Copyright 2005 Northrop Grumman Corporation 1
Quality & Supplier Management
March 2008
Mike GilletteIPIC Quality Assurance ManagerNorthrop Grumman Corporation
Copyright 2005 Northrop Grumman Corporation 2
Quality & Supplier Management
OutlineOutline
History Early Involvement
Proposal ASMB RFP Source Selection
SDD Production
Copyright 2005 Northrop Grumman Corporation 3
ICBMs – A continuing Success Story
•ECS•ISMP•ICU
Atlas Thor Titan MM III PK SICBM
1957 1957 1959 1961 1964 1968 1983 1989
MM IIMM I MM IIISLE
2000
1950s•Atlas 1st Launch (1957)•Thor 1st Launch (1957)•Titan 1st Launch (1959)
1950s•Atlas 1st Launch (1957)•Thor 1st Launch (1957)•Titan 1st Launch (1959)
1960s•MM I 1st Launch (1961)•MM II 1st Launch (1964)•MM III 1st Launch (1968)
1960s•MM I 1st Launch (1961)•MM II 1st Launch (1964)•MM III 1st Launch (1968)
1970s•PK Go-Ahead (1972)
1970s•PK Go-Ahead (1972)
1980s•PK 1st Launch (1983)
•SICBM Go-Ahead (1983)•PKRG Go-Ahead (1986)
•SICBM 1st Launch (1989)
1980s•PK 1st Launch (1983)
•SICBM Go-Ahead (1983)•PKRG Go-Ahead (1986)
•SICBM 1st Launch (1989)
1990s•REACT
•GRP•PRP
•ICBM Prime Award (1997)
1990s•REACT
•GRP•PRP
•ICBM Prime Award (1997)
2000+•MMP•PSRE•SERV•REACT SLEP
2000+•MMP•PSRE•SERV•REACT SLEP
In An Uncertain World ICBMs Continue To Be Important To Our National Defense
In An Uncertain World ICBMs Continue To Be Important To Our National Defense
Hold Targets at Risk Provide Deterrence Against Attack Rapid Receipt and Response to Emergency Action Messages
(EAMs) Flexible Response Against Our Enemies Should Deterrence Fail
A Critical National
Asset
A Critical National
Asset
Copyright 2005 Northrop Grumman Corporation 4
Supplier Management
Key Features Benefits Well established process to identify and
qualify new vendors Programs executed on plan with no
substandard parts or components delivered to field
Focus on developing and qualifying vendors to meet our high standards before production starts
Understanding of our needs as a customer and sound basis for shared success
Monitor suppliers, during design and production, for successful corrective actions addressing variances from plan
Ensures timely awareness of difficulties and provides time to correct without impact to customer
Multi-tier vendor audits and assessments
Reinforces commitment to quality products throughout supply chain
Suppliers evaluated for ability to consistently produce quality products
Vendor oversight approach adapted to needs of supplier
ObjectivesObjectives No quality escapes to the field Quality is built-in, not
inspected-in
Over 3500 end items delivered to field since 2002 with essentially no quality issues
ResultsResults
1
Copyright 2005 Northrop Grumman Corporation 5
Process for Supplier Management
Acquisition Planning
Contract/ Subcontract
Awards
Deliver Accepted Products
Critical Design Review
Functional and Physical
Configuration Audits
Weapon System Integration
Testing
Production Readiness Reviews
Low Rate Production
Full Rate Production
Role of Program Manager and Engineers – Pre Award and Design
Conduct program reviews monthlyCost, Schedule, Technical, Risk, and Corrective Actions to Variances
Conduct independent technical review for design reviews/audits Establish Weapon System Integration test procedures Monitor progress toward production readiness
Role of Program Manager and Engineers – Pre Award and Design
Conduct program reviews monthlyCost, Schedule, Technical, Risk, and Corrective Actions to Variances
Conduct independent technical review for design reviews/audits Establish Weapon System Integration test procedures Monitor progress toward production readiness
Role of Program Manager and Engineers - Production Conduct program reviews every 6-8 weeks
Cost, Schedule, Technical, Risk and Corrective Actions to Variances
Approve Class I changesReview Class II changes
Attend selected on-site joint reviews of sub-tier suppliers
Role of Program Manager and Engineers - Production Conduct program reviews every 6-8 weeks
Cost, Schedule, Technical, Risk and Corrective Actions to Variances
Approve Class I changesReview Class II changes
Attend selected on-site joint reviews of sub-tier suppliers
Role of Quality Engineers – Pre Award and Design Qualify supplier for specific work scope Monitor supplier processes for compliance
Establish and monitor corrective actions when necessary
Team with first tier supplier on supply chain monitoringEstablish baseline for production qualificationAs necessary, develop or disqualify supplier prior to production readiness review
End Item Data Packet definition to ensure traceability to requirements
Role of Quality Engineers – Pre Award and Design Qualify supplier for specific work scope Monitor supplier processes for compliance
Establish and monitor corrective actions when necessary
Team with first tier supplier on supply chain monitoringEstablish baseline for production qualificationAs necessary, develop or disqualify supplier prior to production readiness review
End Item Data Packet definition to ensure traceability to requirements
Role of Quality Engineers - Production Participate in on-site joint reviews of sub-tier suppliers Conduct on-site inspection of process compliance during each
site visitEstablish and monitor corrective actions when necessary
Conduct three-way (Government, Prime, Supplier) buy-off of products
Resolution of material & process discrepancies (MRB)
Role of Quality Engineers - Production Participate in on-site joint reviews of sub-tier suppliers Conduct on-site inspection of process compliance during each
site visitEstablish and monitor corrective actions when necessary
Conduct three-way (Government, Prime, Supplier) buy-off of products
Resolution of material & process discrepancies (MRB)
2
Copyright 2005 Northrop Grumman Corporation 6
Early QA Involvement
Proposal Phase Participate in Alpha Negotiations QA Submits a Basis of Estimate Participate in Supplier Proposal Evaluation Approver of Contract Deliverables Definition Participate in the Final Proposal Review
Copyright 2005 Northrop Grumman Corporation 7
Early QA Involvement
Acquisition Strategy Make Buy (ASMB) SQE is a Signature SEIT is a Participant
Request For Proposal (RFP) Contains a Mission Assurance Requirements
Document Written by SQE in Concert With MA Team
SQE Reviews the Request for Proposal Supplier Selection
Pre-award Assessment Participate in Source Selection
Copyright 2005 Northrop Grumman Corporation 8
Early QA Involvement
Review & approval of Supplier/Subcontractor QA Plans Conduct Sub-tier Supplier Assessment Support Formal Reviews
SRR PDR CDR TRR PRR
Qualification Testing Support Functional and Physical Configuration Audits Conduct First Article Acceptance
Incoming Inspection Verification In-Process Audit and Inspection Verification
Copyright 2005 Northrop Grumman Corporation 9
Supplier Development
Process Owner Reviews Failure Modes and Effects
Analysis (FMEA) Develop/Review Work
Instructions Define/Develop/Document
Critical Processes Assist in Obtaining ISO
Compliance Review and Verification
of Audit Results/Findings
SubTier
QualitySurvey
Current Rating
CommentMitigation
RatingMitigation Plan
1 Date Y
G
2 Y
G
3 R
G
3 Y
G
2 Y
G
3 Y
G
3 R
G
R Y Minor Compliance Issues G ISO CompliantMajor Compliance Issues
Subcontractor
Supplier A
Supplier B
Supplier MonitoringSupplier Monitoring
Section: Overview
Supplier Name :
Date: March 10-11, 2004 NGMS Certification Audit Date
Supplier Site :
Supplier S
elf-
Assessm
ent
Poin
ts
NG
MS A
udit
Poin
ts
Tota
l Possib
le
Poin
ts
NG
MS A
udit
Poin
ts
Prime 19160 Form 260 Green Yellow Red
4.0 Quality Management System 13 2 0 54 43 60 71.7%5.0 Management Responsibility 10 6 1 63 43 68 63.2%6.0 Resource Management 6 2 0 30 23 32 71.9%7.0 Product Realization 10 1 0 41 32 44 72.7%7.3 Design and Development 6 6 3 54 33 60 55.0%7.4 Purchasing 11 3 3 56 42 68 61.8%7.5 Production & Service Provision 15 1 2 60 50 72 69.4%7.6 Control of Monitoring Measuring 8 1 1 40 27 40 67.5%8.0 Measurement, analysis and improvement 16 1 2 71 52 76 68.4%8.3 Control of Nonconforming Product 3 2 3 29 16 32 50.0%8.4 Analysis of Data 3 0 0 12 9 12 75.0%8.5 Improvement 7 2 3 44 28 48 58.3%N/ A Foreign Object Elimination 0 0 0 0 0 N/ A
ESD Program 17 0 1 72 66 72 91.7%N/ A Software 0 0 0 0 0 N/ A
554 398 612
90.5% 65.0% 65.0%
Suppliers Quality Management System has been properly documented in accordance with ISO 9001:2000 standards. Necessary Processes have been identified which pertain to their application throughout the organization. Assessment results indicate several major and minor deficiencies in understanding and meeting requirements, obtaining results of process improvement and effectiveness, and continual improvement of process based on objective measurement.
NGMS Approval
Supplier Assessment and CertificationRevision: Initial Release
Notes:
Total Points
Scores = Total Points / Total Available Points
Supplier Audit IAW ISO9000/AS9100Supplier Audit IAW ISO9000/AS9100
Copyright 2005 Northrop Grumman Corporation 10
Supplier Monitoring
Surveillance Plan Defines the Surveillance Program Enforces the Mission Assurance Requirements Surveillance Includes Mandatory Inspection Points
Production Processes Focus on Process Improvement Lean/Six Sigma Quarterly Scorecard Input Corrective Action
Copyright 2005 Northrop Grumman Corporation 11
Supplier Surveillance
FSMRB
FFSupplier Management
FFCorrective Action System
SFProcurement System
FSTraining Records
FSMetrics and Metrics Analysis
SSProduct Identification
FFConfiguration Management
FSData Management
FFInternal/External QA Audit results
SSTool Control
SSCalibration System
ProductionDevelopmentPeriodic Audits
F = Frequent S = Seldom
•Surveillance Includes Periodic Audits
Copyright 2005 Northrop Grumman Corporation 12
Supply Chain Management
Product Acceptance Verification That All Items Are Being Delivered
Hardware, Software, Documentation, Test Results, Spares, Data and Records
Verification That All Items Meet Contractual Requirements
Item Built IAW the Documented System All Requirements Are Verified Records Are Available As-Built Configuration Is Controlled
Copyright 2005 Northrop Grumman Corporation 13
Product Acceptance Continued Define Data Package
As-Built Configuration (Indentured Parts List) Proof of Traceability Requirements Having Been Met Open Action Items Are Documented Non-Conformances are Properly Corrected Waivers and Deviations are Documented Incorporated ECP’s Are Listed Review Build Paper
Recording of Critical Parameters Certificate of Conformance Accompanied With Objective
Evidence Incident Reports
Supply Chain Management
Copyright 2005 Northrop Grumman Corporation 14
Supplier Management Works at IPIC
Summary Early Participation in a Program Mission Assurance Requirements
Document Accompanies Every RFP Assessments are Accomplished Upfront Surveillance Plans are Defined and
Followed Product Acceptance/Delivery is Exhaustive
and is Unacceptable Without Objective Evidence
Early Recognition of Supplier Development Requirements
Manage the Complete Supply Chain Lessons Learned are Liberally
Incorporated
~ 650 Prime WAWF Sell-offs per year (multiple items & locations)
~ 650 Prime WAWF Sell-offs per year (multiple items & locations)
IPIC SQA Provides High Confidence in Fielded ProductIPIC SQA Provides High Confidence in Fielded Product
•
•••
••
•••
•••
•
•
••
••
•••
•
••
•
•
•