contract strategy for midland bridge
DESCRIPTION
Various contract strategy in use in UKTRANSCRIPT
![Page 1: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/1.jpg)
Contract Strategty for Midland Bridge
By
Nyasha GaziVandhana Lakshmanaperumalsamy
Cengiz MirapHamad Alhasan
Yuzhou ChenAlhassan Saaka
![Page 2: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/2.jpg)
1.1 Primary Objectives
1. Client Objectives
Primary Objectives
QualityPublic
comfort
Safety
![Page 3: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/3.jpg)
1.2 Secondary Objectives
1. Client Objectives
Secondary Objectives
Use oflocal labour
(non-specialist)
Client involvement
Environmental protection
![Page 4: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/4.jpg)
2.1 Work Packages
2. Work packages
Work Packages
Construction of temporary steel structures
Demolition
Jacking
Stressing
![Page 5: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/5.jpg)
2.2 Sequence of Works
2. Work packagesSite Visit
Design of jacks from contractor
Temporary Work
Widening of existing pilecap
Extending the piers
Jacking of deck
Temporary ramps
Install new tendons
Stressing of tendons & pier demolishing works to be
done simultaneously
Constructing new hearting to the 2 main piers
Jack down the deck – remove the jacks and
temporary ramps
Remove falsework
Test
![Page 6: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/6.jpg)
3.1 Organisation roles
3. Contract strategies
![Page 7: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/7.jpg)
3.2 Payment methods
3. Contract strategies
Specialist Contract
Target cost with Activity schedule
Non - specialist Contract
Target cost with Bill of Quantities
![Page 8: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/8.jpg)
3.3 Tendering
3. Contract strategies
Specialist Contract
Tendering stage 1
Tendering stage 2
Single-stage tendering
Non - specialist Contract
![Page 9: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/9.jpg)
4. Risk Assessment
High risks
Damage to deck
Failure of jacking system
Price changes of materials
Medium risksDisruption to
motorway traffic
Low risks
Failure of falsework
Contamination of river
Flood risks
![Page 10: Contract Strategy for Midland Bridge](https://reader036.vdocuments.us/reader036/viewer/2022082822/5695d5561a28ab9b02a4f8c7/html5/thumbnails/10.jpg)
Thank you!