copy of rdr projected manpower schedule
TRANSCRIPT
-
8/11/2019 Copy of RDR Projected Manpower Schedule
1/14
TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM NATURAL HISTORY
LOCATION : RIZAL PARK, MANILASUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows
- Demolition of Helipad 31-Mar 6-Apr 10
- Demolition of Stairs @ courtyard 31-Mar 6-Apr 10
- Hauling of Debris Wing E&C 17-Mar 24-Mar 10 - Demolition of Suspended Slabs For New Elev. & Stairs Opening - Balance Works Removal of Ceiling Insulations Removal of Remaining Condenser @ Helipad Removal of Panel Boards 17-Mar 18-Mar Transfering of Salvageable Materials for Turnover 17-Mar 21-Mar
Lowering of Waste and other used materials 17-Mar 21-Mar1.2 5th Floor- Demolition of RC Walls @ Wing C 17-Mar 23-Mar
- Demolition of Slabs For New Elev. Shaft & Stairs Opening - Hauling of Debris 17-Mar 23-Mar 50 - Balance Works Removal of Existing Windows and walls for New Hallway Opening 22-Mar 26-Mar Demolition of Stairs Support Beams and Walls 22-Mar 26-Mar
1.3 4th Floor Ceiling Systems - Installation of Goosenecked Drum Connection for Chutes 15-Mar 17-Mar 6 - Demolition of RC Walls @ Wing C 24-Mar 30-Mar - Demolition of Suspended Slab for new Elevator Shaft - Hauling of Dedris 24-Mar 30-Mar 40+10=50
ITEM Finish
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
31-Mar 6-Apr 20
Group forChute
Start
DESCRIPTION
ManpowerDEMOLITION WORKS
17-Mar 18-Mar
-
8/11/2019 Copy of RDR Projected Manpower Schedule
2/14
-
8/11/2019 Copy of RDR Projected Manpower Schedule
3/14
- Demolition of Existing Floors 17-Mar 22-Mar 6 - Demolition of Exisiting Windows For New Door Openings 23-Mar 29-Mar 6+6+12 - Demolition of Exisiting Walls 30-Mar 5-Apr 6+6+12
- Demolition of Exisiting Courtyard Elevator Shaft - Hauling of Waste, Debris and used Materials @ courtyard 6-Apr 12-Apr 30 - Demolition of Exisiting Power House -
total manpower 117 6
-
8/11/2019 Copy of RDR Projected Manpower Schedule
4/14
pon omp et on oScaffolding
Upon Completion ofScaffolding
Awaiting Retrofit Plans
23
3
6Awaiting Retrofit Plans
55
6Awaiting Retrofit Plans
to be transfer to the nextfloor upon completion
Upon Completion ofScaffolding
RemarksGroup
to be transfer to the nextfloor upon completion
2
-
8/11/2019 Copy of RDR Projected Manpower Schedule
5/14
2233
6Awaiting Retrofit Plans
Awaiting Retrofit Plans
Awaiting Retrofit Plans
2233
55
Awaiting Retrofit PlansAwaiting Retrofit Plans
2233
10
-
8/11/2019 Copy of RDR Projected Manpower Schedule
6/14
Awaiting Retrofit Plans
26 149overall total
manpower 149
-
8/11/2019 Copy of RDR Projected Manpower Schedule
7/14
TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM NATURAL HISTORY
LOCATION : RIZAL PARK, MANILASUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows - Demolition of Helipad 10
- Demolition of Stairs @ courtyard 10 - Hauling of Debris Wing E&C 10 - Demolition of Suspended Slabs For New Elev. & Stairs Opening - Balance Works
Removal of Ceiling Insulations Removal of Remaining Condenser @ Helipad Removal of Panel Boards 2 Transfering of Salvageable Materials for Turnover 2 Lowering of Waste and other used materials 3
1.2 5th Floor- Demolition of RC Walls @ Wing C 6
- Demolition of Slabs For New Elev. Shaft & Stairs Opening - Hauling of Debris 50 - Balance Works Removal of Existing Windows and walls for New Hallway Opening 5 5 Demolition of Stairs Support Beams and Walls 5 5
1.3 4th Floor Ceiling Systems - Installation of Goosenecked Drum Connection for Chutes 6 - Demolition of RC Walls @ Wing C 6 - Demolition of Suspended Slab for new Elevator Shaft - Hauling of Dedris 40+ 10 =50 - Balance Works Transfering of Salvageable Materials for Turnover 2 Removal of Existing Grills Along Hallways 2 Removal of Existing Windows and walls for New Hallway Opening 3 Lowering of Waste and other used materials 3
1.4 3rd Floor Ceiling Systems - Installation of Goosenecked Drum Connection for Chutes 6 - Demolition of RC Walls @ Wing C and Hallways 6
- Demolition of Suspended slab @ Wing C
- Demolition of Suspended Slab @ Courtyard Elev Lobby
- Demolition of Suspended Slab For new Elevator Shaft
week 1 mar 17-23
week 2 mar 24-30
week 3 march 31-apr 6
we
20
2
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
DESCRIPTION
ITEM DEMOLITION WORKS
-
8/11/2019 Copy of RDR Projected Manpower Schedule
8/14
- Hauling of Dedris 50 - Balance Works Transfering of Salvageable Materials for Turnover 2 Removal of Existing Grills Along Hallways 2 Removal of Existing Windows and walls for New Hallway Openeing 3
Lowering of Waste and other used materials 31.5 2nd Floor Ceiling Systems
- Removal of Exisiting Floor Finish @ Wing C Terrace 5 - Installation of Gooseneck Drum Connection for Chutes 6 - Removal of Existing Entrance Canopy Npdc Area 5 - Removal Pebble Washout finish @ Main Entrance Stairs Wing A 5 - Floor Stripping 6 - Removal of Existing Kiosk And Counter At Marble Hall 5 - Demolition of RC Walls @ Wing C and Hallways 5 - Demolition of Suspended Slab @ Courtyard Elev Lobby - Demolition of Suspended Slab For new Elevator Shaft - Hauling of Dedris - Balance Works Transfering of Salvageable Materials for Turnover 2
Removal of Existing Grills Along Hallways 2 Removal of Existing Windows and walls for New Hallway Opening 3 Lowering of Waste and other used materials 3 Removal of Existing Windows and walls for New Openings Wing A
1.6 Ground Floor Ceiling Systems - Demolition of Existing Ceiling 6 - Demolition of Existing Floors 6 - Demolition of Exisiting Windows For New Door Openings 6 - Demolition of Exisiting Walls 6 6
- Demolition of Exisiting Courtyard Elevator Shaft ` - Hauling of Waste, Debris and used Materials @ courtyard 10 - Demolition of Exisiting Power House -
total manpower/week 114 98 107
Prepared By: Arch. Erickson C. Dominguez/ Site Architect Noted by: Engr. Angelito G. Lagmay/ Asst Engr. Harrie H. Mactal/Site Engineer
Approved by: Engr. Wilfredo S. Salcedo/Pr
-
8/11/2019 Copy of RDR Projected Manpower Schedule
9/14
TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM NATURAL HISTORY
LOCATION : RIZAL PARK, MANILASUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows - Demolition of Helipad
- Demolition of Stairs @ courtyard - Hauling of Debris Wing (A,B,C,D)
- Demolition of Suspended Slabs For New Elev. & Stairs Opening - Balance Works Removal of Ceiling Insulations Removal of Remaining Condenser @ Helipad Removal of Panel Boards Transfering of Salvageable Materials for Turnover Lowering of Waste and other used materials
1.2 5th Floor- Demolition of RC Walls @ Wing C
- Demolition of Slabs For New Elev. Shaft & Stairs Opening - Hauling of Debris (D:C&B) - Balance Works Removal of Existing Windows and walls for New Hallway Opening Demolition of Stairs Support Beams and Walls
1.3 4th Floor Ceiling Systems - Installation of Goosenecked Drum Connection for Chutes - Demolition of RC Walls @ Wing C - Demolition of Suspended Slab for new Elevator Shaft - Hauling of Debris - Balance Works Transfering of Salvageable Materials for Turnover
Removal of Existing Grills Along Hallways Removal of Existing Windows and walls for New Hallway Opening
Lowering of Waste and other used materials
1.4 3rd Floor Ceiling Systems - Installation of Goosenecked Drum Connection for Chutes - Demolition of RC Walls (B,D,E Hallway)
- Demolition of Suspended slab @ Wing C
- Demolition of Suspended Slab @ Courtyard Elev Lobby
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
DESCRIPTION
ITEM DEMOLITION WORKS
-
8/11/2019 Copy of RDR Projected Manpower Schedule
10/14
- Demolition of Suspended Slab For new Elevator Shaft - Hauling of Dedris - Balance Works Transfering of Salvageable Materials for Turnover Removal of Existing Grills Along Hallways Removal of Existing Windows and walls for New Hallway Openeing
Lowering of Waste and other used materials1.5 2nd Floor Ceiling Systems
- Removal of Exisiting Floor Finish @ Wing C Terrace - Installation of Gooseneck Drum Connection for Chutes - Removal of Existing Entrance Canopy Npdc Area - Removal Pebble Washout finish @ Main Entrance Stairs Wing A - Floor Stripping - Removal of Existing Kiosk And Counter At Marble Hall - Demolition of RC Walls @ Wing C and Hallways - Demolition of Suspended Slab @ Courtyard Elev Lobby
- Demolition of Suspended Slab For new Elevator Shaft - Hauling of Dedris - Balance Works Transfering of Salvageable Materials for Turnover Removal of Existing Grills Along Hallways Removal of Existing Windows and walls for New Hallway Opening Lowering of Waste and other used materials Removal of Existing Windows and walls for New Openings Wing A
1.6 Ground Floor Ceiling Systems - Demolition of Existing Ceiling (E:D:Rm. 124-125) - Demolition of Existing Floors
- Demolition of Exisiting Windows For New Door Openings - Demolition of Exisiting Walls
- Demolition of Exisiting Courtyard Elevator Shaft - Hauling of Waste, Debris and used Materials @ courtyard - Demolition of Exisiting Power House -
total manpower/week
Prepared By: Arch. Erickson C. Dominguez/ Site Architect Engr. Harrie H. Mactal/Site Engineer
-
8/11/2019 Copy of RDR Projected Manpower Schedule
11/14
10 31-Mar 6-Apr
10 31-Mar 6-Apr
10 17-Mar 24-Mar
2 17-Mar 18-Mar2 17-Mar 21-Mar3 17-Mar 21-Mar
6 17-Mar 23-Mar
50 17-Mar 23-Mar
5 5 22-Mar 26-Mar5 5 22-Mar 26-Mar
6 15-Mar 17-Mar6 24-Mar 30-Mar
40+ 10 =50 24-Mar 30-Mar
2 27-Mar 29-Mar
2 27-Mar 29-Mar3 27-Mar 31-Mar3 27-Mar 31-Mar
6 18-Mar 20-Mar6 31-Mar 6-Apr
6-Apr
217-Mar 18-Mar
Finish
2031-Mar
week 1 mar 17-23
week 2 mar 24-30
week 3 march 31-apr 6
week 4 april 7-12
Start
-
8/11/2019 Copy of RDR Projected Manpower Schedule
12/14
50 31-Mar 8-Apr
2 1-Apr 3-Apr2 1-Apr 3-Apr3 1-Apr 5-Apr
3 1-Apr 5-Apr
5 17-Mar 18-Mar6 21-Mar 23-Mar5 19-Mar 21-Mar
5 21-Mar 27-Mar6 21-Mar 27-Mar5 28-Mar 30-Mar
5 31-Mar 6-Apr
50+ 20 =70 9-Apr 12-Apr
2 6-Apr 8-Apr2 6-Apr 8-Apr3 6-Apr 10-Apr3 6-Apr 10-Apr
11-Apr 12-Apr
6 17-Mar 22-Mar6 17-Mar 22-Mar
6 23-Mar 29-Mar6 6 30-Mar 5-Apr
`10 +10 +10 =30 6-Apr 12-Apr
5
114 98 107 100
Noted by: Engr. Angelito G. Lagmay/ Asst. Project Manager
Approved by: Engr. Wilfredo S. Salcedo/Project Manager
-
8/11/2019 Copy of RDR Projected Manpower Schedule
13/14
STATUS
Scaffolding
Upon Completion ofScaffolding
DONE, E-97%
Awaiting Retrofit Plans
DONEDONE
PENDINGAwaiting Retrofit Plans HOLD
ON GOING
HOLDDONE
DONE
Awaiting Retrofit Plans
ON GOING
DONE
ON GOING
DONE
Awaiting Retrofit Plans
Awaiting Retrofit Plans
NOT STARTED100%
NOT STARTED
NOT STARTED
90%
100%
90%
100%
to be transfer to the nextfloor upon completion
% ACCOMPLISHMENT
100%
100%DONE
30%
98%
100%100%
Upon Completion ofScaffolding
to be transfer to the nextfloor upon completion
Remarks
-
8/11/2019 Copy of RDR Projected Manpower Schedule
14/14
Awaiting Retrofit Plans
ON GOINGDONEHOLD
ON GOING
HOLDNOT STARTEDDONEHOLD (STORAGE AREA OF DOT)ON GOINGDONE
Awaiting Retrofit PlansAwaiting Retrofit Plans
ON GOING
ON GOING
ON GOINGNOT STARTED
HOLDON GOING
Awaiting Retrofit Plans
ON GOING
114
20%
90%
50%
100%
100%
90%100%