coreworx interface management program deployment lessons learned from the middle east paul tompkins...
TRANSCRIPT
Coreworx Interface Management Program
Deployment Lessons Learned from the Middle East
Paul TompkinsJune 2012
Agenda
• Interface Management Program “Definition”• What is the Business Problem – Why Bother ?
– Customer Snapshot – Saudi Aramco– Project Profiles – Wasit and Shaybah
• Interface Management Meetings – “The New Way”
• Deployment Learning• Q&A
What is Interface Management?
• Interface management is the control and oversight of technical interactions and information flow between the major contracting parties on large, complex, often modular-based mega projects
Interface Types
• Tangible or Hard Interfaces. – Physical connection such as a structural steel
connection, pipe termination, or cable connection
• Intangible or Soft Interfaces– Involve the exchange of information such as
design criteria, clearance requirements, security access(SIMOPS, etc)
• Execution interfaces– Occur when different parties conduct their scope
of work in series with interfaces that are dependent on each other or simultaneous when concurrent activities impact each other(such as shared systems – telecom, etc)
The Problem – Why Bother ?
• With mega projects, the risk of cost growth without properly managed project interfaces is tremendous– The industry’s largest projects have experienced 46% cost growth
over project sanction.1
– In offshore oil & gas projects, interface issues account for up to 20% of TIV1
1. “Interface Management: A critical area for improving on-time, on-budget deliver,” Uri Nooteboom, www.safan.com
2. “Interface Management in Complex Projects,” Richard Collins, www.eptq.com.
Multi-Operator Scenario
EPC 1
EPC 2
EPC 3EPC 4
EPC 5
Inter-Project Interfaces• Technical• Physical• Logistical• Commercial• Organizational
Intra-Project Interfaces• Tie-ins
Independent Projects
Extra-Project Interfaces• Local infrastructure systems• Local and national approvals
Interfaces in a $5 billion Oil & Gas Expansion Project
Customer Profile – Saudi Aramco
• Headquartered in Dhahran, Saudi Arabia• 2010 Revenue > $200 Billion• Proven oil reserves > 260 Billion bbls (global
18 %)• Largest daily oil producer, yearly production
7.9 billion barrels• Manages > 100 oil and gas fields in Saudi
Arabia, including 279 trillion scf of natural gas reserves– Ghawar Field(world’s largest)– Shaybah
Profile - Wasit Gas ProjectOwnership Saudi Aramco (100%)
Asset Gas Plant
Production 2.5 billion cubic feet per day (cfd)
Location Saudi Arabia
Total Installed Value $6 billion
Timeline Startup 2014
• Onshore grassroots central processing facility (CPF)– Will provide for processing of
gas from the Arabiyah and Hasbah offshore sour gas fields
– Includes a gas unit, a cogeneration power plant, a sulphur recovery unit with utilities
Why ?
• Risk Mitigation – minimize rework at commissioning
• Compliance – consistency of project execution• Harvesting of Intellectual property• Project complexity
– Size and scope– Multiple locations, time zones, languages– Insufficient visibility of interface related issues– Contractual complexity(JV, LSTK, LSBP)
“Early Warning” Visibility by Scope Package
Interface Point Summary
Configurable Dashboards
Learnings
• Establish and communicate program goals– Buy in to master interface plan/procedure is critical– Set expectations on participation and approach to
active issue management– Establish “integration strategy” with project
planning• Early interface definition is critical to success
– Technical descriptions included in contract process– Sensitivity to contracting strategy - flexibility
• Focus on contractor on boarding process– User interface simplicity– Contractors create bulk of content, need their buy
in– Focus on value to EPC as well – process
improvements– Be aware of contractor/project culture