8/14/2019 CORCON 2009 MJ.ppt
2/27
Economical and, Ecological Solution Two component solvent free Polyurethane's have been used as
a single protective coating for steel pipes, valves fittings and
other steel structures for over forty years.
Many internationally recognized examples where polyurethane
systems have been selected as the most cost effective and best
suited, for pipeline rehabilitation projects
-
8/14/2019 CORCON 2009 MJ.ppt
3/27
Excellent Chemical Mechanical Properties:
Excellent Adhesion Capacity High Impact & Abrasion resistance.
Corrosion protection with good chemical resistance.
Extremely Short Curing Time.
Advantages of easy application and control on-site.
-
8/14/2019 CORCON 2009 MJ.ppt
4/27
Surface PreparationManual
Automated Equipment
Requires
SA 2 (ISO 8501-1)
-
8/14/2019 CORCON 2009 MJ.ppt
5/27
Manual Surface Preparation In The Trench Project: IOCL Vadinar
Pipeline Rehabilitation:
42 Parallel Pipes
-
8/14/2019 CORCON 2009 MJ.ppt
6/27
Automated Surface Preparation
Uniform surface preparation
Faster
High quality
Good Anchor pattern
More Expensive
-
8/14/2019 CORCON 2009 MJ.ppt
7/27
Coating Application:100% Solids polyurethane coating technology allows
several application techniques including:
Manual two component heated airless spray machine
Automated Rotary Spraying Ring (In-Situ)
Automated Line Travel Equipment (Out of the Trench)
-
8/14/2019 CORCON 2009 MJ.ppt
8/27
Coating Application:100% Solids polyurethane coating technology allows several application
techniques including:
Manual (two component heated airless spray machine)
-
8/14/2019 CORCON 2009 MJ.ppt
9/27
Coating Manual Application
-
8/14/2019 CORCON 2009 MJ.ppt
10/27
Manual ApplicationCan be completed in open areas and areas with difficult access
-
8/14/2019 CORCON 2009 MJ.ppt
11/27
Manual Application Manual application in
Compressor Station
Operating pipeline(operating @ +40oC)
Tenting used to protectspray area and surfacepreparation
-
8/14/2019 CORCON 2009 MJ.ppt
12/27
Manual ApplicationIOCL 42 Pipeline Vadinar
-
8/14/2019 CORCON 2009 MJ.ppt
13/27
Manual ApplicationPossible Problems Encountered:
Slower (Than Automated Spraying Equipment)
Can be inconsistent with thickness
Over consumption can run @ 40% to 100% over
theoretical Qualified skilled labour can prove hard to find
More Economical than Automatic line travel equipment
method
-
8/14/2019 CORCON 2009 MJ.ppt
14/27
Rotary Automatic Spray System(In the Trench) Automatic spray ring system can be employed when speed
of application is an important requirement.
When short distances (Bell hole) Automatic rotary sprayring apparatus, offers the advantages that manual sprayingmethod cannot.
Speed of application. (0.5 meters-to-1 meter per minute)
Consistent & Uniformed thickness. Reduced overspray.
Reducing material costs.
-
8/14/2019 CORCON 2009 MJ.ppt
15/27
Automated Application In-Situ
-
8/14/2019 CORCON 2009 MJ.ppt
16/27
Automated Line Travel
Removal of the existing coating. (CTE, Tapes etc,) using
high pressure water jetting.
Abrasive blast cleaning (Sa 2.5 - ISO 8501-1)
Application of Two Component Polyurethane
Providing a single (Homogeneous) coating.
Multi-step Operation
-
8/14/2019 CORCON 2009 MJ.ppt
17/27
Coating RemovalCTE coating 38 Gas Pipeline Texas USA (1994)
-
8/14/2019 CORCON 2009 MJ.ppt
18/27
Surface Preparation Abrasive Blast
-
8/14/2019 CORCON 2009 MJ.ppt
19/27
Automated ApplicationLine Travel
Single Pass Application of Two Component Polyurethane Coating38 @ DFT 800 m/100m
-
8/14/2019 CORCON 2009 MJ.ppt
20/27
HighBuild CharacteristicsBy
Automated or Manual Application
1.7 mm in 1 pass
-
8/14/2019 CORCON 2009 MJ.ppt
21/27
Typical Alternative Liquid Systems:Two Component Liquid Epoxy :
Slower curing,
Low build thickness characteristics,
Less flexibility; and
Approximately 15% more expensive.
Two Component Liquid Epoxy Offers High operating temperatures (90oC+)
-
8/14/2019 CORCON 2009 MJ.ppt
22/27
Typical Testing Results:S/F Epoxy S/F Polyurethane
These typical testing values illustrate why, solvent free polyurethanes are
selected as the preferred coating system for pipeline rehabilitation
programmes.
Test Standard Solvent Free Epoxy Solvent Free P.U.Sag Resistance Typically 1mm Typically 2mm
Hard dry time
(Fast Setting)
4 Hours 1 Hour
Flexibility: ASTM-D522 Typically < 5% Typically < 40%
Impact Resistance: ASTM-G14 Typically: 3-4 Joules > 8.8 Joules
-
8/14/2019 CORCON 2009 MJ.ppt
23/27
-
8/14/2019 CORCON 2009 MJ.ppt
24/27
Application Temperatures and Curing Time100% Solvent Free Polyurethane
Application Temp. Substrate > 10CComp. A 50C 80C
Comp. B 40C 60C
Pot Life Approx. 40 sec. At 60CCuring Time At 20C At 50C At 90C
touch dry 10 min. 2 min. * < 1 min. *
stackable 8 hours 30 min. * Immediately
-
8/14/2019 CORCON 2009 MJ.ppt
25/27
Holiday Testing - Within 2 Hours
-
8/14/2019 CORCON 2009 MJ.ppt
26/27
Solvent Free PolyurethaneTypical Performance Properties
Test Standard ResultsAdhesion: ASTM-D4541 Greater than 150 kg/cm onto blast
cleaned steel.
Chemical Resistance: - Good in most solutions other than,
aromatic solvents.
Flexibility ASTM-D522 Average 30% - 50% elongation tobreak, with cold bend resistance
down to 12.7mm mandrel.
Hardness: ASTM-D2240 Typically 70-80 Shore D
Abrasion Resistance: ASTM-D4060 Typically 70 mg loss (Taber
abrader, 1000 cycles, CS 10 wheels, 1kg loading)
Tensile Strength: ASTM-D638 13 N/mm
Penetration Resistance: ASTM-G17 Less than 10% of the thickness
penetrated
Impact Resistance: ASTM-G14 > 8.8 Joules
-
8/14/2019 CORCON 2009 MJ.ppt
27/27
Conclusions
Appointment of qualified approved applicators /contractors.
Experience and proven track record in theapplication of, Multi Component Liquid CoatingSystems. Results, Surface preparation, application of the newcoating and final testing, completed to thespecification requirements / criteria.
Which ever method of application selected forpipeline rehabilitation. The most important factorsare: