1616thth Road Pavement ForumRoad Pavement Forum
CSIR Conference CentreCSIR Conference Centre
1111 12 November 200812 November 2008
CONCRETE PAVEMENTCONCRETE PAVEMENT
REHABILITATIONREHABILITATION
Philip Joubert
-
8/14/2019 crack and seat presentation.pdf
2/47
Presentation Overview
Look at:
Restoration of pavement lifein
existing rigid pavementusing techniques
of
Cracking & Seatingor
Rubblizing
-
8/14/2019 crack and seat presentation.pdf
3/47
Rehab. of Concrete Pavement
-
8/14/2019 crack and seat presentation.pdf
4/47
Typical Failed Pavements
-
8/14/2019 crack and seat presentation.pdf
5/47
Typical Failed Pavements
-
8/14/2019 crack and seat presentation.pdf
6/47
Typical Failed Pavements
-
8/14/2019 crack and seat presentation.pdf
7/47
Typical Decision Flow DiagramTypical Decision Flow Diagram
-
8/14/2019 crack and seat presentation.pdf
8/47
1. CRACK AND SEAT (C&S)1. CRACK AND SEAT (C&S)
Principles and MethodPrinciples and Method
ofof
Crack and SeatCrack and Seat
OperationsOperations
-
8/14/2019 crack and seat presentation.pdf
9/47
Principle of Cracking & SeatingPrinciple of Cracking & Seating
-
8/14/2019 crack and seat presentation.pdf
10/47
Objective of C & S
TO:
modify characteristics of rigid pavement:
into a more flexible structure,
BUT ALSO TO:
minimise asphalt overlay thickness :
by retaining max pavement stiffness / strength
-
8/14/2019 crack and seat presentation.pdf
11/47
C & S Technique - 1
Produces shorter slabs
0.6 2m in length
Retains structural integrity
Induces fine, vertical, transverse cracks in JCP
Reduces effective length of slab between joints.
-
8/14/2019 crack and seat presentation.pdf
12/47
C & S Technique - 2 Size of slabs is effectively reduced
Therefore: Horizontal strains - from thermal movements:
distributed more evenly over pavement,
less likely to cause reflective cracks in HMA overlay
Cracks induced in PCC slab so fine that:
load transfer between newly formed slabs = good
because of aggregate interlock.
After cracking:
PCC segments firmly seated by heavy pneumatic tire roller
ensure - no voids beneath PCC segments prior to overlay
-
8/14/2019 crack and seat presentation.pdf
13/47
Typical Equipment
8600 Badger Guillotine Breaker 20 ton Pneumatic Tyre Roller
-
8/14/2019 crack and seat presentation.pdf
14/47
Cracking & Seating Operation
-
8/14/2019 crack and seat presentation.pdf
15/47
Typical Induced Crack
Broken core showing good
aggregate interlocking
Crack should be verticalthroughout depth of core
Core taken from a
450mm thick
pavement
-
8/14/2019 crack and seat presentation.pdf
16/47
C & S @ Heathrow Airport
-
8/14/2019 crack and seat presentation.pdf
17/47
C & S @ Heathrow Airport
-
8/14/2019 crack and seat presentation.pdf
18/47
C & S Issues affecting performanceC & S Issues affecting performance
Foundation = firm with good seating
Too small slab size: accelerate cracking
Better in un-reinforced JCP
Method preferred for cracked/faulted
-
8/14/2019 crack and seat presentation.pdf
19/47
2.2. RubblizationRubblization ((Asphalt Institute)
Process of: breaking / pulverising PCC pavement in-place
into small, interconnected pieces (75 - 200mm)
Serve as base course for HMA overlay.
Deflections / weak spots: filled with coarse aggregate
Rubblized - compact with steel roller The rubblizing process:
reduces slab to an granular base for overlay
eliminates all reflective cracking concerns
-
8/14/2019 crack and seat presentation.pdf
20/47
Distressed Concrete
Mid-panel cracking
-
8/14/2019 crack and seat presentation.pdf
21/47
Water trapped below concrete
-
8/14/2019 crack and seat presentation.pdf
22/47
Before rubblization
-
8/14/2019 crack and seat presentation.pdf
23/47
After rubblization
-
8/14/2019 crack and seat presentation.pdf
24/47
RubblizationRubblization MethodMethodTo meet specifications for concrete pavements:
1. Firstly - break using guillotine
2. Then - 16hammer Breaker
3. Then - grid roller:
to further pulverize
to shape concrete particles at surface
to begin compaction process.
4. Final - seating typically accomplished with:
20-ton pneumatic-rubber tyre roller [PTR]
-
8/14/2019 crack and seat presentation.pdf
25/47
-
8/14/2019 crack and seat presentation.pdf
26/47
-
8/14/2019 crack and seat presentation.pdf
27/47
-
8/14/2019 crack and seat presentation.pdf
28/47
-
8/14/2019 crack and seat presentation.pdf
29/47
-
8/14/2019 crack and seat presentation.pdf
30/47
Layer StiffnessLayer Stiffness
The rubblized layer stiffness:
700 - 3000MPa
Compared a typical high quality crushed
aggregate base 500 MPa
-
8/14/2019 crack and seat presentation.pdf
31/47
Pre-cracking 500mm concrete
-
8/14/2019 crack and seat presentation.pdf
32/47
Pre-cracking pattern
-
8/14/2019 crack and seat presentation.pdf
33/47
Pre-cracking concrete
-
8/14/2019 crack and seat presentation.pdf
34/47
Rubblization
-
8/14/2019 crack and seat presentation.pdf
35/47
Completing the rubblization
-
8/14/2019 crack and seat presentation.pdf
36/47
Completing the rubblization
-
8/14/2019 crack and seat presentation.pdf
37/47
Surface after grid rolling
-
8/14/2019 crack and seat presentation.pdf
38/47
Surface after grid rolling
-
8/14/2019 crack and seat presentation.pdf
39/47
Test hole
T t h l
-
8/14/2019 crack and seat presentation.pdf
40/47
Test hole
T t h l
-
8/14/2019 crack and seat presentation.pdf
41/47
Test hole
P i ith M/T V hi l
-
8/14/2019 crack and seat presentation.pdf
42/47
Paving with M/T Vehicle
Pl i t b l
-
8/14/2019 crack and seat presentation.pdf
43/47
Placing aggregate base layer
C t l i
-
8/14/2019 crack and seat presentation.pdf
44/47
Concrete overlay in process
S t i bilitS t i bilit
-
8/14/2019 crack and seat presentation.pdf
45/47
SustainabilitySustainability
No hauling or disposal costsNo hauling or disposal costs
Existing pavement retainedExisting pavement retained -- saves natural resourcessaves natural resources
Saves landfill spaceSaves landfill space
Expedites constructionExpedites construction
Environmentally friendlyEnvironmentally friendly
CostCost--effective as rehabilitation technique.effective as rehabilitation technique.
Existing concrete pavement stays in placeExisting concrete pavement stays in place
Becomes base for new HMA pavementBecomes base for new HMA pavement
Reduce or eliminate need for new virgin aggregates.Reduce or eliminate need for new virgin aggregates.
Weather delays minimisedWeather delays minimised -- sub grade never openedsub grade never opened
Th k YTh k YG i H ?Going Home?
-
8/14/2019 crack and seat presentation.pdf
46/47
Thank YouThank YouGoing Home?Going Home?
Project sizeProject size
-
8/14/2019 crack and seat presentation.pdf
47/47
Project sizeProject size
Minimum: 25 000mMinimum: 25 000m2
R30/m2 2 weeks on site