AGENDA
• ACE Grant
• Exterior Elevation Concepts
• Weight Room / Board Room Options
• District Administration Options
![Page 3: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/3.jpg)
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Department of Community and Economic Developmentand
Department of Environmental Protection
![Page 4: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/4.jpg)
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Benefits:
• ACE Grant
$2,000,000
• Additional PDE Reimbursement $ 373,000
• Lower Energy Costs annual
$2,373,000
![Page 5: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/5.jpg)
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Required:
• LEED Gold - High Performance Bldg.
![Page 6: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/6.jpg)
Alternative and Clean Energy Program (ACE)
CRA obtained $2 million grant for each:
Lewisburg School District
State College School District
South Middleton School District
![Page 7: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/7.jpg)
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Cost: for LEED Gold
• Energy Efficient Components $ 750,000• Enhanced Commissioning $ 50,000• General Construction $ 50,000• Design / Application Fees $ 132,000
$ 982,000
![Page 8: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/8.jpg)
Montoursville Area School District
Alternative and Clean Energy Program (ACE)
Net Benefit:
• Total Benefits $ 2,373,000
• Cost for LEED Gold less $ 982,000• Scope beyond budget (1%) less $ 384,000 Includes Basic EPDM roofing
$ 1,007,000
![Page 9: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/9.jpg)
Montoursville Area School District
MEPReplace all Roof-top units
ArchitecturalMoveable CaseworkUnforseen floor conditions in Aux Gym / Weight Room area
CivilD zone surfacing of trackAdditional Paving Scoreboard electrical Stadium EntranceFencing
Scope beyond original Budget includes :
![Page 10: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/10.jpg)
1 2Montoursville Montoursville
TREMCO TREMCORoofing Single Ply Built-Up
Add to Base Cost 349,623$ 733,558$
![Page 11: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/11.jpg)
Montoursville Area School District
2Net Benefit : $ 1,007,000Tremco TPO Single Ply $ 350,000
$ 657,000
3Net Benefit : $ 1,007,000Tremco Built-Up Roof $ 734,000
$ 273,000
![Page 12: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/12.jpg)
Current DesignWeight Room and No DAO Board Room
![Page 13: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/13.jpg)
Alternate 1 Add $200,000DAO Board Room with Weight Room Addition
![Page 14: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/14.jpg)
Alternate 2 No Cost ChangeSmaller Weight Room and Smaller DAO Board Room
![Page 15: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/15.jpg)
1st Floor Plan
![Page 16: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/16.jpg)
1st Floor Plan
![Page 17: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/17.jpg)
1st Floor PlanExist. Maintenance, Tech. Ed. Bldg, & Field house
![Page 18: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/18.jpg)
Main Entrance
![Page 19: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/19.jpg)
Classroom Wing
![Page 20: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/20.jpg)
District Administration Entrance 1
![Page 21: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/21.jpg)
Bird’s eye District Administration 1
![Page 22: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/22.jpg)
District Administration Entrance 2
![Page 23: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/23.jpg)
Bird’s eye District Administration 2
![Page 24: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/24.jpg)
District Administration Entrance 3
![Page 25: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/25.jpg)
Bird’s eye District Administration 3
![Page 26: Crabtree, Rohrbaugh & Associates, Architects Montoursville Area School District High School Project Update February 10, 2015](https://reader035.vdocuments.us/reader035/viewer/2022062516/56649e165503460f94b010c7/html5/thumbnails/26.jpg)