countries: burundi and tanzania - afdb.org · with tanzania, the road provides ... the decree-law...
TRANSCRIPT
1
Language: English
Original: English
PROJECT: MULTINATIONAL: RN3: RUMONGE – RUTUNGA -
BUJUMBURA SECTION [77.6 km] AND KABINGO –
KASULU – MANYOVU [300.1 km] ROAD UPGRADE
PROJECT
COUNTRIES: BURUNDI AND TANZANIA
ESIA SUMMARY FOR THE PROPOSED UPGRADING OF RUMONGE-BUJUMBURA
SECTION (77.6km) -BURUNDI.
Date: July 2018
Preparation
Team
Team Leader: J. NDIKUMWAMI, Senior Transport Engineer, PICU.1/COBI
Co-Team Leader: J. B AGUMA, PRINCIPAL Transport Economist, RDGE.4
P. KANYIMBO, Regional Integration Coordinator, RDGE0
E&S Team Members:
P. HORUGAVYE, Chief socio-economist, RDGC4 /SNSC
F. KAYIGAMBA, Environmental expert, Consultant SNSC
E.B. KAHUBIRE, Social Development Officer, RDGE4 /SNSC
2
1. INTRODUCTION
The rehabilitate and upgrading of the Bujumbura – Rutunga – Rumonge road (78km) section project road
is part of EAC Class No. RN3 along RTRN Corridor EA 5 connecting Tanzania and Burundi (Tunduma –
Sumbawanga – Kigoma – Mugina – Nyanza Lac – Bujumbura Corridor).
The project is being implemented by EAC through Burundian Office of Roads (Office des Routes – OdR).
OdR, under the Ministry of Transport, Public Works, and Equipment is the roads authority of Burundi. The
importance of the project road lays on the fact that apart from linking Burundi with Tanzania, the road
provides transportation route for agricultural and mining produce to and from the Great Lakes countries
in particular the eastern DRC. Others products includes mercantile from Kigoma and Kasulu centres,
rice, ground nuts, coconut, salt, oranges, simsim, pineapple, apples, pears, etc. from western regions
of Tanzania regions to Bujumbura. The road is therefore a driver of the economy of the Great Lakes
countries and Burundi in particular.
The objective of the EIA study was to predict and anticipate potential environmental and social impacts
that may arise from the road upgrading and propose mitigation measures to lessen any impacts to ensure
that the project delivers minimum disruption to the environment and surrounding communities.
The ESIA report and standalone detailed ESMP and RAP reports for this project was prepared by EGIS
International in April 2018 based on the Code of Environment (June 2000) and Procedure for
Environmental Impact Assessment (October 2010) of Burundi, the East African Guidelines and AfDB
requirement standards. It reflects the current impact on the physical, biological and socio-cultural
environment based on the current road design.
2. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
2.1 National Legal environment
➢ The Law No 1/010 of 30th June 20000 on the Code of Environment sets basic rules to protect
and management the environment against all forms of degradation and specifies on its article 34
that public works and infrastructure, such as roads, dams, dikes, bridges, and airports are NOT
exempted for carrying out environmental impact assessment for projects that are likely to have
adverse impacts. The decree No 100/22 of 7th October 2010 determines the conditions and
modalities of implementation of the environmental impact assessment procedure. The ministerial
decision of 9th January 2013 specifies the procedure that has to be following during scoping,
aiming to assist the EIA experts to develop site specific Terms of Reference for conducting the
Environmental Impact Assessment.
➢ The Law No 1/02 of 26 March 2012 on Water Code sets the basic rules and related institutional
framework to ensure rational and sustainable management of water resources, amenities, and
hydraulic public interest works. The Article 5 prohibits anthropogenic activities within 150m from
the edge of Lake Tanganyika, 50m from any other lake in the country, 25m from rivers that
discharge into the lake, and 5m from edges of all other rivers. Article 52 prohibits direct or indirect
discharge of sewage or spill of any nature, or commit acts that may cause or increase the pollution
of surface water or groundwater.
➢ The Law No 1/07 of 15 July 2016 on Revision of the Forest Code specifies on its Article 95 that
before carrying out excavations in the ground, to exploit quarries or mines, to open a way of
communication or to rectify the route, to build constructions on a forest domain having at least half
3
a hectare, the developers shall obtain (i) the authorization of the Minister having forests in his
attributions and, where applicable, a cutting or clearing permit; (ii) to take all protective and
conservation measures to ensure that the activities do not cause or aggravate erosion, damage the
vegetation around the sites or alter the quality of the water and do not disturb stream flows and (iii)
restore the site of excavations, extractions or work sites in good condition after prospecting and
exploitation.
➢ The Law No 1/13 of 9 August 2011 Revising the Burundi Land Code specifies on its Article
433 that compensation for expropriation must be based on the value of the expropriated property
assessed and must be paid before the registration of the transfer.
➢ The Decree-Law No 1/037 of 7th July 1993 on Labour Code requires on its article 6 that
everyone to be given equal opportunity and treatment in employment and in the work, without any
discrimination. It opposes any distinction, exclusion or preference based on race, colour, religion,
sex, opinion stated policy, union activity, ethnic or social origin during hiring, promotion,
compensation and termination. The article 11 specifies that (i) every worker must have adequate
measures in his workplace to protect his health and safety; (ii) the Contractor has imperative
obligation to prevent accidents at work places and (iii) the Contractor is obliged to organize and
implement safety training to his workers.
2.2 Regional requirement standards
➢ The East African Community Treaty, 1999 requires Partner States to integrate environmental
management and conservation measures in all developmental activities such as trade, transport,
agriculture, industrial development, mining, and tourism in the Community.
➢ The East African Protocol on Environmental and Natural Resource Management, 2005
requires Partner States to ensure that conservation and management of environmental and natural
resources are treated an integral part of national and local development plans. The article 31
requires that an environmental Impact assessment be carried out for a trans-boundary activities and
projects that are likely to have significant adverse environmental impacts.
➢ The Convention on the Sustainable Management of Lake Tanganyika, signed on 12th June
2003 on its articles 8 and 9 requires Contracting States to take appropriate measures to prevent and
reduce pollution of Lake Tanganyika and its environment arising from activities within their
jurisdiction of control and to take appropriate legal, administrative and technical measures to
prevent all causes of excessive sedimentation in the Lake, such as deforestation, land degradation,
and the destruction of wetlands.
2.3 AfDB Policies and International requirement Standards
The study has taken into account the International environmental and social requirements of the project
financing institutions; these include the African Development Bank policies. The Social and Environmental
assessment of the project was therefore carried in accordance with the AfDB policies and guidelines as
follows: Policy on Environment (2004); Involuntary Resettlement Policy (2003); Policy for Integrated
Water Resources Management (2000); Handbook on Stakeholder Consultation and Participation (2001);
and the AfDB Bank Group Policy on Disclosure and Access to Information (May2011). The AfDB’s
Integrated Safeguard System sets out the five Operational Safeguard requirements that AfDB projects have
to comply with; the project triggers the five operational safeguards as outlined below:
➢ OS 1: Environmental and Social Assessment: since the project requires Environmental and
Social Assessment of anticipated impacts, including on cultural heritage and vulnerable groups and
requires public consultation, grievance procedures. The project has prepared Detailed ESIA studies
4
and a standalone ESMP and RAP that includes Stakeholder Engagement and Grievance Redress
Mechanism.
➢ OS 2: Involuntary Resettlement: Land Acquisition, Population Displacement and Compensation:
the project will have physical and economic displacement of more than 200 people and a RAP has
been prepared by the project to avoid and minimize impacts and compensate for the impacts.
➢ OS3: Biodiversity Conservation and Ecosystems: The project will impact biodiversity through
clearance of vegetation and degradation of water resources due to construction Activities.
➢ OS 4: Pollution Prevention and Control, Greenhouse Gases, Hazardous Materials and
Resource Efficiency: the ESMP includes measures for avoiding and preventing pollution and
ensuring water efficiency during construction.
➢ OS 5: Labor Conditions, Health and Safety: the ESMP includes mitigation of occupational
health and safety impacts and contractor management.
Other International Conventions applicable to the Project are:
➢ The Convention on Biological Diversity (CBD) which was signed and ratified by Burundi in 1997
➢ The Convention on Climate Change (UNFCCC) which was signed and ratified by Burundi in 1997
➢ The Convention on Wetlands (RAMSAR) which was signed and ratified by Burundi in 2002.
2.4 Institutional framework
➢ Ministry of Ministry of Water, Environment, and Urban Planning is the overall responsible
for all matters pertaining to environment, responsible for all policy matters necessary for the
promotion, protection, and sustainable management of Environment in Burundi.
➢ Burundian Office for Environment Protection (OBPE) is responsible among others to (i) ensure
compliance with the Water Code, the Forest Code, the Environment Code; (ii) enforce
environmental standards and propose all measures safeguarding and protecting nature and (iii)
monitor and evaluate development programs to ensure compliance with environmental standards
in the planning and execution of all development projects that may have a negative impact on the
environment.
➢ Burundian Office of Roads (Office des Routes – OdR). OdR, under the Ministry of Transport,
Public Works, and Equipment is the roads authority of Burundi which was created by Decree No.
100/118 of 27 October 2001 as part of the restructuring of the former General Directorate of Roads.
3. PROJECT DESCRIPTION AND JUSTIFICATION
3.1 Project Description
The project road is located in the western part of Burundi along Lake Tanganyika, at the foot of Mumirwa
Mountains for the western branch of East African Rift Valley. It is located in the provinces of Bujumbura
City, Bujumbura Rural, Rumonge, and Bururi and passes Bujumbura City, Kabezi, Kabezi, Rutunga, and
Rumonge urban centres. The project road is part of Class No. RN3 along RTRN Corridor EA 5 (Tunduma
– Sumbawanga – Kigoma – Mugina – Nyanza Lac – Bujumbura Corridor).
5
The project road, which covers a total length of 78km with double carriageways of 7.0m width, and 2.0m
wide shoulders, will constitute widening, realignment and upgrading the existing double bituminous surface
treatment road to Asphalt concrete standard. New cross drainage structures will be constructed to replace
the existing structures that are hydraulically inadequate. One (1) bridge, one hundred twenty-eight (128)
cell structures (box culverts), and twenty eight (28) pipe culverts will be constructed. The remaining
structures will be retained as they adequate.
The road upgrading will also involve improving of safety on various sections of the road with infringed
sight distance (sharp horizontal and vertical curves), which are prone to accidents. Improvement of the road
will also involve introducing a number of safety features such as climbing lanes, non-motorized lane,
service roads in town sections, and widening of shoulders in town sections. The upgraded road will facilitate
efficient transportation of agricultural, marine and diverse products in the region and promote regional
integration/cooperation. The construction of new side and cross drainages structures will improve the
drainage of the existing road, reducing the risks of land degradation.
3.2 Project justification
The importance of the project road lays on the fact that apart from linking Burundi with Tanzania, the road
provides transportation route for agricultural and mining produce to and from the Great Lakes countries in
particular the eastern DRC. Others products includes mercantile from Kigoma and Kasulu centres, rice,
ground nuts, coconut, salt, oranges, simsim, pineapple, apples, pears, etc. from western regions of Tanzania
regions to Bujumbura. The road is therefore a driver of the economy of the Great Lakes countries and
Burundi in particular
Upgrading of the road will therefore: (i) facilitate more efficient transportation of agricultural and marine
products from the project area to the markets in the areas of consumption and verse versa; (ii) promote
regional integration/cooperation; (iii) facilitate/ increase tourism activities within the project areas as well
6
as adjoining area; (iv)reduce maintenance costs of the road; (v) reduce Vehicles Operating Costs and (vi)
improve access to social services such as markets and health services.
A One stop Border Post (OSBP) facility was also proposed to be constructed at Manyovu/ Mugina border
between Tanzania and Burundi. The construction of the One Stop Border Post will reduce processing time
for customers due to single window processing and single administrative documents and a common control
zone will facilitate in cases of irregular migration.
3.3 Key activities on each phases of the project
The proposed project rehabilitation will comprise the following activities:
➢ The mobilization Phase (6 months) that includes (i) Land acquisition for the construction of
camps and materials borrow sites, (ii) Recruitment of construction workers and mobilization of
transport of construction equipment to site and (iii) Establishment of construction of camps for the
Contractor and supervising Consultant. The camp shall comprise residential and material
processing and storage areas as well as workshops for repair and maintenance of equipment.
➢ The construction phase of the project, which is estimates to take 36 months will encompass
earth works to facilitate widening and re-alignment of the road. Expected key activities are: (i)
identification, extraction/ abstraction, and transport of naturally-occurring construction material
borrow sites;(ii) earth works to facilitate widening and re-alignment of the road, including
demolition of buildings within the right of way and existing road structures; (iii) construction of
detours and diversions and construction of access roads to sources of naturally-occurring
construction materials; (iv) Construction of bridges, culverts, and road side drains; (v)filling and
reshaping the road section to sub-grade level and (vii) construction of road pavement.
➢ Decommissioning Phase: The main activities during demobilization phase will engross (i)
collection and disposal of storage facilities such as pallets, packing, boxes, collection and disposal
of construction materials and wastes such as waste oil, sewage, solid wastes (plastics, wood, metal,
papers, etc.) at the workshop, site office etc. to authorized dumpsite. (ii) Disassembling and
transport of construction machines, machinery and equipment, removal of temporary infrastructure,
installations and equipment from the campsite, (iii) rehabilitation/landscaping of the campsite to
the original condition by shaping and grading and (iv) handing over of permanent structures and
facilities in the campsite to OdR who will decide its future use.
➢ Operation and maintenance phase will have as key activities: (i) maintenance of damaged road
sections; (ii) clearing of debris, soil and grass from road side and cross drains road; (iii) re-painting
and installation of signboards and (iv) awareness on road maintenance and security to the
community.
3.4 Required off site investment
➢ Power Source: as not all the collines along the project road are connected to national grid power
supply, the construction site will require diesel driven generators that will be installed to supply
power to the camps and for the operation of electrically-operated equipment at work sites.
➢ Water supply: water will be required for construction activities such as concrete works,
earthworks, lying of some of the pavement layers, dust suppression, as well as for domestic
purposes at the camps.
7
3.5 Land acquisition
The minimum total land area that will be required for road rehabilitation is approximately 94 hectares. In
addition, the project will require land for the construction of site camp as well as access roads to the
borrowing sites.
4. DESCRIPTION OF THE PROJECT ENVIRONMENT
4.1 Projects Boundaries
➢ The Spatial Boundaries of the study area was mainly confined to the Direct Impacted Zone (DIZ)
to the RoW and the 100m on both sides of the road, to accommodate for establishment of borrow
pit, contractor’s campsite or materials storage yard close to the road alignment. The DIZ was
determined on the basis of (i) the distance of travel of noise, vibrations, dust, and exhaust fumes from construction plants and machinery from the site boundary and (ii) marginal zones and
developments from the site within 100 m as it is within this distance that impacts are likely to be
felt. The study has also considered the area beyond the DIZ as Area of Influence (AI) where most
of the environmental impacts will be induced or influenced by the project activities such as areas
around sources of construction materials and villages linked to the existing road.
➢ The Temporal boundaries of the project consist of the durations for mobilization, construction,
and demobilization phases of the project. It addition, the temporal boundaries are the design periods
of the road and its components (road pavement, bridges etc.).
The following are the estimated temporal boundaries of the project:
Phase Time
Mobilization period: 6 months
Construction period: 36 months
Demobilization period: 1 year (inclusive of defect liability period)
Design period of the road pavement: 20 years
Design return period for pipe culverts: 25 years
Design return period for box culverts: 50 years
Design return period for bridges 100 s.
4.2 Physical environment
4.1.1 Topography
The project road traverses areas with varied topography, a small section of the project road (9%) between
Bujumbura City Centre and Kanyosha and Muha Commune characterized by nearly flatland, the rest being
in undulated topography with gentle to moderate slopes.
4.1.2 Climate
The project area is located in tropical equatorial climate characterized by average annual temperature of
230C, with rainy season starting from September and end in May, while dry season starts from June and
ends in August.
4.1.3 Water resources and hydrology
The project road passes along Lake Tanganyika and traverses fifty (50) significant perennial and seasonal
rivers and several drainages as well. Most of the river banks are prone to erosion, some having some
8
protection works at their upstream or downstream parts. The Mutambara River, being the largest perennial
river across the project road, is characterized by elephant grass and oil palm trees on both upstream and
downstream riparians. Its crossing consists of a bridge with pedestrian walkways and guard rails on both
sides. It’s downstream riparian is used for gardening and its soil appears stable against erosion.
Groundwater is abundant throughout along the project road, with water coming to the surface through flood
plains. The project road traverses three (3) floodplains at Kizura, Mwange and Rumonge collines where
palm trees were planted on the both sides of the road.
The study has identified land slide, seasonal flooding of rivers, and transport of rocks and stones from
mountains as the main natural disasters along the project road. 7 streams were identified along the project
road as known to transport rocks and stoned during their seasonal flooding, causing serious disaster to the
locals nearby while three others tend to flood during rainy season causing serious damages to properties.
4.1.4 Road Side Air Quality
Typical air pollutants from road transportation sources are Carbon Monoxide (CO), Nitrogen Dioxide
(NO2), Sulphur Dioxide (SO2) and volatile compounds; and particulate matters (dust). Total current daily
emissions of CO2 (Kg) was estimated of 57,584 for the 78 km based on the current traffic volume counts
(Annual Average Daily Count).
4.1.5 Geology and Soils
The geology of the project area is characterized by Pre-Cambrian rock which are marked by different layers
of sedimentary rock.
The soil of the project road for a number of sections is susceptible to gully erosion development and a
number of gullies have developed along and across the project road, especially on the Km 15 (Ramba-
Kabezi collines). Gully development and landslides frequently occurred on some portions of the road
project during rainy season whereby the road can be blocked by accumulation of soil material.
4.3 Biological environment
4.3.1 Flora
The flora along the project road is characterized by varied mosaics of shade trees and street strip trees, tree
crops (palm, avocado, mango, mandarin), and grassland. Shade and street strips trees are mainly exotic as
most of the indigenous trees have been cleared. The remaining indigenous trees consist of mainly fig,
bamboo, and to a small extend miombo woodland from a protected area. Common practice in the project
area of farming on water courses river banks as well planting trees especially palm trees very near the water
courses can causes significant sedimentation and disturbance of the river system.
4.3.2 Fauna
A section of the road traverses along Nkayamba Natural Forest Reserve; a habitat of wildlife. The forest
reserve is a home of wildlife such as primates, antelopes, jackals, and different species of birds.
Lake Tanganyika is a transboundary water resource protected area and habitat to a variety of endemic
cichlid fish fauna. However, degradation of fish habitats is observed in some part of the Lake for different
reasons including discharge of waste water from palm oil refinery factory and farming activities on rivers
banks. Apart from different species of fish, the lake is a home to hippopotamus and crocodiles. At
Bugarama center, crocodiles and hippopotamus have tendencies to get close to the coast of the lake, which
can be a threat to the transport of goods and persons.
9
4.4 Human environment
4.4.1 Economic environment
The population in Burundi is approximately of 11.2 million people with a density near 470 inhabitants/km²
in 2016. With close to 65% of its population living below the poverty line, Burundi’s economy is heavily
reliant on the agricultural sector, which employs 90% of the population, despite the extreme scarcity of
arable land. Food insecurity is alarming, as Burundi ranks last on the 2013 Global Hunger Index. Almost
one in two households (around 4.6 million people) is food insecure, and more than half of the children are
stunted (WFP, 2014 and 2016).
The Burundian economy is mainly depending on agriculture. Statistics estimate indicate that 90% of the
population relies on agriculture combined with livestock for their livelihood. There are two types of crops
cultivated: Food crops (beans, bananas, sweet potatoes, cassava, maize and sorghum) and cash crops
(coffee, tea, cotton and quinine). Agriculture generates value-added estimated at about 58% of gross
domestic product and produces most the foreign exchange coming to the country. Almost 80% of goods
are exported through this RN3 road to Tanzanian Port of Dar es Salaam. Livestock farming contributes 3%
of gross domestic product and national production of fish is estimated to 15,000 tones, frozen and smoked
fishes being exported too.
4.4.2 Population in the project area
The road will crossover four provinces, Bujumbura City, Bujumbura Rural, Rumonge, and Bururi.
Substantial number of buildings is located very close to the edge of the road as well as perennial crops such
as fruit trees and palm trees; they are likely to be cleared to improve the safety of the road.
The number of People affected by the project either by losing their assets or source of income or
livelihood, is likely to exceed 200, therefore a full Resettlement Action Plan (RAP) shall be conducted
during detailed design of the road. Most of the households (88.5%) are headed by male members of families
in the area.
Land Ownership: most of the households have access to arable land within the RoW and land is being
cultivated. The land tenure systems for most of household are from buying and inheritance. Land along the
road is mostly used for residential and farming and is cultivated yearly.
Gender: Of the total of 148 families, 17 have females as head of household (equivalent to 11.5%).
Vulnerable groups: among the vulnerable groups in the area are widows, disabled persons, orphan, and
the divorced. There are 21 widows, 44 disabled persons, 40 orphans, and 8 divorced.
Water supply: major sources of domestic water supply for settlements along the project road are water
pumped from Lake Tanganyika and rivers across the road, such as Bujumbura city supplied by water
pumped from the lake to a treatment plant. A number of water pipe lines either cross (through culverts) or
runs along the road, within the right of way.
Access to Electricity: less than 5% of the population has access to Electricity; part of the collines along the
road section from Bujumbura to Mutambara (Bururi) road sections are connected to national power supply
grid while the remaining collines to the boarder are not connected to national power supply grid. At several
road sections power supply utilities cross the project road and so during construction such utilities are likely
to be disrupted. In the city of Bujumbura, the power supply lines have been installed underground and some
of the lines cross the road.
10
Access to internet: Burundi is connected to the outside world through fibre optic cable through Tanzania,
the backbone being managed by Burundi Backbone System (BBS). During site survey it was noted the fibre
optic cable has been laid very close to the edge of the road and very shallow on the ground.
5. PROJECT ALTERNATIVES
5.1 “No Go” alternative impact
The impact of this alternative is considered to be detrimental in hampering development in terms of local,
regional, and national wise transport. There is a need to rehabilitating this road in order to cope with rapid
increase in demand for transit of goods and services into other regions but also to address at some extend
the existing unsustainable storm water drainage system in place on the road.
5.2 Design alternatives
Alternative 1: use of cement stabilized sub-base material. This alternative is quite expensive due to the
large use of cement, has a large carbon footprint and unsuitable where granular material is not abundant
and land for borrowing material is scarce.
Alternative 2: use of lime stabilized sub-base material. The use of hydrated lime during stabilization is
associated with a number of health problems if the lime is not handled properly. The use of lime for the
treatment of material that would have been otherwise declared unsuitable for construction works will
minimize the volume and number of borrow sites, generation of waste in the form of spoil material…Lime
treatment of the material increases workability, compressibility, strength (CBR), and durability of the
material.
Alternative 3: increase the number of carriageways for Bujumbura Town Section (first 11 km). Dual
carriageways would increase the road capacity in terms of Passenger car unit per hour and would limit
congestion especially at the entrance of the Capital city. However, this option was found to be unfeasible
because of the potentially high resettlements costs.
5.3 Results of Comparison of Alternatives
The option of stabilizing sub-base with either lime or lime and cement was recognized as a better option
than stabilizing it with cement alone as it is less expensive and can value local material. The single
carriageway for the Bujumbura Town section was maintained to avoid any additional costs on involuntary
resettlement.
6. MAJOR BENEFICIAL AND ADVERSE IMPACTS AND PROPOSED MEASURES and
Complementary INITIATIVES
6.1 Majors impacts during the construction works and proposed mitigation/enhancement measures
6.1.1 Socio-economic impacts
➢ Creation of Employment Construction activities will create both direct and indirect employment
(include food vendors and other small businesses like soft drinks). Enhancement of the impact
11
shall be by priority of employment is given to the local people, compliance with labour law in
particular paying wages in accordance with the law, and avoidance of employment of children.
➢ Displacement and Loss of Properties: Rehabilitation of the road will result into demolition of
buildings that are located within the old RoW as apart from jeopardizing the safety of traffickers
as well as occupiers of the houses. In addition, perennial crops in particular fruit trees and pam trees
that are located very close to the road are likely to be cleared to improve the safety of the road.
To mitigate the impact, owners of affected properties shall be compensated in accordance with
the law.
➢ Disruption/Destruction of Public Utilities and Service: Earthworks during the road rehabilitation
are likely to disrupt and destroy underground power supply, domestic water supply pipe lines,
sewer lines, fibre optic cables, and domestic water points that are located within the corridor of
impact of the road.
To mitigate the impact, the contractor shall liaise with managers of the utilities to establish exact
locations of the utilities within the corridor, work carefully to avoid damages to the utilities and
provide service ducts across the road to allow crossing and future extension of the utilities.
➢ Generation of Noise and Vibrations by construction Equipment and Vehicles, blasting drilling
and rock extraction.
This impact shall be mitigated by ensuring adequate maintenance of the construction equipment,
avoiding construction works, during the night. In addition, drilling, blasting and rock extraction
shall be conducted far from settlement areas and be limited between 08:00 hrs and 16:00 hrs.
Workers working under severe noise environment shall be equipped with ear plugs.
➢ Road Traffic Congestion and Accidents and disruption of community access paths: Increased
project activities will increase traffic volume as well as movements, while roads and drainage
construction on the existing right of way will increase congestion and disruptions of which is
narrow and does not allow for construction of diversion road. Settlements to be particularly affected
are Kanyosha, Ruziba, Kabezi, Migera, Gitaza, Rutunga, Magara, Minago, and Rumonge.
The impact shall be mitigated by: (i) provide suitable temporary crossing structure to
accommodate traffic during construction of bridges and culverts; (ii) post traffic warning signs to
notify the public of potential dangers; (iii) install speed restraining humps across
settlements;(iv)organize road safety awareness training program for all the neighboring schools.
➢ Health Problems Associated with Handling of Cement, Hydrated and Wet-cement Products.
The use of cement will expose workers to Upper Respiratory Tract Infection due to inhaling cement
dust and allergic dermatitis infection due to prolonged contact with cement and wet cement
concrete which may affect respiratory system, skin, and eye. Poor handling of hydrated lime can
cause severe irritation or burning of eyes, including permanent damage and irritation of skin.
➢ Measures to mitigate the impact will include personal protection (use of appropriate protection
gear including overalls, appropriate gloves and footwear as well as eye protection), safe storage
and handling, adequate ventilation and control of exposure to the material. Avail eye wash fountain
and first aid measures.
➢ Occupational Health and Safety Hazards: Construction activities will expose workers, visitors,
and the general public to different physical occupational hazards such as falling of people, objects
or materials, stepping on or striking against objects, manual handling injury (overexertion), workers
being struck by excavating or crane machinery, traffic accidents, electrical shock, and fire and
explosion. In addition, the use of construction materials will expose workers and the public to
chemical health hazards (due to liquids, dusts, gases, and fumes), physical health hazards (due to
heat, noise and vibrations, compressed air, and manual handling), and biological health hazards.
Measures to mitigate such risks will include work practice, personal protection and hygiene.
Measures to prevent workers accidents will include (i) providing toe boards and guard rails that
will be fitted to the outer side and ends of the working and scaffold platforms; (ii) Scaffolding
erection shall be done by an experienced workers and overloading shall be avoided and (iii) workers
under the platform shall wear safety helmet and shoes at all times and (iv) work areas shall maintain
12
good housekeeping all the time. (v) People should be prevented in the vicinity of machine during
excavation cycle and speeds of construction vehicles shall be limited to 60km/hr. (vi) Electrical
shock shall be prevented by ensuring that all electrical control panels and cable are properly
insulated and earthed.
➢ Increased Transmission of STIs/HIV, unwanted Pregnancies and social conflicts can occur
due to increased mobility, migration, and interaction of construction job seekers and the local
people.
Measures to prevent this impact due to increased transmission of STIs/ HIV shall include HIV
awareness and alleviation program.
6.1.2 bio-physical impacts
➢ Roadside and river bank soil erosion due to vegetation clearance, disturbance or removal of top
soil, leaving a soil highly prone to intense runoff and gully development, construction across rivers
and along the L. Tanganyika, leading to soil erosion and heavy sedimentation.
Erosion shall be controlled as follows: (i) sections with high or shallow fills and cuts that are not
paved or covered by permanent structures shall be grassed immediately after construction;(ii)
existing vegetation shall be preserved as much as possible by confining construction activities to
road alignment.
Surface runoff shall be controlled by: (i) excavating catch water drains on upper sides of slopes
to collect and direct runoff water away from cut slopes; (ii) Breaking long slopes with temporary
diversion to reduce the velocity of runoff; (iii) maintaining grades as much as practical to minimize
the velocity of sheet flow over disturbed area and promote infiltration of storm water directly into
the ground;(iv) Installing of gabions to prevent formation of erosion gully along drainage channel
in steep slopes.(v) Installing kerb stones on high fill sections on the edges of carriageway to direct
runoff from pavement to down chutes which shall be installed at determined intervals; (vi)
protecting river systems as much as possible do not disturb areas adjoining water course to act as
buffers and (vii) lining with concrete or stone masonry all line drain sections with slopes steeper
than 4%.
➢ Surface Water and Soil pollution: loose soil resulting from earthworks is likely to be transported
rivers across the road and finally transported to L.Tanganyika. In addition, construction of bridges
and culverts will cause pollution of river systems and soil may occur due to sedimentation,
accidental spillage of hazardous material such as concrete, fuel, and oils from construction
equipment.
The impact shall be mitigated by avoiding disposal of spoil or excess material near water bodies
but at approved areas sites. In addition, catch water drain shall be excavated on the upslope to direct
runoff away from the lake.
➢ Generation of Solid and Liquid Wastes including Human Sanitary Wastes: Construction
workers will generate sanitary wastes at nearly all work sites while construction activities will
generate wastes such as top soil, cleared greens; spoil material, demolition materials from buildings
and structures, and excess naturally-occurring construction materials.
impacts shall be mitigated as follows :(i) obtaining guidance from the Burundian Office for
Environment Protection (OBPE) on disposal of waste and collect and dispose metal wastes, used
oil filters, used lead-acid batteries, used tyres in accordance with Burundian Laws. (ii) top soil to
be used for restoring sites and planted with approved indigenous tree species; (iii) spoil material to
be disposed on specific sites outside the right of way and shall be vegetated; Non-degradable wastes
such as plastic bottles and papers as well as bitumen drums shall be disposed following national
regulations (iv) demolition wastes shall be used to fill pits during their reinstatement. (v) Liquid
wastes, such as grey water (domestic liquid wastes) shall be directed to onsite sanitary treatment
system while mobile sanitation facilities or pits latrines shall be provided at all work sites other
than the camp.
13
➢ Soil and Water Pollution by Concrete Slurry and Concrete Wastewater during construction of
bridges, culverts, and lining of roadside drains is likely to cause leakage of concrete slurry to road
sides. Concrete slurry can pollute soil and affect the growth of young trees. In addition, it is likely
that concrete slurry to find their way to rivers causing burning of fish, insects, and plants.
➢ Impact shall be mitigated by: (i) avoiding access of concrete slurry or wastewater is not into the
storm water system; (ii) slurry control is put in place before concreting is started and concrete slurry
and wastewater are collected or diverted to grass or bare soil.
➢ Surface water flow and water table modification: Construction of road fill embankment across
the flood plains and rivers is likely to interfere with natural surface water flow patterns, resulting
into flooding, soil erosion, and channel modification. Excavation across flood plain is likely to
lower water table in the surrounding areas while construction of embankment is likely to raise water
table by restricting water flow-leading into deterioration of vegetation, increased susceptibility to
erosion.
The impacts have to be addressed in the design stage through proper design of culverts to ensure
that they are capable of sustaining possible peak water flows and on the design of road pavement.
Adequate cross drains shall be designed to minimize ponding on one side of the embankment.
➢ Deterioration of Ambient Air Quality by Dust and Fumes due to movement of construction
machinery and vehicles producing could of dust as well as fumes from exhaust or bitumen.
The impact shall be mitigated by spraying water on diversion along active construction sites and
settlements, covering trucks transporting dusty materials with tarpaulin, and equipping workers
with respirators masks.
➢ Loss of Vegetation by clearing of vegetation to access the borrowing sites, widening of the existing
road to accommodate increased carriage width and its shoulders, road side drain, horizontal
realignment of the existing road to improve safety.
The impact shall be mitigated by avoiding unnecessary clearing of vegetation, including limiting
clearing of vegetation to the corridor of impact. A number of trees shall be planted to compensate
for the cleared trees.
➢ Impact to Nkayamba Natural forest protected area which is a habitat of wildlife will be
traversed by the road. Generation of noise and vibrations, and illegal hunting of wildlife in will
interfere with wildlife home range as well as risks of falls if any borrow pits are exploited within
the forest.
To mitigate the impact, the contractor shall avoid sitting stationery equipment near Nkayamba
natural forest reserve, avoid any borrow pit within the forest and create awareness among project
workers not to be involved in hunting of wildlife.
6.2 major impacts during the operations and maintenance phase of the road
6.2.1 Socio-economic impacts
➢ Reduction in Vehicle Operating Costs and decrease of fuel consumption as good quality of
road will improve vehicle travel speeds.
The impact will be enhanced by ensuring proper and timely repair and maintenance of the road.
➢ Reduced Traffic Accidents due to rehabilitation and widening of the road and set up of safety
features, but also increased Traffic Accidents due to the augmented traffic volume and speeds,
especially at school crossings, and settlements.
The impact can be mitigated by (i) ensuring proper and timely repair and maintenance of the
road; (ii) installing appropriate warning signs at approaches to accident black spots including speed
restraining humps shall be constructed at approaches to settlements and schools and (iii) regularly
organize road safety campaigns and training programs.
➢ Increased Noise and Vibrations nuisance due the augmented traffic volume and speed.
The impact can hardly be mitigated for this type of road.
14
➢ Contribution to climate change effect: Increased traffic volume during the operation phase of the
road will increase the generation of Green Houses Gases, particularly CO2 and N2O exhaust gases.
The impact cannot be mitigated at this level.
6.2.2. bio-physical impacts
➢ Improved Ambient Air Quality due to the road rehabilitation.
This impact can be enhanced by encouraging people to plant strip street trees on road sides which
will provide cleaning effect, alleviating air quality deterioration effects.
➢ Improved Hydrology and Drainage due the road rehabilitation and upgrading.
The impact can be enhanced by proper and timely maintenance of the road furniture facility,
including de-silting of culverts and side drain.
➢ Wildlife Road Kills across Nkayamba Natural Forest Reserve due to accidents.
The impact shall be mitigated by installing speed restraining humps and posting warning signs at
both approaches to the game reserves.
➢ Risks of landside and Interruption of Road Transport during Rainy Season. Prevention
measures shall be (i) to promote watershed management with storm water drainage, trees and grass
on the western side of the road, (ii) maintain the drainage system construction along the road and
(iii) include in the road design the construction of retaining walls made of stones or concrete along
the road in critical areas prone to erosion and landslide.
7. EXPECTED RESIDUAL EFFECTS AND ENVIRONMENTAL HAZARD
MANAGEMENT
7.1 Residual effects of the Project
➢ Generation of Noise and Vibrations due to the road traffic, especially of heavy trucks. If noise
is likely to cause a nuisance at sensitive locations, additional noise suppression techniques will be
considered, but may not be cost effective for such small settlements.
➢ Soil Erosion due to vegetation clearing during the construction phase and during operation
phase due to the nature of the soil, high slopes and poor drainage of the watershed.
➢ Accidents Involving Community Members, livestock or wildlife due to the increased traffic.
➢ Grievances over Land/Properties Compensation and construction works: displacement and
loss of properties will result from acquisition of land and demolition of buildings in order to widen
the existing road, realignment of the existing road to improve safety, and borrowing of material.
Disputes and dissatisfaction of some land owners or users over the compensation process and/or
methodology cannot be avoided. Tensions may also appear between workers and communities at
particular times and locations during the construction phase given the number and range of impacts
that will affect communities. The mitigation measures proposed will minimize the project impacts
but there could be some non-addressed issues that could lead to loss of trust and increased
discontent with the project and project team.
7.2 Occupational, health and safety management
➢ Chemical health hazards associated with Handling of Cement, Wet-cement Products and wet
lime during construction of road pavement, culverts, and lined roadside drains. Workers working
with cement and wet-cement products are likely to be affected by respiratory infection and
dermatitis infection due to prolonged contact with cement and wet-cement concrete. The following
measures shall be in place: (i) workers handling cement to be equipped with PPE including hard
15
gloves, overalls, dust masks and heavy boots, (ii) mix of dry cement in well ventilated areas, and
(iii) contractor to ensure that construction workers adhere to hygiene measures and provide
sufficient water points for body washing.
➢ Chemical health hazards associated with exposure to bitumen/asphalt fumes from bitumen
processing plant or during spraying of bitumen, acute effects to workers are of headache, skin rash,
throat and eye irritation, and cough, with significant risks of lung cancer if prolonged exposure.
Same prevention measures to be applied.
➢ Physical health hazards and accidents resulting from (i) prolonged exposure to high noise levels
from plant and machinery on site or in workshops; (ii) continuous exposure of the hands to high
frequencies of vibrations from tools such as pneumatic hammers, concrete breakers, drills…; (iii)
manual handling injury from tools and machinery; (iv) accidents such as falling of people, objects
or materials, workers being struck by excavating machinery… Prevention measures shall be that
(i) Work areas shall well maintained, with proper disposal of tools, material and solid waste at all
the time, (ii) workers to be equipped with appropriate PPE and to be trained on the use of tools and
machinery and on safety measures.
➢ Fire and Explosion Risks related to activities at mechanical workshops during repair and
maintenance of construction equipment as well as materials that include lubricants (oils, grease
etc.), fuels, and bitumen, paints and solvents, brake fluids, battery acid which poses a risk of fire or
explosion. Prevention measures by the Contractor shall be that (i) to maintain appropriate fire
extinguishers within easy access at all work areas, (ii) recruit Safety Officer and (iii) prohibit
smoking in hot work areas (welding, cutting, and grinding).
➢ Increased Transmission of STIs/HIV and waterborne diseases due to construction workers
mobility, migration, and interaction with local people as well insufficient sanitary facilities (toilets
and water points) within the campsite or along the road under construction. Same prevention
measures mentioned above.
8. PUBLIC CONSULTATIONS AND GRIEVANCE REDRESS MECHANISMS
8.1 Public Consultation and engagement
Public consultation with different stakeholders, aiming (i) to gather information related to population,
socioeconomic activities, environmental issues, sources of livelihood and living standards, (ii) collect
views, concerns, perceptions of stakeholders related to the rehabilitation of the road and (iii) enable project
acceptance and reducing resistance which would otherwise slow down or hamper the project
implementation.
Key stakeholders consulted are among others (i) the proponent of the project, (ii) the Ministry of
Environment and the Lake Tanganyika Authority, (ii) other relevant Government institutions, (iii) public
utilities agencies (REGIDESO, BBS, SETEMU), benefiting commune’s administration and communities
from the Direct Impact zone and Area of Influence.
Consultations and public meetings were held in six (6) different venues to allow community members to
participate fully by arranging close to their places of residences. People from groups of different interests
were involved as well as ward and village and district officials whereby varying views, concerns and
questions about the project were expressed by communities and other stakeholders and were collected by
the consultant team for review and or further use. The meetings were chaired by colline chairmen and
recording of minutes was done by colline secretary.
16
During consultation the stakeholders were briefed on the proposed road project as well as the ESIA process,
and the governing legislations. The public was then given opportunities to air their views and opinions
concerning the project. Potential impacts – both positive and negative impacts as well as mitigation
measures were also gathered as presented in the preceding section.
The road project is generally welcomed as it will improve regional integration and address issues of frequent
accidents occurring because of the narrowness of the road. Most of the concerns and recommendations
provided were considered in this assessment as well as in the RAP. Potential negative impacts mentioned
included soil erosion, deterioration of ambient air quality increased traffic accidents, pollution of water
resources, and disruption of public utilities during the road construction. The spread of HIV/AIDs, STIs
associated with immigrant road construction workforce, sitting of the construction camps and later the
presence of truck drivers that will use the project road were mentioned to be sociological impacts of the
project.
8.2 Grievance redress mechanism
A fair and effective complaints procedure will help to establish a legacy of trust and good relations with
communities. The level of trust will be determined by the quality of implementation of all measures, not
simply those related to community relations.
The project will as much as possible try to follow existing grievance resolution mechanisms in the area at
different levels. Through sensitization meetings, the communities along the road project will be informed
of different grievance mechanisms instituted for them to lodge their complaints and dissatisfactions.
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
An Environmental and Social Management Plan (ESMP) was prepared as a standalone document; it
complements the ESIA and RAP reports as safeguards documents that analyses the scope and magnitude
of the expected impacts on the physical, biological and socio-cultural environment of the road project and
propose suitable mitigation and complementary measures based on the Code of Environment (June 2000)
and Procedure for Environmental Impact Assessment (October 2010) of Burundi, the East African
Guidelines and AfDB requirement standards.
The ESMP intends to outline the mitigating/ enhancing, monitoring, consultative and institutional measures
required to prevent, minimize, mitigate or compensate for adverse environmental and social impacts, or to
enhance the project beneficial impacts. It shall also address capacity building requirements to strengthen
the Borrower’s safeguards capacities if necessary. Its aim is also to specify the environmental and/or social
loan conditions or covenants that are part of the project loan agreements to ensure that the project meets the
Bank’s safeguards requirements.
9.1 Environmental hazard management and contingency plan
An Environmental hazard management and contingency plan (ERP) was prepared additional to the
Environmental Management Plan (EMP). This a general plan through which the Contractor shall prepare
himself and response to an emergency environmental hazard following events such as worker injury,
epidemic outbreaks or serious pollution of water. The purpose of this ERP is to identify emergency
personnel and the logical sequence of actions that should be taken in the event of an emergency during
construction of the road project.
17
9.1.1 Emergency Response Team
Prior to commencement of construction, the contractor will establish the ERT that may include the positions
listed below.
➢ Project Manager: will be the Incident Commander and will have an overall management of
emergencies, including the activation and deactivation of ERT
➢ Construction Manager: will be the Operation Manager and will be responsible for managing
emergency’ tactical activities as per ERP
➢ Environmental and Social (E & S) Manager and Health and Safety (H & S) Manager -
responsible for managing emergency’ tactical activities as per ERP
➢ Construction Supervisor/foreman: will be the Logistic Provider, whose responsibility will be to
provide logistical support for operations during emergency.
9.1.2 Emergency Communication Procedure
An important key to effective emergency response is a communication system which relays accurate
information quickly. To do this, mobile telephone communication method will be used, and personnel
trained. There will be alternative telephone numbers in case one fails by emergency (lack of signal or out
of charge). In the event that there are sections of the project road where mobile signals are either weak or
unavailable, the Contractor shall provide alternative mode of communications (say satellite phones or radio
calls) as alternative means of communication. The list of emergency telephone numbers will be made
accessible by all relevant personnel of the project. The emergency response plan posted in a noticeable
place on the project shall identify the designated equipment and the people to operate it.
9.1.3 Emergency response procedure
An emergency will be reported from any source: supervisor/ foremen, worker on site, an outside agency,
or the public. It should be borne in mind that circumstances may change during the course of an emergency.
The Incident Commander (Project Manager, and/or local emergency agency) will be responsible for the
coordination of all on-site activities including securing the area, accounting for personnel and the public;
and taking actions depending on the type of emergency.
Responders with appropriate training and fire suppression will be authorized to assist in fire emergency
response within the limits of their training and available equipment. Similarly, employees with appropriate
training and spill response and clean-up will be authorized to assist in an emergency response within the
limits of their training and available equipment. The Incident Commander will have the ultimate authority
over how to dispatch project employees to assist with an emergency response. A level 2 or 3 emergency
could cause a need for evacuation such as fire and explosion, particularly at quarry and camp site.
9.1.4 Emergency preparedness
Emergency Preparedness is essential for effective emergency response. Essential elements of emergency
preparedness will include: chain of Command (based on the ERT), resources (include medical first aid kits,
firefighting equipment, containment and clean equipment such as absorbent booms, pads, rice hull, sand),
training and public Education (Community Planning).
9.2 Monitoring and surveillance plan
The Supervising Engineer team will be responsible for regular monitoring of implementation of ESMP,
Site Specific Environmental Management Plan (SSEMP), and Site Specific Health and Safety Management
18
Plan (SSHSMP) by the Contractor. The main tools that will be used for monitoring are checklists, visual
examinations, and quantitative measurements of environmental effects monitoring parameters. Written
records will be kept detailing the dates that monitoring took place and the findings of the monitoring.
Monitoring aimed at attaining the following objectives
➢ Collection of environmental and social baseline data as basis for gauging the effectiveness of
implementation of proposed mitigation measures;
➢ To ensure that mitigation and benefit enhancement measures have been adopted and are effective;
➢ To identify any negative impacts unforeseen during ESIA stage and propose appropriate mitigation
measures;
➢ To provide information on the actual nature and extent of key impacts and effectiveness of
mitigation and benefit enhancement measures.
9.2.1 Modes of Monitoring
There will be two basic forms of monitoring:
➢ Surveillance Activities: Such activities will involve close observation to ensure that the proposed
mitigation and enhancement measures are effectively implemented during the road construction.
➢ Monitoring Activities: Such activities will consist of measuring and evaluating the project impacts
on some environmental and social components of concern and to implement remedial measures, if
found necessary. In that respect, prior to commencement of construction activities, during
mobilization phase the baseline data for environmental (air quality, water quality, noise level, etc.)
components at strategic locations (settlements, camp, quarry, borrow sites, and water courses.) shall
be collected and documented. The baseline data collected will be used to compare environmental
impacts of the “No Project” with the presence of the project and so determine the extent of impacts
caused by the project.
Within the monitoring activities, Effects monitoring will record the consequences of activities on
selected one or more environmental components. This will involve physical measurement of selected
parameters or the execution of surveys to establish the nature and extent of induced changes. Measurement
Based Inspection will involve evaluation of trends in the values of environmental and social parameters
systematically measured (quantitatively and/or qualitatively) and collected, to ensure that they are within
acceptable legal and technical standards. This will involve collection of samples for analysis. In this, water
and air samples will be collected and analyzed. The main tools that will be used for monitoring are
checklists, visual examinations, and quantitative measurements of environmental effects monitoring
parameters. Written records will be kept detailing the dates that monitoring took place and the findings of
the monitoring.
10. INSTITUTIONAL ARRANGEMENT AND CAPACITY BUILDING
ARRANGEMENTS
10.1 Institutional arrangements
Implementation of the proposed mitigation and enhancement measures as well as monitoring plan will
involve a number of key players.
10.1.1 Office of Roads
OdR is responsible for the overall implementation, administration, and enforcement of the
recommendations of the ESIA. OdR will be responsible of:
19
➢ Ensuring that the ESMP provisions are included in all tender documents issued for construction
work and activities on site and shall monitor/enforce that the Contractor(s) abide by the
specifications thereof
➢ Ensure that the Supervising Consultant effectively supervises the Contractor(s) in the
implementation of ESMP and other legal and Contractual environmental and social requirements
of the Contract.
➢ Coordinating the implementation of the ESMP by the contractor(s)
➢ Providing OBPE with reports on environmental and social compliance as part of their annual
progress reports and annual environmental monitoring reports.
10.1.2 Supervising Consultant
The supervising Consultant (Engineer), who will be supervising the construction works, will be responsible
for overall project management. The Consultant will be responsible for ensuring day to day implementation
and compliance with the portions of ESMP relevant to their specific tasks.
To ensure effective implementation of the mitigations measures, the Supervising Engineer shall deploy an
Environmental and Social Specialist (ESS), who will be responsible for regular monitoring of
implementation of ESIA, ESMP, Site Specific Environmental and Social Management Plan (SSEMP), and
Site Specific Health and Safety Management Plan (SSHSMP) by the Contractor. He/she should as well be
responsible for ensuring that reporting of implementation of the measures is completed in accordance with
the requirements. The ESS will have the following responsibilities: (i) Review Contractor’s SSEMP and
SSHSMP; (ii) Monitoring the effectiveness of the ESMP and other mitigation measures. (iii) Asses the
performance of environmental controls and proposed mitigation measures; (iv) Ensure that the Contractor
corrects/ review mitigation measures that are not functioning acceptably; (v) Provide regular reports on
monthly basis on the status of the Contractor’s compliance with the ESIA, ESMP, SSEMP, and
SSHSMP.(vi)Provide input for the preparation of monthly progress report by the Supervising Engineer;
(vii) Visit the project site for 14 days every month and review relevant Contractors documents to determine
the compliance of the Contractor with SSHSMP.
If the ESS believes that there is a potential for unacceptable impacts, he/she may require changes in the
operating procedures or additional mitigations measures. If on the opinion of the ESS, there is serious
environmental, social, of health and safety violation by the Contractor, he/she may advise the Supervising
Consultant to suspend part or all works, until such time that the Contractor has rectified all the serious
environmental, health and safety deficiencies to the satisfaction of the Engineer.
10.1.3 The Contractor
The Contractor is the principal implementer of the mitigation/enhancement measures detailed under the
ESMP, with the close supervision of the Supervising Engineer team and shall develop Site Specific
Environmental Management Plan (SSEMP) and Site Specific Health and Safety Management Plan
(SSHSMP). The two documents shall be reviewed and approved by the Engineer, after consultation with
the Employer. The contractor will have contractual obligation to ensure the control and limitations of
disturbance to the project site, routes, and its surrounding environment and communities during the
construction cycle of the project. The contractor shall therefore be required to comply with the ESMP
requirements.
Within 2 months upon notification of contract award, the contractors shall prepare and submit site specific
Environmental and Social Management Plan. The site specific ESMP shall describe in a detailed manner
specific actions and measures that will be required by the main contractors and their sub-contractors as
appropriate, in order to comply with minimum with the commitments made within the Contractor bids.
20
The Contractor shall employ the following minimum staff to assist him in implementing ESMP: (i) an
Environmental and Social Management; (ii) a Health and Safety Manager; (iii) a Traffic Management
Officer and (iv)a Human Resources Officer. The E & S Manager will be overseeing environmental and
social issues of the ESMP while the H& S Manager will be overseeing occupational health and safety issues
of the ESMP.
10.1.4 OBPE
OBPE is the main responsible agency for foreseeing development projects carried out in the Republic of
Burundi adequately; address environmental and social issues during the lifetime of the program. OBPE
shall therefore periodically carry out or assign an independent evaluator to carry out compliance monitoring
on the project sites and assess on any claims that has been raise; and request for compliance report on ESMP
and take necessary measures including fines to enforce compliance of the ESMP.
10.2 Capacity Building Program
The effective implementation of the ESMP requires that all persons working for the project are aware of
the environmental and social requirements for of the Contracts as well as their roles and responsibilities in
the implementation of the ESMP. They should also be aware of the significant tangible or potential
environmental impacts of their work activities; the benefits of improved performance and the consequence
of not complying with environmental requirements.
The Contractor shall provide appropriate training for their staff on ESMP and shall ensure that all site
personnel fully understand both the objectives of the ESMP and details of the plan that are relevant to their
individual tasks. During the road rehabilitation, the Contractor’s E & S and H & S shall device and
implement training programs on ESMP, but in certain situations when specialized training is required, an
outsourced person shall be invited to conduct the training.
The main Contractors should be aware that he/she is responsible for education and informing all Sub-
Contractors (if any).
The training shall include but not limited to the following areas, whose details will be established by the
Contractor’s Site Specific Environmental and Social Management Plan (SSESMP), which will be reviewed
and approved by the Supervising Consultant:
➢ Environmental Issues:
- Implementation of SSESMP
- Environmental and Social Monitoring Plan, monitoring methods and equipment
- Records keeping and reporting on compliance with SSESMP
- Communication methods and procedures
- Dealing with complaints
- Emergency Preparedness and Response Plan
➢ Health and Safety
- Organization and Responsibilities; especially Work site Management
- Occupational safety risk and prevention
- Site Safety Rules and location of first aid kits
- Safety Incident Plan including Incident responsible person, phone numbers and instructions to
call immediately
- Traffic Management Plan and Traffic Management Signs
- General Hazards present at work sites: mobile plant, working at height, manual handling and
use of Personal Protective Equipment (PPE)
- The Safe Work Methods and other measures adopted to respond to the hazards.
- HIV/Aids, ISTs and waterborne diseases
21
- Fire Prevention and Location of fire extinguishers
11. ENVIRONMENTAL AND SOCIAL MANAGEMENT AND MONITORING COSTS
The total cost for implementing mitigation measures and monitoring plans, excluding the cost of
compensation of affected properties is therefore USD 744,330 (USD Seven hundred forty-four thousand
three hundred thirty only).
22
11.1 Summary of Environmental and Social Management and Monitoring Plans, schedule and costs
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
Mobilization phase
Physi
cal
envir
onm
ent
i) Noise and
vibration
- proper maintenance of
construction equipment
- workers to wear PPE including
ear plugs
6 months - Level of noise, generated
by equipment and trucks
- Presence of exhaust
mufflers
- Use of ear plugs by staff
working in noisy
environment
-Equipment engines properly tuned
- All equipment fitted with mufflers
- All workers working in very noisy
environment equipped with ear plugs
- Noise level ≤ 85 dBA
Cost covered under
another item
ii) Pollution of
ambient air by
dust
- sprinkling water on the access
road to material borrow sites,
- cover dump trucks with
tarpaulin
- workers equipped with PPE
including dust masks
6 months -Level of dust generated
-Implementation of dust
abatement measures
-Use of dust
masks/Respirators
- frequency of dust abatement measures done
-all workers equipped with dusk mask
-Zero complains by workers and local
communities
-level of dust cloud PM2.5 ≤ 25μg/m3
Cost covered under
another item
iii) Soil erosion
- avoid unnecessary clearing of
vegetation
-avoid vegetation clearing,
trenching and stockpiling raw
material during raining season
- establish control measures for
runoff from access roads and
project road
- avoid opening borrow pits
within a buffer of 60m from
watercourse
6 months -implementation of
prevention measures
- condition of areas
adjoining rivers
- management of storm
water during construction
of bridges and culverts
- specified temporary and permanent erosion
control measures in place (grassing, checks,
stone pitching, and tree planting)
implemented
-specified measures to control surface runoff
in place
Cost covered under
another item
Bio
logic
al
env
iro
nm
ent
iv) Loss of
vegetation
- avoid unnecessary removal of
vegetation
- restore vegetation on borrow
pits and campsites after
completion, with local species
- stockpile the top soil to be reuse
for restoring vegetation
- cleared trees to be left for local
people
6 months -Implementation of
measures to minimize loss
of vegetation
- compensation paid for lost
vegetation
- Management of cleared
Trees
- Width of clearing confined to RoW
- volume of top soil stockpiled for future soil
restoration
- number of cleared trees handed over to the
community
-number of complaints from local
communities
Cost covered under
another item
vi) Traffic
accidents
- Limit project vehicles speeds
- Post warning signs at junctions
to material stock route
6 months - Flagmen deployed near
active construction sites and
material borrow sites
- Night-reflective warning
signs
- level of awareness of road users nearby
construction sites
- speed of project vehicles within
construction and borrow sites
- number of speed restraining bumps
Cost covered under
another item
23
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
-Physical barriers (concrete
barricades, tape etc.) in
place
-Speed-restraining humps
installed at approaches to all
accident black spots
-Pedestrians and other
traffic are rerouted away
from active construction
sites
-ground openings with
barriers to prevent any fall
by night and day
-All accidents and incidents
are reported immediately
measures to avoid similar
accidents set in place
- number of warning signboards and night
reflective warning signs
- number of deviations paths for pedestrian
and road users in place
- number of grounds opening protection
barriers set in place
-number of accidents occurred
- number of complaints collected and
addressed
vii) Creation of
employment
- Prioritize recruitment of the
local people
- Complies with Labour Code
(wages payment, age limit and
gender equity)
6 months -Age of employees
- ratio of local people/
immigrants employed
-Workers contracts Wages
paid to workers
- Working hours
- No workers under 16yrs employed
- Non- skilled jobs in favor of
Local people
- All workers have contract
- Working hours and wages in accordance
with Laws
Cost covered under
another item
Construction phase
Physi
cal
envir
onm
ent
i) Noise and
vibrations from
machinery and
trucks, blasting,
drilling and
rock
excavation
- regular maintenance of
machinery and fitted with
exhaust mufflers
- workers exposed to noise level
above the limit of 85dB equipped
with earplugs
- Prevent blasting of rocks at
quarry site during the night and
give advance notice to the
communities
- explosives to be stored in safe
and secured storing place
- handling of explosives to be
done by a person holding
blasting certificate issued by
relevant authority
- drilling sites for blasting to be
clearly marked with flags
36 months - Whether Contractors have
licenses for explosive
storage magazines
- Whether blasting done by
holders of blasting
certificates issued by
relevant authority
-Whether blasting done
between 08:00 - 16:00 hrs
- Contractors have licenses for explosive
storage magazines
- Blasting is done by holders of blasting
certificates issued by relevant authority
- Blasting is done between 08:00 and 16:00
hrs
- Overloading of scaffold is prevented
- no complaints collected
Purchase of sound
level meter for
measuring
noise level
at workplace @
USD 2,200/=
24
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
iii) Pollution of
ambient air by
dust and by
bitumen fumes
- Sprinkling of water on the
project road, diversion and
access roads to borrow sites
- Cover dump trucks with
tarpaulin
- Workers equipped with PPE
including dust masks when
required especially during
materials loading and bitumen
spraying
- Bitumen processing facilities to
be located in a well-ventilated
area to reduce concentration of
bitumen fumes
36 months -Level of dust generated
-Implementation of dust
abatement measures
-Use of dust masks
- Level of bitumen fumes
generated by equipment,
- Working environment for
workers exposed to fumes
- frequency of dust abatement measures done
-absence of clouds of dust
-all workers equipped with dusk mask
- number of complaints by workers and local
communities
No excessive smoke from equipment
-Equipment engine tuning, spray of bitumen,
painting, and welding done in a well-
ventilated area
Dust suppression by
spraying of water on
diversion and access
road @ USD
660/month
= 23,760/=
Purchase of dust level
meter for measuring
dust level at
workplace @ =
3,520/=
Generation of
Solid and liquid
wastes
- Green cutting and top soil to be
used to restore vegetation.
- Dump soil to be used to fill
borrow pits
- Demolition materials and all
non-biodegradable waste to be
collected and disposed following
OBPE instructions
- used motor oil to be safely
collected and disposed following
OBPE instructions
- toilets in the campsite and
mobile toilets and pit latrines
along the project road equipped
with appropriate soaked pits
36 months - wastes are managed,
treated, and disposed of as
prescribed
- lubricants containers
placed on concrete-paved
ground with secondary
containment
-filling and topping up of
lubricant is done by a hand
pump/funnel
-if there is no leakage of
fuel or oil from equipment
-used oil is kept in sealed
leak-proof containers on
concrete-paved ground
-if there are ablution
facilities at all work sites
- Wastes are managed, treated, and disposed
of as prescribed
- Lubricants containers placed on concrete-
paved ground with secondary containment
- Filling and topping up of lubricant is done
by a hand pump/funnel
- Topping up of lubricant done in the
presence of drip pan
- no leakage of fuel or oil from equipment
- Used oil is kept in sealed leak-proof
containers on concrete-paved ground with
secondary containment
- Used oil and fuel filters are stored in leak
proof containers on concrete-paved ground
secondary containment
-All work sites that last for at least month
have ablution facilities
Disposal of plastic
and
other hazardous
wastes
estimated @ USD
660/month for 36
months = 23,760/=
Risks of
Leakage of
Hazardous
Materials and
chemicals
including
concrete slurry
and wastewater
- Fuel shall be stored in onsite
tanks.
-Lubricating oils, paints,
solvents, grease shall be packed
in barrel and tins stored in a
concrete containment.
- Concrete slurry and wastewater
are collected or diverted to grass
or bare soil and shall not enter
storm water system
36 months -Implementation of
prevention measures
-operations of mechanical
workshops
-operations of bitumen
heating chipping and
precoating facilities
- reported occurrence of leakage of fuel or oil
from equipment
-status of the storage containment and
containers of all hazardous materials
- status of the storage containment and
containers for used oil and fuel filters
-status of the containers of bitumen (drums
stored on polythene lined level ground with at
least 10cm layer of sand)
Cost covered under
another item
25
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
- Absorbent materials such as
polypropylene boom and pads
saw dust will be kept on hand for
clean-up of spilled liquids on
pavement, water, and soil.
i) Roadside soil
erosion
- High or shallow fills and cuts
not paved or not covered by
permanent structures shall be
grassed
- Extent of disturbance shall be
limited and soil surface shall be
stabilized
- Existing vegetation shall be
preserved by confining
construction activities to road
alignment
- Storm water to be diverted from
undisturbed area by excavating
catch water drain
-check dams, sediment traps or
silt fence shall be installed to
control erosion on long steep
slopes adjoining watercourses
-Kerb stones shall be installed on
the edges of carriage way to
direct runoff from pavement to
down chutes
- disturbed river banks and heads
of bridges vicinity to be
stabilized by grassing
- drains shall be extended far
from the road and protected by
gabions to prevent formation of
erosion gullies along drainage
channels on steep slopes along
the road
36 months -implementation of
prevention
measures to prevent river
banks erosion and
sedimentation
- Level of sedimentation of
river systems
- Measures to prevent sedimentation are
implemented
-Turbidity as measured inNTU ≤ 10%
deviation from the baseline
- No complaint is received from downstream
users of a river
Cost of vegetation of
10ha unpaved high
fills, cuts and steep
road side
by grassing @ USD
6,600/ha =66,000/=
ii) Surface
water and soil
pollution
- as much as possible, concrete
works shall be isolated from
water courses and concrete
handling equipment shall not be
allowed near watercourses
36 months -lubricants containers
placed on concrete-paved
ground with secondary
containment
-filling and topping up of
lubricant is done by a hand
- No fuel or oil leak from equipment working
on river banks
-no refueling is done near
water courses
-No sign of floating hydrocarbon product
-Purchase of pH
meter
(for measuring pH of
water from streams)
during construction
@USD 1,330
26
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
- Servicing and/or re-fuelling of
equipment shall be restricted at
the workshop
- Excavated materials and other
construction materials shall not be
stockpiled or deposited near
stream banks, or near the edge of
the Lake
- Contractor to avail sufficient
sanitary facilities with septic
tanks within the campsites and
mobile toilets/pit latrines along
the road
-Code of Conduct for workers is
prepared, strictly forbidding
inappropriate or illegal behaviors
on site
pump, in presence of drip
pan
-management (including
storage) of lubricants and
bitumen
-management of used oil
and fuel filters
-Implementation of
measures to prevent cement
pollution
- Concrete works are
isolated
from water courses
- No washing of concrete
handling equipment is done
near water courses
- volume of waste oil, used oil and fuel filters,
empty bitumen drums collected for disposal
- Level of water pollution by cement
-no complaints from local people in the
downstream
-pH ≤ 1 deviation from the
baseline
-Purchase of turbidity
meter for measuring
turbidity of water
from streams during
construction
@ USD 3,100 Total
Cost = 4,430
Part of mobilization
cost for sanitary
facilities covered in
the
BOQ of the design
report
Concrete works
during
construction of
drainage
structures
-Use of Protective Gears such as
Alkali-resistant gloves, coveralls
with long sleeves and full-length
trousers, Water proof boots, Dust
masks and Eye safety protection
-Work practices such as Mix dry
cement in well ventilated areas,
Work upwind from dust sources,
use ready-mixed concrete instead
of mixing on site.
Skin in contact with wet cement
shall be washed immediately with
large amounts of clean water
36 months -Workers working with
cement and concrete are
equipped with appropriate
PPE are used
-Workers work in the
manner that minimizes
release of cement dust and
contact with wet cement
product
PPE are issued and worn-
out replaced
immediately
-Whether appropriate PPE
are used by workers working with cement and
concrete
-Whether workers work in the manner that
minimizes release of
cement dust and contact with wet cement
product
-Whether PPE are issued as required and
worn-out PPE are replaced as required
Cost of purchasing
assorted PPE @ USD
3,550/month for 36
months = 126,000/=
Bio
logic
al e
nvir
onm
ent
Illegal hunting
on Nkayamba
Natural Forest
Reserve /illegal
fishing in the
Lake and rivers
- creating awareness among
Contractor’s staff against illegal
hunting of wildlife in the forest
reserve or use of natural resources
- The contractor to prepare
SSEMP strictly forbidding
inappropriate or illegal behaviors
of workers on site
- No borrow pit shall be located
within Nkayamba natural forest
reserve or near the Lake or rivers.
36 months - Awareness of Contractor’s
workers about the protected
area
- Contractor’s staff are aware of the protected
area
- There are no evidence that Contractor’s staff
is hunting from the nature reserves
Cost covered under
another item
27
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
Loss of
Vegetation
- avoid unnecessary removal of
vegetation especially on the lake
shores and river banks.
- Confine clearing works to
within the working width of 12m
- 15m from the centerline of the
road.
- All the construction affected
surfaces shall be rehabilitated by
filling and grading.
36 months -Implementation of
measures to minimize loss
of vegetation
- compensation paid for lost
vegetation
- Management of cleared
Trees
- Width of clearing confined to RoW
- volume of Top soil stockpiled for future soil
restoration
- number of cleared trees handed over to the
community
-number of complaints by local communities
Cost of providing
3,000 trees and shrubs
seedlings,
transplanting
and managing until
well established
(including watering)
@ USD 22/tree =
66,000
Soci
o e
conom
ic e
nvir
onm
ent
Displacement
and Loss of
Properties
- All the affected properties shall
be compensated before
commencement of construction
works.
- Prior to demolishing buildings
owners of the properties shall be
allowed to salvage valuable
materials such roofing iron…
- a grievance redress mechanism
to be established and help address
complaints throughout the project
construction phase
36 months - Land acquisition
procedure
- implementation of the
RAP
- Land acquisition done in
accordance with land Code
- level of completion of the RAP
implementation
-number of complaints by local communities
Compensation of
properties (includes
crops, land, and
building as well as
accommodation,
disturbance, and
transport allowances
(USD 1,462,562/=
detailed in the RAP)
Disruption/
Destruction of
Public Utilities
and Service
- Constructor to work closely
with services providers for power
lines, optical fibers and water
and sewage pipes identification,
provide ducts for temporary
displacement and
relocation/restoration.
- one month early announcement
to communities using available
medias.
36 months - Consultation and site visits
with utilities agencies for
identification and planning
of earthworks
-Communication to local
communities impacted
- Implementation of
measures to prevent
disruption of access to
utilities
- Response to complaints
with regard to damaged
access to utilities
- Installation of power line
service ducts
-Reinstatement of damaged
utilities
-Minutes of consultation meetings with
power, water supply, sewage and optical fibre
management services providers
-number of press release to the community on
the expected disruptions
- Utilities within RoW carefully removed
before commencement of construction
- timely response to complaints with regard to
damaged utilities
- Locations of service ducts for cables and
pipes.
Provisional sum to
address water supply
disturbance
US$ 266,660/=
Risk of
Accidents from
borrow pits
- Contractor shall devise proper
traffic management, including
deploying a traffic management
36 months - Management of material
operational borrow areas
-constructor to choose borrow areas located at
minimum distance of 100m and approved by
the Engineer
Rehabilitation of
borrow pits estimated
area is 80ha @ USD
28
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
exploitation,
road
construction
and use of
machinery
personal at all active construction
sites.
- Contractor shall established
awareness signposts and night-
reflective traffic warning signs
affixed with reflective hazard
warning tape, to notify the public
from distant about potential
dangers.
- During excavation cycle, no
person shall be allowed in the
vicinity of the machine.
- contractor to prepare an
SSEMP strictly forbidding
inappropriate or illegal behaviors
for workers on the site and to
train workers on health and
safety
-avail first aid boxes on work
sites and facilitate transport to
health centers if any injuries
-all borrow pits and quarries
to be reinstated before
issuance of certificate to the
Contractor
-housekeeping maintained
all the time in the campsite
- Use of PPE by workers
including hard shoes and
helmets
-How excavation and lifting
by crane is done
-Implementation of
prevention
measures to workers and the
public for being hit by
equipment
-Scaffold is erected by
experienced scaffolders and
competent
-implement emergency
measures to treat any
injured worker
- ensure that all borrow pits and quarries are
self-draining
- depths of borrow pits limited to 3m and
quarry face is 10m
- All the workers are equipped with PPE
including hard shoes and safety helmets
- No workers and public in the trench near the
face or the slewing radius of the machine.
-Scaffold board is free from
unacceptable faults
supervision
All workers under the platform of workshop
are equipped with safety helmet and shoes all
times
- first aid boxes available on work sites
- number of accidents registered and injured
workers treated
220/ha = 17,600
Risk of
contracting
waterborne
diseases
after drinking
unsafe water or
eating unsafe
food
- Supply of safe drinking water
to workers
- Availability of sufficient
sanitation facilities with cleaning
water at work sites including
mobile toilets/latrines
-avail first aid boxes on work
sites and facilitate transport to
health centers
36 months Available safe drinking on
work sites
- Available clean sanitation
facilities with cleaning
water at work sites
Available first aid boxes on
work sites and transport
facilitate for sick workers
-Safe drinking water is supplied to workers at
all work sites
- All work sites that last for a month are
equipped with sanitation facilities with
cleaning water
- number of workers treated by health centers
Cost of purchasing
assorted PPE @ USD
3,550/month for 36
months = 126,000/=
Disruption of
Community
Access to their
Dwellings and
Business Areas
- The contractor shall provide
temporary/ permanent concrete
slabs across line drain for
pedestrians
- road design with permanent
access culverts and slabs
connecting to other roads
36 months - Availability of temporary
pedestrian access paths and
slabs across line drains
- temporary pedestrians crossing are availed
at all dwellings
- No complaints about lack of pedestrian
crossings
Cost covered under
another item
Impact to
Cultural Sites
-The Contractor shall work
carefully to avoid any damage to
the at Ruziba and Minago graves.
36 months - implementation of
measures to prevent damage
to graves
-all the graves within the ROW
are relocated in accordance
the law before commencement of
construction
Provisional sum for
relation of graves =
USD 5,000
29
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
- In the event that graves or
artefacts are identified within the
RoW, local authorities will be
contacted and the graves shall be
deconsecrated and relocated with
full participation of communities.
- Graves outside RoW are clearly marked/
and protected from damage
Social
Conflicts;
unwanted
pregnancies
and spread of
HIV/AIDS
- The Contractor hire an
experienced organization to
conduct a HIV/AIDS awareness
and prevention activities and
prepare and implement HIV
prevention program for the
community.
- contractor to prepare a SSEMP
strictly forbidding inappropriate
or illegal behaviors of workers in
the work site and train workers
on health and safety
36 months - level of HIV/AIDs
alleviation program
- Distribution of condoms
- condoms are distributed at
strategic points
- there is evidence that the
Contractor conducts training
-Whether No. of trainings
conducted are in accordance with approved
training program
Implementations of
HIV/ AIDS awareness
and prevention
program @ USD
2,200/ quarter for
12quarters
= USD 26,400/=
Demobilization phase
Generation of
solid waste
- Contractor to prepare and
implement the camp closure plan
after review and approval by the
Engineer (including fuel storage
facility, workshop, bitumen
storage and heating facilities).
- demolition and non-reused
material shall be collected and
disposed as per OBPE
recommendations
- reused material shall be
evacuated or handover to the
agreed institution
12 months - Implementation of
measures for management
of wastes
- Treatment and disposal of
wastes
- Wastes are managed, treated, and disposed
of as prescribed
Cost covered under
another item
Operation and maintenance phase
Physi
cal
env
iro
nm
e
nt
Improved
Hydrology and
Drainage
- ensuring proper and timely
maintenance of the road
including de-silting of culverts
and side drain.
Throughout
its operation
phase
specific road maintenance
work and equipment are
provided (de-silting of
culverts and drains,
signboards…)
Specific road maintenance work and
equipment provided in time
-
30
Impact Mitigation, enhancement
measures
Implement.
schedule
Parameter to be
Monitored
Indicator Costs
frequent
landside and
Interruption of
Road Transport
during Rainy
Season
-establish a watershed
management with storm water
drainage, trees and grass on the
western side of the road
-maintain the drainage system
construction along the road
-Planting of deep-rotted tree and
vetiver grass on the upper road
side to control the speed of runoff
36 months Whether specified
permanent erosion control
measures (top soiling,
grassing, checks, stone
pitching, and tree planting)
are implemented and
maintained
Specified permanent erosion control
measures (top soiling, grassing, checks, stone
pitching, and tree planting) are implemented
Planting of 5 rows of
deep rotted trees
(4,000 trees)
@ 4m X 5m spacing
for a stretch of 4km
(@ USD 22/ trees
=88,000
Lump sum amount for
planting and
managing vetiver
grass = USD 25,000
Bio
logic
al
env
iro
n.
Accidents with
wildlife across
Nkayamba
Natural Forest
Reserve
- ensuring proper and timely
maintenance of the road
including de-silting of culverts
and side drain.
- Establish and maintain speed
restraining humps and warning
signposts
Throughout
its operation
phase
-
Soci
oec
onom
ic e
nvir
onm
ent
Increased
Traffic
Accidents
- Establish and maintain speed
restraining humps and Zebra
crossings with appropriate
warning signposts near to
settlements, school children, and
livestock crossings.
-road safety awareness campaign
Throughout
its operation
phase
-
Reduction of
Vehicle
Operating Costs
and Energy
Consumption
-ensuring proper and timely
repair of the project road.
Throughout
its operation
phase
-
TOTAL USD 744,330
31
12 CONCLUSION
The road upgrading is essential for the development of the economy of Burundi, the neighboring countries
of Tanzania, Rwanda, and EAC at large. The project will have both positive and negative impacts to the
environment and the local communities along it.
Among the positive impacts the project will have are improved road safety, reduced transport and
transportation costs, improved tourism, and regional integration while one of the most negative significant
sociological impacts that will result from the road project will be loss of properties and resettlement owing
to widening, realignment and improvement of the existing road safety. Other negative impacts will include
soil erosion, pollution of water resources, and disruption of public utilities during the road construction as
well as increasing risks of spreading of HIV/AIDs, STIs associated with immigrant road construction
workforce.
Measures have been proposed to enhance or mitigate the impacts of the project intervention to the
communities and their environment. It has estimated that the cost of implementing the predicted adverse
environmental impacts, is of $ US 744,330 (Seven hundred forty-four thousand three hundred thirty US
dollars only). The costs of compensation of affected properties as reported in the standalone RAP report is
of 3.764.384.733 BIF which is around $ US 2,135,215 (two million one hundred thirty-five thousand
two hundred and five US dollars only).
13 References and Contacts
References :
• Environmental and Social Impact Assessment Report for the Proposed Rehabilitation of
Bujumbura – Rutunga – Rumonge Road (77,6km) Section in Bujumbura City, Bujumbura
Rural, and Rumonge Provinces.
• Burundi African Economic Outlook 2012, African Development Bank
Contacts
• NDIKUMWAMI, Senior Transport Engineer:
Email: [email protected]
• J. B AGUMA, Principal Transport Economist
Email: [email protected]
• P. HORUGAVYE, Socio-economist, SNSC
E-mail : [email protected]
• E.B. KAHUBIRE, Social Development Officer, RDGE4 /SNSC
E-mail: [email protected]
• F. KAYIGAMBA ; environnemental expert, consultant, SNSC
E-mail:[email protected]