corpus christi harbor bridge · project needs long-term maintenance existing steel bridge built in...

65
CORPUS CHRISTI HARBOR BRIDGE SHORT COURSE 2017 Overview, CDA Management, and Project Progress October 11, 2017

Upload: others

Post on 16-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

CORPUS CHRISTI HARBOR BRIDGESHORT COURSE 2017

Overview, CDA Management, and Project

Progress

October 11, 2017

Page 2: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

2

Project Needs and Objectives

Page 3: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Project Needs

Long-Term Maintenance

Existing steel bridge built in 1959 has high maintenance

costs

Maintain long-term operation of a US 181 crossing of the

Corpus Christi Ship Channel

Safety

Eliminate risks caused by existing design deficiencies

Improve horizontal sharp curve

Vertical geometry steep grades

Add shoulders

3

Page 4: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Project Objectives

Local Connectivity

Economic Development Opportunities

Page 5: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Project Overview – Design Build (CDA)

Design, construct, and maintain a total

project length of 6.44 miles

New location six-lane Harbor Bridge

Multi-level interchange with intersection

improvements

Six-lane section of US 181

Reconstruction on IH-37

Reconstruction on SH 286

Demolition of existing Harbor Bridge

25 year operation and maintenance

5

Page 6: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

6

Operations & Maintenance (O&M)

Page 7: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Operations and Maintenance (O&M)

O&M during construction

25-year maintenance (O&M) after

substantial completion

Developer responsible for all elements

within ROW, except minor exclusions Bridge

Drainage

Structural elements (Foundation, towers,

cable stays)

Gantry-mounted overhead signs

Lighting

Roadways

Pavement, Joints in concrete, Curbs

Pavement Markings, Object Markers, Barrier

Markers and Delineators

Fences, Sound walls and Abatement

Earthworks, Embankments and Cuttings

ITS Equipment

Handback requirements—Maintenance

Transition Plan

7

Readiness requirements

Baseline condition evaluation report

Staffing and supervision

organization

Stakeholder communication

Training

Equipment

Systems and materials

Page 8: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

8

Developer

Page 9: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Developer

9

Flatiron/Dragados, LLC

Equity Owner: Flatiron Constructors, Inc.

Dragados USA, Inc.

Major Non-Equity members and other team members*:

Figg Bridge Engineers, Inc.

AIA Engineers, Inc.

Iridium Concesiones de Infraestructuras, S.A.

(through ACS Infrastructure Development)

DBI Services, LLC

Austin Bridge & Road, LP

AZTEC Engineering Group, Inc.

Beton Consulting Engineers, LLC

Blanton & Associates, Inc.

D.H. Griffin of Texas, Inc.

IEA, Inc.

Kellogg, Brown & Root Services, Inc.

KCI Technologies, Inc.

M2L Associates, Inc.

PaveTex Engineering & Testing, Inc.

Pinnacle Consulting Management Group, Inc.

Professional Services, Inc.

Randy Burkett Lighting Design, Inc.

RJ Rivera Associates, Inc.

The Boundary Layer Wind Tunnel Laboratory

Ware & Associates, Inc.

*At time of award

Page 10: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

10

Project Execution Timeline

Page 11: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Project Schedule Milestone Dates

11

Activity Date

Issue RFQ March 26, 2014

CDA executed (Flatiron/Dragados USA, JV) September 28, 2015

NTP 1 -- Design February 16, 2016

NTP 2 -- Construction (Phase 1) July 19, 2016

Substantial Completion (Phase 1) – Anticipated May 25, 2020

Substantial Completion (Phase 2) – Anticipated June 14, 2021

Final Acceptance- Anticipated October 12, 2021

O&M Period October 12, 2046

Page 12: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

12

Project Administration

Page 13: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Project Management

13

Page 14: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

14

Developer Management with Owner Interface

Page 15: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

15

Project Controls

Page 16: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

TxDOT Project Management System—Sharepoint® CM Platform

TxDOT developed over last 8 years, collaborative, document storage, sustainability

Single resource for storage of all project communication

Automated workflow for processing submittals

All documentation time stamped when received and sent

Dashboard (below) provides each user a heads up display

16

Page 17: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Developer Internal Controls System—aconex

17

Page 18: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Developer Field Documentation—Fieldwire

18

Developer document management tool

for released for construction products

Uploaded and instantly accessible by

tablet, laptop, & phone

Documentation

shared with QA and

Owner in real time

Page 19: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

19

Non-Compliance Events

Page 20: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Non-Compliance Events

20

General Background

Noncompliance Events

During Construction

Administrative tool

Harbor Bridge is first TxDOT

construction project

application

Past projects, O&M on

Concessionaire Projects

Page 21: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

21

Design Oversight

Page 22: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Formal Review Process—Comment Response Matrix

22

Initially formal review with comments and responses

Close out generally over-the-shoulder, with formal documented concurrence

Page 23: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Early Start of Construction

23

A means to progress design work product in advance of final design package

Early construction and long lead items, examples:

Drill shafts

Piles

Footings

Precast segments

Early traffic phases

TxDOT has sole discretion to accept or disallow

Contractor has greater freedom to advance work product

Page 24: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Certificate of Compliance

24

Documentation that a complete design deliverable for a section of the project

has been delivered

A Final Design Package clearly delineated for a portion of work

Must include:

Complete Design Drawings

Design Calculations

All Associated Design Reports

Comprehensive Specifications

Electronic Deliverable for Project Files

Acquisition of all ROW

Governmental Approvals

Utility Owner Approvals

Accompanied by TxDOT written concurrence

Developer is still at risk for design and construction

Page 25: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

25

Public Information

Page 26: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

26

Public Information Officer

Page 27: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Stakeholder Relations

27

Hillcrest/Washington-Coles Neighborhoods North Beach Neighborhood

Page 28: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

28

Traffic Advisories

Traffic Advisories

Posted on

www.harborbridgeproject.com

HBP social media sites

Developer responsibility

rather than TxDOT District

Page 29: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

29

Unique Bridge Elements

Page 30: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Unique Project Elements

Longest cable-stayed, concrete

segmental bridge in the North

America

Completely spans the ship channel

bank-to-bank

Concrete structure with 170 year

design life

Support cables located down the

middle

LED lighting

Shared use path with mid-span

Belvedere

30

Page 31: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge Scale

31

Existing main span = 620’ New main span = 1661’

Existing vert. clearance = 138’ New clearance = 205’

Existing truss = 243’ New tower height = 528’

Page 32: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Selected Main Span Unit

32

Page 33: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

33

Sustainability

Page 34: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

INVEST

34

Partnering with FHWA

Platinum Rating during design and construction

Recycled materials, low emission equipment, warm-mix, etc.

Platinum Rating during operation and maintenance

Renewable energy, low energy lighting, natural low maintenance

vegetation, etc.

Page 35: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

35

Aesthetic Components

Page 36: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Public Participation—Design Charette

36

Public input provided

on final aesthetic

elements

Post award

To be used for final

detail design

Public votes on

choices of refined

concepts

Page 37: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

North Plaza & Trailhead Concept

37

NORTHBOUND

FRONTAGE ROAD

PARKING

SOUTHBOUND

FRONTAGE ROAD

NORTH

ABUTMENTBRIDGE COLUMN

BIKE RACK

SHARED USE

PATH

TO BRIDGE

Page 38: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

North Plaza & Trailhead Concept

38

NORTHBOUND

FRONTAGE

TO BRIDGE

TO PARKING

RECYCLED

CONCRETE

LANDSCAPING

UNDER BRIDGE

Page 39: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

South Plaza Concept

39

NORTHBOUND

FRONTAGE ROAD

PARKING

SOUTHBOUND

FRONTAGE ROAD

NORTH

ABUTMENTBRIDGE COLUMN

BIKE RACK

SHARED USE

PATH

TO BRIDGE

BIKE RACK

WATER

FEATURE

XERISCAPE

Page 40: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

South Trailhead Concept

40

TRAIL

MAP

WALL

BENCH

Page 41: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Shared Use Path

41

Page 42: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Belvedere

42

BELVEDERE

Page 43: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Shared Use Path & Belvedere

43

Page 44: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

View from the Belvedere

44

USS LEXINGTON TEXAS STATE AQUARIUM ART MUSEUM AMERICAN BANK

CENTER

Page 45: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Landscaping Design – Coastal Beauty

45

Page 46: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

LED Lighting

46

Page 47: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Aesthetic Approach Substructure and Segmental Superstructure

47

Page 48: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

View from Whataburger Field

48

Page 49: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

US 181 Harbor Bridge

49

Construction

Page 50: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

50

Project Worksites

Page 51: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

51

Flato Rd. Concrete Batch Plant

Page 52: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

52

Robstown Casting Yard

Page 53: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Short – Line Casting

53

Page 54: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Mold Layout

54

Page 55: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Mold Layout

55

Page 56: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Rebar Jig

56

Page 57: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Rebar Cage, Placing into Formwork

57

Page 58: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Segment Production

58

Page 59: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Segment Production Line

59

Page 60: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Transporting Segment Within Casting Yard

60

Page 61: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Pile Driving

16” to 24” Piles in groups for most

bridge structures other than main piers

Page 62: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Cofferdam Construction

62

Required for

footings placed

below water table

Utilizing driven

sheet piling

Page 63: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Main Pier Drilled Shafts and Foundations

63

Tower foundation (each):

132’ x 72’ x 18’

6400 CY

Size of 2 basketball courts

Drilled shafts (each)

650 CY per shaft

10-foot diameter,

210-foot deep drilled shafts

Page 64: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Drilled Shaft Installation

64

Page 65: CORPUS CHRISTI HARBOR BRIDGE · Project Needs Long-Term Maintenance Existing steel bridge built in 1959 has high maintenance costs Maintain long-term operation of a US 181 crossing

Questions or Comments?

65

Joseph Briones, P.E.

[email protected]

(361) 808-2327

Ultimate Goal!Hint: Go to the video…