TRANSCRIPT
CP-42:Revenue Recognition Standard ASC606 Addressing the Standard in Costpoint
Andy Unwin, Deltek
Course Description
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 2
Description: Still trying to initialize your
ASC606 Revenue? Come and hear an
overview of the Revenue Standard, ASC
Topic 606. You won't want to miss this
session. We'll also talk about: A new
Revenue Evaluation and Disclosures
screen to help you track your progress with
evaluating your contract revenue. New
revenue formulas that have been added to
Costpoint 7.1.1. How to use your Project
structure and EAC to comply with ASC606
Objectives
By the conclusion of this session, you will be able to :
» Identify the options for complying with the new Revenue Recognition Standard.
» Identify the pros and cons of two distinct methodologies.
» Identify the role of EAC computations and ASC606.
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 3
Agenda» Part 1: Introduction
» Part 2: Where Do I Begin
» Part 3: The Alternate Database.
» Part 4: Project Structure and the
Performance Obligation Level.
» Part 5: Using EAC as an Effective Tool.
» Appendix: Supplemental Info
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 4
Part 1
» Introduction
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 5
BACKGROUND INFO» ASC606 has a core principle:
The recognition of revenue must depict the transfer of promised goods or services to customers in an amount that reflects the consideration to which the entity expects to be entitled in exchange for those goods and services.
» The five-step model for assessing the application of this principle includes:1: Identify the contract.2: Identify the performance obligation.3: Determine the transaction price.4: Allocate the transaction price.5: Recognize the revenue.
© 2019 Deltek, Inc. All Rights Reserved
Attribution: KPMG: Revenue Recognition Fundamentals, 2019
BACKGROUND INFO
© 2019 Deltek, Inc. All Rights Reserved
Attribution:
A&D = Aerospace and Defense Industries
Attribution: “The Coverged Revenue Recognition Model Has Landed”, 09/2/2014, Deloitte
CONFIDENTIAL © Deltek, Inc. All Rights Reserved.8
Attribution: “The Coverged Revenue Recognition Model Has Landed”, 09/2/2014, Deloitte
BACKGROUND INFO
© 2019 Deltek, Inc. All Rights Reserved
Attribution: A&D = Aerospace and Defense Industries
Attribution: “The Coverged Revenue Recognition Model Has Landed”, 09/2/2014, Deloitte
Part 2
» Where Do I Begin?
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 10
AS606: Considerations
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 11
» Not all companies are impacted by ASC606 in the same manner.
» The level of goods and services provided, plus the contract type will influence the your response as a company.
» For specific industries, there is quite a few write-ups on how to address the new standard.
» In Costpoint, traditional revenue recognition methodologies such as CPFF may not best meet the standard’s intent on both Fixed Price and Cost Plus contracts.
» Always consult with your professional auditors for final advice.
Performance Obligation Level
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 12
» As a result of this standard, the recognition of revenue may necessitate
establishing the revenue formula at a higher level of the Project [thereby
combining contracts together].
» The revenue level may different than the billing level.
» The use of EAC (Estimate at Completion) formula may be more common.
» Use of formulas associated with Funded Value may become more
commonplace that with Contract Value.
Part 3
The Alternate Database
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 13
The Alternate DatabaseIn this scenario, changes are NOT made to the
revenue recognition formula. Rather an alternate
profile is created for use in a distinct database and
the results are compared externally through the
use of reporting tool such as CER/Cognos.
© 2019 Deltek, Inc. All Rights Reserved
The Alternate Database: Configuration» Configuration of the Database in preparation for the deployment of the
“the Alternate Database”.
© 2019 Deltek, Inc. All Rights Reserved
The “Alternate Profile” may include different ceilings and BARN codes
The Alternate Database: Configuration» A different formula may be utilized. Historical data can also be changed.
© 2019 Deltek, Inc. All Rights Reserved
The Alternate Database: Configuration» Configuration of the Database in preparation for the deployment.
© 2019 Deltek, Inc. All Rights Reserved
The subtasks can store the new configuration that is only invoked when the
database is flagged as “ALTERNATE”.
The Alternate Database: Configuration
© 2019 Deltek, Inc. All Rights Reserved
The Alternate Profile is created in your Production environment.
Where Do I Begin…
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 19
» Carefully consider the options for the “Alternate Profile”.
» Define the new configuration parameters including revenue formula,
BARN codes, funded value, and PAG.
» Create a copy of the database environment.
» Flag it as “Alternate Revenue Calculations”.
» Activate the “Alternate Profile”.
» Run the normal revenue processing steps.
» Compare results with production environment.
Pros and Cons of this approach…
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 20
» Requires more Project setup.
» Necessitates the existence of another database.
» The alternate database will require ongoing refreshes.
» An external reporting tool such as CER is necessary to compare revenue
computation results.
» A whole another database may appear excessive when all we really need
another PROJ_SUM table.
» This approach requires technical support; not well received.
Part 4
» Project Structural Changes
The Performance Obligation Level
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 21
What You Need To Know…
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 22
» This option requires a re-examination of the existing Project Structure.
» Can the existing structure support a “Performance Obligation” level?
» Can an existing Project Level be repurposed?
» Is it practical to change the level associated with the Revenue formula?
» Can the revenue formula be changed?
» Would I recalculate the revenue in past years to see the impact of the
change in the revenue recognition methodology.
Configuration Item # 3: The “PYREV” Function Code.» Configuration: Modification of the Project Account Group (R&B PAG)
© 2019 Deltek, Inc. All Rights Reserved
Validation of Project Setup
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 24
Prior to modifying any revenue
computations…
Examine all elements of
Project Setup.
Exercise caution: Setup at
the inappropriate Project
level is a common error.
Validate proper usage of
“BARN” codes on ceiling
screens.
What Are Others Doing?
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 25
» External computation with a General Ledger entry only.
» Re-examination of Project Structure with changes for future Projects.
» Adoption of different revenue recognition formula and potentially
modifying the level where the formula resides.
Part 5
» Making Use of the EAC formula
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 26
Why Use EAC
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 27
Attribution: “The Coverged Revenue Recognition Model Has Landed”, 09/2/2014, Deloitte
Why Use EAC
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 28
Using the [Estimate At Completion] EAC formula, may better correlate with the
actual measurement of performance.
An external tool such as Cobra® or Primavera® may be utilized to derive the
proper EAC. Program Control personnel may be the best qualified to provide an
objective assessment.
Revenue recognition is then equated to performance as opposed to simply the
incurrence of cost.
Attribution: “The Coverged Revenue Recognition Model Has Landed”, 09/2/2014, Deloitte
How to Update EAC
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 29
Manually Update the EAC by way of:
Manage Revenue Info, or
Manage Revenue Formulas
An EAC is creating combining Actual and Budget.
» .
© 2019 Deltek, Inc. All Rights Reserved
How to Update EAC» .
© 2019 Deltek, Inc. All Rights Reserved
How To Update EAC» The “Revenue Integration” application takes the EAC and
pushes the number back into the Project Manage
Revenue Info application screen.
© 2019 Deltek, Inc. All Rights Reserved
Other Options…» Any other approaches may occur completely outside of Costpoint.
» Leveraging Costpoint, Planning, and the EAC formula may present the
best option for addressing ASC606.
CONFIDENTIAL © Deltek, Inc. All Rights Reserved.33
In Summary
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 34
Today we have covered:
ASC606 is an Accounting standard that ties the recognition of revenue
more closely to the delivery and acceptance of goods as opposed to the
traditional “matching” principle.
The “Alternate Revenue” profile could be leveraged, but it is difficult to
deploy due to multiple database upkeep.
EAC is typically more in compliance with ASC606; however, this may force
a change in revenue formula and level.
If you opt to change the Project – including the Revenue Formula and
Level, carefully follow checklist to make changes to revenue setup and
then reconcile. [See appendix]
Appendix
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 35
» Additional Information if you opt to restructure the Project.
» This content was also covered in our Session: “Revenue Re-Do”
» It is provided in case you were not able to attend this session.
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 36
Document the
“Before” View
PSR
Revenue
Worksheet
Revenue
Summary
PROJ_SUM
Rows
Change
Revenue
Formula*
* = Must be to any formula other than “Do Not Compute/NONE”
Designate
Current Fiscal
Year
PROJ_SUM
Cleared
Reset Revenue
Formula to
Appropriate
Designate
Current Fiscal
Year
Recalculate
Revenue:
Period 1 to
Current
Regenerate
Project Reports
PSR
Revenue
Worksheet
Revenue
Summary
PROJ_SUM
Rows
Reconcile
Results
Post Revenue
in Current
Period
Validate
Setup
1 2 3 4 5 6
7
What is “PROJ_SUM”…
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 37
» PROJ_SUM: the key table underlying the Project Ledger.
» It stores data by Project, Account, and Organization for Fiscal Year,
Period, and Sub-Period.
» It is a compressed view of transaction data from the General Ledger.
» Burden is stored at “Actual” and “Target” by Pool in the companion table
known as PROJ_BURD_SUM.
» PROJ_SUM is the basis for the computation of revenue.
» The Project Ledger is always reconciled back to the General Ledger.
Checklist: Revenue Reconciliation
© 2019 Deltek, Inc. All Rights Reserved
Step Application Screen Activity
1. Manage Revenue Info Examine the existing setup.
2. Post Revenue Validate that all postings are complete.
3. Reporting Processes Validate that all report tables are updated.
4. View Project Ledger Activity Look for revenue plugs above the formula level.
5. Project Status Report Examine the Year-To-Date Revenue number.
6. Project Revenue Summary Report Examine the Year-To-Date Revenue number.
7. Validation Do numbers from steps 5&6 tie?
8. Print Project Ledger Detail. Aggregate revenue numbers. Tie to steps 5&6.
9. Validation Are there revenue postings at multiple levels?
10. Validation Are there Journal Entry postings?
Checklist: Revenue Formula Change
© 2019 Deltek, Inc. All Rights Reserved
Step Application Screen Activity
1. Project Status Report Print out and retain PRIOR to making any changes.
2. Project Revenue Summary Report Print out and retain PRIOR to making any changes.
3. Revenue Worksheet Print out and retain PRIOR to making any changes.
4. Manage Revenue Information Select the new formula. Enter the Fiscal Year.
[Never select “None”.]
5. View Project Ledger Activity Validate that all revenue data is cleared for the year.
6. Project Settings Validate: prior period revenue calculations are allowed.
7. Accounting Periods Journal “SJR” Compute Revenue must be “Open”.
8. Compute Revenue Compute revenue for Period 1.
9. Compute Revenue Compute for each successive period till Period “n”.
10. Revenue Worksheet Validate the new revenue numbers.
11. Post Revenue Only post if the numbers look reasonable.
Checklist: Changing the Revenue Formula
Checklist: Revenue Formula Level
© 2019 Deltek, Inc. All Rights Reserved
Step Application Screen Activity
1. Project Status Report. Print out and retain PRIOR to making any changes.
2. Manage Revenue Information Select any formula other than “None”. Enter Fiscal Year.
3. View Project Ledger Activity Validate that all revenue data is cleared for the year.
If there are any revenue plugs at a higher level,
remedial action will be necessary!
4. Manage Revenue Information Delete the Revenue formula at the existing level.
5. Manage Revenue Information Set up the Revenue formula at the new level.
6. Project Settings Validate: prior period revenue calculations are allowed.
7. Accounting Periods Journal “SJR” Compute Revenue must be “Open”.
8. Compute Revenue Start with Period 1 through Current Period.
9. Journal Entries Reverse revenue from former level: Debit Revenue and
credit Unbilled Receivables.
10. Revenue Worksheet Validate Revenue.
11. Post Revenue. Only post if the numbers look reasonable.
Checklist: Revenue Level Change
Questions & Answers
CONFIDENTIAL © Deltek, Inc. All Rights Reserved. 41
For further discussion or questions, schedule an appointment at”
“Meet the Experts”