cover of drilling machine - via bowling...

30
VIA BOWLING DRILL ING MACHINE File No.: M2007016-01 COPYRIGHT 2007, VIA BOWLING PRODUCTS

Upload: others

Post on 02-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

VIA BOWLING DRILL ING MACHINE

File No.: M2007016-01

COPYRIGHT 2007, VIA BOWLING PRODUCTS

Page 2: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

Contents I. Safety precautions······································································ 2 II. Major functions and application scope········································· 4 III. Technical parameters·································································· 4 IV. Hoisting and installation······························································ 5 V. Major structure and working principle·········································· 5 VI. Transmission system·································································· 8 VII. Bearings··················································································· 10VIII. Electric system·········································································· 10IX. Commissioning and operation··················································· 14X. Accessories················································································ 17XI. Maintenance and adjustment ······················································ 24XII. Trouble analysis and trouble shoot ··································· ···· 25 XIII. Drilling machine explosive diagram and breakdown table············· 26

Page 3: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 2 -

Thank you for using VIA Bowling Ball drilling machine, which is designed to

drill holes on the Bowling Ball to suit different finger sizes. Please do carefully read this user instruction before the use of this drilling machine to ensure your safe and correct operation, and maintain your drilling machine under good working conditions for long time. I Safety precautions

1. Please carefully read this user instruction to get detailed knowledge on the drilling machine structure and performance and thereby avoid the potential risks.

2. Before the installation of the drilling machine, please check whether those parameters such as voltage etc. indicated on the motor nameplate are in conformity with the voltage on the site.

3. All contact points on the drilling machine power supply connectors should be reliable without such inferiority phenomena as being loosened or no contact.

4. It’s not allowed to pull the power supply cable which is connected on the socket with great force, and keep the power cable away from high temperature, oil and sharp edges.

5. Drilling machine power supply shall be equipped with reliable grounding.

6. In case of drilling machine failure, power supply shall be cut off immediately. Ensure the drilling machine is not connected with the power supply during its inspection and maintenance.

7. During drilling machine working or repair & commissioning, appropriate protection method shall be provided around its surrounding.

8. Before the drilling machine starts, take off the foreign materials on the drilling machine.

9. Working area shall be kept clean, and no use of drilling machine is allowed in unclean, moist, dark, dusty, combustible and explosive locations.

Page 4: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 3 -

10. Children are not allowed to have access to the drilling machine at any time, and all visitors shall be kept outside the safety distance.

11. The operation of the drilling machine requires high attention and focus, and therefore no operation thereof is allowed after drinking alcohol or being at fatigue status.

12. The drilling machine is not allowed to operate at overload and failure status, in order to avoid the occurrence of accident.

13. Those people who enter the working site must wear appropriate labor protection articles, and long hair shall be swirled and put into the working hat. It’s not allowed to operate the drilling machine with gloves.

14. The drilling machine shall be maintained on regular basis to ensure normal operation of each component. The drilling machine shall be put vertically upward, and it CANNOT be laid down and/or put in an inclined way.

15. Before the connection of power supply, it’s required to check the power supply switch and ensure it’s in OFF position.

16. In case of drilling machine failure, please repair as per the “Trouble Analysis and Troubleshoot” as indicated herein. Should there be a need of replacing spare parts and accessories, please use our company produced and recommended spare parts and accessories.

17. Before the use of the drilling machine, please carefully inspect the wearable positions of the drilling machine, so that it facilitates the timely handling.

18. Before the operation, lock the handles, cutting tools, tool fixtures on the drilling machine, which should be locked. The Bowling Ball should be fixed properly and reliably.

Page 5: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 4 -

II Major Use and Applicable Scope The drilling machine is designed to drill holes on the Bowling Ball to suit the different finger sizes. With the support of appropriate accessories, this drilling machine can be used for single ball or batch production processing of finger holes. III Technical parameters

     ≤Φ35m m

130m m

M T 3

12-level speed contro l

590m m

202.5m m

Φ115m m

730x210m m

Four-pole 1.5Kw

1050x1010x1230m m

340Kg/295Kg

M otor M otor speed (r/m in) M ain shaft speed(r/m in) Voltage (v) F requency

(H z)

96, 157, 187, 233,305, 359, 645, 869,997, 1239, 1479 and2107

220 50/60

115,191,225,276,368,432,772,1045,1192,1489,1774 and 2528

110 60

413/8x393/4x483/8 inch

340Kg/295Kg

≤Φ 1 3/8 inch

5inch

M T 3

12-level speed contro l

23 inch

8inch

4 1/2 inch

28 3/4x8 1/4 inch

Four-po le 1.5Kw

M axim um drilling hole d iam eter

M ain shaft m ax im um travel

M ain shaft tapered hole degree

M ain shaft speed level num ber

Y90L-4 1400

M axim um d is tance between m ain shaftend and work ing tab leD istance between m ain shaft center andstand co lum n surface

S tand co lum n d iam eter

M otor/power rate

O uts ide d im ension (length x w idth x he ight

G ross weight/net we ight

M otor configuration and speed

W ork ing tab le s ize (length X w idth)

Page 6: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 5 -

IV Hoisting and installation ① Hoisting This machine is packed with wooden box, and therefore the user has to pay attention to following issues during the hoisting:

1) Remove the base plate bolts before hoisting; 2) During the hoisting, ensure the main shaft box is at upfront direction

and at locked status; 3) Before hoisting, the contact surface of the drilling machine at both

sides will be filled up with soft material to avoid the damage on the paint;

4) Attention will be paid to drilling machine gravity during hoisting, to ensure the stable hoisting and transfer of the drilling machine;

② Installation and positioning Please use the bolts to directly install and fix the drilling machine on the machine frame. When the drilling machine is put on the ground base, please adjust the adjustable steel pad on the base to make the drilling machine working table at level position. V Major structures and working principle ① Major structures

This drilling machine structure includes below components (as indicated in Diagram 1):

1)Electric control system; 2) Motor; 3)Main shaft box; 4)Magnetic measuring digital

display; 5) Bowling Ball drilling fixtures; 6) Drill bits storage table; 7) Working table; 8)

Inverter transmission system; 9) Main shaft precise feeding device; 10) Working

table light; 11) Stand column base plate component; 12) Machine frame

Page 7: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 6 -

1 Electric control system

12Machine frame

11 Stand column baseplate component

7 Working table

8 Inverter transmission system

2 Motor

6 Drill bits storage table

4 Magnetic measuring digital

5 Bowling Ball drillingfixtures

9 Main shaft precise eeding device

f 3 Main shaft box

Drill bits storage table

10 Working table light

Page 8: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 7 -

Inverter transmission system Main shaft feeding device

(Diagram I) Drilling machine main structures diagram

② Working principle

1) Major cutting motion-main shaft rotation working principle

Main shaft rotation motion is powered by motor input via multiple

levels of belt transmission and inversion, which ultimately drives the

main shaft.

2) Feeding motion working principle

Main shaft feeding motion is realized by manually driving the rack on

main shaft sleeve through force amplifier and gear shaft. Additionally,

there is a precise feeding device to control and improve the

processing precision.

3) Main shaft box lifting device working principle

As regards the lifting device installed on the main shaft box, manually

rotate the worm, which will drive the angular gear, and the

counterforce arising from the rolling of angular gear along the rack

(axially fixed on the stand column) will drive the main shaft box to go

UP or DOWN.

4) Main shaft sleeve fixed-travel feeding working principle

It can be divided into rough travel fixing and precise travel fixing as

Page 9: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 8 -

per the precision of the travel fixing. During the rough travel fixing, the

finger will point to the scale line on the nameplate with the minimum

feeding unit of “1mm”; whilst the precise travel fixing is adopting the

worm and worm gear principle to drive the motion of the main shaft

sleeve with the minimum unit of “0.05mm”.

VI Transmission system

① Major transmission system;

The major transmission system of the drilling machine adopts belt

auxiliary transmission and spline auxiliary transmission. Its transmission

route is: motor→belt wheel→spline sleeve→main shaft. When 1.5Kw

1400r/min motor is used as the power source, 12-level inversion

transmission can be achieved by changing the position on triangle

rubber belt pulley. The way to change the speed is: firstly cut off the

power supply, and then open two hasps on the side of the cover; open

the cover, loosen the vane screws, and push the motor toward the main

shaft box. After regulating the triangle rubber belt, push out the motor to

tighten the triangle rubber belt, tighten the vane screws, close the cover

and lock the hasps (Speed indication plate is attached inside the cover).

Attention:

Power supply MUST be cut off during the change of speed!

② Main shaft feeding device is divided into two types:

1)Direct feeding: The feeding handle fixed on the gear shaft will

directly drive the main shaft feeding, where one circle rotation of the

handle leads to the main shaft travel of 88mm.

Page 10: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 9 -

2)Precise feeding: The main shaft feeding handle will drive the main

shaft feeding driven by gear shaft via tapered clutch, where one circle

rotation of the main shaft handle leads to the main shaft travel of

2.5mm.

③ Lifting transmission system:

Its transmission route is: rocker→worm→angular gear→rack.

④ Working table feeding is realized by lead screw driven by the handle,

where one circle rotation of handle wheel leads to the working table

travel of 2.5mm.

Page 11: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 10 -

VII Bearings Breakdown list of bearings

No. Installation position Name Installation size(mm)

Qty. Model

1 Main shaft belt pulley Radial ball bearing 45x75x16 2 6009-2Z

2 Main shaft sleeve Tapered roller bearing 35x72x18 1 30207

3 Main shaft sleeve Tapered roller bearing 30x62x17 1 30206

4 Main shaft feedingworm gear Radial ball bearing 15x35x11 2 6202-2Z

5 Middle belt pulley Radial ball bearing 20x47x14 2 6204-Z

6 Y lead worm Radial ball bearing 17x30x9 2 8103

7 X lead worm Radial ball bearing 17x30x9 2 8103

VIII Electric system The voltage for this drilling machine electric system main circuit, control

circuit and socket is single-phase AC220V, 50/60HZ, or AC110V, 60HZ

at the capacity of 3.5KW; Illuminating circuit voltage is AC24V, and the

power rate is 35W.

① General power supply, switch and precautions

a. Before the use of the drilling machine, the power supply will be

introduced into the drilling machine as required in electric

principle diagram (please refer to Diagram II; the recommended

size for power supply cable is as follows. 110v: 3x6mm2; 220v:

3x4mm2 ). Connect the switch inside the electric box, and the

power supply will be connected to the drilling machine, where

the white power indicator light on the operation faceplate is ON,

and the drilling machine is at General OFF status.

b. Before the start, the drilling machine shall be equipped with

Page 12: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 11 -

reliable grounding. Please carefully inspect whether different

operation parts on the drilling machine is at original position.

c. Reset the red urgent stop button; this button is urgent stop

button, and press this button in urgent conditions, the drilling

machine will stop; it’s required to reset this button in case of

restart of the drilling machine, otherwise it cannot start the

machine.

d. Green button is the “Start” button, and press this green button,

the drilling machine starts working.

e. The black button is the “STOP” button, and after press this

button, the drilling machine stops.

f. As for the drilling machine with vacuum pump- black knob is

ON/OFF switch, where “OFF” position indicates Switch-off and

“ON” position indicates Switch-on.

g. Turn on the switch of the working lamp on the drilling machine,

and the light will be ON; turn off this switch, and the light will be

OFF.

h. During such non-cutting process as cutting tool change, travel

adjustment of installation Bowling Ball etc., please DO make the

drilling machine at General OFF position, to avoid unnecessary

injury or damage.

Before start the drilling machine, it’s required to ensure the safe and reliable grounding of the drilling machine!

Page 13: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 12 -

② Drilling operation

Press the green button, the drilling machine main shaft rotates, and it

can realize the drilling operation. Press the black button, it can stop

the drilling machine main shaft rotation.

③ Drilling machine socket

This drilling machine is equipped with two standard sockets, including

one three-pole socket at the capacity of 1.5KW, and another

two-pole socket at the capacity of 0.5KW, which are both indicated

with the labels. Please pay attention to the right use of them, to

avoid the damage. Attention: In case of urgent and accidental conditions during the

use, press the red Urgent Stop button, and the drilling machine will

stop the working immediately (please note that this drilling machine

socket is still connected with power supply)

Page 14: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 13 -

Electric principle diagram

(Diagram II) Electric diagram

主轴电动机

QF 50A

空气开关 变 、电源指示灯三

插 座真 空 泵

Y90L-4 1.5KW

(带热保护)

压器/照明 孔

主轴电机启/停 两

Y90L-4 1.5KW

(带热保护)

主轴电机启/停主轴电动机 变压器/照明、电源指示灯空气开关三 孔

插 座

两 孔

插 座

switch Main shaft motor

Vacuum pump

Three-pole socket

Two-pole socket

Main shaft motor

ON/OFF

Transformer/illuminating and power indicator

light

switch Main shaft motor

Three-pole socket

Two-pole socket

Main shaft motor

ON/OFF

Transformer/illuminating and power indicator

light

Page 15: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 14 -

IX Commissioning and operation ① Commissioning (please refer to Diagram III)

1) Lifting of the main shaft box Loosen the locking bolts on the main shaft box, rock the lifting handle to

let the main shaft box go UP or DOWN to the needed position, and then tighten the bolts.

Motor

Frame

Cover

Locking bolt

Lifting handle

Stand column

Main shaft

Clamping handle

Operation faceplate I Operation faceplate II (Without vacuum pump) (With vacuum pump)

Diagram III Commissioning indication diagram

Page 16: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 15 -

2) The rotation of main shaft box Loosen two locking bolts on the main shaft box, and the main shaft box can rotate around the stand column (generally it’s not allowed to rotate to the back of the main shaft); rotate it to the needed angle, and then tighten the locking bolts.

3) Adjustment of the main shaft speed During the adjustment of the main shaft speed, let the drilling machine

exit the working status (the main shaft stops rotating), and cut off the power supply; then open the cover, and adjust the belt to the correspond position as indicated on the speed plate; after the adjustment is completed, it’s required to close the cover and then connect the power supply; after that, start the drilling machine, and it will resume the normal operation. ② Operation precautions

1)Before the operation 1.1. Please carefully read this user instruction to get the detailed

knowledge on drilling machine structure, performance and operation procedure.

1.2. Add the lubricating oil as indicated on drilling machine lubrication diagram. Check whether the main shaft box clamping, main shaft sleeve lifting and electric system are safe and reliable. In case of abnormalities, cut off the power supply before the maintenance and repair.

1.3. Make sure there is no foreign materials on the working table, and the fixtures are installed properly and workpiece is clamped tightly and reliably.

1.4. Make sure the main shaft speed is proper, and the cutting tool is installed reliably.

2)During operation 2.1. In order to avoid the drilling machine damage, please use the drilling machine in accordance with the required use. 2.2. During the operation of the drilling machine, it’s not allowed to put

Page 17: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 16 -

hands close to the cutting tools, and no operation with gloves will be permitted.

2.3. The operator will not be allowed to leave the drilling machine during the working, neither allowed to do unrelated things.

3)After the operation 3.1. Cut off the power supply, remove the tools and clean the drilling

machine. 3.2. Add the lubricating oil, and cover the drilling machine with anti-dust

cover. ③ Operation

1) Before the start of the drilling machine, inspect whether the main shaft box is clamped on the stand column, and whether the main shaft sleeve lifting and electric system is at normal condition; install the working table feeding handle base into the head screw end, and screw the handle into the handle screw.

2) In order to avoid the damage to the drilling machine, the drill bit maximum diameter is ≤Φ35mm(1 3/8 inch).

3) Before adjustment of height of main shaft box (UP or DOWN), loosen two locking nuts, rotate the UP/DOWN handle of the main shaft box to lift the main shaft box to the needed position; then tighten two locking nuts, and ensure the main shaft box is tightly clamped on the stand column.

4) During drilling holes, rotate the handle to detach the worm and handle base, and it permits the drilling and milling of general holes. If there is a requirement on the depth of the drilled hole, the fixed-depth cursor can be adjusted to the needed position before the drilling of the hole.

5) If the drilling machine has trouble or gives off abnormal sound during its working, the power supply will be cut off immediately, and inspect the trouble cause and eliminate such trouble.

Page 18: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 17 -

X Accessories When you open the box, please carefully check the drilling machine accessories, and put them back to the accessory box after the check is completed. Please carefully take and put back the accessories during the check in order to avoid the damage to the accessories.

1. Accompanied accessories (please refer to Diagram IV)

(Diagram IV) Accompanied accessories

Tension rod Sleeve Drift

Reduction sleeve

Connecting rod Feeding handle bar

Little handle

Self-lock chuck Centering bar

Fixture center calibratingAdjusting pad Clutch handle pulley

Wrench Lifting handle Uni-key

Page 19: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 18 -

No. Name and size Qty. Part No.

1 Tension rod 1 BLZ-01-001

2 Sleeve 1 BLZ-01-002

3 Drift 1 BLZ-01-003

4 Feeding handle bar 3 BLZ-01-004

5 Reduction sleeve 1 BLZ-01-005

6 Connecting bar 1 BLZ-01-006

7 Self-lock chuck 1 BLZ-01-007

8 Small handle pulley 1 BLZ-01-008

9 Centering bar 1 BLZ-01-009

10 Fixture center calibratingblock 1 BLZ-01-010

11 Adjusting block 1 BLZ-01-011

12 Clutch handle pulley 3 BLZ-01-012

13 24mm wrench 1 BLZ-01-013

14 Lifting handle 1 BLZ-01-014

15 Uni-Key(4/5/6mm) 1 Set BLZ-01-015

2. Special tools

1) Hole grinder

Hole grinder is designed to grind the drilled finger holes and

chamfering on the hole wall, with which the hole will be smooth

without sharp angles and burrs.

The operation steps for hole grinder:

1.1. Rotate the Bowling Ball with drilled holes to the appropriate angle,

or put it at the right position, and then the operator will put the electric

grinder into the finger hole of the Bowling Ball;

Page 20: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 19 -

1.2. The operator presses the hole grinder switch, and the electric

grinder starts;

1.3. The operator will grind the hole mouth at an inclined way, along with the

assistant grinding of the hole inside wall;

Grind the finger hole to the stipulated requirements; when the hole

mouth and inside wall is smooth without burrs, the operator presses the

grinder switch, and the electric grinder will turn off; the operator will take

out electric grinder from the finger hole.

●●● Safety protection articles: The operator must wear the goggle.

Safety articles such as anti-dust mask, anti-skid safety shoes, safety hat and hearing protection etc. at proper conditions will reduce the personal injury;

●●● Avoiding the abrupt start: Make sure it’s in OFF position when the plug is inserted into the socket;

●●● Don’t stretch the arm too much: Pay attention to the ground under the foot and body balance from time to time. With that, it can easily control the electric tool;

●●● In case of damage arising from moisture or accidental fall, or natural wear and damage after long-time use, it will be repaired by professional personnel, and can be reused after qualified insulation examination.

2) Vacuum machine Vacuum machine is designed to suck the drilling scraps into the vacuum machine when the drilling machine is drilling the hole so as to improve the operator working environment.

Use method: start the vacuum machine, and point the suction mouth to the drill bits.

Page 21: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 20 -

Don’t suck any smoky or burning articles into the vacuum machine, such as cigarette, match, and hot cigarette ash etc.; Don’t suck any sharp articles such as head pin and

blade etc. into the vacuum machine; Don’t suck any combustible liquid into the vacuum

machine, such as gasoline; don’t use the vacuum machine in the location where there is combustible liquid is present;

3) Drill bits storage table Drill bits storage table is designed for the storage of drill bits for

different Bowling Ball finger hole sizes so as to facilitate the operator processing operation. Installation and use:

3.1. Put the fixture into two T-shaped grooves of the working table with four T-shaped bolts to make preparation for the bowling fixture installation;

3.2. Fix the drill bits storage table on the drilling machine working table with T-shaped nuts and countersunk screws;

3.3. According to the drill bits outside diameter size indicated on the storage table, insert the drill bits into the corresponding hole positions on the storage table.

4) Magnetic measuring digital display

Use of magnetic measuring digital display: please refer to annex M-10 Operational Manual.

Page 22: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 21 -

5)Drill bits Drill bits breakdown table (1 piece respectively)

No. M etric size

(mm)SAE fraction

size (inch)SAE decimal

size (inch) No. M etric size(mm)

SAE fractionsize (inch)

SAE decimalsize (inch)

1 12.700 1/2 0.500 20 21.412 27/32 0.843

2 13.487 17/32 0.531 21 21.819 55/64 0.859

3 14.275 9/16 0.562 22 22.225 7/8 0.875

4 15.062 19/32 0.593 23 22.606 57/64 0.890

5 15.469 39/64 0.609 24 23.012 29/32 0.906

6 15.875 5/8 0.625 25 23.393 59/64 0.921

7 16.256 41/64 0.640 26 23.800 15/16 0.937

8 16.662 21/32 0.656 27 24.206 61/64 0.953

9 17.043 43/64 0.671 28 24.587 31/32 0.968

10 17.450 11/16 0.687 29 24.994 63/64 0.984

11 17.856 45/64 0.703 30 25.400 1 1.000

12 18.237 23/32 0.718 31 25.781 1 1/64 1.015

13 18.644 47/64 0.734 32 26.187 1 1/32 1.031

14 19.050 3/4 0.750 33 26.568 1 3/64 1.046

15 19.431 49/64 0.765 34 26.975 1 1/16 1.062

16 19.837 25/32 0.781 35 27.762 1 3/32 1.093

17 20.218 51/64 0.796 36 28.575 1 1/8 1.125

18 20.625 13/16 0.812 37 31.750 1 1/4 1.250

19 21.031 53/64 0.828 38 34.925 1 3/8 1.375

6)Bowling Ball drilling fixtures

(Diagram V )Press-type drilling fixture (Diagram VI) Tray-type drilling fixture

Page 23: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 22 -

This drilling machine is equipped with two kinds of drilling fixtures for use

option: press cover type drilling fixture and tray-type drilling fixture, which

can fix the Bowling Ball at different angle to realize the drilling and milling

processing of different finger holes. 6.1. Press cover type drilling fixture (please refer to Diagram V)

6.1.1. Installation of press cover type drilling fixture: The press cover type drilling fixture will be fixed above the drill bits

storage table, put the drill bits storage table to the corresponding

positioning bolts on the fixture base, and then screw in the nuts;

meanwhile adjust the fixture direction to make it parallel to the working

table, and finally tighten the nuts;

Move X-direction dragging plate and Y-direction dragging plate

to make the calibrating fixture center in line with main shaft

center, and meanwhile set the magnetic measuring scale at 0 at

both X-direction and Y-direction;

6.1.2. Press cover type drilling fixture use: Remove the press cover, and put the Bowling Ball into the

fixture storage base tray;

Cover the press cover to make the two positioning slots on the

press cover clamp on corresponding stud bolts, and tighten the

handle;

Rotate the bolts at right and left sides into the positioning slots at two sides

of the press cover, and tighten the handle to press and fix the Bowling Ball;

Inspect and ensure the Bowling Ball is clamped reliably, and

start the drilling processing after it’s clamped at pre-designed

position;

4As per finger hole technical requirements, loosen X-direction

tightening blocks at both sides, and rotate around X-direction

and move to the required position; tighten the tightening blocks

at both sides, and then conduct following finger hole drilling and

Page 24: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 23 -

milling processing.

6.1.3. Maintenance of press-cover type drilling fixtures: Maintain the fixture surface clean and free of dust;

Ensure the fixture surface coating has no drop-off phenomenon;

if glue drop-off is discovered, please use the adhesive to stick

the surface coating completely and reliably; or in case of

replacement of surface coating, it will be redrilled and

reprocessed;

6.2. Vacuum tray-type drilling fixture (please refer to Diagram VI) 6.2.1. Installation of vacuum tray-type drilling fixture: After the vacuum tray-type drilling fixture is fixed at corresponding position

above the drill bits storage table, put the drill bits storage table in alignment with corresponding positioning bolt locations on fixture base, screw in the screws, meanwhile adjust the fixture air pipe connector position to make it parallel to the right side of X-direction of drilling machine, and finally tighten the nuts; Move X-direction dragging plate and Y-direction dragging plate

to make the calibrating fixture center in line with main shaft center, and meanwhile set the magnetic measuring scale at 0 at both X-direction and Y-direction;

6.2.2. Use of vacuum tray-type drilling fixture: Connect the power supply, and start the vacuum pump; Clean the fixture tray, and make it clean and free of foreign

materials;

Rotate the Bowling Ball to the needed position, and carefully put

it on the tray fixture;

Rotate the knob to the suction position, and suck the air inside

the tray fixture to the vacuum to fix the Bowling Ball reliably on

the tray fixture;

Inspect and confirm that Bowling Ball is sucked reliably and at

Page 25: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 24 -

pre-designed position, and then conduct following drilling and

milling processing;

6.2.3. Maintenance of vacuum tray-type fixture: Ensure the roundness and completeness of the fixture, and the

edge of the tray is smooth without defects;

If the vacuum pump filter is blocked, please clean the internal filter

core or replace it with a new filter core;

XI Maintenance and care ① Daily maintenance (operator)

1) Before use of the drilling machine, add the lubricating oil at each

lubricating point (mainly at oil adding cup).

2) In case of discovery of main shaft over-temperature or abnormal sound

during the use of drilling machine, stop the machine immediately for

inspection and Troubleshoot.

3) Maintain the working site clean and tidy. After the work is

completed, remove all kinds of fixtures, cutting tools and Ball etc.

from the drilling machine, clean the wastes, and add the

lubricating oil before the anti-dust cover is covered.

② Weekly maintenance Inspect whether such lubricating surface and moving components as

stand column and sleeve etc. are lack of lubrication, and it will be supplemented on a timely basis in case of insufficient lubrication.

③ Monthly maintenance 1) Lubricate bearings, worm gears, angular gear and rack. 2) At least once inspection of whether cable and connectors are

loose or worn in each month. ④ Annual maintenance: adjust the levelness of the working table to

ensure the precision.

Page 26: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 25 -

XII Trouble analysis and Troubleshoot

Troublephenomenon Cause analysis Troubleshooting method

Bowling ballmispositioning

Workpiece is notclamped tightly Clamp the workpiece tightly

1. Main bearing failure Replacement of bearing2. Drill bits are notinstalled at pre-designedposition

Install the drill bits at pre-designed position

Main shaftrestoration instable

Insuitable tightness ofscroll spring

Adjust the scroll springtightness

1. Prick handle or prickhole has foreignmaterials

Wipe off foreign materialswith clean cloth

2. No-matching of prickhandle model

Adopt the reduction sleeve formatching

Cutting tool drop-off

Drilling hole out oftolerance

Page 27: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 26 -

1

2

3

4

5 6

4

7

89

11

12

13

14

15

1617 18

20(4)

19

21(4)22

23

24(4)

25 26(2)

2728

29

30

3134

35

36

37

38

39

40

414243

44

45

4647

48

49

50

5152

53

5455

5657

5859

60

61

64

63 62

65

66

6768

69

7071

7273(2)

7475

76 77

78(3)

79(3)

80

81(2)

8283828485

8687

88

89 90

91(2)92(2)

93(2)94

95 9697

98(4)

99 100

101(2)

102

103

104

105106

107

10

3233

XIII Drilling machine explosive diagram and breakdown table 1. Main shaft box explosive diagram

Page 28: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 27 -

2. Main shaft box components

No. Name Number No. Name Number1 Nut BLZ-02-001 37 Cover plate BLZ-02-037

2 Pulley BLZ-02-002 38 Upper cover plate BLZ-02-038

3 Spline cover BLZ-02-003 39 Normal V-belt B-838 BLZ-02-039

4 Bearing 6009-2Z BLZ-02-004 40 Normal V-belt B-1016 BLZ-02-040

5 Isolating ring BLZ-02-005 41 Nut M16 BLZ-02-041

6 Screw M8x12 BLZ-02-006 42 Block ring Φ47 BLZ-02-042

7 Main shaft BLZ-02-007 43 Bearing 6204-Z BLZ-02-043

8 Nut M30x1.5 BLZ-02-008 44 Middle belt pulley BLZ-02-044

9 Gasket Φ35 BLZ-02-009 45 Middle belt pulley shaft BLZ-02-045

10 Bearing 30206 BLZ-02-010 46 Nut M16 BLZ-02-046

11 Main shaft sleeve BLZ-02-011 47 Bolt M8x30 BLZ-02-047

12 Pad BLZ-02-012 48 Gasket Φ8 BLZ-02-048

13 Bearing 30207 BLZ-02-013 49 Belt pulley support BLZ-02-049

14 Bearing cover BLZ-02-014 50 Lower cover BLZ-02-050

15 Feeding base BLZ-02-015 51 Angular gear shaft BLZ-02-051

16 Nut M6 BLZ-02-016 52 Angular gear BLZ-02-052

17 Gasket Φ6 BLZ-02-017 53 Worm rod BLZ-02-053

18 Bolt Zn.DM6x50 BLZ-02-018 54 Wrom rod support BLZ-02-054

19 Ruler BLZ-02-019 55 Screw M6x16 BLZ-02-055

20 Screw ST2.9-9.5 BLZ-02-020 56 Lifting handle BLZ-02-056

21 Screw ST2.9-9.5 BLZ-02-021 57 Oil cup Φ6 BLZ-02-057

22 Name plate BLZ-02-022 58 Littlehandle BLZ-02-058

23 Front cover plate BLZ-02-023 59 Gasket Φ6 BLZ-02-059

24 Screw M6x8 BLZ-02-024 60 Gasket Φ8 BLZ-02-060

25 Knob BLZ-02-025 61 Spring cover BLZ-02-061

26 Flexible pin 3x18 BLZ-02-026 62 Worm spring BLZ-02-062

27 Positioning sleeve BLZ-02-027 63 Screw M5x16 BLZ-02-063

28 Nut M16 BLZ-02-028 64 Pin 3x10 BLZ-02-064

29 Fixing nut BLZ-02-029 65 Bearing BLZ-02-065

30 Adjusting bar BLZ-02-030 66 Oil cup Φ6 BLZ-02-066

31 Constant distance stopper BLZ-02-031 67 Clamp handle BLZ-02-067

32 Adjusting rod nut BLZ-02-032 68 Clamping block BLZ-02-068

33 Screw M4x16 BLZ-02-033 69 Thread tightening block BLZ-02-069

34 Indicating plate BLZ-02-034 70 Gear bearing BLZ-02-070

35 Screw M4x8 BLZ-02-035 71 Key 8x22 BLZ-02-071

36 Round cover BLZ-02-036 72 Feeding device base BLZ-02-072

Page 29: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 28 -

No. Name Number No. Name Numb

73 Screw M8x16 BLZ-02-073 91 Bolt M16x150 BLZ-02-091

74 Worm BLZ-02-074 92 Gasket Φ16 BLZ-02-092

75 Spring 2x16x25 BLZ-02-075 93 Nut M16 BLZ-02-093

76 Handle base BLZ-02-076 94 Locking handle component BLZ-02-094

77 Big handle BLZ-02-077 95 Spring 1.4x12x80 BLZ-02-095

78 Straight handle bar BLZ-02-078 96 Tension pin BLZ-02-096

79 Elipse handle cover BLZ-02-079 97 Rubber sleeve BLZ-02-097

80 Feeding worm rod BLZ-02-080 98 Bolt M8x25 BLZ-02-098

81 Screw M5x16 BLZ-02-081 99 Gasket Φ8 BLZ-02-099

82 Bearing 6202-2Z BLZ-02-082 100 Nut M8 BLZ-02-100

83 6202 bearing block ring BLZ-02-083 101 Bolt M12x20 BLZ-02-101

84 End cover BLZ-02-084 102 Motor frame BLZ-02-102

85 Main shaft feeding scale plate BLZ-02-085 103 Motor Y90L-4 BLZ-02-103

86 Connecting sleeve BLZ-02-086 104 Motor key BLZ-02-104

87 Little handle pulley 12x100 BLZ-02-087 105 Screw M6x10 BLZ-02-105

88 Little handle M6x40 BLZ-02-088 106 Motor belt pulley BLZ-02-106

89 Screw M5x10 BLZ-02-089 107 Tension rod BLZ-02-107

90 Screw M5x10 BLZ-02-090

er

37

38

1213

16

39

23

919

2025

14 15 40

35(2)28(2)

41

42

43

45(2)

46(2)

3(2)

1

2

3(2)45

6(2)

7(2)8(2)

910

11

1213

14

15

1617

189

19(2)20(2)

21

22

22

923 19

2025

24

16

26

15

14

27

2829

30

30(2)

31(2)31

32(2)

33

34 28(2)35(2)

34

22

22

36

44

Page 30: Cover of Drilling Machine - via bowling productsviabowlingproducts.com/admin/uploadfile/m200716.pdf · 2010. 3. 23. · Title: Microsoft Word - Cover of Drilling Machine Author: AA

User Instruction for Bowling Ball Drilling Machine

- 29 -

No. Name and size Number No. Name and size Number

1 Guard plate BLZ-03-01 24 Scale plate BLZ-03-24

2 Guard plate fixed piece BLZ-03-02 25 Screw M5x12 BLZ-03-25

3 Bolt M8x12 BLZ-03-03 26 Right hand claw clutch BLZ-03-26

4 Guard plate connecting piece BLZ-03-04 27 Screw M8x50 BLZ-03-27

5 Working table BLZ-03-05 28 Gasket Φ8 BLZ-03-28

6 Nut BLZ-03-06 29 Sliding saddle BLZ-03-29

7 Stop block BLZ-03-07 30 Lock handle component BLZ-03-30

8 Screw M6x14 BLZ-03-08 31 Steel ball Φ6.5 BLZ-03-31

9 Oil cup Φ6 BLZ-03-09 32 Bolt M8x12 BLZ-03-32

10 Right hand screw mandrel BLZ-03-10 33 Stop plate BLZ-03-33

11 Right hand screw mandrel nut BLZ-03-11 34 Screw BLZ-03-34

12 Gasket Φ5 BLZ-03-12 35 Screw M8x25 BLZ-03-35

13 Screw M5x12 BLZ-03-13 36 Upper saddle BLZ-03-36

14 Rotating handle BLZ-03-14 37 Lower saddle BLZ-03-37

15 Handle pulley BLZ-03-15 38 Left hand screw mandrel nut BLZ-03-38

16 Pin 5x35 BLZ-03-16 39 Left hand screw mandrel BLZ-03-39

17 Zinc coat steel plate BLZ-03-17 40 Bottom base BLZ-03-40

18 Left hand claw clutch BLZ-03-18 41 Stand column cover BLZ-03-41

19 Pin 8x24 BLZ-03-19 42 Ring BLZ-03-42

20 Screw M8x20 BLZ-03-20 43 Rack BLZ-03-43