contractor selection ahp

Upload: apmegremis

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Contractor Selection AHP

    1/12

    Construction Management and Economics (December 2004) 22, 10211032

    Construction Management and Economics

    ISSN 0144-6193 print/ISSN 1466-433X online 2004 Taylor & Francis Ltd

    http://www.tandf.co.uk/journals

    DOI: 10.1080/0144619042000202852

    *Author for correspondence. E-mail: [email protected]

    Contractor selection using the analytic network

    process

    EDDIE W. L. CHENG and HENG LI*

    Department of Building and Real Estate, The Hong Kong Polytechnic University, Hunghom, Kowloon, Hong Kong

    Received 30 January 2003; accepted 9 January 2004

    Contractor selection is one of the main activities of clients. Without a proper and accurate method for selecting

    the most appropriate contractor, the performance of the project will be affected. The multi-criteria decision-

    making (MCDM) is suggested to be a viable method for contractor selection. The analytic hierarchy process

    (AHP) has been used as a tool for MCDM. However, AHP can only be employed in hierarchical decisionmodels. For complicated decision problems, the analytic network process (ANP) is highly recommended since

    ANP allows interdependent influences specified in the model. An example is demonstrated to illustrate how this

    method is conducted, including the formation of supermatrix and the limit matrix.

    Keywords: Analytic network process, analytic hierarchy process, multi-criteria decision making, contractor

    selection

    Introduction

    Contractor selection is one of the main decisions made

    by the clients. In order to ensure that the project can becompleted successfully, the client must select the most

    appropriate contractor. This involves a procurement

    system that comprises five common process elements:

    project packaging, invitation, pre-qualification, short-

    listing and bid evaluation (Hatush, 1996; Hatush and

    Skitmore, 1997). Moreover, there are methods attemp-

    ting to estimate the values of contractors by using various

    selection criteria (e.g. Samuelson and Levitt, 1982;

    Jaselskis and Russell, 1990). These methods include

    multi-criteria decision-making (MCDM), multi-

    attribute analysis (MAA), multi-attribute utility theory

    (MAUT), multiple regression (MR), cluster analysis

    (CA), bespoke approaches (BA), fuzzy set theory (FST)and multivariate discriminant analysis (MDA) (Hatush

    and Skitmore, 1997; Holt, 1998; Mahdi et al., 2002).

    Selection criteria on the other hand can be classified as

    pre-qualification and project-specific (Alarcon and

    Mourgues, 2002).

    Among those well-known methods, MCDM is

    relatively new to be employed to select contractors.

    MCDM aims at using a set of criteria for a decision

    problem. Since these criteria may vary in the degree of

    importance, the analytic hierarchy process (AHP) tech-

    nique is employed to prioritize the selection criteria (i.e.assign weights to the criteria). In the existing literature

    of contractor selection, studies have utilized AHP to set

    up a hierarchical skeleton within which multi-attribute

    decision problems can be structured (e.g. Fong and

    Choi, 2000; Mahdi et al., 2002). Conceptually, AHP

    is only applicable to a hierarchy that assumes a uni-

    directional relation between decision levels. The top

    level of the hierarchy (apex) is the overall goal for the

    decision model, which decomposes to a more specific

    level of elements until a level of manageable decision

    criteria is met (Meade and Sarkis, 1999). Yet, the strict

    hierarchical structure may need to be relaxed whenmodelling a more complicated decision problem that

    involves interdependencies between elements of the

    same cluster or different clusters. This requires the

    generic analytic method the analytic network process

    (ANP) that can evaluate multidirectional relationship

    among decision elements (Saaty, 1988; Meade and

    Sarkis, 1998).

    In most studies of contractor selection, selection

    criteria are assumed to be independent of each other.

  • 7/30/2019 Contractor Selection AHP

    2/12

    1022 Cheng and Li

    Apparently, these criteria are likely to affect each other.

    For example, Fong and Choi (2000) used a sample

    of 13 respondents to identify and prioritize eight un-

    correlated criteria (tender price, financial capability,

    past performance, past experience, resources, current

    workload, past relationship and safety performance) for

    contractor selection. In fact, the eight criteria are

    interrelated to a certain extent. For example, good past

    experience may lead to good safety performance if the

    past experience includes good safety records. Good past

    performance and experience are good evidence of suc-

    cessful projects, which in turn results in strong financial

    capability. Resources and financial capability may be

    positively correlated. Tender price may be negatively

    related to other criteria. Therefore, ANP is more

    favourable to be employed in this interdependent

    relationship framework. Since ANP is new to the

    construction field, this study will demonstrate how to

    apply ANP to improve the prioritization of contractor

    selection criteria. It is expected that by using ANP,clients are able to establish a complete decision model

    without sacrificing the validity due to limitations of the

    analytical tool.

    Contractor selection

    Existing literature on contractor selection mainly deals

    with how to identify and assess the criteria to make the

    most appropriate decisions (Holt, 1997). A more pro-

    mising approach to classifying the contractor selection

    criteria has been provided by Hatush and Skitmore

    (1997), who focused on two of the five-stage process ofcontractor selection: (1) pre-qualification, and (2) bid

    evaluation. Holt (1998) and Valentine (1995) referred

    to this as a two-stage procedure: (1) pre-qualification,

    and (2) evaluation of tenderers. Figure 1 illustrates a

    typical bespoke approach that shows where these stages

    are located.

    Pre-qualification is the process that compares the key

    contractor-organizational criteria among a group of

    contractors desirous to tender. Such criteria can be past

    performance, past experience, and financial stability. In

    order to identify the contractor-organizational criteria,

    researchers have proposed useful methods, such as

    MAA (e.g. Russell and Skibniewski, 1987; Russell et al.,

    1992; Holt et al., 1994).

    Evaluation of contractors on the other hand considers

    specific criteria that can measure the suitability of con-

    tractor for the proposed project (Holt, 1998). Contrac-

    tor evaluation is not equivalent to contractor selection.

    Specifically, contractor evaluation is the process of

    investigating or measuring project-specific attributes,

    while contractor selection refers to as the process of

    aggregating the results of evaluation to identify

    optimum choice. In practice, these two processes are

    always grouped together to represent a single procedure

    to prioritize the contractors according to the project spe-

    cific criteria, which can be office location with respect to

    the project, experience in the geographical region, and

    experience of the proposed construction methods.

    There are methods apt to identify project-specific

    criteria. For example, MAUT is one of the current

    available techniques (Alarcon and Mourgues, 2002).

    MAA, MAUT and AHP are comparable methods

    that assign weights to selection criteria (Holt, 1998;

    Alarcon and Mourgues 2002). Table 1 illustrates their

    respective formula to show why their functions are alike

    (Holt, 1998). As shown in Table 1, these contractor

    evaluation methods are known to calculate an aggregate

    (or composite) score for each criterion. The differences

    between these methods are that: (1) MAA and AHP use

    Figure 1 A simplified bespoke approach (note: this simpli-

    fied bespoke approach (BA) is typically run in a large client in

    Hong Kong. It may be different from other BAs (e.g. Holt,

    1998)

  • 7/30/2019 Contractor Selection AHP

    3/12

    1023Contractor selection using analytic network process

    simple scoring for rating the criteria, while MAUT

    makes use of utility value; and (2) AHP employs pair-

    wise comparison for determining the weights, while

    MAA and MAUT use simple scoring. Yet, Mahdi et al.(2002) suggested that AHP could be the weighting

    method incorporated into MAA or MAUT. When con-

    sidering that the criteria are somewhat related and what

    Holt (1997) mentioned about the rationalization,

    resource saving and objectivity, ANP (analytic network

    process) would be a more reliable method to assign

    weights to correlated attributes. This paper is not

    intended to compare existing contractor evaluation

    methods. Those who are interested in knowing more

    about other methods may refer to Holt (1998).

    AHP and ANP

    AHP and ANP are two separate concepts introduced by

    Saaty (1980, 1996). Saaty (1980) first developed the

    AHP, which helps to establish decision models through

    a process that contains both qualitative and quantitative

    components. Qualitatively, it helps to decompose a

    decision problem from the top overall goal to a set of

    manageable clusters, sub-clusters, and so on down to

    the final level that usually contains scenarios or alterna-

    tives. The clusters or sub-clusters can be forces,

    attributes, criteria, activities, objectives, etc. Quantita-

    tively, it uses pair-wise comparison to assign weights to

    the elements at the cluster and sub-cluster levels and

    finally calculates global weights for assessment taking

    place at the final level. Each pair-wise comparison

    measures the relative importance or strength of the

    elements within a cluster by using a ratio scale. One of

    the main functions of AHP is to calculate the consis-

    tency ratio to ascertain that the matrices are appropriate

    for analysis (Saaty, 1980). Nevertheless, AHP models

    assume that there are unidirectional relationships

    between clusters of different decision levels along the

    hierarchy and uncorrelated elements within each cluster

    as well as between clusters. It is not appropriate for

    models that specify interdependent relationships

    in AHP. ANP is then developed to enhance the toolsanalytical power.

    ANP is a generic form of AHP and allows for more

    complex interdependent relationships among elements

    (Saaty, 1996). It is also known as the systems-with-

    feedback approach (Meade and Sarkis, 1998). Inter-

    dependence can occur in several ways: (1) uncorrelated

    elements are connected, (2) uncorrelated levels are con-

    nected and (3) dependence of two levels is two-way (i.e.

    bi-directional). Figure 2 illustrates examples of these

    interdependencies. By incorporating interdependencies

    Table 1 Comparison of MAA, MAUT and AHP

    Method Formula Description

    Multi-attribute n ACrj is the aggregate score for contractorj;

    analysis (MAA) ACrj= SVijWi Vijis the attribute iscore with respect to contractorj;

    i = 1 n is the number of attributes considered in the analysis;

    Wi is the weighting indices to Vi

    Multi-attribute utility n ACrj is the aggregate score for contractorj;theory (MAUT) ACrj= SUijWi Uijis the attribute iscore with respect to contractorj;

    i = 1 n is the number of attributes considered in the analysis;

    Wi is the weighting indices to UiAnalytic hierarchy n Cri is the composite score for contractor i;

    process (AHP) Cri= SciVij ciis the relative weight for Viwith respect to contractorj;

    i = 1 and Vijis the selection criterion iwith respect to contractorj

    Note: Partially adapted from Holt (1998).

    Figure 2 Examples of interdependence (notes: (1) uncorre-

    lated elements are connected; (2) uncorrelated levels are

    connected; (3) dependence of two levels is two-way (i.e.

    bi-directional)

  • 7/30/2019 Contractor Selection AHP

    4/12

    1024 Cheng and Li

    Figure3

    Hierarchicalstructureofcontractorselection(source:FongandChoi,2000)

  • 7/30/2019 Contractor Selection AHP

    5/12

    1025Contractor selection using analytic network process

    (i.e. addition of the feedback loops in the model), a

    supermatrix will be developed. The supermatrix

    adjusts the relative importance weights in individual

    matrices to form a new overall matrix with the eigen-

    vectors of the adjusted relative importance weights

    (Meade and Sarkis, 1998). According to Sarkis (1999),

    ANP comprises four main steps:

    (1) Conducting pair-wise comparisons on the

    elements at the cluster and sub-cluster levels;

    (2) Placing the resulting relative importance

    weights (eigenvectors) in submatrices within the

    supermatrix;

    (3) Adjusting the values in the supermatrix so that

    the supermatrix can achieve column stochastic;

    and

    (4) Raising the supermatrix to limiting powers until

    the weights have converged and remain stable.

    Methodology

    The current study revises the hierarchical model of

    Fong and Choi (2000) by adding interdependent influ-

    ences at the selection criteria level. Figure 3 illustrates

    the original model being composed of four levels. At the

    top level is the decision problem itself, while the bottom

    level comprises the three decision alternatives (i.e. con-

    tractor candidates). The criteria and sub-criteria repre-

    sent the middle two levels. Figure 4 illustrates a general

    view of the new decision network model. In this model,

    the main difference from the original model is that there

    Figure 4 The ANP network component

    is a feedback loop in the selection criteria level. It is

    assumed that the eight selection criteria are interdepen-

    dent. Figure 4 also illustrates a clearer view of the inter-

    relationship structure by the callout box. Moreover,

    only four of the eight criteria have sub-criteria (see

    Figure 3). It is worth noting that sub-criteria decom-

    posed from their respective criterion are not assumed tobe interdependent.

    Pair-wise comparisons

    The normal procedure of a pair-wise comparison is to

    invite experts to compare two sub-clusters elements

    with respect to their respective clusters element. Saaty

    (1980) has developed a 9-point priority scale of mea-

    surement, with a score of 1 representing equal impor-

    tance of the two compared elements and 9 being

    overwhelming dominance of one element (row element)

    over another element (column element). When there is

    overwhelming dominance of a column element over arow element, a score of 1/9 is given. Figures 5 and 6

    provide an illustration of the use of the scale to represent

    the judgments generated in this study.

    After having consulted with five construction pro-

    fessionals, the pair-wise comparisons in this paper are

    of three bases. First, this paper adopts the original

    pair-wise comparison results in Fong and Choi (2000)

    who compared the criteria and sub-criteria for the three

    candidates, which had fifteen sets of judgment matrices.

    Second, this paper adjusted part of the original relative

    weights of the criteria with respect to the top goal and

  • 7/30/2019 Contractor Selection AHP

    6/12

    1026 Cheng and Li

    those of the sub-criteria with respect to their respective

    criteria. Figure 5 presents these five sets of judgment

    matrices. Third, for synthesizing the relative weights

    among the criteria, other pair-wise comparisons have

    to be made for this study. This is to compare two criteria

    with respect to a selected criterion. This requires

    establishing eight additional sets of judgment matrices

    for analysis. Figure 6 presents these eight paired

    comparison matrices. For example, with respect to the

    criterion tender price, financial capability is relatively

    Figure 5 Relative weights of criteria and sub-criteria

    more important than safety performance. Noteworthy,

    clients should develop their own set of scores for

    the criteria and sub-criteria matching their project

    requirements.

    Relative weights of elements and consistency

    ratio of matrices

    After the pair-wise comparison matrices are developed,

    a vector of priorities (i.e. a proper or eigen vector) in

  • 7/30/2019 Contractor Selection AHP

    7/12

    1027Contractor selection using analytic network process

    Figure 6 Criteria interdependency comparisons

  • 7/30/2019 Contractor Selection AHP

    8/12

    1028 Cheng and Li

    Figure 6 Continued

  • 7/30/2019 Contractor Selection AHP

    9/12

    1029Contractor selection using analytic network process

    each matrix is calculated and is then normalized to

    sum to 1.0 or 100 per cent. This is done by dividing

    the elements of each column of the matrix by the sum

    of that column (i.e. normalizing the column); then,

    obtaining the eigen vector (eVector) by adding the

    elements in each resulting row (to obtain a row sum)

    and dividing this sum by the number of elements in

    the row (to obtain priority or relative weight)(Cheng and Li, 2002). Moreover, for ascertaining the

    consistency of the judgment matrices, Saaty (1994)

    suggested three threshold levels: (1) 0.05 for 3-by-3

    matrix; (2) 0.08 for 4-by-4 matrix; and (3) 0.1 for all

    other matrices. Those who want to know the algo-

    rithm for computing consistency ratio may refer to

    Saaty (1980) and Cheng and Li (2001). Figures 5 and

    6 present the relative weights (priorities) and the CR

    values for the comparison matrices.

    Supermatrix and the limit matrix

    With interdependent influences, the system that con-

    sists of cluster and sub-cluster matrices must translate

    to a supermatrix. This can be achieved by entering the

    local priority vectors in the supermatrix, which in turn

    obtains global priorities. Table 2 shows the super-

    matrix for the ANP decision model. It contains the

    weights (or priorities) for the judgment matrices.

    After entering the sub-matrices into the super-

    matrix and completing the column stochastic, the

    supermatrix is then raised to sufficient large power

    until convergence occurs (Saaty, 1996; Meade and

    Sarkis, 1998). Table 3 presents the final limit matrix.

    Each column is the same and provides the localrelative weights of individual sets of elements.

    Discussions

    The limit matrix shows the local relative weights for

    all the elements in the supermatrix. In order to ascer-

    tain the value of ANP, results of the normalized rela-

    tive weights of the candidates obtained from ANP and

    AHP are compared. Table 4 presents the local relative

    weights of the three candidates based on the results

    from ANP, as well as the local relative weights from

    AHP. In the demonstrated example, candidate Ashould be chosen because it has the largest relative

    weights (= 0.473, from ANP in Table 4). However, if

    the decision model does not specify the interdepen-

    dent relationships (i.e. only AHP model), candidate

    B should have been selected since it had the largest

    relative weights (= 0.448, from AHP in Table 4).

    Candidate A was even the worst among all candi-

    dates. It is because the ANP decision model has taken

    into account the interdependencies among selection

    criteria that exert extra influences on the model.

    AHP has its limitation because it can only be applied in

    simple hierarchical structures, while ANP provides pow-

    erful capability in solving nowadays construction manage-

    ment issues that involve more complicated decision

    problems. It is not to say that results from AHP would be

    different from those of ANP. It depends on the subjective

    and/or objective ratings given to the judgment matrices.

    However, when there are interdependent influences, ANP

    is a viable method for prioritization. In this study, the

    ANP method is applied in contractor selection, and ANP

    enhances the increasingly popular multi-criteria decision-

    making (MCDM) approach to criteria prioritization.

    When researchers and practitioners have realized that

    lowest-price is not the promising approach to attain the

    overall lowest project cost upon project completion,

    multi-criteria selection becomes more popular (Wong

    et al., 2001). There are various methods used for multi-

    criteria contractor evaluation. Multivariate statistical ana-

    lytic methods are more quantitative in nature. Wong et al.

    (2001) refer to them as the objective tender evaluationmethods. Yet, these methods need a sufficiently large

    amount of respondents in order to ensure the objective

    quality. Although researchers tend to believe the need for

    identifying a set of general selection criteria using empiri-

    cal surveys (Holt et al., 1995; Fong and Choi, 2000; Wong

    et al., 2001), assigning weights to these general criteria is

    however the internal business decisions made by indi-

    vidual clients. In other words, the clients evaluate contrac-

    tors according to the requirements of individual projects.

    Basically, there are two types of projects: public and pri-

    vate. There may be necessary to develop individual sets of

    criteria for these project types. For example, there is an

    expanding view that long-term or strategic partneringbecomes more appropriate in private projects procure-

    ment. Hence, the relationship between the client and

    the bidding contractors may be an important selection

    criterion. On the other hand, the competitive tendering

    process is still the current practice for public projects

    although some may argue that it is becoming less popular.

    The private relationship criterion would be inappropri-

    ate when selecting contractors in the process of public

    tendering.

    In normal practices of contractor selection, only a small

    group of experts (mainly the top management of the

    client) is responsible for evaluating the contractor candi-

    dates. In such circumstances, using the MCDM approach

    to contractor selection is more plausible (Mahdi et al.,

    2002). ANP and AHP can help assign weights to selection

    criteria so as to increase the accuracy of judgments made

    by experts. They are not only the decision tools appropri-

    ate for contractor evaluation at both the pre-qualification

    and project-specific stages but can also act as the quantita-

    tive tools for assigning weights to criteria in other methods

    (e.g. MAA and MAUT). These decision tools set the new

    horizon for contractor selection by raising key processes of

  • 7/30/2019 Contractor Selection AHP

    10/12

    1030 Cheng and Li

    Table2

    Supermatrix(major

    components)

    Go

    al

    Selectioncriteria

    Selectionsub-criteria

    F.C.

    P.P.

    P.E.

    R.

    T.P.

    F.C.

    P.P.

    P.E.

    R.

    C.W.

    C.R.S.P.

    F.S.

    F.R.C

    .C.C.O.

    D.

    A.Q.S.C.T.C.

    E.A.

    P.R.

    H.R.

    Goal

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    Selection

    T.P.0.38

    0.00

    0.56

    0.33

    0.31

    0.21

    0.20

    0.17

    0.18

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    criteria

    F.C.0.28

    0.14

    0.00

    0.37

    0.32

    0.24

    0.26

    0.17

    0.14

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    P.P.

    0.13

    0.20

    0.06

    0.00

    0.20

    0.21

    0.18

    0.17

    0.17

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    P.E.

    0.08

    0.11

    0.06

    0.06

    0.00

    0.18

    0.18

    0.09

    0.16

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    R.

    0.04

    0.20

    0.06

    0.06

    0.04

    0.00

    0.07

    0.17

    0.23

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    C.W.0.03

    0.11

    0.06

    0.06

    0.04

    0.09

    0.00

    0.17

    0.03

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    C.R.0.04

    0.11

    0.06

    0.06

    0.06

    0.04

    0.03

    0.00

    0.10

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    S.P.

    0.02

    0.11

    0.12

    0.06

    0.03

    0.04

    0.07

    0.04

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    Selection

    F.C.F.S.

    0.00

    0.00

    0.90

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    sub-criteria

    F.R.0.00

    0.00

    0.10

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    P.P.C.C.0.00

    0.00

    0.00

    0.71

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    C.O.0.00

    0.00

    0.00

    0.11

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    D.

    0.00

    0.00

    0.00

    0.11

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    A.Q.0.00

    0.00

    0.00

    0.07

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    P.E.S.C.0.00

    0.00

    0.00

    0.00

    0.48

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    T.C.0.00

    0.00

    0.00

    0.00

    0.41

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    E.A.0.00

    0.00

    0.00

    0.00

    0.11

    0.00

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    R.

    P.R.0.00

    0.00

    0.00

    0.00

    0.00

    0.50

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    H.R.0.00

    0.00

    0.00

    0.00

    0.00

    0.50

    0.00

    0.00

    0.00

    0.00

    0.000

    .00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    0.00

    Contractor

    A

    0.00

    0.07

    0.00

    0.00

    0.00

    0.00

    0.47

    0.81

    0.18

    0.20

    0.750

    .18

    0.80

    0.69

    0.77

    0.73

    0.40

    0.12

    0.75

    0.69

    candidates

    B

    0.00

    0.65

    0.00

    0.00

    0.00

    0.00

    0.08

    0.07

    0.59

    0.40

    0.060

    .59

    0.12

    0.22

    0.07

    0.08

    0.20

    0.42

    0.18

    0.09

    C

    0.00

    0.28

    0.00

    0.00

    0.00

    0.00

    0.45

    0.12

    0.23

    0.40

    0.190

    .23

    0.08

    0.09

    0.16

    0.19

    0.40

    0.46

    0.07

    0.22

    Note:Allfiguresareroundedtotw

    odecimalplaces.

  • 7/30/2019 Contractor Selection AHP

    11/12

    1031Contractor selection using analytic network process

    Table3

    Thelimitmatrix(lo

    calprioritiesformajorcomponents)

    G

    oal

    Selectioncrite

    ria

    Selectionsub-criteria

    F.C.

    P.P.

    P.E.

    R.

    T.P.

    F.C.

    P.P.

    P.E.

    R.

    C.W.

    C.R.S.P.

    F.S.F.R.C.C.C.O.

    D.

    A.Q.

    S.C.

    T.C.

    E.A.

    P.R.H.R.

    Selection

    T.P.0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.250.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    0.25

    criteria

    F.C.0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.190.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    0.19

    P.P.0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.140.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    0.14

    P.E.0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.100.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    R.

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.110.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    C.W.0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.070.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    C.R.0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.070.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    S.P.0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.070.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    Selection

    F.C.F.S.0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.900.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.90

    0.05

    sub-criteria

    F.R.0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.100.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.10

    0.01

    P.P.C.C.0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.710.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.71

    0.03

    C.O.0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.110.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.01

    D.

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.110.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.01

    A.Q.0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.070.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.07

    0.00

    P.E.S.C.0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.480.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.48

    0.02

    T.C.0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.410.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.41

    0.01

    E.A.0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.110.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.11

    0.00

    R.

    P.R.0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.500.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.02

    H.R.0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.500.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.50

    0.02

    Contractor

    A

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.470.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    0.47

    candidates

    B

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.270.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    0.27

    C

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.260.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    0.26

    Notes:(1)Eachcolumnisthesam

    e.(2)Allfiguresareroundedtotwodecimalplaces.

  • 7/30/2019 Contractor Selection AHP

    12/12

    1032 Cheng and Li

    decomposing a complex problem to a manageable

    network or hierarchical structure, eliciting accurate

    rating by employing pair-wise comparison and consis-

    tency measure, and obtaining overall priority vector by

    dependent and/or interdependent matrix computations.

    Conclusions

    ANP extends the function of AHP and is a viable

    method for multi-criteria decision problems that involve

    interdependent relationships. In order to highlight the

    possible difference between the use of AHP and ANP,the results obtained from both supermatrix and limit

    matrix are compared. The mathematics performed in

    this research may not be familiar to every reader. Yet,

    Saaty is now developing a software tool for conducting

    ANP. Once the software tool is available for sale, a

    much faster growing use of ANP can be anticipated.

    Acknowledgement

    This paper was financially supported by The Hong

    Kong Polytechnic University under grant number

    G-YW72.

    References

    Alarcon, L.F. and Mourgues, C. (2002) Performance model-

    ling for contractor selection. Journal of Management in

    Engineering, 18(2), 5260.

    Cheng, E.W.L. and Li, H. (2001) Analytic hierarchy process:

    an approach to determine measures for business perfor-

    mance.Measuring Business Excellence, 5(3), 306.

    Cheng, E.W.L. and Li, H. (2002) Construction partnering

    process and associated critical success factors: a quantitative

    investigation. Journal of Management in Engineering, 18(4),

    194202.Fong, S.P. and Choi, S.K. (2000) Final contractor selection

    using the analytical hierarchy process. Construction Manage-

    ment and Economics, 18, 54757.

    Hatush, Z. (1996) Contractor selection: using multiattribute

    utility theory, unpublished thesis, Department of Surveying,

    University of Salford, Salford.

    Hatush, Z. and Skitmore, M. (1997) Criteria for contractor

    selection. Construction Management and Economics, 15,

    1938.

    Holt, G.D. (1997) Classifying construction contractors: a

    case study using cluster analysis. Building Research and

    Information, 25(6), 37482.

    Holt, G.D. (1998) Which contractor selection methodology?

    International Journal of Project Management, 16(3), 15364.

    Holt, G.D., Olomolaiye, P.O. and Harris, F.C. (1994)

    Evaluating prequalification criteria in contractor selection.

    Building and Environment, 29(4), 43748.Holt, G.D., Olomolaiye, P.O. and Harris, F.C. (1995)

    A review of contractor selection practice in the U.K.

    construction industry. Building and Environment, 30(4),

    55361.

    Jaselskis, E. and Russell, J. (1990) Risk analysis approach

    to selection of contractor evaluation method. Journal of

    Construction Engineering and Management, 118, 41723.

    Mahdi, I.M., Riley, M.J., Fereig, S.M. and Alex, A.P.

    (2002) A multi-criteria approach to contractor selection.

    Engineering, Construction and Architectural Management,

    9(1), 2937.

    Meade, L. and Sarkis, J. (1998) Strategic analysis of logistics

    and supply chain management systems using the analyticnetwork process. Transportation Research Part E: Logistics

    and Transportation Review, 34(3), 20115.

    Meade, L. and Sarkis, J. (1999) Analyzing organizational

    project alternatives for agile manufacturing processes:

    an analytic network approach. International Journal of

    Production Research, 37(2), 24161.

    Russell, J.S. and Skibniewski, M.J. (1988) Decision criteria

    in contractor prequalification. Journal of Management in

    Engineering, 4(2), 14864.

    Russell, J.S., Hancher, D.E. and Skibniewski, M.J. (1992)

    Contractor prequalification data for construction owners.

    Construction Management and Economics, 10, 11729.

    Saaty, T.L. (1980) The Analytic Hierarchy Process, McGraw-

    Hill, New York.Saaty, T.L. (1994) How to make a decision: the analytic

    hierarchy process. Interfaces, 24(6), 1943.

    Saaty, T.L. (1996) Decision Making with Dependence and

    Feedback: The Analytic Network Process, RWS Publications,

    Pittsburgh, PA.

    Samuelson, N.M. and Levitt, R.E. (1982) Owners guidelines

    for selecting safe contractors. Journal of the Construction

    Division, 108(CO4), 61723.

    Sarkis, J. (1999) A methodological framework for evaluating

    environmentally conscious manufacturing programs.

    Computers & Industrial Engineering, 36, 793810.

    Sarkis, J. and Sundarraj, R.P. (2002) Hub location at

    Digital Equipment Corporation: a comprehensive analysisof qualitative and quantitative factors. European Journal of

    Operational Research, 137, 33647.

    Valentine, R. (1995) Effective Contract Administration: For

    Road, Bridge and General Civil Engineering Works, Ecat

    Publications, Tuscon, AZ, pp. 131.

    Wong, C.H., Holt, G.D. and Cooper, P.A. (2000) Lowest

    price or value? Investigation of UK construction clients

    tender selection process. Construction Management and

    Economics, 18, 76774.

    Table 4 Comparing the results from ANP and AHP

    Candidate ANP AHP

    A 0.473 0.262

    B 0.271 0.448

    C 0.255 0.290