corrigendumgc14est287[1]
DESCRIPTION
aaaTRANSCRIPT
-
GUWAHATI REFINERY
Dated: 14thFeb 2015
SUB: CORRIGENDUM OF TENDER
Tender No. / Name of work Critical Dates
1. GC14EST287: EPCM Services for Revamp of Existing Flare with Additional NewFlare System at Guwahati Refinery.
Download : 23.01.15 to 21.02.15Bid Submission : 14.02.15 to 21.02.15Opening : 23.02.15
This is with reference to the Tender No.GC14EST287 for which Pre-Bid meeting was held on 09.02.15. During the Pre-Bid Meeting various issueswere discussed and clarifications is being issued here by for the queries asked by one of the bidder which is given below in Part-A. In addition tothe clarification of queries, corrigendum is being issued for technical clarification regarding clause no 3.16 of Chapter-1 of Annexure-A which isgiven below in Part-B:
PART-A (CLARIFICATION OF QUERIES):
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
1 Annexure A Chapter-1 4 of 52 3.14 SIL We presume other studies
such as SIL are not required.
Please confirm
Confirmed.
However, for field
instruments where SIL is
applicable it is to be
incorporated.
2 Annexure A Chapter-1 4 of 52 3.14 HAZOP Please confirm whether External HAZOP chairman
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
external HAZOP Chairman is
required?
is required.
3 Annexure A Chapter-1 2 of 52 3.2 Development of
P&IDs for the
existing flare
network
Please confirm that Existing
editable copy of P&IDs would
be given by IOCL
P&IDs of existing flare
network will be required to
be developed. IOCL will
provide the hard copy of
the present flare network
for reference. This P&ID
however is not as-built at
site.
4 PDS Flare system 1 of 2 - Reference P&ID
nos: A447-02-41-
010-1111
P&IDs mentioned in
datasheet would be made
available by IOCL. Please
confirm.
Confirmed.
5 Annexure A
Annexure 1 to Chapter 2
36 of 52 3.4 Consultant shall
use PDS and / or
other design and
engineering
software for
preparing detail
Bidder has considered only
New Facilities related to
Flare System for 3D
Modelling.
Existing Facilities are not
Bidder has to incorporate
existing Flare Header
(Outside Battery Limits of
Units) also in new 3-D
Modelling of complete flare
system.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
engineering works. considered for 3D Modelling.
Kindly Confirm
As such the 3 D model
shall be a composite model
incorporating both the
existing and new flare
system.
6 Annexure A
Annexure 1 to Chapter 2
37 of 52 3.7 (ii) Stress Analysis Stress Analysis Reports and
documentation of Existing
Flare System shall be made
available to bidder.
Kindly confirm
Stress analysis is under the
scope of EPCM consultant
and the stress analysis
data will be taken as input
for detailing. IOCL will be
accept the stress analysis
report of the EPCM
consultant.
Bidder to note that Stress
analysis report of existing
flare system is not
available. Bidder has to do
stress analysis of piping
system as per good
engineering practice, site
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
survey and their expertise.
7
a)
b)
NIT No.GC14EST287
Technical Notes &
Special Conditions-
Document No.
GR/ES/10B/Flare/Tender-
01, Annexure A,
Chapter 1
20
5 of 52
i
4.4
Special Conditionsof Contract -Scope of work Inspection of Critical
Equipment at
Vendors works by
deputing engineers
Broad Scope ofConsultant(EPCM)- As per the scope,Procurement
Services includes
Inspection of Critical
equipment at
vendors works.
There are two possible
understanding.
(1) In addition to
Inspection by Third
Party Inspection
Agency,
Selected/Critical
Only selected critical
equipment are to be
inspected by EPCM
Consultant at vendors
works
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
c)
d)
Technical Notes &
Special Conditions-
Document No.
GR/ES/10B/Flare/Tender-
01, Annexure A,
Annexure-1 to Chapter-2
Technical Notes &
Special Conditions-
Document No.
GR/ES/10B/Flare/Tender-
01, Annexure A,
43 of 52
44 of 52
4.0 vii)
4.2. ii)
ProcurementServices Allmaterial inspection
including foreign
inspection is
considered to be
carried out by Third
Party or by Owners
Representatives
INSPECTIONS -Inspection of
materials/equipment
procured by Owner/
Contractor shall be
Equipment are to be
inspected by EPCM
Consultant.
(2) Items are to be
inspected only by
Third Party Inspection
Agency. Inspection by
EPCM Consultant is
not required.
Please confirm which option
is to be followed.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
e)
Annexure-1 to Chapter-2
Technical Notes &
Special Conditions-
Document No.
GR/ES/10B/Flare/Tender-
01, Annexure A,
Annexure-II to Chapter-2
52 of 52
8. g)
carried out by Third
Party
ProcurementServices-Procurement
Service includes
Procurement of
Inspection of
Selected equipment
8 Technical Notes &
Special Conditions-
Document No.
GR/ES/10B/Flare/Tender-
01, Annexure A,
Annexure-1 to Chapter-2
43 of 52 4.0 ix) ProcurementServices - Approvalof QAP/Spares for
all items in line with
PO.
Bidders understanding is
that only QAP shall be
approved by EPCM
Consultant. All other
Inspection related documents
such as Test Procedures,
For procurement items,
QAP shall be approved by
EPCM Consultant.
For site execution works,
EPCM Consultant shall
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
WPS/PQR shall be
approved/Reviewed by
Inspecting Authority.
review and approve all
inspection related
document and ensure site
work quality that will be
defined in the drawings &
contract document.
9 Annexure A / Chapter -1 4 of 52 A 3.12 Subsoil exploration Bidder has considered that
the scope of Consultant is
limited to preparation of
tender, floating and bid
evaluation.
Owner shall place direct
order on contractor for
subsoil exploration.
Please confirm.
Confirmed
10 Annexure A / Chapter -1 6 of 52 B 3.0 c) Flare stack with
structure
Bidder has considered that
the vendor for flare stack
shall design the required
guide, derrick structure
including fabrication drawing
EPCM Consultant shall
prepare drawing for
procurement of Flare stack
with supporting structure.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
for structural steel.
The scope of Consultant is
limited to review of design
calculations, design drawings
and fabrication drawings
prepared by the vendor for
flare stack.
Please confirm.
The scope of Consultant is
to review, finalise and
approve of design
calculations, design
drawings and fabrication
drawings submitted by the
vendor for flare stack.
11 Annexure A / Chapter -2 9 of 52 1.1 Engineering for
enabling job
including execution
Bidder has considered that
the scope of Consultant is
limited to engineering
services. Bidder has not
considered any execution in
the scope of consultant.
Please confirm.
EPCM Consultant shall be
responsible for execution of
the job through the
executing agency that will
be lined up for the project.
12 Annexure A / Chapter -2 /
Annexure -1
43 of 52 3.12 (14) Review and
approval of
fabrication drawings
for structural steel
submitted by the
The subject scope of
consultant does not match
with Special Condition of
contract no. d on page 4
(17).
Fabrication drawing of
structural apart from Flare
Stack will be under the
scope of EPCM consultant.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
contractor. Please confirm. The drawings shall not be
prepared by the executing
contractor.
13 Annexure B Annexure -
III
10 Detailed Feasibility
report -
Recommendations
and summary of
modifications
The DFR clause does not
specify modifications for any
structures, pipe racks and
sleepers.
In addition to new flare area
and KO drums area, bidder
has considered engineering
scope for following areas:
a. Design of New pipe
trestles for new flare
line from Wax unit &
other process units to
new flare area.
b. No design activity is
considered for
existing pipe rack for
existing flare line.
If any modification arises in
the existing flare
network,during detailed
engineering, EPCM
Consultant to carry out the
same.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
14 Annexure II, of Chapter
2 of Annexure A of
Tender Doc.
GC14EST287
11 of 52 2.11 Obligations of
OWNER
Bidder understands that the
accommodation for Bidders
staff, posted at site, shall be
in the scope of OWNER.
No. Bidder (EPCM
Consultant) has to make
their own arrangement for
staff posted at site.
15 Chapter 2 of Annexure
A of Tender Doc.
GC14EST287
31 of 52 14.2 Man months As per Division of
responsibility for major
activities under Sl.no 9 of
Annexure-II to Chapter 2,
Material management is in
the scope of Bidder ( page
52 of 52).
Site warehouse
management shall be done
by IOCL Store. However,
EPCM Consultant shall
make planning/ expediting
services for procurement
items for the project. Also
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
However, no man months
have been specified by
OWNER for this activity
against Clause 14.2 of
Chapter 2 of Annexure A.
OWNER to clarify if Bidder is
to consider man months for
Material management, in
addition to the 76 man
months specified by
OWNER.
unloading/loading of heavy
equipment, flare stack
structure shall be arranged
by Consultant though
execution contractor of
project.
No separate material officer
should be considered in
addition to 76 man-month
specified.
16 BOQ_23686 Excel
Sheet
1 Price Changes in the Lump sum
Price either Less or More
have similar implication on
Man-Month rate. Request
you to change the BOQ
which allows different change
BOQ shall be as per tender
document only and there
shall be no change in BOQ.
-
GUWAHATI REFINERY
SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject
to the different heads.
PART-B (CORRIGENDUM FOR TECHNICAL CLARIFICATION REGARDING CLAUSE NO 3.16 OF CHAPTER-1 OF ANNEXURE-A):
Clause No. 3.16 of Chapter-1 of Annexure-A (Page No. 4 of 52) shall be read as:
Site Enabling Job:The proposed new Flare Stack will be located on North West of the Refinery. (Please see DFR Copy 28 page of Annexure-B) at a FGL 84 meter. The
contour map of the existing area of the North West side of the Refinery is showing the new Flare location is attached as Annexure-C (Drg No
GR/TSP/P/01).
Presently the area is hilly which will require development with proper infrastructure to install new Flare stack. The area development will also require
proper and adequate approach roads for movement of heavy vehicle like fire tender, crane, hydra, ODC equipment etc. to the area up to the flare
stack.
While considering the development of the area shown in the drawing for the flare stack, the bidder has also to consider development of nearby area
towards both the north-eastern and the southern side also. This additional area development is clearly marked on the drawing enclosed herewith
(Drg No: GR/TSP/P/01-highlighted in green).
While considering the development of additional area, the bidder has to consider adequate approaches for movement of heavy vehicles, equipment
-
GUWAHATI REFINERY
as defined above. Detailed Engineering of the above will be under the scope of EPCM.
Agency for carrying out the execution of enabling job for the total area including flare stack area will be lined up by IOCL GR. All engineering
documents and other input required for site enabling shall be provided by EPCM Consultant.
Site supervision of execution of enabling job of the total identified and finalized area will be under the scope of EPCM Consultant and EPCM
Consultant shall be compensated on man-month rates for construction specialist.
-
CorrigendumGC14EST287.pdf (p.1-13)Dwg no GR TSP P 01.pdf (p.14)