  • 8/8/2019 Cost Coding System-old

    1/1

    Method of getting Cost Code

    Cost Code = XX-YYY-ZZ

    General

    IntakeDam-General

    RiverDiversion

    Dam

    Structure

    IntakeFacilities

    RBServiceRoad

    LBServiceRoad

    HeadpondArea-General

    LandReclamation

    A7HighwayBridge

    River&SlopeProtection

    RelocationofA7

    BridgeNo.2

    RelocationRoadacross

    Railway

    SlopeTreatment-Land

    SlideArea

    ProtectionWork-Railway

    Bridge

    SolidWasteDisposal

    Facility

    HeadraceTunnel-General

    Adit-1

    Adit-2

    HRTunnel

    DewateringChannel

    Adit-4

    UpstreamSurgeTank-

    General

    SurgeTank

    ReclamationArea

    ServiceRoadto

    ReclamationArea

    ExistingRoadImprovement

    Penstock-General

    PenstockTunnel

    Adit5

    Adit6

    LandReclamation

    Powerhouse-General

    PowerCavern

    AccessTunnel

    CableTunnel

    Tailrace-General

    TailraceTunnel

    D/SSurgeChamber

    AccessTunneltoD/SSC

    OutLet

    OutdoorSwitchyard

    ArchitechturalWorks-

    General

    IDControlBuilding

    PowerHouse

    SYControlBuilding

    SYVentilationBuildings

    SYStandbyGenerator

    Building

    CarShelters

    GuardHouses

    IDGateControlHouse

    IDMaintenanceOffice

    SWDA

    SYMaintenanceOffice

    SWDA

    St.ClareViewingGalery

    050 100 110 120 130 140 150 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 400 410 420 430 440 500 510 520 530 540 600 610 620 630 700 710 720 730 740 800 900 910 920 930 940 950 960 970 980 990 991 992

    00Land

    01 General

    02 Site Investigation & Testing

    03 Site Installations and Services

    04 Surveying

    05 River Diversion and Care of Water

    06 Clearing, Grubbing, and Stripping

    07 Open Excavation

    08 Underground Excavation

    09 Banking and Backfill

    10 Drilling and Grouting

    11 Concrete Works

    12 Reinforcing Steel

    13 Masonry for Civil Works

    14 Shotcreting

    15 Rock Bolt

    16 Steel Support

    17 Slope Protection

    18 Drainage

    19 Instrumentation

    20 Road Work

    21 Concrete Bridge

    22 Grounding System

    23 Metal Work for Civil Works

    24 Miscellanious Work for Civil Structures

    25 Structural Steel Works

    26 Metal Work for Buildings

    27 Masonry Works for Buildings

    28 Painting

    29 Waterproofing

    30 Plaster

    31 Tiling

    32 Finishing Work

    33 Door and Window

    34 Architectural Miscellanious Works

    35 Illumination System and Power Control System

    36 Fire Protectioin System

    37 Plumbing System

    38 Ventilation and Air-Conditioning System

    39 Elevator

    40 Miscellanious Building and Facilities

    41 Utilities

    42 Environmental & Safety

    43 Temporary Works

    01 Cement

    02 Aggregates03 Tunnel Steel Material

    04 Reinforcements

    05 Other Steel Material

    06 Wooden Material

    07 Explosives and Detonators

    08 Electrical

    09 Other materials

    10 Plant and equipments

    11 Labour

    12 Fuel, Oil and Lubricants

    13 Sub-Contractors

    14Land

    15 Overheads

    16 Spare parts

    20 All others

    97 E.P.F.

    98 E.T.F

    99VAT

    XX-SpecificationWorkActivity(BQCode)

    YYY - Work Section (Area Code)

    ZZ - Resource Unit (Cost Code)