copyright 2012 john wiley & sons, inc. chapter 10 monitoring and information systems

30
Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

Upload: christy-feathers

Post on 15-Dec-2015

219 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

Copyright 2012 John Wiley & Sons, Inc.

Chapter 10

Monitoring and Information

Systems

Page 2: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-22

Terms

Monitoring - Collecting, recording, and reporting information concerning any and all aspects of project performance

Controlling - Uses the data supplied by monitoring to bring actual performance into compliance with the plan

Evaluation - Judgments regarding the quality and effectiveness of project performance

Page 3: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-33

The Planning–Monitoring–Controlling Cycle

We mainly want to monitor:– Time (schedule)– Cost (budget)– Scope (project performance)

Closed-loop system– Revised plans and schedules following

corrective actions

Page 4: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-44

Project Authorization and Expenditure Control System Information Flow

Figure 10-1

Page 5: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-55

Designing the Monitoring System

Identify key factors to be controlled– Scope– Cost– Time

Information to be collected must be identified

Page 6: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-66

Designing the Monitoring System Continued

Do not want to avoid collecting necessary data because it is hard to get

Do not want to collect too much dataThe next step is to design a reporting

system that gets the data to the proper people in a timely and understandable manner

Page 7: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-77

Data Collection

Once we know the data we want, we need to decide how to collect it

Should the data be collected after some event?

Should it be collected on a regular basis?Are there any special forms needed for

data collection?

Page 8: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-88

Much Data Involves

Frequency counts Raw numbers Subjective numeric ratings Indicators Verbal measures

Page 9: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-99

Information Needs and Reporting

Everyone should be tied into the reporting system

Reports should address each levelNot at same depth and frequency for

every level– Lower-level needs detailed information– Senior management levels need overview

reportsReport frequency is typically high at low

levels and less frequent at higher levels

Page 10: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1010

The Reporting Process

Reports must contain relevant dataMust be issued frequentlyShould be available in time for controlDistribution of project reports depends on

interest– For senior management, may be few

milestones– For project manager, there may be many

critical points

Page 11: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1111

Benefits of Detailed and Timely Reports

Mutual understanding of the goalsAwareness of the progress of parallel

activitiesUnderstanding the relationship of tasksEarly warning signals of problemsMinimizing the confusionHigher visibility to top managementKeeping client up to date

Page 12: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1212

Report Types

Routine - Reports that are issued on a regular basis or each time the project reaches a milestone

Exception - Reports that are generated when an usual condition occurs or as an informational vehicle when an unusual decision is made

Special Analysis - Reports that result from studies commissioned to look into unexpected problems

Page 13: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1313

Meetings

Reports do not have to be writtenThey can be delivered verbally in

meetingsProjects have too many meetingsThe trick is to keep them to as few as

possible

Page 14: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1414

Meeting Rules

Use meetings to make group decisionsStart and end on time and have an agendaDo your homework before the meetingTake minutesAvoid attributing remarks to individuals in

minutesAvoid overly formal rules of procedureCall meeting for serious problems

Page 15: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1515

Common Reporting Problems

Too much detailPoor interface between the

data/procedures of the project and the information system of the parent company

Poor correspondence between the planning process and the monitoring process

Page 16: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1616

Earned Value Analysis

Have covered monitoring parts– Timing and coordination between individual

tasks is importantMust also monitor performance of entire

project – Crux of matter should not be overlooked

One way is by using an aggregate performance measure called earned value

Page 17: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1717

The Earned Value Chart and Calculations

Actual against baseline ignores the amount of work accomplished

Earned value incorporates work accomplished

Multiply the estimated percent work complete for each task by the planned cost

Only need percent complete estimate for tasks currently in progress

Page 18: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1818

Rules to Aid in Estimating Percent Completion

50-50 rule0-100 percent ruleCritical input use ruleProportionality rule

Page 19: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-1919

The Earned Value Chart

Figure 10-6

Page 20: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2020

Variances

Variances can help analyze a project1. A negative variance is bad

2. Cost and schedule variances are calculated as the earned value minus some other measure

Will look at some of the more common ones

Page 21: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2121

Cost Variance (CV)

CV = EV – AC

Negative variance indicates a cost overrun

Magnitude depends on the costs

Page 22: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2222

Schedule Variance (SV)

SV = EV – PV

Negative variance indicates you are behind schedule

Measured using costs

Page 23: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2323

Time Variance (TV)

TV = ST – AT

Negative variance indicates you are behind schedule

Page 24: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2424

Indices

Cost Performance Index CPI = EV/AC

Schedule Performance Index SPI = EV/PV

Time Performance Index TPI = ST/AT

Cost Schedule Index CSI = EV2/(AC)(PV)

Page 25: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2525

“To complete” and “At Completion”

Project manager reviewing what is complete and what remains

Final cost and final completion date are moving targets

The project manager compiles these into a to complete forecast

Actual + forecast = final date and cost at completion

Page 26: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2626

ETC and EAC

ETC = (BAC + EV)/CPIEAC = ETC + ACwhere,

ETC = Estimated cost to completeBAC = Budget at completionEV = Earned valueCPI = Cost performance indexEAC = Estimated cost at completionAC = Amount expended to date (actual cost)

Page 27: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2727

Milestone Reporting

Reports that are created when a project reaches a major milestone

They are designed to keep everyone up-to-date on project status

For executives and clients, these may be the only reports they receive

Page 28: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2828

Computerized PMIS (Project Management Information Systems)

Real projects are often large– Hundreds of tasks– Thousands of work units

Reporting is clearly a job for the computerProject management information systems

were one of the earlier applications Initially focus was on schedulingNow it includes, earned values, variances,

and more

Page 29: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-2929

PMIS Errors

Managing the PMISComputer paralysisPMIS verification Information overloadProject isolationComputer dependencePMIS misdirection

Page 30: Copyright 2012 John Wiley & Sons, Inc. Chapter 10 Monitoring and Information Systems

10-10-3030

PMIS Desirable Attributes

FriendlinessSchedulesCalendarsBudgetsReports

GraphicsChartsMigrationConsolidationAccess