contruss engineering company
TRANSCRIPT
1
Contents Introduction: ................................................................................................................... 2
1- introduction of double-sided voided slab ................................................................. 2
1-1- two-way voided slab with I-shaped section: ..................................................... 2
1-2- double-sided voided slab history: ...................................................................... 2
1-3- advantages of double-sided voided slab applied for spans beyond 7 meters . 5
2- Contruss filler introduction ....................................................................................... 7
3- Contruss system installation ...................................................................................... 8
4- Contruss system advantages .................................................................................... 11
4-1- economic advantages: ....................................................................................... 11
4-2- architectural advantages: ................................................................................. 13
4-3- technical advantages: ........................................................................................ 15
4-4- practical advantages: ........................................................................................ 18
5- comparison with the other systems ......................................................................... 25
5-1- comparison of the Contruss system with the rib and block slab tutorial: ... 25
5-2- comparison of the Contruss system with the metal deck ceiling: ................. 31
5-3- comparison of Contruss system with beam and slab floor system: .............. 37
5-4- comparison of Contruss system with prestressed slab system: .................... 41
6- projects constructed by the use of Contruss system .............................................. 45
7- Conclusion and ultimate comparison table: .......................................................... 58
2
Introduction: Contruss system is a permanent filler that is created for constructing voided slabs, an innovative
system developed by Contruss engineering company. The patent was issued in 2014 in which, I-
shaped sections are created in the voided slabs along with mutually perpendicular ribs. It is a
composite filler that will provide more functional and technical advantages, compared to other
permanent ones because of special forming, material and components. The commercial named
Contruss, is consist of the words concrete+ truss, defined as a concrete truss, suitable for long
spans. In the following, the functional and technical advantages is elaborated.
1- introduction of double-sided voided slab
1-1- two-way voided slab with I-shaped section: Mutually ribs with I-shaped sections are so practical in constructions; Due to inclusion of high
moment of inertia, it will contribute the slab to operate properly in large spans, when subjected
to vibration and deflection. In addition, it is capable of providing openings in various dimensions
in the concrete slab, as regard to existence of much indeterminate degrees.
By involving of two concrete layers, I-shaped sections are appeared in two directions in the
double-sided voided slab system, which will enrich the rigidity and resistance of the ceiling. On
the other words, this system includes two concrete layers connected by orthogonal shear webs
in the ceiling, that is a so-called concrete truss which will result in high rigidity as well as lower
concrete consumption.
Figure 1.1. beam created in the Contruss voided slab
1-2- double-sided voided slab history: The concept is actually quite old. Based on the lack of structural benefit, all of the constructed
concrete systems were come up with a solution to eliminate unloadable concrete in structures
during previous centuries.
3
Figure 1.2. the manners of creating voided slab
The origins of concrete voided slab applied in constructions, can be traced to the long-times ago,
as some samples belong to last century. The initial voided slab with I-shaped section, that is
known as a double-sided voided slab along with permanent fillers, first recognized in 1995 in
Europe. It was created by the use of spherical hollow fillers as permanent ones in the concrete
slab.
Figure 1.3. schematic image of spherical voided slab
In 2002, the exclusive companies initiated changing the manner of manufactured permanent
fillers, created them as rectangular cuboid ones. In comparison to the spherical as special
forming, the new fillers enriched them with a reduction in self-weight and concrete consumption.
4
Figure 1.4. schematic image of rectangular cuboid formwork
With no structural benefit, the filler is aimed to eliminate unloadable concrete as well as creating
hollow zone inside the concrete, which is referred as permanent filler.
Besides the advantages issued for the permanent cuboid fillers, there are some possible defects
in the system. As seen in some projects, some of the possible defects are existence of stress
concentration on the connection band of shear web and flange in the ribs, fracture of the fillers
during installation, difficulty in concrete flowing to the bottom surface of fillers and considering
inadequate cover clearance for rebar.
Contruss engineering group, a pioneer company in creating and practicing innovative technology
for constructions, initiated activity on development of voided slabs created by permanent fillers
in 2008 in the Middle East, as the first one to extend this innovative system, locally and
internationally.
Based on conceptual technical knowledge upon voided slab systems, the research and
development department of company, locally and globally, began innovating in conjunction with
designing and manufacturing of permanent fillers in order to resolve the mentioned defects.
Subsequently, the company initiated manufacturing of its invented permanent fillers,
commercially named “Contruss”, issued in 2014. At the same time, by practicing the fillers in
constructions as voided slab system with permanent fillers, it was advocated by employers and
contractors.
5
Figure 1.5. Contruss permanent formwork
1-3- advantages of double-sided voided slab applied for spans beyond 7 meters a) two-way function:
In many types of concrete slabs, the transfer of loads occurs in the plane of floor with straight
trajectory along one direction of the slab, that makes the transfer trajectory longer, which will
increase beams and columns dimensions as well as ceiling weight. On the contrary, the two-way
voided slab distributes the loads equally in two directions on supports.
b) elimination of beams:
As respect to the high moment of inertia and rigidity as well as lightened weight, the use of
voided slabs makes it possible to transfer dead and live loads directly on the supports; there is
no need to use beams. Although this function is the same as mushroom slabs, the lightened
weight of the voided slabs reaches 30 to 40 percent compared to the filled ones, with equal
rigidity. Therefore, it can be practiced for long spans as provides possibility of omitting beams
and creates a flat soffit (smooth bottom surface of the ceiling). This omission will result in
following advantages:
- achieving long spans without beams
- reduced height of structure as well as increased number of floors
- creating flat intrados floor without drops
Note that removing beams is totally depended on the structural system. By providing shear walls
or in the structures with total height less than 10 meters, the elimination is possible; Unless, the
presence of beams is essential.
c) lightening, fewer columns and high strength in earth quake:
- reduction in dead load that leads to involving of fewer columns; the result is less applied load
on the foundation that leads to less deep foundation excavation.
6
- reduction in dead load applied on the ceiling that leads to decreased lateral force, ultimate shear
and consequently increased structural strength in earthquake.
- reduced deflection as well as increased slab rigidity
d) flexibility in architectural design:
Thanks to the use of voided slab with permanent fillers, creating long span will be possible. From
the architectural point of view, providing long span will allow suitable flexibility in scheme as
well as increasing useful space; additionally, it will provide possibility of using reallocation.
e) suitable operation as an acoustic subjected to noise, heat and vibration:
High rigidity due to the existence of two solid concrete layers and mutually perpendicular ribs,
contribute the slab to control vibration.
As covered by polystyrene up to 80 percent of slab surface, the Contruss system will operate
more properly in subjected to noise and heat, compared to the conventional filled slabs. With a
15-cm-thick as well as much lower heat and sound transmission coefficient compared to the
concrete, polystyrene functions suitably as insulation in transmission of noise and heat.
Note: concrete ceiling is not appropriate insulation in transmission of airborne noise; but the
double-sided voided slab is capable of acting as an acoustic system, since the presence of hollow
space inside the slab.
f) providing possibility of great openings in the slab:
Structural function of slab as a rigid diaphragm for distributing seismic loads among supports
does matter much. Creating openings, from the structural point of view, might disorder the loads
distribution in floors. The double-sided voided slab, due to the high moment of inertia and much
indeterminate degrees, will form a rigid and solid slab that act properly as a diaphragm, even
though in the presence of large openings.
7
2- Contruss filler introduction Contruss filler is a composite combination with a middle core made of EPS material, along with
plastic plates, supports and piles made of PP material, that will provide more functional and
technical advantages, by use of a lightened weight filler compared to the other permanent ones.
Figure 2.1. the positioning manner of Contruss fillers
8
3- Contruss system installation 3-1- ceiling formwork:
The entire surface of the ceiling is shuttered continuously with metal or wood deckings (or other
similar systems); then the scaffolds or jacks are positioned under it.
Figure 3.1. ceiling formwork
3-2- positioning of the lower rebar:
The lower rebar is positioned in two mutually perpendicular directions along with add rebar,
middle beam rebar and dowel rebar. Ceiling deflection must be controlled by a survey camera in
this phase.
figure 3.2. positioning of the lower rebar
9
3-3- positioning of the Contruss fillers:
The Contruss fillers are placed on site according to the design, then attached together by the belts
so they can't move or float upward.
Figure 3.3. positioning of the permanent fillers
3-4- positioning of the upper rebar:
the upper rebar is positioned according to the design; then the slab is ready for concrete pouring.
figure 3.4. positioning of the upper rebar
10
3-5- Concrete pouring, vibration and levelling:
The concrete pouring must be performed in one phase; and concrete slump must be adequate to
fill the lower layer totally. By adding of accelerating admixture, the concrete viscosity is
increased that will enhance the strength and performance quality of the ceiling. Once properly
performed, completely burying the Contruss filler. Then, the pouring is levelled and smoothed
in a traditional manner.
Figure 3.5. Concrete pouring, vibration and levelling
3-6- removing the formwork:
Once the concrete has been hardened, the formwork can be removed and a smooth surface with
flat soffit is created.
Figure 3.6. removing the formwork
11
4- Contruss system advantages
4-1- economic advantages: a) reduced construction cost for long spans:
Most of ceiling slabs exerted in the constructions, function as a one-way system. According to
the increased deflection and vibration in the ceiling as well as using additional beams over spans
beyond 7 meters, the use of one-way slab is not practical, economically and practically. Based
on participating of two concrete layers and orthogonal webs, the Contruss system will form a
high rigid and two-way slab by which, achieving long spans up to 20 meters will be possible.
In general, one of the major difficulty related to the concrete structures is large dimensions of
columns, which can be solved by using of this system as omitting the middle columns.
Furthermore, the Contruss ceiling system will form a high rigid and resistant slab operating
properly subjected to lateral forces, due to the inclusion of two concrete layers along with
orthogonal webs. Additionally, providing long spans, from an architectural point of view, offers
better aesthetic.
Figure 4.1. increased effective span
12
b) variability of filler dimensions:
The Contruss fillers are the only permanent ones in which, dimensions can be evaluated by
engineers to be slashed down in size in factory by means of CNC machine to fit the required
spaces when installing on site, that will simplify slab installation. In correspondence of
economically and functionally improvement, the Contruss filler is capable to be manufactured
with dimensions ranging from 45 to 60 cm, and 12 to 65 cm in height.
Figure 4.2. various dimensions of Contruss filler
c) increased number of parking lots:
Thanks to the use of Contruss voided slab system in terms of removing middle columns, the
numbers of provided parking lots are increased. beyond the financial aspect, this increase will
make the movement and turning of the cars easier.
In some cases, the increased number of parking lots will result in the elimination of a parking
floor as well as costs reduction.
Figure 4.3. increased number of parking lots
13
4-2- architectural advantages: a) increased span length (the distance between columns):
It is known as the most considerable benefit by the architectures, as achieving long spans in
structural design will accompany by following advantages: larger spaces, increased number of
parking lots, facilitated use reallocation, retaining walls displacement and architectural freedom.
figure 4.4. increased effective span
b) creating a flat soffit by eliminating drops:
By the use of Contruss system, ceiling thickness will be decreased; for example, the ceiling will
be 35-cm-thick in a span with length of 12 meters, but a flat surface is created under of ceiling
that can be simply used for systems installation as well as plastering. Vice versa, creating beams
with 80 cm height, drops and uneven intrados surface will complicate the passage of systems by
use of other fillers.
Advantages gained by removing drops and creating a flat intrados floor:
- reduced construction costs because of decreased floor height
- simplified formwork, concrete pouring and rebar performance
- reduced dropped ceiling costs
- flexibility in architecture
- facilitated passage of systems
14
Figure 4.5. creating a flat intrados floor
c) creating large irregular openings:
According to the high rigidity as well as two-way function, the Contruss system is capable of
creating large irregular openings in the rigid diaphragm, which matters much in reception halls,
villas, commercial and educational centers. Also, creating additional openings for passage of
systems will be possible even after completion of slab installation.
Figure 4.6. creating large irregular opening
15
4-3- technical advantages: a) possibility of creating openings after slab construction:
As considering various reasons for creating openings after completion of installation, it is
prohibited in one-way systems, due to beams disrupting. The Contruss system, by involving of
two concrete layers and perpendicular webs, will form a high rigid and two-way slab, that is
capable of creating openings after slab installation.
b) fire resistant slab:
Since composed of flame retardant polystyrene, the Contruss ceiling will provide high quality
acoustic operation in transmission of heat, function more properly in burning compared to the
other systems, certified that is a non-flammable material.
The polystyrene used in the Contruss is a fire-retardant material, which is expanded and
manufactured by hot steam at 100 degrees C, that will be stable in volume per a week.
c) resistant subjected to noise and vibration:
Material strength in sound transmission is investigated in two segments: 1) airborne noise, 2)
percussion noise.
In general, the concrete resists properly in transmission of airborne noise; as consequence, the
Contruss slab operates suitably subjected to airborne noise, because of participating two concrete
layers.
Furthermore, by involving trap air bubbles inside the polystyrene, sound power level will be
reduced by passing of percussion noise through the slab. The use of polystyrene in the Contruss
filler will result in improved acoustic behavior.
With regard to the increased rigidity of Contruss voided slab, less ceiling vibration will be
transferred in comparison with the common concrete slabs, that will be a relief for residents.
Figure 4.9. schematic image of sound waves transmission in a building
16
d) reduced ceiling weight:
Since the variability of Contruss filler dimensions, it will provide more reduction in weight and
cost of ceiling, compared to other voided slab systems. Slashing by CNC machine in the factory,
makes it possible to manufacture the fillers in various dimensions, according to the structural
design requirements. The dimensions of a prismatic formed Contruss filler can be 45 to 60 cm
with the height of 12 to 65 cm, that will provide the most optimum slab construction, technically
and economically.
Figure 4.10. variability of Contruss filler dimensions
The main goal in creating voided slab is referred to eliminating of unloadable concrete in the
middle spaces of ceiling. To come up with, it is highly influenced by the dimensions of the filler,
based on the variation of loading and span length. The Contruss filler is known as the unique
one, which is capable to be designed in any arbitrary dimensions according to the order of
builders in order to minimize ceiling weight and costs.
Table 4.1. filler size and height
Filler height Ceiling thickness(cm) Effective span(m)
Size 15 30 9
Size 20 35 11.5
Size 25 40 13
Size 30 45 14
Size 35 50 15.5
Size 40 55 17.5
Size 45 60 19
Size 50 65 20.5
Size 55 70 22
Size 60 75 25
17
e) providing appropriate clearance for rebar:
Based on the design of trays placed over the fillers, rebar will be positioned in desired distance
as clearance is provided suitably in the Contruss system, which makes it possible to design the
steel mesh without restrictions.
Figure 4.11. providing clearance for rebar
f) controlling vibration and deflection of the ceiling:
Due to the inclusion of perpendicular I-shaped ribs, the double-sided voided slab will provide
high moment of inertia, compared to flat, prestressed and waffle slab, for the ceiling. Generally,
The Contruss ceiling can be known as a hollow concrete truss with much high rigidity, that will
transfer the lateral loads properly as a rigid diaphragm as well as suitably control vibration and
deflection.
g) lack of stress concentration in the shear web:
Providing I-shaped ribs is the major advantage of two-way voided slab. Due to the special
forming of Contruss filler, as depicted in figure 4.12, the connection zone between web and
flanges in the rib is curved and shear force will transfer properly, which prevent it from creating
stress concentration. Stress concentration is a main defect existed in plastic fillers, that is
resolved thanks to the innovative Contruss filler.
Figure 4.12. lack of stress concentration in the I-shaped ribs
18
h) easy to be slashed:
By using of polystyrene, the Contruss filler can be slashed down easily by means of saw to fit
the required spaces in correspondence of irregular scheme with various span length. This unique
qualification will make it easy to position the fillers at the corner region on site.
figure 4.13. use of slashed filler
4-4- practical advantages: a) simplified implementation:
Due to the elimination of middle beams in the Contruss voided slab, the ceiling formwork will
be so simple that can be performed by conventional reinforcement workers. Additionally, by
removing beams, the numbers of rebar and stirrups practiced in the ceiling is decreased that will
permit quick installation.
b) construction speed:
The positioning of fillers, lower and upper rebar and concrete pouring are main steps to install
the Contruss ceiling. The speed of installation will increase as much as 25 percent compared to
other systems since performing continuous formwork, and also will be completed quicker than
the beam and slab floor system, due to a flat soffit.
c) no need for special advanced technology to install:
The use of advanced technology in building construction requires spending much time and cost
as well as protection and surveillance of instruments in some cases. Meanwhile, the Contruss
system is needed no special group to install that can be easily exerted by conventional workers
after simple training.
d) benefit during installation compared to the other permanent fillers:
Because the permanent fillers are maintained in the ceiling, the installation costs are highly
depended on the materials used in manufacturing process. As a consequence, recycled plastics
applied in previous fillers presented different resistance when subjected to cold and warm
conditions. High quality as well as competitive costs are superior advantages of the composed
Contruss filler.
19
The innovative application of a combined polypropylene, compatible adhesive and a polystyrene
core is accompanied by the following advantages:
1 - being solid that leads to avoiding fracture and concrete penetrating inside the fillers during
installation:
As a hollow recycled plastic with lower strength in daily heat interactions, the previous
permanent fillers might be fractured during or before concrete pouring, which will allow the
concrete penetration inside the filler that result in increased ceiling weight.
Since a solid form, the Contruss filler is impossible to be fractured as well as exposing high
flexibility subjected to heavy loads.
Figure 4.14. Contruss system installation
2 - the fillers adapt to drilling in order to simplified concrete pouring:
By increasing dimensions of filler in the double-sided voided slab, consuming concrete will be
reduced, though it may cause honeycomb in concrete at lower regions. Thanks to the engineers
involved at the research and development department of Contruss company, an exhaust hole can
be drilled at the middle of Contruss filler in order to facilitate concrete pouring as well as
preventing from created honeycombing concrete.
Manufacturing in various dimensions and drilled forming are the unique superior benefits of the
Contruss filler that will make it possible to create the most optimized voided slab.
Figure 4.15. a perforated Contruss filler
20
The advantages gained by the use of polypropylene trays:
a) increased filler strength subjected to tensions created by flexure acting on the middle of filler:
The Contruss filler has been qualified to resist over bending fracture, shear punch and
overturning in an experimental test subjected to a load as much as 150kg applied on a surface
with dimension of 8*8cm.
One of the main reasons that has satisfied the builders is mentioned as the strength of Contruss
filler during installation. Once loading applied on the filler during installation, the trays are
stretched as preventing the filler from being deflected; while the hollow fillers will be deflected
or fractured in similar circumstance.
Figure4.16. Contruss filler
b) providing appropriate clearance:
Most of the previous plastic cuboid fillers used in the voided slabs are manufactured in a form
that will provide rebar clearances at the middle of filler, which is known as a defect because the
rebar must be positioned on center of it. The task is not viable or not performed properly in many
projects. Thanks to the use of hollow trays on the Contruss filler, a 2-cm clearance will be
provided simply.
Figure 4.17. providing appropriate clearance
21
c) piles applied to determine the thickness of lower concrete layer:
The filler piles are considered to set the thickness of lower concrete layer as well as preventing
it from floating upward.
Figure 4.18. Contruss piles
d) indicators applied to determine the thickness of upper concrete layer:
The concrete pouring of ceiling is going to be performed after the positioning of fillers and rebar,
while it is difficult to determine required concrete volume. Thanks to the use of indicators over
the upper tray, the concrete pouring level will be determined simply that permits accurate
concrete pouring.
Figure 4.19. indicators applied to determine concrete thickness
e) belts installation:
One of the efficient component engaged in the installation of the fillers is belt, which applied to
create perpendicular integrated ribs in two directions in the slab. Based on the technical concept,
the ribs must be formed integrated and orthogonal, that is achieved by preventing the fillers from
movement during installation. Meanwhile, it is difficult to achieve because of various
circumstances in construction workshop such as passing workers and systems over the ceiling.
The Contruss fillers are attached tightly and regularly by the practice of an integrated belt, which
will permit high quality installation.
While keeping the fillers, the belts are capable of supporting rebar up to size 32, which are
referred as the upper rebar belong to the ribs, that were impossible to be positioned in previous
22
permanent fillers, due to the lack of belts. Consequently, the builders had been required to apply
prefabricated vaults that result in the use of unnecessary rebar in the slabs.
Prefabricated vaults contain shear rebar formed as W in which, one of the applied paired bar will
not be involved in the shear strength because the shear rebar must be positioned perpendicular
to the shear flow to help for strength of slab. Furthermore, there is no need to apply rebar in
many parts of the slabs such as middle, due to lack of shear loads. Therefore, the use of
prefabricated vaults is not recommended in the slabs because of involving unnecessary rebar.
Thanks to the use of belts in the Contruss fillers, the upper rebar of ribs is maintained in the
position; there is no need to use highly cost prefabricated ribs.
figure 4.20. belt on the Contruss filler
23
figure 4.21. fillers maintenance during execution
Figure 4.22. positioning of upper rebar over the belts
24
f) easy to store and transport:
By using piles, the Contruss fillers are attached totally upon each other, which will simplify
storing as well as transporting to site.
Figure 4.23. the attached fillers Figure 4.24. storing the fillers
25
5- comparison with the other systems
5-1- comparison of the Contruss system with the rib and block slab tutorial: a) flexibility in architecture:
Great architectures have dreamed to design over large spaces without columns and long
cantilevers over the history. The Contruss voided slab system will create a space without middle
columns in order to provide architectural freedom as well as facilitated use reallocation.
In the rib and block slab tutorial system, span created will be as much as 7-meters long, while
beyond, it is difficult to be exerted because of increasing deflection and vibration as well as
double ribs required. As regard to the inclusion of two concrete layers and perpendicular webs,
the Contruss ceiling will form a high rigid slab that can be constructed over span up to 20-meters
long.
Figure 5.1. ceiling exerted by the Contruss voided slab
b) one-way slab and seismic function:
The concept in applying rib and block is based on regarding of T-shaped elements, which will
transfer the loads to the supports in one single direction, and also allow elimination of tensioned
concrete that leads to reduced ceiling weight.
Figure 5.2. schematic section of Contruss voided slab Figure 5.3. schematic section of ribs and block
26
By supplying permanent composite fillers in the concrete, the unloadable concrete in the slab
with no structural efficiency will be omitted in the Contruss system, that will permit creation of
I-shaped ribs with two-way function. Due to creating two integrated concrete layers as well as
perpendicular mutually ribs, the slab will provide much bearing capacity.
Figure 5.4. two-way Contruss voided slab Figure 5.5. one-way rib and block
The Contruss voided slab is constructed continuously in two layers that will form a rigid
diaphragm slab in earthquake which transfer lateral forces suitably on supports. It will operate
much more properly compared to the rib and block slab tutorial, in which, just a few centimeters
of tensioned rebar are involved in the ceiling.
Figure 5.6. Contruss system construction Figure 5.7. rib and block construction
c) ceiling thickness:
In the Contruss system, total thickness of ceiling is lower than the rib and block slab tutorial
system. for example, the ceiling will be 35-cm-thick in a span with 12-meters long, but it will
create a flat soffit that can be used for simple passage of systems. While in the rib and block slab
tutorial ceiling, creating beams with 80 cm height, drops and uneven intrados surface along with
the passage of systems will create a ceiling much thicker than the Contruss ceiling.
27
Figure 5.8. Contruss ceiling thickness compared to the rib and block slab tutorial
d) creating large openings:
Impossible to adapt to openings, from the architectural point of view, is one of the main
restriction in use of the rib and block slab tutorial system. As regard to the one-way attribute of
the rib and block slab tutorial system, cutting ribs will disrupt load transfer, which will cost much
to create openings in the ceiling.
On the contrary, according to one of the most major property, the Contruss system is capable of
creating large irregular openings, which matters much in reception halls, villas, commercial and
educational centers.
Figure 5.9. large opening created in the Contruss ceiling
28
e) ceiling weight:
For spans beyond 7 meters along with heavy loads such as parking floor, applying the rib and
block slab tutorial system will be required to accompanied by double ribs as well as much costs.
Although for shorter spans the Contrus system weighs more, it will provide much savings for
spans up to 7-meters long, due to high moment of inertia.
f) final cost:
Because the Contruss system formwork is performed continuously, a flat intrados floor will be
appeared; while there is no need for integrated formwork in the rib and block slab tutorial system,
the costs will be reduced but it will present an uneven surface for the ceiling.
Additionally, due to the existence of uneven surface, large soffit (uneven bottom surface of the
ceiling because of thick beams) and drops, dropped ceiling will be required in buildings. By
representing a flat soffit in the Contruss system, there will be no need for dropped ceiling that
makes the Contruss system costs approximately equal to the traditional rib and block slab tutorial
system.
Figure 5.10. chassis of dropped ceiling
g) simplified installation:
the Contruss system is so easy to be installed that can be performed by conventional parties with
a simple training. no need for special advanced technology to install, the Contruss system is
similar to the rib and block slab tutorial, from constructional point of view.
29
Figure 5.11. the rib and block slab tutorial execution Figure 5.12. the Contruss system execution
h) construction speed:
As required integrated formwork in the Contruss ceiling, construction duration will be increased
as much as 5 percent, that is not considerable.
Required construction duration is same as needed for the rib and block slab tutorial execution,
in both, every floor will be completed in 15 days.
Figure 5.13. Contruss execution compared to the rib and block slab tutorial
i) ceiling deflection and vibration:
Once creating voided slabs via the Contruss system, the slab moment of inertia will remain stable
while dead load will be reduced. As ceiling vibration and deflection is highly depended on the
moment of inertia, the Contruss voided slab system will operate more suitably than the rib and
block slab tutorial.
30
j) adapt to highly irregular supports:
The Contruss system will be able to adapt to irregular supports schemes, as regard to the
integrated mutually function. Consequently, it will provide possibility of changing the columns
scheme as well as positioning the columns in the retaining walls, that is impossible in the rib and
block slab tutorial.
k) fire resistance:
Concrete structures will endure better than the steel structures in fire, generally. Due to existence
of two concrete layers, the Contruss ceiling will function properly in transmission of heat when
subjected to fire, provide more strength than the other ceiling systems. The polystyrene used in
the Contruss filler has been certified that is a flame retardant material.
Figure 5.14. slower transmission of heat in the Contruss system
31
5-2- comparison of the Contruss system with the metal deck ceiling: a) cash flow:
The major issue considered as a distinction between the Contruss and metal deck system is
referred to financial subject. In general, steel structures construction will cost much higher than
concrete structures by 35 to 50 percent, as applying metal deck will increase the costs.
Moreover, concrete structure will offer a better opportunity for builders, who are willing to spend
money upon construction segments by segments as regard to project progress. Because of using
metals in steel structures, it is required to spend much cash at the beginning of project.
Figure 5.15. comparison of concrete structure cash flow to steel structure
32
b) ceiling thickness:
By providing shear walls, the Contruss ceiling formwork will be performed continuously, that
result in creating a flat intrados floor. On the contrary, metal deck ceiling performance is
accompanied by thick girders that will reduce useful height due to executing dropped ceiling.
For large spans up to 10-meters, the Contruss system will come up with a lower total thickness
of ceiling.
Figure 5.15. passage of systems above girders
Figure 5.16. thick girders in metal deck system
In the metal deck ceiling, by passing of systems over the girders, floor useful height will be
reduced.
33
Figure 5.17. increased thickness and costs as dropped ceiling execution
c) adapt to openings:
As a one-way system, cutting ribs will disrupt load paths, that will make it so difficult to create
openings in metal deck system. In order to create openings (for systems passage) after
construction, the decking must be slashed initially as well as reinforcing cutting beams, then the
ceiling is ready for creating opening.
According to the high rigidity and two-way function, the Contruss system is capable of creating
large irregular openings in the rigid diaphragm, which matters much in reception halls, villas,
commercial and educational centers. Also, creating additional openings for the passage of
systems will be possible even after completion of slab installation.
d) fire resistance:
Inefficiency in fire is considered as one of the most prominent defect about metal deck system.
Figure 5.18. fallen apart metal deck system because of fire
34
Due to existence of two concrete layers, the Contruss ceiling will function properly in
transmission of heat when subjected to fire, provide much more strength than metal deck ceiling.
The polystyrene used in the Contruss filler has been certified that is a flame retardant material.
e) construction speed:
Although steel structures are capable of being constructed as much as 30 percent quicker than
concrete structures, but there are two subjects to be considered:
1) By constructing concrete structures over two times per day as a so-called Fast-track project,
it will be completed quicker than the steel structures and at the same time it is more economical
even by two times working per day.
2) After constructing a few bottom stories in tall concrete structures, it is allowed to begin the
brickworks and systems installation in mentioned stories and keeping formwork in upper stories
simultaneously, that will make construction speed of concrete structures equal to steel structures.
Figure 5.19. Contruss system compared to metal deck
35
f) strength subjected to noise and vibration:
Sound resistance of materials is investigated in two segments: 1) airborne noise, 2) percussion
noise.
In general, the concrete ceilings operate properly in transmission of airborne noise; once by
involving polystyrene, acoustic function in percussion noise will be improved. As a result, the
Contruss slab will function more properly than metal deck when subjected to both airborne and
percussion noise
Figure 5.20. percussion noise
On the other hand, resistance in transmission of vibration regarded to ceiling is known as one of
the most essential property for the residents. Providing such strength will cost much in steel
structures. On the contrary, due to the high rigidity of Contruss voided slab, it will operate more
properly subjected to vibration, which is a relief for residents.
Figure 5.21. noise and vibration transmission in floors
36
g) ceiling weight:
The Contruss voided slab weighs more than metal deck which will be acceptable by considering
lower costs, adapt to large spans, less ceiling thickness in large spans, high rigidity and the other
superior related to the Contruss system.
h) providing large span:
Metal deck can be performed simply for spans up to 8 meters; while beyond, it will require much
cost as well as increased ceiling thickness. As inclusion of two concrete layers along with
perpendicular webs, the Contruss ceiling form a high rigid slab that will provide a rigid
diaphragm subjected to lateral forces as well as provide spans up to 20-meters long.
Figure 5.22. ceiling created by the Contruss voided slab
In general, from an architectural point of view, one of the major defect related to concrete
structures is the large dimensions of columns, which can be solved by removing the middle
columns and creating large spans, thanks to the Contruss system. Providing large spans will
result in numerus efficiency such as greater exposed spaces, increased the number of parking
lots, partitions reallocation and architectural freedom.
37
5-3- comparison of Contruss system with beam and slab floor system: a) ceiling thickness:
Large soffit and drops will be accompanied by following defects:
1- increased total height of structure due to increased floor height
2- increased costs as well as difficulty in formwork, concrete pouring and rebar performance
3- additional costs respect to dropped ceiling
4- architectural restrictions
5- difficulty in passage of systems
Figure 5.23. easy to install systems due to a flat soffit
Figure 5.24. better aesthetic by omitting drops
38
b) increased construction costs for spans up to 8 meters:
The Contruss voided slab has been come up to develop the conventional beam and slab system,
based on the elimination of unloadable concrete in middle spaces with no structural benefit. The
Contruss voided slab system weighs less compared to solid slabs, that will reach up to 50 percent
with equal rigidity in some cases.
Due to high rigidity and low weight as well as two-way function, the voided slabs will be able
to create large spans along with low ceiling thickness. For example, in a double-sided voided
slab with 35-cm-thick, the concrete is poured in 22-cm height that will demonstrate optimized
concrete consumption. Afterwards, a 22-cm-thick flat slab will provide a maximum 7-meters
span, which express the voided slab advantages.
Moreover, the loads are transferred to secondary beams, main beams and then the columns in
the beam and slab floor system. In the Contruss system, vice versa, the loads are transferred
directly to the columns because of two-way function. Therefore, the Contruss ceiling system will
offer better function and lower costs in large spans; however, for spans beneath 7 meters, as
reduced bending moment at the middle of slab, the conventional beam and slab floor system will
cost less.
Figure 5.25. two-way function of Contruss system
Similar to flat slabs, the Contruss system formwork will provide a flat intrados floor. Due to
existence of beams and large soffit in the beam and slab floor system, dropped ceiling will be
required which will increase construction duration and formwork costs.
c) construction speed:
As creating a flat soffit, a flat integrated formwork will be required for the Contruss system
which permit easy and quick construction.
39
Figure 5.25. the beam and slab floor system figure 5.26. the Contruss voided slab system
d) adapt to large and irregular openings:
The loads are transferred to supports through I-shaped mutual ribs in the Contruss system. In the
beam and slab floor system however, such transfer is accomplished by secondary beams which
makes it difficult to crate openings in the slab because of disrupting in beams.
e) easy to install:
The use of advanced technology in building construction requires spending much time and cost
as well as protection and surveillance of the instruments during construction in some cases.
Meanwhile, the Contruss system is needed no special group for installation in spite of known as
innovative engineering technology, that can be exerted easier than the beam and slab floor
system.
Figure 5.27. positioning the Contruss fillers to perform a voided slab
40
f) fire resistance:
Concrete structures will endure better than steel structures in fire, generally. Due to existence of
two concrete layers, the Contruss ceiling will function properly in transmission of heat when
subjected to fire, provide more strength than the beam and slab floor systems. In addition,
polystyrene used in the Contruss filler is a slow burning certified that is a flame retardant
material.
g) strength subjected to noise and vibration:
Material resistance in sound transmission is investigated in two segments: 1) airborne noise, 2)
percussion noise.
In general, the concrete ceilings resist properly in transmission of airborne noise; as consequence,
the Contruss slab operates suitably as well as the beam and slab floor system when subjected to
the airborne noise. However, the difference is appeared over percussion noise.
By involving trap air bubbles inside the polystyrene used in the Contruss system, sound power
level is reduced by passing of percussion noise through the slab. Polystyrene is known as the
second available materials that represents best acoustic function in sound transmission according
to the building codes. Overall, applying polystyrene along with two concrete layers in the
Contruss fillers have provided proper resistance subjected to airborne and percussion noise
transmission.
Figure 5.28. noise transmission through walls and ceiling
Furthermore, with regard to the increased rigidity of Contruss voided slab, it will transfer less
ceiling vibration in comparison with the beam and slab floor system, that is a relief for the
residents.
41
5-4- comparison of Contruss system with prestressed slab system: a) required advanced technology and specialist parties to construct:
The use of advanced technology in building construction requires spending much time and cost
as well as protecting of instruments during construction. As regard to scientific and technical
complication, the prestressed system is accompanied by special complicated pre-tensioning, high
advanced technology materials and difficult performance which will discourage the builders to
use unless for bridges or large spans up to 30 meters. Consequently, the Contruss system is more
acceptable, from the technical and economical point of view.
Figure 5.29. instruments of the prestressed system
One example about complexity of the prestressed system is releasing of post-tensioning cables,
which is required to be inspected that is not viable in buildings, though it can be controlled after
a while in bridges.
Figure 5.30. pre-tensioning process
Another example about complexity of the prestressed system is occurred when opening is needed
after slab installation. As providing much resistance subjected to forces applied on the slab via
such cables, it will be required high accuracy to protect the cables for creating openings in the
ceiling after slab construction.
42
Figure 5.31. post-tensioning cables
Positioning of cable pods according to the curvature of scheme is another difficulty in the
prestressed system installation, which is required specialist parties to position, tension and cover
the cables.
On the contrary, installing the Contruss ceiling is followed by positioning of the fillers, lower
and upper rebar and concrete pouring that is as simple as conventional ceiling system but it is
capable of providing large spans up to 20 meters.
Figure 5.32. positioning of the Contruss fillers Figure 5.33. performing pre-tensioned arch cable
pods
b) construction speed:
Based on the following reasons, the prestressed system will require more time to complete than
the Contruss system:
1- concrete must be hardened before pre-tensioning:
Concrete is required to be hardened before applying the pre-tensioning force in the post-
tensioned system, so the executive party has to complete the process after hardening. Then the
formworks are removed to use for next ceiling.
2- In many prestressed slabs, in addition of integrated ceiling formwork, drops and large soffit
formwork is needed which will increase the construction duration and costs.
3- Because of involving specialist parties, delay in presence of parties will increase total
construction duration.
43
c) existence of drops and large soffit in most of prestressed ceilings:
As the cables must be restrained in two directions in the slab, around beams will form a thick
and large section in the prestressed systems that leads to creating large soffit.
Figure 5.34. structure exerted by prestressed system Figure 5.35. structure exerted by Contruss system
There will be more difficulties related to the prestressed ceilings constructed by pre-tensioning
method such as creating flaw in the ceiling, architectural restrictions and installation problems.
As regarding of such difficulties, pre-tensioning manner is usually applied for industrial ceilings.
Figure 5.36. ceiling exerted by prestressed system
d) weight of used materials:
By involving total concrete section under compression, the neutral axis is conducted upward that
will result in decreased materials consumption as well as reduced concrete section in the
prestressed ceiling. On the other side, because of creating middle voids in the ceiling, moment
of inertia is increased and concrete consumption is reduced in the Contruss system that will
present a lower weight ceiling by 5 to 15 percent compared to the prestressed system.
44
e) cost:
Due to simplified performance, the Contruss system will cost less by 5 to 10 percent than the
prestressed system.
f) adapt to openings:
Because of disrupting the cables trajectory, it is so difficult to create openings in the prestressed
slab system, and also impossible to implement special formed openings in many cases.
In the Contruss system however, creating large irregular openings in ceilings will be so simple
that matters much in reception halls, villas and commercial and educational centers.
g) acoustic function of ceiling:
By involving middle polystyrene cavities, the Contruss voided slab system is a suitable insulation
in transmission of airborne noise which is so important in religious and educational centers.
h) fire resistance:
Due to existence of two concrete layers along with flame retardant polystyrene between them,
the Contruss ceiling will function properly in transmission of heat when subjected to fire, provide
more strength than the prestressed ceiling systems. The polystyrene used in the Contruss filler is
has been certified that is a flame retardant material.
The major defect related to the prestressed ceiling when subjected to fire is releasing of the post-
tensioning cables. As regard to providing much resistance for total strength of the slab by the
cable, it will be expanded and fail in fire that leads to collapse of the ceiling.
45
6- projects constructed by the use of Contruss system
Pratham residential complex:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
6.5*10.5 24*55 8 residential 2731
46
Vaikunth official complex:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
6.5*10.25 20*55 7 official 1470
Sivanta residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
10*12 13 22 residential 14334
47
Anandvan residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11.5*10 20 9 residential 5422
Diamond commercial project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
13*8 24 10 commercial 3200
48
Asha residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11*9 13 7 residential 1875
Soham Residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
12.5*10 24 8 residential 2731
49
Kalpvan residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
9.5*8 20 4 residential 1000
Ashirward residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11*7 20 5 residential 960
50
Snakalp residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11.5*9.5 19 7 residential 1442
Venus tower project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
10.5*10 20 14 residential 11000
51
Chamatkar villa project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
10.5*7.5 19 5 residential 1315
Kalpana terminal project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
12 25 5 terminal 1300
52
Ranjit residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
19*16 32*19 2 residential 1394
Preet project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
10 25 7 residential 35000
53
Sukharm project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11*12 20 5 residential 1600
Arpan complex project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
12 25 8 residential 11000
54
Daya residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11.5*10 20 11 residential 3600
Vivanta residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
12*9 19 7 residential 1347
55
Mannat villa project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
12*9.5 15 2 villa 425
Sumel reception hall& commercial complex:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
13.5*10 32 10 commercial 900
56
Surabhi residential project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11*10 15 9 residential 9827
Ahand shopping project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
11.5*15 19 10 commercial 5370
57
Doctors building complex:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
13.5*10 24 8 official 6497
Rajhans project:
Effective
span (m)
Filler size
(cm)
Story
numbers use Area (m)
10*13 24 12 residential 4595
58
7- Conclusion and ultimate comparison table: Thanks to the use of modern Contruss voided slab system, technical advantages along with
simple performance are provided as well as much economic benefits for large spans. Due to
providing two concrete layers and mutually I-shaped ribs, the system presents high rigidity
subjected to gravity and lateral loads that will provide possibility of creating spans up to 20
meters. Because of inappropriate function of one-way ceiling over spans beyond 7 meters, the
integrated two-way function of Contruss voided slab will be so practical in such spans. The
following table is illustrated the attributes and advantages of the Contruss system compared to
the other constructional ceiling systems.
59
Comparison table of Contruss voided slab system with the other ceiling systems:
Contruss
Rib and
block slab
tutorial
Beam and
slab
system
Prestresse
d system
Metal
deck
Adapt to large spans
and cantilevers
Resistant in sound
transmission
No need for dropped
ceiling
Construction speed
Simplified
implementation
Lack of large soffit
and drops
Fire resistance
Construction costs
for spans beneath 8-
meters
Construction costs
for spans beyond 8-
meters
Reduced vibration
and deflection
Reduced weight of
structure
No need for special
parties to install
Adapt to irregular
large spans
Adapt to irregular
supports
Complete points: