Description of our past project; converting Well-Test to Well-Stimulation vessel.TRANSCRIPT
![Page 1: Converting for Al Mansoori](https://reader038.vdocuments.us/reader038/viewer/2022100603/559553a21a28ab02798b45e0/html5/thumbnails/1.jpg)
2013: Al Shaheen: Well-Test to Well-Stimulation
Our Conversion Operation for Al Mansoori
![Page 2: Converting for Al Mansoori](https://reader038.vdocuments.us/reader038/viewer/2022100603/559553a21a28ab02798b45e0/html5/thumbnails/2.jpg)
Well-Test• Process of testing
planned data to maximise knowledge of oil and gas wells.
• Vessels for well-testing incorporate a processing plant; capturing oil and gas flared during testing operations
Originally designed by Henderson International in 2003 for Well-Testing; commissioned by Al Mansoori in 2004.
SHIP PARTICULARS
Length Overall 56 m
Length on Waterline 50.5 m
Breadth Moulded 13.6 m
Depth Moulded 6 m
Summer Draft 4.7 m
Trial Speed 12.5knot
s
![Page 3: Converting for Al Mansoori](https://reader038.vdocuments.us/reader038/viewer/2022100603/559553a21a28ab02798b45e0/html5/thumbnails/3.jpg)
Well-Stimulation; The Conversion• Done to stimulate
existing wells increasing production and flow of hydrocarbons.
Conversion required; addition of 11.4 section parallel to the middle body. Along with 2x acid tanks.
New exhaust chimneys with mounting and securing stimulation equipment on-deck
MACHINERY
Main Engines 2 x 1440 kW
Main Generators 3 x 190 kW
Emergency DG 1 x 120
Main Propulsion System 2 x Schottel SRP
Bow Thruster 2 x 534 kW
Pump Jet 1 nos
Capstans 2 x Elec Driven Vertical HeadPull 10t/5t @ 10/20 m/min
Deck Crane 3t @ 25m radius25t @ 3m radius
Acid Tanks 2 x 30,000 USG
![Page 4: Converting for Al Mansoori](https://reader038.vdocuments.us/reader038/viewer/2022100603/559553a21a28ab02798b45e0/html5/thumbnails/4.jpg)
What Was Done; Summary
• Ship was cut in the middle at 11.4.• 2x acid tanks added at midship• Alteration of air ventilation
• Re-design of piping
• Well-stimulation cabin added on upper forecastle deck
• Well-stimulation equipment installed, secured on deck• Exhaust chimney and air intake installed on deck.WHY? Vessel, initially was 60M; not meeting longitudinal length criteria.
Heavy weight of the midship, also warranted tank loading modifications; meeting strength criteria.
Ventilation, by IBC regulations was also modified for acid tanks
For more detailed inquiries; contact [email protected]