cqy stn paper k27oct06

Upload: seng-siong

Post on 05-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 CQY Stn Paper K27Oct06

    1/19

    CLARKE QUAY MRT STATION - Engineering Provisions for Future

    Development and subsequent Design of the Development

    K Mahmood and S Mahatma

    Maunsell Consultants (S) Pte Ltd

    S S SohKTP Consultants Pte Ltd

    Abstract

    Clarke Quay Station is part of a 20km long Mass Rapid Transit (MRT) North East Line,

    in Singapore. To fully exploit development potential of the underground transit station,

    its design incorporated the planning guidelines required by Urban Redevelopment

    Authority (URA) for the future development. The land above and adjacent to the stationwas subsequently sold as a white site parcel and is now known as CENTRAL.

    This paper describes URAs requirements for the planned development at Clarke Quay

    Station and the engineering provisions incorporated in planning and design of the station.

    The issues discussed include the structural and foundation provision to support the

    development, integration of future developments skewed grid arrangement with that of

    the station and provisions for station integration with the development. As the

    development partially sits above the station, it subjects the station to non-uniform loads.

    The complexity of design for this varying load condition has also been discussed.

    The paper also describes structural behavior of the station with the envisagedconstruction sequence for the development. The use of these provisions, in planning and

    designing the development, is explained in subsequent part of the paper. Actual structural

    behavior of the station, during construction of the development, is also presented for a

    comparison with its analyzed behavior.

    1.0 IntroductionUnderground rail transit system, in Singapores urban environment, helps avoid

    sterilizing scarce land and making it available for more valuable use such as commercial

    and residential developments. Transit oriented developments, especially those integrated

    with the stations, also help to maximize access by transit transportation and encouragetransit ridership. It is important to make necessary provisions, where feasible, for such

    developments during the early stages of transit station planning and design. This would

    help materialize full commercial potential of such developments by mitigating constraintson their development.

    Clarke Quay (CQY) Station is a part of 20km long Mass Rapid Transit (MRT) North East

    Line (NEL), in Singapore, where Urban Redevelopment Authority (URA) required to

    incorporate its planning guidelines for the site during the planning and design of the

    station. Subsequently, during construction of the stations, the land above and adjacent to

  • 7/31/2019 CQY Stn Paper K27Oct06

    2/19

    the station was sold as a White Site Parcel. The site has now been developed and is

    known as Central.

    Maunsell led the multi-disciplinary design team during tender, detailed design andconstruction stages of the CQY MRT Station. The station planning and design required

    provision for up to a 12 storey future development above the station and a 20 storey

    future development next to it, both with basements.

    2.0 LocationThe 2-level underground station is located

    on the south bank of the Singapore River,

    opposite Clarke Quay, near the Coleman

    Bridge and partially below the Eu Tong

    Sen Street / New Bridge Road. During theinitial planning phase of NEL, it was

    considered to be an ideal location forachieving the urban redevelopment

    objectives and transportation integration

    objectives. The alignment of the North

    East Line, at CQY Station, resulted in a

    station orientation skew to and partly

    below the Eu Tong Sen Street / New

    Bridge Road (Figure 1). The station is founded about 23m below the ground level.

    Figure 1: Site Plan of Clarke Quay MRT Station

    This space restriction and the skew orientation resulted in a layout of the station with

    triangular shape enlargements at three corners. These large triangular areas were

    required to accommodate the plant rooms at both concourse and platform levels.

  • 7/31/2019 CQY Stn Paper K27Oct06

    3/19

    3.0 Requirements for Planned URA Future DevelopmentURA during the design stage of Clarke Quay Station issued their requirements for theintegrated development above and adjacent to the station. URAs plan for the

    development consisted of one block of 4-storey promenade, 2 blocks of 12-storey

    buildings with a basement, one block of 6 storey building with a basement and a 3-storeylink bridge. All these developments were required to be positioned over the station either

    wholly or partially. Another block of 20-storey building with 2 basements was planned

    just outside the station box (Figure 2).

    Figure 2: Station Box Geometry and URAs Future Development

    4.0 CQY Station BoxThe station box orientation and geometry, respecting the transit structure needs, followed

    the orientation of the alignment. At the same time, it also incorporated the requirements

    of future development with respect to road orientation. The station is about 200m long

    with varying width along its length. It is 70m wide at the northern end near the river,

    57m wide at the southern end near the Merchant Court Hotel and 28m wide along the

    central public platform area. The station was designed as a Civil Defence Shelter.

    The future development columns were generally supported on the station columns below.

    However, due to different grid systems for the two structures, some of the future

    development columns were supported directly on the 1950mm thick roof slab. In some

    areas, the roof slab thickness was increased locally to 2500mm to transfer the future

    development loads to the columns and walls below.

    5.0 Provisions for Future Development in Station Planning

  • 7/31/2019 CQY Stn Paper K27Oct06

    4/19

    5.1 Four Gridline SystemFor a normal rectilinear shape station box, an orthogonal 2-grid line system is sufficient

    to plan and define the station geometry. However, the future development was orientatedwith respect to the road alignment and was oblique to the station structure. The future

    development columns were not located on the station grid line. Station grid also did not

    satisfy URA requirement for a regular pattern grid for the future development. Thisnecessitated the need for a four gridline system for CQY station. Two grid lines matched

    the station platform orientation and the other two matched the skew ends and the future

    development column positions. It was considered important to arrange the two-grid

    systems complementary to each other. This was to achieve an arrangement of column

    locations common to both the station and the development. The odd shape layout made

    the transit architecture more challenging to obtain optimal use of the space.

    Fig 3: Grid Systems defining Station Box and Future Development Geometries

    With the adoption of four gridline system, an alternative column grid was proposed byadjusting some of the future development column positions. The revised column grid

    arrangement was developed for better structural integration of the station and

    development, considering the following: Future development column grids to suit station platform edge columns

    Future development columns to rest on the station diaphragm wall where theywere close to the wall,

    To allow for 3.6m wide promenade along the river side

    To suit the location of the vent shaft structures

    5.2 Transfer of Future Development LoadsThe varying heights of future development resulted in concentrated loads of varying

    magnitudes on the station structure below. In addition, part of the station box area, below

  • 7/31/2019 CQY Stn Paper K27Oct06

    5/19

  • 7/31/2019 CQY Stn Paper K27Oct06

    6/19

    developments were planned with columns outside the station box but in close proximity

    It required installation of foundations very close to the station structure. The subsurfacesoil profile at CQY consisted of deep Kallang formation. Deep foundation elements were,

    therefore, needed as a foundation system for the future development. To minimize theeffect of constructing the deep foundation element, in close proximity of an operational

    station, barrettes and bored piles were provided as part of the station development.

    Figure 5: Foundation Provisions outside the Station Box

    5.4 Unbalanced Excavation adjacent to Station BoxThe future development consisted of a 2-level basement adjacent to the station box,

    extending over a length of about 80m along the station box (Figure 2). To facilitate the

    basement construction adjacent to the station box, the station design allowed for a 14mdeep unbalanced excavation (up to the concourse of the station) on west side of the

    station structure.

    Figure 6: Provision for Unbalanced Excavation outside the Station Box.

  • 7/31/2019 CQY Stn Paper K27Oct06

    7/19

    5.5 Integration with the other DevelopmentsStation planning also considered its integration with other future developments in itsvicinity to allow convenient movement of people between the two. As there were no

    specific details available for such future developments, provision was made in the station

    external walls for knock-out panels to facilitate future connection to the developmentdirectly or by means of subway structure. The locations of knock-out panels were

    selected to suit the known future development towards West and unknown development

    towards East. In total, there are seven knock-out panels provided at the concourse level

    in the station external walls.

    6.0 Envisaged Construction SequenceFor the design of the station box and associated entrances, feasible construction methodsand sequence were considered for the future development. They included construction of

    future developments basement adjacent to the station entrance subway

    future connection at knock-out panels

    6.1 Basement adjacent to the Station BoxA feasible construction sequence for (the basement of) the future development was

    developed to minimize the effect of its construction on the station box, as follows:

    The basement above the station roof in areas A & C to be constructed within thestrutted excavation. This is to be completed before the construction of the

    basement outside the station box.

    The basement outside the station box, Area B, could then proceed without a need

    to support the station box against unbalanced loads.(Figure 7)

    Figure 7: Basement Construction Sequence

    B

    A

    C

  • 7/31/2019 CQY Stn Paper K27Oct06

    8/19

    6.2 Entrance SubwayPart of future development basement was planned adjacent to the station entrance subwaynear the Merchant Court Hotel. The subway structure was supported on piles and located

    between the bored tunnel on one side and the future basement structure on the other side.

    An assessment was carried out to evaluate a feasible construction method to limit theimpact of future basement excavation on the station entrance structure and on the

    adjacent tunnels. It was proposed to construct the future basement using diaphragm walls

    as rigid ground support system, with pre-installed jet grouted slab, at the level of entrance

    subway base.

    Figure 8: Scheme for Basement Construction next to Entrance Subway

    6.3 Connection at Knock-out PanelsA suitable construction scheme was developed to minimize load transfer from the futurelink to the station structure.

  • 7/31/2019 CQY Stn Paper K27Oct06

    9/19

    Figure 9: Future Connection at Knock-Out Panel Locations

    7.0 Analyzed Structural Behaviour of the Station BoxUsing 3-dimensional analysis model, 27 independent load cases and 7 load combinations

    were considered to simulate various external loads acting on the station box including

    those from the future development and unbalanced loads from adjacent future basements.

    The lateral displacement at roof level of the station box, from unbalanced excavation,was estimated at about 6mm and was well within the allowable 15mm. Such a controlled

    movement reflected realistic behaviour of the rigid station box and was only expected

    from a 3-dimensional model.

    The settlement of the station box under varying load was also estimated using soil-

    structure interaction program FLAC. For deformation analysis, stages of construction for

    the station box were modeled in FLAC. For the maximum vertical downward loads, total

    estimated settlement of the raft at the most heavily loaded column was within theallowable 20mm. It was also noted from the assessment that, under the differential

    loading condition, the base slab settlement gradient was within the permissible limits of 1

    in 1000.

  • 7/31/2019 CQY Stn Paper K27Oct06

    10/19

    Figure 10: Station Box Deformation from Unbalanced Loads

    8.0 Design of Central8.1 Development on Station StructureThe URA white site development located directly over the station structure is a podium

    with one basement, a 12-storey SOHO1 (small office home office) near to the Coleman

    Bridge and a 8-storey SOHO2 in front of Merchant Court Swissotel. The podium and

    basement are designed for retail & beverage outlets.

    SOHO1 starts from the 5th storey whereas SOHO2 starts from 4th storey. The 25-storey

    tower block that is located north of the station sits on a triangular footprint and comprises

    of 4-storey of retail & beverage, carparking and offices in the upper floors. There is a

    basement in the tower block and a link to the concourse level. At the time of preparation

    of this paper, the podium, SOHO1 and SOHO2 had been completed whereas the tower

    block was partially completed.

    The loads to be supported by station and the raft foundation were given by URA based on

    the number of floors and the usage of the floors. In the design development phase, theseloads were a governing factor especially for the SOHO1 block.

  • 7/31/2019 CQY Stn Paper K27Oct06

    11/19

    Figure 11: View of SOHO1 structure over the Clarke Quay MRT Station.

    Figure 12 shows the plan with the column locations and design loads for the new

    development. The provision for future developments loads, in the station design,was considered sufficient as the actual column loads were less than those originallyprovided.

    Figure 12: Plan showing the URA columns above the Clarke Quay Station.

  • 7/31/2019 CQY Stn Paper K27Oct06

    12/19

    8.2 Design CriteriaIn addition to the LTAs Code of Practice for Railway Protection, there were other

    specific requirements in land sale conditions for the Clarke Quay MRT Station site. Forthe station structure, a maximum deformation of 20 mm and 15mm were permitted in

    vertical and horizontal directions respectively.

    The complex provision of a range of column loads for the different levels of the buildings

    above the station would cause uneven settlement. Likewise, the station is supported by

    peripheral diaphragm wall that would settle less than the raft foundation. To minimize the

    effect of the differential settlement, the structure longitudinal differential movement was

    limited to 1/1000.

    The complex provision of a range of column loads for the different levels of the buildings

    above the station would cause uneven settlement. Likewise, the station is supported byperipheral diaphragm wall that would settle less than the raft foundation. To minimize the

    effect of the differential settlement, the structure longitudinal differential movement was limited to 1/1000.

    Table 1: Design criteria for station structure movement.

    Type of movement LTA Contract C708

    Structure total movement in vertical direction 20 mm

    Structure total movement in horizontal direction 15 mm

    Structure longitudinal differential movement 1/1000

    Track vertical dip or peak 5 mm over 5 m chord

    Track horizontal corresponding versine 6 mm over 15.8 m chord

    These design criteria are applicable during construction as well as for in the long term

    condition. On the completion of the station construction, the rail tracks were aligned

    vertically and horizontally before the tracks were put to use.

    8.3 Design Parameters for Raft Foundation AnalysisThe design parameters used in the settlement analysis was adopted from Maunsellsearlier design. These are summarized in Table 2. The 1500 mm thick raft is supported on

    three soil types at the founding depth, 23 m below ground level. Beneath the raft slab, at

    northern end, there was a thin layer of soft soil that was treated with suitably spaced jet

    grout piles. At central zone of the station box, soil improvement was carried out with

    concrete trenches.

    The penetration of 1200mm thick diaphragm wall varies from about 32 m to 38 m . The

    diaphragm wall is founded in S2 material of the Jurong Formation sedimentary siltstones.

  • 7/31/2019 CQY Stn Paper K27Oct06

    13/19

    Table 2: Subgrade modulus adopted for settlement analysis.

    Soil Type Subgrade Modulus

    Lightly JGP treated or lean concrete trench soil 13,000 kPa

    Heavy JGP treated soft soil 16,000 kPa

    S4a/b Weathered rock of Jurong Formation 22,500 kPa

    Figure 13: Ground improvement layout plan.

    8.4 Raft Foundation AnalysisThe SAFE finite element program was used to model the entire raft including the

    diaphragm wall along the periphery of the station. The various load cases and

    combinations are given in Table 3.

    During the course of the construction of CENTRAL, there was no instrumentation to

    monitor the hydrostatic pressure beneath the station raft. Even though the Singapore

    River is next to the station, the diaphragm wall around the peripheral of the station could

    have maintained the hydrostatic pressure acting beneath the raft slab. The tidal

    fluctuation in the Singapore River varies from RL98.5 m to RL101.5 m. The raft soffitlevel is RL 79.0 m.

    Table 3: Load case and load combination for the settlement analysis.

    Ref. Load Case/ Combination Load Type

    1 Load case 1 Station (ST)

    2 Load case 2 Development Load (DEV)

  • 7/31/2019 CQY Stn Paper K27Oct06

    14/19

    3 Load case 3 Hydrostatic (UPLIFT)

    4 Load combination 1 ST+ UPLIFT

    5 Load combination 2 DEV + UPLIFT

    6 Load combination 3 ST + DEV

    7 Load combination 4 ST + DEV + UPLIFT

    The governing load combination is the development load. The settlement analysis was

    also carried out with three different ground water level conditions, i.e at 96.0 RL, 101.0

    RL and 92.5 RL to assimilate simulate the minimum uplift, the maximum uplift and the

    temporary condition during the end of excavation. The maximum settlement under theeffects of full development load is estimated asat 17.5 mm.

    Figure 14: The settlement plot for load combination with the development loads and

    hyhdrostatic uplift.

    The figure 14 shows the contour plot of the raft foundation under the full development

    load. The settlement is not uniform due to varying column loads. The geometry also

    affects the contour of the settlement. As shown in the settlement contour, the maximum

    settlement occurs at the location where the width in the vertical direction is greatest. Thislocation is also directly under the SOHO1 and is close to the south-bound tunnel line.

    8.5 Comparison of Predicted & Observed SettlementThere were no available measurements of the settlement during the construction of the

    station and the period between the completion of the station and the commencement of

    the new development over the station. However, the observed settlement can be

    accurately obtained from the automatic tunnel monitoring system (ATMS) of the south

    bound tunnel instead of the north-bound tunnel that is too close to the diaphragm wall on

    the northern side.

  • 7/31/2019 CQY Stn Paper K27Oct06

    15/19

    Figure 15: Lateral and vertical displacement of South-bound tunnel at the crown level.

    The ATMS was installed before any engineering works commenced and showed amaximum settlement of 13 mm when the construction of podium, SOHO1 and SOHO2were completed. It is assumed that the maximum settlement would occur when the floors

    are fully loaded. This scenario is not easily simulated and monitoring over a period of

    time during heavy human traffic and having all outlets fully utilized is necessary to obtain

    the maximum settlement.

    For the lateral displacement, the ATMS for the north-bound tunnel and the south-bound

    tunnel hardlydid not register any movement towards the excavation in the tower block.

    Table 4: Comparison of predicated settlement against observed settlement.

    As of 15 Oct 06 Predicted Observed LTA

    Settlement at fullsuperimposed dead

    load (80% of full load)

    14 mm13 mm

    (from ATMS)

    16 mm(80% of max

    permissible)

    Settlement at fullsuperimposed dead

    load + live load17.5 mm not available

    20 mmmax permissible

    The table 4 shows the comparison between the predicted and observed settlement of the

    station structure when loaded to about 80% of the full design load and the permitted

    settlement by LTA.

  • 7/31/2019 CQY Stn Paper K27Oct06

    16/19

    The recorded settlement is based on the south-bound tunnel crown level and it also shows

    the differential settlement at 5 m intervals. The measured settlement of 13 mm comparesvery favourably with the predicted settlement of 14 mm.

    The construction of the basement above the station roof commenced in November 2004

    and the roof of SOHO1 and SOHO2 was completed on June 2006 and September 2006

    respectively.

    9.0 Interfacing Details Vent Shafts & Entrances9.1 Hacking of Column Stumps by Darda Splitter Method

    During the construction of the MRT station, starter bars extending from the roof were

    covered by concrete stumps and were to be exposed for lapping with the reinforcement

    for the development columns. There were 55 column stumps on the station roof that

    requires breaking with minimal vibration and disturbance to the users and operators in theMRT station. The contractor proposed the Darda method to be used during the daytime

    and pneumatic breakers is unbearable during the train non-operating hours.

    Figure 16: Column stumps above the station roof.

    Darda splitting cylinders are handheld demolition devices, which controllably split

    material with the use of hydraulic pressure. Larger conventional demolition devices are

    ruled-out because they produce dust, flying debris, vibrations, noise and possibly exhaust

    fumes.

    Figure 17: Silent demolition of column stump by Darda hydraulic splitter.

  • 7/31/2019 CQY Stn Paper K27Oct06

    17/19

    9.2 North and South Vent shafts

    The north vent shaft is located near to the river promenade. URA land sale requirementdoes not permit the ventilation discharge at the covered walkway level. Due to the space

    constraints and the ventilation requirements, a 4 storey high vent shaft was integrated tothe faade of the podium facing the Singapore River. The engineering solution was to

    design an enclosure that would enable an interfacing without disrupting the station andtunnel operation.

    The south vent shaft facing Eu Tong Sen Street and Merchant Court Swissotel had a

    similar method for the interfacing. The new ventilation intake and discharge are located

    on the 1st

    storey with the openings away from the covered walkway and the 2nd

    storey

    levels.

    9.3 Precast System over MRT Entrances

    The use of precast beams and prestressed hollow core slabs over the MRT entrances were

    introduced for the construction of 2nd

    storey floors. The access to the station is not to be

    disrupted during the train operation hours. As a mandatory precautionary measure, the

    launching of the precast beams and the hollow core slabs were carried out during non-

    operating hours of the NEL.

    9.4 Cutting of Diaphragm Wall Openings by Wire Saw System

    There are three large openings for the interfacing from the development area to the

    station concourse and the staircase area as well as eight other large openings in the

    diaphragm wall above the station roof level.

    The Hilti DS-WS15 wire saw system was used to cut the 1200 mm diaphragm wall at the

    knock-out panels for the openings. Due to its small size, cutting even the most difficultsituation such as the less accessible location at the lower end of the escalator to the

    concourse was completed efficiently. Smooth surface was achieved quietly without

    distressful vibration.

    Figure 18: Diaphragm wall opening by wire saw method.

  • 7/31/2019 CQY Stn Paper K27Oct06

    18/19

    10.0 Effects of Excavation on Station

    The design of the station permitted various sequences of engineering works such as theexcavation for the basement construction up to a depth of 14 m without a bracing system.

    For the construction of the development, the substructure and superstructure commenced

    simultaneously with the installation of the diaphragm wall and piling works.

    The excavation for the basement beneath the tower block commenced after the

    completion of the basement slab and the podium above the station roof. The effect of the

    excavation on the station structure was negligibleminimal due to the stiffness of the

    station box. Also, there was no trend to show the effects of the excavation on the

    settlement of the station box while it was being loaded by the superstructure works of

    SOHO1 and SOHO2.

    11.0 Monitoring Works during Construction

    The automatic tunnel monitoring system (ATMS) for north and south bound tunnel gives

    accurate measurement for the settlement and lateral movement due to vertical loading and

    excavation works. Prisms were installed at the crown, side wall and the rack levels in the

    station and tunnel. The readings are taken every eight hours and sent by email to the

    various parties including LTA. When the alert level or work suspension level is reached,

    the system would send the data by sms to the key persons.

    Ground instrumentation monitoring was implemented before the piling and diaphragm

    wall works. The instrumentation includes water standpipes, piezometers, vibrationtransducers, inclinometers, ground settlement markers, building settlement markers amd

    tiltmeters. Building settlement monitoring was carried out on a regular frequency and

    compared with the readings from ATMS.

    During the excavation stage of the construction, monitoring meeting was convened

    weekly. Contingency measures and action plans together with the criteria levels wereestablished before the engineering works began.

    12.0 Engineering Issues and Solutions

    The engineering issues for the construction of the CENTRAL over the Clarke Quay MRT

    Station are:

    i. To ensure that there are no adverse effects on the station structure due tounbalanced loading on the station during excavation works.

    ii. To minimize vibration for the hacking of column stumps, diaphragm wall openings.iii. To ensure that there is no disruption to users and operator during the interfacing

    works.

    iv. To ensure that fire engine access to station is not affected.

  • 7/31/2019 CQY Stn Paper K27Oct06

    19/19

    v. To keep dust free operation near the vent shafts and MRT entrances.vi. In view of the engineering, environmental and safety issues, solutions specific to

    the situation have been implemented and in compliance with the regulatory

    authorities and the operators of the NEL. The assistance by the LTA authorities andSBST (operator) in guiding the implementation was also critical to resolving these

    issues.

    13.0 Conclusions.For seamless integration of transit oriented developments, it is essential to make

    provisions, for such developments, during initial planning and design stages of a station.

    Provisions for URAs future development requirements were integrated in the design of

    CQY MRT Station. Provision of such requirements presented challenges in planning and

    design of the station. Many of these challenges resulted from constrained geometry of the

    station box, its orientation being different from that of future development anddevelopment of suitable interfaces between the column grids of the two developments.

    The difficulties of station design were overcome by incorporating suitable engineeringprovisions in the station design. It also included suitable considerations for construction

    schemes and sequence for the future development. Such considerations were documented

    and conveyed to the developer of future development, through a Development Interface

    Report (DIR) for his incorporation during design and construction of future development.

    For the design of CENTRAL, station design / deformation limitations were carefully

    studied and appropriate design parameters were suitably implemented in the analysis ofthe development. Deformation behavior of the station was monitored through an

    appropriate monitoring system. The resulting station deformations / settlements arewithin acceptable limits.

    References

    1) Integrated Planning and Development of Clarke Quay Station [Ong Gin Lip, PaulBroom]

    2) Clarke Quay MRT Station: Civil Engineering Challenges [G Pughazendhi, KMahmood, S Mahatma, P Broom and P Sebastian]