cooooost
TRANSCRIPT
-
7/31/2019 COOOOOST
1/12
6.0 APPENDIX
VAPORIZER PURCHASED COST ESTIMATION
Specifications; D=1.8 m, L=3 m, P=30 bar
Purchased cost of vaporizer, Cp, is read from the Figure A.13 [Ref1] as 20000 $. Since P=
30 bar=29 barg pressure factor FP is read from the Table A.19 as Fp=2.492.5 [Ref1].
Carbon-steel can be selected as construction material. From Table A.20 bare module
factor for vaporizer is found as FBM=2.8 [Ref1].
Then, purchased cost for the vaporizer is calculated:
based on mid-1996.
Hence, the purchased cost of the vaporizer is estimated to be 97219 $.
REACTOR PURCHASED COST ESTIMATION
For the reactor used in cumene plant of 3 m length and 1 m diameter, volume is 2.36 m3.
Selecting carbon steel as manufacturing material.
Ce=CSn where Ce is purchased equipment cost and C is cost constant from [Ref.2] in $.
2004 Chemical engineering cost index is taken as 457.4 [Ref2]
Ce= CSn =9300$ (2.36)0.4 =13111 $ based on mid-2004.
Reactor includes cooler section so cooler economic design is required for all cost analysis
of reactor. For the cooler used in cumene plant of 18.84 m2 heat transfer area:
Purchased Cost= (bare cost from figure)* Type factor*Pressure factor
Bare cost is taken from figure A.1, pressure factor is taken from Table A.19 type factor is taken
from Table A.2 [Ref1].
-
7/31/2019 COOOOOST
2/12
Purchased Cost=8000*1.0*1.0=27000 based on mid-1996
Hence, the purchased cost of the reactor is estimated to be 33236 $.
COOLER-CONDENSER PURCHASED COST ESTIMATION
For the cooler-condenser used in cumene plant of 367.31 m2 heat transfer area, totally:
Purchased Cost= (bare cost from figure)* Type factor*Pressure factor
Bare cost is taken from figure A.1, pressure type factor is taken from Table A.19 [Ref1].
Purchased Cost=25000*1.0*1.0=25000 based on mid-1996
Cost index in year A 539Cost in year A= Cost in year B* 25000* 35275
Cost index in year B 382
Hence, the purchased cost of the cooler-condenser is estimated to be 35275$.
FURNACE COST ESTIMATION
The heat duty of furnace is 41376 kW and area of furnace is 181.7 m 2.
From Table A12;
BENZENE DISTILLATION COLUMN
Assuming the column is a vertical pressure vessel including plates, for the column
-
7/31/2019 COOOOOST
3/12
designed of 2.18 m diameter and 3 m height, working at 1.75 atm, plate cost can be
estimated as:
Sieve trays cost is read 580 $ from Figure A.7. Pressure factor (Fq) is selected as 2.33
respected to number of trays [Ref.1]. Material of construction (FBM) is selected as 1.2.
Number of trays is 5.
For the condenser used in cumene plant of 249 kW driver power,
CP is read as 60000$ from Figure A.12. Fp is read as 1 from Table A.17. Bare module
factor (FBM) is read as 2.1 from Table A.17 [Ref.1].
* * 2.1*60000*1 126000BM BM P P
C F C F $ based on mid-1996
Cost index in year A 539Cost in year A= Cost in year B* 126000* 177785
Cost index in year B 382 $
For the boiler used in cumene plant of 1469 kW driver power,
CP is read as 100000$ from Figure A.12. Fp is read as 1 from Table A.17. Bare module
factor (FBM) is read as 2.1 from Table A.17 [Ref.1].
* * 2.1*100000*1 210000BM BM P PC F C F $ based on mid-1996
Cost index in year A 539Cost in year A= Cost in year B* 210000* 296309
Cost index in year B 382 $
Total HCL tower purchased cost is found as 482560$.
PROPYLENE TOWER PURCHASED COST ESTIMATION
Assuming the column is a vertical pressure vessel including plates, for the column
designed of 0.527 m diameter and 4 m height, working at 1.5 atm, plate cost can be
estimated as:
Sieve trays cost is read 270$ from Figure A.7. Pressure factor (Fq) is selected as 2
respected to number of trays [Ref.1]. Material of construction (FBM) is selected as 1.2.
Number of trays is 7.
* * * 1.2*270*2*7 4536BM BM P qC F C F N $
-
7/31/2019 COOOOOST
4/12
Cost index in year A 539Cost in year A= Cost in year B* 4536* 6400
Cost index in year B 382 $
Vertical vessel cost is read 8000$ from Figure A.4. Pressure factor (FP) is selected as 1 in
range of -0.5
-
7/31/2019 COOOOOST
5/12
Vertical vessel cost is read 9000$ from Figure A.4. Pressure factor (FP) is selected as 1 in
range of -0.5
-
7/31/2019 COOOOOST
6/12
in range of -0.5
-
7/31/2019 COOOOOST
7/12
3
3
3
0.0257
(24 )
36000.0257 50 24 *1
704
157.7
mix
mix
kmolF
s
F MW hV
kmol kg shs m hV
kg
m
V m
Select; DT =2
H T
V = TT HD 2
4
3
TD2
V
3
2
10 1 2 10 3 10
157.72
4.64
9.3
log *log *(log )
T
T
T
p
D
D
H
C K K A K A
Mixer is selected as vertical orientation process vessel.
Cost index in year A 539Cost in year A= Cost in year B* 293000* 413421$
Cost index in year B 382
MIXER II PURCHASED COST ESTIMATION
1 2 3 1 2
1 2
2
10 10 10
4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3 & .4 [Re 1] 9.3
1 0.5 3.7 arg
*( * * )
log 4.3919 0.2859*log 9.3 0.1842*(log 9.3)
69432$
M T
P
BM P P M
p
p
BM
K K K B B F TableA TableA f A H
F is selected in range of P b
C C B B F F
C
C
C
69432* (2.5 1.72*1*1) 293000$
-
7/31/2019 COOOOOST
8/12
3
3
3
0.0308
(24 )
36000.0308 46.7 24 *1
672
185
mix
mix
kmolF
s
F MW hV
kmol kg shs m hV
kg
m
V m
Select; DT =2
H T
V = TT HD 2
4
3
TD2
V
3
2
10 1 2 10 3 10
1852
4.9
9.8
log *log *(log )
T
T
T
p
D
D
H
C K K A K A
Mixer is selected as vertical orientation process vessel.
1 2 3 1 2
1 2
2
10 10 10
4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3& .4 [Re 1] 9.8
1 0.5 3.7 arg
*( * * )
log 4.3919 0.2859*log 9.8 0.1842*(log 9.8)
71824$
M T
P
BM P P M
p
p
BM
K K K B B F TableA TableA f A H
F is selected in range of P b
C C B B F F
C
C
C
71824* (2.5 1.72*1*1) 303100$
Cost index in year A 539Cost in year A= Cost in year B* 303100* 427673$
Cost index in year B 382
MIXER III PURCHASED COST ESTIMATION
-
7/31/2019 COOOOOST
9/12
3
3
3
0.026
(24 )
36000.026 41 24 *1
583
158
mix
mix
kmolF
s
F MW hV
kmol kg shs m hV
kg
m
V m
Select; DT =2
H T
V = TT HD 2
4
3
TD2
V
3
2
10 1 2 10 3 10
1852
4.65
9.3
log *log *(log )
T
T
T
p
D
D
H
C K K A K A
Mixer is selected as vertical orientation process vessel.
1 2 3 1 2
1 2
2
10 10 10
4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3& .4 [Re 1] 9.3
1 0.5 3.7 arg
*( * * )
log 4.3919 0.2859*log 9.3 0.1842*(log 9.3)
69432$
M T
P
BM P P M
p
p
BM
K K K B B F TableA TableA f A H
F is selected in range of P b
C C B B F F
C
C
C
69432* (2.5 1.72*1*1) 293000$
Cost index in year A 539Cost in year A= Cost in year B* 293000* 413421$
Cost index in year B 382
MIXER IV PURCHASED COST ESTIMATION
-
7/31/2019 COOOOOST
10/12
3
3
3
0.02118
(24 )
36000.02118 42 24 *1
522
147
mix
mix
kmolF
s
F MW hV
kmol kg shs m hV
kg
m
V m
Select; DT =2
H T
V = TT HD 2
4
3
TD2
V
3
2
10 1 2 10 3 10
1852
4.5
9.0
log *log *(log )
T
T
T
p
D
D
H
C K K A K A
Mixer is selected as vertical orientation process vessel.
1 2 3 1 2
1 2
2
10 10 10
4.3919; 0.2859; 0.1842; 2.5; 1.72; 1; .3 & .4 [Re 1] 9.0
1 0.5 3.7 arg
*( * * )
log 4.3919 0.2859*log 9.0 0.1842*(log 9.0)
67990$
M T
P
BM P P M
p
p
BM
K K K B B F TableA TableA f A H
F is selected in range of P b
C C B B F F
C
C
C
67990* (2.5 1.72*1*1) 286918$
Cost index in year A 539Cost in year A= Cost in year B* 286918* 404840$
Cost index in year B 382
TOTAL CAPITAL INVESTMENT (TCI)
-
7/31/2019 COOOOOST
11/12
Since purchase cost of all of the major equipments are estimated, using values given in
PPC can be calculated:
Purchase Cost of Major Equipment Items:
PCE=3117515$
Total Physical Plant Cost:
PPC=PCE*Lang Factor= (3117515)* 4.74 =1.48*107$
Estimating the working capital as 12% of the fixed capital total investment required can
be calculated to be:
TCI=1.48*107$ +0.12*(1.48*107$) =1.66*107$
OPERATING COSTS
Operating time is assumed to be 7200 h/year and following the route described above:
1. RAW MATERIALS:Chloride, propylene, water:
6
6
3
$ $cost of chlorine 0.18 *0.005063 *3600 *71 *7200 1.677*10
kg
$ $cost of propylene 0.47 *0.004599 *3600 *42 *7200 2.353*10
kg
$cost of water=0.3*10 *0.012 *36kg
kmol s kg h
s h kmol year year
kmol s kg h
s h kmol year year
kmol
s
$00 *18 *7200 1680
s kg h
h kmol year year
Total=4.03*106$
2. MAINTANANCE:Assume to be 6% of fixed capital cost=0.06*1.66*107$ = 0.99*106$/year
3. OPERATING LABOUR:Assume to be 28000 $/year
4. LABORATORY COSTS:Assume to be 15% of operating labour cost = 28000 $/year*0.15 = 4.2*103$/year
5. SUPERVISION:Assume to be 12% of operating labour cost=28000$/year*0.12=3.4*103$/year
6. PLANT OVERHEADS:Assume to be 40% of operating labour cost=28000$/year*0.4=11.2*103$/year
7. CAPITAL CHARGES:Assume to be 6% of fixed capital cost=0.06*1.66*107$=0.99*106$/year
-
7/31/2019 COOOOOST
12/12
8. INSURANCE:Assume to be 1% of fixed capital cost=0.01*1.66*107$=1.66*105$/year
9. LOCAL TAXES:Assume to be 2% of fixed capital cost=0.02*1.66*107$=3.32*105$/year
10.ROYALTIES:Assume to be 1% of fixed capital cost=0.01*1.66*107$=1.66*105$/year
Direct Production CostsTotal=6.7*106$/year
Sales expense
General overheads %25 of Direct Production Costs=0.25*6.7*106$=1.68*106$
Research and development
ANNUAL PRODUCTION COST=6.7*106$+1.68*106$=8.38*106$/year
Selling price of 32wt% hydrochloric acid = $0.075/kg [Ref.4]
Selling price of 99.5 wt% pure allyl-chloride = $1.72/kg [Ref.4]
Waste disposal costs of 2 chloro propene = $0.20/kg [Ref.4]
Waste disposal costs of di chloro propene = $0.20/kg [Ref.4]
6 5
6 5 5
6 5 5
$ kg $Selling Pr ice of HCL 0.075 *4.8*10 3.6*10
kg year year
$ kg $ kg $Waste disposal cos t 0.075 *1.32*10 0.075 *2.55*10 1.18*10
kg year kg year year
$ $ $8.38*10 1.18*10 3.6*10
year year yeProduction Cost of allyl chloride
6
6 6
7
6
$ar0.9
kg kg9*10
year
$Selling Price of allyl chloride 1.7kg
$ kg $Annual Income 1.7 *9*10 15.3*10
kg year year
1.66*10 $RATE OF RETURN 1.1 year
$15.3*10
year