cooooost

Upload: melike-oezbinek

Post on 05-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 COOOOOST

    1/12

    6.0 APPENDIX

    VAPORIZER PURCHASED COST ESTIMATION

    Specifications; D=1.8 m, L=3 m, P=30 bar

    Purchased cost of vaporizer, Cp, is read from the Figure A.13 [Ref1] as 20000 $. Since P=

    30 bar=29 barg pressure factor FP is read from the Table A.19 as Fp=2.492.5 [Ref1].

    Carbon-steel can be selected as construction material. From Table A.20 bare module

    factor for vaporizer is found as FBM=2.8 [Ref1].

    Then, purchased cost for the vaporizer is calculated:

    based on mid-1996.

    Hence, the purchased cost of the vaporizer is estimated to be 97219 $.

    REACTOR PURCHASED COST ESTIMATION

    For the reactor used in cumene plant of 3 m length and 1 m diameter, volume is 2.36 m3.

    Selecting carbon steel as manufacturing material.

    Ce=CSn where Ce is purchased equipment cost and C is cost constant from [Ref.2] in $.

    2004 Chemical engineering cost index is taken as 457.4 [Ref2]

    Ce= CSn =9300$ (2.36)0.4 =13111 $ based on mid-2004.

    Reactor includes cooler section so cooler economic design is required for all cost analysis

    of reactor. For the cooler used in cumene plant of 18.84 m2 heat transfer area:

    Purchased Cost= (bare cost from figure)* Type factor*Pressure factor

    Bare cost is taken from figure A.1, pressure factor is taken from Table A.19 type factor is taken

    from Table A.2 [Ref1].

  • 7/31/2019 COOOOOST

    2/12

    Purchased Cost=8000*1.0*1.0=27000 based on mid-1996

    Hence, the purchased cost of the reactor is estimated to be 33236 $.

    COOLER-CONDENSER PURCHASED COST ESTIMATION

    For the cooler-condenser used in cumene plant of 367.31 m2 heat transfer area, totally:

    Purchased Cost= (bare cost from figure)* Type factor*Pressure factor

    Bare cost is taken from figure A.1, pressure type factor is taken from Table A.19 [Ref1].

    Purchased Cost=25000*1.0*1.0=25000 based on mid-1996

    Cost index in year A 539Cost in year A= Cost in year B* 25000* 35275

    Cost index in year B 382

    Hence, the purchased cost of the cooler-condenser is estimated to be 35275$.

    FURNACE COST ESTIMATION

    The heat duty of furnace is 41376 kW and area of furnace is 181.7 m 2.

    From Table A12;

    BENZENE DISTILLATION COLUMN

    Assuming the column is a vertical pressure vessel including plates, for the column

  • 7/31/2019 COOOOOST

    3/12

    designed of 2.18 m diameter and 3 m height, working at 1.75 atm, plate cost can be

    estimated as:

    Sieve trays cost is read 580 $ from Figure A.7. Pressure factor (Fq) is selected as 2.33

    respected to number of trays [Ref.1]. Material of construction (FBM) is selected as 1.2.

    Number of trays is 5.

    For the condenser used in cumene plant of 249 kW driver power,

    CP is read as 60000$ from Figure A.12. Fp is read as 1 from Table A.17. Bare module

    factor (FBM) is read as 2.1 from Table A.17 [Ref.1].

    * * 2.1*60000*1 126000BM BM P P

    C F C F $ based on mid-1996

    Cost index in year A 539Cost in year A= Cost in year B* 126000* 177785

    Cost index in year B 382 $

    For the boiler used in cumene plant of 1469 kW driver power,

    CP is read as 100000$ from Figure A.12. Fp is read as 1 from Table A.17. Bare module

    factor (FBM) is read as 2.1 from Table A.17 [Ref.1].

    * * 2.1*100000*1 210000BM BM P PC F C F $ based on mid-1996

    Cost index in year A 539Cost in year A= Cost in year B* 210000* 296309

    Cost index in year B 382 $

    Total HCL tower purchased cost is found as 482560$.

    PROPYLENE TOWER PURCHASED COST ESTIMATION

    Assuming the column is a vertical pressure vessel including plates, for the column

    designed of 0.527 m diameter and 4 m height, working at 1.5 atm, plate cost can be

    estimated as:

    Sieve trays cost is read 270$ from Figure A.7. Pressure factor (Fq) is selected as 2

    respected to number of trays [Ref.1]. Material of construction (FBM) is selected as 1.2.

    Number of trays is 7.

    * * * 1.2*270*2*7 4536BM BM P qC F C F N $

  • 7/31/2019 COOOOOST

    4/12

    Cost index in year A 539Cost in year A= Cost in year B* 4536* 6400

    Cost index in year B 382 $

    Vertical vessel cost is read 8000$ from Figure A.4. Pressure factor (FP) is selected as 1 in

    range of -0.5

  • 7/31/2019 COOOOOST

    5/12

    Vertical vessel cost is read 9000$ from Figure A.4. Pressure factor (FP) is selected as 1 in

    range of -0.5

  • 7/31/2019 COOOOOST

    6/12

    in range of -0.5

  • 7/31/2019 COOOOOST

    7/12

    3

    3

    3

    0.0257

    (24 )

    36000.0257 50 24 *1

    704

    157.7

    mix

    mix

    kmolF

    s

    F MW hV

    kmol kg shs m hV

    kg

    m

    V m

    Select; DT =2

    H T

    V = TT HD 2

    4

    3

    TD2

    V

    3

    2

    10 1 2 10 3 10

    157.72

    4.64

    9.3

    log *log *(log )

    T

    T

    T

    p

    D

    D

    H

    C K K A K A

    Mixer is selected as vertical orientation process vessel.

    Cost index in year A 539Cost in year A= Cost in year B* 293000* 413421$

    Cost index in year B 382

    MIXER II PURCHASED COST ESTIMATION

    1 2 3 1 2

    1 2

    2

    10 10 10

    4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3 & .4 [Re 1] 9.3

    1 0.5 3.7 arg

    *( * * )

    log 4.3919 0.2859*log 9.3 0.1842*(log 9.3)

    69432$

    M T

    P

    BM P P M

    p

    p

    BM

    K K K B B F TableA TableA f A H

    F is selected in range of P b

    C C B B F F

    C

    C

    C

    69432* (2.5 1.72*1*1) 293000$

  • 7/31/2019 COOOOOST

    8/12

    3

    3

    3

    0.0308

    (24 )

    36000.0308 46.7 24 *1

    672

    185

    mix

    mix

    kmolF

    s

    F MW hV

    kmol kg shs m hV

    kg

    m

    V m

    Select; DT =2

    H T

    V = TT HD 2

    4

    3

    TD2

    V

    3

    2

    10 1 2 10 3 10

    1852

    4.9

    9.8

    log *log *(log )

    T

    T

    T

    p

    D

    D

    H

    C K K A K A

    Mixer is selected as vertical orientation process vessel.

    1 2 3 1 2

    1 2

    2

    10 10 10

    4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3& .4 [Re 1] 9.8

    1 0.5 3.7 arg

    *( * * )

    log 4.3919 0.2859*log 9.8 0.1842*(log 9.8)

    71824$

    M T

    P

    BM P P M

    p

    p

    BM

    K K K B B F TableA TableA f A H

    F is selected in range of P b

    C C B B F F

    C

    C

    C

    71824* (2.5 1.72*1*1) 303100$

    Cost index in year A 539Cost in year A= Cost in year B* 303100* 427673$

    Cost index in year B 382

    MIXER III PURCHASED COST ESTIMATION

  • 7/31/2019 COOOOOST

    9/12

    3

    3

    3

    0.026

    (24 )

    36000.026 41 24 *1

    583

    158

    mix

    mix

    kmolF

    s

    F MW hV

    kmol kg shs m hV

    kg

    m

    V m

    Select; DT =2

    H T

    V = TT HD 2

    4

    3

    TD2

    V

    3

    2

    10 1 2 10 3 10

    1852

    4.65

    9.3

    log *log *(log )

    T

    T

    T

    p

    D

    D

    H

    C K K A K A

    Mixer is selected as vertical orientation process vessel.

    1 2 3 1 2

    1 2

    2

    10 10 10

    4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3& .4 [Re 1] 9.3

    1 0.5 3.7 arg

    *( * * )

    log 4.3919 0.2859*log 9.3 0.1842*(log 9.3)

    69432$

    M T

    P

    BM P P M

    p

    p

    BM

    K K K B B F TableA TableA f A H

    F is selected in range of P b

    C C B B F F

    C

    C

    C

    69432* (2.5 1.72*1*1) 293000$

    Cost index in year A 539Cost in year A= Cost in year B* 293000* 413421$

    Cost index in year B 382

    MIXER IV PURCHASED COST ESTIMATION

  • 7/31/2019 COOOOOST

    10/12

    3

    3

    3

    0.02118

    (24 )

    36000.02118 42 24 *1

    522

    147

    mix

    mix

    kmolF

    s

    F MW hV

    kmol kg shs m hV

    kg

    m

    V m

    Select; DT =2

    H T

    V = TT HD 2

    4

    3

    TD2

    V

    3

    2

    10 1 2 10 3 10

    1852

    4.5

    9.0

    log *log *(log )

    T

    T

    T

    p

    D

    D

    H

    C K K A K A

    Mixer is selected as vertical orientation process vessel.

    1 2 3 1 2

    1 2

    2

    10 10 10

    4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3 & .4 [Re 1] 9.0

    1 0.5 3.7 arg

    *( * * )

    log 4.3919 0.2859*log 9.0 0.1842*(log 9.0)

    67990$

    M T

    P

    BM P P M

    p

    p

    BM

    K K K B B F TableA TableA f A H

    F is selected in range of P b

    C C B B F F

    C

    C

    C

    67990* (2.5 1.72*1*1) 286918$

    Cost index in year A 539Cost in year A= Cost in year B* 286918* 404840$

    Cost index in year B 382

    TOTAL CAPITAL INVESTMENT (TCI)

  • 7/31/2019 COOOOOST

    11/12

    Since purchase cost of all of the major equipments are estimated, using values given in

    PPC can be calculated:

    Purchase Cost of Major Equipment Items:

    PCE=3117515$

    Total Physical Plant Cost:

    PPC=PCE*Lang Factor= (3117515)* 4.74 =1.48*107$

    Estimating the working capital as 12% of the fixed capital total investment required can

    be calculated to be:

    TCI=1.48*107$ +0.12*(1.48*107$) =1.66*107$

    OPERATING COSTS

    Operating time is assumed to be 7200 h/year and following the route described above:

    1. RAW MATERIALS:Chloride, propylene, water:

    6

    6

    3

    $ $cost of chlorine 0.18 *0.005063 *3600 *71 *7200 1.677*10

    kg

    $ $cost of propylene 0.47 *0.004599 *3600 *42 *7200 2.353*10

    kg

    $cost of water=0.3*10 *0.012 *36kg

    kmol s kg h

    s h kmol year year

    kmol s kg h

    s h kmol year year

    kmol

    s

    $00 *18 *7200 1680

    s kg h

    h kmol year year

    Total=4.03*106$

    2. MAINTANANCE:Assume to be 6% of fixed capital cost=0.06*1.66*107$ = 0.99*106$/year

    3. OPERATING LABOUR:Assume to be 28000 $/year

    4. LABORATORY COSTS:Assume to be 15% of operating labour cost = 28000 $/year*0.15 = 4.2*103$/year

    5. SUPERVISION:Assume to be 12% of operating labour cost=28000$/year*0.12=3.4*103$/year

    6. PLANT OVERHEADS:Assume to be 40% of operating labour cost=28000$/year*0.4=11.2*103$/year

    7. CAPITAL CHARGES:Assume to be 6% of fixed capital cost=0.06*1.66*107$=0.99*106$/year

  • 7/31/2019 COOOOOST

    12/12

    8. INSURANCE:Assume to be 1% of fixed capital cost=0.01*1.66*107$=1.66*105$/year

    9. LOCAL TAXES:Assume to be 2% of fixed capital cost=0.02*1.66*107$=3.32*105$/year

    10.ROYALTIES:Assume to be 1% of fixed capital cost=0.01*1.66*107$=1.66*105$/year

    Direct Production CostsTotal=6.7*106$/year

    Sales expense

    General overheads %25 of Direct Production Costs=0.25*6.7*106$=1.68*106$

    Research and development

    ANNUAL PRODUCTION COST=6.7*106$+1.68*106$=8.38*106$/year

    Selling price of 32wt% hydrochloric acid = $0.075/kg [Ref.4]

    Selling price of 99.5 wt% pure allyl-chloride = $1.72/kg [Ref.4]

    Waste disposal costs of 2 chloro propene = $0.20/kg [Ref.4]

    Waste disposal costs of di chloro propene = $0.20/kg [Ref.4]

    6 5

    6 5 5

    6 5 5

    $ kg $Selling Pr ice of HCL 0.075 *4.8*10 3.6*10

    kg year year

    $ kg $ kg $Waste disposal cos t 0.075 *1.32*10 0.075 *2.55*10 1.18*10

    kg year kg year year

    $ $ $8.38*10 1.18*10 3.6*10

    year year yeProduction Cost of allyl chloride

    6

    6 6

    7

    6

    $ar0.9

    kg kg9*10

    year

    $Selling Price of allyl chloride 1.7kg

    $ kg $Annual Income 1.7 *9*10 15.3*10

    kg year year

    1.66*10 $RATE OF RETURN 1.1 year

    $15.3*10

    year