Tadano GR-700EX used for man
box access. These sections were installed
at the four oclock or eight oclock
position, with the wheel rotated between
lifts using hydraulic winches.
The outer rim was built in sections on
the ground, with each section joining apair of spokes. The sections were
approximately 30m long and 6.5m wide,
and weighed 32t. When each section
was constructed it was walked into
position for the lift, using the Tadano GR-
700EX and two 20t Franna articulated
pick-and-carry cranes.
A 200t all terrain crane was hired in
as the main crane for these lifts, with
the GR-700EX acting as a tailing crane
and Alfasis 55t Tadano GT-550EX truck
crane supporting a man box for the
riggers to connect the rim section. Each
section was installed in the seven
oclockeight oclock position. TheSCX1500-2 was used to tension the top
spoke, which sagged when not
connected to the outer rim, and 17t of
force was required to correct the sag.
The boom of the 200t crane was
positioned under the spoke above for
the rim section lifts, with only 0.5m
clearance between the boom head and
the spoke steelwork.
The wheel was rotated between lifts
with the hydraulic winches so that all
outer rim segments were erected in the
same position. Each lift took 56 hours.
The main work remaining is to attach
hangers to the outer rim to support the
21 observation cabins, and to attach the
cabins (each weighing 14t). The cabins
will be lifted onto a raised slab that
forms part of the permanent works,
skated into position and jacked up for
attachment to the hangers.
The first four spokes
were installed at threeo'clock; the final four at
one o'clock
The Terex-Demagcrawler was at 99%capacity lifting the
152t hub
Two cranes tandemlifted the rim; a finalraised the saggingspoke above
-
7/29/2019 Cranes Today April 08
37/68
www.parts-supply.nl
NEW PARTS
USED PARTS
REFURBISHED PARTS
YourpartnerforChinese equipmentparts
DEALER FOR CRANE AND HEAVY DUTY EQUIPMENT PARTS
RS/MAINTENANCE PARTS
BRAKE PARTS
ENGINES AND PARTS
GEARBOXES AND PARTS
TRANSFER CASES
YDRAULIC COMPONENTS
HYDRAULIC CYLINDERS
ELECTRIC COMPONENTS
TELESCOPIC BOOMS
BOOM EXTENSIONS
HOOK BLOCKS
COUNTERWEIGHTS
ROPES
AXLE PARTS
CABINS
LUBRICANTS
ATTACHMENTS
SLEWING RINGS
BALL JOINTS
CRAWLER PARTS
TYRES
European headquarters:
Parts Supply Worldwide B.V.,Steenovenweg 2 A,3417 XR Montfoort,The Netherlands.
T 0031 (0)348 46 85 05 F 0031 (0)348 46 85 36 [email protected] www.parts-supply.nl
Parts Supply Worldwide Branch Oce Far East:
T 00-86-769-8509-6620 F 00-86-769-8509-6621 [email protected]
Your specialist for Chinese equipment partsXCMG mobile crane parts Zoomlion mobile crane parts
PAT safe load indicators (China make)
Steyr engine parts
Bosch Rexroth hydraulics (China make)
Your specialist for parts of European crane brandsReconditioned engines, gearboxes and slewing rings from stock
Over 30 cranes for dismantling: Demag, Liebherr and Grove/Krupp
Stock of many dierent reconditioned exchange components also with guarantee
Genuine quality and reliable delivery for new parts of European crane brands
Small things that make us greatWe carry large stock of parts in our warehouses based in Montfoort and
Moerdijk in The Netherlands and Guangzhou, China
Availability of an extended database with documentation of technical
parts and (Chinese) component manufacturers
High service level from our well trained sta. We know your business!
Quick response: we reply to inquiries (usually) within 24 hoursDedicated East branch oce in Guangzhou, China
-
7/29/2019 Cranes Today April 08
38/68
-
7/29/2019 Cranes Today April 08
39/68
Vanguard holds its beer
Alternative lifting
CRANES TODAY APRIL 2008 39www.cranestodaymagazine.com
Vanguard holds its beer
Having set up the system, the tanks
were then brought onto the site one at
a time on low bed trucks,lying on their
sides.A small mobile crane was used to
stabilise the bottom end of the tank
while the top was attached via a hook
to the portal crane system.
The tank was th en lif ted
incrementally to move it into a vertical
position. Once vertical the system
rolled on the rails to position the tank
above its respective base.
Boshoff notes that in addition to the
space limitations that restricted
movement, it was also a challenge to
complete the portal crane assembly in
such a small area.Moreover, we had to
deal with some heavy winds, but overall
we relied on our experience, skilled staff
and project engineers from our
Mombasa (Kenya) and Johannesburgoffices,and the job was completed
successfully.
T
he eight 8t tanks measure 21m
by 5.2m,and needed to be
installed in two rows of four in
a tight industrial site, with only
50mm clearance in some
places. Vanguard rigging and installation
manager, Wynand Boshoff,says,The
installation of the tanks was challenging:
The main issue was the lack of space
surrounding the stands on which the
tanks needed to be positioned. For this
reason traditional cranes were not
considered. We developed a new solution
for the lift by designing and supplying a
portal crane that spanned the foundation
with a hook height of 25m.
This new portal crane system was
designed and constructed in
Johannesburg, packed into containers
and shipped to Tanzania, says Boshoff.
On site, the system took two weeks toassemble, and was then lifted onto rails
on top of the platform using a crane.
One of the tanks islifted into a vertical
position by thegantry, with atailing mobile crane.
South African transport andinstallation specialist Vanguard used
a tailor-made gantry system to lift
eight tanks into place at a Tanzanian
brewery. Will North reports
-
7/29/2019 Cranes Today April 08
40/68
-
7/29/2019 Cranes Today April 08
41/68
-
7/29/2019 Cranes Today April 08
42/68
+,*+
3(5)250$1&(
:,5( 523(6
7@;/65 PZ H ^VYSK^PKL Z`UVU`T MVY OPNO X\HSP[` Z[LLS ^PYL YVWLZ 7YVK\JPUN Z[HUKHYK HUK /PNO 7LYMVYTHUJL >PYLVWLZ Z UJL V\Y WYV \J[ WVY[ V V JVU[H UZ \[ Z UV[ T [L [V YVWLZ VY!
/HYIV\Y ZOPW HUK OLH]` SVHK JYHULZ 4VIPSL HUK JVU[HPULY JYHULZ ;V^LY JYHULZ ;Y\JR JVUZ[Y\J[PVU JYHULZ HUK JYH^SLYZ 4PUPUN Z\YMHJL TPUPUN HUK KLLW MV\UKH[PVU 6MMZOVYL \ZHNL
L UN H L [V THU\ HJ[\YL YVWLZ ^ [ HTL[LYZ \W [V TT [ [VUZ TH_ T\T ^LN [ WLY W LJL TH LZ \Z VUL V
[OL SLHKPUN ^PYL YVWL WYVK\JLYZ ^VYSK^PKL
>P[O ULHYS` [VUZ VM Z[VJR ^L ZLY]L HSTVZ[ L]LY` KLTHUK VU H ZOVY[ [LYT IHZPZ ^VYSK^PKL
+YHO[ZLPS^LYR +VY[T\UKLPSLYZ[Y
+ +VY[T\UK;LS! -H_ ,4HPS! KVY[T\UK'^KPW [OVUKL
+YHO[ZLPS^LYR :`RL(T 9PZ[LK[LY >LN + :`RL;LS! -H_
,4HPS! Z`RL'^KPW`[OVUKL
:;(053,:: :;,,3 >09, 967,:
>,:;-f30:*/, +9(/;05+,9 *OVVZL `V\YZ
^^^^KPW`[OVUKL70) 9LZ[ [O :[YLL[,HZ[ /HaLSJYLZ[,/
-
7/29/2019 Cranes Today April 08
43/68CRANES TODAY APRIL 2008 43www.cranestodaymagazine.com
than the working load of the item.
When this happens, the equipment is
certainly being misused; unfortunately,
even the best-trained and most
conscientious rigger can, and
occasionally will, make such mistakes.
It is part of what makes us human and
should be recognised as such. In the
worst case it can lead to immediate
failure. More often, if the equipment is
in good condition, it results in damage
to the equipment, not failure. The
rigging gear might prevent an accident,
but the damage, if undetected, can lead
to premature failure when the rigging
gear is subsequently used. With the
proper facilities and procedures in
place, the effects of such errors
can be minimised.
The facilities and procedures
required are relatively simple.
Essentially they are storage, control and
inspection. The storage must protect
the equipment from the elements and
accidental damage, prevent
unauthorised access and provide a
means of segregating or quarantining
unserviceable equipment.
The control must keep track of whom
the equipment has been issued to.
Furthermore, if appropriate, it shouldcover who authorised it, where
equipment is to be used and for how
long, and record when it is returned to
store and whether it is serviceable. The
system must also keep track of when
equipment is due for maintenance and
its periodic inspection.
At least two levels of inspection are
necessary. Many countries have
legislation requiring a periodic
inspection and a formal record of the
result. However, even if this is not the
case, it is good practice to do so and it
provides useful information for the
management of the organisation. The
periodic inspection is normally done at
six monthly intervals. If this inspection is
finding equipment that is already in an
unserviceable condition, then there is
something wrong with the day-to-day
in-service inspection regime.
Because rigging gear is vulnerable to
accidental damage every time it is used,
it should effectively be inspected every
time it is used. This is much less onerous
than it sounds. A trained rigger should
be able to look after thetools of the
trade. Without wishing to understate
the importance of inspection, most
general purpose rigging gear is not
complex and can be adequately
inspected by someone with a few days
training. With practice, riggers should be
able to run their eyes over the
equipment as it is being handled.
These then are the essential
components of a rigging storage and
control facility. Depending upon the
amount of equipment involved, the
facility can range from a permanent
building complete with staff to alockable box. The basic principles
remain the same.
A place for everythingDerrick Bailes, chief executive of theLifting
Equipment Engineers Association, explains why, and
how, awell-designed rigging store canmake lifting
operations safer, regardless of the size of the business
No matter what type of crane
is used, virtually every lifting
operation requires
additional equipment to
connect the load to the
crane. The terminology used around the
world for such equipment varies, but for
the sake of simplicity I shall use the
general term of rigging gear.
One only has to consider the
consequences of sudden equipment
failure to appreciate that the suitability
and condition of rigging gear are of vital
importance to the overall safety of lifting
operations. Not only will the load drop,
but the recoil could damage the crane.
On a counterbalanced crane, this might
result in overturning or collapse, clearly a
situation to be avoided. However, given
the way that some organisations treat
rigging gear, it is clear that many are still
failing to recognise the potential
dangers. All too often equipment is
poorly stored, left exposed to the
elements and rarely inspected.
As well as damage arising from poor
storage, rigging gear is also generally
vulnerable to accidental damage in use.
Errors in the geometry of the rigging,
sharp edges and dynamic or shock
loading can all overload or permanentlydamage rigging gear even though the
weight of the load being lifted is less
Rigging
Lifting Engineers,www.leea.co.uk,accredits liftinggear testers andvendors worldwide.It also publishes The
Code of Practice forthe Safe Use ofLifting Equipment.
-
7/29/2019 Cranes Today April 08
44/68
-
7/29/2019 Cranes Today April 08
45/68
www.effer.it - [email protected]
HEAD OFFICESOL.GE. S.p.A.40013 CASTEL MAGGIORE (BO) ITALYVia Bonazzi, 12/14Tel. +39 051 41 81 211Fax +39 051 70 14 92
THE POWER OF PERFORMANCE
Conditioned to maximum performance40 years ago we launched a challenge to gravity,on land and on sea.A challenge that every day our cranes win, lifting tonnes
of goods around the world.A challenge that we win, thanks to the technology,power and performances of our innovative range of models.
EXAGGERATION!
www.inprima.i
t
Come to see us at:
SMOPYC - Zaragoza (SPAIN)22-26 April - Stand D/E 43-44
SED - Corby - Rockingham (UK)13-15 May - Stand 241 Avenue Q
TRANSMISSION TECHNOLOGYPlanetary gears as component system for lifting, towing and
free-fall winches and slewing gears. Made to customersspecification as well as in series. Torques from 1 to 1000 kNm,ratios from 13 to 1000.
Plant Herbertingen
ZOLLERN GmbH & Co. KG
Transmission Technology - Gears and WinchesHeustrae 1 D-88518 Herbert ingenPhone +49 7586 959-566Telefax +49 7586 [email protected]
www.zollern.com
Further branches: Casting Technology Phone +49 7571 70-440Steel Profiles Phone +49 7571 70-246Mech. Engineering Components Phone +49 7525 948-130Plain Bearing Technology Phone +49 531 2605-0
www.r
evoLUZion.d
e
Tall
on Power
Small
in Size
Tall
on Power
Small
in Size
G E T S T H I N G S M O V I N G !
Y E A R S
-
7/29/2019 Cranes Today April 08
46/68
Technical Specialist
Competitive Salary +Benefits
ZF Great Britain Ltd is part of a worldwide organisation recognised as a market leader in the automotive industry. We are a remanufacturingsales and service organisation, looking to recruit a Technical Specialist within the Off Highway Division.
The successful candidate will be required to provide technical and diagnostic support for OH products at all levels, including OEMs, importersand operators of ZF equipment. In addition, the candidate will be required to promote ZFGB service capabilities at every opportunity whenon site and while customer facing. The candidate will also provide feedback to the parent factories and internal departments within ZFGB byproducing and circulating Technical Visit Reports.
Ideally candidates for the position will have completed apprentice training with a mechanical bias, prior ZF product knowledge (both theoreticaland practical) would also be advantageous, combined with proven OH product related diagnostic experience. In addition, the role requiresknowledge of mechanical, pneumatic, electric and hydraulic systems across the Off Highway product range.
Excellent communication skills, computer literacy and the ability to present findings, are essential skills needed to fulfil the positionrequirements. Experience in dealing with customers and the ability to train others will also be an advantage.
If you think this position would suit you, please contact Paula Saunders, HR Manager, for further information. Candidates must be flexibleand be prepared to work unsociable hours when required. All applications must be made in writing and sent with an up-to-date CV.
ZF Great Britain LtdAbbeyfield RoadLentonNottinghamNG7 2SXTel: 0115 986 9211
Email: [email protected]
Deadline for applications: 14 April 2008
ZF Great Britain Ltd is an equal opportunities employer.
Driveline & Chassis Technology
a newgeneration
mobile cranes
For information0031 - 412 - 62 69 64
www.spieringscranes.comor call your crane hire company
Spierings folding crane, the best solution
-
7/29/2019 Cranes Today April 08
47/68CRANES TODAY APRIL 2008 47www.cranestodaymagazine.com
chemical environments. The range of
equipment used, and the long journeys
much of it went on, made this difficult.
Back in 1996, Sutton had been
appointed recently as rigging manager,
but was stuck at home with a broken
leg. Rather than leaving him with
nothing to do, Airbus set him the task of
devising a system to track the firms
rigging equipment. He worked closely
with the plant's insurance inspectors,
Bureau Veritas.
The basis of the system is that each
item of equipment is tracked, all the way
from the manufacturer. Airbus only
works with suppliers who can provide
equipment marked with a part numberthat fits Airbus' in-house tracking system.
Each piece of equipment carries a tag
with a year and unit number.
Airbus Filton's procurement staff are
trained to recognise lifting equipment
when it appears on an order. When it
does, it is flagged up by them and
marked for quarantine, so it can only be
accepted on to the site by the rigging
management team, or insurance
inspectors. When new equipment
comes on site, it is inspected, and a
record of the inspection kept. Inspection
logs, manuals, and any other
documentation, are scanned and stored
on a secure server, so that the history of
any piece of equipment can be called up
at the click of a mouse.
While this part of Sutton's systemensures that the equipment is all
identified and trackable, it doesn't
Colour codedAirbus Filton uses 10,000 separate items of loose equipment, many of which
leave the site for long periods. Rigging manager Jason Sutton faced a challenge
to make sure all of this equipment can be properly tracked. Will North reports
Airbus builds planes across
Europe. At Filton, in south
west England, it makes
leading and trailing edges
for wings, and the wing
boxes that fit them to the planes
fuselage, as well as a wide range of other
parts. The wings are lifted and turned as
they are built, using customised
spreader beams, vacuum pads, and a
range of slings and chains.
Wing sections are sent to Seville, in
Spain, for assembly, and working parties
from Filton often visit the Spanish plant.
When they do, the rigging equipment
they use can travel with them. Airbus
wanted to ensure that all loose liftingequipment was inspected every six
months, or more where it worked in
A rigging store andorange dump bin,with colour codechart, at AirbussFilton plant.
Rigging
-
7/29/2019 Cranes Today April 08
48/6848 CRANES TODAY APRIL 2008 www.cranestodaymagazine.com
provide an easy way for lifting staff to see
if the equipment is due for inspection.
Sutton realised that a colour coded
system of tags would ensure that items'
inspection dates could be clearly marked.
Under his initial scheme, a four
colour system was used, with a
different coloured tag for each three
month period. This was simple, and
made it easy to see when the
equipment was past its inspection due
date. On a site where equipment never
travelled out of the system, this would
work well. However, in Airbus, working
parties from Filton often travel to
plants across Europe, taking equipment
with them. Often, they would be away
long enough that when they returned
their equipment appeared to be
carrying the correct tag for safe use,
when it was in fact a long way past its
inspection due date.
A new system needed to be
developed. Sutton and Bureau Veritas
developed a 12 colour system instead.
Cable ties were used, with the year the
equipment would be due inspection
marked on the tie. A second tag, on the
tie, carries the inspection month, both
in writing, and in a colour code. Under
this system, it's impossible for
equipment to be incorrectly identifiedas safe to use. This system has now
been rolled out to other sites inspected
by Bureau Veritas, including aircraft
engine makers Rolls Royce.
The plant's working practices and
physical layout support the system.
Around the plant, specially designed
stands hold the equipment that staff will
need. Each stand is marked with the
safe working load for the equipment it
carries. Most of the stands are partnered
by bright orange 'non-retrieve' cages.
The cages have a hole in the top, for staff
to deposit equipment if it loses its tag, or
if it is damaged. The equipment inside
cannot be reached from the top, but
only from a locked door at the bottom of
the cage. Only the rigging management
team and the insurance inspectors have
a key to this door.
The rigging management team and
inspectors regularly empty the bins. If
equipment has just lost a tag, it can be
identified by its part number, and the
correct tag replaced. If it may have been
damaged, a proper inspection is carried
out. If it can be reused, a new tag with a
due date six months away, is fitted.
When equipment leaves the site, the
system keeps working. It would be
expensive to send an inspector out to
Seville every time equipment needs to
be checked, so instead equipment
returns to base for inspection. As smallpieces of equipment approach their
inspection due date, replacements are
flown out in a steel cargo box. Old
equipment is sent back to Filton for
testing. For larger pieces of equipment,
such as pallet trucks, replacements are
sent out by road. Rather than sending
the old pieces of large equipment back a
piece at a time, it works out cheaper to
buy extra pieces, and send them back
when there is enough to fill a truck.
Staff at Filton know that it's a serious
breach of safe working practices to use
equipment that isn't tagged, or is past its
inspection due date, so the system rarely
goes wrong. This year, the plant has not
found a single piece of 'maverick'
equipment, that falls out of the system.
Last year, one piece of kit did manage to
enter the system.
A supplier had sent a pallet load of
goods to the plant. When it arrived, the
supplier offered the pallet truck the
goods came on, for free. As the truck
had entered the system outside of the
normal procurement process, it was
able to escape quarantine and
inspection. However, it was spotted on
the same day by a member of staff,
used to the routine of checking every
piece of equipment for the correct tag.
The truck was quarantined,
immediately. The supplier, Sutton says,
received a 'stern email', reminding themnot to supply equipment outside of
Filton's tracking system.
Adumpbin,withits
spacemarkedon theplant floor (left)and
a tag(right)withpartnumber and
colour-coded cableties showing nextinspectiondate.
Rigging
-
7/29/2019 Cranes Today April 08
49/68
IMET s.r.l. - Via Fornace, 8
33077 Sacile (PN) Italy
Tel. +39 0434 7878
Fax +39 0434 737848
Tailor made radio remote controls
-
7/29/2019 Cranes Today April 08
50/6850 CRANES TODAY APRIL 2008 www.cranestodaymagazine.com
Rigging
possible on the form to resist tipping.
But the obstruction of the concrete slab
above means that the crane hook is not
located above the centre of gravity of the
form. If a crane tried to lift the form with
four slings of the same length, the form
would swing, and then hang at an angle.
This is where the chain hoist comes in.
First front, and then rear, pick points are
hooked up as the form is rolled out of the
building. As the crane hook lifts up, the
chain hoist hook is lowered by remote
control, to keep the form horizontal.
During the process, the hoist can take up
to two-thirds of the form's weight.
Signal-Rite has built three sizes of
spreader, and specced a different sized
Harrington chain hoist for each; a 5 US
ton hoist with three falls of chain, 10 US
ton hoist with four falls of chain and 15
US ton hoist with six falls of chain.The company teamed up with
Harrington supplier and parent firm, Kito
of Japan, to develop a modified kit hoist
whose power cable and remote pendant
cable both come out the same side.
Signal-Rite chose Harrington because its
hoists are more forgiving of side pulling
than other brands, said president Jeff
York. The hoist chain angle ranges from
vertical (90 degrees) to 65 degrees.
Signal-Rite has sold more than 20
systems over the past 18 months and it
has been 'wet stamped' (approved) by
professional engineer Avery Miller of
Oakland, California. Customers include
Atlas Construction Supply, Penta
Group, Marnell Corrao, Patton Systems,Nibbe Brothers, Webcor Builders and
Ceco Concrete.
S
ignal-Rite has designed, built
and had approved a rigging
system hung from a
construction crane for
moving concrete forms out
from underneath concrete slabs.
The concrete slab poured on top of
the form covers about a third of an 80ft
(24m)-long form, including all of one
end. The slab obstructs access to the
natural lifting points on one end.
The Signal-Rite rigging system
consists of a 52in (1.3m) spreader bar
and four wire rope slings. Two 7/8in (22
mm) wire rope slings run from the edges
of the spreader bar to each side of the
form just beside the slab. Beneath the
chain hoist, balanced with 150 lb (46kg)
of counterweight, two lines attach to the
form about 20ft (6m) from the first two
points. Two tether lines keep the hoistfrom rotating.
The hooks are spread as widely as
There are fourcables in thesystem: two runningfrom the chain sling,and two runningfrom the edges ofthe spreader bar.
Rigging safety company Signal-Ritehas developeda
wayto lift out a concrete formwhen one endhas
been covered bycast concrete, reportsWill Dalrymple
Hoist keeps
forms level
Hoist keeps
forms level
The Signal-Ritecompensator
system up close
The rigging systemenables the load to be
picked off-centre
-
7/29/2019 Cranes Today April 08
51/68
Catalogue DigestTo advertise your company literature please contact Martin McCarthy on: Tel + 44 (0)20 8269 7848 Fax + 44 (0)20 8269 7803
Please contact Mr Hellmich / Mrs Petri / Mr HeinrichAm Schwarzbach a. d. B 44 D-64560 Riedstadt-Erfelden German y
Tel: +49-6158-188411 F ax: +49-6158-6929Email: [email protected]
www.hellmich-kranservice.dewww.allkran-hellmich.de
USED CRANESUSED CRANES
LIFT-N-LOCKLift and move heavy loads safely and
conveniently with J&R Engineering hydraulic
boom gantries as detailed in this brochure.
The exclusive LIFT-N-LOCK feature holds
up the load in the event the lift cylinder loses
pressure. Other exclusive patented safety
features include Stabilizer bars, Octagon
booms, Load sensing, Digital height
indicating system and Oscillating header
plates. Field proven models up to 1800 ton
capacity and lift heights up to 100 feet.
Crawler mounted gantries up to 700 ton
capacity and other specialized lifting and
transportation equipment available.
Tel: +1 (262) 363-9660
Fax:+1 (262) 363-9620
E-mail:[email protected]
Web Site: www.jrengco.com
Casar, a leading wire ropeproducer, has publisheda new brochure covering
various aspects of safety ingeneral and the safe use ofwire ropes in particular.
The brochure is availablefree of charge.
Please contact Casar [email protected] No. +49 6841 8091 359www.casar.de
Are You Safe?
In business with a purpose
We have developed products to meet the
stringent requirements of the offshore oil &
gas industry for many years. The working
conditions are tough and products have to
be able to sustain extreme conditions. Our
new BKD safety hook with an extra latch
secures a safe operation even when
unexpected opening of the hook might
occur. We have taken the aero
space industry as a role model;
when the normal system fails, another
is ready to save the situation. That is
business with a purpose.
Gunnebo Industrier AB [email protected] www.gunnebolifting.com
SPARE PARTS and SECOND HAND CRANES FOR SALE
(POTAIN, BPR, RICHIER, PPM, CADILLON, GROVE.)
Worldwide delivery in 24 to 48 hours.
Extremely competitive price and excellent service.
Second hand cranes available for sale:Potain 646G, 764, F2/23B, Cadillon 1410
Website: www.saudem.comTel: +33 1 48 52 80 00
Email: [email protected]
Fax: +33 1 48 92 02 01
-
7/29/2019 Cranes Today April 08
52/6852 APRIL 2008 CRANESTODAY
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
TIME TO CHANGE.
www.cranes-4-less.com
YOUR PARTNER
FOR CRANES & PARTSYoung Hitachi and Kobelcocrawler cranes in stock!
Immediate availability
of quality plant and
construction equipment
worldwide
Check our website:
www.borcherts.com
or contact us at: [email protected]
Tel: +31 - 653 652 522
Fax: +31 - 514 569 186
Hitachi CX 650 1998 70 T
Kobelco CKE 700 2006 70 T
Hitachi CX 900 1999 90 T
Sumitomo LS 238 1992 100 T
USED CRANES FOR SALE
M. STEMICK GMBH
Kran-u. Baumaschinenhandel
Annabergstr. 97
D-45721 Haltern/Germany
Import - Export
Tel: +49-2364-108203
Fax: +49-2364-15546
Mobile: +49-172-2332923e-mail: [email protected]
Internet: http://www.stemick-krane.de
HINEMAN CRANE SALES LTD
GROVE TMS635BE TRUCKCRANE 30T 1997/8
DEMAG AC55 ALL TERRAIN 55T 2004
DEMAG AC80-2 ALL TERRAIN 80T 2007
DEMAG AC100 ALL TERRAIN 100T 2008
LIEBHERR LTM1055 ALL TERRAIN 55T 2003
LIEBHERR LTM1080-1 ALL TERRAIN 80T 2004
Tel: +44 (0)1794 322777 Fax: +44 (0)1794 322070
Mobile: +44 (0)7785 291922
Email: [email protected]
P.O.B Crane and plant services LtdDealer in used Liebherr tower cranes
In Stock: Liebherr 71 Ec. Yom. 1994
Liebherr 91 Ec. Yom 1992Liebherr 112. Yom 1991
Wolff 91, 135, 200 280 available
Liebherr 280 Ec-h. Yom 1992
Liebherr 200 Ec-h. Yom 1998, 1991
Liebherr 140 Ec-h. Yom 1992, 97, 96
Tower section. 200. 120. 71
Phone: 00353 1 821 9656 Fax: 00353 1 824 3678
Email: [email protected]
-
7/29/2019 Cranes Today April 08
53/68
-
7/29/2019 Cranes Today April 08
54/68
-
7/29/2019 Cranes Today April 08
55/68CRANES TODAY APRIL 2008 55
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
EJAR IS DEDICATEDTO PROVIDINGSTATE-OF-THE-ART
RENTAL CRANES ANDEQUIPMENT
FOR CONSTRUCTION
EJAR PROVIDES
THE RIGHT LIFTINGSOLUTIONSTHROUGH
INNOVATIONAND COMMITMENT
TO EXCELLENCE
ADD VALUE TOYOUR PROJECTS WITH
EJARS FLEETOF CRANES AND
EQUIPMENT
N E W N A M EN E W
TECHNOLOGIES
N E W
C R A N E S
A N D
E Q U I P M E N T
E J A R C R A N E S & E Q U I P M E N T L L C
P.O.Box 282352 Dubai, United Arab Emirates | Tel: 04-3298580 | Fax: 04-3298856 | Web: www.ejarco.ae | E-mail: [email protected]
-
7/29/2019 Cranes Today April 08
56/6856 APRIL 2008 CRANESTODAY
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
Contact:[email protected]@Cranepart.nl
Supply of spareparts for axles,
gearboxes and transmissions.
Repairs of above units in our
workshop equipped with
testing facility.
Nieuwenhuysen-Universeel B.V.
Nieuwenhuysen-Universeel B.V.
Giessenweg 28,3044 AL Rotterdam
Phone : +31(0)10 415 98 22Fax : +31(0)10 415 28 22Internet : www.Cranepart.nl
ucmholland.nlwww.
THE NETHERLANDS
Tel: +31(0)252 235 468 Fax: +31(0)252 231 874
the BIGGEST in GERMAN BUILT CRANE PARTS, USED CRANES and MATERIALS
WE REPAIR OR BUY YOUR DAMAGED CRANES
10 MINUTES BY CAR FROM AMSTERDAM (SCHIPHOL) AIRPORT
BEFORE AFTER
Main Office:LIFT SYSTEMS216 40th St (61265)P.O. Box 906Moline, IL 61266-0906 USAPhone: +1 (309) 764-9842F ax : +1 (3 09 ) 764 -9 84 8E-Mail: lif t [email protected]: www.l i ft -sys tems.com
International Sales:INKRA GmbH / KRAH GmbHRichard-Strauss-Str. 31D-74629 PfedelbachGermanyPhone: +49 (0) 7941-8325Fax : + 49 ( 0) 7 941 -37 99 4E-Mail: krah@lift -systems.deWeb: www.l i ft -sys tems.de
Lift SystemcombinationModel 22A and
Model 24 A offloading a 95 tonconcrete dryer
INNOVATION IN LIFTINGINNOVATION IN LIFTING
Wellbe th
ere!
OUTSIDE AR
EAF9
N926/6
www.baum
a.de
RAIL BEAMS
The substitute for concrete
sleepers for tower cranes
Tel: +45 3966 1866
Email: [email protected]
www.tradehouse.dk
www.niggplant.com
used cranesfor sale
Contact: David Symon
Mobile Number: +44 (0) 7747 568587
Telephone Number +44 (0) 1226 785588
Fax Number +44 (0) 1226 785577
Nigg Plant LimitedNigg Plant Limited
Please contact Martin McCarthy:
Used Cranes, Equipment,Spares and Repairs
MARKETPLACE
www.cranesmarketplace.com
-
7/29/2019 Cranes Today April 08
57/68CRANES TODAY APRIL 2008 57
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
MTI-LUX S.A.
2a, Rue Prince Henri
L-6735 Grevenmacher
Luxemburg
Tel. +352 / 267 454 80
Fax +352 / 267 454 83
www.mti-lux.com
Your number onedistributor
Your first choice forusedLiebherr, Peiner and Potain
tower cranes
Liftyour
image!
STOCKLIST
Model Ton Year
DEMAG AC 25 25to 1997
LIEBHERR LTM 1030-1 30to 1997
LIEBHERR LTM 1030-2 30to 2000
KRUPP KMK 3045 45to 1990
TEREX HC110 110to 2008
LIEBHERR LTM 1120 120to 1994
LIEBHERR LTM 1120-1 140to 1997
LIEBHERR LTM 1160 160to 1987
KRUPP KMK 6180 180to 1995
KRUPP KMK 6200 200to 1992
AMERICAN HC275 250to 2007
DEMAG AC 300 300to 2000
DEMAG AC 400 400to 2000
DEMAG AC 500-1 500to 2001
HAC CranesGmbH&Co.KG
Excellent service for our customers.
From crane inspection to aftersales service. For maintenance,repairs and spare parts supplies.
Lindhooper Str. 54, 27283 Verden, Germany
T: +49 4231 933 489
F: +49 4231 961 657
E: [email protected]: www.hac-cranes.com
W: wwww.hac-commerz.com
MORE CRANES AVAILABLE
ON REQUESTCONTACT: GUDRUN STEER
SALES OF USED CRANES AND AFTER SALES SERVICE WORLDWIDE
Tel: 972-97499300 Fax: 972-9-7499356Mob: 972-52-2455132
Email: [email protected]
MD-265-1995
K30-30C-1995
MD-208-2004
MD-175-1996
MD-125-2001
F3-29-1990
646-G
643-J
-
7/29/2019 Cranes Today April 08
58/6858 APRIL 2008 CRANESTODAY
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
MICHIELSENS TRADING NV Bisschoppenhoflaan 275 Tel: +32 3 324 40 002100 D eurne Belgium (Europe) Fax: +32 3 888 42 22
Email: [email protected]
Web: www.cranes4u.com
OFFERS EXCELLENT USED AND NEW CRANES 4T-250T
BEST QUALITY, EXCELLENT AFTER SERVICE and
DELIVERY OF SPARE PARTS
NEW XCMG CRANESCE-tested + Mercedes Engine
Michielsens quality proofed
GROVE
GROVE INDUSTRIAL 24 4 T
GROVE GMK6250 250 T
GALIONGALION 150A 15 T
LIEBHERR
LIEBHERR LTM1025 25 T
LIEBHERR LTM1040 40 T
LIEBHERR LTM 1060/2 60 T
LIEBHERR LTM1070 70 T
TADANO
TADANO TR300EX 30 T
KRUPP
KRUPP KMK4080 80 T
XCMG
QY25K5 25 T
QY50K 50 T
NEW: QY25K5
KRUPP KMK 4080
GROVE GMK 6250
7021 Performance Dr., Syracuse, NY 13212
Syracuse Office: Phone 315-458-4101
www.empirecrane.com
TOLLFREE: 1-800-342-7575Fax: 315-458-3169
Email: [email protected]
Upstate Crane Parts - Supplying Crane Parts World-Wide!7021 Performance Drive, North Syracuse, New York 13212 - USA
Contact our PARTS DEPARTMENT TodayDomestic Parts Sales Email: [email protected]
International Parts Sales Email: [email protected]: (315) 458-4101 or (315) 701-4933 | Fax: (315) 458-3169 or (315) 701-4934
Crane Parts: All Makes, All Models
**Be sure to include your Model & Serial Number with your part number.
Terex T560-1 AVAILABLE IMMEDIATELY
Terex RT230-1AVAILABLE IMMEDIATELY
TEREX T560-1
TEREX
RT230-1
At Best Parts we combine an experienced sales and engineering
staff with an excellent customized manufacturing facility, quality
workmanship and a readily available supply of spare parts to assist
you in any way.
Best Parts & Machinery is official supplier for:
TEREX, P&H, AMERICAN CRANE, SUMITOMO-HITACHI,
MANITOWOC, AND LINK-BELT PARTS
Biggest parts stock in Europe, AMERICAN, SUMITOMO,
LINK-BELT, MANITOWOC
Best Parts & Machinery B.V.
De Gorzen 4
4731 TV Oudenbosch
The Netherlands
BEST PARTS & MACHINERY
YOUR NUMBER ONE SUPPLIER OF CRANES,
CRANE PARTS AND MAINTENANCE
Tel.: +31(0)16533 22 22 Fax: +31(0)16533 11 20 E-mail: [email protected] www.bestparts.nl
-
7/29/2019 Cranes Today April 08
59/68CRANES TODAY APRIL 2008 59
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
LIEBHERR
90 EC 1991
110 EC-B 6 FR 2006
112 EC-H 8 1993
154 EC-H 6 1994
154 EC-H 6 2000
280 EC-H12 2002
PEINER
SK 186/1 1995
SK 315 1998
SK 415 2001
Visit our Website for more
details and additional offers.
Tel: (+49) 62 21 82 81 80
Fax: (+49) 62 21 83 12 04www.wetzelcranes.de
Hitachi Sumitomo
Crawler Crane UKDistributors
For further information:
NRC PLANT LTD
Neagron House Tel: +44 (0)1375 361616
Stanford Road Fax: +44 (0)1375 361818
Orsett R M16 3 BX email: [email protected]
United Kingdom web: nrcplant.co.uk
HITACHI SUMITOMO1500-2
150 TONNE CRAWLER CRANE
SEE THIS CRANE AT SED 2008 STAND 620
75 METRE BOOM & SHORT JIB
28 METRE FLY JIB
20t WINCHES
LINE SPEED: 110mpm
WORLD STANDARD TOTAL
MOMENT LIMITER
MITSUBISHI 6D24 ENGINE
-
7/29/2019 Cranes Today April 08
60/6860 APRIL 2008 CRANESTODAY
The Market Place
Buy used cranes online www.cranestodaymagazine.com and click on used cranes
All Terrain Cranes
Ace Crane + Engineering Ltd
T: 01474 321721
F: 01474 321821
W: www.acecranehire.co.uk
Bigge Crane & Rigging Co.
T: 510-638-8100
F: 510-639-4053
W: www.bigge.com
BMSA/S
T: (+45) 44949048
F: (+45) 44943760
W: www.bms.dk
Heinrich Schacke GmbH & Co.KG
T: +49 (0) 203 / 99 52 90
F: +49 (0) 203 / 58 60 58
W: www.schacke.de
Hellmich Kranservice
T: 0049 6158 1001
F: 0049 6158 6929
W: www.hellmich-kranservice.de
KMS GmbH & Co. Handels-KG
T: 0049 2595 386980
F: 0049 2595 3869888
W: www.kms-cranes.com
M. Stemick GmbH
T: 0049 2364 108203
F: 0049 2364 15546
W: www.stemick-krane.de
TAT HONG HeavyEquipment
T: +65 6269 0022
F: +65 6367 1917
W: www.tathong.com
Vema Cranes
T: 0031 162 68 1050
F: 0031 162 68 6262
W: www.vemacrane.com
Crawler Cranes
Bigge Crane & Rigging Co.
T: 510-638-8100
F: 510-639-4053
W: www.bigge.com
BMSA/S
T: (+45) 44949048
F: (+45) 44943760
W: www.bms.dk
Cranebusiness BVLogicrane Fushun
T: +31 168 381 575
F: +31 168 381 576
W: www.cranebusiness.com
Heinrich Schacke GmbH & Co.KG
T: +49 (0) 203 / 99 52 90
F: +49 (0) 203 / 58 60 58
W: www.schacke.de
Hellmich Kranservice
T: 0049 6158 1001
F: 0049 6158 6929
W: www.hellmich-kranservice.de
House of Equipment
T: + 971 4 8803079F: + 971 4 8803078
W: www.hoeuae.ae
Crawler Cranes (continued)
Mammoet Trading
T: +31 10 204 25 85 / 204 2637
F: +31 10 204 24 42
W: www.mammoettrading.com
NRC Plant Ltd
T: 01375 361616
F: 01375 361818E: [email protected]
W:www.nrcplant.co.uk
Promech Resources Co. Ltd
T: 00(662) 7171406-7
F: 00(662) 7171408
W: www.promechresources.com
TAT HONG HeavyEquipment
T: +65 6269 0022
F: +65 6367 1917
W: www.tathong.com
Vema Cranes
T: 0031 162 68 1050
F: 0031 162 68 6262
W: www.vemacrane.com
Dockside Cranes
Grove Worldwide
T: 0191 522 2000
F: 0191 522 2051
W: www.groveworldwide.com
Heinrich Schacke GmbH & Co.KG
T: +49 (0) 203 / 99 52 90
F: +49 (0) 203 / 58 60 58
W: www.schacke.de
Gantry Cranes
Bigge Crane & Rigging Co.
T: 510-638-8100
F: 510-639-4053
W: www.bigge.com
Heinrich Schacke GmbH & Co.KGT: +49 (0) 203 / 99 52 90
F: +49 (0) 203 / 58 60 58
W: www.schacke.de
Heavy Crawler Cranes
Sarens UK Limited (Middlesbrough)
Cranes up to 1200 Tonne
T: +44 (0)1642 621621
F: +44 (0)1642 621620
Heavy Strut Jib Cranes
Sarens UK Limited (Middlesbrough)
Cranes up to 2000 Tonne
T: +44 (0)1642 621621
F: +44 (0)1642 621620
Heavy Telescopic Cranes
Sarens UK Limited (Middlesbrough)Cranes up to 1000 Tonne
T: +44 (0)1642 621621
F: +44 (0)1642 621620
Hooks and Slings
Gunnebo Industrier AB
T: 0046 220 384 00
F: 0046 220 384 98
W: www.gunnebolifting.com
Hydraulic Cranes
Mammoet Trading
T: +31 10 204 25 85 / 204 2637
F: +31 10 204 24 42
W: www.mammoettrading.com
Hydraulic Lifting Gantries
Bigge Crane & Rigging Co.
T: 510-638-8100
F: 510-639-4053
W: www.bigge.com
Hydraulic Lifting Gantries (continued)
Krah GmbH
T: 0049-7941-8325
F: 0049-7941-37994
W: www.Lift-systems.de
Level Luffing Slewing Cranes
Heinrich Schacke GmbH & Co.KG
T: +49 (0) 203 / 99 52 90
F: +49 (0) 203 / 58 60 58
W: www.schacke.de
Light/Heavy Equipment Rental
The Paramount Transport &
Trading Co. Ltd
T: +1 868 653 3802/3
F: +1 868 652 8030
W: www.paramounttransport.com
Mobile Cranes
A Soulis Enterprises
T: +357 2