copy of tors issued by moef, new delhi vide letter...
TRANSCRIPT
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 1
COPY OF TORs ISSUED BY MoEF,
NEW DELHI
VIDE LETTER No.
F.No. J-11011/569/2010-IA II (I) Dated 31-12-2010
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 2
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 3
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 4
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 5
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 6
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 7
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 8
COMPLIANCE OF TORs
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 9
COMPLIANCE OF T. O. R.
Issued by MoEF vide letter No. J-11011/569/2010-IA-II (I) dated 31st Dec 2010
Their 13th – 14
th meeting held on 14
th July 2010
S.No. DESCRIPTION ACTION TAKEN
1. Executive summary of the project. See Page no.25-37 of EIA Report
2. Photographs of the existing and proposed
plant area.
Attached as Annexure-II in Page no-
145 & 146 of EIA Report.
3. Compliance to the conditions stipulated in
the Environmental Clearance / NOC granted
by the SPCB
NOC attached as Annexure-III in
Page no- 147 & 148 of EIA Report.
4. A line diagram/flow sheet for the process
and EMP
See Page No. 70 of EIA Report for
Flow Diagram of Process and for
EMP see chapter 8 (page no- 99) of
EIA Report.
5. Coal linkage documents The amount of coal usage is very low,
15 ton/day. It is available in local
market.
6. The earlier questionnaire for industry sector
should be submitted while submitting
EIA/EMP
Enclosed as Annexure-VII at Page
no- 158
7. A site location map on Indian map of 1:10,
00,000 scale followed by 1:50,000/1:25,000
scale on an A3/A2 sheet with at least next
10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200
GTS Sheet for 10 km radius is
already given in EIA Report. Refer
Fig No. 5.4 at Page no- 56.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 10
m. contours should be included. 3-D view
i.e. DEM (Digital Elevation Model) for the
area in 10 km radius from the proposal site.
8. Present land use should be prepared based
on satellite imagery. High-resolution
satellite image data having 1m-5m spatial
resolution like quickbird, Ikonos, IRS P-6
pan sharpened etc. for the 10Km radius area
from proposed site. The same should be
used for land used/land-cover mapping of
the area.
The existing land use is available
quite accurately on Google maps &
GTS sheets and further checked
through site visits. Its verification
through satellite imaginary may not
kindly be stressed. Refer fig no-5.2,
5.2-a at page no- 53 & 54 for location
on Google map.
9. Location of national parks / wildlife
sanctuary / reserve forests within 10 km.
radius should specifically be mentioned. A
map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks,
tiger reserve etc in 10 km of the project site.
Jamunwala Reserved Forest (about
2.5 km) Garib Nath & Rampur Beli
Reserved Forest (about 1.5 km).
Kalesar National Park is within the 10
km radius but no wildlife sanctuary/
within 10 km radius See Fig 5.2 & 5.4
of the EIA Report at page no- 53 and
56.
10. Project site layout plan showing raw
materials and other storage plans, bore well
or water storage, aquifers (within 1 km.)
dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the
project site should be included.
Details given in EIA Report Refer
page 55 and Fig 5.3 of the same.
11. Details and classification of total land
(identified and acquired) should be
It is an existing Unit and Land
already acquired. No additional land
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 11
included. required.
12. Proposal should be submitted to the
Ministry for environment clearance only
after acquiring total land. Necessary
documents indicating acquisition of land
should be included.
It is an existing Unit and Land
already acquired. No additional land
required.
13. Rehabilitation & Resettlement (R & R)
should be as per policy of the State Govt.
and a detailed action plan should be
included.
It is an existing Unit and Land
already acquired no additional land
required. Therefore no Rehabilitation
& Resettlement (R&R) policy is
required.
14. Permission and approval for the use of
forest land and recommendations of the
State Forest Department regarding impact
of proposed expansion on the surrounding
reserve forests, if applicable, should be
included.
There is no forest land use in the
project land.
15. A list of industries within 10 km radius of
the plant area.
Given in Table No.4.2 at page no- 49.
16. Residential colony should be located in
upwind direction.
No Residential colony is needed in
the Industry.
17. List of raw material required and source
along with mode of transportation should be
included. All the trucks for raw material and
finished product transportation must be
Environmentally Compliant?
List of raw material required is given
in EIA Report. Refer table-6.1 of
page no- 67 of the same. PUC
certificate of trucks used in
transportation will be complied.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 12
18. Petrological and Chemical analysis and
other chemical properties of raw materials
used (with GPS location of source of raw
material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite, quartz etc. using high
definition and precision instruments
mentioning their detection range and
methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-
WDXRF, EPMA, XRD, Nano studies or at
least as per I30-10500 and WHO norms.
These analyses should include trace element
and metal studies like Cr (vi) Ni, Fe, As, Pb,
Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
Lime stone, Clay, Gypsum, Clinker
and Fly ash are used in the
manufacturing process and their
quality is well established for cement
manufacturing. No further analysis
will be needed.
19. Petrography, grain size analysis and Major
element analysis of raw material and soil
from project site and raw material should be
done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O, CO2.
Analysis of soil from project site is
given in EIA report at Table no-7.9 of
page no-95. Lime stone, Clay,
Gypsum, Clinker and Fly ash are used
in the manufacturing process as such
chemical properties are not needed.
20. If the rocks, ores, raw material has trace
elements their petrography, ore microscopy,
XRD, elemental mapping EPMA, XRF is
required to quantify the amount present in it
and hence future risk involved while using
it and management plan.
No rocks and ores are used in the
process. Lime stone, Clay, Gypsum,
Clinker and Fly ash are used in the
manufacturing process.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 13
21. Studies for fly ash, muck disposal, slurry,
sludge material and solid waste generated
should also be included, if the raw materials
used has trace elements and a management
plan should also be included.
Trace elements are not found in the
raw materials; hence further studies &
Management plan for fly ash, muck
disposal, slurry, sludge material and
solid waste generated are not
applicable.
22. Manufacturing process details for all the
cement plant, captive power plant and mine
should be included.
Manufacturing Process detail of
cement plant is given in EIA Report
refer Para 6.5 on page No. 68. There
is no captive power plant and mine.
23. Possibility of installation of WHRB will be
explored and details included
There is no installation of Waste
Heater Recovery Boiler nor is it
required.
24. Mass balance for the raw material and
products should be included.
See fig-6.2 of Page No. 71 of EIA
Report.
25. Energy balance data for all the components
including proposed power plant should be
incorporated.
Energy Balance data is incorporated
in EIA Report. Refer Para 6.7 in Page
no-72.
26. Site-specific micro-meteorological data
using temperature, relative humidity, hourly
wind speed and direction and rainfall is
necessary.
Micro –Metrological data given in
EIA Report refer Para no. 5.4 - 5.9 at
page no- 57 to 61.
27. Sources of secondary emissions, its control
and monitoring as per the CPCB guidelines
should be included. A full chapter on
fugitive emissions and control technologies
For Process related emissions, there
will be dust extraction cum bag filter
systems. For non-process related
emissions there will be covered shed,
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 14
should be provided. tarpaulin cover, water sprinkler.
28. An action plan to control and monitor
secondary fugitive emissions from all the
sources as per the latest permissible limits
issued by the Ministry vide G.S.R. 414(E)
dated 30th
May, 2008.
For Process related emissions, there
will be dust extraction cum bag filter
systems. For non-process related
emissions there will be covered shed,
tarpaulin cover, water sprinkler.
Permissible limits issued by the
Ministry vide G.S.R. 414(E) dated
30th
May, 2008 are not applicable for
Cement Plant.
29. Vehicular pollution control and its
management plan should be submitted.
PUC certificate of vehicles used in
transportation will be complied.
Vehicle with-out PUC certificate will
not be allowed inside the industry
premises.
30. A write up on use of high calorific
hazardous wastes from all the sources in
kiln and commitment regarding use of
hazardous waste should be included.
There is no source of high calorific
hazardous wastes.
31. Ambient air quality at 8 locations within the
study area of 10 km., aerial coverage from
project site with one AAQMS in downwind
direction should be carried out.
See Table No. 7.4, 7.5 at page no- 78-
85 of the EIA Report.
32. The suspended particulate matter present in
the ambient air must be analyzed for the
presence of poly-aromatic hydrocarbons
(PAH), i.e. Benzene soluble fraction.
Detailed given in EIA Report refer
Table no- 7.5 in Page no-80-85. .
No Poly-Aromatic Hydrocarbons are
present in RSPM.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 15
Chemical characterization of RSPM and
incorporating of RSPM data.
33. Determination of atmospheric inversion
level at the project site and assessment of
ground level concentration of pollutants
from the stack emission based on site-
specific meteorological features.
Assessment of GLC of pollutants
from stack is given in Annexure-VI in
Page no-153 of the EIA report.
Maximum concentration is 1.527
μg/m3 at 2060 m from stack base
34. Air quality modeling for specific pollutants
needs to be done. APCS for the control of
emissions should also be included to control
emissions within 50 mg/Nm3.
Air quality modeling is given in EIA
report as Annexure-VI in Page no-
153.
35. Action plan to follow National Ambient Air
Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th
November, 2009 should be included.
Standards as fixed by the MoEF in
November, 2009 will be followed by
the project proponent.
36. Ambient air quality monitoring modeling
alongwith cumulative impact should be
included for the day (24 hrs) for maximum
GLC alongwith following :
i) Emissions (g/second) with and
without the air pollution control
measures
ii) Meteorological inputs (wind
speed, m/s), wind direction,
ambient air temperature, cloud
The outgoing air from the unit will
pass through APCD like Wet
Scrubber & Bag filters and will be
well within the permissible limits is
less then 150 mg/nm3
Meteorological data has been given.
See chapter 5, Page no- 57-62.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 16
cover, relative humidity &
mixing height) on hourly basis
iii) Model input options for terrain,
plume rise, deposition etc.
iv) Print-out of model input and
output on hourly and daily
average basis
v) A graph of daily averaged
concentration (MGLC scenario)
with downwind distance at
every 500 m interval covering the
exact location of GLC.
vi) Details of air pollution control
methods used with percentage
efficiency that are used for
emission rate estimation with
respect to each pollutant
vii) Applicable air quality standards
as per LULC covered in the
study area and % contribution of
the proposed plant to the
applicable Air quality standard.
In case of expansion project, the
contribution should be inclusive
of both existing and expanded
capacity.
The unit is on plain land near foothills
& the same has been considered while
considering modeling results.
Air quality modeling is given in EIA
report as Annexure VI in Page no-
153.
Graph of GLC concentration is given
in Annexure VI in Page no- 153.
Bag filters will be provided to control
Stack emissions. The efficiency of
bag filters will be 98-99 %.
It is an expansion project and result of
existing ambient air quality is given
in page no- 80-85.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 17
viii) No. I-VII are to be repeated for
fugitive emissions and any other
source type relevant and used for
industry
ix) Graphs of monthly average daily
concentration with down-wind
distance.
x) Specify when and where the
ambient air quality standards are
exceeded either due to the
proposed plant alone or when the
plant contribution is added to the
background air quality.
xi) Fugitive dust protection or
reduction technology for workers
within 30 m of the plant active
areas
Agreed & will be complied.
Graph of GLC concentration is given
in Annexure VI in Page no- 153.
The standards do not exceed at any
place & in view of highly efficient
APCD. They are not likely to exceed
in future also.
Fugitive emission will be collected
through exhaust fan and canopy
hoods and passed through bag filters.
37. Impact of the transport of the raw materials
and end products on the surrounding
environment should be assessed and
provided.
There is no impact of transport of raw
material on the surrounding
environment of the project as the
transport vehicles will have PUC
certificate always
38. One season data for gaseous emissions other
than monsoon season is necessary
Baseline data for all parameters has
already been given for three months.
Refer chapter-7, Table – 7.5 of page
no-69-74.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 18
39. Presence of aquifer/aquifers within 1 km of
the project boundaries and management
plan for recharging the aquifer should be
included.
Ground water level within 1 km is
about 10 m below ground level.
Ground water is recharged by Rain
Water Harvesting detail given
Chapter -11 at page no-97 of EIA
Report.
40. Source of surface/ground water level, site
(GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical
analysis for water to be used. If surface
water is used from river, rainfall, discharge
rate, quantity, drainage and distance from
project site should also be included.
Results of Ground water and Surface
water monitoring are enclosed in EIA
report, Refer Table no. 7.7 in page
no- 88-90.
No water is used from any river.
41. Ground water analysis with bore well data,
litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and
its management.
Enough ground water is available as
per report of CGWB. Since No waste
water goes to under ground its quality
will not change.
42. Ground water modeling showing the
pathways of the pollutants should be
included
No pollutants go to under ground
water from the unit.
43. Column leachate study for all types of
stockpiles or waste disposal sites, at 20oC-
50oC should be conducted and included.
The raw materials are in covered
shed. There are no possibilities of
leachatebility.
44. Action plan for rainwater harvesting
measures at plant site should be submitted
to harvest rainwater from the roof tops and
Rain Water Harvesting is done at the
project details given in Chapter-11 of
the EIA report at page no-107.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 19
storm water drains to recharge the ground
water and also to use for the various
activities at the project site to conserve fresh
water and reduce the water requirement
from other sources. Rain water harvesting
and groundwater recharge structures may
also be constructed outside the plant
premises in consultation with local Gram
Panchayat and Village Heads to augment
the ground water level. Incorporation of
water harvesting plan for the project is
necessary, if source of water is bore well.
45. Permission for the drawal of water from the
concerned authority and water balance data
including quantity of effluent generated,
recycled and reused and discharged is to be
provided. Methods adopted/to be adopted
for the water conservation should be
included.
Water will be drawal form the
Existing unit. No further permission
is required.
Water balance is given in Annexure-
IV at page no-149.
46. A note on the impact of drawl of water on
the nearby River during lean season.
The river is far from the unit. There
will be no impact on the river flow.
47. Surface water quality of nearby River (60 m
upstream and downstream) and other
surface drains at eight locations must be
ascertained.
Yamuna river is about 2 km from the
site and Giri river is about 6 km from
the site. Surface water quality results
of this two rivers are given in page
no- 90. There are no other perennial
surface drains present.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 20
48. If the site is within 10 km radius of any
major river, Flood Hazard Zonation
Mapping is required at 1:5000 to 1: 10,000
scales indicating the peak and lean river
discharge as well as flood occurrence
frequency.
Yamuna river is about 2 km from the
site and Giri river is about 6 km from
the site. The site is at a higher level
and above the HFL. It will not be
affected.
49. A note on treatment of wastewater from
different plants, recycle and reuse for
different purposes should be included.
Domestic waste-water is treated in
septic tank within the premises and
reused in the plantation within the
premises.
50. Provision of traps and treatment plants are
to be made, if water is getting mixed with
oil, grease and cleaning agents.
Water does not mix with any oil and
grease or any cleansing agent as such
trap and treatment plant is not
required.
51. If the water is mixed with solid particulates,
proposal for sediment pond before further
transport should be included. The sediment
pond capacity should be 100 times the
transport capacity.
It is only domestic waste water and
necessary sedimentation has been
provided in the septic tank.
52. The pathways for pollution via seepages,
evaporation, residual remains are to be
studied for surface water (drainage, rivers,
ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
Monitoring of ground water as well as
surface water is given in EIA report.
Refer page no- 88-90. It will be
regularly monitored as mentioned in
the EIA report.
53. Ground water monitoring minimum at 8
locations and near solid waste dump zone,
Results of Ground water monitoring
at 8 locations are given in EIA report,
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 21
Geological features and Geo-hydrological
status of the study area are essential as also.
Ecological status (Terrestrial and Aquatic)
is vital.
Refer Table no. 7.7 at page no- 88-90.
There is no wildlife sanctuary near
the site. The river is quite far, so that
Terrestrial and Aquatic life is not
affected.
54. Geo-technical data by a bore hole of upto 40
mts. in every One sq. km area such as
ground water level, SPTN values, soil
fineness, geology, shear wave velocity etc.
for liquefaction studies and to assess future
Seismic Hazard and Earthquake Risk
Management in the area and impacts due to
land slides.
The area lies in Zone – IV of seismic
zone. There is no history of any major
earthquake in the last 50 years.
55. Action plan for solid/hazardous waste
generation, storage, utilization and disposal.
A note on the treatment, storage and
disposal of all type of solid waste should be
included. End use of solid waste viz. fly ash
etc. and its composition should be covered.
Refer Para 7.5.8 and 7.5.9 at page no-
98 of EIA Report.
56. All stock piles will have to be on top of a
stable liner to avoid leaching of materials to
ground water.
The raw materials are in covered
shed. There are no possibilities of
leaching.
57. Action plan for the green belt development
plan in 33 % area should be included. The
green belt should be around the project
boundary and a scheme for greening of the
Given in layout plan. Refer page no –
101 of the EIA report.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 22
travelling roads should also be incorporated.
All rooftops/terraces should have some
green cover.
58. A scheme for rainwater harvesting has to be
put in place. Incorporation of water
harvesting plan for the project is necessary,
if source of water is bore well. Efforts
should be made to make use of rain water
harvested. If needed, capacity of the
reservoir should be enhanced to meet the
maximum water requirement. Only balance
water requirement should be met from other
sources.
Detail is given in Chapter-11 in page
no-107 of the EIA report.
59. Detailed description of the flora and fauna
(terrestrial and aquatic) should be given
with special reference to rare, endemic and
endangered species.
Detailed description of flora and
fauna along with special reference to
rare, endemic and endangered species
is given in EIA report, Refer Para
5.15 at page no- 64 of the report.
60. Action plan for the green belt development
plan in 33 % area should be included. The
green belt should be around the project
boundary and a scheme for greening of the
traveling roads should also be incorporated.
All rooftops/terraces should have some
green cover.
Given in layout plan. Given in layout
plan. Refer page no – 55 of the EIA
report.
61. Detailed description of the flora and fauna
(terrestrial and aquatic) should be given
Detailed description of flora and
fauna along with special reference to
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 23
with special reference to rare, endemic and
endangered species.
rare, endemic and endangered species
is given in EIA report, Refer Para
5.15 at page no- 64 of the report.
62. At least 5 % of the total cost of the project
should be earmarked towards the corporate
social responsibility and item-wise details
along with time bound action plan should be
included. Socio-economic development
activities need to be elaborated upon.
5% of the cost of the project shall be
spent on welfare projects as CSR.
Details given on Page no-137 of EIA
report.
63. Disaster Management Plan including risk
assessment & damage control needs to be
addressed and included. Landslide hazard
map and mitigation plan, Earthquake history
and management plan should be submitted.
Given in EIA Report. See page no-
118 of Chapter-12.
64. Details regarding expected Occupational &
Safety Hazards. Protective measures for
Occupational Safety & Health hazards so
that such exposure can be kept within
permissible exposure level so as to protect
health of workers. Health of the workers
with special reference to Occupational
Health. Plan of exposure specific health
status evaluation of workers; pre placement
and periodical health status of workers; plan
of evaluation of health of workers by pre
designed format, chest x ray, Audiometry,
Spirometry Vision testing (Far & Near
vision, colour vision and any other ocular
defect) ECG, during pre placement and
periodical examinations and plan of
monthly and yearly report of the health
status of workers with special reference to
The details about the occupational
Health of workers have been given in
Chapter-13 of the EIA Report in page
no-128.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 24
Occupational Health and Safety.
65. Plan for the implementation of the
recommendations made for the cement plant
in the CREP guidelines must be prepared.
The project does not fall under the
CREP guidelines Industries. As such
this is not attracted.
66. At least 5 % of the total cost of the project
should be earmarked towards the corporate
social responsibility and item-wise details
along with time bound action plan should be
prepared and incorporated.
5% of the cost of the project shall be
spent on welfare projects as CSR.
Details given on Page no-137 of EIA
report.
67. A note on identification and implementation
of Carbon Credit project should be
included.
Given in Annexure-V at page no-
150-152.
68. Total capital cost and recurring cost/annum
for environmental pollution control
measures.
Given. Refer Chapter-14 in page no-
136 of EIA Report.
69. Public hearing issues raised and
commitments made by the project
proponent on the same should be included
separately in EIA/EMP Report in the form
of tabular chart.
The result of public hearing
conducted by the Himachal Pradesh
Pollution Control Board has been
given in Annexure-I in Page no-139-
144 of EIA report.
70. Any litigation pending against the project
and / or any direction / order passed by any
Court of Law against the project, if so,
details thereof.
No. There is no litigation pending
against the project and / or any
direction / order passed by any Court
of Law against the project
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 25
EXECUTIVE SUMMARY
For
AMBASSADOR CEMENTS LTD.
Village-Patti Natha Singh, Paonta Sahib, Distt. - Sirmaur,
Himachal Pradesh.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 26
EXECUTIVE SUMMARY
I. INTRODUCTION
Environmental awareness is growing day by day and the development actions viz-
a-viz their consequences are getting due attention at all levels. Department of
Environment and Forest G.O.I & State Pollution Control Boards have already
taken stringent actions to protect the bio-diversity and environment of the Country
and have enacted various laws towards that end.
M/S Ambassador Cements Limited., proposed to enhance the capacity of existing
cement manufacturing unit from 15,000 MTA to 45,000 MTA at Village Patti
Natha Singh, Teh. Paonta Sahib, Distt. Sirmaur, Himachal Pradesh. As per
requirements they have to get Environmental Clearance as per G.O.I Notification
No. 1533 dated 14-09-2006 for which necessary documents were submitted to the
EAC, MOEF, New Delhi who have desired to submit the Final E.I.A. report as
per TOR laid out by them in the meeting held on 14-12-2010 at New Delhi. One
of the conditions in the TOR is that public hearing should be got done & result
should be incorporated in the EIA Report. Accordingly, State Pollution Control
Board conducted the Public Hearing on 22/03/2012 and EIA Report of the project
has been prepared incorporating Public Hearing result. This final report has,
therefore, been as per the TOR issued to assess the likely impact of the proposed
project on various factors which may be affected with the implementation of the
programme and to suggest remedial/ precautionary measures, if any.
II. PROJECT DESCRIPTION
General
M/s Ambassador Cements Ltd. proposes to enhance the capacity of their Cement
Plant at Village Patti Natha Singh, Tehsil Paonta Sahib, District Sirmaur, H.P. It is
on the outskirt of Paonta Sahib Town, where there are other Industries also.
However it is away from the residential area. The Project has been envisaged to
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 27
meet the growing demand of cement in the market. The site plan and location plan
are given as Figure 4.1 and 4.2 respectively.
Finished Product
The firm proposes to manufacture pozzolana portland cement.
Installed Capacity
The existing capacity of the unit is 15,000 MTA and the proposed additional
capacity is 30,000 MTA Thus the total capacity of the unit will be 45,000 MTA.
Taking 300 working days in a year the daily production will be 150 TPD.
Raw Materials
The major raw materials and their requirements per day are as under:
S.No. Raw Materials Quantity (MTD) Source
a. For Clinker
1. Lime Stone 123 H.P
2. Coke Breeze 23 Gujarat
3. Clay 15 Rajasthan
4. Additives 4 Kala Amb
b. For Cement
1. Clinker 98.5 Own Unit
2. Gypsum 7 Rajasthan
3. Fly Ash 45 PanipatT.P., Haryana
Manufacturing Process
Vertical shaft kiln process has been adopted for the manufacturing of Portland
cement conforming the specification IS 269:1976. The process involves two steps.
i) Preparation of clinker
ii) Grinding of clinker and other additives & mixing
The brief description of the process is given as under:-
i)The basic raw-materials i.e. lime stone, calcinated clay and breeze coke are
stored in the storage yard, crushed separately and transferred to the individual
raw-material silos with the help of bucket elevators. These are then weighed in a
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 28
desired ratio and transferred to a ball mill for grinding. The mixture is sent to the
blending silo where they are mixed under high pressure blower. It is then
transferred to nuduliser to prepare nodules before feeding them into the kiln. The
nodules are then transferred to the vertical shaft kiln, uniformly spread over the
entire area of the fire bed of the kiln and they travel downward and undergo
various reactions like drying, calcining and sintering and cooling and get
converted into clinker. The required combustion air in the kiln is supplied by a
blower. The hot exhaust gasses escape through air pollution control devices and
then to the chimney. The clinker is sent to clinker storage shed.
ii) The clinker is then grinded with gypsum to manufacture Portland cement.
Around 4 to 5% gypsum and about 30% flyash is added to the clinker and
material is crushed to 0.25 mm size. The crushed material is then taken to a
cement grinding mill for fine grinding of the product to a level of 200 mesh.
Grounded cement is transferred to blending silo with the high pressure blower
where thorough mixing is carried out. It is finally weighed / packed in bags
through automatic machines.
Other Features:
Addition of Fly ash from Panipat Thermal Power Station (TPS) in the PPC
adds value to the waste product generated from TPS, i.e. fly ash – an
environment unfriendly waste.
The plant would incorporate the most modern control system using the
latest microprocessor based Dust Control System
Cooling water circuit is close circuited, whereby ensuring no generation of
waste water
The process, selected envisages re-cycling all the material collected in the
pollution control equipment whereby ensuring no generation of solid
waste.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 29
The plant lay out is so arranged that the major production units are laid in a
straight line whereby minimizing / avoiding the various transfer points.
Capacity of the units is planned so as to minimize the number of
equipment.
Power
The power demand for the proposed unit is about 1200 KW. The unit has
already 432 KW and it is proposed that the additional demand of 768 KW will
be met by sourcing the power from HP Electricity Board from the nearby Sub-
station.
Water
Water consumption for the cement manufacturing unit will be small as the
requirements are only for Nodulising, scrubbing system and domestic use.
The requirement of water will be 10 KLD per day. The makeup water of about
03 KL/day is required for meeting the evaporation losses. In addition about 2.0
KLD water will be needed for domestic purpose and 05 KLD will be used in
process. Source of water would be from ground water through a tube-well
within the premises.
HUMAN SETTLEMENTS
The unit is situated in Industrial area. The nearest major town Paonta Sahib is
close to site, about 1.5 Kms, with a population of 19086 approx.
PLACES OF TOURIST INTEREST
There are no major places of tourist interest near the plant. However a historic
Gurudwara in Paonta Sahib is at a distance of about 4 Kms from the site.
SOIL
Soil where the Industry is located is sandy loam and clayey type and is good
for agriculture purposes. The topography of the area is semi hilly on the foot
hills of Shivalik Range.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 30
DRAINAGE
The entire area is near the Shivalik foot hills and has good slope from North-
East to South-West. The area is well drained and is frequented with seasonal
choes which take the entire rain water flows to river Yamuna.
LAND USE
Land use pattern means how the land is being used for various purposes. It
highlights the environmental quality of a particular area. It is an important
indicator of environmental health, intensity of human activity and degree of
interaction between the two. Land use pattern is significantly influenced by the
nature of soil, water availability and climatic conditions of the area. Data on land
use pattern of Sirmaur District have been collected to present baseline status of the
study area which falls in this District and is given below:.
Land use pattern
Total Area - 2, 82,500 Ha Cultivated Area - 74,700 Ha
(26.4%) Forest area - 1, 74,820 Ha (62%)
Non agriculture use - 72,980 Ha(11.6%)
FOREST
A number of reserved forests exist in the study area. Species like in these
forests are Sal, Chil, Oaks, Deodar, Khair, Firand Spurce are found. On the
north side the dense forests are at a distance of 3-5 km. Reserve Forest
Jamunwala exists at a distance about 2.5 km & Garib Nath at about 1.5 km
North, Rampur Beli exists at a distance 1.5 km on the South side, Danda RF
exists at a distance 5 km on the North-East side from the site. Reserve Forest
along the Shivalik range like Khulhal, Dhaula & Aduwala are at a distance of
about 4-5 km on the South side. It is worth mentioning here that the promoters
plan to plant about 200 trees in the unit area.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 31
III ENVIRONMENTAL IMPACT ASSESMENT
Present Environment
Various Environmental factors as existing in the study area which are liable
to be affected by the activities have been assessed both quantitatively and
qualitatively. Following are the factors which could be sensitive to the plant
activities.
i) Ambient Air
ii) Water Quality
iii) Noise Levels
iv) Transport & Communications
v) Educational Facility
Ambient Air Quality
To quantify impact of the project on the Ambient Air quality it is necessary to
measure the background level of Air Pollutants which are existing in the
surrounding areas of the Unit. On this, the value effect due to the unit is to be
added to obtain the future predicted quality levels. The background air quality of
RSPM, SO2 and NOx has been determined quantitatively by conducting field
monitoring. Sites of the monitoring stations were selected keeping in view
the dominant wind direction. They were spread in an area of 10 KM round the
site. The values are well with in the prescribed limit. Effects of the expected
pollutants coming out of the unit have been studied. Presently the values of
various parameter of ambient air quality at project site are as under:
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 32
Existing Permissible
PM2.5 - 31 ug/m3 60 ug/m
3
PM10- 59 ug/m3
100 ug/m3
SO2 - 2.9 ug/m3 80 ug/m
3
NOx - 19.6 ug/m3
80 ug/m3
The existing levels from the stack emission were also checked up. These are of
the order of 50 mg/Nm3. GLC with the emission was checked through a model &
it was seen that the resultant maximum effect will be about 1.5 ug/m3
at a
distance of 2060 m in the windward direction. Thus even after increase in
capacity the total SPM level in the ambient air will still be well within the limits.
Water Quality
Study of water environment is essential to know what is contained within the
existing natural environment & how it can be expected to respond to the
activities of the unit. Water resources in the study area may be classified in two
categories.
i) Ground Water
ii) Surface Water
The principal source of water for both these categories is the precipitation.
Rainfall, thus, is the single most important factor controlling the water availability
in the area. The annual rainfall in the area is about 978 mm and the major
precipitation is in the months of July to September (Monsoon Season) and
nominal in summer months of March to May.
There are small seasonal streams in the study area, which remain dry during
whole year except rainy season. Company proposes to draw water from the
underground source through a tube-well drilled within their premises. For
assessing the quality of water in the study area samples of water (ground &
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 33
surface) were collected and the results of water samples have been given in the
detailed EIA Report.
Waste Water
Various likely sources of waste water from the plant are as below.
i) Process Water
A small quality of water is used for Nodulising in the process as such there is
no waste water from this activity.
ii) Domestic Sewage
Domestic waste from the toilets is treated through septic tank and then used
for plantation within the premises.
Noise Environment
Noise is defined as unwanted sound, which interferes with speech &
communication, causes annoyance, distracts from work and disturbs sleep and
thus adversely affects quality of human environment. Noise levels in the
area have been assessed and are within limits. Further the Ball mill &
blower are inside shed & room and no noise of appreciable value shall be
allowed to go outside.
Transport and communications
The project is located adjacent to Paonta Sahib and the site is well connected
to other towns like Yamuna Nagar and Sirmour through pucca roads. There is
frequent Bus service and approach to site is easy. There will be no impact of the
expansion on the existing transport & communication system.
Educational Facility
Educational facility in Paonta Sahib, the nearest City is good. There are
Government Colleges & Schools in the city. Adequate Education facility is
available. Primary Schools exist in the nearby villages. No change will be
needed in these institutions.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 34
Hazardous Materials
No hazardous materials are used in the process nor do the finished goods fall in
this category. There is no impact on the environment on this score.
IV ENVIRONMENT MANAGEMENT PLAN
Environmental Management Plan (EMP) is aimed at mitigating the
possible adverse impact of a project and for ensuring to maintain the
existing environmental quality. It is essential to implement the EMP right
from the planning stage and then continuing it throughout0 the construction
and operation stage. The impacts due to development works / construction
will be first minimized by adequate planning and taking construction
activities in a well organized manner. The specific measures that shall be
put to practice to minimize the impact on the environment are as below:
Air Pollution
The main sources of pollution from mini cement plants are as under:
1. Vertical Shaft Kiln emissions
2. Fugitive emission
The main emissions are generated from vertical shaft kiln. Wet scrubber will
be provided to control the emissions within prescribed limit and the treated
emission shall be discharged through stack of 40 feet height. There are no
process gases. Fugitive emissions which are due to handling of materials
will be collected through exhaust fans and bag filters will be provided in
various sections to control these emissions. Water shall be sprinkled on
roads to avoid dust generation by vehicles.
Water Pollution
A small quantity of water is consumed in the manufacturing process for
Nodulising only. There is no waste water from the process. Waste from the
toilets is treated in the STP and used for plantation within the premises.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 35
Noise Pollution
Although some noise is created due to Ball Mill & Jaw Crusher but the
machines are in enclosed sheds & it is not allowed to go outside. No specific
measures for noise control have, therefore, been provided by the firm. The
DG Set will be noise free. Acoustics shall be provided in the DG set room to
minimize the noise, if any.
Industrial Waste
Dried Sludge from scrubber and dust collected in the bag filters will be re-used
as raw material. No hazardous waste is generated from the factory; as such no
special arrangements are required towards that end.
V ENVIRONMENT MONITORING PLAN
Regular monitoring of all significant environmental parameters is essential
to check the compliance status vis-à-vis the environmental laws and
regulation. The frequency of the monitoring will be as follows:
The ambient Air quality shall be monitored at project site and two
upward and downstream locations once every quarter for RSPM, NOx &
SO2, levels during the Construction Phase and Operational Phase.
The Ambient Noise Levels shall also be monitored once every six
months.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 36
Environment Management Cell:
The Environment Management Cell shall be created to effectively monitor
all parameters. Thus the Environment Management Cell shall include:
Representative of Management (Head of Environment Cell)
Process Incharge from STP/APCD, Water Works
Incharge Maintenance Department
A representative of Environmental Consultants
VI RAIN WATER HARVESTING
Recharge Potential
To compensate the withdrawal of underground water to some extent, Rain
Water harvesting has been done. The recharge is proposed to be done from
the roof top of the building only. The recharge potential thus available is as
below:-
Area of the catchment (Roof Top) A = 3150.9 m2
Average annual rainfall R = 0.978 m.
Runoff coefficient C = 0.8
About 80% of rainfall that falls on the roof (Roofs with tiles) is available
for use.
Annual Roof Top Rain Water Harvesting Potential = A x R X C
= 2465 m
3
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 37
VII. EXPENDITURE ON ENVIRONMENTAL MEASURES
Cost of environment protection measures
S.No Title Capital Cost
Rs. Lacs
Recurring Cost
Rs. Lacs
(Annum)
1. Air Pollution Control 15.0 1.5
2. Noise Pollution Control
(Including cost of
Landscaping, Green Belt)
5.0 0.5
3. Environment Monitoring
and Management (Including
Establishment of
Laboratory)
1.0 --
4. RWH 1.0 0.5
5. Miscellaneous
(Appointment of
Consultants, Management of
Environment Cell, Consent
fees and monitoring)
3.0 --
Total 25.0 2.5
Note: - Rs. 13.0 lacs shall be spent on CSR annually for the benefit of the
society specially the weaker section.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 38
FINAL ENVIRONMENT IMPACT
ASSESSMENT REPORT
For
AMBASSADOR CEMENTS LTD.
Village-Patti Natha Singh, Paonta Sahib, Distt. - Sirmaur,
Himachal Pradesh.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 39
CHAPTER-1.0
1. 1 INTRODUCTION
Environmental movement in India in its present form has its genesis in the
United Nations Conference on Human Environment held at Stockholm, in
June 1972. Mrs. Indira Gandhi, the then Prime Minister of India made a
mark in the conference with her off quoted remark “Poverty is the worst
Polluter”. The conference marked a water-shed in India’s efforts in
Protection of the Environment, forests & Wildlife. Legislations were
enacted for protection of the bio-diversity of the country.
Earlier, the assessment of the Projects was done on technical feasibility
reports and Cost-Benefit-Ratio which mainly considered financial &
technical resources. But no consideration was given to the Environment
protection in this evaluation and these flaws became apparent with
continuous deterioration of Environment. Thus in order to have more
realistic evaluation, and keeping in view the deteriorating condition,
another dimension was added which is now called as “Environmental
Impact Assessment” (E.I.A.). This forms an integral part of the Project and
is taken into account while appraising the Project at different stages. Thus
in the new comprehensive approach all considerations like, Technical,
Financial & Environmental are given due weightage.
M/s Ambassador Cements Ltd., are already manufacturing cement in
Village Patti Natha Singh, Tehsil Paonta Sahib, District Sirmaur, Himachal
Pradesh. They want to enhance the capacity of this plant. As per
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 40
requirements they have to get Environmental Clearance as per G.O.I
Notification No. 1533 dated 14-09-2006 for which necessary documents
were submitted to the EAC, MOEF, New Delhi who have desired to submit
the Final E.I.A. report as per TOR laid out by them in the meeting held on
14-12-2010 at New Delhi. One of the conditions in the TOR is that public
hearing should be got done & result should be incorporated in the EIA
Report. Accordingly, State Pollution Control Board conducted the Public
Hearing on 22/03/2012 and EIA Report of the project has been prepared
incorporating Public Hearing result. This final report has, therefore, been as
per the TOR issued to assess the likely impact of the proposed project on
various factors which may be affected with the implementation of the
programme and to suggest remedial/ precautionary measures, if any. Key
plan of the site is attached as Fig 1.1
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 41
FIGURE – 1.1
KEY – PLAN
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 42
CHAPTER-2.0
2.1 SCOPE
This study contains various information on the Environmental factors viz-a-
viz contribution of pollution by the proposed unit. These factors include air,
water, noise, health and welfare facilities, land use and agricultural pattern
etc., and discuss the predicted impact of the proposed plant activities on
these factors. Broadly under the scope of E.I.A. report it is envisaged:-
To assess the present status of air, water, land, noise, biological &.
Socio economic components of environment.
To identify, quantify & evaluate positive or negative impacts of various
operations on different environmental components.
To evaluate proposed pollution control measures and to suggest
additional control strategies, if any, to mitigate the adverse effects.
To prepare Environmental Management Plan for utilization and adoption
of safety measures.
To delineate future Environmental quality monitoring programme.
2.2 METHODOLOGY
Various steps involved in Environmental Impact Assessment study of the
proposed project are divided into the following phases:
Identification of significant environmental parameters and to study the
existing status within the impact zone with respect to air, water, noise, soil
and socioeconomic components of the environment.
Study of various activities of the proposed project to identify the areas
leading to impact/change in environmental quality.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 43
Identification/Prediction of impacts for identified activities and to
study levels of impact on various environmental components.
Evaluation of impacts after superimposing the predicted impact over
the baseline quality.
Formulation of Environmental Management Plan for implementation
in the proposed project.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 44
CHAPTER-3.0
3.1 PROFILE OF THE PROMOTORS & COMPANY
M/s Ambassador Cements Ltd is a public limited company registered
with the Registrar of Companies. It has three directors as below:
Name and address of Directors
1. Sh. Jaswinder Pal Singh Kohli
R/o Ward No. 9, Devi Nagar,
Paonta Sahib, H.P.
2. Sh. Pritpal Singh Kohli
R/o Ward No. 9, Devi Nagar,
Paonta Sahib, H.P
3. Smt. Jasver Kaur
R/o Ward No. 9, Devi Nagar,
Paonta Sahib, H.P
All the directors are experienced business men. They have been
running other units also.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 45
CHAPTER-4.0
4.1 MARKET SCENARIO
Cement growth is expected to be above the GDP growth of the country,
which is expected to be around 8% for the coming years. The Indian
cement Industry is poised for a period of significant growth and the demand
for cement is expected to match the current availability by the end of the
current fiscal. Cement demand has registered a CAGR of about 8% over the
last decade. In fact, at the current levels of growth, the cement industry may
have to add over 40 Million Tons of cement capacity to meet the demand
for cement over the next 5 years.
The industry performance during 2006-07 was characterized by volume
growth, stable to better cement prices and favorable demand-supply balance
in certain regions. Cement companies were operating at levels below
capacity in the past but with the demand and supply reaching equilibrium;
almost all plants are working at above 90% capacity. The rate of growth in
cement demand is growing at a faster pace as compared to the capacity
expansion. This will improve the realizations of the industry in the coming
financial years.
Due to heavy growth in the construction industry the demand for the
product so produced can never be under estimated. The unit’s main
objective would always be to satisfy the requirements of the potential
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 46
customers by providing them with products of good quality and proper
standard.
4.2 GROWTH POTENTIAL
India is one of the largest cement markets in the world, per capita
consumption of cement is just around 170 kg, which is very low in
comparison to the global average consumption of about 430 kg (as of
November, 2011). Cement Industry has growth potential not only within
the country but also for exports to the neighboring countries. With Indian
growth rate rising, the opportunities for the industry seem to be large.
Cement consumption in the coming years is likely to get a fillip from
Government initiatives for various housing and infrastructure.
4.3 NORTHERN MARKET
The Northern region consists of eight high-growth market clusters,
expected to grow at > 9% CAGR over next 5 years. The main objective of
this project is to meet the future requirement of the markets in the Northern
Region especially in Uttrarakhand and Northern U.P. markets. These
markets are large and growing, and remain attractive in the future, given
net demand-supply position. This project represents the optimal asset
footprint to meet future volume requirements. Also large number of
housing colonies, Malls, Bridges, Ready Mix Concrete plants & projects
are coming up in Punjab, Haryana & Himachal Pradesh. This project will
meet some of their needs.
4.4 OTHER FEATURES:
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 47
Addition of Fly-ash from Thermal Power Station (TPS) in the PPC adds
value to the waste product generated from TPS, i.e. fly ash – an
environment unfriendly waste.
The plant would incorporate the most modern control system using the
latest microprocessor based Dust Control System
Scrubbing water is close circuited, whereby ensuring no generation of
waste water.
The process, selected envisages re-cycling all the material collected in
the pollution control equipment whereby ensuring no generation of solid
waste.
The plant lay out is so arranged that the major production units are laid
in a straight line whereby minimizing / avoiding the various transfer points.
Capacity of the units is planned so as to minimize the number of
equipment.
Plant site & location details are given in table 4.1
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 48
Plant Site and Location Details
TABLE 4.1
S.No Particulars Details
1 Location
a Village Patti Natha Singh
b Tehsil Paonta Sahib
c District Sirmour
d State Himachal Pradesh
e Latitude 30° 27'29” North
f Longitude 77° 39'29” East
2 Elevation 389 mts. approx.
3 Land use at the project site Industrial area
4 Climatic Conditions
i) Tem. Min/Max/Average Min: 6.0oC, Max:40
oC
ii) Rainfall : Average, 900-1000 mm (average)
iii) Relative Humidity, % Min: 23%, Max:80%
iv) Wind speed, Kms/hour 15 Km (approx.)
5 Nearest highway National Highway-NH-72
(Nahan - Dehradun)
6 Nearest railhead/Railway station Yamuna Nagar (about 60 km)
7 Nearest airport Dehradun (about 42 km)
8 Features within 10 kms
i) Defence installations within 10 Kms Nil
ii) Archaeological important places within 10
Kms
Nil
iii) Wild life/ Elephant & Tiger reserve
sanctuaries within 10 Kms
Nil
iv) Reserved forest/Protected forest/National
Park within 10 km radius
Kalesar Natinal Park, Jamunwala
Reserved Forest (about 2.5
km),Garib Nath & Rampur Beli
Reserved Forest (about 1.5 km),
Danda RF (about 5 Km)
v) Industries Industrial Area ( list given on Page
no- 49)
vi) Rivers Yamuna River (about 2 km)
vii) State boundary in 10-Km radius Uttarakhand, Uttar Pradesh and
Haryana state boundary
vii) Hill ranges Shivalik
9 Nearest Major City Yamuna Nagar
10 Nearest Major Settlement Paonta Sahib
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 49
TABLE 4.2
List of Industries within 10 km radius of the plant area
S.No. Name of Industries Location
1. Nanz Med Science Pharma (P) Ltd. Paonta Sahib, Distt- Sirmour
2. Newtramax Healthcare Paonta Sahib, Distt- Sirmour
3. Next Wave India. Puruwala, Paonta Sahib, Distt- Sirmour
4. Nirman Cements Ltd. Patti Natha Singh, Paonta Sahib, Distt-
Sirmour
5. Nitin Lifescience Ltd. Rampur road, Paonta Sahib, Distt- Sirmour
6. P.D.C.Health Care Ltd. Paonta Sahib, Distt- Sirmour
7. Paonta Tyer Sales Paonta Sahib, Distt- Sirmour
8. Pharma Force Lab. Paonta Sahib, Distt- Sirmour
9. Quadricon Pvt. Ltd. Paonta Sahib, Distt- Sirmour
10. Ranbaxy Laboratories Ltd. Ganguwala, Paonta Sahib, Distt- Sirmour
11. Savitri Engineering Products Suraj Pur, Paonta Sahib, Distt- Sirmour
12. Sea Pharmaceuticles Suraj Pur, Paonta Sahib, Distt- Sirmour
13. Shree Shoes Misserwala, Paonta Sahib, Distt- Sirmour
14. Super Chem Industries Paonta Sahib, Distt- Sirmour
15. Surbhi Telelink Pvt. Ltd. Paonta Sahib, Distt- Sirmour
16. Tirupati Medicare Ltd. Paonta Sahib, Distt- Sirmour
17. Tirupati Zeon Medicare Ltd. Paonta Sahib, Distt- Sirmour
18. Tyre Top Paonta Sahib, Distt- Sirmour
19. Zee Laboratories, Unit-II Paonta Sahib, Distt- Sirmour
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 50
CHAPTER-5.0
BASELINE ENVIRONMENTAL SETTINGS
5.1 THE STATE
Himachal Pradesh having world’s mightiest mountain ranges and one of the
hilly States situated in the Northern part of India. It is blessed with some of
the most spectacular and beautiful landscapes. The total area of the State is
about 55,700 sq. km., with a population of more than 68 lacs. The literacy
rate is about 84% (as per 2011 census). The main fruits / crops in the State
are apple, plum, ginger, peach, potato, forest produce, rice and wheat. The
State has good deposits of minerals like gypsum, lime stone and slate etc.
Earlier the economy of the State mostly depended on tourism and a large
number of tourist sites had been developed by the State. However, after the
re-organization, the State has made big strides in the field of
industrialization also. Industries like Cement, Electronics, Fertilizers,
Pharmaceuticals and Liquor can be found in good number at different
places in the State. Hydel Power in the State has given a big boost to the
Industries. A number of Industrial areas have been developed in the State,
where all facilities are provided to the entrepreneurs. Parwanoo,
Barotiwala, Baddi, Paonta Sahib are some of the important industrial areas
developed by the State in the last two decades.
5.2 SIRMAUR DISTRICT:
District Sirmaur is located in outer Himalayas which is commonly
known as Shivalik range. The district is bounded by district Shimla in
North, Uttaranchal in East, Haryana in South and Distt. Solan in North-
20. Zeon Lifescience Limited Paonta Sahib, Distt- Sirmour
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 51
West. Like other parts of Himachal Pradesh , it has beautiful
landscapes, bracing climate, big and small game and legendry temples
which hold abiding attraction for the tourists. Head quarter of the district is
Nahan which is connected by metalled roads with Shimla, Chandigarh,
Solan and Yamuna Nagar. Population and area details of the districts are
as under:-
Population
Total 5,30,164 No. According to Census
2011
Male 2,76,801 No.
Female 2,53,363 No.
Rural 472,926 No. Male 246,599
Female 226,327
Urban 57,238 No. Male 30,202
Female 27,036
Sex Ratio 918
Density of Population 188 per sq. km
Geographical Area
Total Area 282500 Hect
Area under Forest 174822 Hect
Total Cultivated Area 74702 Hect
Net Cultivated Area 40775 Hect
Net Irrigated Area 13883 Hect
Source: Census 2011
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 52
5.2 PROJECT SITE
The Project site is situated at 30° 27'29” N, Latitude and 77° 39'29”E
longitude on National Highway No. NH-72. It is also connected by road
with Chandigarh (130 KM), Nahan (42 km), Paonta Sahib (04 km). The
area on the North & East Side of the project is comparatively plain and on
the West and South side, across the road, it has jungle growth. Total area of
the plot is 7 bigha 6 biswah.
A key plan showing various towns is attached as Fig. 1.1. Location of the
plant with respect to other features is shown is Fig. 5.1.
Location on Google Map & Layout plan of the unit is given in Fig. 5.2,
5.2-a and Fig. 5.3.
Figure 5.1
LOCATION PLAN
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 53
Figure 5.2
LOCATION ON GOOGLE MAP
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 54
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 55
Figure 5.2-a
LOCATION OF THE PLANT ON SATELLITE IMAGERY
(COURTESY GOOGLE EARTH)
PROJECT SITE
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 56
Figure 5.3
LAYOUT PLAN
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 57
Fig- 5.4
10 km Radius Map (Topo sheet No. H 43 L 11)
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 58
5.4 Climate:
Paonta Sahib has a sub-tropical continental monsoon climate characterized
by a seasonal rhythm, hot summers, slightly cold winters, unreliable rainfall
and great variation in temperature (0 °C to 40 °C). In winters, frost
sometimes occurs during December and January. It also receives occasional
winter rains from the western disturbance. Meteorological Data for the area
has been taken from the Chandigarh station which is the nearest
observatory for the site located at the distance of about 70 kms.
5.5 Temperatures
The area is semi-hilly with steep slopes and has Semi-arid climate.
December and January are the coldest months whereas in May and June the
heat is quite intense. The wettest months of the seasons are July, August
and September. The temperature varies from about 6oC minimum to about
40oC maximum during the year. Monthly average temperatures of the area
are given in Table-5.1
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 59
TABLE - 5.1
MONTHLY AVERAGE TEMPERATURE
Month
Mean Temperature oC
Daily
Minimum
Daily
Maximum
Jan 6.1 20.4
Feb 8.3 23.1
Mar 13.4 28.4
Apr 18.9 34.5
May 23.1 38.3
Jun 25.4 40.6
Jul 23.9 34.0
Aug 23.3 32.7
Sep 21.8 33.1
Oct 17.0 31.8
Nov 10.5 27.3
Dec 6.7 22.1
Source: IMD Data (2004-2009) Chandigarh
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 60
5.6 RAINFALL
The rainfall in the Zone is caused by the South-West monsoon. It starts in
the month of July and extends upto the end of September. During this
period the monsoon rain-fall contributes about 70% of the total annual
rainfall. The average annual rain fall is in the range of 900 to 1000 mm.
The annual number of rainy days on an average are about 51 in a year, out
of which about 31 fall in the monsoon period of July to September.
Monthly rainfall data for this zone is given in Table-5.2.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 61
Source: IMD Data (2004-2009) Chandigarh
5.7 HUMIDITY
In summer months of April, May and June, which is the driest part of the
year, the afternoon humidity comes down to 23% to 25% while the relative
humidity during monsoon months goes upto 75% to 80%. Monthly
humidity given in Table-5.3
TABLE - 5.3
MONTHLY HUMIDITY
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 62
5.8 CLOUDINESS
During monsoon season skies are over cast with moderate to heavy clouds.
During rest of the year, the sky is mostly clear. It is lightly clouded
occasionally during winter season.
5.9 WINDS
The Wind direction in the area is mostly from North-West to South-East.
During January to May the winds are quite strong while July to October is
calm months. The general trends of various meteorological data from
meteorological observatory by CSWCRT (Chandigarh) and field
observations are used to draw Wind Rose Diagram. The Wind rose diagram
is shown in Figure-5.5
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 63
Fig. 5.5
WINDROSE DIAGRAM
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 64
5.10 HUMAN SETTLEMENTS
The unit is situated in Industrial area. The nearest major city Paonta Sahib
is close to site, about 4 Kms, with a population of 19090 (as per 2001
census). Other small villages lying within 10 kms radius of the plant have
been shown in Table No- 7.1.
5.11 PLACES OF TOURIST INTEREST
There are no major places of tourist interest near the plant. However a
historic Gurudwara in Paonta Sahib is at a distance of about 4 Kms from
the site.
5.12 SOIL
Soil where the Industry is located is sandy loam and clayey type. The
topography of the area is semi hilly on the foot hills of Shivalik Range.
5.13 DRAINAGE
The entire area is near the Shivalik foot hills and has good slope from
North-East to South-West. The area is well drained and is frequented with
seasonal choes which take the entire rain water flows to river Yamuna.
5.14 LAND USE
Land use pattern means how the land is being used for various purposes. It
highlights the environmental quality of a particular area. It is an important
indicator of environmental health, intensity of human activity and degree of
interaction between the two. Land use pattern is significantly influenced by the
nature of soil, water availability and climatic conditions of the area. Data on
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 65
land use pattern of Sirmour District have been collected to present baseline
status of the study area which falls in this District and is given in Table 5.4.
TABLE-5.4
LAND USE PATTERN
Geographical Area (as on 31.03.2011)
Total Geographical Area 224738 Hect.
Area under Forest 48276 Hect
Total Cultivated Area 74347 Hect
Net Cultivated Area 40347 Hect
Net Irrigated Area 14312 Hect
Area sown more than once 34000 Hect
Source: Census 2011
5.15 FOREST
A number of reserved forests exist in the study area. Species like in these
forests are Sal, Chil, Oaks, Deodar, Khair, Firand Spurce are found. On the
north side the dense forests are at a distance of 3-5 km. Reserve Forest
Jamunwala exists at a distance about 2.5 km & Garib Nath at about 1.5 km
North, Rampur Beli exists at a distance 1.5 km on the South side, Danda RF
exists at a distance 5 km on the North-East side from the site. Reserve Forest
along the Shivalik range like Khulhal, Dhaula & Aduwala are at a distance of
about 4-5 km on the South side. It is worth mentioning here that the
promoters plan to plant about 200 trees in the unit area.
Flora and fauna:
Ecological system consists of varieties of interrelationship between both
biotic and abiotic components. Biotic components comprise of both plant
and animal communities, which interact not only within and between them
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 66
but also within the abiotic physical. Animal plant communities in their
natural habitat exist in a well organized manner. This natural setting may be
disturbed by any external man induced or nature induced influences.
Himachal Pradesh comprises of diverse terrain ranges from plain to the
mountains and has varied climatic zone. This diversity has endowed it with
very rich natural resources. In the area around the project where many
reserved forests exist, the flora generally consists of khair, shisham, sahl,
kordia and variety of climbers can be found. The fauna in the area include
the animals & birds like Samber, Spotted Deer, Barking Dear, Jakel, Hare,
Jungle cat, Blue Jay, Black Partridge, Hill Crow, Bulbuls and Grey Pigeons
etc.
5.16 DEMOGRAPHY AND SOCIO-ECONOMIC SCENARIO:
As per census of 2011 the population of Sirmaur district is given in Table
5.5:
TABLE-5.5
Total Population 530,164 (100%)
1. Male 2, 76,801 (52.2%)
2. Female 2, 53,363 (47.7%)
3. Literacy Rate (Avg.) 369,651 (69.7%)
4. Male Literacy Rate 2, 09,608 (39.5%)
5. Female Literacy Rate 1, 60,043 (30.1%)
Source: Census of India: 2011.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 67
CHAPTER-6.0
PROJECT DESCRIPTION
6.1 General
M/s Ambassador Cements Ltd, propose to enhance the capacity of their
Cement Plant at Village Patti Natha Singh, Tehsil Paonta Sahib, District
Sirmaur, H.P. It is on the outskirt of Paonta Sahib Town. However it is
quite far from the residential area. The Project has been envisaged to meet
the growing demand of cement in the market. The location plan is given as
Figure 5.1.
6.2 Installed Capacity
Existing Capacity : 15,000 MTA
Proposed Capacity : 30,000MTA
TOTAL : 45,000 MTA
The unit operates for an effective period of 300 days in a year on three shift
of 24 hrs. per day basis.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 68
6.3 RAW MATERIALS
The major raw materials and their requirements per day are as under:
TABLE 6.1
DETAIL OF RAW MATERIAL
S.No. Raw Materials Quantity
(MTD)
Source
a. For Clinker
1. Lime Stone 123 H.P
2. Coke Breeze 23 Gujarat
3. Clay 15 Rajasthan
4. Additives 4 Kala Amb
b. For Cement
1. Clinker 98.5 Own Unit
2. Gypsum 7 Rajasthan
3. Fly Ash 45 Panipat T. P,
Haryana
6.4 MACHINERY:
The unit has some existing machinery / equipment at site. It is proposed to
add some more equipment. The details of major components are as under:-
S.No. Machinery/Equipment Existing Proposed
1. Raw Material storage Shed 1 1
2. Jaw Crushers for
Limestone, Clay & Gypsum
3 3
3. Motorized Weigh Batcher 1 -
4. Raw Material Silos 3 2
5. Raw Meal Grinding Ball
Mill
1 1
6. Blending Silos 2 2
7. Belt Conveyors for all
Sections
4 2
8. kiln 1 1 (previous one
will be replaced)
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 69
6.5 MANUFACTURING PROCESS
Vertical shaft kiln process has been adopted for the manufacturing of
Portland cement conforming the specification IS 269:1976. The process
involves two steps.
Preparation of clinker
Grinding of clinker and other additives & mixing
The brief description of the process is given as under:-
i) The basic raw-materials i.e. lime stone, calcinated clay and breeze coke
are stored in the storage yard, crushed separately and transferred to the
individual raw-material silos with the help of bucket elevators. These are
then weighed in a desired ratio and transferred to a ball mill for grinding.
The mixture is sent to the blending silo where they are mixed under high
pressure blower. It is then transferred to nuduliser to prepare nodules
before feeding them into the kiln. The nodules are then transferred to the
vertical shaft kiln, uniformly spread over the entire area of the fire bed of
the kiln and they travel downward and undergo various reactions like
drying, calcining and sintering and cooling and get converted into clinker.
The required combustion air in the kiln is supplied by a blower. The hot
exhaust gasses escape through air pollution control devices and then to the
chimney. The clinker is sent to clinker storage shed.
ii) The clinker is then grinded with gypsum to manufacture Portland cement.
Around 4 to 5% gypsum and about 30% fly ash is added to the clinker and
material is crushed to 0.25 mm size. The crushed material is then taken to a
cement grinding mill for fine grinding of the product to a level of 200
mesh. Grounded cement is transferred to blending silo with the high
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 70
pressure blower where thorough mixing is carried out. It is finally weighed
/ packed in bags through automatic machines.
Other Features:
Addition of Fly ash from Panipat Thermal Power Station (TPS) in the PPC
adds value to the waste product generated from TPS, i.e. fly ash – an
environment unfriendly waste.
The plant would incorporate the most modern control system using
the latest microprocessor based Dust Control System
Cooling water circuit is close circuited, whereby ensuring no
generation of waste water
The process, selected envisages “re-cycling all the material
collected in the pollution control equipment whereby ensuring no
generation of solid waste.
The plant lay out is so arranged that the major production units are
laid in a straight line whereby minimizing / avoiding the various
transfer points.
Capacity of the units is planned so as to minimize the number of
equipment.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 71
Lime Stone
Breeze Coke
Calcinated Clay
& China Clay Noduliser Kiln Clinker
Dispatch Trucks
Fly Ash SiloClinker
Silo
Gypsum
(Covered Shed)Fly Ash
From WagonsUnloading
of Clinkers
Cement Grinding Ball Mill
Packing Plant Cement Silo
WaterLime Stone
Breeze Coke
Calcinated Clay
& China Clay Noduliser Kiln Clinker
Dispatch Trucks
Fly Ash SiloClinker
Silo
Gypsum
(Covered Shed)Fly Ash
From WagonsUnloading
of Clinkers
Cement Grinding Ball Mill
Packing Plant Cement Silo
Water
Fig. 6.1
Manufacturing Flow Chart
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 72
Fig. 6.2
MATERIAL BALANCE (MTD)
LIME STONE
123
COKE BREEZE
23
CLAY
15
ADDITIVES
4
MOISTURE
64.5
VERTICAL SHAFT KILN
165
APCD
2.0
GYPSUM
07
CLINKER
98.5
FLY ASH
45
APCD
0.5 BALL MILL CEMENT
150
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 73
6.6 LAND
The Unit has 7 bighas and 6 biswas of land where the entire machinery
has been installed. The additional machinery will also be installed in the
same premises and no new land will be acquired.
6.7 POWER
The power demand for the proposed unit is about 1200 KW. The unit has
already 432 KW and it is proposed that the additional demand of 768 KW
will be met by sourcing the power from HP Electricity Board from the
nearby Sub-station. Details of Energy balance is given below:
A. Total Load : 1200 KW
1. Power load : 1165 KW
2. Office lighting load : 20 KW
3. Street lighting load : 15 KW
B. Savings:-
1. Energy savers (@ 4% energy saving) : 46.6 KW
2. Use of CFL for inner lighting : 10 KW
(CFL of 20 W instead of 40 W tubes @ 50%)
3. Use of solar energy for street lighting : 15 KW
(100% replacement)
Total Saving : 71.6 KW
% saving : 5.96%
6.8 WATER SUPPLY
Major water consumption for the unit will be in manufacturing, domestic
and cooling etc. For manufacturing process about 5 KLD water is
required. For cooling water will be re-circulated and only makeup water
of about 3.0 KLD is required for meeting the evaporation losses in the
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 74
cooling circuit. In addition about 02 KLD water will be needed for about
50 workers within the factory area. The total requirement of water is
about 10 KLD. Source of water is from ground water through a tube-well
within the Premises.
6.9 MANPOWER
The requirement of personnel for the proposed cement plant has been
made keeping in view of the following:
Technical concept of plant, including process control and
instrumentation.
Smooth and efficient operation of the plant.
Effective co-ordination between the various departments within the
plant.
Optimum organization will well defined and judicious job distribution
Optimum utilization of different grades of workmen and supervisory
Staff and
Maximum capacity of the facilities.
In all about 50 workers will be working in the unit.
6.10 WASTE HANDLING
There are no solid or liquid process wastes. Some waste from the toilets is
received which will be treated separately through Septic tank and used
within the premises for plantation.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 75
CHAPTER-7.0
ENVIRONMENTAL IMPACT ASSESMENT
7.1 General
The Cement Manufacturing Unit in Village Patti Natha Singh, Tehsil-
Paonta Sahib, Distt. Sirmaur, in Himachal Pradesh is about 4 Kms from
Paonta Sahib. The firm has already acquired 5490 sq.mt of land. In order
to assess the impact of the unit on the Environment, it is necessary to know
the existing level of various parameters & then superimpose the effect of
the units to know the end results of the same. For this purpose an area of
10 Km radius has been selected around the unit. Details of villages fallings
in this area are given in Table 7.1.
TABLE – 7.1
STUDY AREA DETAILS
(Within 10 Km Radius Area)
Sr.
No.
Name of Village Direction Distance
(Km)
1. Project Site - -
2. HaripurTohana N 0.5
3. Rampur S 0.75
4. Shivpur NE 2.0
5. Akalgarh E 1.5
6. Mohkampur E 2.0
7. Ambwala Singhpura E 2.5
8. Barotiwala E 0.5
9. Kanhuwala NE 3.0
10. Phulpur NE 3.25
11. Suratgarh N 4.0
12. Manpur Dewra E 4.5
13. Shyampur Bhur NE 5.0
14. Khorowala NE 4.75
15. Gorhawala NE 5.5
16. Harbatpur SE 7.5
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 76
17. Haripur N 0.75
18. Ramgarh SE 7.5
19. Dhakrani E 6.5
20. Devinagar SW 2.5
21. Badrinagar SW 3.5
22. Paonta Sahib SW 4.0
23. Surajpur SW 7.5
24. Kishanpur N 1.5
25. Jawalapur N 2.25
26. Matak Majri S 3.75
27. Ganguwala W 5.5
28. Fatehpur W 9.0
29. Purruwala NE 5.5
30. Misarwala W 9.5
31. Pipliwala W 9.0
32. Khara NW 6.0
33. Patiliyan SW 8.0
34. Naraigarh N 3.25
35. Kartarpur N 4.0
36. Nihalgarh NW 1.5
37. Amarkot NW 1.75
38. Taruwala W 3.0
39. Jamunwala W 6.0
40. Ajaiawala NW 6.0
41. Bhagwanpur W 8.0
42. Kiratpur N 4.0
43. Dhalipur SE 4.2
7.2 Population
The study area falls in district Sirmaur. The total population of the district
is about 530,164 persons in an area of 2825 sq kms and details are in Table
7.2: TABLE-7.2
Total Population No
Males 2,76,801
Females 2,53,363
Total Area 2825 sq kms
Population Density 188 per sq. km Source: Census 2011.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 77
7.3 Workers
People are mostly engaged in agriculture related activities. However, other
occupations are also practiced, although to a lesser degree, as per details
given below in table 7.3:
TABLE-7.3
Occupational Structure in the Area
Occupation 1991 2011 Percentage Growth
Agriculture Labour 591 505 -14.55
Agriculture Labour Supported by
Other employment
571 697 22.6
Cultivators 20255 20473 1.07
Cultivation Supported by other
Employment
690 756 9.5
House Hold Industry 571 425 -25.56
Transport and Communication 1234 3556 188
Trade and commerce 875 1586 81
Government Services 7499 7623 15
Government Services Supported
By other employment
2232 2487 11
Construction 245 1460 467
Industry 4326 17844 312
Ref: Census of India 2011.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 78
7.4 Present Environment
Various Environmental factors as existing in the study area which are liable
to be affected by the activities have been assessed both quantitatively and
qualitatively. Following are the factors which are sensitive to the plant
activities.
i) Ambient Air
ii) Water Quality
iii) Soil and Agriculture
iv) Land use pattern
v) Demography and Socio-economic pattern
vi) Transport & Communications
vii) Educational facility
7.4.1 AMBIENT AIR QUALITY
An area of 10 kms radius has been selected for study of various
parameters. The Status of Ambient Air Quality in the Study Area has
been determined by monitoring air quality in the Project Area at different
Locations. The study area is a mix of rural, urban and industrial area and
the various sources of pollution are dust arising from agricultural
activities, vehicular traffic and industries. Location of the monitoring
stations for Ambient Air Quality is given in Table 7.4 and shown in Fig.
7.1.The results are given in Table-7.5.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 79
TABLE 7.4
AIR MONITORING STATIONS
Sl.No. Sample code Name of village Coordinate
1 AA-1 Project site
Longitude: 77o39’29” N
Latitude: 30o 27’ 29” E
2 AA-2 Manpura Dewra Longitude: 77o41’50” N
Latitude: 30o 27’ 50” E
3 AA-3 Jawalapur Longitude: 77o38’19” N
Latitude: 30o 28’39” E
4 AA-4 Taruwala Longitude: 77o36’54” N
Latitude: 30o 27’15” E
5 AA-5 Devi Nagar Longitude: 77o36’39” N
Latitude: 30o 27’01” E
6 AA-6 Purruwala Longitude: 77o41’31” N
Latitude: 30o 30’ 13” E
7 AA-7 Matak Majri Longitude: 77o39’33” N
Latitude: 30o 25’34” E
8 AA-8 Dhalipur Longitude: 77o42’15” N
Latitude: 30o 26’29” E
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 80
Project SiteProject Site
Figure 7.1
Ambient Air Monitoring Station
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 81
TABLE-7.5
Summary of Ambient Air Quality Monitoring Results
AMBIENT AIR QUALITY (ug / m3 and CO in mg/m
3)
Location MONTH Concentration of Pollutants (µg/m3) 24-Hour
Average Value
Parameters SO2 NOX Pb CO PM2.5 PM10
Permissible Limits 80 80 1.0 2.0 60 100
AA1
Project
Site
Jan-2011 3.0 19.5 <0.01 0.4 29 59
Feb-2011 2.9 19.8 <0.01 0.4 31 59
Mar-2011 2.8 19.6 <0.01 0.4 33 60
Average 2.9 19.6 <0.01 0.4 31 59
AA2
Manpur
Dewra
Jan-2011 3.1 19.1 <0.01 0.4 30 58
Feb-2011 3.0 20.0 <0.01 0.4 32 58
Mar-2011 2.9 18.6 <0.01 0.4 31 59
Average 3.0 19.4 <0.01 0.4 31 58
AA3
Jwalapur
Jan-2011 2.7 18.5 <0.01 0.4 33 59
Feb-2011 2.8 18.8 <0.01 0.4 30 58
Mar-2011 3.0 19.8 <0.01 0.4 34 57
Average 2.8 19.0 <0.01 0.4 32 58
AA4
Taruwala
Jan-2011 3.1 18.5 <0.01 0.4 30 58
Feb-2011 2.9 18.8 <0.01 0.4 32 59
Mar-2011 3.0 18.6 <0.01 0.4 33 58
Average 3.0 18.6 <0.01 0.4 31 58
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 82
TABLE-7.5 (Contd...)
Summary of Ambient Air Quality Monitoring Results
AMBIENT AIR QUALITY (ug / m3 and CO in mg/m
3)
Location MONTH Concentration of Pollutants (µg/m3) 24-Hour
Average Value
Parameters SO2 NOX Pb CO PM2.5 PM10
Permissible
Limits
80 80 1.0 2.0 60 100
AA5
Devi Nagar
Jan-2011 3.1 17.5 <0.01 0.4 33 59
Feb-2011 3.2 18.1 <0.01 0.4 32 58
Mar-2011 3.0 18.6 <0.01 0.4 30 56
Average 3.1 18.0 <0.01 0.4 31 57
AA6
Purruwala
Jan-2011 2.9 18.1 <0.01 0.4 34 51
Feb-2011 2.8 18.9 <0.01 0.4 34 52
Mar-2011 3.2 19.6 <0.01 0.4 30 54
Average 2.9 18.8 <0.01 0.4 32 52
AA7
Matak
Majri
Jan-2011 2.9 18.9 <0.01 0.4 34 56
Feb-2011 2.8 19.6 <0.01 0.4 32 59
Mar-2011 3.2 18.6 <0.01 0.4 30 54
Average 2.9 19.0 <0.01 0.4 32 56
AA 8
Dhalipur
Jan-2011 2.9 19.6 <0.01 0.4 33 50
Feb-2011 2.8 18.8 <0.01 0.4 32 54
Mar-2011 3.2 18.1 <0.01 0.4 30 60
Average 2.9 18.8 <0.01 0.4 31 54
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 83
TABLE-7.5
AA 1-Project Site
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 04-01-2011 29 58 3.0 18.6 0.4 <0.01 ND ND 20 ND
2. 17-01-2011 28 62 2.9 19.4 0.4 <0.01 ND ND 17 ND
3. 28-01-2011 30 59 3.1 20.5 0.4 <0.01 ND ND 19 ND
4. 02-02-2011 32 58 2.8 19.7 0.4 <0.01 ND ND 17 ND
5. 12-02-2011 30 65 2.9 20.9 0.4 <0.01 ND ND 19 ND
6. 22-02-2011 31 56 3.0 18.8 0.4 <0.01 ND ND 18 ND
7. 07-03-2011 33 56 2.8 20.7 0.4 <0.01 ND ND 20 ND
8. 18-03-2011 32 67 2.9 18.4 0.4 <0.01 ND ND 19 ND
9. 29-03-2011 34 57 2.7 19.8 0.4 <0.01 ND ND 18 ND
MIN.
MAX.
28
34
56
67
2.7
3.1
18.4
20.9
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 17
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
TABLE-7.5
AA 2-Manpura Dewra
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 04-01-2011 29 60 3.0 17.6 0.4 <0.01 ND ND 16 ND
2. 17-01-2011 30 58 3.1 20.4 0.4 <0.01 ND ND 17 ND
3. 28-01-2011 31 56 3.2 19.5 0.4 <0.01 ND ND 19 ND
4. 02-02-2011 31 60 2.9 18.7 0.4 <0.01 ND ND 18 ND
5. 12-02-2011 33 58 3.0 21.9 0.4 <0.01 ND ND 17 ND
6. 22-02-2011 32 56 3.1 19.8 0.4 <0.01 ND ND 16 ND
7. 07-03-2011 31 60 3.0 19.7 0.4 <0.01 ND ND 19 ND
8. 18-03-2011 30 58 2.8 17.4 0.4 <0.01 ND ND 17 ND
9. 29-03-2011 32 59 2.9 18.8 0.4 <0.01 ND ND 18 ND
MIN.
MAX.
29
33
56
60
2.8
3.2
17.4
21.9
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
19
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 84
TABLE-7.5
AA 3-Jawalapur
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 04-01-2011 33 60 2.8 18.6 0.4 <0.01 ND ND 18 ND
2. 17-01-2011 34 58 2.7 19.4 0.4 <0.01 ND ND 16 ND
3. 28-01-2011 32 59 2.6 17.5 0.4 <0.01 ND ND 17 ND
4. 02-02-2011 29 60 2.9 18.7 0.4 <0.01 ND ND 17 ND
5. 12-02-2011 30 59 2.7 19.9 0.4 <0.01 ND ND 18 ND
6. 22-02-2011 31 55 2.8 17.8 0.4 <0.01 ND ND 19 ND
7. 07-03-2011 35 58 3.0 19.7 0.4 <0.01 ND ND 19 ND
8. 18-03-2011 33 56 2.9 20.9 0.4 <0.01 ND ND 20 ND
9. 29-03-2011 34 57 3.1 18.8 0.4 <0.01 ND ND 18 ND
MIN.
MAX.
29
35
55
60
2.6
3.1
17.5
20.9
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
TABLE-7.5
AA 4-Taruwala
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 04-01-2011 29 60 3.0 17.6 0.4 <0.01 ND ND 19 ND
2. 17-01-2011 30 59 3.2 18.4 0.4 <0.01 ND ND 17 ND
3. 28-01-2011 31 55 3.1 19.5 0.4 <0.01 ND ND 18 ND
4. 02-02-2011 33 60 2.8 19.7 0.4 <0.01 ND ND 17 ND
5. 12-02-2011 32 58 2.9 18.9 0.4 <0.01 ND ND 16 ND
6. 22-02-2011 31 59 3.0 17.8 0.4 <0.01 ND ND 18 ND
7. 07-03-2011 34 59 2.9 19.7 0.4 <0.01 ND ND 19 ND
8. 18-03-2011 32 58 3.1 18.4 0.4 <0.01 ND ND 20 ND
9. 29-03-2011 33 57 3.0 17.8 0.4 <0.01 ND ND 18 ND
MIN.
MAX.
29
33
55
60
2.8
3.2
17.6
19.7
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 85
TABLE-7.5
AA 5-Devi Nagar
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 07-01-2011 33 60 3.0 16.6 0.4 <0.01 ND ND 16 ND
2. 20-01-2011 34 59 3.1 18.4 0.4 <0.01 ND ND 17 ND
3. 31-01-2011 32 58 3.2 17.5 0.4 <0.01 ND ND 18 ND
4. 05-02-2011 31 59 3.3 19.7 0.4 <0.01 ND ND 17 ND
5. 14-02-2011 32 58 3.2 16.9 0.4 <0.01 ND ND 19 ND
6. 26-02-2011 33 57 3.1 17.8 0.4 <0.01 ND ND 18 ND
7. 10-03-2011 31 56 2.9 19.7 0.4 <0.01 ND ND 18 ND
8. 21-03-2011 30 57 3.0 17.4 0.4 <0.01 ND ND 19 ND
9. 31-03-2011 29 55 3.1 18.8 0.4 <0.01 ND ND 20 ND
MIN.
MAX.
29
34
55
60
2.9
3.3
16.6
19.7
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
TABLE-7.5
AA 6-Purruwala
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 07-01-2011 35 51 2.8 19.7 0.4 <0.01 ND ND 18 ND
2. 20-01-2011 34 50 2.9 16.9 0.4 <0.01 ND ND 17 ND
3. 31-01-2011 33 52 3.0 17.8 0.4 <0.01 ND ND 19 ND
4. 05-02-2011 35 52 2.8 19.7 0.4 <0.01 ND ND 18 ND
5. 14-02-2011 33 51 2.9 18.4 0.4 <0.01 ND ND 19 ND
6. 26-02-2011 34 53 2.7 18.8 0.4 <0.01 ND ND 20 ND
7. 10-03-2011 30 55 3.1 20.7 0.4 <0.01 ND ND 17 ND
8. 21-03-2011 31 54 3.2 18.4 0.4 <0.01 ND ND 19 ND
9. 31-03-2011 29 53 3.3 19.8 0.4 <0.01 ND ND 18 ND
MIN.
MAX.
29
35
51
60
2.8
3.3
16.9
20.7
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 17
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 86
TABLE-7.5
AA 7-Matak Majri
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 07-01-2011 33 54 2.8 19.7 0.4 <0.01 ND ND 18 ND
2. 20-01-2011 35 58 2.9 18.4 0.4 <0.01 ND ND 17 ND
3. 31-01-2011 34 56 3.0 18.8 0.4 <0.01 ND ND 16 ND
4. 05-02-2011 31 59 2.8 20.7 0.4 <0.01 ND ND 18 ND
5. 14-02-2011 32 58 2.9 18.4 0.4 <0.01 ND ND 19 ND
6. 26-02-2011 33 60 2.7 19.8 0.4 <0.01 ND ND 20 ND
7. 10-03-2011 29 55 3.1 19.7 0.4 <0.01 ND ND 20 ND
8. 21-03-2011 30 54 3.2 17.4 0.4 <0.01 ND ND 17 ND
9. 31-03-2011 31 53 3.3 18.8 0.4 <0.01 ND ND 19 ND
MIN.
MAX.
29
35
53
60
2.7
3.3
17.4
20.7
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
TABLE-7.5
AA 8-Dhalipur
S.NO DATE OF
MONITORING
PM2.5
(ug/m3)
PM10
(ug/m3)
SO2
(ug/m3)
NOX
(ug/m3)
CO
(mg/m3)
LEAD
(ug/m3)
NICKEL
(ng/m3)
ARSENIC
(ug/m3)
OZONE
(ug/m3)
AMMONIA
(ug/m3)
1. 07-01-2011 33 51 2.8 20.7 0.4 <0.01 ND ND 18 ND
2. 20-01-2011 34 50 2.9 18.4 0.4 <0.01 ND ND 17 ND
3. 31-01-2011 32 49 3.0 19.8 0.4 <0.01 ND ND 16 ND
4. 05-02-2011 31 55 2.8 18.7 0.4 <0.01 ND ND 18 ND
5. 14-02-2011 32 54 2.9 19.9 0.4 <0.01 ND ND 17 ND
6. 26-02-2011 33 53 2.7 17.8 0.4 <0.01 ND ND 19 ND
7. 10-03-2011 31 56 3.1 19.7 0.4 <0.01 ND ND 20 ND
8. 21-03-2011 30 67 3.2 16.9 0.4 <0.01 ND ND 17 ND
9. 31-03-2011 29 57 3.3 17.8 0.4 <0.01 ND ND 19 ND
MIN.
MAX.
29
34
49
67
2.7
3.3
16.9
20.7
0.4
0.4
<0.01
<0.01
ND
ND
ND
ND 16
20
ND
ND
Permissible Limits 60 100 80 80 4 1 20 6 100 400
The monitoring for PM10, PM2.5, Pb, CO, SO2 and NOX has been
undertaken from January, 2011 to March, 2011 as per CPCB guidelines.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 87
7.4.2 WATER QUALITY
Water quality of ground as well as surface resources in the study area
has been studied for assessing the water environment and to evaluate the
anticipated impact of the project. The monitoring locations have been
identified considering drainage pattern, population and croplands and
likely areas that represent base line conditions. Location of the
monitoring stations for Ground and Surface Water is given in Table 7.6 and
shown in Fig. 7.2.The results are given in Table-7.7.
TABLE-7.6
DETAILS OF GROUND WATER MONITORING STATIONS
S.No. Name Source
1. Project Site
(Patti Natha Singh)
Tube-well
2. Manpura Dewra Tube-well
3. Jawalapur Tube-well
4. Taruwala Tube-well
5. Devinagar Tube-well 6. Purruwala Tube-well
7. Matak Majri Tube-well 8. Dhalipur Tube-well
DETAILS OF SURFACE WATER MONITORING STATIONS
S.No. Name Source Coordinate
1. Jamuna River River Water Longitude: 77o42’14” N
Latitude: 30o 27’ 37” E
2.
Giri River River Water Longitude: 77o41’26” N
Latitude: 30o 27’57” E
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 88
Project SiteProject Site
Figure 7.2
Ground / Surface Water Monitoring Stations
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 89
TABLE-7.7
RESULTS OF WATER SAMPLES (mg/l except pH)
Ground Water
Characteristic GW-1
(Project Site)
GW-2
(Manpura Dewra)
GW-3
(Jawalapur)
GW-4
(Taruwala)
Colour, Hazen,
units.
<5 <5 <5 <5
Odour Unobjectionable Unobjectionable Unobjectionable Unobjectionable
Taste Agreeable Agreeable Agreeable Agreeable
Turbidity, NTU <5 <5 <5 <5
pH 7.2 7.2 7.0 7.1
Total Hardness (as
CaCO3)
180 168 172 186
TDS 210 206 214 232
Chloride (as CI) 32 46 42 56
Magnesium 7 10 8 12
Sulphate (as SO4) 82 94 78 92
Calcium 16 14 18 16
Fluoride (as F) BDL BDL BDL BDL
Sodium (as Na) 18 22 16 20
Cadmium(as Cd) BDL BDL BDL BDL
Iron (as Fe) 0.2 0.1 0.1 0.1
Cyanide (as CN) BDL BDL BDL BDL
Lead (as Pb) BDL BDL BDL BDL
Chromium (as Cr) BDL BDL BDL BDL
Mineral Oil BDL BDL BDL BDL
Ecoli/Total
Coliforms
Absent Absent Absent Absent
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 90
TABLE-7.7 (Contd.)
RESULTS OF WATER SAMPLES (mg/l except pH)
Ground/ Surface Water
Characteristic GW-5
(Devinagar)
GW-6
(Purruwala)
GW-7
(Matak Majri)
GW-8
(Dhalipur)
Colour, Hazen,
units,.
<5 <5 <5 <5
Odour Unobjectionable Unobjectionable Unobjectionable Unobjectionable
Taste Agreeable Agreeable Agreeable Agreeable
Turbidity, NTU <5 <5 <5 <5
pH 7.4 7.2 7.5 7.3
Total Hardness
(as CaCO3)
180 192 185 210
TDS 212 210 190 214
Chloride (as CI) 42 58 34 28
Magnesium 14 12 15 16
Sulphate (as SO4) 70 80 65 75
Calcium 14 16 15 14
Fluoride (as F) BDL BDL BDL BDL
Sodium (as Na) 16 20 20 14
Cadmium(as Cd) BDL BDL BDL BDL
Iron (as Fe) 0.1 0.1 0.1 0.1
Cyanide (as CN) BDL BDL BDL BDL
Lead (as Pb) BDL BDL BDL BDL
Chromium (as Cr) BDL BDL BDL BDL
Mineral Oil BDL BDL BDL BDL
Ecoli/Total
Coliforms
Absent Absent -- --
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 91
TABLE-7.7 (Contd.)
RESULTS OF WATER SAMPLES (mg/l except pH)
Ground/ Surface Water
Characteristic SW-1
Jamuna River
SW-2
Giri River
Colour, Hazen, units. <5 <5
Odour Unobjectionable Unobjectionable
Taste Agreeable Agreeable
Turbidity, NTU <5 <5
pH 7.8 8.0
Total Hardness (as CaCO3) 280 310
TDS 190 214
Chloride (as CI) 34 28
Magnesium 26 32
Sulphate (as SO4) 14 08
Calcium 72 64
Fluoride (as F) BDL BDL
Sodium (as Na) 20 14
Cadmium(as Cd) BDL BDL
Iron (as Fe) 0.1 0.1
Cyanide (as CN) BDL BDL
Lead (as Pb) BDL BDL
Chromium (as Cr) BDL BDL
Mineral Oil BDL BDL
Ecoli/Total Coliforms -- --
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 92
7.4.3 Ambient Noise Quality
Noise is defined as unwanted sound due to any operation. It has become
a common problem and ambient noise levels are on the rise all around.
Noise levels were measured at various locations and are reported in
Table 7.8 and shown in Fig. 7.3.
TABLE-7.8
NOISE LEVEL RESULTS
(BETWEEN, 9.00 A.M. – 12.00 NOON)
S. NO. SITE NOISE LEVEL COORDINATE
1. Project Site 52 Longitude: 77o39’29” N
Latitude: 30o 27’ 29” E
2. Manpur Dewra 42 Longitude: 77o41’50” N
Latitude: 30o
27’ 50” E
3. Jwalapur 46 Longitude: 77o38’19” N
Latitude: 30o
28’39” E
4. Taruwala 40 Longitude: 77o36’54” N
Latitude: 30o
27’15” E
5. Devi Nagar 41 Longitude: 77o36’39” N
Latitude: 30o
27’01” E
6. Purruwala 43 Longitude: 77o41’31” N
Latitude: 30o
30’ 13” E
7. Matak Majri 44 Longitude: 77o39’33” N
Latitude: 30o
25’34” E
8. Dhalipur 46 Longitude: 77o42’15” N
Latitude: 30o
26’29” E
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 93
Project SiteProject SiteProject Site
Figure 7.3
Noise Monitoring Station
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 94
7.4.4 SOIL
Soil is generally sandy loam and clay type almost all over the District and
Soil depth is generally shallow except in areas having good vegetative
cover. It is generally dry, shallow and deficient in organic matters. The
study area comprises mostly of alluvial deposits of Quaternary age. The
geological formations in the area comprise of Sandstone largely micaceous
and form major features. The top zone of this stage consists of maroon
clays and buff clays alternating one by one. Soil samples were collected
and have been analyzed. Average values of various properties of the soil are
given in Table 7.9 and location shown in Fig 7.4.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 95
Figure 7.4
Soil Monitoring Station
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 96
TABLE-7.9
RESULT OF SOIL SAMPLES
S. No. Parameter Monitoring Stations
Project Site Manpur Dewra
1. pH 8.2 8.0
2. Chlorides as Cl (ppm) 1.1 1.2
3. Sulphates as SO4 (ppm) 0.7 0.73
4. Soluable Sodium (%) 4.2 3.8
5. Potassium as K2O (kg/ha) 410 450
6. Calcium as Ca (ppm) 1.5 1.4
7. Megnesium as Mg (ppm) 0.8 0.9
8. Electrical Conductivity
(mili Siemens)
0.8 0.7
9. Bulk Density (g/cc) 1.2 1.2
10. Phosphorus as P2O5
(kg/ha)
58 56
11. Organic Carbon (%) 0.8 0.9
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 97
7.5 IMPACT / RISK ASSESSMENT
Under the "Present Environment" at the Project Site, the important factors which
are likely to be affected either positively or negatively have been brought out.
These will be checked up after the implementation of the project to cross check
the likely impact discussed here under.
7.5.1 Ambient Air Quality
Impact on ambient air quality at site and in the immediate neighborhood
could be attributed to the following sources of emissions. There are only
two sources of likely pollution:
SPM Emission from the clinker plant grinding units.
D.G. Sets emission.
Exhaust gases from the Vertical shaft kiln shall be passed through APCD
(Wet Scrubber) and then released to atmosphere. In the grinding unit the
raw material alongwith clinker shall be grinded in closed operation.
However, bag filter shall be provided to arrest any SPM coming out of the
grinding unit.
Flue gas from the DG Sets will pass through a chimney and the final gas
will be within permissible limits. Thus air environment is not likely to be
affected significantly.
7.5.2 Water Quality
The domestic use of water will be about 2.0 m3/day. The domestic effluent
will be treated through septic tank. It is used for plantation for which
species consuming large amount of water. Treated effluent will not be
thrown in any water body. Thus water environment is not likely to be
affected. Further, ground water will be balanced through recharge by rain
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 98
water harvesting from the roof top through recharge wells. Thus pressure
on underground water will be reduced.
7.5.3 Land Environment
It is an existing unit having land about 7 bighas 6 biswah. No extra land is
required for expansion of the unit. The land is already in use for industrial
purpose as such there will be no adverse effect on the land environment
with the coming up of the additional machinery.
7.5.4 Soil and Agriculture
The soil of the study area contains medium level of primary and secondary
nutrients. Agricultural operations will not be affected with the setting up of
the unit. The major crops in the study area are maize, wheat and rice with small
percentage of cotton. The emissions from the unit having insignificant pollution
load will not be of any threat to the vegetation & soil in this area.
7.5.5 Transport &. Communication
The existing transport communication system is good and the same would be
utilized by the workers for this unit which are about 50 in number. No additional
requirements are needed. Nor the existing ones will be affected in any manner.
The total quantity of the product after expansion will be about 150 MTD, which
does not require any special heavy transport arrangements.
The existing Transport &. Communication facilities are good enough to take
care of the activities of the unit. Thus the impact of the unit on this aspect
will be insignificant.
7.5.6 Demographic and Socio-Economic Growth
The strength of workers and staff in the factory is about 50 persons. All workers
are drawn mostly from the local population. Thus, there will not be any
appreciable change in population in the nearby towns. However, additional
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 99
employment potential will be generated which will be helpful to the local
area.
7.5.7 Noise Level
There will be some noise producing machinery. The D.G. Set will be
placed in acoustically sound proof room causing least disturbance in the
area. Ball Mill & Blower are inside shed & room and no noise of
appreciable value shall be allow to go outside. There is no likely hood of
change in noise environment. The existing noise levels in the areas are quite
low and are not likely to be disturbed by the unit. Hence noise impulses
would not cause any adverse impact on nearby human settlements.
7.5.8 Hazardous Materials
No hazardous materials are used in the process nor do the finished goods fall in
this category. There is no impact on the environment on this score.
7.5.9 Waste Disposal
No liquid or solid waste will be disposed off outside the factory. Toilet wastes
will be used for raising plantation within the factory premises after treatment.
There will be no effect of waste disposal on the environment in general.
Toilet facilities to the labour during construction will be provided @ 1 toilet
for 20 labourers and separate septic tank will be provided for the same. No
waste water shall be allowed to go outside.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 100
CHAPTER-8.0
ENVIRONMENTAL MANAGEMENT PLAN:
8.1 General
Environment Management Plan (E.M.P) in a project is prepared to mitigate
the possible adverse effect of various activities on the existing
environmental factors, during construction as well as in operational stages,
to avoid their deterioration, if any. It is desirable that necessary steps are
taken right from the beginning of the project to be more effective. As a
social and moral obligation on the part of every body it becomes our
bounden duty to leave our environment to the next generation in a state at
least what we inherited from our ancestors, if not in a better condition.
E.M.P. for this project has been prepared keeping in view the existing
conditions and likely changes which may occur due to the proposed project.
The implementation and monitoring of different control measures have also
been covered. These are discussed as under:-
8.2 EMP FOR AIR ENVIRONMENT:
a) During construction stage water will be sprinkled on the soil to avoid
dust generation.
b) The debris and unused construction malbas shall be removed
immediately for recycling, if any, or for land fill.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 101
c) Bag filters shall be provided to arrest SPM to keep it within permissible
limits.
d) All vehicles for service activities at the project site shall be checked for
vehicular emission.
e) The agencies will be asked to keep them within prescribed limits. They
will also be asked to maintain them properly.
f) After the project comes under operation, a chimney of suitable height
shall be provided for the D.G. Set to control the G.L.C. of S.P.M., SO2, &
NOx levels.
g) Extensive tree plantation shall be resorted to for further improving the
air environment in general.
8.3 EMP FOR WATER ENVIRONMENT:
a) Drinking water shall be drawn from a tube-well installed in the factory
area and distributed through an Over Head Service Reservoir. This will all
be a closed system.
b) During construction septic tank shall be provided for the labour with
toilet facilities for daily use. Waste water from the toilets shall be taken to
septic tank through underground delivery system.
c) Treated water will be completely used within the premises for tree
plantation, landscaping, parks and recycling for flushing etc. to reduce
withdrawal. It will not be thrown outside either on land or in any water
body.
d) Roof top Rain Water shall be harvested and used for ground water
recharge to minimize effect of withdrawal of water from the underground.
8.4 EMP FOR NOISE ENVIRONMENT
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 102
Noise is defined as unwanted sound, which interferes with speech &
communication, causes annoyance, distracts from work and disturbs sleep and
thus adversely affects quality of human environment. Noise levels in the
area have been assessed and are within limits. Further
a) The Ball mill & blower are inside shed & room and no noise of
appreciable value shall be allowed to go outside.
b) Tree plantation can also minimize the noise levels.
8.5 EMP FOR LAND ENVIRONMENT:
a) To avoid erosion of the top soil the development is planned in the
shortest possible time and land-clearing activity shall be kept to the
absolute minimum by working at the specific sites one by one where
construction is to take place so as to increase detention and infiltration.
b) The activities that result in soil being laid bare shall be scheduled in such
a way that some type of vegetative cover appropriate to the site shall be
established prior to onset of monsoons.
c) Natural waterways/drainage pattern shall be maintained by providing
culverts where needed.
d) The requirements of sand and aggregates for the construction works will
be supplied by venders. The land use is thus so planned that there is
minimum adverse impact.
8.6 EMP FOR SOLID WASTE
a) The solid waste generated from the construction activities shall be
effectively recycled within the project. Recyclable shall be sold to vendors.
b) The other solid wastes shall be dumped in a dumping pit of R.C.C.
construction and disposed off in the designated land fill places.
8.7 GREEN BELT:
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 103
The main objective of the green belt is to provide a barrier between the
source of pollution and the surrounding areas. The green belt helps to
capture the fugitive emission and to attenuate the noise generated, apart
from improving the aesthetics. Development of green belt and other forms
of greenery shall also prevent soil erosion and washing away of topsoil
besides helping in stabilizing the functional ecosystem and further, to make
the climate more conducive and to restore water balance. It is also
presumed that the selected plants will be grown as per normal horticultural
(or forestry) practice and authorities responsible for plantation will also
make sure that adequate provision for watering and protection of the
saplings exists at site.
The landscaping and green belt will be designed and trees will be planted
in open areas, around factory boundary along footpaths and dividers.
Standard practice will be followed for planting of saplings in pits of
substantial dimensions, 1m x 1m x 1m for big trees and almost half of
these dimensions for smaller trees and shrubs. The pits shall then be
filled with earth, sand, silt and manure in predetermined proportions.
Saplings planted in the pits will be watered liberally. The growing plants
will be cared for the first five years under favorable conditions of climate
and drainage. Care will be taken for nutrient supplement (healthy growth),
plant protection, absence of water stress (to maintain openness of stomata
apertures and epidermal structures) and exposure to normal atmospheric
conditions (free air flow). The guidelines as laid out in National Building
Code of India shall be followed in the overall development of Green Belt.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 104
CHAPTER-9.0
FIRE FIGHTING
9.1 INTRODUCTION:
The proposed unit is coming up in an area, which is a mix of industrial and
residential area. It is, therefore, desirable that there should be an
emergency plan in case there is any accident in any industry and worker
residents are to be evacuated.
9.2 MANAGEMENT OF FIRE & OTHER HAZARDS
Industrial fires and explosions cause considerable damage to lives and
property besides impending productivity. This damage may extend to
neighboring areas.
The fundamental approach, governing fire safety attempts to ensure that
fires do not at all start in the first place and should they occur, to restrain
their spread by quick detection and extinguishment.
9.3 PREVENTION OF SPREAD OF FIRE:
Despite the many precautions taken, fires do break out. Hence every
factory should have established measures to detect a fire and to attack it
immediately. Automatic fire detection has many advantages such as speed
and reliability and is recommended for warehouses, control
rooms/computer rooms and unoccupied areas with high fire hazard.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 105
Depending on the nature of the occupancy and the hazard, a variety of
detection systems are available. They are activated by one of the effects
of fire such as temperature rise, smoke flame or heat and can be coupled
to an alarm system which would provide visual/audible alarms at
designed manned locations. They can also be designed to automatically
actuate fire- extinguishing systems. The selection/installation of the
detection system shall conform to the applicable National Standards.
Equipment for fire fighting shall be chosen with care and suited to the
task.
9.4 MANAGEMENT PLAN:
The task of accident and emergency control can be simplified and made
effective if pre- planned systems and procedures are available. Without
these, important matters may be overlooked at the time of an emergency.
As an elaborate system of control and training of the workers will be
developed to cope for any emergency.
To have effective control a Management Plan will be prepared to alert and
take care of the workers and residents of the area, in case there is any fire
or other accident in the adjoining Industrial unit. That includes:
9.5 ALARM SYSTEM DURING DISASTER
For meeting any emergency and alerting the workers properly spread
alarm system shall be provided alongwith a control room. On receiving
the message of Disaster from the site, the control room will sound siren
“wailing type for 5 minutes.” The message shall also be broadcasted
through Public Address System. On receiving the message of emergency
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 106
over, the alarm shall be sounded for 2 minutes. The features of alarm
system shall be explained to all during trainings to avoid any confusion.
CHAPTER-10.0
ENVIRONMENT MONITORING PROGRAMME
Regular monitoring of all significant environmental parameters is essential
to check the compliance status vis-à-vis the environmental laws and
regulation. The objectives of the monitoring will be as follows:
To verify the results of the impact assessment study with respect to the
proposed projects.
To study the trend of concentrated values of the parameters, which have
been identified as critical and then planning the mitigating measures.
To check and assess the efficacy of pollution control equipment.
To ensure that any additional parameters, other than those identified in
the impact, do not turn critical after the commissioning of proposed
project.
To implement the EMP, a structured Environment Management Cell
(EMC) interwoven with the existing management system will be created.
EMC will undertake regular monitoring of the environment and conduct
yearly audit of the environmental performance during the construction of
the project. It will also check that the stipulated measures are being
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 107
satisfactorily implemented and operated. It shall also co-ordinate with local
authorities to see that all environmental measures are well coordinated.
A comprehensive environmental monitoring program that has been
prepared for the purpose of implementation in the proposed unit by the
EMC is described below:
The ambient Air quality shall be monitored at project site and two
upward and downstream locations once every quarter for PM2.5,
PM10, NOx, Pb, SO2, and CO levels during the Construction Phase
and Operational Phase. The Ambient Noise Levels shall also be
monitored once every six months.
The vehicles shall be checked for PUC once every quarter during the
development period and records shall be maintained.
Groundwater quality of the Tube-wells in site area will be regularly
monitored preferably once in a quarter during the development
period.
APCD and Sewage Treatment Plant shall be provided with a small
Laboratory and weekly monitoring of the parameters shall be
undertaken. In addition monitoring shall be got done from an
independent agency as laid down by State Pollution Control Board.
All the above observations will be compiled and documented by the
EMC to serve the following purposes.
Identification of any environmental problems that are occurring in
the area.
Initiating or providing solution to those problems through designed
channels and verification of the implementation status.
Controlling activities inside the project, until the environmental
problem has been corrected.
Suitably responding to emergency situations.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 108
Environment Management Cell:
The Environment Management Cell shall include:
Representative of Management (Head of Environment Cell)
Process Incharge from STP/APCD, Water Works
Incharge Maintenance Department
A representative of Environmental Consultants
CHAPTER-11.0
RAIN WATER HARVESTING
11.1 Introduction
Rain Water Harvesting is collecting and using precipitation from a
catchments surface. The rainwater collected can be stored for direct use or
can be recharged into the groundwater. Rain Water Harvesting is thus
becoming essential as it helps to meet our demand for the water either
directly as rain water is stored and put to different uses or indirectly via
replenishing the ground water.
Thus, there are two main techniques of Rain Water Harvesting (RWH)
depending on the end use.
- Storage of rain water on surface for direct use
- Recharge to ground water
For RWH, the rainwater that falls on a catchment is carried through
pipelines or drains for storage or recharge. The catchment can be a paved
area like a roof, terrace or courtyard of a building, or an unpaved area like a
lawn or open ground.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 109
11.2 METHODOLOGY
The decision whether to store or recharge the harvested water depends on:
- Hydro-meteorological characters viz. Rainfall duration, general
pattern and intensity of rainfall.
- Hydro-geology of the area including nature and extent of aquifer,
soil cover, topography, depth to water levels and chemical quality
of ground water.
In areas where rain falls throughout the year, barring a few dry periods, one
can make use of small size storage tanks for storing rainwater, since the
period between two spells of rain is short. On the other hand in areas where
the majority of the rainfall occurs during 3 to 4 months of monsoon, the
storage will require large size storage tanks and therefore it may be better to
use rainwater to recharge. However, a combination of two systems may
have to be adopted where hydro-geology of the area makes recharging
uneconomical due to depth to aquifers, nature of strata etc. Both the
approaches are discussed below:
11.2.1 Storage of Rainwater for Direct Use
Rainwater can be stored in an underground RCC/masonry tank. Pre-
fabricated tanks such as PVC can be installed above the ground. Each tank
must have an overflow system for situations when excess water enters the
tank. The overflow can be connected to the drainage system.
In general, runoff from only paved surfaces is used for storing since it will
be relatively less contaminated. Drainpipes that collect water from the
rooftop are diverted to the storage container. Rainwater collected from
rooftops is free of mineral pollutants like fluoride and calcium salts which
may be found in groundwater. But it is likely to be contaminated with
pollutants in air and on surface.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 110
To prevent leaves and debris from entering the system, mesh filters should
be provided at the mouth of the drainpipe.
A first-flush device should be provided in the conduit before it is connected
to the storage container. This is to drain-off the first spell of runoff the
season, which may be more laden with dust and impurities.
A sedimentation tank can also be provided before the main storage tank to
collect dust and impurities as settlement. This is particularly useful in case
of underground storage water tanks.
It is preferable to use the stored water for purposes like gardening, flushing,
bathing, augmenting storage for fire-fighting etc. If it is to be used for
drinking purposes it should be used after boiling or disinfecting with
chlorine tablets of after filtration.
11.2.2 Artificial Recharge to Ground Water
Artificial recharge techniques are adopted where:
- Adequate space for surface storage is not available especially in
urban areas.
- Water level is deep enough (>8m.) and adequate subsurface storage
is available.
- Permeable strata are available at shallow/moderate depth.
- Where adequate quantity of surface water is available for recharge to
ground water.
- Ground water quality is bad and the aim is to improve it.
- Where there is possibility of intrusion of saline water especially in
coastal areas.
- Where the evaporation rate is very high from surface water bodies.
11.2.3 Methods of Ground Water Recharge
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 111
(i) Recharge Pits
Recharge pits are constructed for recharging the shallow aquifers. These are
constructed 1 to 2 m. wide and 2 to 3 m. deep which are back filled with
boulders, gravels & coarse sand. The size of filter material is generally
taken as below:
Coarse sand: 1.5 – 4 mm
Gravels: 5 – 10 mm
Boulders: 5 – 20 cm
The filter material should be filled in graded form. Boulders at the bottom,
gravels in between & coarse sand at the top so that the silt content that will
come with runoff will be deposited on the top of the coarse sand layer and
can easily be removed. If clay layer encountered at shallow depth, it should
be punctured with auger hole and that auger hole should be refilled with
fine gravel of 3 to 6 mm size.
(ii) Recharge Trenches
These are constructed when the permeable strata is available at shallow
depths. Trenches may be 0.5 to 1 m. wide, 1 to 1.5 m. deep and 10 to 20 m.
long depending upon availability of water. These are back filled with filter
materials. In case of clay layer encountered at shallow depth, the number of
auger holes may be constructed & back filled with fine gravels.
(iii) Abandoned Dug wells
Existing abandoned dug wells may be utilized as recharge structure after
cleaning and de-silting the same. For removing the silt contents, the runoff
water should pass either through a de-silting chamber or filter chamber.
(iv) Hand Pumps / Tube-wells
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 112
The existing abandoned hand pumps may be used for recharging the
shallow/deep aquifers, if the availability of water is limited. Water should
pass through filter media before diverting it into hand pumps.
Abandoned tube-well may be used for recharging the shallow/deep
aquifers. These tube-wells should be redeveloped before use as recharge
structure. Water should pass through filter media before diverting it into
recharge tube well.
(v) Recharge Wells
Recharge wells of 100 to 300 mm. Diameter are generally constructed for
recharging the deeper aquifers and roof top rain water is diverted to
recharge well for recharge to ground water. The runoff water may be passed
through filter media to avoid choking of recharge wells.
(vi) Recharge Shafts
For recharging the shallow aquifers, which are located below clayey surface
at a depth of about 10 to 15 m, recharge shafts of 0.5 to 3 m. diameter and
10 to 15 m. deep are constructed depending upon availability of runoff.
These are back filed with boulders, gravels & coarse sand. For lesser
diameter shafts, the reverse/direct rotary rigs are used and larger diameter
shafts may be dug manually. In upper portion of 1 or 2m depth, the brick
masonry work is carried out for the stability of the structure.
(vii) Lateral Shafts with Bore Wells
If the aquifer is available at greater depth say 20 or 30 m, a shallow shaft of
2 to 5 m diameter and 5 to 6 m deep may be constructed depending upon
availability of runoff. Inside the shaft, a recharge well of 100 to 300 mm
diameter is constructed for recharging the available water to deeper aquifer.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 113
At the bottom of the shaft a filter media is provided to avoid choking of the
recharge well.
For recharging the upper as well as deeper aquifers, lateral trench of 1.5 to
3 m. wide & 10 to 30 m. long depending upon availability of water with
one or more bore wells may be constructed. The lateral trench is back filled
with boulders, gravels & coarse sand
(viii) Open Spreading
When permeable strata starts from top then open spreading is used. Water
is spread in streams/nalah by making check dams, nalah bunds, cement
plugs, gabion structures or percolation ponds.
11.3 General Arrangements Proposed
In the present case since the land available in the colony is limited and large
tanks cannot be constructed it is proposed to recharge the ground water
through deep bores.
11.4 Recharge Potential
The recharge is proposed to be done from the roof top of the building only.
The recharge potential thus available is as below:-
However, affords will be made to store this water for use in plantation
during non rainy days.
Area of the catchment (Roof Top) A = 3150.9 m2
Average annual rainfall R = 0.978 m.
Runoff coefficient C = 0.8
About 80% of rainfall that falls on the roof (Roofs with tiles) is available
for use.
Annual Roof Top Rain Water Harvesting Potential = A x R X C
= 2465 m3
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 114
CHAPTER-12.0
RISK ASSESMENT, ITS MITIGATION & DISASTER
MANAGEMENT PLAN
12.1 GENERAL
All projects, whether industrial or otherwise, do have some pitfalls. The
gravity of such happenings depends on manufacturing process, quality of
the materials used, man power utilized and general working environment.
While small Industrial projects employ comparatively less number of
employees some big projects deal with large number of persons. In both
cases adequate measures have to be taken to reduce possible accidents and
save human life. Keeping these factors in mind Risk Assessment and
Disaster Management Plan for this project has been prepared.
12.2 RISK ASSESSMENT
Risk can be defined as possibility of harm, which can occur during the life
time of a project and its anticipated severity. In absolute terms, 100% risk
free projects, cannot be achieved. Thus, the safety of a Plant is considered
in terms of acceptability of the risk created. “Safety at any cost” is ideal
and desirable but sometimes the cost involved in such a situation is
prohibitive. Thus a crucial decision has to be taken on “safety-at-what-
cost”. The need for safety provisions are felt only when the mishaps occur.
It is rare that all the problems are anticipated and an answer is sought
before a disaster occurs. The risk evaluation is, therefore, done within the
prescribed limits fixed for a Unit to be safe enough. But when the risks in a
process are greater than the acceptable limiting risk the project is termed as
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 115
a `dangerous’ and appropriate measures have to be adopted to bring the risk
within limits for the safety of the project.
Normally almost all Plants handle some materials and processes which are
hazardous/ toxic in the Industry. All precautions have therefore, to be taken
to handle such materials as per HWM Rules. The processes and layout of
the machinery have to be regulated as per the norms fixed to minimize the
risks involved.
Broadly, following types of possible risk/ hazards are encountered in the
Industrial Units and their safeguards are suggested as under:-
(i) Physical Hazards like heat, humidity, light & noise etc.
(ii) Electrical Hazards like unsafe equipments, unsafe work practices, unsafe
environment.
(iii ) Mechanical Hazards like machinery having moving parts and unguarded.
(iv) Lightening like strokes during rainy season causing damage to buildings.
(v) Fire Emanating from different sources and due to different causes.
These are discussed as under:-
(i) Physical Hazards:
(a) Heat: Heat is the most common hazards in the Industries especially
where furnaces and boilers are used. Its continuous exposure causes heat,
exhortion, heat strokes and heat cramps. Thus, for safety of the workers,
reasonable temperature which is normally acceptable in working area
should be maintained which is about 70° F to 80° F and could be achieved
by proper ventilation.
(b) Light: Inadequate light or extreme glares are also big hazards in an
Industry as they cause eye strain and headache etc. Thus, proper lighting
with adequate distribution and steadiness has to be maintained to reduce the
risk factor.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 116
(c) Noise: Noise is a big stress factor and annoyance to the workers. It can
lead to accidents, if the worker is not relieved of the stress by having
different measures to reduce noise in the area like mufflers, acoustics in the
room and providing ear-plugs and muffs to the employees.
(ii) Electrical Hazards :
Most electrical accidents occur from one of the following factors:
a) Unsafe equipment
b) Unsafe environment
c) Unsafe work practices
Electrical accidents could, therefore be prevented through use of:
Proper Insulation
Guarding
Earthing
Electrical protective devices
Safe work practices
Insulators
Insulators such as glass, mica, rubber, or plastic used to coat metals and
other conductors help stop or reduce the flow of electrical current. This
helps prevent shock, fires, and short circuits. Before connecting electrical
equipment to a power source, it's a good idea to check the insulation for any
exposed wires for possible defects. Insulation covering flexible cords such
as extension cords is particularly vulnerable to damage. No live wires shall
be allowed to hang at any place, where persons can normally go.
Guarding
Guarding involves locating or enclosing electrical equipment to make sure
that people don’t accidently come into contact with its live parts. This
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 117
should be done for equipments with exposed parts operating at 50 volts or
more especially where it is accessible to authorized people, qualified to
work with it. The recommended locations are room, vault or similar
enclosure, a balcony, a gallery or elevated platform. Sturdy permanent
screens also can serve as effective guards. Conspicuous signs shall be
displayed at the entrances to electrical rooms and similar guarded locations
to alert people to the electrical hazards and to forbid entry of unauthorized
persons. These signs may contain the word “Danger”, “Warning” or
“Caution” and beneath that appropriate concise wording that alerts people
to the hazard or gives an instruction such as, “ Danger / High Voltage /
Keep Out” should be given.
Earthing
Earthing a tool or an electrical system means intentionally creating a low
resistance path that connects to the earth. This prevents the build up of
voltages that could cause an electrical accident. Earthing helps to protect
the operator as it provides an alternative path for the current to pass through
from the tool or machine to the ground and does not affect the operator.
Safe Work Practices :
Electrical accidents are largely preventable by adopting safe work practices
such as:
Checking Insulation of the equipment before installation
Properly earthing the equipment
De-energizing electrical equipments before inspection or repair
Keeping electrical tools properly maintained.
Using appropriate protective equipment such as:
a) Rubber insulating gloves
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 118
b) Hoods
c) Sleeves
d) Matting
e) Line Hose
f) Protective Helmets
g) Protective Eye Glasses
(iii) Mechanical Hazards:
Mechanical Hazards like protruding and moving parts of machinery are big
Hazards/ risk factors in almost all Units. Proper fancing should be provided
in such areas and sufficient space for proper movement should be avoided
to avoid any accident.
(iv) Lightening
Tall buildings are prone to lightening strikes especially during rainy
seasons which can not only damage the building but can result in fatal
accidents for workers. It is, therefore, necessary that in order to avoid
lightening strikes, causing any damage, lightening arresters should be
provided with proper earthing as per the electricity rules in all the buildings
individually.
(v) Fire
In spite of all precautions taken, fires do break out in factories where
furnace, electrical heaters and other equipments are used extensively. To
meet such exigencies, adequate fire extinguishers shall be provided at
suitable places with suitable hydrants. Underground tanks shall be provided
and kept always full with water so that during emergency the same could be
utilized. These tanks should be accessible by road for the fire tenders.
Supervisory staff should be fully aware and given adequate training for
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 119
meeting such exigencies. First aid shall be available near by for affected
persons.
12.3 DISASTER MANAGEMENT PLAN
Despite of all efforts made accidents do occur which need immediate
attention. The risks involved in this project have been identified and their
mitigation measures have been delineated in earlier paras. But when serious
accidents occur & negligence could result in loss of life the whole thing
has to be handled in a systematic well planned manner Accordingly
following plan of disaster management has been evolved:-
12.3.1 Major Activities
Broadly Disaster Management Plan covers the following activities:
Pre - Emergency Preparedness
Emergency actions
Post Emergency activities
These activities are aimed at facing any emergency so that at the required
time there is no chaos and everything is handled in a very effective manner.
a. Pre-emergency Preparedness:
The activities falling in this category are carried out in a normal situation
without any reference to any particular accident / hazard. They are of a
precautionary nature. These normally include:
i) Internal safety
ii) Non-destructive testing
iii) Fire fighting system testing
iv) Mock drills
v) Training
vi) Productive equipment
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 120
vii) Communication
viii) Emergency lights
ix) Emergency control Room
x) Assembly points
xi) Liaison with state authorities
xii) Hospital activities
xiii) Outside shelters
b. Emergency Time Activity:
During emergency the staff at various levels is expected to work in
coordinated manner with pre-assigned duties to meet the emergency
situation and bring normalcy with the help of the resources available within
and outside the premises. Availability and correct use of different means of
communication and control is very important during emergency time.
Duties of the various persons shall be defined properly.
c. Post Emergency Procedures:
After the emergency is over investigations are required to be made to
establish the reasons for emergency and preventative measures needed for
future happenings. These activities include:
i) Collection of records
ii) Conducting enquiries
iii) Making insurance claims, if any,
iv) Preparation of enquiry report and suggestion
v) Implementation of enquiry report and recommendations.
vi) Rehabilitation of affected persons.
12.3.2 Emergency Plan
This includes following actions:-
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 121
i) Site Layout:
Site plan of the Plant will be kept at a conveniently approachable place.
The plan will show the storage site of the various materials alongwith the
details of the surrounding areas. This gives a layout of the Buildings and
other facilities like roads, open and work areas etc.
i) Emergency Control Centre:
The Control Centre will be established within the premises which will be
marked on the site plan. It will be the focal point from where all operations
to handle the emergency will be directed and coordinated. It will have
internal and external telephone communications alongwith list of essential
telephone numbers and list of key persons and their addresses.
ii) Assembly Point:
Assembly area will be earmarked for the people to get together in case of
emergency which will be away from material storage. A list of all the
employees/ residents will be available at this site so that their roll call could
be taken and missing person, if any, could be located.
iii) Emergency Alarm System:
An audible emergency alarm system will be installed in the premises. It
will be operated from at least 4 different points spread over the entire area
and clearly marked as “Emergency Area Switch”. The system will be tested
regularly. The alarm will signify to the persons & staff that the emergency
has occurred and emergency services should be put in operation. The
Public Address System will also be activated and specific instructions for
eventualities will be passed on to the staff working in the colony.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 122
iv) Service & Control:
a) Emergency Services
This includes Fire fighting, First Aid and rescue teams. Alternative source
of power supply for operating fire pumps and communication with local
bodies and fire brigade etc shall be given.
b) Control Centre:
The control centre could be either in Security room or Fire Station and shall
have:
i) Adequate No. of Internal and external telephones.
ii) Layout Plan of the colony buildings showing:
a) Sources of safety equipment.
b) Fire hydrant system and alternate supply source
c) Stock of other fire fighting materials
d) Assembly points & first aid centers.
e) Surrounding habitation within ½ km distance.
iii) Additional work plans which may illustrate during emergency
a) areas affected / endangered
b) deployment of emergency vehicles and personnel
c) Areas where particular problems arise, e.g. fractured
pipe-line.
d) Areas evacuated.
It would be useful if these plans be covered with plastic/glass sheets
on which felt ink markings can be deciphered.
iv) Normal roll of employees.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 123
v) List of key persons and their addresses with telephone
numbers.
vi) Note pads, pencils, etc to record messages received and
instructions to be passed on through runners.
vii) A tape recorder on which the incident and actions, being
taken and progress could be recorded.
viii) Roll call – Roll Call board listing the names of all persons
department wise and shift wise should be placed in the
allocated places called assembly points. All personnel
including visitors and contractors except those who are
detailed to fight emergency to man such services, shall
proceed to such allocated points as soon as an evacuation is
ordered over PAS or orally by the section in charge and roll
call taken. Section incharge should see that these boards are
always kept up-to-date. The assembly point incharge shall
report to control room immediately any absentee/unaccounted
for persons. He will also keep the group until advised to move
or return to work by the site controller or any other person
pre-nominated by him.
12.3.2 Key Personnel and their Duties
Following persons will be designated for emergency situation.
1. Site Controller
2. Incident Controller
3. Personnel / Administrative Managers
4. Communication Officers
5. Telephone operator
6. Engineer Incharge and Electrician
7. Fire pump attendants
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 124
8. First Aid
Their duties are given as under: -
1. Site Controller:
General Manager or his nominated deputy will retain overall
responsibility for the premises and its personnel. As soon as he is
informed of the emergency, he shall proceed to the control room and
meet the communication officer. His duties shall be:
i) Assess the magnitude of the situation and decide if people
need to be evacuated from their assembly points.
ii) Exercise direct operational control over areas other than those
affected.
iii) Maintain a continuous review of possible development and
assess, in consultation with incident Controller and other key
personnel, as to whether evacuation of persons is required.
iv) Liaise with senior officials of Police, Fire Brigade, Medical
provide advice on possible effects on areas outside the factory
premises.
v) Control rehabilitation of affected areas on discontinuation of
emergency.
vi) Issue authorized statements to news media, and ensures that
evidence is preserved for enquiries to be conducted by
statutory authorities.
2. Incident Controller:
Manager or Officer of similar rank nominated will act as Incident
Controller. On hearing of an emergency he will rush to the incident
point and take overall charge and report to site controller. On arrival
he will assess the scale of emergency and decide if major emergency
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 125
exists or is likely and inform the communication officer accordingly.
His duties will be:
i) Direct all operations within the affected area with the
priorities for safety of personnel minimize damage, property
and environment and minimize loss of materials.
ii) Pending arrival of Site Controller, assume the duties of his
post and in particular:
a) Direct the evacuation of the persons from areas likely
to be adversely affected by the emergency and
b) Ensure that all key personnel and outside help is called
in.
iii) Provide advice and information to the Fire and Security
officer and the local Fire Service as and when they arrive.
iv) Ensure that all non-essential workers / staff of the areas
affected are evacuated to the appropriate assembly points
and the areas are searched for casualties.
v) In the event of failure of electric supply and thereby PAS
and Internal telephones, set up communication point and
establish contact with Emergency Control Centre.
vi) Report on all significant developments to the
communication officer.
vii) Have regard to the need of preservation of evidence so as to
facilitate any enquiry into the causes and circumstances
which caused or escalated the emergency.
3. Personnel / Administrative Manager:
He will also work as Liaison Officer and will be stationed at
the main entrance (Gate House) during the emergency. He
will under the direction of the site controller, handle police,
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 126
press and other enquiries, receive reports from roll-call
leaders from assembly points and pass on the absentee
information to the incident controller. His responsibilities
shall include.
i) To ensure that casualties receive adequate attention / to
arrange additional help, if required, and inform
relatives.
ii) To control traffic movements into the premises and
ensuring that the alternate transport is available when
need arises.
iii) When emergency is prolonged, arrange for the relief of
personnel and organize refreshments / catering facility.
4. Communication Officer:
He will, on hearing the alarm, proceed to Control Centre and
maintain communication with the Incident Controller. He
will:-
i) Advise the Site Controller of the situation,
recommending (if necessary) evacuation of persons
from assembly points.
ii) Recruit suitable staff to act as runners between the
Incident Controller and himself if the telephone and
other system of communication fails due to
whatsoever reasons.
iv) Maintain prior agreed inventory in the control centre.
v) Maintain a log of the incident on tape.
vi) In case of prolonged emergency involving risk to
outside areas by wind-blown materials – contact local
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 127
meteorological office to receive early notification of
changes in weather conditions.
5. Telephone Operator: -
On hearing the emergency alarm, he will immediately contact
site controller and on his advice call the local Fire Brigade or
mutual aid scheme members. In case the PAS, Internal /
external telephone system becomes inoperative he shall
inform the Communication Officer through a messenger /
runner. In case fire is detected and the alarm is not in
operation, he shall receive information about location from
the person who detected the fire and thereafter immediately
consult the Incident Controller and make announcement on
PAS or telephone telling the residents about location of the
incident and to evacuate to their assembly points. He will
continue to operate the switch board advising the callers that
staffs are not available and pass all calls connected with the
incident to the Communication Officer.
6. Engineer In-charge and Electrician: -
They will report to the scene of the incident and close down
the services as requested by the Incident Controller.
7. Fire – pump Attendants: -
Two persons identified will work as fire-pump attendants. On
hearing the fire alarm, they will immediately proceed to pump
house to ensure that pumps are operating and stand by to
maintain them. At the end of emergency they will be relieved
of their duty by the Fire and Security officers.
8. First Aid Teams: -
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 128
The Manager shall keep the roll call lists for the Fire and
First-aid team on duty. Roll call leaders shall check their rolls
as members of the services and report for emergency duty.
Names of any unaccounted for absentees will be informed to
the Fire and Security Officer. Members of the First – aid
teams will report to the Incident Controller on hearing of the
alarm and follow his directions.
9. Factory Fire Brigade Personnel: -
The duty Fire – Brigade personnel under the command of the
Fire and Security Officer shall be responsible for fire fighting
and rescue. On hearing the alarm, they shall proceed to the
place of incident, if known, otherwise to the Fire station. The
men at Fire station shall find out the location of the
emergency, the equipment and proceed to the site of
occurrence. At the site, all the squad members will respond to
the direction given by the Incident Controller.
12.4 TRAINING
The promoters shall ensure that everyone employed on the premises is
made aware of the risks involved and has been given adequate training on
the action to be taken in case of any emergency and that provision has been
made for other people also, for example, visitors and contractors who may
also be on the premises. Such training shall ensure that those people who
are not involved in dealing with the emergency, leave the vicinity of the
Incident and go to a place of safety. So that those people needed to carry
out the emergency plans shall be capable of carrying out their specified
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 129
tasks. They shall be thoroughly trained, given the correct personal
protective & other equipment and be adequately supervised.
Further, it shall be ensured that the plan is thoroughly tested and rehearsed.
It will also be reviewed and revised on a regular basis.
CHAPTER-13.0
OCCUPATIONAL HEATLH
13.1 General:
Occupational Health basically relates to protecting the Industrial Workers
from the ill effects of various parameters at the work place or in other
words, “Occupational Environment”. It is synonymous with `Preventive
Medicine’ as both aim at prevention of diseases & physical discomfort.
This in the long run increases their efficiency and ultimately results in
better production. Thus, both the workers and the industrialists are gainers.
13.2 Occupational Environment:
Occupational Environment includes external conditions and influences
which prevail at the place of work and which have a bearing on the health
of workers. These are of three types i.e.
(a) Man and physical, chemical & biological agents.
(b) Man and Machine
(c) Man & Man.
Details of these factors are as under:-
13.2.1 Man & Physical, Chemical & Biological Agents:
i) Physical Agents: Physical factors which affect the health of the workers
adversely are heat & cold, humidity, air movement, light, noise and
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 130
vibration. These factors act in different ways on the health and efficiency of
the workers, singly or in different combinations.
ii) Chemical Agents: These comprise chemicals, toxic dust and gases
which are potential hazardous to the health of the workers.
iii) Biological Agents: These consist of viral, bacterial and parasictic agents
which may result from close contact with animals or their products,
contaminated water, soil or food.
13.2.2 Man and Machine:
Every industry or factory uses machines driven by power to improve
production. Unguarded machines, protruding & moving parts, lack of safety
measures are the major causes of the accidents in the industries.
13.2.3 Man and Man:
These factors include human relationship among workers themselves on the
one hand and those in authority over them on the other. In case of discord
in either of them, the health of the workers & efficiency suffers and may
result in sleep & mental disorders.
13.3 Occupational Hazards:
Keeping in view the above environmental factors, the workers may be
exposed to following types of hazards depending upon his occupation.
(a) Physical hazards
(b) Chemical hazards
(c) Mechanical hazards
(d) Biological hazards
These are discussed as under:-
(a) Physical hazards:
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 131
(i) Heat: Common physical hazard in most of the industries is heat. The direct
affects of heat exposure are burns, heat exhortations, heat strokes and heat
cramps. The indirect affects are decreased efficiency, increased fatigue etc.
Radiant heat from the ovens & furnaces is the main problem in some of the
industries. Thus for gainful work a reasonable temperature has to be maintained
at each work place. Normally, temperatures between 70° to 80° F are
considered as the Comfort Zone in this country and temperature above 80° F
causes discomfort.
(ii) Light: In some of the industries, the workers are exposed to poor
illumination. This causes eye-strain, headache, eye pain and eye fatigue etc.
Similarly, excessive brightness or glare causes discomfort, annoyance & visual
fatigue. Intense direct glare may also result in blurring of vision and lead to
accidents.
(iii) Noise: Noise is a big health hazards in many industries. Its effects are of
two types:-
(a) Auditory effects – which result in temporary or permanent hear loss.
(b) Non-Auditory effects like nervousness, fatigue, inference with
communication by speech, decreased efficiency and annoyance.
(iv) Vibration: In some heavy industries where pneumatic tools such as drills
and hammers are used, vibration affects the hands & arms. With long exposure
fine blood vessels of the fingers may become increasingly sensitive. Joints of
the hands limbs & shoulders can be affected.
(b) Chemical hazards: In almost all industries chemicals are used at one place
or the other. They affect the health of workers in three ways depending on the
duration and quantum of exposure as under:-
(i) Local Action
(ii) Inhalation
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 132
(ii) Ingestion
(c) Mechanical hazards: Mechanical hazards in the Industries centre round
machinery, protruding and moving parts. With proper planning these can be
taken care of.
(d) Biological hazards: These hazards occur in Units dealing with animals and
animal products like hair, wool, hides etc. These cause fungal infection and
some others also.
13.4 Mitigation Measures:
The main aim of occupational health is the promotion & maintenance of the
highest degree of physical, mental and social well being of workers in all
occupations. Thus, different measures are required to control ill-effects of the
various activities in the industries. Following measures therefore, are required
to be taken in this respect.
13.4.1 Environmental Sanitation:
(i) Water supply: A sufficient supply of whole-some drinking water is one of
the basic requirements in all Industrial Units. Installation of drinking water
fountains or taps should be provided at convenient points.
(ii) Toilets: There should be sufficient number of latrines & urinals, separate
for males & females, preferably at the rate of 1 Toilet for 20 workers.
(iii) Sufficient space: Sufficient floor space & cubic space should be provided
to prevent not only the respiratory infections but to ensure a comfortable
working environment. A provision of 500 cft. of space per worker is considered
comfortable.
13.4.2 Physical Agents:
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 133
(i) Heat: Ill-effects of high temperature can be prevented by observing
following precautions:-
(a) Replacement of water: Persons working under condition of high
temperature and humidity should drink cold water frequently, preferably one
litre per hour.
(b) Regularization of work: The duration of exposure to hot environment
should be cut-down. Persons should be rotated on such duties.
(c) Clothing: Clothing should be light, loose and of light colour.
(d) Protective Devices: Protective goggles, shields and helmets should be
encouraged.
(e) Work Environment: Temperature and humidity in working environment
may be controlled by proper ventilation & air-conditioning.
(ii) Humidity: Although humidity does not directly affect the workers physical
health it causes discomfort as the comfortable value ranges from 30% to 65%.
Anything above or below these limits is unpleasing. Humidity can be controlled
through proper ventilation in the work place. 4 to 6 air changes per hour are
considered appropriate to make it a comfort zone.
(iii) Light:
(a) Sufficiency: Good light is essential for efficient functioning. Poor lighting
causes strain which leads to eye fatigue & loss of efficiency. Illumination of 15
to 20 foot candles is an accepted basic norm.
(b) Distribution: Distribution of light should be uniform having the same
intensity over the whole area of work, otherwise it will strain the eyes and
affect visual acuity.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 134
(c) Absence of glare: Glare has an excessive contrast. Direct glare from a
light source should be avoided & camouflaged, otherwise it causes annoyance.
(d) Steadiness: The source of light should be constant and not flickering.
(e) Colour of light: Since day light has a soothing affect on the eye, artificial
light, as far as possibly, be approximately of day light.
(iv) Noise: Noise is defined as unwanted sound or more precisely as “wrong
sound, in wrong place, at the wrong time”. It has now become a very
important stress factor in the environment of man. Acceptable norms in
industries may be 40 to 60 dBA. Annoyance can be controlled as under:-
- By segregating the noisy machines, application of Mufflers or other noise
reducers to machines.
- Transmission of noise can be controlled by applying enclosures and
covering the room walls with sound absorbing materials.
- Protection of workers can be achieved by providing ear plugs & air muffs.
Employees should be regularly rotated from noisy areas to comparatively
calm areas in the Factories.
13.4.3 Chemical Hazards: Chemical agents act in 3 ways as under:-
(i) Local action: Some chemicals which come directly in contact with skin
cause, irritation and other problems. Hand gloves can be used where there is
possibility of the chemicals coming in contact with hands.
(ii) Inhalation: Dust, Gases & Metals and their compounds are the biggest
health hazards in the industry. They are absorbed in the body through
inhalation. Although, dust particles larger than 10 Microns settle down in
the air immediately but smaller ones, less than 5 Microns, are inhaled &
directly go into lungs. This is called respirable dust. To avoid their effect
face masks should be provided to the workers at vulnerable places.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 135
(iii) Ingestion: Some chemical substances like Lead, Mercury, Arsenic and Zink
etc. may be swallowed in minute amounts through contaminated hands,
food and cigarettes. Although these are mostly excreted, but a small portion
may reach the blood stream. Use of hand gloves in such areas should be
used extensively.
13.4.4 Mechanical Hazards:
These are related to the machinery and other equipment having moving
parts. Following precautions will be necessary for such hazards.
(i) Proper guards should be provided around of moving parts, so that
accidental toching by the workers is avoided.
(ii) Sufficient space should be available around the machines for the workers to
move freely. All machines should be properly earthed to avoid any
electrical shocks.
(iii) Safety Boots & Belts should be provided to workers where necessary to
save damage due to accidents.
13.4.5 Biological Hazards:
These hazards occur mostly in industries dealing with the animals and
animal products like hair, wool and hides etc. Hand gloves, face masks, and
gum boots can be provided to all the workers to save them from the infective
and parasitic agents.
13.5 Safety Precautions & Suggestions:-
To protect the health of the workers in an Industry, following measures shall
be taken:-
i) Proper housing shall be provided to workers in large Units for comfortable
& stress free living.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 136
ii) Personal Protection Equipment (PPE) shall be provided to workers, such as
Earplugs, Gloves, Eye Goggles, Helmets, Gum/ Safety Boots & Safety
Belts etc.
iii) Clean & cool drinking water shall be available to workers near work places
especially near hot spots.
iv) Proper ventilation shall be provided in work place, especially where heat is
generated.
v) Employees working near furnaces & other hot areas shall be rotated to
minimize exposure time.
vi) Accoustics shall be provided in rooms where noise creating machines work.
vii) All moving & protruding parts of machinery shall be guarded, so those
workers do not come in contact with them.
viii) Proper lighting shall be provided in the work place. Glares will be avoided.
ix) Exhaust fans & canopy hoods shall be provided in the areas where dust &
other gases are expected from the operations.
x) First Aid Box shall be kept at prominent place to be used in emergent
cases.
xi) All fire fighting equipment shall be frequently checked to see that they are
effective always.
xii) Frequent health check-up of the workers shall be done on regular basis and
the results documented. Timely medical treatment shall be provided to
affected person, if any.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 137
CHAPTER-14.0
EXPENDITURE ON ENVIRONMENTAL MEASURES
Cost of environment protection measures
S.No Title Capital Cost
Rs. Lacs
Recurring Cost
Rs. Lacs
(Annum)
1. Air Pollution Control 15.0 1.5
2. Noise Pollution Control
(Including cost of
Landscaping, Green Belt)
5.0 0.5
3. Environment Monitoring
and Management (Including
Establishment of
Laboratory)
1.0 --
4. RWH 1.0 0.5
5. Miscellaneous
(Appointment of
Consultants, Management of
Environment Cell, Consent
fees and monitoring)
0.5 --
Total 22.5 2.5
Note: - Rs. 13.0 lacs shall be spent on CSR annually for the benefit of the
society specially the weaker section.
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 138
CHAPTER-15.0
CORPORATE SOCIAL RESPONSIBILITY
For CSR a corpus of about 5% of the project cost i.e. Rs. 2.56 crore shall be
created and following activities shall be taken up within three years after
expansion.
(5% of 2.56 crore = 12.8 Lacs ≈ Rs. 13 Lacs)
DETAIL OF CSR AND ITS TIME BOUND IMPLEMENTATION
S.No. Name of the Village Welfare action Plan Estimated
Cost (Rs
Lacs)
1. Patti Natha Singh, Barotiwala,
Rampur
Environmental education cum
awareness campaign through
audio/video in each of these
villages and High schools of these
villages once a year.
1.5 lacs
2. Akalgarh, Haripur, Tohana,
Shivpur
Health check up camps including
vision, audiometry, spirometry,
respiratory disorders and free
medicines whenever required
once a year.
2.5 lacs
3. Patti Natha Singh, Haripur,
Tohana, Mohkampur
Purified drinking water and
separate toilets in the schools and
their upkeep.
2.0 lacs
4. Akalgarh, Haripur, Tohana,
Shivpur, Mohkampur
Distribute uniforms, books &
bags to students in the school
especially from weaker section.
2.5 lacs
5. Patti Natha Singh, Haripur,
Tohana, Mohkampur
Providing community centre with
all facilities for marriage and
other functions.
3.0 lacs
6. Patti Natha Singh, Haripur,
Tohana, Mohkampur
Cleaning and improvement of
village ponds, construction of
metal road from kacha road
1.5 lacs
Total
13.0 lacs
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 139
ANNEXURES
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 140
ANNEXURE – I
PROCEEDING OF PUBLIC HEARING
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 141
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 142
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 143
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 144
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 145
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 146
ANNEXURE-II
SITE PHOTOGRAPHS
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 147
SITE PHOTOGRAPHS
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 148
ANNEXURE-III
Renewal of Consent
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 149
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 150
ANNEXURE-IV
Total Consumption (10 KLD) = 2 KLD + 3 KLD + 5 KLD
Total Water Requirement
Water Balance (KLD)
Domestic Water 2
Septic tank 1.5
On land for plantation
1.5
Consumption 0.5
Cooling 70
Process 5
Consumed
Evaporation
3
Nil Recycled
67
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 151
ANNEXURE-V
SAMPLE CALCULATIONS FOR CARBON FOOTPRINTS M/s Ambassador Cements Ltd. – Village- Patti Natha Singh, Sirmour (H.P)
I BASIC DATA
Plot Area = 5490 m2
Ground Covered Area = 2716 m2
Open area = 2774 m2
Industrial shed = 1
Connected Load = 1200 kW
No. of Workers = 50
Fuel Used:
Diesel oil = 3000 litre / month
Electricity Consumed = 518400 units / month
Coal used at Kiln = 450 tons/ month
Petrol = 150 lit/ month
II ASSUMPTIONS
Since Patti Natha Singh is a small village and distances are small it is expected
that 6% workers will be using cars 10% workers will be using two-wheelers and
the remaining 84% will come on foot.
Distance traveled by each scooter is likely to be 400 km on an average per month.
100 sq mt of the roof top painted white will offset 10 tons of CO2 emissions per
year.
50 trees absorb 1 ton of CO2 per year.
.
III NO. OF EMPLOYEES = 50
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 152
IV FUEL CONSUMPTION PER MONTH
1. Vehicles for 50 Employees
i) No. of Scooters = 10% = 5
ii) No. of Cars = 6% =3
iii) On foot = 84% = 42
2. Anticipated Distance traveled by each transport per month: -
i) By Scooter = 5 X 400 = 2000 KM
ii) By Cars = 3 X 400 = 1200 KM
3. Petrol Consumption for the above systems / month:
i) Petrol for 2000 km by scooter @ 40 km / L = 50 lit
ii) Petrol for 2000 km by car @ 12 km / L = 100 lit
= 150 lit (Total)
4. Fuel Oil Consumption per month:
i) Diesel for generators during Electricity break = 3000 lit
downs of about 2 hours daily @ 50 L / hr
5. Coal Consumption per month:
i) Coal used at Kiln = 450 tons
V ELECTRICITY CONSUMPTION PER MONTH
i) Connected Load = 1200kW
ii) Anticipated Consumption = 518400 kWh
VI CO2 EFFECT GENERATION PER MONTH
Item Qty. Rate CF
i) Petrol 150 l X 9.58 X 0.24 = 344.88 kg
ii) Diesel 3000 l X 10.52 X 0.25 = 7890 kg
iii) Elect. 518400 U X 1.0 X 0.52 = 269568 kg
iv) Coal 450000 kg x 7.583 x 0.32 = 1091952 kg
Total = 1369754.88 kg
Or Say =1369.8 T/ month
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 153
Annual Generation =1369.8 X 12 =16438 ton
VII REDUCTION OF CO2 EFFECT BY MITIGATION MEASURES
i) Painting 2716 m2 of roof top and pavement white = 271.6 ton
@ 10 ton / 100 m2
ii) Planting 200 trees @ I ton / 50 trees = 4 ton
iii) Saving Electricity by use of solar energy and CFL = 16 ton
@ 5.8%
TOTAL 291.6 ton
Or Say = 292 ton
Net Carbon Effect = 16438 – 292 = 16146 ton
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 154
ANNEXURE-VI
GLC GRAPH WITH INPUT AND OUTPUT FILE
09/06/13
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 155
17:48:27
*** SCREEN3 MODEL RUN ***
*** VERSION DATED 96043 ***
Tutorial - Point Source in Complex Terrain
SIMPLE TERRAIN INPUTS:
SOURCE TYPE = POINT
EMISSION RATE (G/S) = 0.170000
STACK HEIGHT (M) = 30.0000
STK INSIDE DIAM (M) = 0.7000
STK EXIT VELOCITY (M/S) = 9.0000
STK GAS EXIT TEMP (K) = 383.0000
AMBIENT AIR TEMP (K) = 313.0000
RECEPTOR HEIGHT (M) = 0.0000
URBAN/RURAL OPTION = RURAL
BUILDING HEIGHT (M) = 0.0000
MIN HORIZ BLDG DIM (M) = 0.0000
MAX HORIZ BLDG DIM (M) = 0.0000
THE REGULATORY (DEFAULT) MIXING HEIGHT OPTION WAS SELECTED.
THE REGULATORY (DEFAULT) ANEMOMETER HEIGHT OF 10.0 METERS WAS
ENTERED.
BUOY. FLUX = 1.976 M**4/S**3; MOM. FLUX = 8.109 M**4/S**2.
*** STABILITY CLASS 6 ONLY ***
*** ANEMOMETER HEIGHT WIND SPEED OF 3.33 M/S ONLY ***
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 156
**********************************
*** SCREEN AUTOMATED DISTANCES ***
**********************************
*** TERRAIN HEIGHT OF 10. M ABOVE STACK BASE USED FOR FOLLOWING
DISTANCES ***
DIST CONC U10M USTK MIX HT PLUME SIGMA SIGMA
(M) (UG/M**3) STAB (M/S) (M/S) (M) HT (M) Y (M) Z (M) DWASH
------- ---------- ---- ----- ----- ------ ------ ------ ------ -----
100. 0.000 6 3.3 6.1 10000.0 37.29 4.55 3.09 NO
200. 0.1493E-08 6 3.3 6.1 10000.0 37.29 8.37 5.21 NO
300. 0.8211E-04 6 3.3 6.1 10000.0 37.29 12.00 7.03 NO
400. 0.5665E-02 6 3.3 6.1 10000.0 37.29 15.45 8.61 NO
500. 0.3237E-01 6 3.3 6.1 10000.0 37.29 18.64 9.75 NO
600. 0.1050 6 3.3 6.1 10000.0 37.29 21.81 10.88 NO
700. 0.2370 6 3.3 6.1 10000.0 37.29 24.95 12.00 NO
800. 0.3885 6 3.3 6.1 10000.0 37.29 28.07 12.96 NO
900. 0.5592 6 3.3 6.1 10000.0 37.29 31.17 13.89 NO
1000. 0.7342 6 3.3 6.1 10000.0 37.29 34.24 14.80 NO
1100. 0.8833 6 3.3 6.1 10000.0 37.29 37.29 15.62 NO
1200. 1.018 6 3.3 6.1 10000.0 37.29 40.32 16.42 NO
1300. 1.136 6 3.3 6.1 10000.0 37.29 43.33 17.20 NO
1400. 1.236 6 3.3 6.1 10000.0 37.29 46.31 17.96 NO
1500. 1.319 6 3.3 6.1 10000.0 37.29 49.28 18.70 NO
1600. 1.386 6 3.3 6.1 10000.0 37.29 52.23 19.42 NO
1700. 1.439 6 3.3 6.1 10000.0 37.29 55.16 20.13 NO
1800. 1.478 6 3.3 6.1 10000.0 37.29 58.08 20.83 NO
1900. 1.507 6 3.3 6.1 10000.0 37.29 60.98 21.51 NO
2000. 1.526 6 3.3 6.1 10000.0 37.29 63.87 22.19 NO
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 157
2100. 1.527 6 3.3 6.1 10000.0 37.29 66.74 22.76 NO
2200. 1.523 6 3.3 6.1 10000.0 37.29 69.60 23.31 NO
2300. 1.515 6 3.3 6.1 10000.0 37.29 72.45 23.86 NO
2400. 1.503 6 3.3 6.1 10000.0 37.29 75.28 24.39 NO
2500. 1.489 6 3.3 6.1 10000.0 37.29 78.10 24.92 NO
2600. 1.473 6 3.3 6.1 10000.0 37.29 80.92 25.44 NO
2700. 1.456 6 3.3 6.1 10000.0 37.29 83.72 25.95 NO
2800. 1.437 6 3.3 6.1 10000.0 37.29 86.51 26.45 NO
2900. 1.417 6 3.3 6.1 10000.0 37.29 89.29 26.94 NO
3000. 1.396 6 3.3 6.1 10000.0 37.29 92.06 27.43 NO
3500. 1.278 6 3.3 6.1 10000.0 37.29 105.77 29.40 NO
4000. 1.169 6 3.3 6.1 10000.0 37.29 119.27 31.23 NO
4500. 1.071 6 3.3 6.1 10000.0 37.29 132.59 32.95 NO
5000. 0.9850 6 3.3 6.1 10000.0 37.29 145.75 34.56 NO
MAXIMUM 1-HR CONCENTRATION AT OR BEYOND 100. M:
2060. 1.527 6 3.3 6.1 10000.0 37.29 65.56 22.52 NO
DWASH= MEANS NO CALC MADE (CONC = 0.0)
DWASH=NO MEANS NO BUILDING DOWNWASH USED
DWASH=HS MEANS HUBER-SNYDER DOWNWASH USED
DWASH=SS MEANS SCHULMAN-SCIRE DOWNWASH USED
DWASH=NA MEANS DOWNWASH NOT APPLICABLE, X<3*LB
********************************************
* SUMMARY OF TERRAIN HEIGHTS ENTERED FOR *
* SIMPLE ELEVATED TERRAIN PROCEDURE *
********************************************
TERRAIN DISTANCE RANGE (M)
HT (M) MINIMUM MAXIMUM
__________________________________________________________________________ AMBASSADOR CEMENTS LTD., CPTL ENVIROTECH, CHANDIGARH
PAONTA SAHIB, SIRMAUR, H.P. 158
------- -------- --------
10. 100. 5000.
*** INVERSION BREAK-UP FUMIGATION CALC. ***
CONC (UG/M**3) = 0.000
DIST TO MAX (M) = 1350.53
DIST TO MAX IS < 2000. M. CONC SET = 0.0
***************************************
*** SUMMARY OF SCREEN MODEL RESULTS ***
***************************************
CALCULATION MAX CONC DIST TO TERRAIN
PROCEDURE (UG/M**3) MAX (M) HT (M)
-------------- ----------- ------- -------
SIMPLE TERRAIN 1.527 2060. 10.
***************************************************
** REMEMBER TO INCLUDE BACKGROUND CONCENTRATIONS **
***************************************************