corrigendumgc14est287[1]

14
GUWAHATI REFINERY Dated: 14 th Feb’ 2015 SUB: CORRIGENDUM OF TENDER Tender No. / Name of work Critical Dates 1. GC14EST287: EPCM Services for Revamp of Existing Flare with Additional New Flare System at Guwahati Refinery. Download : 23.01.15 to 21.02.15 Bid Submission : 14.02.15 to 21.02.15 Opening : 23.02.15 This is with reference to the Tender No.GC14EST287 for which Pre-Bid meeting was held on 09.02.15. During the Pre-Bid Meeting various issues were discussed and clarifications is being issued here by for the queries asked by one of the bidder which is given below in Part-A. In addition to the clarification of queries, corrigendum is being issued for technical clarification regarding clause no 3.16 of Chapter-1 of Annexure-A which is given below in Part-B: PART-A (CLARIFICATION OF QUERIES): SN Reference of Bidding Document Bidder’s Queries IOCL Clarification Part / Section Page No. Clause No. Subject 1 Annexure –A Chapter-1 4 of 52 3.14 SIL We presume other studies such as SIL are not required. Please confirm Confirmed. However, for field instruments where SIL is applicable it is to be incorporated. 2 Annexure –A Chapter-1 4 of 52 3.14 HAZOP Please confirm whether External HAZOP chairman

Upload: koyasrujana

Post on 20-Nov-2015

4 views

Category:

Documents


2 download

DESCRIPTION

aaa

TRANSCRIPT

  • GUWAHATI REFINERY

    Dated: 14thFeb 2015

    SUB: CORRIGENDUM OF TENDER

    Tender No. / Name of work Critical Dates

    1. GC14EST287: EPCM Services for Revamp of Existing Flare with Additional NewFlare System at Guwahati Refinery.

    Download : 23.01.15 to 21.02.15Bid Submission : 14.02.15 to 21.02.15Opening : 23.02.15

    This is with reference to the Tender No.GC14EST287 for which Pre-Bid meeting was held on 09.02.15. During the Pre-Bid Meeting various issueswere discussed and clarifications is being issued here by for the queries asked by one of the bidder which is given below in Part-A. In addition tothe clarification of queries, corrigendum is being issued for technical clarification regarding clause no 3.16 of Chapter-1 of Annexure-A which isgiven below in Part-B:

    PART-A (CLARIFICATION OF QUERIES):

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    1 Annexure A Chapter-1 4 of 52 3.14 SIL We presume other studies

    such as SIL are not required.

    Please confirm

    Confirmed.

    However, for field

    instruments where SIL is

    applicable it is to be

    incorporated.

    2 Annexure A Chapter-1 4 of 52 3.14 HAZOP Please confirm whether External HAZOP chairman

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    external HAZOP Chairman is

    required?

    is required.

    3 Annexure A Chapter-1 2 of 52 3.2 Development of

    P&IDs for the

    existing flare

    network

    Please confirm that Existing

    editable copy of P&IDs would

    be given by IOCL

    P&IDs of existing flare

    network will be required to

    be developed. IOCL will

    provide the hard copy of

    the present flare network

    for reference. This P&ID

    however is not as-built at

    site.

    4 PDS Flare system 1 of 2 - Reference P&ID

    nos: A447-02-41-

    010-1111

    P&IDs mentioned in

    datasheet would be made

    available by IOCL. Please

    confirm.

    Confirmed.

    5 Annexure A

    Annexure 1 to Chapter 2

    36 of 52 3.4 Consultant shall

    use PDS and / or

    other design and

    engineering

    software for

    preparing detail

    Bidder has considered only

    New Facilities related to

    Flare System for 3D

    Modelling.

    Existing Facilities are not

    Bidder has to incorporate

    existing Flare Header

    (Outside Battery Limits of

    Units) also in new 3-D

    Modelling of complete flare

    system.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    engineering works. considered for 3D Modelling.

    Kindly Confirm

    As such the 3 D model

    shall be a composite model

    incorporating both the

    existing and new flare

    system.

    6 Annexure A

    Annexure 1 to Chapter 2

    37 of 52 3.7 (ii) Stress Analysis Stress Analysis Reports and

    documentation of Existing

    Flare System shall be made

    available to bidder.

    Kindly confirm

    Stress analysis is under the

    scope of EPCM consultant

    and the stress analysis

    data will be taken as input

    for detailing. IOCL will be

    accept the stress analysis

    report of the EPCM

    consultant.

    Bidder to note that Stress

    analysis report of existing

    flare system is not

    available. Bidder has to do

    stress analysis of piping

    system as per good

    engineering practice, site

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    survey and their expertise.

    7

    a)

    b)

    NIT No.GC14EST287

    Technical Notes &

    Special Conditions-

    Document No.

    GR/ES/10B/Flare/Tender-

    01, Annexure A,

    Chapter 1

    20

    5 of 52

    i

    4.4

    Special Conditionsof Contract -Scope of work Inspection of Critical

    Equipment at

    Vendors works by

    deputing engineers

    Broad Scope ofConsultant(EPCM)- As per the scope,Procurement

    Services includes

    Inspection of Critical

    equipment at

    vendors works.

    There are two possible

    understanding.

    (1) In addition to

    Inspection by Third

    Party Inspection

    Agency,

    Selected/Critical

    Only selected critical

    equipment are to be

    inspected by EPCM

    Consultant at vendors

    works

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    c)

    d)

    Technical Notes &

    Special Conditions-

    Document No.

    GR/ES/10B/Flare/Tender-

    01, Annexure A,

    Annexure-1 to Chapter-2

    Technical Notes &

    Special Conditions-

    Document No.

    GR/ES/10B/Flare/Tender-

    01, Annexure A,

    43 of 52

    44 of 52

    4.0 vii)

    4.2. ii)

    ProcurementServices Allmaterial inspection

    including foreign

    inspection is

    considered to be

    carried out by Third

    Party or by Owners

    Representatives

    INSPECTIONS -Inspection of

    materials/equipment

    procured by Owner/

    Contractor shall be

    Equipment are to be

    inspected by EPCM

    Consultant.

    (2) Items are to be

    inspected only by

    Third Party Inspection

    Agency. Inspection by

    EPCM Consultant is

    not required.

    Please confirm which option

    is to be followed.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    e)

    Annexure-1 to Chapter-2

    Technical Notes &

    Special Conditions-

    Document No.

    GR/ES/10B/Flare/Tender-

    01, Annexure A,

    Annexure-II to Chapter-2

    52 of 52

    8. g)

    carried out by Third

    Party

    ProcurementServices-Procurement

    Service includes

    Procurement of

    Inspection of

    Selected equipment

    8 Technical Notes &

    Special Conditions-

    Document No.

    GR/ES/10B/Flare/Tender-

    01, Annexure A,

    Annexure-1 to Chapter-2

    43 of 52 4.0 ix) ProcurementServices - Approvalof QAP/Spares for

    all items in line with

    PO.

    Bidders understanding is

    that only QAP shall be

    approved by EPCM

    Consultant. All other

    Inspection related documents

    such as Test Procedures,

    For procurement items,

    QAP shall be approved by

    EPCM Consultant.

    For site execution works,

    EPCM Consultant shall

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    WPS/PQR shall be

    approved/Reviewed by

    Inspecting Authority.

    review and approve all

    inspection related

    document and ensure site

    work quality that will be

    defined in the drawings &

    contract document.

    9 Annexure A / Chapter -1 4 of 52 A 3.12 Subsoil exploration Bidder has considered that

    the scope of Consultant is

    limited to preparation of

    tender, floating and bid

    evaluation.

    Owner shall place direct

    order on contractor for

    subsoil exploration.

    Please confirm.

    Confirmed

    10 Annexure A / Chapter -1 6 of 52 B 3.0 c) Flare stack with

    structure

    Bidder has considered that

    the vendor for flare stack

    shall design the required

    guide, derrick structure

    including fabrication drawing

    EPCM Consultant shall

    prepare drawing for

    procurement of Flare stack

    with supporting structure.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    for structural steel.

    The scope of Consultant is

    limited to review of design

    calculations, design drawings

    and fabrication drawings

    prepared by the vendor for

    flare stack.

    Please confirm.

    The scope of Consultant is

    to review, finalise and

    approve of design

    calculations, design

    drawings and fabrication

    drawings submitted by the

    vendor for flare stack.

    11 Annexure A / Chapter -2 9 of 52 1.1 Engineering for

    enabling job

    including execution

    Bidder has considered that

    the scope of Consultant is

    limited to engineering

    services. Bidder has not

    considered any execution in

    the scope of consultant.

    Please confirm.

    EPCM Consultant shall be

    responsible for execution of

    the job through the

    executing agency that will

    be lined up for the project.

    12 Annexure A / Chapter -2 /

    Annexure -1

    43 of 52 3.12 (14) Review and

    approval of

    fabrication drawings

    for structural steel

    submitted by the

    The subject scope of

    consultant does not match

    with Special Condition of

    contract no. d on page 4

    (17).

    Fabrication drawing of

    structural apart from Flare

    Stack will be under the

    scope of EPCM consultant.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    contractor. Please confirm. The drawings shall not be

    prepared by the executing

    contractor.

    13 Annexure B Annexure -

    III

    10 Detailed Feasibility

    report -

    Recommendations

    and summary of

    modifications

    The DFR clause does not

    specify modifications for any

    structures, pipe racks and

    sleepers.

    In addition to new flare area

    and KO drums area, bidder

    has considered engineering

    scope for following areas:

    a. Design of New pipe

    trestles for new flare

    line from Wax unit &

    other process units to

    new flare area.

    b. No design activity is

    considered for

    existing pipe rack for

    existing flare line.

    If any modification arises in

    the existing flare

    network,during detailed

    engineering, EPCM

    Consultant to carry out the

    same.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    14 Annexure II, of Chapter

    2 of Annexure A of

    Tender Doc.

    GC14EST287

    11 of 52 2.11 Obligations of

    OWNER

    Bidder understands that the

    accommodation for Bidders

    staff, posted at site, shall be

    in the scope of OWNER.

    No. Bidder (EPCM

    Consultant) has to make

    their own arrangement for

    staff posted at site.

    15 Chapter 2 of Annexure

    A of Tender Doc.

    GC14EST287

    31 of 52 14.2 Man months As per Division of

    responsibility for major

    activities under Sl.no 9 of

    Annexure-II to Chapter 2,

    Material management is in

    the scope of Bidder ( page

    52 of 52).

    Site warehouse

    management shall be done

    by IOCL Store. However,

    EPCM Consultant shall

    make planning/ expediting

    services for procurement

    items for the project. Also

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    However, no man months

    have been specified by

    OWNER for this activity

    against Clause 14.2 of

    Chapter 2 of Annexure A.

    OWNER to clarify if Bidder is

    to consider man months for

    Material management, in

    addition to the 76 man

    months specified by

    OWNER.

    unloading/loading of heavy

    equipment, flare stack

    structure shall be arranged

    by Consultant though

    execution contractor of

    project.

    No separate material officer

    should be considered in

    addition to 76 man-month

    specified.

    16 BOQ_23686 Excel

    Sheet

    1 Price Changes in the Lump sum

    Price either Less or More

    have similar implication on

    Man-Month rate. Request

    you to change the BOQ

    which allows different change

    BOQ shall be as per tender

    document only and there

    shall be no change in BOQ.

  • GUWAHATI REFINERY

    SN Reference of Bidding Document Bidders Queries IOCL ClarificationPart / Section Page No. Clause No. Subject

    to the different heads.

    PART-B (CORRIGENDUM FOR TECHNICAL CLARIFICATION REGARDING CLAUSE NO 3.16 OF CHAPTER-1 OF ANNEXURE-A):

    Clause No. 3.16 of Chapter-1 of Annexure-A (Page No. 4 of 52) shall be read as:

    Site Enabling Job:The proposed new Flare Stack will be located on North West of the Refinery. (Please see DFR Copy 28 page of Annexure-B) at a FGL 84 meter. The

    contour map of the existing area of the North West side of the Refinery is showing the new Flare location is attached as Annexure-C (Drg No

    GR/TSP/P/01).

    Presently the area is hilly which will require development with proper infrastructure to install new Flare stack. The area development will also require

    proper and adequate approach roads for movement of heavy vehicle like fire tender, crane, hydra, ODC equipment etc. to the area up to the flare

    stack.

    While considering the development of the area shown in the drawing for the flare stack, the bidder has also to consider development of nearby area

    towards both the north-eastern and the southern side also. This additional area development is clearly marked on the drawing enclosed herewith

    (Drg No: GR/TSP/P/01-highlighted in green).

    While considering the development of additional area, the bidder has to consider adequate approaches for movement of heavy vehicles, equipment

  • GUWAHATI REFINERY

    as defined above. Detailed Engineering of the above will be under the scope of EPCM.

    Agency for carrying out the execution of enabling job for the total area including flare stack area will be lined up by IOCL GR. All engineering

    documents and other input required for site enabling shall be provided by EPCM Consultant.

    Site supervision of execution of enabling job of the total identified and finalized area will be under the scope of EPCM Consultant and EPCM

    Consultant shall be compensated on man-month rates for construction specialist.

  • CorrigendumGC14EST287.pdf (p.1-13)Dwg no GR TSP P 01.pdf (p.14)