counsel for respondent

31
INTERNATIONAL CONSTRUCTION ARBITRATION MOOT MEMORANDUM FOR RESPONDENT COUNSEL FOR RESPONDENT ON BEHALF OF: AGAINST: Employer (From Commonia) Contractor (From Civilia) RESPONDENT CLAIMANT

Upload: others

Post on 24-Dec-2021

3 views

Category:

Documents


18 download

TRANSCRIPT

Page 1: COUNSEL FOR RESPONDENT

INTERNATIONAL

CONSTRUCTION

ARBITRATION

MOOT

MEMORANDUM FOR RESPONDENT

COUNSEL FOR RESPONDENT

ON BEHALF OF:

AGAINST:

Employer

(From Commonia)

Contractor

(From Civilia)

RESPONDENT

CLAIMANT

Page 2: COUNSEL FOR RESPONDENT

i

Table of Contents

TABLE OF ABBREVIATIONS ......................................................................................................................... iii

TABLE OF AUTHORITIES ................................................................................................................................ iv

STATEMENT OF FACTS .................................................................................................................................... 1

TIMELINE OF EVENTS ...................................................................................................................................... 3

SUMMARY OF ARGUMENTS ........................................................................................................................... 4

ARGUMENTS ........................................................................................................................................................ 6

I. ISSUE 1: THE PARTIES DO NOT HAVE VAILD ARBITRATION AGREEMENT BETWEEN

THEM ...................................................................................................................................................................... 6

A. Arbitration Agreement is Invalid under UNCITRAL and RAC Rules................................................. 6

1. Claimant did not Adhere to Arbitration Clause .................................................................................. 6

2. Arbitration Clause does not fulfil formal requirements of International Arbitration .................... 7

B. Arbitration Clause does not refer to the Russian Arbitration Centre ................................................... 7

1. Parties’ intention was to choose an institution used primarily for international arbitration ......... 8

2. Interpretation does not lead to the conclusion that the Russian Arbitral Institution refers to

Russian Arbitration Centre ........................................................................................................................... 8

3. There is Substantial difference between the arbitration clause in contract and the Model Clause

of RAC. ............................................................................................................................................................ 8

C. Answer to Request for Arbitration does not indicate the validity of arbitration Agreement ............. 9

D. Even if Arbitration agreement is valid, preconditions to arbitration have not been fulfilled. ............ 9

E. Russian Arbitration Center is authorized to determine its own jurisdiction even if Respondent fails

to challenge. ....................................................................................................................................................... 10

II. ISSUE 2: CLAIMANT DID NOT TAKE REASONABLE STEPS TO RESOLVE THE DISPUTE

AMICABLY. ......................................................................................................................................................... 10

A. Condition precedent of multi-tier arbitration clause was not satisfied ............................................... 11

B. Claimant did not respond to Pre-trial by Respondent .......................................................................... 11

C. Claimant raised baseless argument of raising issue of pre-arbitral steps at time of filing request... 11

D. Demanding a waiver from Respondent is not reasonable step to resolve dispute amicably. ............ 12

E. Not a single Reasonable step was taken by claimant ............................................................................. 12

F. Claimant did not file request with consultation of Respondent ........................................................... 13

G. “To take reasonable steps to resolve dispute amicably” is a mandatory clause ................................. 13

H. “To take reasonable steps to resolve dispute amicably” is enforceable ............................................... 13

I. Burden lies on both parties ...................................................................................................................... 14

J. No one should be given excessive advantage .......................................................................................... 14

K. RAC Rules recommend pre-trail negotiations or mediation ................................................................ 14

Page 3: COUNSEL FOR RESPONDENT

ii

III. Issue 3: Respondent is entitled to recover the costs associated with preparing for the jurisdictional

hearing that was adjourn. .................................................................................................................................... 15

A. Respondent has right to recover costs under the UNCITRAL, RAC Rules and UNIDROIT

Principles ........................................................................................................................................................... 15

1. Laws does not prevent entitlement to recover costs for adjourned hearing ................................... 15

2. Claimant exercised his due process right in bad faith ...................................................................... 16

B. Cost follows Conduct principle is recognized in Arbitration ............................................................... 16

C. Parties should be treated equally ............................................................................................................ 16

D. Extra expense occurred of Respondent due to adjourned hearing ...................................................... 16

E. Respondent Supports Cost follows event ............................................................................................... 17

F. Delay caused by Claimant could have been avoided ............................................................................. 17

IV. ISSUE 4: THE RESPONDENT IS ENTITLED TO A COMPLETE INDEMNITY FOR THE

COSTS OF PREPARATION AND PRESENTATION OF ITS DEFENCES EVEN IF THE TRIBUNAL’S

JURISDICTION IS NOT DEVELOPED ........................................................................................................... 17

A. The plea for challenging jurisdiction can be made at the procedural stage: ...................................... 18

B. The ‘loser pays’ rule is not only applicable if the respondent loses: .................................................... 18

V. ISSUE 5 ......................................................................................................................................................... 19

A. ISSUE 5(A): THE LIABILITY FOR THE PREPARATION OF A NEW DESIGN

CORRESPONDING TO A NOVEL SITUATION FALL ON THE SHOULDER OF CONTRACTOR.

19

1. The respondent did not lay extra burden on the claimant: .............................................................. 19

2. The contractor cannot be let go of his responsibility if a new situation is emerged ....................... 19

3. The contractor is not liable for time-related costs for the unexpected design difficulty. ............... 19

B. ISSUE 5 (B): THE CONTRACTOR HAD NOT THE RIGHT TO RECOVER THE

TIMERELEATED COSTS INCURRED DURING THE COURSE OF NEGOTIATION WITH THE

EMPLOYER. .................................................................................................................................................... 20

1. The claimant is not facing hardship ................................................................................................... 20

2. The claimant was not allowed to stop the work, fearing non-performance by respondent if any 20

3. The claimant was not entitled to waiver ............................................................................................. 21

C. ISSUE 5 (C): CLAIMANT BEARS THE COSTS FOR ADMINISTRATIVE MOBILIZATION. . 21

1. The mobilization works fall under the duty of the claimant ............................................................ 21

VI. ISSUE 6: THE EMPLOYER IS ENTITLED TO CREDIT FOR THE ANTICIPATED WORK. .. 22

A. The claimant is liable for any delays and defects during the construction work ............................... 22

B. The claimant is not allowed to nonperformance if the work is sophisticated ..................................... 22

C. The employer can ask for the credit for the flawed job performed by the contractor ...................... 22

REQUEST FOR RELIEF.................................................................................................................................... 23

Page 4: COUNSEL FOR RESPONDENT

iii

TABLE OF ABBREVIATIONS

¶/¶¶ Paragraph/Paragraphs

Art./Arts. Article/Articles

Claim. Memo Claimant Memorandum

Clar. ICAM Clarifications 2021

GC General Conditions

ICC International Chamber of Commerce

No. Number

NYC The New York Convention on the Recognition and Enforcement of Foreign Arbitral Awards

p./pp. Page/Pages

PC Particular Conditions

Prob. ICAM Problem 2021

RAC Russian Arbitration Center

RAC Rules RAC Arbitration Rules

RIMA Russian Institute of Modern Arbitration

UNCITRAL UNCITRAL Model Law on International Commercial Arbitration with 2006

amendments

UNIDROIT UNIDROIT Principles of International Commercial Contracts, 2016

Page 5: COUNSEL FOR RESPONDENT

iv

TABLE OF AUTHORITIES

PRIMARY SOURCES

Cited as Full Citation Cited in ¶/¶¶

NYC

Convention on the Recognition and

Enforcement of Foreign Arbitral Awards (New

York, 1958.

26

RAC Rules Russian Arbitration Center’s Arbitration Rules

15-17,22-

25,31,37,39,42,

43,45,47,53,54,62,71-

76,79,85,87,88,91.

UNCITRAL UNCITRAL Model Law on International

Commercial Arbitration with the 2006

amendments

15,17,22-

26,36,42,45,53,75,78,82-

84,87,90

UNIDROIT UNIDROIT Principles of International

Commercial Contracts (2016)

17,70,74,87,94,97,98,99

CASES

Cited as Full Citation Cited in ¶/¶¶

McCron Case

Canada

Birtzu v McCron, 2019 ONCA 777

91

Düsseldorf Case

Germany

Oberlandesgericht Düsseldorf; 14 January 1994

17U 146/93

52

NTPC v Singer Case

India

National Thermal Power Corporation v Singer Co.

and Ors, Supreme Court of India, 7 th May, 1992.

1992 3 SCC, 551.

36

Board of Intermediate

Case

Pakistan

Board of Intermediate and Secondary Education,

Multan v. Fine Star & Company, Engineers and

Contractors [1993 SCMR 530],

64

Hanover Case

Hanover Contractors v. Pakistan Defence Officers

Housing Authority [2002 CLC 1880]

64

Pak. U.K. Association

Case

Pak. U.K. Association (Pvt.) Ltd. v. Hashemite

Kingdom of Jordan [2017 CLC 599]

56

Page 6: COUNSEL FOR RESPONDENT

v

WAPDA Case

WAPDA v. S.H. Haq Noor and Company [2008

MLD 1606]

64

International Research

Corp Case

Singapore

International Research Corp PLC v. Lufthansa

Systems Asia Pacific Pte Ltd [2013 SGCA 55]

57

Singapore High Court

case

Singapore High Court case of HKL Group Co Ltd

v Rizq International Holdings Pte Ltd, [2013]

SGHCR 5

26

Swizz Case

Switzerland

(4A_628/2015) 2016

58

Cable & Wireless Case

United Kingdom

Cable & Wireless v IBM United Kingdom

60

Emirates Trading Case

Emirates Trading Agency LLC v. Prime Mineral

Exports Private Ltd [2014 EWHC 2104 (Comm)]

57

Emirates Trading Case

Emirates Trading Agency LLC v Prime Mineral

Exports Private Ltd [2014] EWHC 2104 (Comm)

61

Paradine Case

Paradine v Jane (1647) EWHC KB J5

104

Steamboat Case

Herne Bay Steamboat Co. v Hutton (1903) 2 KB

683

99

United Group Rail Case

United Group Rail Services Limited v. Rail

Corporation New South Wales [2009 NSWCA

177]

57

William Case

William Cory & Son v Wingate Investments,

(1980) 17 BLR 109

105

Street-Car Case

United States

Klauber v. San Diego Street-Car Co.(1893), 95

Cal. 353

99

Transatlantic Case

Transatlantic Fin. Corp. v. United States - 124

U.S. App. D.C. 183, 363 F.2d 312 (1966)

96

AWARD

ICC Award 6276 ICC International Court of Arbitration, Arbitral

Award 1990, ICC Case No. 6276

48

LETCO Case LETCO v. Liberia, ICSID Case No. ARB/83/2, para.

378

74

Page 7: COUNSEL FOR RESPONDENT

vi

SECONDARY SOURCES

Cited as Full Citation Cited in ¶/¶¶

Berg Albert Jan van den Berg, The New York

Arbitration Convention of 1958: Towards a

Uniform Judicial Interpretation, Deventer:

Boston: Kluwer Law and Taxation 1981

80

Blackaby/Partasides Nigel Blackaby, Constantine Partasides

with Alan Redfern and Martin Hunter,

Redfern and Hunter on International

Commercial Arbitration (5th Ed.) (New

York, Oxford University Press: 2009).

42

Born Gary B. Born, International Commercial

Arbitration Kluwer Law International: New

York, 2nd edn. (2014), pp. 779-780.

28,36,80

BORN Gary Born, International Commercial

Arbitration Austin (2009)

42

Delvolvé/Jean/Gerald Jean-Louis Delvolvé, Jean Rouche and

Gerald H. Pointon, French Arbitration Law

and Practice: A Dynamic Civil Law

Approach to International Arbitration (2nd

ed, Kluwer Law International 2009), pp.

65-67 and Blackaby, n 5, pp. 146-149

27

Derains/Schwartz Derains, Schwartz; Eric A Guide to ICC

Rules of Arbitration, 2nd Ed. Hague (2005)

34

DOUG JONES DOUG JONES, Using Costs Orders to

Control the Expense of International

Commercial Arbitration, The International

Journal of Arbitration, Mediation and

Dispute Management, 2016, p. 298 et seq

81

FOUCHARD/GAILLARD/GOLDMAN Fouchard, Philippe Gaillard, Emmanuel

Goldman, Berthold; On International

Arbitration 1st Edition 1999, Kluwer Law

International, The Hague.

33, 36, 41,44

Frédéric Eisemann

(Frédéric Eisemann, ‘La clause d’arbitrage

pathologique’ in Commercial Arbitration

Essays in Memoriam Eugenio Minoli

(Torino: Unione Tipografico-editrice

Torinese 1974)

27

Page 8: COUNSEL FOR RESPONDENT

vii

Gaillard/Savage Emmanuel Gaillard, John Savage,

Fouchard Gaillard Goldman on

International Commercial Arbitration,

Kluwer Law International (1999)

80

Honnold/Fletcher John O Honnold, Harry Flechtner, Law for

International Sales under the 1980 United

Nations Convention Wolters Kluwers Law

& Business (2009)

52

ICC ICC Case No. 11490 in Albert Jan van den

Berg (ed), Yearbook Commercial

Arbitration, vol. XXXVII (Kluwer Law

International 2012), p. 35.

48

ICC COMMISSION REPORT ICC COMMISSION REPORT, Decisions

on Costs in International Arbitration, ICC

Disp. Resolution Bull 2015/2, para. 78-84,

and Appendix A, p. 23

81

POUDRET, BESSON Comparative Law of International

Arbitration 2nd ed. Zurich (2007)

41

REDFERN, HUNTER Alan Redfern, Martin Hunter, Law and

Practice of International Commercial

Arbitration, 4th Ed. London (2004)

42

Schlectriem/Schwenzer Peter Schlechtriem, Ingeborg Schwenzer,

Commentary on the UN Convention on the

International sale of Goods (CISG), Oxford

University Press (2005)

52

UNIDROIT COMMENTARY Commentary on UNIDROIT Principles of

International Commercial Contracts, Rome,

2010

70

Page 9: COUNSEL FOR RESPONDENT

1

STATEMENT OF FACTS

1. The employer (respondent) from Commonia hires a contractor (claimant), from Civilia. for the

construction of a flood alleviation culvert of 1.5 km in length and 2.4 m in diameter. The culvert was to

be constructed beneath the four-lane highway.

2. A dispute arose after the commencement of construction when uncontemplated 150-year-old iron cast

water main of 1.07m diameter running under the main road was discovered. This iron cast water main

was running at a short distance above the culvert.

3. The information about a similarly aged brick oval main sewer was given by the employer to the

contractor. The contractual price included the stabilizing work for the brick-built water sewer.

4. The water main was discovered during the 3rd week of the construction. It took further 3 weeks to find

its exact position. Then it took 12 more weeks to find a solution acceptable to the statutory water and

local authorities for safely protecting the water main. During these 12 weeks, 7 weeks were passed

preparing the design and 5 weeks for obtaining approvals.

5. The work was stopped during all this time except for an unsuccessful attempt of fiberglass lining

around the brick sewer and it is delayed further because before commencing the stabilization work for

the water main, the contractor seeks a waiver from the Employer for any risk arising from this additional

work. The employer showed reluctance as the contractor is responsible for the ground risks.

6. There is a delay of 3 more weeks before the employer reluctantly gives the waiver. The additional

temporary works last for 8 weeks and the total delay of work is 26 weeks.

7. Due to the huge delay the employer argues the contractor’s entitlement to time-related costs arising

and seeks credit for the additional temporary works required on the basis that the contractor was

responsible for the in-ground risks, so any delay is the contractor’s risk. Secondly, the contractor’s

originally intended work for sewer failed so a similar solution to that of water mains was required

anyway. The contractor should not have delayed construction until the employer signed the waiver.

8. It was agreed by both the parties in the contract to take all reasonable steps to resolve the dispute

amicably, at first and if they choose to arbitrate, they will go to Russian Arbitral Institution. Contractor

bypassed the pre-arbitral steps and directly filed request for arbitration to Russian Arbitration Centre.

9. In his submission before the tribunal, the employer denied the liability for time-related costs and

claimed credit for the temporary works that would always have been required for the brick sewer. The

employer also challenged the jurisdiction of the arbitral tribunal on the basis that parties did not choose

RAC as the administering institution.

10. The employer requested the tribunal for the jurisdictional issue to be heard first to save the cost of

preparing the cases and to keep the merits of the case from being heard until the Tribunal's locale was

established.

Page 10: COUNSEL FOR RESPONDENT

2

11. Due to travel restrictions in the covid pandemic, the tribunal decided to hold the preliminary hearing

on jurisdiction through videoconference. The employer objected, saying that he was entitled under the

arbitration agreement and the RAC Rules to an in-person hearing at the hearing venue. Despite this

objection, the Tribunal ordered a videoconference hearing to determine jurisdiction

12. Three days before the hearing on jurisdiction, the spouse of the Claimant’s counsel contracted Covid-

19. Counsel along with his family was obligated to isolate in their apartment and could not attend the

video hearing.

13. The claimant moved an application for the adjournment of the jurisdictional hearing but with no other

timeslot available between then and the main hearing, the Tribunal indicated to parties that granting the

adjournment could result in the jurisdictional challenge at the outset of the main evidentiary hearing.

14. Claimant maintained its application and the jurisdictional challenge was left to be determined at the

main evidentiary hearing, the Respondent added to its plea a claim for wasted costs, both for the delay

in the jurisdictional determination and for the preparation of the main evidentiary hearing if the Tribunal

finds itself without jurisdiction.

Page 11: COUNSEL FOR RESPONDENT

3

Week 3

• Existance of the water main is discovered in week 3 of construction of the culvert.

Next 3 Weeks

• Survey and ascertainment of exact position of the water main. Work is suspended.

Next 12 Weeks

• Arrive at solution acceptable to the statutory water authority and the local authoirty. 7 Weeks for Preparing Designs & 5 Weeks for Approval to be obtained.

Next 3 Weeks

• Employer refusal to give waiver for any risk arising from additional work. Work is dealyed.

Next 8 Weeks

• Additional Temporary Work

Total Delay

• The total dealy to re-commencement of the tunnel boring work is 26 Weeks.

1.5 month gap

• Gap between the Employer's Pre Trial Letter and Contractor's request for arbitration.

2 Month gap

• Gap between the video conference hearing scheduled (and consequently adjourned) and the main hearing scheduled after that.

TIMELINE OF EVENTS

Page 12: COUNSEL FOR RESPONDENT

4

SUMMARY OF ARGUMENTS

15. The Respondent respectfully submits that the parties do not have a valid arbitration agreement, and

the Russian Arbitration Center does not have the requisite jurisdiction to settle the dispute. Arbitration

agreement is invalid under UNCITRAL and RAC rules. Arbitration Clause does not refer to RAC as

arbitral institution. Claimant did not Adhere to Arbitration Clause. Arbitration Clause does not fulfil

formal requirements of International Arbitration. Arbitration Clause is Ambiguous, defective, unclear

and does not mention seat, applicable rules, and procedure. Answer to Request for Arbitration does not

indicate the validity of arbitration Agreement. Even if there is valid arbitration agreement, the

preconditions to arbitration have not been fulfilled. The Tribunal has the right to decide on its own

jurisdiction and Respondent requests the Tribunal to decide that it has no jurisdiction over the dispute.

[I].

16. Claimant did not take reasonable steps to resolve the dispute amicably. Condition precedent of multi-

tier arbitration clause was not satisfied, Claimant did not respond to Pre-trial by Respondent. Claimant

raised baseless argument of raising issue of pre-arbitral steps at time of filing request. Demanding a

waiver from Respondent is not reasonable step to resolve dispute amicably. Not a single Reasonable step

was taken by claimant. Claimant did not file request with consultation of Respondent. “To take

reasonable steps to resolve dispute amicably” is a mandatory clause. “To take reasonable steps to resolve

dispute amicably” is enforceable. Burden lies on both parties. No one should be given excessive

advantage and RAC Rules recommend pre-trail negotiations or mediation. [II].

17. The respondent is entitled to recover the costs associated with preparing for the jurisdictional hearing

that was adjourned. Respondent has right to recover costs under the UNCITRAL, RAC Rules and

UNIDROIT Principles. Laws does not prevent entitlement to recover costs for adjourned hearing.

Claimant exercised his due process right in bad faith. Cost follows Conduct principle is recognized in

Arbitration. Parties should be treated equally. Extra expense occurred of Respondent due to adjourned

hearing. Respondent Supports Cost follows event. Delay caused by Claimant could have been avoided.

[III].

18. The claimant initiated the proceedings before the tribunal without opting for any amicable resolution.

The arbitration clause clearly stated the prerequisite of the friendly resolution before matter can be taken

up before the tribunal. As a response to the claimant’s wantonly request for the arbitration, the respondent

filed a counterclaim as the last option to still convince the claimant to resort to a mutual friendly

resolution. However, even this step could not convince the claimant to sit for talks which led the

respondent to challenge the jurisdiction of the tribunal in the very next procedural document. As the case

was taken up by the claimant before the tribunal, the respondent is fully liable to be indemnified for the

costs and fees of the arbitration and for presenting the case on the merits of the dispute when the tribunal

finds itself without jurisdiction. [IV].

19. Since the conditions stipulated in the contract, i.e., GC-21, GC-22(B), PC-21, make it the

responsibility of the claimant to have himself satisfied regarding all the risks and novel situations that

may arise during the course of construction. Therefore, the claimant cannot shift the burden on the

shoulders of the respondent. The risk taken by the claimant was foreseen, hence the doctrine of ‘hardship’

cannot be invoked. Also, the mobilization work falls under the duty of the claimant as a normal course

of business. The claimant, consequently, is not entitled to recover time-related costs incurred during

Page 13: COUNSEL FOR RESPONDENT

5

identifying acceptable additional temporary works engineering solution, obtaining waiver from the

employer, and mobilizing the additional temporary works solution. [V].

20. The claimant failed to provide a workable solution for the intended safety work required for the water

sewer, although the contractual price deemed to include it. Though the failed intended safety solution

was a defect on part of the claimant in performing his responsibility, the respondent still agreed to

reimburse for the temporary safety works required for the water main. The mala fide intention of claimant

was obvious when he argued that his liability to provide an alternative solution for the failure to

accomplish his task was not the common intention of the parties. Therefore, the respondent, on the basis

of reimbursement principle developed in the Wingate Investments case, is entitled to credit for the less

extensive temporary works that would always have been required to support the brick sewer. [VI].

Page 14: COUNSEL FOR RESPONDENT

6

ARGUMENTS

I. ISSUE 1: THE PARTIES DO NOT HAVE VAILD ARBITRATION AGREEMENT

BETWEEN THEM

21. The dispute is between the respondent who is employer and the claimant who is contractor in this

case and is about the validity of the arbitration agreement. Employer (Respondent) challenges the

jurisdiction of the arbitral tribunal on the basis that parties did not choose RAC as administering

institution. However, even if the arbitration clause is valid the protracted dealings between the Parties on

these issues cannot be considered reasonable steps taken to resolve the dispute amicably.

22. Claimant puts forth three arguments to show that the Tribunal should have jurisdiction and there is a

valid arbitration agreement. First, Claimant relies on the UNCITRAL and RAC Rules to demonstrate

that there is a valid arbitration clause. Second, it claims that it was the Parties’ intention was to choose

the RAC as the relevant arbitration institution, and third that response to request for arbitration made by

claimant indicated that respondent did recognize the validity of the Arbitration agreement [Claim. Memo.

P. 10].

23. The Respondent submits that all three arguments made by claimant are incorrect. The parties did not

have valid arbitration agreement and the Russian Arbitration Center does not have the requisite

jurisdiction to settle the dispute because: (A) Arbitration agreement is invalid under UNCITRAL and

RAC rules; (B) Arbitration Clause does not refer to RAC as arbitral institution; (C) Answer to Request

for Arbitration does not indicate the validity of arbitration Agreement; (D) Even if there is valid

arbitration agreement, the preconditions to arbitration have not been fulfilled; and (E) The Tribunal has

the right to decide on its own jurisdiction and Respondent requests the Tribunal to decide that it has no

jurisdiction over the dispute.

A. Arbitration Agreement is Invalid under UNCITRAL and RAC Rules

24. Contrary, to Claimant’s assertion, Respondent will prove that the Clause is pathological and invalid

under UNCITRAL and RAC rules because: (1) Claimant did not adhere to arbitration clause (2)

Arbitration clause does not fulfil formal requirements of International Arbitration.

1. Claimant did not Adhere to Arbitration Clause

25. Claimant claims that the validity of the agreement will depend on whether the parties adhered to the

provisions of UNCITRAL Model Law, RAC rules and the contract’s arbitration clause [Claim. Memo, ¶

1, p.10]. Claimant itself did not fulfil the above requirement as both the parties should agree before they

move towards arbitration. The UNCITRAL Art. 7 Option I explicitly require for consent of the parties.

Further that, parties never choose RAC as arbitral institution in arbitration clause. Claimant did not follow

the pre-arbitral steps; hence, claimant itself did not adhere to arbitration clause.

Page 15: COUNSEL FOR RESPONDENT

7

2. Arbitration Clause does not fulfil formal requirements of International Arbitration

26. The Respondent argues that agreement to arbitrate is invalid because it is ambiguous, defective,

unclear, inoperative and does not mention seat, applicable rules, and procedure. Arbitration agreement

will be declared invalid if it is inoperative or incapable of being performed [Art. II (3) NYC; Art. 8(1)

UNCITRAL]. Singapore High Court case which involved a good example of how a badly drafted

arbitration clause increases uncertainty, time and costs for the parties involved. This was because the

arbitration clause in issue was a so-called pathological arbitration clause i.e., a defective arbitration

clause. Clause might be so defective such that it cannot be enforced as an arbitration clause at all.

a) Arbitration Clause is Ambiguous

27. If arbitration agreement is incomplete, ambiguous, incoherent, or contradictory it should not be given

effect and is invalid [Frédéric Eisemann; Delvolvé/Jean/ Gerald].

b) Arbitration Clause is Defective

28. Agreement does not comply with the formal requirements of the law governing the arbitration

agreement. The arbitration agreement is defective as agreement refer to an incorrectly described or a non-

existent arbitral institution or a set of arbitration rules [Born]. Arbitration agreement is inoperative

because it does not state that arbitral tribunal has jurisdiction to hear all disputes relating to the

Agreement.

c) Arbitration Clause is unclear

29. The Tribunal will notice that the Clause differs from the Model Clause. The Clause is so unclear as

to the selected institution and rules that it is impossible for a reader to detect the Parties’ intention, or for

there to be a quick and effective arbitration. Therefore, the Clause frustrates an effective settlement of

the dispute between the Parties and must be considered as incurable and ineffective.

d) Arbitration Clause does not mention seat, applicable rules, and procedure

30. The requirement that the agreement should address issues such as the place of arbitration, the

applicable rules of procedure, the language of the arbitration or the number of arbitrators and the method

pursuant to which they are to be appointed is not fulfilled in arbitration clause in contract.

B. Arbitration Clause does not refer to the Russian Arbitration Centre

31. Arbitration agreement provides that “The Parties agree to resolve all disputes that may arise between

them by arbitration in Russian arbitral institution.”. [Prob., ¶1, p.4]. Claimant asserts that the Parties

intended to choose RAC. However, Respondent claims that the Clause does not refer to RAC for the

following reasons, (1) Parties intention was to choose an institution used primarily for international

arbitration (2) Interpretation does not lead to the conclusion that the Russian Arbitral Institution refers to

Russian Arbitration Centre and (3) There is substantial difference between Arbitration clause in contract

and Model Arbitration clause in RAC Rules.

32. Claimant referred to Hiscox Dedicated Corporate Member v Weyerhaeuser Co [Claim. Memo., ¶2,

P. 10] which is irrelevant to this case because there the question was whether to pursue claim before the

District Court, or to go for arbitration. But in present case, it is unclear which arbitration institution is

meant and which procedure should be followed. The contention of Claimant that parties choose RAC as

Russian Arbitral institution is totally wrong.

Page 16: COUNSEL FOR RESPONDENT

8

1. Parties’ intention was to choose an institution used primarily for international

arbitration

33. In international commercial arbitration it is also a general concept that there should be arbitrational

clause that refers the arising dispute to the arbitration center. According to the principle of interpretation

in good faith, the Parties’ intention was to choose an institution used primarily for international

arbitration. The principle of interpretation in good faith means that the parties’ true intention should

prevail over their declared intention [Fouchard/Gaillard/Goldman]. It states that “when interpreting a

contract, one must look for the parties’ common intention” [Fouchard/Gaillard/Goldman, p. 257].

34. Where the parties involved in an arbitration clause are of different nationalities with no connection

to the place specified in the arbitration clause, tribunals tend to assume that it must have been their wish

to refer their disputes to an institution used primarily for international arbitration [Derains/Schwartz].

The Parties in this case have different nationalites, Commonia and Civilia, and have no connection to the

place specified in the Clause, Russian arbitral institution. It must therefore be assumed that they wished

to refer their disputes to an institution used primarily for international arbitration.

35. Derived from the principles of interpretation applied to arbitration agreements: according to the

principle of interpretation in good faith, the Parties intention was to choose an institution used primarily

for international arbitration. Consequently, the Clause does not refer to the RAC. The most popular and

reliable arbitral institution in Russia for international disputes is the International Commercial Arbitration

Court at the Russian Federation Chamber of Commerce (ICAC). Parties might have intention to choose

the International Commercial Arbitration Court at the Russian Federation Chamber of Commerce

(ICAC) or any other arbitral institution. In any event, the Clause must be interpreted against Claimant

because he itself choose the arbitral institution without consulting respondent.

2. Interpretation does not lead to the conclusion that the Russian Arbitral Institution

refers to Russian Arbitration Centre

36. The interpretation of the arbitration agreement is governed by the law of seat of arbitration [Born p.

489; NTPC v Singer Case], which in the present case is the UNCITRAL Model Law. [Clar., ¶3, p. 3].

According to the principle of effective interpretation, arbitration clauses selecting an inadequately

defined institution can still remain effective when only one such institution exists, i. e. where the

institution can be identified with a sufficient degree of certainty [Fouchard/Gaillard/Goldman, p. 264]

However, the principle of effective interpretation in this case does not lead to the conclusion that the

Russian Arbitral Institution refers to Russian Arbitration Centre.

3. There is Substantial difference between the arbitration clause in contract and the

Model Clause of RAC.

37. RAC provides the standard recommended arbitration clause [RAC Rules, ¶1, p. 8], The clause given

in the problem reads differently [Prob., ¶1, p.4]. There is substantial difference between the arbitration

clause in contract and the Model Clause of RAC. This shows that arbitration clause recommended under

the RAC rules was not made by the parties. In any event, the Clause must be interpreted against Claimant.

Page 17: COUNSEL FOR RESPONDENT

9

Difference between the Clause in Contract and the Model Clause of the RAC

Arbitration Clause Model Clause

Contract RAC Rules

The Parties agree to resolve all disputes that may

arise between them by arbitration in Russian

arbitral institution. The Parties agree first to take

all reasonable steps to resolve the dispute

amicably. Should they choose to arbitrate, they

agree to make all efforts to prepare their claims

and defenses expeditiously and to present their

respective cases at the hearing venue in an

efficient manner.

Any and all disputes, controversies or claims

arising out of or in connection with this

Contract, or a breach, termination or invalidity

hereof, shall be settled by arbitration at the

Russian Arbitration Center at the Autonomous

Non-Profit Organisation “Russian Institute of

Modern Arbitration” in accordance with the

Arbitration Rules.

C. Answer to Request for Arbitration does not indicate the validity of arbitration Agreement

38. Claimant’s contention that giving response or answer to request for arbitration indicates that they did

recognize the validity of the Arbitration agreement [Claim. Memo, ¶3, p.10] is incorrect and false

assumption. Parties does not choose RAC as administrating institution. Even if RAC is considered

arbitral institution then, answer by respondent in request for arbitration made by claimant does not make

arbitration clause valid.

39. The party denying that the tribunal has jurisdiction can file objections to the tribunal's jurisdiction

until the filing of the statement of defences against the claim (counterclaim). Objections to the Arbitral

Tribunal’s jurisdiction may be raised by a Party as it files its first submission related to the merits of the

dispute, i.e. an Answer, a Response to the Claim, a Counterclaim or a Response to the Counterclaim.

[Art. 83(3) RAC Rules]

D. Even if Arbitration agreement is valid, preconditions to arbitration have not been

fulfilled.

40. The preconditions to arbitration have not been fulfilled because the contractor did not take a single

reasonable step to resolve dispute amicably before arbitration can commence. The requirement to “take

reasonable steps to resolve dispute amicably” is a mandatory obligation. Agreements to negotiate in good

faith are enforceable. Claimant is bound to mutually resolve the dispute amicably.

41. In an arbitration proceeding, the primary source of the Arbitral institution’s authority to decide the

dispute is whether the arbitration agreement is entered freely by the parties.

[FOUCHARD/GAILLARD/GOLDMAN, p. 650; POUDRET/BESSON, p. 457]. In present case parties

first agree to take all reasonable steps to resolve the dispute amicably and then if they choose to arbitrate

by arbitration in Russian arbitral institution [Prob., ¶ 1, p.4].

Page 18: COUNSEL FOR RESPONDENT

10

E. Russian Arbitration Center is authorized to determine its own jurisdiction even if

Respondent fails to challenge.

42. RAC must decide its own competence and can rule on its own jurisdiction under the doctrine of

Kompetenz/Kompetenz. It can hear the arguments as to jurisdiction and proceed to decide on its own

jurisdiction [Art. 16, UNCITRAL; Article 5.2 RAC Rules; Art. 83 RAC Rules; BORN, pp. 855-856;

REDFERN/HUNTER, pp. 5-37; Blackaby/Partasides ¶5.99].

43. Objections to the Arbitral Tribunal’s jurisdiction may be raised by a Party as it files its first

submission related to the merits of the dispute, i.e., an Answer, a Response to the Claim, a Counterclaim

or a Response to the Counterclaim. [Art. 83(3) RAC Rules]. In the case it was filed after answer in the

next procedural document. Objection raised by the respondent on jurisdiction is valid.

44. The fact that a party failing to challenge the arbitrators’ jurisdiction does not prevent the arbitrators

from determining whether they do, or do not, have jurisdiction. This is based upon the universally

accepted principle in modern international arbitration according to which arbitrators have the inherent

power to determine whether they have jurisdiction. In other words, arbitrators are competent to determine

their own competence [Gaillard, Savage, Goldman, pp. 395-397].

45. Issue 1 Conclusion: Arbitration agreement is invalid under UNCITRAL and RAC rules. Arbitration

Clause does not refer to RAC as arbitral institution. Claimant did not Adhere to Arbitration Clause.

Arbitration Clause does not fulfil formal requirements of International Arbitration. Arbitration Clause is

Ambiguous, defective, unclear and does not mention seat, applicable rules, and procedure. Answer to

Request for Arbitration does not indicate the validity of arbitration Agreement. Even if there is valid

arbitration agreement, the preconditions to arbitration have not been fulfilled. The Tribunal has the right

to decide on its own jurisdiction and Respondent requests the Tribunal to decide that it has no jurisdiction

over the dispute.

II. ISSUE 2: CLAIMANT DID NOT TAKE REASONABLE STEPS TO RESOLVE THE

DISPUTE AMICABLY.

46. Claimant instead of stating the reasonable steps, made two baseless arguments. Claimant argues first

that respondent should have raised this issue at the time of filing the request. Second, that sought a waiver

from the Respondent by stopping and delaying the work is a reasonable step.

47. The Respondent respectfully submits that claimant did not take reasonable steps to resolve the dispute

amicably and protracted dealings between the Parties on these issues cannot be considered steps taken to

resolve the dispute amicably as: (A) Condition precedent of multi-tier arbitration clause was not satisfied;

(B) Claimant did not respond to pre-trial letter by respondent (C) Claimant raised baseless argument of

raising issue of pre-arbitral steps at time of filing request; (D) Sought of waiver from respondent is not

a reasonable step; (E) Not a single reasonable step was taken by claimant (F) Claimant did not file request

with consultation of Respondent; (G) “To take reasonable to resolve dispute amicably” is a mandatory

clause; (H) “To take reasonable steps to resolve dispute amicably” is enforceable; (I) Burden lies on both

parties; (J) Nobody should be given excessive advantage and; (K) RAC Rules recommend pre-trail

negotiations or mediation.

Page 19: COUNSEL FOR RESPONDENT

11

A. Condition precedent of multi-tier arbitration clause was not satisfied

48. Claimant has admitted that the question on amicable settlement of disputes was a requirement on the

arbitration clause which was part of a contract signed by both parties [Claim. Memo. ¶1, p.11].

Clause imposes an obligation, and such an obligation has not been satisfied.

Where there is a clear and precise condition that was intended to be binding on the parties and was not

fulfilled, arbitrators should reject the request for arbitration as procedurally inadmissible [ICC Award

6276, ICC].

49. Multi-tire clauses, a MTDR clause involves a series of steps in the overall dispute resolution process.

The main point of this type of clause is to offer parties the chance to settle their disputes outside of court

or arbitration. The clauses state, step-by-step, the procedure that the parties should follow to in order to

resolve a dispute. They usually contain different phases, each one independent from the other, such as

negotiation, mediation or expert determination.

50. Arbitration clauses must be construed “strictly”, therefore requiring completion of the “pre-

conditions” to arbitration.

B. Claimant did not respond to Pre-trial by Respondent

51. Claimant instead answering pre-trial letter and trying to solve the despite amicably directly filed

request for arbitration. The time gap between Employer’s Pre-trial Letter and the Contractor’s Request

for Arbitration is 1.5 months [Clar, ¶5 p.3]. Claimant did not make any communication during this time

to resolve the dispute. This statement of claimant is false that respondent did not raise any objection that

claimant did not provide amicable solutions to the dispute.

52. The absence of an assurance of performance in response to a notice constitutes a clear indication that

a breach is going to occur [Düsseldorf case]. Failure to provide adequate assurance is sufficient to permit

avoidance because it becomes clear that claimant will commit a fundamental breach

[Schlectriem/Schwenzer, p. 720; Honnold/Fletcher p. 565]. Additionally, mere retraction of a declaration

of repudiation is no adequate source of future performance [Schlectriem/Schwenzer p. 724].

C. Claimant raised baseless argument of raising issue of pre-arbitral steps at time of filing

request

53. Statement made by Claimant “the claimant sent a request for arbitration to the respondent before

filing. the request” [Claim. Memo., ¶2, p.7] is false and misinterpretation of facts of the case. Right of

respondent to object was not waived under Article 8 of RAC Rules and Article 4 of UNCITRAL. Article

83 of RAC states that “A Party’s claim that the Arbitral Tribunal has exceeded its jurisdiction shall be

advanced as soon as the issue that the Party believes to fall beyond the Arbitral Tribunal’s jurisdiction is

raised in the arbitration.”

54. Article 29 Arbitral Tribunal may for good cause and considering the circumstances of the specific

case, extend the period for submitting the Counterclaim. Under Article 67(2) RAC Rules the Respondent

may file a Counterclaim in accordance with the requirements stipulated by Article 29 of the Arbitration

Rules together with the Response.

Page 20: COUNSEL FOR RESPONDENT

12

D. Demanding a waiver from Respondent is not reasonable step to resolve dispute amicably.

55. The claimant submitted that he sought a waiver from the employer for any risks that may arise from

the additional work and delayed commencing the solution by a further three weeks during which the

issue was being debated, is proof that the Claimant took reasonable steps to resolve the dispute.

Respondent submits that Issue being debated at that time was waiver not entitlement to time-related costs

arising, and credit for the additional temporary works. Pre-trial letter was sent by respondent. Claimant

instead of replying to pre-trial letter of respondent move towards arbitration bypassing the dispute

resolution clause.

56. In Pak. U.K. Association case, court expressed the view that if parties have agreed on certain

conditions that precede the operation of an arbitration clause, such conditions precedent need to be

fulfilled before the arbitration clause can be invoked. The Court noted that in construction or engineering

contracts which provide for a multi-tiered dispute resolution process, an aggrieved party’s right to refer

contractual disputes to arbitration is pre-conditioned with a reference of such disputes, prior to the

commencement of arbitration, to the dispute resolution mechanism agreed upon by the parties.

57. In Emirates Trading Case, the English High Court has held that it is in the public interest to enforce

conditions precedent to arbitration agreements, since commercial entities expect courts to enforce

obligations that they have entered into freely. In International Research Corp case, the Singapore Court

of Appeal determined that preconditions for arbitration must be fulfilled where the parties have clearly

contracted for a specific set of dispute resolution procedures. In United Group Rail Services Case, the

New South Wales Court of Appeal in Australia found a dispute resolution clause in an engineering

contract, which required senior representatives of the parties to undertake “good faith negotiations” prior

to commencing arbitration, to be valid and enforceable.

58. In a Swizz Case,the Swiss Supreme Court decided the long-open question of the consequence of a

failure to comply with a mandatory pre-tier to arbitration, finding that such failure leads to the stay of

the arbitration proceedings until the pre-arbitral tier has been conducted. The case holds that where a

party skips without a valid excuse a mandatory contractual pre-arbitration tier – whether by failing to

initiate the tier at all or by prematurely terminating the tier – the arbitral tribunal must stay the arbitration

until the pre-arbitral tier has been complied with.

E. Not a single Reasonable step was taken by claimant

59. The claimant took no reasonable steps to resolve the matter amicably. Facts quantified that the issue

was deteriorated from the claimant [Prob., ¶5, p.3]. Claimant does not reply to pre-trial letter by

respondent, which is deemed to be the failures in amicably resolving the issue [Prob., ¶3, p.4].

Respondent tried to bring the claimant for the solution, but no response was given by claimant.

60. In Cable & Wireless Case in which the court ruled that pre-arbitral consultation clauses would be

enforced if they were ‘sufficiently defined’ and set out tangible obligations capable of enforcement by

courts (such as requiring parties to initiate mediation, appoint a mediator and present their case).

However, even absent an ‘identifiable procedure’ such clauses would be enforced so long as there was

‘an unqualified reference to ADR, a sufficiently certain and definable minimum duty of participation

should not be hard to find’.

Page 21: COUNSEL FOR RESPONDENT

13

61. Emirates Trading Case has effectively broken new ground by holding that arbitration cannot proceed

unless and until that obligation is satisfied. In the more recent case of Emirates Trading Case the English

High Court upheld a tiered clause which required parties to attempt to resolve their dispute by ‘friendly

discussion’ for a continuous period of four weeks before initiating arbitration. The court enforced the

clause because it was complete and certain in that it required ‘fair, honest and genuine discussions. The

court cautioned against conflating the difficulty of proving a breach with uncertainty and further held

that such clauses were in the public interest (in helping parties avoid an ‘expensive and time-consuming

arbitration’).

F. Claimant did not file request with consultation of Respondent

62. Claimant has filed a ‘claim’ that includes the ‘request’ for commencement of arbitration and that

claim is to be filed after consultation and intimidation to the respondent [Art. 10 of RAC rules].

The claimant made no effort to resolve the dispute amicably but directly approached to the RAC [Prob.,

¶1, p.4].

G. “To take reasonable steps to resolve dispute amicably” is a mandatory clause

63. Claimant took no reasonable steps to resolve dispute amicably before arbitration can commence. The

requirement to “take reasonable steps to resolve dispute amicably” is a mandatory obligation.

Agreements to negotiate in good faith are enforceable. Claimant is bound to mutually resolve the dispute

amicably.

64. In Board of Intermediate Case, the Supreme Court of Pakistan dismissed an application under Section

20 of the Arbitration Act because the applicant had failed to approach the Chairman of the appellant

Board for his decision on the dispute, as provided for in the applicable dispute resolution clause. The

Sindh High Court followed this decision in Hanover Case and the Lahore High Court in WAPDA Case,

with both courts holding that a pre-condition contained in a dispute resolution clause is binding upon the

parties.

H. “To take reasonable steps to resolve dispute amicably” is enforceable

65. In Emirates Trading Agency case, it was held that an agreement to settle disputes amicably is

enforceable. Where the wording of a clause is clear and unambiguous, the provision must be applied as

it reads.

66. It is settled law in most jurisdictions that only when the language is ambiguous can surrounding

circumstances and the commercial purpose of a contract be used as an aid to interpretation. Courts have

applied the same principles of interpretation to dispute resolution and pre-arbitration consultation clauses.

Such clauses are strictly enforceable as pre-conditions to the commencement of arbitration, if they are

sufficiently specific and drafted in mandatory terms [Cable & Wireless Case].

67. In HSBC Institutional Trust Services (Singapore) Ltd (trustee of Starhill Global Real Estate

Investment Trust) v Toshin Development Singapore Pte Ltd [[2012] SGCA 48.] the Singapore Court of

Appeal held that a requirement that parties ‘in good faith endeavour to agree’ was mandatory because it

was in the public interest and because a breakdown of negotiations would cause no harm to the parties,

since the dispute could still be resolved by other means. The decision in HSBC Institutional Trust

Services was followed by the Singapore Court of Appeal in International Research Corp Plc v Lufthansa

Systems Asia Pacific Pte Ltd. [2013] 1 SLR 973.] In Lufthansa, parties had provided for a four-tier

dispute resolution clause requiring consultation by three different committees followed by arbitration as

the final step. The court rejected the argument that seven meetings conducted between the parties

Page 22: COUNSEL FOR RESPONDENT

14

constituted compliance with the clause because ‘the precise persons required to be involved pursuant to

the clause 37.2 process were not so involved’.The court ruled that where parties have stipulated a

‘specific set of dispute resolution procedures as preconditions for arbitration’, substantial compliance

with such preconditions would not be sufficient, actual compliance must be proved.

I. Burden lies on both parties

68. The arbitration clause reads as: "Parties agree first to take all reasonable steps to resolve the dispute

amicably” [Prob., ¶1, p.3]. If we interpret it we see here the word “parties” is mentioned not the party,

so it is not the burden of one party only (claimant) but both.

69. The question here is how effective the language of the clause cited above is helping the parties to

settle their differences. This is because amicably can mean any effort, regardless of how useful that effort

is, for a meaningful and healthy consultation process. Good healthy communication is impossible without

openness, honesty, and vulnerability. But sometimes, one may say, is not healthy to be very open, as

vulnerabilities shared in support of a possible settlement can be used against us in case the attempt is not

successful.

J. No one should be given excessive advantage

70. UNIDROIT vests the right to a party to the contract to avoid an individual term of the contract which

unjustifiably gives the other party an excessive advantage [UNIDROIT, Art. 3.2.7(1)]. It is clear that the

advantage must be one which leads to disequilibrium between the procedural and substantive rights of

the parties to the contract [UNIDROIT COMMENTARY, pp. 108-109]. Mere fact that at the time of the

conclusion of the contract the performance of the obligation assumed was impossible does not affect the

validity of the contract [UNIDROIT Art. 3.1.3].

K. RAC Rules recommend pre-trail negotiations or mediation

71. Article 21(2) RAC provides Prior to the negotiation of the Timetable of Arbitration Proceedings, the

Arbitral Tribunal shall recommend that the Parties consider settling the dispute through negotiation or

mediation. If the Parties agree, the Arbitral Tribunal shall allocate them time and (if required) place to

discuss the issue.

72. Issue 2 Conclusion: Claimant does not take reasonable steps to resolve the dispute amicably.

Condition precedent of multi-tier arbitration clause was not satisfied, Claimant did not respond to Pre-

trial by Respondent. Claimant raised baseless argument of raising issue of pre-arbitral steps at time of

filing request. Demanding a waiver from Respondent is not reasonable step to resolve dispute amicably.

Not a single Reasonable step was taken by claimant. Claimant did not file request with consultation of

Respondent. “To take reasonable steps to resolve dispute amicably” is a mandatory clause. “To take

reasonable steps to resolve dispute amicably” is enforceable. Burden lies on both parties. No one should

be given excessive advantage and RAC Rules recommend pre-trail negotiations or mediation.

Page 23: COUNSEL FOR RESPONDENT

15

III. Issue 3: Respondent is entitled to recover the costs associated with preparing for the

jurisdictional hearing that was adjourn.

73. The Respondent respectfully submits that it is entitled to recover the costs associated with preparing

for the jurisdictional hearing that was adjourn because: (A) Laws give entitlement to recover costs for

adjourned hearing; (B) “Cost follows Conduct” Principle is recognized in Arbitration; (C) Delay caused

by claimant could be avoided; (D) Parties should be treated equally; (E) To determine the question of

jurisdiction is inherent right of tribunal; and (F) Claimant exercised their due process right in bad faith.

A. Respondent has right to recover costs under the UNCITRAL, RAC Rules and

UNIDROIT Principles

74. The respondent is entitled to complete indemnity for the costs of preparing and presenting its defenses

in case the tribunal finds itself without jurisdiction as it is his right given under the article 14(1) of the

RAC rules (Annex I) regarding costs incurred by the parties. It is also evident from the fact the delay of

jurisdictional hearing was because of nonperformance by the claimant so it gives the right to respondent

to complete indemnity of costs under the article 7.4.1 of the UNIDROIT. In LETCO Case, the tribunal

awarded the full costs of arbitration to the claimants including their own expenses holding that “the

decision is based largely on Liberia’s procedural bad faith.

1. Laws does not prevent entitlement to recover costs for adjourned hearing

75. If we analyze different laws of arbitration, we will come to know that a party can recover costs for

adjournment from other party. It is nowhere mentioned in (1) RAC Rules or (2) UNCITRAL that a party

cannot claim for wasted costs, both for the delay in the jurisdictional determination and for the

preparation of the main evidentiary hearing if the Tribunal finds itself without jurisdiction. Claimant

himself caused the delay by moving application for adjournment and therefore respondent is entitled to

recover any costs caused by such delay.

a) RAC Rules does not prevent respondent to recover costs for adjourned hearing

76. RAC Rules mentions the instances where the arbitration fee can be reduced and refunded but it is not

described anywhere that any party is not entitled to the recovery of the cost when the hearing is adjourned.

[Rules on Arbitration Fees and Arbitration Costs RAC Rules]. Hence, respondent is entitled to the

complete indemnity of the costs of preparation. The related provision Art. 13 RAC Chapter: Rules on

Arbitration Fees and Arbitration Costs clearly states this rule that in a case where the arbitration cannot

proceed “, the arbitration fee and arbitration costs shall be paid by the Claimant.” [Art. 13 RAC Chapter:

Rules on Arbitration Fees and Arbitration Costs]. Under the ambit of Article 60, lack of jurisdiction also

serves as the basis for the termination of the arbitration proceedings [Art. 60(2)(B), RAC Rules].

77. The Arbitral Tribunal shall consider the amount of the claims advanced, the value of the claim, the

complexity of the dispute, the scope of the representative’s services, the time necessary for drafting

procedural documents, the length of dispute resolution when placing the costs incurred by that Party as

well as other specific circumstances of the dispute. If the Arbitral Tribunal decreases the amount of the

costs of the Parties and third parties. The arbitral award shall be accompanied by a reasoned opinion of

the Arbitral Tribunal specifying the reasons for decreasing the amount of the costs [Article 14 (2,3,4)

Rules on Arbitration Fees and Arbitration Costs RAC procedural rules]. Therefore, respondent is entitled

to recover the cost based on adjournment of hearing.

Page 24: COUNSEL FOR RESPONDENT

16

b) UNCITRAL does not prevent respondent to recover costs for adjourned hearing

78. UNCITRAL is silent about the allocation and recovery of the cost of arbitration and arbitration fee by

a party from another in case of adjournment of hearing.

2. Claimant exercised his due process right in bad faith

79. The Parties shall exercise their due process rights in good faith without abuse and comply with the

specified terms (periods of time) for exercising the same. The Parties shall cooperate in good faith and

take all possible measures to increase the efficiency of arbitration and resolution of disputes [Art. 20(2)

,21(5) RAC Rules]. Claimant exercised due process right in bad faith to adjourn the hearing and

maintaining application to adjourn hearing knowing that no other time slot is available.

80. Good faith and Bad faith are one of the most universally applied principles in interpreting

international arbitration agreements [Gaillard/Savage ¶ 256]. This is the result of the belief that good

faith is enshrined in the provisions of the New York Convention [Berg ¶ 185; Born p. 1475]. Further,

the principle is recognized in most civil law [French Civil Code, Art. 1156; German BGB, Art. 133] and

common law [UCC Sec. 1-304] jurisdictions. Therefore, good faith and bad faith are applicable here in

this case based on international law practices.

B. Cost follows Conduct principle is recognized in Arbitration

81. There are various scenarios that might warrant considering the parties’ conduct in cost decisions. In

general, the circumstances that call for the application of the “costs follow conduct” rule have been

described such as falsifying witness or expert evidence, late counsel appointments that create a conflict

of interest, repeated unsuccessful challenges against an arbitrator, voluminous or continuous document

requests, unjustified failure to meet deadlines, false submissions to the tribunal, failure to comply with

procedural orders, excessive legal arguments or exaggerated claims, dilatory tactics, due process paranoia

etc. [DOUG JONES; ICC COMMISSION REPORT].

C. Parties should be treated equally

82. Claimant stated that According to Article 18 of the UNCITRAL Model Law on International

Arbitration, the parties shall be treated with equality and each party shall be given a full opportunity of

presenting his case. Claimant’s counsel was unable to attend these proceedings as a result of the isolation

requirements. [Claim. Memo, ¶1, p.11] Claimant counsel could have attended hearing from home. Both

parties should be treated equally, why respondent should have extra burden for the adjourned hearing

This case law Fontaine v Amesbury [Claim. Memo, ¶1, p.11] has no relevance with arbitration and is

based on civil procedure rules which are quite different and have different procedure and jurisprudence.

83. Parties shall be treated with equality. [Art. 18 UNCITRAL]. So as the claimant counsel’s spouse is

infected with COVID-19 not the claimant counsel. Claimant has enough opportunity to avoid the delay

of hearing.

D. Extra expense occurred of Respondent due to adjourned hearing

84. Article 28 (1) of the RAC Arbitration rules states that “The Respondent is entitled to file with the

Claimant, the Arbitral Tribunal and the RIMA a Response to the Claim…” Moreover, article 23(1) of

the UNCITRAL Model Law stipulates that “...the respondent shall state his defence in respect of these

particulars, unless the parties have otherwise agreed as to the required elements of such statements...”

Extra expense occurred of Respondent due to adjourned hearing.

Page 25: COUNSEL FOR RESPONDENT

17

E. Respondent Supports Cost follows event

85. With regard to the fees and costs payable to the Arbitration Institution, Article 13(1) of the RAC

Rules of Arbitration Fees and Arbitration Costs aligns itself with the arbitration principle that “costs

follow events”. The Article stipulates that the arbitration fee and arbitration costs shall be paid by the

Party against which the arbitral award is rendered. These fees and costs are therefore to be borne by the

claimant against whom the arbitral award should be made as shown by the arguments presented in this

document.

F. Delay caused by Claimant could have been avoided

86. Three days before the hearing on jurisdiction claimant’s spouse contracted Covid-19 and the

claimant’s counsel said that the obligation for the family to isolate together in their small apartments

prevented him from attending the video conference and there was no time to retain and instruct another

advocate [Prob., ¶5, p.4]. The restrictions are the part of public regulations which are mandatory and are

like those, imposed all over the world during the severe stage of the pandemic [Clar, ¶5, p.3]. Claimant

counsel had enough time to manage online hearing at home. Claimant only wanted to delay the

jurisdictional hearing knowing that no other time slot is available.

87. Issue 3 Conclusion: The respondent is entitled to recover the costs associated with preparing for the

jurisdictional hearing that was adjourned. Respondent has right to recover costs under the UNCITRAL,

RAC Rules and UNIDROIT Principles. Laws does not prevent entitlement to recover costs for adjourned

hearing. Claimant exercised his due process right in bad faith. Cost follows Conduct principle is

recognized in Arbitration. Parties should be treated equally. Extra expense occurred of Respondent due

to adjourned hearing. Respondent Supports Cost follows event. Delay caused by Claimant could have

been avoided.

IV. ISSUE 4: THE RESPONDENT IS ENTITLED TO A COMPLETE INDEMNITY FOR

THE COSTS OF PREPARATION AND PRESENTATION OF ITS DEFENCES EVEN IF THE

TRIBUNAL’S JURISDICTION IS NOT DEVELOPED

88. The issue in dispute corresponds to the eligibility of the respondent for the indemnity of the arbitration

fee and costs. The facts of the case state that the issue was taken by the claimant before the tribunal. The

bar to bear all the costs lies on the claimant if the tribunal’s jurisdiction is not established. The related

provision Art. 13 RAC Chapter: Rules on Arbitration Fees and Arbitration Costs clearly states this rule

that in a case where the arbitration cannot proceed “, the arbitration fee and arbitration costs shall be

paid by the Claimant.” [Art. 13 RAC Chapter: Rules on Arbitration Fees and Arbitration Costs]. Under

the ambit of Article 60, lack of jurisdiction also serves as the basis for the termination of the arbitration

proceedings [Art. 60(2)(B), RAC Rules]. This force behind this rule is further elaborated in Article 83(6)

as, “If the Arbitral Tribunal renders an order on the lack of jurisdiction, it shall not examine the dispute

on the merits” [Art. 83(6), RAC Rules]. Because of the tribunal’s termination of arbitration to proceed

on the merits of the case, the costs and fees incurred are to be borne only by the person who took the

matter before the tribunal.

Page 26: COUNSEL FOR RESPONDENT

18

A. The plea for challenging jurisdiction can be made at the procedural stage:

89. The claim made by the claimant regarding the illegality of the respondent to question the Jurisdiction

of the tribunal in the first procedural document does not stand ground [Claim. Memo. ¶1, p.13].

According to the Director of the Australian Centre for International Commercial Arbitration and the

Australian Disputes Centre, Mrs. Bronwyn, plea for Challenging jurisdiction of the tribunal can be made

at the procedural stage even at the enforcement stage of the award [Challenges to the jurisdiction of an

arbitral tribunal at the award enforcement stage (2018) Brown Lincoln].

90. Furthermore, there is a vivid proviso that is very stated in the said article about the admission of the

jurisdictional plea, ‘‘The arbitral tribunal may admit a later plea if it considers the delay justified”

[UNCITRAL, Art 16(2)]. The facts of the case state that the counterclaim was not initiated in the first

instance when the matter was filed before the arbitration institution, it was the ‘reaffirmation’ of the

respondent’s stance that was already reiterated before the initiation of the proceedings. The respondent

already conveyed his concerns [Prob., p.3] to the claimant, and the claimant without paying any heed to

such concerns and opting for a an ‘amicable resolution’ [Prob, p.4] directly took the matter before the

arbitration. The conduct of the claimant shows reluctancy to sort the matter out in a friendly and workable

environment. The respondent never wanted to put the dispute before the worthy arbitrators when there

was an opportunity for an easier solution. The counterclaim by the respondent before the arbitration

center was a result of the disheartened feelings and the reaffirmation of the respondent’s stance against

the scheme of the claimant. The intentions of the respondent remained for a friendly solution even after

he filed the counterclaims but even this step did not make the claimant to recourse to an amicable

solution, and he remained persistent by sorting this issue out from the worthy arbitrators. When the

respondent was convinced that there left no chance for a recourse, he finally decided to get along with

the method that the claimant has been persistent to adopt and thus raised the question of jurisdiction in

the very first procedural document before the tribunal [Prob., p.4].

B. The ‘loser pays’ rule is not only applicable if the respondent loses:

91. The claimant made reference to the Article 13 sub-clause 1 of the RAC Rules on Arbitration Fees

and Arbitration Costs [Claim. Memo, ¶ 3, p. 13] in which he reiterated the principle that the party against

whom the award is rendered is liable to bear the costs and fee of the arbitration. The principle of ‘loser

pays’ as mentioned in the claimant’s memo [ibid] is not merely applicable if the claimant wins the case.

This principle has its application vice-versa, i.e., any litigant party winning the case has the right for

credit for the costs borne by that party. The application of this principle was clearly evident in the McCron

case, where the court of appeal for Ontario order the claimant to compensate the defendant for her costs

that she incurred in the proceedings. The issue framed by the arbitrators asks for the eligibility of the

respondent for indemnity in case the tribunal finds itself without jurisdiction. The comments made by

the claimant himself and the caselaw mentioned makes it the vested right of the respondent for indemnity

when the tribunal finds itself with no jurisdiction.

92. Issue IV Conclusion: The claimant initiated the proceedings before the tribunal without opting for

any amicable resolution. The arbitration clause clearly stated the prerequisite of the friendly resolution

before matter can be taken up before the tribunal. As a response to the claimant’s wantonly request for

the arbitration, the respondent filed a counterclaim as the last option to still convince the claimant to

resort to a mutual friendly resolution. However, even this step could not convince the claimant to sit for

talks which led the respondent to challenge the jurisdiction of the tribunal in the very next procedural

document. As the case was taken up by the claimant before the tribunal, the respondent is fully liable to

Page 27: COUNSEL FOR RESPONDENT

19

be indemnified for the costs and fees of the arbitration and for presenting the case on the merits of the

dispute when the tribunal finds itself without jurisdiction.

V. ISSUE 5

A. ISSUE 5(A): THE LIABILITY FOR THE PREPARATION OF A NEW DESIGN

CORRESPONDING TO A NOVEL SITUATION FALL ON THE SHOULDER OF

CONTRACTOR.

1. The respondent did not lay extra burden on the claimant:

93. The contractor is deemed to have obtained all the necessary information and is satisfied with the

contract and all the inground requirements. The contractor was given ample time to analyze the area. The

clause GC-21 of the contract establishes that the Contractor shall be deemed to have inspected and

examined the Site, access to the Site, its surroundings, the information available, and to have been

satisfied before submitting the Tender as to all matters relevant to the execution of the Works. Even in

the presence of this condition, the respondent did not burden the claimant when the water main was

discovered and agreed to bear the time-related costs that incurred in its discovery, investigation, and the

execution of its temporary engineering works.

2. The contractor cannot be let go of his responsibility if a new situation is emerged

94. Furthermore, in the Particular Condition 21, the contractor was not bound to assume the details only

about the sewer or the similar structure. The contractor was to submit his tender by assuming all the

possible conditions that can exist in the sub-soil. Corbin explained this situation as, “He (the contractor)

is not discharged from duty by actually unexpected difficulties or expense, and he has no right to extra

pay for completing job “[Corbin on Contracts, sec 1333]. The argument made by the opposing counsel

that since the work was unseen, “therefore it would be the duty of the employer to pay as priced by the

contractor for such works” [Claim. Memo, ¶ 1, p. 14] are clearly ultra-virus to the vivid conditions

stipulated in GC-21, GC-22(B), and PC-21 of the contract. In their memorandum the claimant has argued

that the article 1.9 of the UNIDROIT Principle binds the parties by usage [Claim. Memo, ¶ 2, p. 14].

However, the commentary of the said article vividly elaborates that not every transaction can be said to

have constituted a usage to be followed. “Whether a particular practice can be deemed to be

“established” between the parties will naturally depend on the circumstances of the case, but behaviour

on only one previous transaction between the parties will not normally suffice.” [UNIDROIT Principles

Art. 1.9, ¶ 2, p. 24]. The previous transactions made between the parties had the force of the very contract

contracted by the parties. Therefore, the driving force for the future transactions shall also be the contract.

3. The contractor is not liable for time-related costs for the unexpected design difficulty.

95. In one of the most famous construction cases, the House of Lords decided on the matter related to

unexpected difficulty that emerged during the construction [Tharsis Sulphur & Copper Co v M’Elroy

(1878)]. the respondents were employed to erect a structure including cast-iron trough girders. They

attempted to cast the girders in accordance with the specified dimensions but found that the girders were

liable to warp and crack at that thickness. Girders with increased thickness to overcome the problem. On

completion of the work, the respondent contractor claimed a considerable amount in excess of the

contract price for the extra weight of metal supplied however, the claim was rejected. All the in-grounds

Page 28: COUNSEL FOR RESPONDENT

20

risks were the responsibility of the claimant. Therefore, the respondent cannot be asked to bear the load

of the claimant’s responsibility.

96. In Transatlantic case the court did not accept the excuse of impracticality of the voyage when there

was another possible route. Therefore, the court did not excuse the plaintiff of his responsibility to sort

to the other possible means to do the job. The time-related costs for the acceptable works engineering

solution falls on the shoulders of the claimant to bear as a part of the overall contract that the claimant

willfully entered into, to get the job done. The claimant implied in his arguments that the Engineer being

working for the respondent was liable for the delay caused to the project, hence, the respondent would

be liable for the delay caused by the Engineer. The Engineers works as an independent body; therefore,

the respondent cannot be said to have the vicarious liability of the Engineer. Furthermore, the works were

stalled during this inspection which is also contrary to the GC-23 clause B as stipulated in the contract.

Therefore, the claimant is not entitled for the time-related costs for the identification of the temporary

works engineering solution.

B. ISSUE 5 (B): THE CONTRACTOR HAD NOT THE RIGHT TO RECOVER THE

TIMERELEATED COSTS INCURRED DURING THE COURSE OF NEGOTIATION

WITH THE EMPLOYER.

1. The claimant is not facing hardship

97. The claimant stated in his memorandum, “Additionally, the Claimant ‘foresaw’ significant risks

arising from the execution of these extra works. This amounted to hardship as defined in the Article

6.2.2(b)of the UNIDROIT Principles of International Commercial Contracts.” [Claimant’s memo, ¶ 4,

p. 15]. The claimant agreed to condition that the risks were foreseen. In sub-clause D of the said principle,

it is clearly stated that the hardship would only be constituted if “the risk of the events was not assumed

by the disadvantaged party.” [Art. 6.2(2)(D) UNIDROIT Principles 2016]. As the claimant admitted that

the risks were foreseen by him, his claim regarding the constitution of the hardship will stand ultra-virus

to the condition stipulated in the UNIDROIT Principles.

2. The claimant was not allowed to stop the work, fearing non-performance by

respondent if any

98. The opposing counsel argued the application of the Article 7.3(4) of the UNIDROIT Principles and

stated in their memorandum, “The works to be undertaken would have resulted in significant losses to

the Claimant if the Respondent did not perform.” [ Claim. Memo, ¶ 4, p. 15]. The facts of the case do

not point out to any responsibility that the respondent was liable to perform, nor there was any such

condition stipulated in the contract. The respondent is only liable in terms of payment to the claimant for

the work done as stipulated in the agreement. The only performance was on the part of the claimant to

carry the work as agreed upon. Here the only non-performance is on part of the contactor himself because

he intentionally paused the works which cost the employer a lot of additional time to complete the project.

The claimant further argued that because of the ‘equitable estoppel’ as enshrined in ‘Hughes v.

Metropolitan Rly’ [Claimant’s memo, ¶ 5, p. 15], the respondent is estopped from denying the

responsibility. The facts of the case nowhere state that the respondent backed from the waiver. The

respondent, till the completion of safety work, took full responsibility of any damage arising out of the

work. The claimant argument clearly depicts misappropriation of the facts.

Page 29: COUNSEL FOR RESPONDENT

21

3. The claimant was not entitled to waiver

99. In Street-car case it was held that mere difficulty of performance cannot serve as an excuse for the

non-performance of an act. Same view was reiterated in the Steamboat case where it was stated that the

difficulty cannot frustrate a contract. According to clause G-23 of the contract, the contractor signed after

taking into account all the risks that could arise. The demand for waiver was not an inherent right of the

claimant because it is duty of the contractor to deal with the risks involved in the work [ibid]. The

employer could not have been forced to take responsibility of the claimant’s job. But the coercion made

respondent to reluctantly acquiesce to waiver, as his work was stopped for the whole three weeks, and

he was suffering substantial loss during that time. Article 7.1(1) defines non-performance, and the

employer is entitled to claim damages for this deliberate non-performance under article 7.4(1) of the

UNIDROIT Principles [Art. 7.1(1) & 7.4(1) UNIDROIT]. Furthermore, article 1.7 of UNIDROIT

establishes principle of good faith and fair dealings and the claimant also violated this law by

intentionally withholding the execution of work and coercing the respondent to accept the waiver. Hence

the respondent is entitled to recover the time-related costs during the time claimant stalled the work to

get the waiver.

100. The claimant argued that he is entitled to costs incurred in the process of negotiations and gave

reference to Rees & Kirby v. Swansea City Council [Claimant memo, ¶ 6, p. 15]. The mentioned case

only allows for the entitlement when the event falls under the auspices of the contract. The event of

waiver is an independent one and was not contemplated while entering into contract. Therefore, this

referenced case by the opposing counsel cannot be applied to our situation.

C. ISSUE 5 (C): CLAIMANT BEARS THE COSTS FOR ADMINISTRATIVE

MOBILIZATION.

1. The mobilization works fall under the duty of the claimant

101. The claimant, being the contractor, is responsible for all the risks emerging out of the work. This

condition was not imposed on the claimant, rather he willfully agreed to such conditions while entering

into the contract. GC-22 makes the claimant to bear any responsibility related to his course of work i.e.,

“Contractor’s obligations under the Contract and all things necessary for the proper execution of the

Works in accordance with the Contract.” The mobilization work is required for the proper execution of

the work. This work falls under the routinely conduct of contractor’s business. Mobilization, be it

administrative, is a precursor for any work. It is not prudent to put the liability of a person on the shoulders

on another. Any work-related situation emerging in the construction is the duty of the contractor to

handle. Therefore, any delay should be answered by the contractor managing the contract. Condition

2.32 & 2.3.7 of the Standard Form of Building Contract allows the employer to recover liquidated or

delay damages where “the contractor has failed to complete the works by the Completion

Date”[Standard Form of Building Contract SBC(2005) Condition 2.32 & 2.3.7]. Therefore, the claimant

cannot be made entitled to recover the time-related costs for the mobilisation works that were actually a

part of his duty.

102. Issue 5 Conclusion: Since the conditions stipulated in the contract, i.e., GC-21, GC-22(B), PC-21,

make it the responsibility of the claimant to have himself satisfied regarding all the risks and novel

Page 30: COUNSEL FOR RESPONDENT

22

situations that may arise during the course of construction. Therefore, the claimant cannot shift the burden

on the shoulders of the respondent. The risk taken by the claimant was foreseen, hence the doctrine of

‘hardship’ cannot be invoked. Also, the mobilization work falls under the duty of the claimant as a normal

course of business. The claimant, consequently, is not entitled to recover time-related costs incurred

during identifying acceptable additional temporary works engineering solution, obtaining waiver from

the employer, and mobilizing the additional temporary works solution.

VI. ISSUE 6: THE EMPLOYER IS ENTITLED TO CREDIT FOR THE ANTICIPATED

WORK.

A. The claimant is liable for any delays and defects during the construction work

103. The solution anticipated for the water sewer was not up to the mark in the first place. Therefore, a

more substantial solution would have always been required. The employer is eligible to ask for the better

solution at the cost of contractor’s money. Condition 3.18 of the SBC provides that if the work is not

followed as stipulated in the contract, then “it is made good at the contractor’s cost (in terms of time and

money).” [Standard Form of Building Contract SBC(2005) Condition 3.18]. Condition 2.1 further

elaborates that if there happens to be some defects during the during the construction, against what was

stipulated in the contract, “the contractor will be responsible if the need to remedy these defects causes

delay to the project” [Standard Form of Building Contract SBC (2005) Section 2.1]. The defect in the

workable safety solution should be rectified by the claimant under the same cost as stipulated in the

contract.

B. The claimant is not allowed to nonperformance if the work is sophisticated

104. In Paradine case it was developed that the impossibility to perform a duty cannot serve as an excuse

for nonperformance. It was maintained that “Where a party creates a duty or charge upon himself by

virtue of a contract, he is bound to perform the duty or pay the charge” [Paradine Case]. The employer

cannot be expected to pay for the nonperformance on part of the claimant, therefore, making claimant

liable for the costs emerging out of it. The claimant argued that there was no common intention between

the “any amounts of works not accomplished would be diverted to any extra scope of works.” [Claimant

memo, ¶ 1, p. 16]. This argument portrays the mala fide intention of the claimant for the nonperformance

of his duty.

C. The employer can ask for the credit for the flawed job performed by the contractor

105. According to Jeremy Glover where an employer can be seen to rely on a contractor for the design,

the contractor’s legal responsibility is to produce (in the absence of express provision in the contract) a

final work which is reasonably suitable for its purpose [Jeremy Glover, Liability for Defects in

Construction Contracts - who pays and how much? ¶ 38, p. 8]. The claimant is bound to offer the work

as it was stipulated in the contract. It was construed in the contract that the cost for a workable solution

for the protection of water sewer would be deemed to be included in the contractual price. It was later

revealed that the intended solution to be provided was flawed. Though the employer paid for the

temporary works required for the new solution, but he cannot be burdened to bear the costs of the flawed

intended solution. This view was maintained in Wingate Investments case, where the claimants were

Page 31: COUNSEL FOR RESPONDENT

23

warehousemen who had entered into arrangements whereby the hardstanding’s should have been

concrete. Instead, they were constructed of tarmacadam. It was maintained by the court that “the prima

facie rule is that the Plaintiff is entitled to such damages as will put him in a position to have the building

to which he contracted”[William Case]. Accordingly, it can be said that, as the intended safety work for

the water sewer failed and the respondent even agreed to reimburse the claimant for the costs incurred

during the temporary work adopted for the safety of the water main, the respondent is entitled for the

credit of the temporary works that would always have been required for the brick sewer and were

construed when entering into the contract.

106. Issue 6 Conclusion: The claimant failed to provide a workable solution for the intended safety work

required for the water sewer, although the contractual price deemed to include it. Though the failed

intended safety solution was a defect on part of the claimant in performing his responsibility, the

respondent still agreed to reimburse for the temporary safety works required for the water main. The

malafide intention of claimant was obvious when he argued that his liability to provide an alternative

solution for the failure to accomplish his task was not the common intention of the parties. Therefore,

the respondent, on the basis of reimbursement principle developed in the Wingate Investments case, is

entitled to credit for the less extensive temporary works that would always have been required to support

the brick sewer.

REQUEST FOR RELIEF

In the light of the above submissions, the Counsel for Respondent requests the Arbitral Tribunal to:

1. Declare that parties do not have a valid arbitration agreement between them;

2. Declare that Respondent is entitled to recover the costs associated with preparing for the

jurisdictional hearing that was adjourn;

3. Admit the respondent’s claim for indemnity.

4. Reject the claimant’s claim of time-related costs incurred during the process of:

a) Reaching an acceptable temporary engineering works solution,

b) Negotiating with the respondent for waiver, and

c) Mobilising temporary works solution.

5. Accept respondent’s claim to credit for the less extensive anticipated work;

6. Order the Claimant to pay the costs of these arbitration proceedings;

7. Grant any other relief that the Arbitral Tribunal deems necessary.

12 September 2021