contract strategy for construction proje

101
CONTRACT STRATEGY FOR CONSTRUCTION PROJECTS A dissertation submitted to The University of Manchester for the degree of MSc Construction Project Management In the Faculty of Engineering and Physical Sciences 2012 UNMESH DHANUSHKODI SCHOOL OF MECHANICAL, AEROSPACE AND CIVIL ENGINEERING (MACE)

Upload: payel-pal

Post on 09-Feb-2016

43 views

Category:

Documents


1 download

DESCRIPTION

contract

TRANSCRIPT

Page 1: Contract Strategy for Construction Proje

CONTRACT STRATEGY FOR CONSTRUCTION

PROJECTS

A dissertation submitted to The University of Manchester for

the degree of

MSc Construction Project Management

In the Faculty of Engineering and Physical Sciences

2012

UNMESH DHANUSHKODI

SCHOOL OF MECHANICAL, AEROSPACE AND CIVIL

ENGINEERING

(MACE)

Page 2: Contract Strategy for Construction Proje

2

TABLE OF CONTENT

TABLE OF CONTENT ...................................................................................................................... 2

LIST OF FIGURES ............................................................................................................................ 5

LIST OF TABLES .............................................................................................................................. 6

ABSTRACT ...................................................................................................................................... 7

DECLARATION ............................................................................................................................... 8

INTELLECTUAL PROPERTY STATEMENT......................................................................................... 9

ACKNOWLEDGEMENTS ............................................................................................................... 10

1. INTRODUCTION ....................................................................................................................... 11

1.1OVERVIEW .......................................................................................................................... 11

1.2 AIM & OBJECTIVES ............................................................................................................ 12

1.3 SCOPE AND LIMITATIONS ................................................................................................. 12

1.4 DEFINITIONS ...................................................................................................................... 13

1.5 GUIDE TO CONTENTS ........................................................................................................ 14

2. RESEARCH METHODOLOGIES.................................................................................................. 16

2.1 INTRODUCTION ................................................................................................................. 16

2.2 KEY WORDS ....................................................................................................................... 16

2.3 ONLINE SEARCH PROCEDURE ........................................................................................... 16

2.4 RESEARCH FOR CASE STUDY ............................................................................................. 18

2.5 SUMMARY ......................................................................................................................... 18

3. LITERATURE REVIEW ............................................................................................................... 19

3.1 INTRODUCTION ................................................................................................................. 19

3.2 DEFINITONS OF CONTRACT STRATEGY ............................................................................. 19

3.3 IMPORTANCE OF CONTRACT STRATEGY ........................................................................... 20

3.4 ROLE OF THE CLIENT ......................................................................................................... 26

3.5 CONTRACT STRATEGY AND PROJECT MANAGEMENT ...................................................... 28

3.6 CONTRACT STRATEGY AND RISK MANAGEMENT ............................................................. 30

Page 3: Contract Strategy for Construction Proje

3

3.7 SUMMARY ......................................................................................................................... 33

4. BACK GROUND TO CONTRACT STRATEGY: EXISTING PRACTICE ............................................. 34

4.1 INTRODUCTION ................................................................................................................. 34

4.2 PROCUREMENT ................................................................................................................. 34

4.3 PROCUREMENT SELECTION CRITERIA ............................................................................... 34

4.4 TYPES OF PROCUREMENT METHODS ............................................................................... 35

4.6 SUMMARY ......................................................................................................................... 43

5. REVIEWS OF CONDITIONS OF CONTRACT ............................................................................... 44

5.1 INTRODUCTION ................................................................................................................. 44

5.2 STANDARD FORMS OF CONTRACT .................................................................................... 44

5.3 TRADITIONAL CONTRACT .................................................................................................. 45

5.4 NEED FOR ALTERNATIVE CONTRACTING APPROACHES ................................................... 46

5.4.1 Reducing Construction Time ...................................................................................... 46

5.4.2 Reducing Construction Cost ....................................................................................... 46

5.4.3 Applying Improved Technology and Techniques ....................................................... 47

5.4.4 Deploying Contractor Innovation ............................................................................... 47

5.4.5 Reducing Impacts on the Public ................................................................................. 47

5.5 DIFFERENT FORMS OF CONTRACT .................................................................................... 47

5.5.1 FIDIC ........................................................................................................................... 47

5.5.2 GENERAL CONDITIONS ............................................................................................... 51

5.5.2 JCT .............................................................................................................................. 54

5.5.3NEC .............................................................................................................................. 56

5.6 SUMMARY ......................................................................................................................... 62

6. CASE STUDIES .......................................................................................................................... 63

6.1 INTRODUCTION ................................................................................................................. 63

6.2 CASE STUDY – 1: Gateshead Millennium Bridge—an eye-opener for engineering .......... 63

6.3 CASE STUDY – 2: Hungerford Bridge ................................................................................. 66

Page 4: Contract Strategy for Construction Proje

4

6.4 CASE STUDY – 3: Delivering of London Olympic Park 2012 .............................................. 69

6.5 CASE STUDY - 4: The Montreal Olympic Complex ............................................................ 74

6.6 CASE STUDY – 5: Construction of an Industrial Building .................................................. 77

6.6.1 EXERCISE .................................................................................................................... 77

6.6.2 Changes in contract price using Traditional method ................................................. 80

6.6.3 General Lessons ......................................................................................................... 81

6.6.4 Evaluation of BOQ with the separation of method-related charges ......................... 81

6.6.5 Evaluation using NEC forms of contract..................................................................... 82

6.7 COMPARISON OF TRADITIONAL CONTRACTS WITH NEC ................................................. 83

6.8 SUMMARY ......................................................................................................................... 85

7. GENERAL DISCUSSIONS ........................................................................................................... 86

7.1 INTRODUCTION ................................................................................................................. 86

7.2 LESSONS LEARNT ............................................................................................................... 86

7.3 RECOMMENDATIONS FOR THE MANAGEMENT OF FUTURE PROJECTS ........................... 90

7.3.1 High risk factors involved in future complex projects ............................................... 91

7.4 SUMMARY ......................................................................................................................... 91

8. CONCLUSIONS ......................................................................................................................... 92

REFERENCE .................................................................................................................................. 95

Final word count: 2020

Page 5: Contract Strategy for Construction Proje

5

LIST OF FIGURES

Figure 1: Organisational choices for project and construction management

Figure 2: Contractual procedure involved in Traditional Procurement Method

Figure 3: Contractual procedure involved in Design and Built Procurement Method

Figure 4: Contractual procedure involved in Management Contracting

Procurement Method

Figure 5: Nature of various Payment Terms

Figure 6: Flow chart for mechanism to be follwed while a Compensation Event

Figure 7: Gateshead Millennium Bridge

Figure 8: Crane used for Gateshead Millennium Bridge

Figure 9: Before the construction of Hungerford Bridge

Figure 10: The new Hungerford Bridge

Figure 11: Graphical Representation of key factors involved in Management of

London Olympic Park

Figure 12: Pie chart representing the distribution of Management Authority

involved in London Olympic Park

Figure 13: A complete view of London Olympic Park 2012

Figure 14: A complete view of The Montreal Olympic Complex 1976

Page 6: Contract Strategy for Construction Proje

6

LIST OF TABLES

Table 1: List of data source used for search strategy

Table 2: Main features of the FIDIC “Red”, “Yellow” and “Silver” books

Table 3: Various NEC options along with their Incentives, Financial and other Risks

Table 4: Various NEC options used in London Olympic Park along with their Usage

and Rationale

Table 5: A Comparison of physical Condition of clauses in Traditional and NEC

form of Contract

Page 7: Contract Strategy for Construction Proje

7

ABSTRACT

There are many numbers of projects taking place around the world and contracts

are signed for each project comprising of major firms in action. The client parties

shall quote their title objective in the contract and expect the contractor to abide

by their agreement for mutual benefits. This shows the importance of contract

strategy. This research is aimed at exploring the different types of contract

strategy in construction industry to determine their time of application. A

comparison of Traditional method of contracting with the modern form of

contracting will be executed as a part of research.

The research will be carried out with the help of several journal articles and books

by major contract and project management authors. The author’s intention is to

first enlighten the importance of contract strategy to the readers by reviewing

different authors view on role of various project participants and project

management in contracts. The second part of this research explores the different

types of contracts and case studies are conducted based on them which reflect the

different trends of contract options considered over a period of time. The later

parts of the research consist of a comparison between the Traditional form and

NEC form of contracts with the concept derived from project records.

It is concluded the NEC contracts prove to be more efficient when it comes to

complex and high risk projects and client’s role plays a major part in the project

success. It is considered that the findings will be of interest to project managers for

larger and complex engineering and construction projects in any country.

Page 8: Contract Strategy for Construction Proje

8

DECLARATION

No portion of the work referred to in the dissertation has been submitted in

support of an application for another degree or qualification of this or any other

university or other institute of learning.

Page 9: Contract Strategy for Construction Proje

9

INTELLECTUAL PROPERTY STATEMENT

i. The author of this dissertation (including any appendices and/or schedules to

this dissertation) owns certain copyright or related rights in it (the “Copyright”)

and s/he has given The University of Manchester certain rights to use such

Copyright, including for administrative purposes.

ii. Copies of this dissertation, either in full or in extracts and whether in hard or

electronic copy, may be made only in accordance with the Copyright, Designs and

Patents Act 1988 (as amended) and regulations issued under it or, where

appropriate, in accordance with licensing agreements which the University has

entered into. This page must form part of any such copies made.

iii. The ownership of certain Copyright, patents, designs, trademarks and other

intellectual property (the “Intellectual Property”) and any reproductions of

copyright works in the dissertation, for example graphs

and tables (“Reproductions”), which may be described in this dissertation, may not

be owned by the author and may be owned by third parties. Such Intellectual

Property and Reproductions cannot and must not be made available for use

without the prior written permission of the owner(s) of the relevant Intellectual

Property and/or Reproductions.

iv. Further information on the conditions under which disclosure, publication and

commercialisation of this dissertation, the Copyright and any Intellectual Property

and/or Reproductions described in it may take place is available in the University

IP Policy (see http://documents.manchester.ac.uk/display.aspx?DocID=487), in

any relevant Dissertation restriction declarations deposited in the University

Library, The University Library’s regulations (see

http://www.manchester.ac.uk/library/aboutus/regulations) and in The

University’s Guidance for the Presentation of Dissertations.

Page 10: Contract Strategy for Construction Proje

10

ACKNOWLEDGEMENTS

I consider my obligation to acknowledge and express my gratitude to my

supervisor Mr. Peter Thompson for his guidance, assistance and invaluable

support throughout the dissertation.

I would like to thank the University of Manchester for providing me this

opportunity for submitting this research by providing me essential resources.

I would also like to thank my family and all my friends who were helpful in

completing this dissertation by motivating me and supporting me whenever I

needed them.

Page 11: Contract Strategy for Construction Proje

11

1. INTRODUCTION

1.1 OVERVIEW

The recent development around us shows us that the world is fast growing. For

these developments to take place it requires more than just one field in operation.

For instance, in a construction process there are so many groups of entrepreneurs

involved like suppliers, buyers and builders. The relationships among these parties

are maintained by forming contract. A contract is a legal agreement made between

two or more parties for a delivery of certain services in return for money or any

other value. In past, promises were made in place of contract where in several

disputes arose; due to which the legal entities are made in modern times. The

study taken into consideration here belongs to the construction industry sector

however there may also be certain sections relating to other industrial sectors.

This shall be due to the fact that the latest trend in carrying out any project entails

integration of various engineering sectors.

In a civil engineering construction contracts the Contractor obligates to carry out

works of construction and other ancillary obligations. Majority of the civil

engineering works are performed under the contract which requires the

Contractor to finish the work and the Client to pay for it. The main functions of a

contract are:

1) To specify the work to be done,

2) The amount to be paid,

3) To assign responsibility to the concerned parties to finish the work and

4) Decide who takes charge for the unexpected events if they occur.

Based on these, there are different types of contracts used in the construction

industry; this research is focussed to explore them.

Page 12: Contract Strategy for Construction Proje

12

1.2 AIM & OBJECTIVES

AIM

The aim of the research would be to investigate different types of contract strategy

in construction industry and factors that are considered for the use of appropriate

ones for the given project situations.

OBJECTIVES

To examine the concept of contract strategy.

To investigate the different contract strategies used in construction industries.

To interrogate the role of contract strategy in project management.

To examine the implications of contractual variations in construction

industries.

To compare and evaluate changes in a project by applying the Traditional

contract strategy with the new engineering contract systems.

To look into the merits and demerits of various contract procedures for the

given situation.

1.3 SCOPE AND LIMITATIONS

A contract is an agreement made between two or more parties with an intention of

executing a work such that the parties involved get agreed benefits. A proper

contract makes a good business sense and provides motivation to encourage high-

quality Contractor performance. In this research the author helps to develop and

implement an effective procurement strategy for a given situation. He proposes to

analyse the best practise process for the management of contracts and the supply

chain and its management techniques to achieve maximum value at minimum cost.

The comparing of the New Engineering Contract with the Traditional contracts are

focussed to help choosing the best type of contract and compensation terms which

results in both the Contractor and the Client satisfaction. The study will also be

examining the various risk management techniques involved in procurement or

contracting strategies.

This research is aimed at personnel at all levels who are responsible and involved

in the procurement process. This refers mainly to the Organisations or the Clients

Page 13: Contract Strategy for Construction Proje

13

who are on the verge of pursuing an engineering project and Contractors intending

to catch the Employer’s attention. The study will also be helpful to other parties

such as, project management representatives (employed by the Client) for signing

lucrative deals by examining the results.

The civil engineering contracts existing within a procurement and legal

environment may affect them in their interpretation and operation. The study may

not necessarily be effective to all the problems in contracting world. The research

work for this study is limited to a set of peer reviewed journal articles and

interpretation and conclusion will revolve around the paper works only. Due to the

time constraints no site works are done and no construction professionals are to

be approached.

1.4 DEFINITIONS

Project

A project is an investment of resources to produce goods and services. A project

can be any new structure, plant, process, system or software, large or small, or

replacement, refurbishing, renewal or removal of an existing one. It is a one-off

investment.

Programme

A programme of projects means a set of related projects. A project programme

means a list of activities for a project showing the dates for starting and finishing

them. It is also called a Schedule.

Project Management

Project management is the planning, organisation, monitoring, and control of all

aspects of a project and the motivation of all involved to achieve project objectives

safely and within a defined time, cost and performance. (Association of Project

Managers, 1995)

Project Manager

The (NEC, 2005) states “the Project Manager is appointed by the Employer, either

from his own staff or from outside. His role within the ECC is to manage the

Page 14: Contract Strategy for Construction Proje

14

contract for the Employer with the intention of achieving the Employer’s

objectives for the completed project”.

The Client and Contractor

The Client is the natural or legal person/individual who carries out a construction

project for him or another person/organisation that took the initiative of the

construction.

The Contractor is the one responsible for day-to-day oversight of

a construction site, management of trades and vendors, and communication of

information to involved parties throughout the course of a construction project.

Contract Strategy

Contract terms should be designed to motivate all parties to try to achieve the

objectives of the project and to provide a basis for project management.

Cost and Price

Cost is “the cost directly attributable to completion of an element of work,

including direct overheads, for example – supervision” (Smith, 1995).

Smith (1995) defines Price as “the charge for completing an element of work; it is

the cost plus allowances for general overheads, insurances, taxes, finance (i.e.

interest charges) and profit”.

Conditions of contract

The conditions of contract are defined as “sets of terms which state the general

responsibilities, risks and liabilities of the parties to the contract and establish

procedures between them, including terms of payment” (Smith, 1995). The

structure of each forms of contracts along with their applications are discussed.

1.5 GUIDE TO CONTENTS

This research further includes seven chapters and each chapter is briefly described

below.

Chapter 2 reveals the methods, procedures and processes that were used to

accomplish the aims and objectives of this research. It showcases the methodology

for the selection of resources and the reason behind the author’s choice. The data

Page 15: Contract Strategy for Construction Proje

15

collection methods applied by the author for selection of the resources are

mentioned.

Chapter 3 reviews the importance of contract strategy into the construction

industry. It explains the need for introducing the project management into the

contract strategies. The roles played by the Client and Project Manager are

depicted and their impacts are analysed.

Chapter 4 provides an outline of the various procurement strategies used in the

construction industry. It offers background information of the Client’s choice of

procurement for various situations and the terms of payment involved in the

contract.

Chapter 5 describes the different forms of contracts employed in general industrial

purposes. It explains about the standard conditions of contract and their

applications towards the construction industry. The forms of contracts such as

Traditional, FIDIC, JCT and NEC are explained in detail in this chapter.

Chapter 6 analyses the different projects which took place in recent times for

drawing out a comparison between the forms of contracts. The main differences

between the Traditional form of contracts and NEC form of contracts are compared

and contrasted stating the most effective one of them for the future use.

Chapter 7 focuses on the author’s comments about this entire research. It

comprises of two parts the first one being the findings throughout this dissertation

emphasising the trends being followed by the Clients/Contractors along with their

scope and limitations. The second part consists of the author’s recommendations

for the future use and applicability of project management in construction

industry.

Chapter 8 concludes the research by listing the objectives met by the author and

other key findings achieved en route to meeting the objectives.

Page 16: Contract Strategy for Construction Proje

16

2. RESEARCH METHODOLOGIES

2.1 INTRODUCTION

This chapter deals with the selection criteria for the various articles present in this

dissertation. This section describes various procedures followed and the selection

criteria of the author in choosing the sources. The different key words used along

with their application in online search engines are listed in this chapter.

The search was conducted to extract the study materials used for the topic

Contract Strategy for Construction Projects in the course Management of Projects.

There are several journal articles selected for the purpose of conducting this

research. The author's interest in the field of study played a major role in the

selection. The search strategies applied to find the relevant articles are given

below.

2.2 KEY WORDS

The search was initiated after consulting with the dissertation supervisor. The

supervisor assisted in outlining the key concepts for the topic. Further with the

help of the topic brief manual, the key words for the study were drawn out. The

following are the Key-Words around which the search was based.

Procurement strategies used in construction industries

Evaluation and management of contacts

Conditions of contract

Planning and scheduling in project management

Contracting and management techniques used in construction projects.

Forms of contract used in Construction Industry

Comparison of Traditional Contract with NEC

Role of Client and Project Manager in Contract strategies

2.3 ONLINE SEARCH PROCEDURE

With these Key-words as the basis of reference, the search was conducted in

various online search engines. The journal articles and thesis present in the

university library were also explored for discovering any related articles. The

Page 17: Contract Strategy for Construction Proje

17

following tools were useful in conducting the search and detecting the relevant

sources for the study.

Search Engines Journal Names

University of Manchester Library

Catalogue

Google Scholar

ScienceDirect

1

Internet Public Library

Virtual Learning Resource Centre

ERIC (Education Resources Information

Centre)

Directory of Open Access Journals

Google Scholar

Google Books

Peer Reviewed Open Access Journals

Open Access Journals Search Engine

Open Science Directory

Digital Librarian: Magazines and

Journals

Open Thesis

Construction Innovation

Construction Management & Economics

International Journal of Construction

Education and Research

Journal of Civil Engineering and

Construction Technology

Journal of Construction Engineering and

Management

Journal of Construction in Developing

Countries (JCDC)

Journal of Performance of Constructed

Facilities

New Civil Engineer International

Civil Engineering Innovation

Civil Engineering Practice

Construction Management & Economics

Engineering Construction and

Architectural Management

ICE Proceedings

ICE Proceedings: Engineering Divisions

ICE Selected Engineering Papers

International Journal on Recent Trends in

Engineering & Technology

Journal of the ICE

New Civil Engineer (NCE)

Proceedings of ICE - Civil Engineering

Table 1: List of data source used for search strategy

By accessing the above tools several papers were found in relation to the key-

words search applied. However the majority of sources selected were books

Page 18: Contract Strategy for Construction Proje

18

written by the project management theorists. The selected books and other articles

were produced to the supervisor and with his acceptance and guidance the

research was moved forward.

2.4 RESEARCH FOR CASE STUDY

There are five projects selected for the case study and they are chosen for

their magnum opus value of construction. The uniqueness of the project structures

also makes a stand out point in the selection of the respective source articles.

Although the projects taken into consideration belong to the construction sector,

there may also be certain sections relating to other industrial sectors. This is done

due to the fact that the latest trend in carrying out any project entails integration of

various engineering sectors. The case studies reflect the change in trend of the

contract strategies in a considerable period of time. Great efforts were made to

select the projects and acquire their sources. The selected Journals not only

emphasis about the contract strategies applied but they also consider several

project management aspects involved in the Project Life Cycle of constructing a

mega structure. All the projects reviewed in the articles are of massive value and

considered as most challenging projects in the world.

2.5 SUMMARY

The selection of resources used for carrying out this research was depicted in this

section. The list of different journal names and the methods applied to find the

related articles were explained. Finally the work was started with the aim of

learning important lessons in the field of project management by reviewing the

articles. The usage of sources acquired can be seen in the upcoming chapters.

Page 19: Contract Strategy for Construction Proje

19

3. LITERATURE REVIEW

3.1 INTRODUCTION

The importance of contract strategies will be reviewed in this chapter. The author

discusses about the contract strategy and their effective application in

construction field with the help of different author’s comments. This literature

review highlights the role Project Management can play in execution of contracts

3.2 DEFINITONS OF CONTRACT STRATEGY

A contract is a key component of a procurement system and it is an essential

element required between two parties collaborating for a work. A contract

impresses upon the parties the solemnity of the occasion. It requires the parties to

seriously consider the effects of performance and non-performance upon

themselves. Contract as defined by Veld & Peeters (1989) is “an agreement

between two parties, whereby one party commits itself to deliver goods, software

or services to a second party within a certain delivery time and for an agreed

price”. He defines ‘The Client’ as “The party ordering goods” and ‘Contractor’ as

“The party delivering goods”. Section 104(1) of the HOUSING GRANTS

CONSTRUCTION AND REGENERATION ACT 1996 PART II (2010) states that a

‘construction contract’ includes:

• The carrying out of construction operations

• Arranging for the carrying out of construction operations by others, whether

under a subcontract to him or otherwise

• providing his own labour, or the labour of others, for carrying out construction

operations.

The contracts used by the Client can be of different types and different strategies.

“Contract strategy is the main components of the process used to determine how

the project will be procured” (Wearne, 1995). He says that different contract

strategy must be applied for every project. The author feels that this definition is

vague in nature and does not fully outcast the nature of the contract strategy. For

enforcing a better strategy Cooke & Williams (2004) inferred that one must fully

understand what the contract strategy is, for no one can effectively plan and

control a construction project without fully understanding the cultures and

Page 20: Contract Strategy for Construction Proje

20

methodologies of the industry carrying out the work. There is a lot clearer

statement when compared to the above one stated by Perry (1985), who goes by

saying that: “The organisational and contractual policies which are chosen for the

execution of a specific project”. Though it can be considered as the better one when

compared with its predecessor the author still feels awkward to move forward

with the available concepts. Both the definitions do not adequately explain the

features of the contract strategies. However there is a definition provided by

Procurement Guide: Procurement and contract strategies (2003) in Procurement

and contract strategies achieving excellence in construction procurement guide.

The definition states that “The contract strategy determines the level of integration

of design, construction and on-going maintenance for a given project and should

support the main project objectives in terms of risk allocation, delivery, and

incentivisation and so on”. The author feels this is by far the best definition

available about the contract strategy. This version of the definition proves to be

more descriptive, the organisation structure provided in the book explains well

about the strategy adopted and its significance with the level of integration of

design and construction for a given project. Accessing a good definition for a

contract strategy is necessary since it would help in developing and implementing

a highly effective procurement strategy and plan for an organisation which would

reduce overall cost of purchasing along with a better supply chain management.

3.3 IMPORTANCE OF CONTRACT STRATEGY

Selecting an appropriate contract strategy is as much important as selecting other

major characteristics of project. A contract strategy is important as it impacts in

the progress of the project through a right direction, when a good strategy is

applied it improves the supply management in order to deliver maximum value at

minimum cost, and how to develop and implement a best-practice process for the

management of contracts. Bower (2003) has stated his view on the importance of

contract strategy as “Contract strategy has a major impact on the timescale and

ultimate cost of the project”. He further emphasizes the negative effects on the

project outcomes over an inappropriate selection of a contract strategy for a

project. Bower (2003) says that when a wrong contract strategy is selected it may

Page 21: Contract Strategy for Construction Proje

21

cause over budget of project and delay in completion time. Perry (1985) in his

study outlines the key decisions for contract strategy:

a) The project characteristics

b) Organisational structure for design and construction

c) Types of contracts

d) Tendering process including conditions of contract, contract selection and

tender analysis.

These are key decisions the Client must consider while selecting a contract

strategy for carrying out a project, the above points highlight the areas which build

the contract strategy and are regarded as a subsystem of a contract strategy. Perry

(1985) has also given his views on the nature of an effective contract strategy. He

quotes “Optimal contract strategy will be one which displays a consistent

integration of the selection within each of these strategic areas”. However he also

reacts to his own quotes that the optimal strategy will not be truly known until the

project is fully finished. And the best Contractor strategy need not necessarily be

the most feasible one.

The author suggests that the Client must thoroughly enquire about the various

choices available before zeroing on a single contract strategy. The contract strategy

chosen must be able to fulfil the primary objectives of the project. The Client sets

the primary objectives of a project along with Contractor and other parties. In

accordance to the Client’s dilemma of setting the objectives there are different

choices available, as Bower (2003) traces “Due to the diversity of both

construction and the Client’s requirements there are different types of strategies

available and no single uniform approach to contractual arrangements shall be

advocated”. With so many options available the Client certainly has an upper hand

in selecting one of them but it isn’t an easy job as it seems to be. Within those

several options the Contractor has to select out a single contract which meets the

necessity of the Contractor. While deriving information from the past projects it

must be noted that the contracts used in those projects may not suit the current

needs. If needed the Client must be bold enough to amend the contracts as per the

requirements for effective project outcomes.

Page 22: Contract Strategy for Construction Proje

22

Smith (1995) outlines some main topics to be taken into consideration for setting

up a contracting strategy. They are:

a) Project objectives

b) Organisation system for design and implementation

c) Risk allocation

d) Terms of payment

e) The conditions of contract and

f) Tendering procedure

Haswell & De Silva (1989) has stated in his book that it is not well appreciated by

many people (the Clients) the importance for the correct type of contract to be

selected and one is always in demand for obtaining value of money. Opposing the

Client’s mentality from Haswell & De Silva (1989) book and in favour of Smith

(1995), Aboushiwa & Bower (2000) has stressed the importance of contract

strategy and describes it as an amalgam of activities that runs from defining the

Client’s:

a) Project objectives

b) Priorities

c) Responsibilities

d) Organisational structure

e) Types of contract

f) Conditions of contract

g) Contractor selection

h) Tender procedures, and

i) Risk allocations to the selection of most appropriate contract strategy.

The author reiterates the importance of the contract strategy and its process which

is carried out in order to reach the required end products. “A contract strategy

should be established at an early stage to meet the cost, programme and quality

objectives of a particular project” Aboushiwa & Bower (2000). He urges the

introduction of contract strategy as early as possible into the project for its

betterment. The author supports this point by saying that the contract strategy is

the most important aspect of a project because it forms the foundation on which

Page 23: Contract Strategy for Construction Proje

23

everything else is built. Therefore earlier the contract strategy is decided and the

works are planned the better will be the project outcomes.

In order to select a correct procurement procedure Masterman (1992) suggests

the Clients must first understand that there is no standard solution among the

procurement systems and the construction projects vary so considerably that a

single procurement method does not suit for all projects. For making a decision

about selecting a contract strategy it is essential that the Client’s primary and

secondary objectives are analysed and these objectives are to be compared with

the characteristics of all available procurement methods and the most logical

method is to be chosen out of it. The author agrees with this point stating the

difficulty involved in the selection process. The selection must be carried out with

a substantial amount of attention. “It is evident that no unambiguous solution can

be found for each specific project each contract type should be tailored to the

specific requirements of the project” (Veld & Peeters, 1989). Not only the

procurement types are to be analysed but also the different conditions of contract

to be used must also be considered. This paper further investigates the different

types of contracting strategy used in construction industry.

Contract strategy is an important factor concerning the successfulness of a project.

However Venters (2005) expresses his view that nevertheless its importance, it

won’t be the sole dependent for the success of the project. He argues “Successful

project must also require a solid work scope commitment of a project team and a

realistic budget to support a successful project.” The author is not fully satisfied

with Venters (2005) comments as he feels the contract strategy is the foundation

for everything in a project. When an inappropriate strategy is chosen then the

whole project may fail and no solid work scope no project team and no budget can

be of any use. In the support of Venters (2005) another author named Langdon &

Rawlinson (2006) has cashed in his view that “It is the performance of the team

that is at the root of project success not the strategy per se”. The author is staying

firm in his decision that whatever it may be, contract strategy is the prime

necessity for a project and it’s above everything else for its success and outcomes.

In a research work carried out by Perry (1985) he revealed that ‘Decision taken

before the sanctions have the most significant impact’. It means that the decisions

Page 24: Contract Strategy for Construction Proje

24

which are made before the selection of contracts or even beginning the project are

the most significant ones which decide the flow of the project. These decisions

have their direct effects on the project outcomes and will encompass on the

procurement strategy that has to be chosen. For this purpose Aboushiwa & Bower

(2000) has advised on the meticulous effort to be taken by the Client on deciding

the parameters of the project. He quotes “It is evident that no unambiguous

solution can be found for each specific project; each contract type should be

tailored to the specific requirements of the project”. It is bizarre that, usually very

big things start with small beginnings; such is in this case where the least budget

allocated stage of the project makes most of the impacts on the outcomes of

project. Therefore each and everything needs to be put under scrutiny in these

phases because it may affect the clarity of project definitions and incomplete

tenders if something goes wrong. When these stages are disturbed they deeply

harm the project outcomes and result in over budget and delay in time.

Page 25: Contract Strategy for Construction Proje

25

Figure 1: Organisational choices for project and construction management

Source: Perry (1985)

Page 26: Contract Strategy for Construction Proje

26

3.4 ROLE OF THE CLIENT

The Client according to Rowlinon & Mcdermott (1999) can be regarded as the

sponsor of the building process. He is the one who initiates the building process

and appoints the team. The Client is the ultimate owner of a project and he is the

one gets affected by the results more than anyone. As Bower (2003) illustrates, the

Client has the highest responsibility of a project and he is the chief decision maker.

He must be careful on the things he is deciding. His responsibilities include:

a) Setting parameters of project

b) Provide finance

c) Make key decisions

d) Give approval and

e) Guidance

Langdon & Rawlinson (2006) has emphasised the role of the Client in selecting a

procurement strategy by saying that “The Clients should always devise their

strategy on the basis of their project priorities, management capabilities and the

extent of risk that they are prepared to accept”. He says the strategic decisions

made at the outset of the project are the most crucial so they must be critically

reviewed and examined by the Client.

The author appreciates the point made by Aboushiwa & Bower (2000) that the

improved understanding of the project by the Client and contract as well as better

contract strategy can lead to the reduction of unnecessary expenses. In recent

years most of the unnecessary expenses are caused by disputes and litigation. One

of the important points to be taken care by the Clients is the objectives. The Client

must be very specific and clear on his objectives i.e. what he needs. Giving

attention to this part can save the Client from many other troubles that are to come

in future such as variation because some contracts do not flexibly allow the Clients

to bring in variations. However there are some contracts which give rooms for

changes, the contracts must be selected wisely according to this. This dissertation

has researched on the variations in a project and the case study will be dealt later.

In order to convey what they require first the Clients must truly know what they

Page 27: Contract Strategy for Construction Proje

27

actually want. For this purpose the Clients must understand the contract strategy

that is the reason why the importance of contract was explained in the earlier part

of this dissertation.

The attitude of the Client towards a project is a matter of consideration. This

means the levels of involvement in the building and contracting process. For the

Clients with little or no experience, they shall wish to stay away from the internal

affairs of the project. For the Clients who are well aware of the work culture would

like to have a closer look at the construction process. The level of involvement

must be specified at the beginning of the contract. Next comes the funding of the

project, whether the project is going to be funded by private or public sector. The

funding shall also be in form of instalments or whole sum paid. This funding choice

will be considered while selecting the contract strategy. Depending upon the

Clients funding choice, liabilities during the crunch situations are decided

beforehand. For instance, in case of a cost overrun the contract strategy must

clearly specify the party responsible for it. All these details decide the costing

adjustments such as whether the incentives are required, will the Client reimburse

the Contractor for inflation or not.

The next factor that needs consideration is the risk. The type of contract and the

clauses used in the contract will be determined using the preferred choice of the

Client on the amount of risk he is willing to share with the Contractor. Taking into

account both the management and effect of risks occurring Bower (2003) has

stated it is essential that the risk should be shared between both the Client and

Contractor in a ‘realistic and equitable manner’. With the transfer of risks to the

Contractors, the Clients may lift their burden from exposing themselves to any

major threats. On the other hand contracts can charge money from the Client with

respect to the amount of risk they are facing. Hence the risk faced by the Clients

and Contractors are related to the preferred contract type and specified at the start

itself.

In a case study illustrated by Masterman (1992), he found that for majority of the

Clients it meant ‘certainty of completion date’ more important rather than

‘shortest design and construction period’. The author agrees with this point that

the trend has been changing and the Clients have started giving attention to time

rather than money. For the effective completion within time a type of contract

Page 28: Contract Strategy for Construction Proje

28

strategy can be selected where the construction process begins before the

completion of design stage. For an efficient working of the Contractor the Clients

may employ the services of incentives. The Client can also wish to control the

presence of the number of the sub-Contractors involved in the project.

Bennett & Flanagan (1983) researched about the various the Clients expectations

and produced a list of typical the Client requirements comprising of the following:

1) Functional building at the right price

2) Quality at the right price, i.e. value for money

3) Speed of construction

4) Balance between capital cost and long term ownership costs

5) Recognition of the risks and uncertainty associated with the project

6) Accountability in the public sector

7) Innovative design, high-technology building

8) Maximizing taxation benefits

9) Flexibility to change the design during construction

10) The building should reflect the Client’s activities and image

11) Minimizing future maintenance

12) Need to keep any existing buildings operational during building work

13) A desire to be actively involved in and kept informed about the project

throughout its life.

Just how the Client wishes that the Contractor he appoints must be an efficient

worker as well as good, the construction industry too will judge the performance

of the Client. Rowlinon & Mcdermott (1999) emphasises the role of the Client

impacts heavily on the Contractor’s mentality and this factor plays a major role in

the performance of the character. The Client will be judged on his behaviours such

as: prompt payment, fair and open tendering system, the experience and

knowledge to understand the implication of design changes and the ability to

provide prompt, timely decisions. Therefore it is clear that the role of the Client

plays a major factor in the success of the project.

3.5 CONTRACT STRATEGY AND PROJECT MANAGEMENT

The project management is very useful in the contract strategy. “The primary task

of project management is to deliver the maximum value in return for the resources

Page 29: Contract Strategy for Construction Proje

29

employed… delivering a project to an agreed quality, safety, time and cost” (Spring

& Wearne, 2003). The author accepts with this point and feels the significance of

project management in contract strategy. Perry (1985) talks about the importance

of positive effects the project management can bring into the contract strategies.

He concludes “Contract strategy is an integral part of the project management

decision making process because the development of a contract strategy for any

project should comprise a thorough assessment of the choices available for the

implementation and management of design and construction”. Both Spring &

Wearne (2003) and Perry (1985) mention the use of the Project Manager in the

entire project. They encourage the appointment of the Project Manager at the very

start of project. Spring & Wearne (2003) describes the role of the Project Manager

as the one who provides essential direction, discipline and drive to a project and

“The Project Manager with experience, enthusiasm and energy for the project is a

good starting point”.

In support of them Haswell & De Silva (1989) illustrates the roles of an engineer in

a project. The first role is to ensure the work for the Client that it is viable and the

Employer is given due value for money. Another equally important role is that he

must act impartial and be fair to each of two parties i.e. to the Employer and

Contractor. The use of the Project Manager will definitely assist the Client when it

comes to get the job done. It is becoming increasingly popular that most the Clients

starting major projects have started using one of their own staff or an independent

project management organisation to carry out the management of the works to

exercise more control over project (CIRIA, 1991). There are several case studies

researched and reviewed in the later sections of this dissertation where the

applications of project management in contracting strategies are extensively used.

Therefore it is suggested that the use of the Project Manager is advantageous not

only to the Client and Contractor but for project itself as it helps in deriving better

outcomes. Especially when a complex project is being undertaken the appointment

of the Project Manager in a project as soon as possible is suggested. Admitting to

this Bower (2003) has also derived some qualifications for the Project Manager. He

opts for an experienced Project Manager for the effective function of the project

team and completion of work in a time. He believes only experienced managers

could help in progress of the projects even during the crunch situations. A Project

Page 30: Contract Strategy for Construction Proje

30

Manager’s role would be to control the changes and execution of project on behalf

of the Client and execute authority if activities are to be effective. He concludes by

saying that the Project Manager’s role would be to control the changes and

execution of project on behalf of the Client and execute authority if activities are to

be effective.

3.6 CONTRACT STRATEGY AND RISK MANAGEMENT

All projects comprise of a substantial amount of risks. Risks are the most common

reason for projects to finish late and cost more than they should. When deciding

about the contract strategy for any project it must be done in a manner that it

effectively tackles the risks. “A prime function of contract is to allocate risk” (Smith,

1995). He further says that the identification and allocation of risk is a lengthy

process that will need to be carried on for multiple times for the best possible

results. The author has nothing to say against the above interpretations of risk. The

identification of risks has never been a piece of cake for the analysts. No matter

what, even after several examinations and processing the risks still remain in any

project and can never be gotten rid of. However there can be some arrangements

made to tackle these risks in the project. Even after much mitigation some of the

uncertainties may still remain even after a contract is chosen and this is where the

tender should have a contingency for it.

The risks in a project cannot be avoided completely but they can be dealt with

contracts. Haswell & De Silva (1989) points out that “Proper consideration of

contract risk and contract responsibility leads to better documentation of a civil

engineering contract”. What he means is that the risks must be considered in the

earlier stages of project itself. A well-considered contract on the various risks

involved will be a much better contract. Kalvet & Lember (2010) in his study have

stated that order to successfully implement an effective procurement the Clients

have to be capable of dealing with all possible process risks. This is illustrated by

the identification and management of:

1. Technology risks

2. Market risks

3. Financial

Page 31: Contract Strategy for Construction Proje

31

4. Organizational risks

5. Societal risks

6. Turbulence risks

Bower (2003) & Smith et al., (2006) list the following common questions to

consider while forming a contract:

a) Which party can best control events

b) Which party can best manage risks

c) Which party should carry the risks if it cannot be controlled

d) What is the cost of transferring the risk

If the Client thinks he does not want to bear risks then he can transfer his risk to

the Contractor as per his wish. “The Contractor can be motivated to control and

possibly reduce construction costs by making him bear some risk” (Olsen &

Osmundsen, 2005). However for trading the risks the Client needs to pay money to

the Contractor and the money may depend on the amount of risks being

transferred. He adds on "Trading off risk bearing and incentives, the buyer will

offer more incentive based compensation (less cost sharing) in cases where the

remaining project risk is low”. He reckons financial incentives aim to increase the

efficiency and effectiveness of projects by stimulating the motivation to work

harder and smarter in pursuit of such goals. All these details on incentives must be

put forth in the start of the project while framing the contract itself. Bower &

Merna (2002) has listed the main types of financial incentives used on

construction contracts:

1. Share of savings incentives, where cost savings are shared between the Client

and the Contractor based on an agreed formula;

2. Schedule incentives, where a premium is offered to the Contractor for the early

completion of the project; and

3. Technical performance bonuses for meeting performance targets, other than

cost and schedule. A performance bonus arrangement can be applied to a wide

range of performance areas such as quality and functionality.

Assaf & Al-Hejji (2006) feels that the common cause of risk by increasing the cost

and time of the project is ‘Change’. This point is totally agreeable by the author.

Page 32: Contract Strategy for Construction Proje

32

The variation in a project is the main cause for any effects in the project outcomes.

Variation could also be considered as a risk in a project and must be foreseen.

Enough arrangements must be made in the contract strategy to deal with the

variation like mentioned in the earlier part of this dissertation. The time period of

the change occurring in a project also impacts the project performance. “Changes

that occur near the end of the project are likely to be particularly disruptive and

expensive. Conversely, changes near the start of project, unless they affect the

contracted project specification and scope of work will probably cost only time in

design office” (Lock, 2007). Therefore it is assumed that sooner the changes occurs

lesser the disruption in the project performance.

Risk management is not a onetime process rather it should continue throughout

the Project Life Cycle (PLC). However the risk management has not been

considered seriously by many firms as Barnes (2006) mentions that risk

management is a new entrant to the project management techniques and it has yet

to achieve the penetration it should. The author too encourages the consideration

of risk management in construction industry and into contract strategy for

complex projects. The risks cannot be controlled by everyone and it is a wrong

approach to do so. Griffiths (1989) explains “The contract establishes the risk to be

carried by each party. The general principle suggested is that risks should be

carried by the party best able to either control the risk or estimate the risk”. He

illustrates the work of the Contractor must be intense to reduce the risk. He has

advised certain duties to Contractor for reducing the risks. His studies reveal that

the contract should:

Recognise areas of significant risks

Identify who is to carry the risk and to what extent and

Attempt to include adequate incentives to meet the Employer’s/main

Contractor’s objectives, preferably by attempting to align the objectives of the

Employer with those of the Contractor and sub-Contractor.

A risk free project is almost impossible but a project with a maximum number of

mitigated risks is always the better option. A contract strategy helping in effective

risk mitigation is a good one indeed. Therefore good projects are derived from the

Page 33: Contract Strategy for Construction Proje

33

good contract strategies implemented. Thus the necessities of better contract

strategies are effectively explained in this chapter.

3.7 SUMMARY

This literature review fully focussed on the views of various project management

expert authors about the contract strategies and role of different project

participants played in it. The need for Project Management and Risk Management

were also analysed in detail with several evidence suggesting their significance for

effective outcomes. The theories discussed in this section can be contrasted with

the procedures practiced in the industry in the coming chapters.

Page 34: Contract Strategy for Construction Proje

34

4. BACK GROUND TO CONTRACT STRATEGY: EXISTING PRACTICE

4.1 INTRODUCTION

This chapter describes the general contracting procedure practiced in the

construction industry. The different types of procurement methods and the

payment terms are explained in detail along with the place of their employability.

4.2 PROCUREMENT

Procurement is a process of obtaining goods and services. It is involved in every

industry for all sorts of acquisitions and there are many methods of procurement

available. The selection of an ideal procurement method according to the situation

is mandatory since the procurement methods play a major role in defining as well

as shaping contractual and work relationships between parties involved. In a MOP

– Commercial Contract Management: Lecture 1 by Mr Alan. F. Comish states that

the purpose of contract strategy by listing its purpose. He states that the

procurement types cover various aspects including (Comish, 2012):

How are the funds to be obtained

How is design to be carried out

How is construction/production to be arranged

Who is to have the managerial role to oversee or supervise the project

Who is to use the finished building/product

4.3 PROCUREMENT SELECTION CRITERIA

Before selecting an appropriate procurement method the Clients must analyse

their objectives of the project and based on their needs the procurement choice

might differ. JCT (2011) offers few external factors that may influence the choice of

procurement method adopted. The external factors that need to be taken into

consideration are:

a. The nature of the project

b. The scope of the works

c. Measure of control by the Client

d. Accountability

Page 35: Contract Strategy for Construction Proje

35

e. Appointment of the Contractor

f. Certainty of final cost

g. Start and completion times

h. Restrictions

i. Changes during construction

j. Assessment of risks

k. Building relationships with the supply chain

The choice of procurement should never be made on some arbitrary basis. The

Clients must always come to conclusion only after a careful analysis of the

situation.

4.4 TYPES OF PROCUREMENT METHODS

The different types of procurement procedures commonly used are explained

below:

1. Traditional

In the Traditional method, the Client appoints the Contractor to build to a defined

scope of works for a fixed price lump sum. And the responsibility for the design

and the project team is held by the Client.

According to Wearne (1989) the advantage of the Traditional system is that the

competition between the Contractors results in the offering of the lowest prices in

order to be selected by the Client and hence the Client only needs to pay the

tendered value. Another advantage scripted by Cooke & Williams (2004) is that the

design stage is completed before the tender stage ensuring the cost certainty for

the Client. He also appreciates the simplicity of this method.

One of the major disadvantages of this method as described by Wearne (1989) can

be the poor state of clarity existing between the design and construction team as

they are separately dealt. Masterman (1992) too has quoted some demerits on the

conventional techniques of the procurement. He blames them for their sequential,

fragmented and confrontational nature since they cause lengthy design and

construction periods along with poor communication residing in between the

Client and Contractor.

Page 36: Contract Strategy for Construction Proje

36

Figure 2: Contractual procedure involved in Traditional Procurement Method

Source: (Rashid et al., 2007)

2. Design and Build

Here the Contractor provides a completed building to an agreed cost and

programme. The Contractor is responsible for design and construction. There are

three types of design and build arrangements. ‘The Employer-led design’,

‘Contractor-led design’ and ‘other design and build options’. One of the merits of

this type of contract is the undivided responsibility for both design and

construction Wearne (1989). However he says design and build could also be a

potential threat when the Client does not clearly specify his needs, the Contractors

tend to build in their own way when not specified accurately. Nevertheless when

accurately specified, Masterman (1992) points out a merit in this method in the

form of cost savings. This method could be the cheapest of all methods. The

disadvantage is that the Client cannot exercise much of the control in the project.

Figure 3: Contractual procedure involved in Design and Built Procurement Method

Source: (Rashid et al., 2007)

Page 37: Contract Strategy for Construction Proje

37

3. Two Stage Tendering

As the name suggests there are two stages involved in this method, the first being

the appointment of the Contractor based on the tender and the second stage

involves the Contractor working with a project team for preparing designs and

cost estimates for each and every process of PLC. The Client then enters into a

contract on a fixed price basis after having a close look and proposing changes at

the various design strategies involved.

Wearne (1989) describes the potential benefits of a promoter employing this type

of procurement are cost certainty and time saving. This procurement type

encourages early engagement of the Contractor to the work. Masterman (1992)

too agrees with the view of Wearne (1989). However he draws out the ill-effects

on the two stages tendering as they may cause problems to the Client as the

Contractor may take advantage after the first stage since he comes to know that

the Client needs to carry on the work for second stage with the same Contractor

only.

4. Public Private Partnerships / Private Finance Initiative

This procedure is mainly used for public sector infrastructure projects where

private sector capacity and public resources are utilized. In this method, the

contract is given to a consortium for the building and operating. The capital is

derived from the taxes paid by the public for usage of property. The asset may or

may not be returned back at the end of the contract.

While opting for a Public Private Partnership Wearne (1989) asks the the Client; it

should be noted that the tendering process shall be expensive and requires

negotiation rather than competitive tendering. When compared to other

procurement methods the time from inception of the project to attaining a start on

site is substantially longer. Some general merits and demerits given by Cooke &

Williams (2004) are listed below:

Advantages:

a) Potential for high returns

b) Continuity of work

c) More control over the program

Page 38: Contract Strategy for Construction Proje

38

Dis-Advantages:

a) Very high bidding costs

b) High level of resource required

c) Complex and demanding

d) Tough contract terms

5. Management Contracting

a) Management Contracting

This is a fast track strategy where certain elements of construction process starts

even before the completion of the design. The management Contractor is given

charge of whole of the project including the design and build ability in return of a

fee. Here the management Contractor assigns work packages to the individual sub-

Contractors

b) Construction Management

This is the same as the Management Contracting except that here the work

packages and the individual sub-Contractors are assigned by the Client.

In this method there are maximum overlap between design and construction.

Cooke & Williams (2004) see’s this feature as a potential benefit. Other advantages

of the management contracts cited by Wearne (1989) are that the Contractor’s

project team is enriched with the contracting and construction expertise, the

service of which could be hired or fired. As per Cooke & Williams (2004) the

disadvantage these methods possess is the risk carrying threat for the Client; this

threat mainly applies to the construction management arrangement.

Page 39: Contract Strategy for Construction Proje

39

Figure 4: Contractual procedure involved in Management Contracting

Procurement Method

Source: (Rashid et al., 2007)

6. Cost – Reimbursable and Target- Cost Contracts

a) Cost-Reimbursable contract

It is a type of contract where the Contractor is paid on the basis of actual costs of

‘time and materials’ plus agreed amount to cover profits and overheads.

b) Target-cost contracts

These are the type of contracts where the Contractor is paid based upon its

established costs. To make sure that costs are not allowed to exceed a target, the

cost is fixed at the outset. The target is adjusted to take care of any changes and

other price risks allocated to the Employer under the initial terms of the contract.

There are also incentives provided to all parties involved such that costs and time

are controlled.

The advantages of the cost-reimbursable contracts can be seen well as Masterman

(1992) reclaims that when there is insufficient definition of work in tender, during

high inflation, when the project is extremely complex and unquantifiable amount

of risks involved. This method may prove to be effective at those times. He also

shares his views on the drawbacks involved with this method by stating the lack of

contractual commitment by the Contractor to the final cost and absence of

financial incentive to be used.

Page 40: Contract Strategy for Construction Proje

40

7. Framework Agreements

This is a form of a contractual agreement which allow suppliers to be brought

together with the relevant expertise and experience resulting in savings to both

the parties where a number of projects are involved. Cooke & Williams (2004)

explain the main difference between other contracts is that with framework

contract there will be no ‘main Contractor’. These agreements also cover different

forms of procurement including Design and Build, Traditional, etc.

4.5 TERMS OF PAYMENT

While planning a contract the promoter must consider the type of payment that

shall motivate the Contractor and fulfil the objectives of the Client. Wearne (1989)

says that when it comes to cost the Employer gets to choose between two types of

payment, either by price or by cost. The payment by price is preferred by most of

the promoters since it carries less risk on promoter and more on the Contractor

when compared to the actual cost. The different terms of payment shall be

discussed below.

1. Lump sum payment

In the lump sum contract the payment is settled at the end when all the works are

complete. Here the payment is of a single type and to a single Contractor who is

responsible for both design and construction as mentioned in the signing of

contract. Wearne (1989) says that this method proves advantageous to the Client

since the Contractor gets to take the risks of actual costs being greater than the

contract prices. The potential disadvantage is that it costs extra time and money to

the Client if needs to make any changes from the agreed plan.

Lump sum contract is a quite simple one provided only a single payment is due for

completion of performance. This method is usual in employing contracts for the

design and supply of mechanical, electrical and process plant.

2. Milestone and planned progress payment systems

The payment in this type is based on the milestones achieved by the Contractor i.e.,

the stages of the project finished. Wearne (1989) explains the advantages and

limitations of this method. The promoter gains in this by providing incentive to the

Page 41: Contract Strategy for Construction Proje

41

Contractor for proceeding with his work and also Contractor benefits by getting

paid sooner. The demerit in this method shall be the lack in clarity and resulting

disputes when the milestones are not defined properly at the start.

3. Bill of Quantities (BOQ)

In the bill of quantities the work agreed to be done under the contract are listed as

each item along with the quantity of material needed and quality specified for the

work. The Contractor is usually paid according to the quantities of items completed

each month. One of the advantages of this method is that it induces performance. It

can be effective because the Contractor is paid as soon as possible after incurring

costs and the Client gains in by reducing the total cost of the construction. The

disadvantage is that this method is more complex and expensive for all parties

when compared to the basic lump sum contract.

4. Schedule of Rates

This method is similar to the BOQ in listing the work to be performed, however the

rates are more related to the total quantity of work done rather than the amounts

expected. The basis of payment is considered to be a more flexible form of bill of

quantities. Wearne (1989) says that this method can be useful when the work type

is certain but the quantity of work is not clear enough. The risk for the Client is that

sometimes it causes very uneconomic use of resources. Schedule of rates are used

in civil engineering for preparatory and site exploration work, contracts for design,

demolition, repairs and maintenance.

5. Cost-reimbursable payment

This method is different from all other cost based terms of payment. In the

simplest form of a Cost-reimbursable contract the Employer reimburses the

Contractor’s costs of work on a project, plus usually a fixed sum or percentage for

financing, overheads and profit. Wearne (1989) feels this type of contract is used

for design studies, development, some repair, demolition and emergency work.

The advantage of this method is that the work is started as the changes are defined

and the Contractor won’t incur any prices avoiding the disputes. On the other hand

the Client has to deal with the demerit that Contractor may not be responsible for

the economic use of his resources and cost control.

Page 42: Contract Strategy for Construction Proje

42

6. Target incentive contracts

This is the development of the Cost-reimbursable method where the Client and the

Contractor agree prior to the initiation of the work regarding the cost for an

uncertain scope of work. It is agreed that the Contractor shall share his savings in

cost related to the target but when the target is exceeded the Contractor may

reimbursed less. Wearne (1989) lists the advantage as both the parties shall get

incentive to limit costs and Contractor benefits by his cost being reimbursed.

Problems shall arise if the target is not precise or changed.

7. Liquidated damages terms

In most of the engineering contracts certain terms are agreed under which the

Contractor is liable to pay liquidated damages to the Client for a breach of contract

for instance if the promoter delays the completion of work than the agreed time.

The main intention of introducing liquidated damages is to induce Contractors to

perform their contractual obligations. Wearne (1989) feels advantage of this

agreed terms are that the results are more predictable and quicker.

Page 43: Contract Strategy for Construction Proje

43

Figure 5: Nature of various Payment Terms

Source: (Corrie, 1991)

4.6 SUMMARY

This chapter explained the various types of procurement methods along with their

advantages and disadvantages. The procurement selection criteria from the

Client’s perspective were listed. The author has managed to show the procurement

procedures and their time of usability with respect to situation to the readers. The

natures of the payment terms were graphically explained. The application of the

above procurement types and terms of payment can be seen in the forms of

contract which is discussed in the next chapter.

Page 44: Contract Strategy for Construction Proje

44

5. REVIEWS OF CONDITIONS OF CONTRACT

5.1 INTRODUCTION

This chapter deals with the various forms of contract and their applications. The

various conditions of contracts are analysed in the chapter. The conditions of

contract are defined as “sets of terms which state the general responsibilities, risks

and liabilities of the parties to the contract and establish procedures between

them, including terms of payment” Smith (1995). The structure of each forms of

contracts along with their applications are discussed.

5.2 STANDARD FORMS OF CONTRACT

Smith (1995) defines “Model or standard forms of contract are Conditions of

Contract which have been prepared for general use in a particular industrial sector

by an appropriate or representative authority”. The terms of the contract shall be

negotiated between the parties and amended accordingly. Comish (2012) states

that for large, complex or risky engineering projects; usually contract is formed by

a set of documents:

1. The form of agreement

2. The conditions of contract

3. The contract specification

4. The contract drawings

And if required the contract will often comprise of following items:

a. Bill of quantities or schedule of rates

b. Programme

The Nature of Construction (2007) insists there are advantages that can be gained

by using standard form of contracts. Smith (1995) too lauds the application of

these contracts as they are tried and tested. The various advantages and

disadvantages are illustrated in The Nature of Construction (2007) are given

below:

Page 45: Contract Strategy for Construction Proje

45

Advantages Smith (1995)

The risks are shared equitably.

a) With the help of a standard form of contract the cost and time of individually

negotiated contracts are avoided.

b) Tender comparisons are made easier since the risk allocation is same for each

tenderer.

Disadvantages The Nature of Construction (2007)

The forms are cumbersome, complex and often hard to understand.

a) Often the resulting contract will be a compromise and they are very resilient

towards change. It takes quite a time to bring a change.

Traditional forms of contract are described below.

5.3 TRADITIONAL CONTRACT

In the Traditional contract, the Client employs an architect or Consulting Engineer

for carrying out the design work and the Contractor enters into a contract with the

Client for constructing the design work. . However there is no guarantee that the

designed works given by the Employer to the Contractor can be built. For carrying

out the work, the Contractor seeks services of both sub-Contractors and suppliers

for goods and equipment.

[NOTE: The Architect or Engineer is also employed to manage the contract on

behalf of the Employer. The Client is called as the Employer in most Contract

Conditions.]

The Nature of Construction (2007) summarises the main features of Traditional

form of contracts as:

There is no contractual relationship between the Employer and sub-Contractors

a) In the absence of a warranty there is no contractual relationship between the

Employer and sub-Contractors and suppliers.

b) Third parties have no contractual rights.

Lewendon (2003) in his study has demonstrated that “Traditionally the

procurement of civil engineering construction projects has used one of the editions

Page 46: Contract Strategy for Construction Proje

46

of the ICE or FIDIC Conditions of Contract or similar”. He explains their advantages

as legally tried and tested. He further adds on “a custom of usage has developed by

their extensive and successful use over the years”. In this form of procurement the

designer does not have direct link with the specialist and hence all the

communications need to pass through the main Contractor. This is a drawback

since the main Contractor won’t be obligatory towards the specialist’s

requirements. Lewendon (2003) too supports this point. In his book he has

literally backed this view; he has said “when all work can be identified, a project

can be completely designed and detailed and a Bill of Quantities produced then

these standard Conditions are a very capable form to use”. However in case of

uncertainties of scope he reports, the flaw in Traditional form will reveal itself. The

over reliance of Traditional form of contracts on the ‘Bill of Quantities’ to give a

contract price will cause inflexibility which is a major flaw.

5.4 NEED FOR ALTERNATIVE CONTRACTING APPROACHES

Innovative contracting mechanisms as explained by Carpenter, et al. (2003) offer

the opportunity to reduce the negative impacts often associated with construction.

He feels that the agreement of a programme is not a normal requirement in the ICE

or FIDIC contract. The following are major potential reasons for using innovative

contracting methods listed in his report:

5.4.1 Reducing Construction Time

One of the major reasons for the use of innovative contracting methods is to

reduce the construction time. In construction industries the need to finish the

project on time is becoming a major issue nowadays. In the areas of high traffic

congestion for the low-bid contracting projects, the cost and time overruns are

frequently experienced. To improve this situation use of an alternative contracting

procedures and specifications are recommended.

5.4.2 Reducing Construction Cost

The time and cost overruns over the allocated schedule and budget are one of the

major concerns experienced with the Traditional method. Although certain

overruns are inevitable, with the help of a better planning and project

Page 47: Contract Strategy for Construction Proje

47

management techniques some of them could be avoided or prevented by

forecasting.

5.4.3 Applying Improved Technology and Techniques

To improve the efficiency of a project and for improved project outcome

innovative techniques need to be used. Therefore to take advantage of advances in

technology and techniques relating to construction materials, equipment, and

methods a departure must be made from the Traditional approach.

5.4.4 Deploying Contractor Innovation

The incentives provided in innovative contracting methods tempt the Contractor

to accept more risk and responsibility for providing project performance for lower

costs and that too in a shorter period of time.

5.4.5 Reducing Impacts on the Public

Certain construction projects such as highway projects have an impact on the

public. Innovative contracting methods reduce construction time, which means

shorter times driving through and around work zones enhancing safety and

productivity. In addition, the use of technologies, materials, and techniques that

reduce noise and other environmental impacts invariably reduce the public

impacts of highway construction.

5.5DIFFERENT FORMS OF CONTRACT

5.5.1 FIDIC

FIDIC is an abbreviated form of Federation Internaionale des Ingenieurs-Conseils

was founded in 1913; FIDIC claimed by its official website (FIDIC, n.d.) “Is charged

with promoting and implementing the consulting engineering industry’s strategic

goals on behalf of its Member Associations, and to disseminate information and

resources of interest to its members”. The FIDIC forms of contracts are known for

its standard conditions for construction and design industries. FIDIC (n.d.) regards

the FIDIC forms of contract as the most widely used forms of contract

internationally.

Page 48: Contract Strategy for Construction Proje

48

Totterdill (2006) states that the FIDIC conditions of contract include:

1. The general conditions and

2. The particular conditions

The ‘General conditions’ are planned to be used as such without any modification

i.e., unchanged for all projects, whereas the ‘Particular conditions’ is modified for

every project based on the Client’s requirements or Contractor’s terms or due to

the project situations (Totterdill, 2006).

In 1999, FIDIC released a new edition of family of contracts consisting of four new

standard forms of contracts (CIDB, 2005).

1. Conditions of Contract for Construction (“Red Book”)

2. Conditions of Contract for Plant and Design-Build (“Yellow Book”)

3. Conditions of Contract for EPC/Turnkey Projects (“Silver Book”)

4. Short Form of Contract (“Green Book”)

The above forms of contracts are advised for common use where tenders are

invited. For the preparation of particular conditions guidance is provided into each

book. Masons (2011) points out that one of the common principles dealt with the

FIDIC forms are that it recommends a fair allocation of risks among the parties to a

contract. It calls for the best possible team to control the risk.

All the books in the FIDIC contracts specify roles for the Employers and

Contractors they ought to follow. Their respective roles are listed by Masons

(2011) as follows:

5.5.1.1 Role of the Engineer:

a) Issues instructions and notices

b) Monitors the works

c) Acts as certifier.

5.5.1.2 Role of the Contractor:

Fitness for purpose – make sure that the design will meet the Employer's

needs;

Design responsibility – for temporary works necessary for construction

Carrying out the works in a proper and workmanlike manner with properly

equipped facilities

Page 49: Contract Strategy for Construction Proje

49

Providing those facilities and choosing those materials

Accountability for method of working.

Along with these roles the Contractor also needs to perform certain administrative

functions to facilitate performance. The functions include providing information

for carrying out works and delivering notices for events increasing cost and

completion time.

For ensuring the protection of time and money it is important that an effective

administration of FIDIC contract is carried out. It is essential to write notices in

clear and unequivocal terms.

Page 50: Contract Strategy for Construction Proje

50

Table 2: Main features of the FIDIC “Red”, “Yellow” and “Silver” books

Source: (CIDB, 2005)

Page 51: Contract Strategy for Construction Proje

51

5.5.2 GENERAL CONDITIONS

Summary of clauses in the FIDIC conditions of contract for construction (1999),

related to measurement, valuation & payment as per given in Haswell & De Silva

(1989) are:

Clause 1.1.4 Contract Price

Cost includes site & H.O. overheads

Clause 1.9 Disruption of Progress/ Delay & Delay of Drawings

Can lead to extension of time under Clause 8.4 and/or to additional

cost under Clause 20

Clause 3.3 Instructions from the Engineer

Clause 4.11 Sufficiency of Tender

Clause 4.12 Unforeseeable Physical Conditions or artificial obstructions – can

lead to extension of time (Clause 8.4) and/or additional cost (Clause

20).

Giving of notice by the Contractor and response to that notice by the

engineer

Clause 8.3 Programme to be furnished by the Contractor together method of

construction and resource forecasts.

Revision of programme

Early warning of adverse circumstances

Engineer’s consent

Clause 8.4 Extension of Time for Completion – arising from delay, variation

and exceptional circumstances

Contractor to provide notification in accordance with Clause 20

Page 52: Contract Strategy for Construction Proje

52

Clause 8.7 Delay Damages payable by the Contractor to the Employer. The

limit of these damages is stated in the Appendix to the tender, and

these are the only damages for delay due to default by the

Contractor.

Clause 12 Measurement and Method of Measurement

Clause 12.3 Evaluation using tendered rates.

New rates are appropriate –

When the measured quantity of an item is changed by more than

10% from the billed quantity, etc...

The work is instructed under Clause 13 and/or no appropriate rate

exists.

Clause 13 Right to introduce Variations

Clause 13.2 Value Engineering

Contractor can be paid a fee related to the saving.

Clause 13.3 Variations Procedure

Instructions

Evaluation in accordance with Clause 12

Payment in appropriate currencies

Clause 13.5 Provisional sums

Clause 13.6 Dayworks

Clause 13.8 Adjustments for changes in cost

Clause 14.1 Contract Price to be determined under Clause 12.3

Certificates & Payment

Page 53: Contract Strategy for Construction Proje

53

Clause 14.2 Advance Payment

Contractor to provide Guarantee

Clause 14.8 Delayed payment

Clause 14.9 Payment of Retention Money

Clause 20.1 Contractor’s Claims

Contractor to give notice

Claim to be determined in accordance with Clauses 3.5 & 8.4

Clause 20.2 Dispute Adjudication Board

Amicable settlement

Clause 20.6 Arbitration

Page 54: Contract Strategy for Construction Proje

54

5.5.2 JCT

The Joint Contracts Tribunal commonly known as JCT form of contracts was first

established in 1931. In her study about the JCT contracts Taylor (2008) claims JCT

provides a range of building contracts, subcontracts, warranties and associated

guidance notes. Masons (2012) reports the JCT is made up of seven members

representing a wide range of interests in construction industries. It also regards

the JCT as the most common form of contracts used in UK with 70% of the

construction projects employing this form of contract.

The main contracts in the JCT suite are listed below (Masons, 2012):

Standard Building Contract (SBC)

Design & Build (DB)

One of the main principles of JCT as stated by Ensom (1998) is that, all the design

works are to be carried out by the Employer. The main task of the Contractor is to

carry out the works according to the design provided to him. If this routine is

disturbed for instance if incomplete design is provided by the Employer then this

in itself will cause problems. In JCT contracts there is someone referred as

‘Contract Administrator’ whose duties and functions are set out in the contract

Ensom (1998), He lists the role of a ‘Contract Administrator’ as:

1. Administrative functions

2. Functions performed as an agent of the Employer

3. Certifying functions

5.5.2.1 Format and structure

The standard format of a JCT contract document consists of (Fellows, 1991):

A. Contract drawings

B. Contract bills

C. Articles of agreement

D. Conditions of contract

E. Appendix to the conditions

Page 56: Contract Strategy for Construction Proje

56

5.5.3NEC

The NEC Engineering and Construction Contracts (ECC) previously known as the

New Engineering Contracts are created by the Institution of Civil Engineers. The

purpose of developing this form of contract as explained by The Institution of Civil

Engineers (1995) is to meet the current and future needs. The application of NEC

in construction projects is becoming increasingly common, and it is the contract of

choice for the 2012 Olympics.

5.5.3.1 Objectives

The objectives for the design of NEC contracts were to improve the following

characteristics (Lewendon, 2003):

Flexibility - in accord with a multi-disciplined approach

Clarity and Simplicity - to be exportable and understandable and lead to

fewer disputes

To be a stimulus for good management by all parties

5.5.3.2 Intent

The intent of the NEC forms of contracts is the effective collaboration of all the

project participants in order to deliver efficient project outcomes. The

collaboration helps in the speedy processing of the projects by reducing the

decision making time and avoiding conflicts and disputes among the various

project participants.

5.5.3.3 Structure of the NEC

Eggleston (1996) provides an outline structure for the NEC contract. He describes

that each contract is distinctively put together to meet the Employer’s

requirements. The structure defined by him is given below:

The contract documents

Eggleston (1996) claims that the written contracts are intended to bring certainty

to the objectives of the parties. He lists the following as the essential documents in

NEC contracts:

a) Contract data (by the Employer)

b) The Contractor’s pricing document

Page 57: Contract Strategy for Construction Proje

57

c) Conditions of contract with main options and secondary options

d) Work information from the Employer and Contractor

e) Site information (by the Employer)

f) Contract data (by Contractor)

g) Form of tender

h) Letter of acceptance

Contract data:

This section is a very important one since it contains all the contract-specific

necessary information. In the contract data the part one should be issued by the

Employer, and Part two by the Contractor. Masons (2011) explains that it

comprises of the Works Information and Site Information, for example; scope of

work and design responsibility.

Broome (1997) in his findings has stressed in importance of preparing the contract

documents in a scrutinised manner as they are considered to be the primary cause

of delays and inefficiencies and thereby causing claims and disputes.

1. The key players

The main parties involved in the NEC contracts are: the Employer, Contractor,

Project Manager, supervisor and adjudicator (Eggleston, 1996).

The Employer:

The Employer is the sole owner of the project and he has the liberty to opt for the

type of contract strategy he wishes. Therefore his job includes:

1. Makes a selection from the six main options to decide the type of pricing

mechanism he wants

2. Includes the nine sections of core clauses in the contract

3. Includes any section from 14 detailed secondary option clauses if required.

1. The Project Manager

The Project Manager’s role is a more demanding one and has several duties to take

care of. The Project Manager is envisioned to work with the Client till the end of

the project. He must make sure the contract goes well by progressing towards an

effective completion. Eggleston (1996) states the Project Manager’s reputation is

Page 58: Contract Strategy for Construction Proje

58

significant to the project since for the Employer the project success is dependent

on the competence of the Project Manager.

2. General core clauses

These nine sections listed by the Masons (2011), are the similar in every form.

They cover the basics that are applicable for all contracts. The clauses are:

1. General - includes defined terms, interpretation, communications, ambiguities;

2. Contractor's main responsibilities – provision of works, design, people,

subcontracting;

3. Time – starting, completion dates, key dates, programme, access, takeover,

acceleration;

4. Testing and defects – tests and inspections, notifying defects, correcting

defects, accepting defects, uncorrected defects;

5. Payment – assessing amounts due, payment provisions, pain share/gain share

where appropriate;

6. Compensation events – events which will give rise to time and money and

procedures for dealing with these;

7. Title – for example, to plant and materials;

8. Risks and insurance – Contractor and the Employer risks, insurance

requirements;

9. Termination – grounds, procedures and payments on/for termination.

Main options:

These relate to contract structure and pricing mechanism. The Client shall opt for

any option from A to F. The options are (Eggleston, 1996):

A: Priced Contract with Activity Schedule;

B: Priced Contract with Bill of Quantities;

C: Target Contract with Activity Schedule;

D: Target Contract with Bill of Quantities;

E: Cost Reimbursable Contract;

F: Management Contract

Page 59: Contract Strategy for Construction Proje

59

Secondary options:

There are seventeen additional clauses for certain matters, for example; changes in

law, modification of pricing for inflation and provision of performance bonds.

These options can be selected as suitable.

3. Time (The Programme)

Hide (2007) beholds from his study that NEC helps the Contractors to produce and

maintain; Project Managers to accept a ‘live’ programme. (Davis, n.d.) Compliments

the role of programme stating its significance in

Outlining the role in management of works

Setting out the work to be executed

Requirements to carry out that work, and

The periods and dates in which to accomplish it.

With the help of the programme and by proper maintenance Davis (n.d.) feels the

Employer will have better opportunities in minimising the effects of delays in

project and cost overruns. Broome (1997) acknowledges the higher priority of ‘the

programme’ in ECC than in other contracts. Overall with the programme in the

hand of the Client and the Contractor will have a tool by which, they can manage

the entire construction process.

4. Compensation events

NEC (2005) defines the compensation events as “events which, if they occur and do

not arise from the Contractor’s fault, entitle the Contractor to be compensated for

any effect the event may have on the Prices. A compensation event will normally

result in additional payment to the Contractor but in a few cases may result in

reduced payment”. Broome (1997) reports in his study that in a NEC contract

when a compensation event occurs, the Project Manager has a liberty to ask the

Contractor to submit a quotation in best interests of keeping the completion date

and price of the project close to the originally planned. But in order to make an

appropriate decision from the available options Broome (1997) insists, the Project

Manager must be aware of the Client’s objectives concerning time, cost and quality.

The Project Manager must also have considered the Employer’s attitude towards

risk.

Page 60: Contract Strategy for Construction Proje

60

The following diagram shows the mechanism being followed in case of a

compensation event.

Figure 6: Flow chart for mechanism to be follwed while a Compensation Event

Source: (Contract & Construction Consultant , 2011)

Page 61: Contract Strategy for Construction Proje

61

The various NEC options along with their incentives, financial and other risks they

bear are tabled below as per given by Lewendon (2003):

Table 3: Various NEC options along with their Incentives, Financial and other Risks

Source: (Lewendon, 2003)

Page 62: Contract Strategy for Construction Proje

62

The advantages and disadvantages of the NEC type of contracts are analysed by

Boulding (2006).

Advantages

a. It employs a user friendly language.

b. NEC places a laudable emphasis on endorsing good project management

practice.

c. NEC is considered an appropriate choice for partnering as well as other

collaborative arrangements (Gould, 2007).

d. In NEC it is possible for an early identification of risks.

Disadvantages

a. Use of narrative and descriptive present tense causes distress to the legal

advisers who have to interpret its consequence.

b. It places the Project Manager in an extremely challenging role which demands

an intense use of resources and it also involves certain amount of uncertainty

(Broome, 1997).

c. It causes concerns that it may sway in the Contractor’s favour.

5.6 SUMMARY

This chapter described about the improvements in the contracts from the

traditionally followed forms. The NEC forms of contracts were examined in detail

with its merits and demerits. In the next chapter case studies based on the

Traditional form and NEC will be carried out. With the help of an exercise, the

Traditional and NEC contracts will be compared and their characteristics will be

discussed.

Page 63: Contract Strategy for Construction Proje

63

6. CASE STUDIES

6.1 INTRODUCTION

This chapter analyses different projects based on the forms of contracts studied in

the previous sections of this dissertation. The nature of the projects selected, the

problems faced by them and the contract solutions for solving the obstacles will be

reviewed in this part. At the end of this chapter a comparison of Traditional forms

of contract and NEC forms of contract will be carried out as inference to the case

studies.

6.2 CASE STUDY – 1: Gateshead Millennium Bridge—an eye-opener for

engineering (Johnson & Curran , 2003 )

This study describes about the construction of a pedestrian and cyclist Tilt Bridge

opened at 2002 spanning the River Tyne in Great Britain between Gateshead's

Quays arts quarter on the south bank, and the Quayside of Newcastle upon Tyne on

the north bank. This bridge while construction surpassed several milestones of

creativity and spectacles which thrusts for an in-depth research of its edifice. One

such milestone which turned several heads towards this project was that the

bridge was carried by one of the world's largest floating cranes for about 10 km

before laying it on its supports.

The bridge had to be an opening bridge such that it accommodates shipping

since a straight one could not afford it; therefore the concept of the double-arch

structure was then introduced with bridge curved on plan in a way that the whole

bridge form rotating about a common pivot point mounted on each end support.

This feature of the bridge made it a unique structure and won several accolades

nationwide. The management of this project was an absolute marvel as the work

from start to its final stages was carried out in a glamorous fashion. For

encouraging a local interest in this project, design competitions were conducted

and best out of it was selected with the help of public's choice as well as a judiciary

of senior professors. After several adjustments of the target cost on continual

additional works and agreed compensation events the bridge was finally

completed at a budget of £ 22 million.

Page 64: Contract Strategy for Construction Proje

64

Figure 7: Gateshead Millennium Bridge

Source: (Johnson & Curran , 2003 )

This project is an important contribution to the ‘Management of Projects’ course

with its effective management of construction lifecycle involving various

challenges and constraints. The funding of the project was a major highlight in this

project; the bidding was supposed to be made in such a way that, It would have to

be capable enough of attaining credit as a new millennium landmark; secondly it

would have to be completed by year 2000 and, lastly, the council would have to

provide assurance for 50% of projected cost as well as 100% of any overspend and

also potentially bear the full expense of an unsuccessful bid. The contract type

used in this Bridge construction is 'Target Cost contract with bill of quantities'

which is one of the options of NEC3. As per NEC3 (2007), in this option the

Contractor tenders (or negotiates) a target price established by means of a bill of

quantities. Each activity is priced as a lump sum and a Fee is also tendered as a

percentage for subcontract work. The initial target price is the sum of the activity

prices and the fee. During the course of the contract, the target price is adjusted to

allow for changes of quantities as well as for compensation events. Thus, the

Employer carries a greater risk. Here an unusual form of contract strategy was

applied where the position of Project Manager was shared between the Client,

Contractor, architect and Engineer, this action was very helpful in the site as the

Page 65: Contract Strategy for Construction Proje

65

conflicts and disputes were effectively resolved and the construction works

progressed in a quick manner. The Contractors work was highly satisfactory that

the accounts were finalised even before the works were finished.

Figure 8: Crane used for Gateshead Millennium Bridge

Source: (Johnson & Curran , 2003 )

The project was completed and this unique structure was officially opened by Her

Majesty Queen Elizabeth II on 7 May 2002 as part of her Golden Jubilee

celebrations. This bridge was critically acclaimed as a worthy addition to the

bridges in UK.

Page 66: Contract Strategy for Construction Proje

66

6.3 CASE STUDY – 2: Hungerford Bridge (Parker et al., 2003)

The project is situated in London. At those times pedestrians faced

difficulties in crossing the Thames between Charing Cross station and the South

Bank Centre. The walkway was bridge was narrow, noisy, frequently wet and

somewhat unsafe underfoot since it was near a railway bridge.

Figure 9: Before the construction of Hungerford Bridge

Source: (Parker et al., 2003)

For the design work to construct the bridge over 40 entrants were invited and the

judges chose six finalists to submit more detailed proposals. The final design was

selected following a public consultation exercise and exhibitions around London.

The funding was properly organized for this project as the Westminster City

Council took the lead in management as well as providing a substantial share of

capital along with other members of the cross river partnership promising to join

hands. Several innovative methods of constructing the bridge were proposed by

the design engineers and Contractors. In particular the foundation designs shared

a significant part in contributing to the uniqueness of the bridge.

Page 67: Contract Strategy for Construction Proje

67

One of the most significant concerns during the design stage was the ship impact.

The design work required a significant effort for producing a substructure that was

capable of resisting these forces without being visually obstructive.

The Client decided to seek help from a consultant called Halcrow for helping the

Client with the critical decisions on the progress of the project. Several innovative

construction methods were proposed by the Contractor and its designer

concentrating mainly on the foundations. Initially the contract was based on the

ICE’s Design and Build form but the consultant recommended a change in the

contract form accommodating more changes in the design features if needed in

future. The resulting contract called as ‘adopt and build’ was sensed that it was no

longer suitable as the Client’s engineer had to infiltrate changes to the design

before starting the contract. The resultant of this move shall cause additional delay

and unnecessary extra cost. Hence for this purpose a new contract was negotiated,

NEC Engineering and Construction Contracts were brought in for a more equitable

allocation of cost and risk as well. The contract with option C was selected which

was target contract with activity schedule. This move was helpful in allocating all

the design responsibility to the Contractor and the designer. To reduce additional

costs a value-engineering exercise was also carried out. This involved close

cooperation of the whole project team and identified significant cost savings.

Page 68: Contract Strategy for Construction Proje

68

Figure 10: The new Hungerford Bridge

Source: (Parker et al., 2003)

Finally the bridge was successfully constructed and opened. The upstream bridge

opened in May 2002 and the downstream in September 2002. It has proved

popular and also gained a structural achievement award in 2004 institution of

structural engineer’s awards. The new Hungerford Bridge has become a favourite

spot for tourist photographs.

Page 69: Contract Strategy for Construction Proje

69

6.4 CASE STUDY – 3: Delivering of London Olympic Park 2012 (Cornelius

et al., 2011)

The project is situated in London, United Kingdom. The situation of the project is a

tight schedule and a on time delivery was needed. Therefore a better contracting

method was needed. This paper describes the work of ODA (Olympic delivery

authority) organization and its delivery partner’s program management deployed

to keep the works on track for successful delivery.

Mission

The mission of the ODA was to deliver venues, facilities, infrastructure and

transport for the London 2012 Olympic Games on time to budget.

Objectives

To create infrastructure and facilities associated with games venues to agreed

time and budget.

To deliver necessary transport infrastructure for the games and devise an

effective plan for a smooth transport flow.

To assist London development agency (LDA) in the finalisation of sustainable

legacy plans for all Olympic venues.

Priority themes

Along with the delivering of construction projects on the right time, cost and

quality, the ODA is also committed to provide sustainable economic, social and

environmental benefits. The Olympic park had to open on 27th July 2012 with

following features:

a. An extremely noticeable public profile.

b. A large investment from the public purse (taxes), with attendant scrutiny from

government bodies, the media and the public.

c. Dual goals of delivering both functional venues for the games and a long-lasting

legacy thereafter.

d. Multiple the Clients.

Page 70: Contract Strategy for Construction Proje

70

Figure 11: Graphical Representation of key factors involved in Management of

London Olympic Park

Source: (Cornelius et al., 2011)

Once ODA was formed, a delivery partner with loads of experience was decided to

be employed for helping the ODA with delivery and manage the construction

programme. After an intense discussion, NEC3 Engineering and Construction

Contract was employed to hire the consortium called CLM. CLM was appointed

both as ODA’s overall programme management partner and as Project Manager for

the major construction projects. With the objective of guaranteeing constant

alignment of the Employer and delivery partner organisational models, skills and

resources, combined reviews by ODA and CLM of organisational design took place

during the programme.

Page 71: Contract Strategy for Construction Proje

71

Figure 12: Pie chart representing the distribution of Management Authority

involved in London Olympic Park

Source: (Cornelius et al., 2011)

Procurement using NEC3 contracts

To ensure transparency of costs and to boost a cooperative approach with the

suppliers as the project progressed ODA decided to use the NEC3 suite of contracts

for most of its procurement activity. The believed to provide following attributes:

a. A flexible approach, offering a contract solution with the design information

available

b. A pro-active risk management technique as a fundamental element of the

entire contract forms

c. A collaborative approach supporting timely delivery

d. Complete visibility of costs for an effective programme budget management

Table 4: Various NEC options used in London Olympic Park along with their Usage

and Rationale

Source: (Cornelius et al., 2011)

Page 72: Contract Strategy for Construction Proje

72

Design, construction and management of this massive project have been rightly

praised. Completion within time and budget without a single fatality is an

outstanding achievement. The programme for the £7 billion project included to

years of planning followed by four years of implementation with a final one year of

testing and rehearsals. NEC was the best contract which offered a prescribed

project management methodology of processes and procedures to manage

delivery as expected. Finally the Olympic delivery authority with the help of NEC

established a clear delivery strategy, maintaining a high level of transparency, clear

definition of scope and focused delivery. The role of NEC played in delivering

London Olympics is being praised by everyone; one such view is presented below.

“I think NEC3 is the unsung hero of the Olympic Games – a bit like the spine or the

heartbeat in the human body” Owen (2012), Commercial director at CLM he

expressed his views on NEC by stating, “I believe it helped deliver the project”.

Owen (2012) specified the effect of three factors that are important, “If you just

focus your teams on those three elements that will go a long way to success……..

And that’s what NEC3’s all about – those three ingredients are very clear but it’s

actually making them work”.

The idea was to making NEC work for adapting the contract to CLM’s purposes

therefore first factor Owen (2012) named was the ‘people’: “When you’re looking

at something of this size and scales don’t forget about the organization around it

and the people you put in place”. Secondly it was important that the supply chain

was trained which was fundamental in overcoming a disconnection between

corporate and operational understanding of NEC3. And the third key enablers

were that the team adopted a web based collaboration tool to manage the contract.

With the help of this the entire team had covered around 70000 formal contract

communications. Owen (2012) conceited the success of the project, “I think that’s a

real mark of success because we have managed the contract how it was intended

to be managed from day one”.

Page 73: Contract Strategy for Construction Proje

73

Figure 13: A complete view of London Olympic Park 2012

Source: (BBC, 2012 )

Page 74: Contract Strategy for Construction Proje

74

6.5 CASE STUDY - 4: The Montreal Olympic Complex (Thompson, 1981)

The subject of the study is the Olympic complex in Montreal, Canada build to

accommodate summer Olympics in 1976. This is one of the severely affected

projects by cost overruns due to poor planning, design, estimating and execution.

Each of the flaws along with the inflation caused the final financial outcome which

was a nightmare.

The design of the structure was dramatic and ultra-model in concept however for

reducing the cost and time some of the designs were removed. The constructions

of design works were very complicated. Along with the design there were many

problems this project faced during its construction period. They are:

Design: The design of the viaduct was made complicated in order for a better

appearance. This increased the cost of the formwork 15times the cost actually

planned.

Labour: A total of 100 days of work disruption was caused by labours out of which

80 days were strike and rest were lost through slowdowns. The improper contract

signing tempted the labour to take advantage.

New construction technique: It is usual that with any new techniques learning

process will be slow, painful and expensive. This was exactly the case at Montreal.

Due to the heavy construction all the resource materials were exhausted and they

had to be imported from outside. This would cost them more money.

Weather: The weather in Canada is not always favourable to the construction and

the post construction works need to be finished before starting another. To reach

the dead line the curing was sometimes done by heating and the cost of heating

was about $400000 per day.

Scheduling: The scheduling was prepared by unfamiliar theorists who did not

have a very good civil engineer experience. After some days due to the

ineffectiveness of schedule, the schedule was abandoned everything became a

daily crash action.

Fixed deadline: The late award of construction contracts and a fixed deadline for

the project had pushed for a schedule compression. This caused chaos with double

Page 75: Contract Strategy for Construction Proje

75

crews, double shifts and overtime. Doubling the crane alone increased the overall

productivity by 25%.

Procurement type

For constructing this design an innovative contract strategy had to be developed.

The Olympic site was built on a cost plus fixed free arrangement. The Contractor

agreed this on a condition with the Client that he is not responsible for the

completed structure.

Figure 14: A complete view of The Montreal Olympic Complex 1976

Source: (Crooks, 2000)

Page 76: Contract Strategy for Construction Proje

76

Finally after starting the project with a budget of $120 million at the finish it had

cost $1.5 billion. The final project contained less than originally envisioned and the

government has been since trying to cover this huge debt via taxes to the

frustration of the citizens. The incomplete Olympic site was finally opened on July

17, 1976 and offered for commencing the games. The Montreal case may prove as a

lesson to be learnt by the Client and Contractor while undertaking a project. This

failure emphasises on the importance of the need for right evaluation of the cost

and time and those features which translate into higher average costs.

Page 77: Contract Strategy for Construction Proje

77

6.6 CASE STUDY – 5: Construction of an Industrial Building (Thompson,

1981)

The design defined in the contract documents was a reinforced concrete framed

building ten bays long by six bays wide, six storeys high with identical floor slabs.

Columns and slabs were plain, of constant section and with regular spacing. The

successful tenderer, (the Contractor), carefully planned the job, designed his

formwork and compiled his estimate on the basis of constructing successive floors

of columns and slabs, always starting at the same end of the building, full width,

along its length.

While the Contractor was constructing the foundations and the first rows of

ground floor columns, the design of the structure was altered to permit the

installation of additional heavy machinery on the third floor. This floor slab was

strengthened and increased in complexity and thickness over half the length of the

building. The section of the supporting columns was increased. It is predicted that

redesign of the second half of the structure will take several weeks.

6.6.1 EXERCISE

In projects changes may cause either benefits or drawbacks. One of the

major drawbacks is the cost overruns. The major cost due to change is by the cost

of rework or revision of work. Rework is the unnecessary effect of re-doing a

process or activity that was incorrectly implemented in the first place and can be

created by defects or variations. The effects due to the changes can be grouped as

direct effects and indirect effects. Rework is an example of a direct effect of project

change and in addition to this, project changes can also bring some indirect effects,

which will ultimately have an impact on project cost and schedule.

Direct effects

■ Addition of work

■ Deletion of work

■ Demolition of work already done

■ Rework

Page 78: Contract Strategy for Construction Proje

78

■ Specification change

■ Time lost in stopping and restarting current tasks in order to make the variation

■ Revisions to project reports and documents

■ Reorganise schedule and work methods to make up lost time

Indirect effects

■ Loss of productivity due to reprogramming; loss of rhythm, unbalanced gangs

and acceleration

■ Change in cash flow, financial costs, loss of earnings

■ Increased risk of co-ordination failures and errors

■ Loss of float, therefore increased sensitivity to further delays

The major sources from which the Contractor may try to recover the additional

costs are:

1. Materials

For any building work the construction materials are bought beforehand. When

the building plan changes the work as planned gets halted and therefore the

materials bought do not serve their purpose at that time. These materials need to

be either stored or used for other purpose. For the variation new construction

materials have to be bought. With the inflation, the rates of the materials change.

Certain materials can’t be save for use at another time they are nothing but waste.

For the extra reinforcement work needed additional quantity of steel will be

required. These buying will affect the cash flow as well as the tender quoted at the

beginning.

2. Formwork

The change in formwork increases the cost of total construction. Reinforcements

are required for a formwork construction; hence for a specified plan the

reinforcement materials are brought in advance. When the plan changes and a

higher quality of formwork are required, the materials currently available do not

match the quantity required. Materials of a higher specification are required which

Page 79: Contract Strategy for Construction Proje

79

incur additional costs and time. Due to this the time and price quoted in the tender

for the formwork are not followed as planned ultimately causing chaos.

3. Delay

The delay caused in the project due to variation affects the entire characteristics of

the project. The work planned, the materials purchased and the equipment

borrowed all are wasted due to the delay. For instance, a tower crane is rented for

the work with the money already had been paid. In this situation when the project

is delayed the tower crane could not be utilised for the real purpose it was brought

and with the work unfinished the crane needs to be rented again. Along with this

the overheads from the administrator point of view would also be affected.

4. Disruption

The variation causes disruption to the entire programme of the project. The

disruption mainly affects the Contractor’s work. Initially the Contractor would

have planned for a certain program for the flow of works. With the variation

coming into the play, this program is affected. Disruption to the work occurs as the

work has to be stopped for the new design to be made until that the materials pre

ordered for the construction work continues to arrive. Later the storage of these

materials becomes a concern. This causes a loss of productivity to the Contractor

and additional costs to carry out the works using new rates.

5. Cash Flow

Due to variation disruption in work takes place, this affects the works ordered to

the sub-Contractors and the materials supplier because the cash had already been

paid by the Contractor for the progress of the work. When the work gets stopped

the payment made to the Contractor gets delayed causing a serious damage to the

Contractor’s cash flow. During this period his outcome exceeds his income forcing

him to operate at loss.

6. Consequential Factors

This factors deal with the various consequences the the Client and Contractor need

to face for delaying the project. Say if the project was initially planned to be built

on summer due to the delay now the project needs to be built on winter in the

presence of horrible weather. This causes extra money for delaying and sometimes

Page 80: Contract Strategy for Construction Proje

80

reheating the materials if needed. Certain equipment need to be rented again for

the work to progress. There are several consequences that need to be faced caused

by the variation.

6.6.2 Changes in contract price using Traditional method

Assuming that a Traditional ad-measurement contract otherwise called Unit Rate

is being used in this case, an ad-measurement contract as claimed by Smith (1995)

is based on bills of quantities (BOQ) or schedules of rates. He states that this type

of contract works on a monthly payment basis where the payment is based on

measuring the quantities of completed work and valuing rates as per tender or

new rates negotiated from the tender rates. He further stresses that in the time of

bidding the Contractors have to set rates per unit items on the basis for indications

of potential threats to total quantities within a limit of plus or minus 15% variation

of these quantities. With reference to this O'Reilly (1999) claims that in certain

circumstances, admeasure and value system shall be used in Traditional contract

and those circumstances being highly uncertain materials such as earthworks,

different types of sub-soil materials and the volumes of fill materials or mass

concrete. During these periods the works are carried out under the supervision of

an engineer who shall ask to strengthen the foundation, strengthen the slab, and

other reinforcements, which perfectly suits in our case. Hence with the help of

Traditional contract this situation shall be evaluated. However using the

Traditional methods the evaluation, cost adjustments in the contract are evaluated

by following methods (Franks , 1991).

For certain works if the quantity of work and the rates and prices used in the

contract bills are same then same values could be used for similar works.

a) On the other hand if the works from one another vary in the bill then use of fair

rates and prices shall be expected.

b) In certain cases if the work types set out in the bill are similar but quantity and

conditions of the work are different then with a typical rates of a work as a

basis of determination, the evaluation of other works are carried out making

reasonable allowances for the quantity and conditions of the work.

Page 81: Contract Strategy for Construction Proje

81

6.6.3 General Lessons

There are several lessons to be learned from this case study about a variation in a

project. The challenges faced by the Contractor and the Client and the

consequences they need to face for finishing the project. Some general lessons

learned when dealing with the changes under Traditional contract are described

below.

1) When using an admeasurement contract, no changes in the plan or

construction must be brought into action unless and until it is mandatory for

the functioning of the facility.

2) It is necessary that the Client considers all the possibilities before going for the

change and if the Client decides to go for the change then he/she must be fully

aware of the consequences that need to be faced. Sometimes it is much

comfortable for the Contractor to make changes once the project is finished.

3) It is important to realize the impact of the variations not only in terms of

money and material but also on all values of the various characteristics of the

project which may affect the outcome, such as time. Apart from the project cost

other subsidiary costs must also be taken into account.

4) When the Client thinks there is a major change to be made then all forms of

contract must be analysed and a contract form should be chosen which best

suits the situation that is adequate to enforce the changes.

6.6.4 Evaluation of BOQ with the separation of method-related charges

The separation of method related charges helps the Contractor setting up the

prices for a new contract in the tendered B.O.Q once the variation order is issued.

Method related charges as stated by Langdon & Rawlinson (2006) are that: “The

Contractors have the option to define a group of bill items and insert charges

against them to cover those expected costs which are not proportional to the

quantities of permanent works. To distinguish these items they are called method

related charges”. He lists out them as:

1) Time related cost elements or frequent charges

2) Charges for elements which are either repeated or directly related to

quantities.

Page 82: Contract Strategy for Construction Proje

82

In this case the Contractor shall insert the method related charges in the tendered

B.O.Q to charge extra for the variation introduced. Because of the variation the

Contractor have to strengthen the slab and thickening column’s section which

involves some extent of complexity. He can also include some time related cost

elements, if it took more time to re-draw the design the material price may be

inflated which in-turn costs the Contractor more than expected. So using method

related charges in the Traditional admeasurement contract as assumed, the

Contractor can sustain his credited cash flows and can manage the project within

the anticipated budget having the variation in mind. Although the method related

charges does not have specific standard to be followed which depends on the

Contractor this might help him in retaining the control of the project in all aspects.

6.6.5 Evaluation using NEC forms of contract

NEC is a development to the Traditional forms of contract and it is prepared by the

project management specialists for the purpose of making the contracts user

friendly and more effective. In case of a variation the mechanism for evaluation of

the situation using the NEC form of contracts are:

There will be an early warning issued. With this warning the Clients and the

contracts shall be alerted about the forthcoming problems. With the vast number

of contract solutions available in this format of contracts, the parties could decide

of something to deal with the issue.

One of the main features of the NEC contract which are regarded as its advantages

are its better programme management techniques and shared contract data. With

the contract data being shared the parties would be aware of their roles and

responsibilities and how to act when a situation arises. Along with the contract

data the risk is also shared mutually between the parties.

In the NEC variation is considered as a compensation event. For any losses suffered

by the Contractor the Client has to compensate it. These details shall be encrypted

on the contract details at the start of the project. There are also special types of

allotments for variations in a contract in NEC.

Page 83: Contract Strategy for Construction Proje

83

Sometimes the compensation to the Contractor from the Client shall be based on

the forecast change in actual costs. The disruptions caused, the parties suffering

and the amount to be compensated. All these details are forecasted and dealt with.

According to NEC (2005), “Compensation events are valued before they occur,

ensuring that project parties have early awareness of the cost and time

implications of events, allowing for effective planning and reductions in disputes”.

Therefore with the help of NEC the variation can be better tackled when compared

to the Traditional methods. The benefits will be better communications and faster

development of a close working relationship between the parties, with little or no

extra cost involved. In the Traditional methods the variation causes severe cost

and time overruns whereas in NEC there are some accommodating features in the

contracts for variation. Thereby enlightening us that NEC is a preferred choice of

contracts over the Traditional methods in case of complex projects and crunch

situations where the risk is very high.

6.7 COMPARISON OF TRADITIONAL CONTRACTS WITH NEC

With the growth in use of NEC all over the world, the Traditional contracts have

been taking a backseat in the major projects where their absence is no longer felt.

In a study Broome & Hayes (1997) felt that it was the clarity of NEC that

outperformed the other forms of contract. He listed the beneficial features of NEC

as:

Ease of understanding

Clear text

Clear risk allocation

Clear definitions of roles and responsibilities of each party

Clear guidance and procedures

Clear payment for charges

Reduced sources of conflicts

Broome (1997) explains the minimum difference between the conventional and

ECC practice as:

1. Relocation of the specification material into the contract data, site information

and works information.

Page 84: Contract Strategy for Construction Proje

84

2. Changing the terminology in existing specifications to that used in the ECC.

One of the characteristics mentioned by Bennett & Baird (2001) is “The actions

required by the parties to the ECC are designed to be solution oriented rather than

problem focussed, in contrast to Traditional forms of contract which pay little

attention to teamwork”. He explains that along with the clarity the approach of the

NEC is very modest when compared to the Traditional method. From an interview

conducted by Broome & Hayes (1997) it is inference from various interviewees

that in NEC the various parties in contract feel to be having a greater knowledge on

the financial and time outcomes of the project. This is mainly because the risks are

identified, allocated and their consequences are settled. With this knowledge the

contracting parties and the Project Managers can feel certain of finishing the

project within the given budget and time. Broome & Hayes (1997) also points out

another distinctive feature of NEC as “The reduced level of argument over

responsibility for risks that have occurred has contributed to the greater degree of

cooperation and openness compared with normal contracts”. One of the

comparisons he cites out in his study is given below.

Table 5: A Comparison of physical Condition of clauses in Traditional and NEC

form of Contract

Source: (Broome & Hayes, 1997)

Page 85: Contract Strategy for Construction Proje

85

The philosophies of the NEC contracts which are the main reasons for its success;

as described in the NEC (2005) are:

1) A collaborative approach to any issues mitigates them and also reduces the risk

inherent in construction work

2) A clear definition of roles and responsibilities helps accountability and

motivates people to play their part

This philosophy has widely been accepted by the world for the essential popularity

of the NEC contracts. Wright & Fergusson (2009) lauds the NEC contracts for its

versatility when compared to its other forms of contract. He claims that NEC is

suitable for any engineering and construction projects due to its exclusion of

discipline specific matters. Therefore he relishes its use by any discipline or

combination of disciplines including civil, mechanical, electrical, building and

process.

6.8 SUMMARY

The contracting strategies applied in some major construction projects in the

world were analysed in this chapter. From the case studies a comparison was

drawn between the Traditional and NEC form of contract. From the difference it

was learnt that NEC offers a better contracting solutions. The further lessons learnt

will be described in the next chapter of this dissertation.

Page 86: Contract Strategy for Construction Proje

86

7. GENERAL DISCUSSIONS

7.1 INTRODUCTION

This chapter presents some results of research carried out by the author so far in

this dissertation. The purpose of the research was to learn the importance of

contract strategy, different types of contract strategies involved in the construction

industry and the difference between Traditional form of contracting and New The

Engineering Contracts. The author has studied the FIDIC and ICE form of contracts

as the example for the Traditional form of contract. During his research the

following issues have been highlighted by the author.

7.2 LESSONS LEARNT

The dissertation was carried out in order to describe the importance of

procurement strategies and the author has got a handful of lessons learned about

them. One of the first findings was about the purpose of the procurement

strategies. They are learned to achieve: firstly, certainty of cost and time for a

design created by an architect working for the Client, next it is supposed to achieve

speed and cost certainty and lastly its purpose to achieve speed for a design

developed by an architect employed by the Client.

While examining about the procurement types, the author came across the

different types of procurement methods and their use. The Traditional method was

found to be suitable for the projects where the functionality is prime objective and

it is lauded for its price and cost certainty. However the Traditional method would

be inefficient for the fast track projects. On the other hand the Design and Built

shall be suitable for the fast track project but it cannot be employed for the

complex projects. There is a procurement type which could tackle both the fast

track as well as complex project, the Management contracting however it will

prove ineffective in front of the inexperienced the Client. The Clients cannot pass

the risk to the Contractor in this type of procurement method. The author has

made efforts to study that where prompt completion is the prime objective a

Management Contract is frequently employed. Here a professional organisation is

employed to manage design and construction which overlap. The PFI projects are a

superior option for the publicly funded government aided infrastructure projects.

Page 87: Contract Strategy for Construction Proje

87

Cost–Reimbursable and Target–Cost contracts are commonly employed for sudden

emergency projects and for high-risk projects. It was found in this case the

Contractor is supposed to reimburse his actual cost and may have the incentive of

a bonus or penalty arrangement. These are collaborative arrangements and the

Client must be involved, through his Project Manager, in all major decisions. This is

a very flexible contract from but any target must be realistic as a low figure will

destroy the incentive. In such a situation where the time factor plays a major role

the management of an agreed programme is substantial and it is probable that

either a management contract or a target-cost contract will be adopted.

One of the most important factors first learned during the research is that for

success of project it is essential that an early interest must be developed by the

Client in appointing a most appropriate organisation for the design and

construction of the project. There are many situations where it is necessary and

may prove advantageous to involve the construction Contractor in the early stages

of project development to consider methods of erection. There was enough

evidence produced in the literature review in favour of the above theory. Along

with an early involvement the Client must also carefully analyse the options

thoroughly, the Client must decide on the contract strategy usually in consultation

with the Engineer before making a choice. The need to look at certain project

performance factors for a successful conclusion of project were also analysed and

listed as: culture, leadership, motivation and commitment. Effective application of

these characteristics is essential in all departments of the project team for avoiding

any disappointments. This was well illustrated in the Gateshead Bridge case study.

Secondly, the research in this dissertation focused on the different types of

contract strategies (contract forms) available. All conditions of contract were

examined with reference to various project management authors’ comments

regarding those contract types. Along with the procurement types the different

forms of contract available were also discussed. From the research it was found

that the Traditional forms of contracts were not always suitable these days. The

contracting approach must be amended to meet the current demands. The

demerits of the Traditional form of contracting were studied and the impacts of

their ineffectiveness were determined as cost overruns and time overruns which

Page 88: Contract Strategy for Construction Proje

88

severely affects the Client’s objectives. Hence it was stressed that innovations have

to be brought on. Developments have already started arising; the various

developments were described in this dissertation with the comprising changes and

speciality.

To study the role of project management and the Clients in the contract selection

for effective completion of project, case studies were illustrated. The case studies

were selected appropriately to reflect the current trend of contract strategies

implemented and compare them with the Traditional methods. For example the

paper Delivering London 2012: procurement stands as a perfect example for the

NEC form of contracts used. In recent years most of the modern projects are opting

for the developed forms of contract rather than the conventional forms. From the

case studies dealt it is inference that for a complex project where there are scope

for uncertainties and variation, the Traditional form of contracts are not suitable

anymore. In the case studies it can be seen with the help of NEC contracts the

projects are completed well in time and budget. There are different types of

contracts into the NEC each one of which could be accommodated as per the

requirement of the project. The case studies also explained us that the contract

alone is not the match winner for the project but also the various parties involved

in the project. In the Gateshead project all the parties collaborated with each other

and formed as the Project Manager which helped them with a quicker decision

making process. The appointment of a special Project Manager for the Client’s

consultation and overlooking the Contractor’s work was also observed. The

findings derive from the case studies were that the use of NEC had made the

project outcome more effective and efficient. An early forecasting of the cost and

other characteristics of the project by the NEC methods alerts both the Client and

Contractor. This makes them work together and solve the problem.

With the help of these case studies, the author has studied the effective

implementation of the innovative contract strategies such as NEC form of contracts

in the projects. The author has learned about the NEC contracts and depicts one of

its main features as: it will highlight the shortcomings and deficiencies by the

project participants. The reason for this is the definitions of roles, risks and

processes in the NEC contract are much tighter than in any other form of contracts.

Page 89: Contract Strategy for Construction Proje

89

The case studies outcast the advantages of the improved form of contracts to the

Traditional form. In The Montreal Olympic Complex project, the project fails and

results in severe cost overrun. The budget of the project increased ten times the

planned amount. There were no specific single reason for the failure, rather it

could be said that everything on the project was faulty. Starting from the design to

the construction the project faced so many problems. The project management

was not efficiently applied into the project; if a different contract strategy is to be

applied into the project the results could be very different.

The time factor in the project has been fast growing as the fundamental factor in

upcoming projects. The study from case studies reveals the Clients opt for

‘certainty of completion date’ when compared to the ‘shortest design and

construction period’. From the case studies dealt in this dissertation, in the case of

Olympic park the main objective of the project is the timely delivery. The Montreal

Olympic project stands as a perfect example to stress the importance of project

completion in time. It is learnt from these projects that delay in time causes the

cost overrun as well. For reducing any further defaults completion of project in

time is suggested.

An effective application of a good project management technique is also equally

important in a project. This research has stressed on the project management in

contract strategy. The author has learned the positive effects out of this

involvement. It is learned that the quintessential characteristics of project

management is its ability to look at the needs of the Client and the risks involved in

it. It is also helpful in anticipating problems and communicating the contingency

plan and priorities to rest of the participants. The most important reason for

employing project management was discovered to be its ability to produce quality

and deliver value for money.

Role of the Client is another important component in the project success criteria.

However not all the Clients are the same and so do their needs vary accordingly.

The author emphasises from his research that the Clients must first find out their

needs and set objectives such that they are clearly specified to the Contractor. The

Clients’ need so far has focussed on the classic trio of time, cost and

functionality/quality. But the modern the Clients have started demanding more

involving the reduction in time or reduction in cost based on the project situation.

Page 90: Contract Strategy for Construction Proje

90

The research has discovered that the Clients have started setting incentives for

effective performance of the Contractor. However studies have revealed setting

incentives does not always help rather an effective collaboration of the Contractor

and the Client is the most important factor for project success.

Lastly the author has made a comparison between Traditional forms of contracting

with the NEC forms. From the exercise it was learnt that the NEC can effectively

deal with the variation with minimal demerits. Whilst dealing with case studies it

was determined that the Clients using NEC feel they are well aware of financial and

time outcome of project at any time. This is due to the transparent nature of the

NEC contracts which makes the project participants feel comfortable. The variation

exercise teaches that the Client must not always go for changes once the project is

initiated and construction work going on, unless he is fully aware of the

consequences he has to face. The Client must also learn to select the contract

strategy well keeping in mind the progress of project.

7.3 RECOMMENDATIONS FOR THE MANAGEMENT OF FUTURE

PROJECTS

It is not an easy job to prejudge the evolution and development of existing systems.

However prediction could be made based on the currents trends and relating them

with the historical approaches. Therefore based on a thorough analysis it could be

stated that the future project shall have complex designs, larger size, higher

budgets and a more demanding the Clients. Hence to meet the demands the

contract strategies will continue to evolve and developments will be arising.

The author suggests that the Traditional form of contracts may be helpful in

dealing with very small projects but when it comes to complex projects with high

the Client demands the conventional contracts do not stay up to their expectations.

As per the current trends an extensive use of modern form of contract has been

widely applied throughout the world. Since this approach has been proved

advantageous the author recommends following actions to be followed for greater

good in the construction industry:

1. Provide increased training for project teams and project management the

Contractors.

Page 91: Contract Strategy for Construction Proje

91

2. Increase the awareness of the benefits of the developed form of contracts to the

Clients.

3. Promote wider future use of the innovative contracting strategies in the

Engineering and construction industry.

4. Actively promote the joint working approach of the Client, the Contractor and

Project Manager Collaboration by co-locating future project teams in site offices.

7.3.1 High risk factors involved in future complex projects

The author is wary about the High risk factors the future projects are on the verge

of facing. Therefore he suggests certain procedures to be followed in order to

reduce the risk factors causing any problems. The first things the author suggests

is an early qualitative assessment, he emphasises its significance to the

stakeholders particularly those who are inexperienced. The common point learned

from this dissertation is that one must understand about something which he

wishes to undertake; likewise it is preferably a good option the adoption of the list

of high risk factors which could help stakeholders to take great care of it from the

early stages of the project. Another procedure to overcome these risks is to involve

the Project Manager in all preliminary discussions, programme planning and cost

estimating. This will help in Project Manager directing his team in such a way that

the risk factors are not disturbed. The risk management process must be an on-

going process and the interested parties must remain focussed in tackling them

throughout the year.

7.4 SUMMARY

This chapter focussed on the author’s perception of the dissertation. The lessons

learnt from the start of the research till the end were analysed. The case studies

were examined and their views about the form of contracts used were mention.

Lastly this chapter is concluded with the recommendation for future purpose by

the author.

Page 92: Contract Strategy for Construction Proje

92

8. CONCLUSIONS

The author has researched the Engineering contracts and contract management

along with all aspects of contract strategy. He has compared theory with practice

by the introduction of case studies of recent projects. Finally the author has

achieved his project objectives namely:

Examining the concept of contract strategy.

Investigating the different contract strategies used in construction industries.

Interrogating the role of contract strategy in project management.

Examining the implications of contractual variations in construction industries.

To compare and evaluate changes in a project by applying the Traditional

contract strategy with the new engineering contract systems.

Analysing into the merits and demerits of various contract procedures for the

given situation.

The author has analysed the necessity for contract strategy study and has limited

his research to risk analysis and the Clients objectives involved in success of the

project. Initially the author’s intention was to study the various contract strategies

available and suggest an appropriate one over each type of project. Therefore he

has discussed about the application of different types of contract strategies and

place of their use. For example, in a case where the time is stated as the most

important objective a suggestive use of management contract or a cost

reimbursement contract with time target is encouraged. However at the later

stages of the research the author has learnt, the decision of the contract strategies

vary by the project situation and the Client/the Contractor needs and it is

inappropriate to judge based on the project types.

The author feels that the project management is an essential part in contract

strategy and it is important that the Client is informed about the progress or

changes in the project. For example, in all but the simplest repetitive contracts

there is need for the Client to appoint the Project Manager and the Project Manager

must keep the Client informed about all major decisions. From the research it is

deduced contract strategies alone do not cause the success in projects, but also an

effective collaboration of all project participants along with a wise application of

Page 93: Contract Strategy for Construction Proje

93

project management techniques. The satisfaction of all the participants is essential

for a motivated and dedicated effort made towards the project completion.

The author has studied that the completion of all technical and engineering

projects involves risk and uncertainty. The proper allocation of risk between the

parties involved is a major consideration during contract strategy studies. The

risks may occur in any form and one such form is need for change. The author has

observed that the contract strategies could be amended based on the situation for

an effective outcome. For instance even after the start of the construction phase

the approach may change during the life of the project and the Contractor may

bring in change according to the calamities surrounding the project i.e., either due

to the shortage of time or for applying different construction method. The author

has learned a major lesson about the variations in a project from this dissertation,

it is that do not vary the work included in a current contract unless it is vital to the

safety or functioning of the facility. The consequences of a major variation in terms

of cost, delay and disruption were illustrated in the case study of the multi-

storeyed building. Evaluation of the change was seen to be very problematic when

the Traditional ad-measurement contract was applied, due to the absence of an

agreed programme. However it proved much easier when treated as a

compensation event in NEC, but even here sometimes it is unsure whether the

Client fully understood the full after effects of the change.

The author has noted a rise in the number of projects in recent years for which

early or timely completion is a major concern. But this research incurs that the

Traditional method emphasis on price which does not potentially focus on the

increasing importance of timely completion and rapid completion in technical

projects. For this purpose developments in contracts were formed. One such

development is NEC (New Engineering Contract). NEC is used for almost all U.K

infrastructure projects for its collaborative nature; early caution requirement and

attention to programme were applauded by the highly successful managers of the

London 2012 Olympic park project. The major advantages of NEC contracts found

to be helpful for the Client are as follows:

1. It employs a user friendly language

2. It is possible for early findings of risks

Page 94: Contract Strategy for Construction Proje

94

3. A collaborative approach to any issues mitigates them and also reduces the risk

inherent in construction work

4. A clear definition of roles and responsibilities helps accountability and

motivates people to play their part.

Finally the author is satisfied with his work that he has explored the range of

contract types and administrations which have progressed to meet the varied

requirements of the industry as well as society and changes in technology. From

his findings the author states the future of the contracts in construction industry

lies in the hands of developed forms of contracts rather than the traditionally

followed ones. The author feels that such innovative contracts which promote

collaboration and facilitate project management will be widely used in the future

for major high budget and high risk projects.

Page 95: Contract Strategy for Construction Proje

95

REFERENCE Aboushiwa, M.A. & Bower, D., 2000. Promoter Briefing on the Procurement and

Selection of Contract Strategy Offering the Best Value for Money. London: UMIST.

Assaf, A. & Al-Hejji, S., 2006. Title: Causes of delay in large construction projects.

International Journal of Project Management, 24(4), pp.349-57.

Barnes , M., 2006. Project Management inUncertainty An Integrated Approach.

Speech. Shangai: 20th IPMA World Congress of Project Management.

BBC, 2012. London 2012: Olympic Park in pictures. [Online] Available at:

<http://www.bbc.co.uk/news/in-pictures-18239274 > [Accessed 20 August 2012].

Belew, S., n.d. Benefits of Developing a Written Contract. [Online] Available at:

<http://consulting.about.com/> [Accessed 20 April 2012].

Bennett, & Baird, , 2001. NEC and Partnering: The Guide to Building Winning Teams.

London: Thomas Telford.

Bennett, J. & Flanagan, R., 1983. Building. In For the good of the client. p.26–27.

Boulding , Q.P., 2006. The New Engineering Contract: A Progress Report. [Online]

Available at:

<http://www.keatingchambers.co.uk/resources/publications/2006/the_new_engi

neering_contract_a_progress_report.aspx > [Accessed 23 August 2012].

Bower, D., 2003. Management of procurement. London : Thomas Telford.

Bower, D. & Merna, A., 2002. Finding the optimal contractual arrangement for

projects on process job sites. Journal Of Management In Engineering, 18(1), pp.17-

20.

Broome, J.C., 1997. Best Practice with the New Engineering Contract. Proceedings of

the Institution of Civil Engineers, 120(2), pp.74-81.

Broome, J.C. & Hayes, R.W., 1997. A comparison of the clarity of traditional

construction contracts and of the New Engineering Contract. International Journal

of Project Management, 15(4), pp.255-61.

Page 96: Contract Strategy for Construction Proje

96

Carpenter, B., Fekpe, E. & Gopalakrishna, D., 2003. PERFORMANCE-BASED

CONTRACTING FOR THE HIGHWAY CONSTRUCTION INDUSTRY. [Online] Available

at: <http://www.ncppp.org/resources/papers/battellereport.pdf > [Accessed 14

July 2012].

CIDB, 2005. CONSTRUCTION PROCUREMENT. [Online] Available at:

<http://www.cidb.org.za/toolkit06/toolkitpages/module5/20SupplementaryInfor

mation/5S11%20PGC2-%20ecc%20edition%202.0.pdf > [Accessed 11 August

2012].

CIRIA, 1991. Roles, responsibilities and risks in management contracting. CIRIA.

Comish, F., Alan. 2012. Commercial Contract Management, MACE60067

Commercial Contract Management: Lecture 1. University of Manchester,

unpublished.

Contract & Construction Consultant , L., 2011. NEC3 Compensation Events

Flowchart. [Online] Available at: <http://www.contract-

consultants.com/publication/CCC-publication23.pdf [Accessed 16 August 2012].

Cooke, B. & Williams, P., 2004. Construction Planning, Programming & Control. 2nd

ed. London: Blackwell.

Cornelius, , Fernau, , Dickinson, & Stuart, , 2011. Delivering London 2012:

procurement. Proceedings of the ICE - Civil Engineering, 164(5), pp.34 - 39.

Corrie, R.K., 1991. Project evaluation. London: Thomas Telford.

Crooks, G., 2000. "A bird's eye view of Montreal". [Online] Available at:

<http://members.virtualtourist.com/m/tt/282f6/ > [Accessed 2 August 2012].

Davis, S., n.d. The Construction Programme under the NEC Contract. [Online]

Available at:

<http://www.trett.com/digest/Pages/TheConstructionProgrammeundertheNECC

ontract,SDavis(DigestIssue35).aspx > [Accessed 12 July 2012].

Eggleston, B., 1996. The New Engineering Contract. 1st ed. London: Blackwell

Science.

Page 97: Contract Strategy for Construction Proje

97

Ensom, C., 1998. Adjudication on JCT 81 contracts. Structural Survey, 16(3),

pp.130-35.

Fellows, R.F., 1991. 1980 JCT Standard Form of Building Contract. 2nd ed. London:

Macmillan Education LTD.

FIDIC, n.d. International Federation of Consulting Engineers. [Online] Available at:

<http://fidic.org/about-fidic > [Accessed 10 August 2012].

Franks , J., 1991. Building contract administration and practice. 1st ed. London:

Batsford in association with the Chartered Institute of Building.

Gould, N., 2007. NEC3: Early Warning and Compensation Events. [Online] Available

at: <http://www.fenwickelliott.com/files/Contract%2012%20-%20NEC3%20-

%20Early%20Warning%20and%20Compensation%20Events.pdf > [Accessed 18

August 2012].

Griffiths, F., 1989. Project contract strategy for 1992 and beyond. International

Journal of Project Management, 7(2), pp.69-83.

Haswell, C.K. & De Silva, D.S., 1989. Civil Engineering Contracts: Practice and

Procedure. 2nd ed. London: Butterworths.

Hide, G., 2007. New course on managing NEC programmes. NEC USERS’ GROUP

NEWSLETTER, MARCH. p.38.

HOUSING GRANTS CONSTRUCTION AND REGENERATION ACT 1996 (PART II),

2010. BUILDING CONTRACT DIRECTIVE. [Online] CAPITAL & ASSET

MANAGEMENT Available at:

<http://www2.westsussex.gov.uk/yourcouncil/finances/propertyservices/bcds/

BCD44.pdf [Accessed 23 July 2012].

JCT, 2011. Practice Note – Deciding on the appropriate JCT contract. [Online]

Available at: <http://www.jctcontracts.com/files/dac2011.pdf > [Accessed 1

August 2012].

Johnson , & Curran , , 2003. Gateshead Millennium Bridge—an eye-opener for

engineering. Proceedings of the ICE - Civil Engineering, 156(1), p.16 –24.

Page 98: Contract Strategy for Construction Proje

98

Kalvet, & Lember, V., 2010. Risk management in public procurement for

innovation: the case of Nordic Baltic Sea cities. Innovation-The European Journal of

Social Science Research, 23(3).

Langdon, D. & Rawlinson, S., 2006. Procurement: Construction management.

[Online] Available at: <http://www.building.co.uk/data/procurement-

construction-management/3072705.article# > [Accessed 6 August 2012].

Lantry, T.L., 1988. THE END OF STATUS BENEFITS? WILL TRADITIONAL

CONTRACT PRINCIPLES PREVAIL? American Business Law Journal, 26(2), p.363.

Lewendon, R., 2003. The Use of NEC: Engineering and Construction Contract.

[Online] Available at:

<https://www.waterways.org.uk/pdf/restoration/the_use_of_nec__engineering_an

d_construction_contract > [Accessed 20 June 2012].

Lewendon, S., 2003. The Use of NEC: Engineering and Construction Contract.

[Online] Available at:

<https://www.waterways.org.uk/pdf/restoration/the_use_of_nec__engineering_an

d_construction_contract > [Accessed 29 July 2012].

Lock, , 2007. Project Management: Project and programme management resources

for students. 9th ed. Gower.

Masons, P., 2011. Standard Form Contracts: FIDIC. [Online] Available at:

<http://www.out-law.com/en/topics/projects--construction/construction-

standard-form-contracts/standard-form-contracts-fidic/ > [Accessed 21 July

2012].

Masons, P., 2011. Standard Form Contracts: NEC. [Online] Available at:

<http://www.out-law.com/en/topics/projects--construction/construction-

standard-form-contracts/standard-form-contracts-nec/ > [Accessed 19 August

2012].

Masons, P., 2012. Standard form contracts: JCT. [Online] Available at:

<http://www.out-law.com/en/topics/projects--construction/construction-

Page 99: Contract Strategy for Construction Proje

99

standard-form-contracts/standard-form-contracts-jct/ > [Accessed 23 August

2012].

Masterman, W.E., 1992. An Introduction to Building Procurement Systems. 1st ed.

London: E & FN Spon.

NEC, 2005. NEC3 Term Service Contract - Guidance notes. London: Thomas Telford

Ltd.

NEC3 COMPENSATION EVENTS FLOWCHART, 2011. NEC3 COMPENSATION

EVENTS FLOWCHART. [Online] Available at: <http://www.contract-

consultants.com/publication/CCC-publication23.pdf > [Accessed 20 August 2012].

Ojo, S.O., Adeyemi, A.Y. & Fagbenle, O.I., 2006. THE PERFORMANCE OF

TRADITIONAL CONTRACT PROCUREMENT ON HOUSING PROJECTS IN NIGERIA.

Traditional Contract Procurement on Housing Projects In Nigeria / CED, 8(2), p.81–

86.

Olsen, T.E. & Osmundsen, , 2005. Sharing of endogenous risk in construction.

Journal of Economic Behavior & Organization, 58(4), p.511–526.

O'Reilly, M., 1999. Civil engineering construction contracts. 2nd ed. London: Thomas

Telford.

Owen, K., O.D.A.Learning Legacy. Projects July 2012

Parker, S. et al., 2003. Hungerford Bridge millennium project—London.

Proceedings of the ICE - Civil Engineering, 156(2), pp.70 - 77.

Perry, J.G., 1985. The development of contract strategies for construction projects.

Ph.D. thesis.

Procurement Guide: Procurement and contract strategies, 2003. OGC. [Online]

Available at: <http://www.forthconstruction.co.uk/downloads/achieving-

excellence-guide-6.pdf > [Accessed 20 July 2012].

Rashid, R.A. et al., 2007. EFFECT OF PROCUREMENT SYSTEMS ON THE

PERFORMANCE OF CONSTRUCTION PROJECTS. [Online] Available at:

Page 100: Contract Strategy for Construction Proje

100

<http://eprints.utm.my/790/1/Procurement_performanceRosli.pdf > [Accessed

14 July 2012].

Rowlinon , S. & Mcdermott, P., 1999. Procurement Systems: A guide to best practice

in construction. 1st ed. London: E & FN SON.

Smith, N.J., 1995. Engineering Project Management. 2nd ed. London: Blackwell

Science.

Smith, J., Merna, T. & Jobling , , 2006. Managing Risk in Construction Projects. 2nd

ed. London: Blackwell.

Spring, & Wearne, , 2003. Procuring the services of a project manager. In

Management of Procurement. London: Thomas Telford. pp.49-57.

Taylor, , 2008. JCT building contracts: What’s new? Journal of Building Appraisal,

3(4), p.259–266.

The Institution of Civil Engineers, 1995. The engineering and construction contract.

2nd ed. London : Thomas Telford.

The Nature of Construction, 2007. The Nature of Construction. [Online] Available at:

<http://www.palgrave.com/PDFs/9780230521650.pdf > [Accessed 12 July 2012].

Thompson, P., 1981. Organization and economics of construction. London :

McGraw-Hall.

Totterdill, B.W., 2006. FIDIC user's guide: A particular guide to the 1999 Red and

Yellow Books. 1st ed. London: Thomas Telford.

Veld, J.i.'. & Peeters, W.A., 1989. Keeping large projects under control: the

importance of contract type selection. International Journal of Project Management,

7(3), p.155–162.

Venters, S., 2005. Importance of contract strategy - A case study of the OLE and

distribution Alliance project.

Wearne, , 1989. Civil Engineering Contracts. 1st ed. London: Thomas Telford.

Page 101: Contract Strategy for Construction Proje

101

Wearne, S.H., 1995. Engineering project management. London: Blackwell Science.

pp.3-8.

Wright, J.N. & Fergusson, W., 2009. Benefits of the NEC ECC form of contract: A

New Zealand case study. International Journal of Project Management, 27, p.243–

249.