contracting overview things needed in a contract what’s being agreed to? when changes are needed...
TRANSCRIPT
Contracting Overview
• Things needed in a contract
• What’s being agreed to?• When changes are needed• Followup / status reviews
(And why!)
Program Specific
• Follow program rules• Who’s eligible?• Limitations?• What form to use?• Contract length?
• Some things are universal
Contract ComponentsGM 120 404.45
• Contract form with signatures• Special provisions and supplements,
as needed• Plan/Schedule of Operations• Plan maps• Explanation of violations and
procedures to be followed.
Signatures
• Program participant(s)• SCIMS (they are who they say they are!)• Evidence of Authority for Entities• Power of Attorney (if applicable)
• NRCS
• Legally binding
Participant agrees to:
• Participate in program for specified term
• Implement the conservation plan
• Comply with terms & conditions in contract, appendix, addenda
• Pay liquidated damages as per appendix, if applicable
GM 120 404.42
NRCS agrees to:
• Establish cost share rate• Provide authorized technical
assistance• Make payment
• When work passes checkout• And participant furnishes certifications &
itemized statements of costsGM 120 404.42
Agreed-to Items
• Work to be done• Participant is responsible• Measurable components• Government money to be paid• Follow the Plan: what & when
• Operation and Maintenance for the program life of the practice
GM 180 Part 500.11
Why Measurable Components?
• Clearly identifies what’s being done• Can adjust quantities (estimated vs
designed) • Can tell if it’s done & ready for payment• Can compare billed items to contract for
quality assurance
• Keeps us out of trouble!
Streamline FO operations
Cost Share Definitions
=Actual cost not to exceed the average cost
=Actual cost not to exceed a specified maximum cost
=Average cost (AC times % cost share equals producer payment)
=Flat rate (no percentage applied)
AA
AM
AC
FR
GM 120 404.30
Explain the money part
Example: 60% cost share on an acre of waterway
If the cost list says:
Earthwork ACRE $1800 AM
…then the participant will get 60% of what it cost to build the practice ONLY IF the cost to build was less than or equal to $1800!
Overbuilding
• NRCS pays on what was designed.• Least cost alternative to achieve NRCS standards on
the resource concerns.
• Additional costs borne by the participant
EQIP Manual 515.101g
ProTracts can help:
• Checks program rules• Fills in contract terms• Puts electronic signatures in the
right place
Spending Adjustment?
• Minor changes to quantities • Money is available in the contract• No formal modification procedure is
required
• See specific program manual for more details
GM 120 404.50
It’s OK to do a modification
• Substituting, adding, or deleting a practice
• Cost overruns (not enough money budgeted in the contract)
• Scheduling changes• Changing participant(s) or land• Adding TSP $$• Repairing a failure
GM 120 404.50
Following up
• Make sure there are no violations of the contract
• Determine the need for contract modification