contract documents & technical...

81
CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONS Ralston Flood Mitigation Project Repairs Village of Ralston McIntyre Township, Lycoming County, PA Prepared for: MCINTYRE TOWNSHIP SUPERVISORS PO Box 171 Ralston, PA 17763 Prepared by: LARSON DESIGN GROUP 1000 Commerce Park Drive, Suite 201 Williamsport, PA 17701 LDG Project No. 5713-013 March 2015 SUBMISSION QUALITY ASSURANCE Prepared By: DJS Date: 1/21/2015 Checked By: JTS Date: 1/30/2015 QA/QC’d By: KAB Date: 2/20/2015

Upload: doanthuan

Post on 01-Sep-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONS Ralston Flood Mitigation Project Repairs Village of Ralston McIntyre Township, Lycoming County, PA Prepared for:

MCINTYRE TOWNSHIP SUPERVISORS PO Box 171 Ralston, PA 17763 Prepared by:

LARSON DESIGN GROUP 1000 Commerce Park Drive, Suite 201 Williamsport, PA 17701 LDG Project No. 5713-013 March 2015

SUBMISSION QUALITY ASSURANCE

Prepared By: DJS Date: 1/21/2015 Checked By: JTS Date: 1/30/2015 QA/QC’d By: KAB Date: 2/20/2015

Page 2: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

TABLE OF CONTENTS ____________________________________________________________________________________________ ADVERTISEMENT FOR BIDS INFORMATION FOR BIDDERS ..................................................................................................... 1.1 - 1.3 BID PACKAGE ................................................................................................................................. 2.1 - 2.7 AGREEMENT PACKAGE ............................................................................................................. 3.1 - 3.14 GENERAL CONDITIONS .............................................................................................................. 4.1 - 4.21 PAYMENT ITEMS ......................................................................................................................... 5.1 - 5.11 SPECIAL CONDITIONS .................................................................................................................. 6.1 - 6.2 DEP/USACOE STANDARD JOINT PERMIT ........................................................................................ 7.1 PA PREVAILING WAGE RATES ................................................................................................. 8.1 - 8.14 ____________________________________________________________________________________________

Page 3: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

ADVERTISEMENT FOR BIDS

Owner: McIntyre Township Supervisors PO Box 171 Ralston, PA 17763 Sealed bids for Ralston Flood Mitigation Project Repairs, which involves sediment removal and construction of rock protection along Lycoming Creek in the Village of Ralston in Lycoming County, PA, will be received by Larson Design Group, 1000 Commerce Park Drive, Suite 201, Williamsport, PA, 17701, until 1:00 p.m. (prevailing time), March 19, 2015. The bids will be publicly opened and read aloud on March 19, 2015 at the Transportation Conference Room, 1020 Commerce Park Drive, Entrance B, Williamsport, PA 17701, at 1:00 p.m. The bidders and the public are welcome to attend the meeting. Sets of the CONSTRUCTION DRAWINGS and the CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONS must be obtained from the following website; bidplans.larsondesigngroup.com. Interested parties are required to register on the website for the ability to view and/or acquire the Construction Drawings and the Contract Documents & Technical Specifications for this project. It is the responsibility of any person or organization interested in a hard copy of the Bidding Documents to pay all costs associated with printing. Contact the Engineer, Larson Design Group, 1000 Commerce Park Drive, Suite 201, Williamsport, PA 17701; 570-323-6603 between the hours of 8:00 a.m. and 5:00 p.m., Monday through Friday, with any questions pertaining to access and use of the website. Each BID must be accompanied by a Bid Bond payable to the Owner for ten percent (10%) of the total amount of the BID. As soon as the BID prices have been compared, the Owner will return the Bonds of all except the three lowest responsible bidders. When the Agreement is executed, the bonds of the two remaining unsuccessful bidders will be returned. Bidders must submit with their initial bid, a statement as to whether they have previously performed work subject to the President's Executive Order No. 11246 (30 F.R. 12319-25) "Equal Opportunity Clause". The Owner reserves the right to reject any or all bids, to waive any informalities in the bidding, or to limit the scope of work involved. No bidder may withdraw a bid within sixty (60) days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period; the time may be extended by mutual agreement between the Owner and the Bidder. Pennsylvania Department of Transportation prequalification is not required for this contract; however, contractor should be able to provide proof of prior experience. Bidders are advised that PA prevailing wage rates apply to contracts in excess of $100,000. March 2015 McIntyre Township Supervisors

Page 4: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

INFORMATION FOR BIDDERS Bids will be received by Larson Design Group on behalf of the McIntyre Township Supervisors (herein called the "Owner") at the Larson Design Group Williamsport, PA office until 1:00 p.m., March 19, 2015. The bids will be publicly opened and read aloud on the same day at the Transportation Conference Room, 1020 Commerce Park Drive, Entrance B, Williamsport, PA 17701, at 1:00 p.m. The bidders and the public are welcome to attend the meeting. Each Bid must be submitted in a sealed envelope, addressed to:

Kurt Brungard, P.E. Larson Design Group

1000 Commerce Park Drive, Suite 201 Williamsport, PA 17701

Each sealed envelope containing a Bid must be plainly marked on the outside as “BID FOR RALSTON FLOOD MITIGATION PROJECT REPAIRS” and the envelope should bear on the outside the name of the bidder, bidder’s address, license number (if applicable), and the name of the project for which the Bid is submitted. Only one copy of the Bid Form is required. The Owner may waive any informalities or minor defects or reject any and all bids. Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified shall not be considered. No bidder may withdraw a bid within 60 days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period; the time may be extended by mutual agreement between the Owner and the Bidder. Bidders must satisfy themselves of the accuracy of the estimated quantities in the Bid Schedule by examination of the site and a review of the drawings and specifications including Addenda. After bids have been submitted, the Bidder shall not assert that there was a misunderstanding concerning the quantities of work or of the nature of the work to be done. Each Bidder is required to check with the Owner for posted Addenda. The Owner shall provide to bidders prior to bidding, all information that is pertinent to, and delineates and describes, the land owned and rights-of-way acquired or to be acquired. The Contract Documents contain the provisions required for the construction of the Project. Information obtained from an officer, agent, or employee of the Owner or any other person shall not affect the risks or obligations assumed by the Contractor or relieve him from fulfilling any of the conditions of the Contract. Each Bid must be accompanied by a Bid Bond* payable to the Owner for ten percent (10%) of the total amount of the Bid. As soon as the Bid prices have been compared, the Owner will return the Bonds of all except the three lowest responsible Bidders. When the Agreement is executed, the Bonds of the two remaining unsuccessful Bidders will be returned. A certified check may be used in lieu of a Bid Bond. A Performance Bond* and Payment Bond*, each in the amount of 100% of the Contract Price, with a corporate surety approved by the Owner, will be required for the faithful performance of the contract. Attorneys-in-fact who sign Bid Bonds or Payment Bonds and Performance Bonds must file with each Bond a certified and effective dated copy of their power of attorney. The party to whom the contract is awarded will be required to execute the Agreement and obtain the Performance Bond and Payment Bond within ten (10) calendar days from the date when Notice of Award

1.1

Page 5: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

is delivered to the Bidder. The Notice of Award shall be accompanied by the necessary Agreement and Bond Forms. In case of failure of the Bidder to execute the Agreement, the Owner may at his option consider the Bidder in default, in which case the Bid Bond accompanying the proposal shall become the property of the Owner. The Owner, within ten (10) days of receipt of acceptable Performance Bond, Payment Bond, and Agreement signed by the party to whom the Agreement was awarded, shall sign the Agreement and return to such party an executed duplicate of the Agreement. Should the Owner not execute the Agreement within such period, the Bidder may by written notice withdraw his signed Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by the Owner. The Notice to Proceed date shall be issued within thirty (30) days of the execution of the Agreement by the Owner. Should there be reasons why the Notice to Proceed cannot be issued within such period; the time may be extended by mutual agreement between the Owner and Contractor. If the Notice to Proceed has not been issued within the thirty (30) day period or within the period mutually agreed upon, the Contractor may terminate the Agreement without further liability on the part of either party. An in-stream construction restrictions will be in place from March 1st to June 15th and from October 1st to December 31st. No work can be performed in the stream during the construction restriction; therefore, the anticipated start date in the field is June 16, 2015 with 75 consecutive days to complete the project. Bidders are not required to be Pennsylvania Department of Transportation prequalified for the proposed work to be done, however, contractor should be able to provide proof of prior experience relevant to the contract work. The Owner may make such investigations as he deems necessary to determine the ability of the Bidder to perform the Work, and the Bidder shall furnish to the Owner all such information and data for this purpose as the Owner may request. The Owner reserves the right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the Owner that such Bidder is properly qualified to carry out the obligations of the Agreement and to complete the Work contemplated therein. A conditional or qualified Bid will not be accepted. * Bonds shall be signed by a guaranty or surety company listed in the latest issue of the U.S. Treasury Circular 570 and the penal sum shall be within the maximum specified for such company in said Circular 570. After the proposals are opened, the total bid amount in the schedule and the name of the apparent low bidder will be publicly announced. Proposals will then be compared, on the basis of adding the products of the approximate quantities shown in the Bid Schedule, multiplied by the unit bid prices. Bid proposals will then be promptly verified and if judged by the Owner to be satisfactory, the results of the determination of the lowest responsible bidder will be made available to the public based on the corrected extensions. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the Project shall apply to the contract throughout. Each Bidder is responsible for inspecting the site and for reading and being thoroughly familiar with the Contract Document. The failure or omission of any Bidder to do any of the foregoing shall in no way relieve any Bidder from any obligation in respect to his Bid. Further, the Bidder agrees to abide by the requirements under Executive Order No. 11246, as amended, including specifically the provisions of the equal opportunity clause set forth in the Supplemental General Conditions. The low Bidder shall supply the names and addresses of major material suppliers and subcontractors when requested to do so by the Owner.

1.2

Page 6: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

All Construction Drawings are based on an 11”x17” ANSI “B” format and the Contract Documents on an 8.5”x11” letter format. Neither the Owner nor Engineer assumes the responsibility for errors or misinterpretations resulting from incomplete sets or improperly printed Bidding Documents. All requests for information or document clarifications during the bid process shall be emailed through the website; bidplans.larsondesigngroup.com. In person, telephone and/or facsimile questions will not be accepted. All responses and addendums will be posted on the website. The Engineer is:

Larson Design Group 1000 Commerce Park Drive, Suite 201 Williamsport, PA 17701 (570) 323-6603

1.3

Page 7: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

BID PACKAGE

Bid .............................................................................................................................................................. 2.1

Bid Schedule .............................................................................................................................................. 2.2

Bid Bond .................................................................................................................................................... 2.4

Certification of Bidder Regarding Equal Employment Opportunity ......................................................... 2.5

Non-Collusion Bidding Certification ........................................................................................................ 2.7

Page 8: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

BID

Proposal of _____________________________________ (hereinafter called "Bidder"), organized and existing under the laws of the Commonwealth of Pennsylvania doing business as ____________________________________________.*

To the McIntyre Township Supervisors (hereinafter called "Owner").

In compliance with your Advertisement for Bids, Bidder hereby proposes to perform all work for the Ralston Flood Mitigation Project Repairs in strict accordance with the Contract Documents, within the time set forth therein, and at the prices stated below.

By submission of this Bid, each Bidder certifies, and in the case of a joint Bid each party thereto certifies as to his own organization, that the prices in this bid have been arrived at independently without collusion, communication, or agreement as to any matter relating to this Bid with any other Bidder or with any competitor.

Bidder hereby agrees to commence work under this contract on a date to be specified in the Notice to Proceed and to fully complete the project within 75 days. The Bidder further agrees to pay as liquidated damages, the sum of $200.00 for each consecutive calendar day thereafter as provided in Section 14 of the General Conditions.

Bidder acknowledges receipt of the following Addendum:

___________________________________________________________________________________ ___________________________________________________________________________________

*Insert "a corporation", "a partnership", or "an individual" as applicable.

The Bidder shall submit a Unit Price Bid (except where pay items require a lump sum bid) for all work included in this contract. On the following pages, the Bidder shall break down his Unit Price Bid by each item listing the unit price and extension by which he arrived at his Unit Price Bid. These items are estimated approximate quantities provided to the Bidder to be used as a guide. The Bidder shall be satisfied to the accuracy of these quantities prior to submitting the Bid.

The Unit Prices will be used to negotiate Change Orders should the Owner desire to increase or decrease the Scope of the Project. All Change Orders shall be executed on the Document provided in Section 3 and subject to the terms set forth in Sections 13 and 14 of the General Conditions.

The Owner reserves the right to reject any or all Bids.

2.1

Page 9: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

RALSTON FLOOD MITIGATION PROJECT REPAIRS

BID SCHEDULE

Bidder agrees to perform all work described in the Contract Documents for the following unit prices:

Item No. Description Unit Estimated

Quantity Unit Price Total

1 Mobilization LS 1

2 Construction Access LS 1

3 Sediment Deposit Removal LS 1

4 Rock, Class R-7 TON 331

5 Diversion Dike System LS 1

6 Mud Sill Cribbing LS 1

UNIT PRICE BID (Total of 1 through 6) ...................................... $ _______________________

(Bid shall include sales tax and all other applicable taxes and fees).

Bidder agrees to perform all the work described in the Contract Documents for the following sum of Pay Items 1 through 6.

TOTAL UNIT PRICE BID WRITTEN IN WORDS __________________________________________

___________________________________________________________________________________

2.2

Page 10: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

Respectfully submitted:

___________________________________________________________________________________ Bidder

______________________________________ ______________________________________ Signature Address

______________________________________ ______________________________________ Title Date

Telephone No. ___________________________

License No. (if applicable) _________________

(Seal - If Bid is by a Corporation)

ATTEST _______________________________ (Witness)

Please complete information requested below:

Federal Identification No. __________________

The P.O. Address of the Bidder is:

______________________________________ Street

______________________________________ City, State & Zip

______________________________________ Phone Number

If a Corporation:

Name __________________________________ President ______________________________

Address ________________________________ Secretary ______________________________

______________________________________ Treasurer ______________________________

If a Firm:

Name __________________________________

Address ________________________________

______________________________________

2.3

Page 11: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

BID BOND

KNOW ALL MEN BY THESE PRESENT, that we, the undersigned, _______________________ as Principal, and ________________________________________ as Surety, are hereby held and firmly bound unto the McIntyre Township Supervisors as Owner in the penal sum of $___________________ for the payment of which, well and truly to be made, we hereby jointly and severally bind ourselves, successors and assigns.

Signed, this _________ day of ______________________________, 20___.

The condition of the above obligation is such that whereas the Principal has submitted to the McIntyre Township Supervisors a certain Bid, attached hereto and hereby made a part hereof to enter into a contract in writing, for the Ralston Flood Mitigation Project Repairs.

NOW, THEREFORE,

(a) If said Bid shall be rejected, or (b) If said Bid shall be accepted and the Principal shall execute and deliver a contract in the form of Contract attached hereto (properly completed in accordance with said Bid) and shall furnish a Bond for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the agreement created by the acceptance of said Bid.

Then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood as agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated.

The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and it's Bond shall be in no way impaired or affected by any extension of the time within which the Owner may accept such Bid; and said Surety does hereby waive notice of any such extension.

IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals and such of them as are corporations have caused their corporate seals to be hereto affixed and these presents to be signed by their proper offices, the day and year first set forth above.

______________________________________ Principal ______________________________________ Surety

By: ____________________________________

IMPORTANT - Surety companies executing Bonds must appear on the Treasury Department's most current list (Circular 570) as amended) and be authorized to transact business in the state where the project is located.

2.4

Page 12: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT

CERTIFICATION OF BIDDER REGARDING EQUAL EMPLOYMENT OPPORTUNITY

___________________________________________________________________________________ INSTRUCTIONS

___________________________________________________________________________________

This certification is required pursuant to Executive Order 11246 (30 F.R. 12319-25). The implementing rules and regulations provide that any bidder or prospective contractor, or any of their proposed subcontractors, shall state as an initial part of the bid or negotiations of the contract whether it has participated in any previous contract or subcontract subject to the equal opportunity clause; and, if so, whether it has filed all compliance reports due under applicable instructions.

Where the certification indicates that the bidder has not filed a compliance report due under applicable instructions, such bidder shall be required to submit a compliance report within seven calendar days after bid opening. No contract shall be awarded unless such report is submitted.

___________________________________________________________________________________ CERTIFICATION BY BIDDER

___________________________________________________________________________________

Name and Address of Bidder (include zip code)

___________________________________________________________________________________

1. Bidder has participated in a previous contract or subcontract subject to the Equal OpportunityClause.{ } Yes { } No_____________________________________________________________________________

2. Compliance reports were required to be filed in connection with such contract or subcontract.{ } Yes { } No_____________________________________________________________________________

3. Bidder has filed all compliance reports due under applicable instructions, including SF-100.{ } Yes { } No { } None Required_____________________________________________________________________________

4. Have you ever been or are you being considered for sanction due to violation of Executive Order11246, as amended?{ } Yes { } No_____________________________________________________________________________

2.5

Page 13: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

______________________________________ NAME AND TITLE OF SIGNER (Please type)

______________________________________ ______________________________________ SIGNATURE DATE

Replaces Form HUD-238.CD-1, which is Obsolete HUD-950.1

2.6

Page 14: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

NON-COLLUSION BIDDING CERTIFICATION

By submission of this bid, each bidder and each person signing on behalf of any bidder, certifies, and in the case of a joint bid, each party thereto certifies as to its own organization, under penalty of perjury, that to the best of knowledge and belief:

1. The prices in this bid have been arrived at independently without collusion, consultation,communication, or agreement for the purpose of restricting competition as to any matter relatingto such prices with any other bidder or with any competitor;

2. Unless otherwise required by law, the prices which have been quoted in this bid have not beenknowingly disclosed by the bidder and will not knowingly be disclosed by the bidder prior toopening, directly or indirectly, to any other bidder or to any competitor; and

3. No attempt has been made or will be made by the bidder to induce any other person, partnership,or corporation to submit or not to submit a bid for the purpose of restricting competition.

______________________________________

______________________________________

______________________________________

Subscribed and sworn to before me this _______ day of ____________________, 20___

Title_____________________________________________

My commission expires_____________________________

NOTE: If Bidder is a Corporation, the corporate name and title of officer signing must be stated.

2.7

Page 15: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

AGREEMENT PACKAGE

Agreement .................................................................................................................................................. 3.1

Payment Bond ............................................................................................................................................ 3.3

Performance Bond ..................................................................................................................................... 3.5

Notice of Award......................................................................................................................................... 3.7

Notice to Proceed ....................................................................................................................................... 3.8

Change Order ............................................................................................................................................. 3.9

Certificate of Substantial Completion ..................................................................................................... 3.10

Consent of Surety for Final Payment ....................................................................................................... 3.12

Affidavit of Release of Liens ................................................................................................................... 3.13

Punch List ................................................................................................................................................ 3.14

Page 16: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

AGREEMENT

This AGREEMENT, made this ________ of _____________________, 20___, by and between the McIntyre Township Supervisors, hereinafter called "Owner" and ________________________________ doing business as (an individual), or (a partnership), or (a corporation) hereinafter called "Contractor".

WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned:

1. The Contractor will commence and complete the construction of:

Ralston Flood Mitigation Project Repairs

2. The Contractor will furnish all of the material, supplies, tools, equipment, labor andother services necessary for the construction and completion of the Project describedherein.

3. The Contractor will commence the work required by the Contract Documents on the datespecified in the Notice to Proceed and to fully complete the project within 60 days unlessthe period for completion is extended otherwise by the Contract Documents.

4. The Contractor agrees to perform all of the work described in the Contract Documentsand comply with the terms therein for the sum of$_______________________________, or as shown in the Bid Schedule.

5. The term "Contract Documents" means and includes the following:

a.) Advertisement for Bids b.) Information for Bidders c.) Bid d.) Bid Bond e.) Agreement f.) General Conditions g.) Supplemental General Conditions h.) Payment Bond i.) Performance Bond j.) Notice of Award k.) Notice to Proceed l.) Change Order m.) Specifications and location plans prepared or issued by

Larson Design Group, Inc. n.) Addenda:

No. _____ dated ____________ No. _____ dated ____________ No. _____ dated ____________ No. _____ dated ____________

6. The Owner will pay to the Contractor in the manner and at such times as set forth in theGeneral Conditions such amounts as required by the Contract Documents.

7. This Agreement shall be binding upon all parties hereto and their respective heirs,executors, administrators, successors, and assigns.

IN WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized officials, this Agreement in each of which shall be deemed an original on the date first above written.

3.1

Page 17: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

OWNER:

McIntyre Township Supervisors

By ___________________________________

Name _________________________________ (please type)

Address _______________________________

_________________________________ (SEAL) ATTEST ______________________________

Name _________________________________ (please type)

Title ___________________________________ CONTRACTOR: _______________________

By ___________________________________

Name _________________________________ (please type)

Address _______________________________

_________________________________ (SEAL) ATTEST ______________________________

Name _________________________________ (please type)

Title ___________________________________

3.2

Page 18: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS; THAT

___________________________________________________________________________________ (Name of Contractor)

___________________________________________________________________________________ (Address of Contractor)

a __________________________________________________________________________________ (Corporation, Partnership or Individual)

hereinafter called Principal.

and ________________________________________________________________________________ (Name of Surety)

___________________________________________________________________________________ (Address of Surety)

hereinafter called Surety, are held and firmly bound unto

McIntyre Township Supervisors (Name of Owner)

P.O. Box 171, Ralston, PA 17763 (Address of Owner)

hereinafter called Owner,

in the penal sum of _______________________________________ Dollars, ($____________)

in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the Owner, dated the______day of ______________________, 20___, a copy of which is hereto attached and made a part hereof for the construction of:

Ralston Flood Mitigation Project Repairs

NOW, THEREFORE, if the Principal shall promptly make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the Work provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such Work, and all insurance premiums on said Work, and for all labor performed in such Work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED FURTHER, that the said Surety for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the Work to be performed thereunder or the specifications accompanying the same shall in any way affect it's obligation

3.3

Page 19: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

on this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the term of the contract or to the Work or to the specifications.

PROVIDED FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

IN WITNESS WHEREOF, this instrument is executed in ___________ counterparts, each one of which shall be deemed an original, this the ____________ day of ____________________________, 20___.

ATTEST: ______________________________________ (Principal)

______________________________________ (Principal) Secretary

(SEAL) By _________________________________ (s)

____________________________________ (address)

____________________________________ ______________________________________ Witness as to Principal

______________________________________ (Address)

______________________________________ ______________________________________ Surety

ATTEST: by ___________________________________ Attorney-in-Fact

______________________________________ ______________________________________

Witness as to Surety ______________________ (Address)

______________________________________ ______________________________________ (Address)

______________________________________

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute Bond.

IMPORTANT: Surety companies executing Bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located.

3.4

Page 20: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS: that

___________________________________________________________________________________ (Name of Contractor)

___________________________________________________________________________________ (Address of Contractor)

______________________________________ hereinafter called Principal (Corporation, Partnership or Individual)

and _________________________________________________________________________________ (Name of Surety)

__________________________________________________________________________________ (Address of Surety)

hereinafter called Surety, are held and firmly bound into

McIntyre Township Supervisors (Name of Owner)

P.O. Box 171, Ralston, PA 17763 (Address of Owner)

hereinafter called Owner, in the penal sum of _________________________________________ Dollars, ($________________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the Owner, dated the ________ day of _______________________, 20___, a copy of which is hereto attached and made a part hereof for the construction of:

Ralston Flood Mitigation Project Repairs

NOW THEREFORE, if the Principal shall well, truly and faithfully perform it's duties, all the undertakings, covenants, terms, conditions, and agreements of said contract during the original term thereof, and any extensions thereof which may be granted by the Owner, with or without notice to the Surety and during the one year guaranty period, and if he shall satisfy all claims and demands incurred under such contract, and shall fully indemnify and save harmless the Owner from all costs and damages which it may suffer by reason of failure to do so, and shall reimburse and repay the Owner all outlay and expense which the Owner may incur in making good any default, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED FURTHER, that the said surety, for value received hereby stipulates and agrees that no change, extension of time alteration or addition to the terms of the contract or to work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this Bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the work, or to the specifications.

PROVIDE FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

3.5

Page 21: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

IN WITNESS WHEREOF, this instrument is executed in counterparts, each one of which shall be deemed an original, this the day of , 20___.

ATTEST: ______________________________________ (Principal)

______________________________________ By____________________________________ (Principal) Secretary

(SEAL)

______________________________________ ______________________________________ (Witness as to Principal) (Address)

______________________________________ ______________________________________ (Address)

______________________________________ ______________________________________ Surety

ATTEST:

______________________________________ (Surety) Secretary

(SEAL)

______________________________________ By____________________________________ (Witness as to Surety) (Attorney-in-Fact)

______________________________________ ______________________________________ (Address) (Address)

______________________________________ ______________________________________

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is Partnership, all partners should execute Bond.

IMPORTANT: Surety companies executing Bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located.

3.6

Page 22: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

NOTICE OF AWARD

To: ______________________________________

______________________________________

______________________________________

______________________________________

Project Description: Ralston Flood Mitigation Project Repair

The Owner has considered the Bid submitted by you for the above described work in response to its Advertisement for Bids dated _____________________________________ and Information for Bidders.

You are hereby notified that your Bid has been accepted for items in the amount of $________________________.

You are required by the Information for Bidders to execute the Agreement and furnish the required Contractor's Performance Bond, Payment Bond, and Certificates of Insurance within ten (10) calendar days from the date of this Notice to you.

If you fail to execute said Agreement and to furnish said Bonds within ten (10) days from the date of this Notice, said Owner will be entitled to consider all your rights arising out of the Owner's acceptance of your Bid as abandoned and as a forfeiture of your Bid Bond. The Owner will be entitled to such other rights as may be granted by law.

You are required to return an acknowledged copy of this Notice of Award to the Owner.

Dated this _________ day of _________________________, 20___.

MCINTYRE TOWNSHIP SUPERVISORS

By __________________________________________

Title ________________________________________

ACCEPTANCE OF NOTICE

Receipt of the above Notice of Award is hereby acknowledged

by __________________________________________

this the ______ day of _______________________, 20___

By __________________________________________

Title ________________________________________

3.7

Page 23: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

NOTICE TO PROCEED

To: Date:

Project:

Ralston Flood Mitigation Project Repairs

You are hereby notified to commence work in accordance with the Agreement dated ___________________, on or before _______________________ you are to complete the work no later than ________________________________________.

The date of completion of all work is therefore___________________________.

MCINTYRE TOWNSHIP SUPERVISORS

By __________________________________________

Title ________________________________________

ACCEPTANCE OF NOTICE

Receipt of the above Notice to Proceed is hereby acknowledged by

____________________________________________

this the _____ day of ________________________, 20___

By __________________________________________

Title _________________________________________

3.8

Page 24: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

CHANGE ORDER

Change Order No. ________________________ Date __________________________________

Owner's Project No. ______________________ Engineer's Project No. 5713-013

Project: Ralston Flood Mitigation Owner: McIntyre Township Supervisors Project Repairs

Contractor _____________________________ Contract Date __________________________

To: CONTRACTOR

The following changes are hereby made to the Contract Documents:

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

Enclosures:

The changes result in the following adjustment of Contract Price and Time:

Contract Price Prior to This Change Order ............................................................. $ _________________

Net (Increase) (Decrease) Resulting From this Change Order ................................ $ _________________

Current Contract Price Including This Change Order ............................................. $ _________________

Contract Time Prior to this Change Order ............................................................... _______Calendar Days

Net (Increase) (Decrease) Resulting from this Change Order ................................. _______Calendar Days

Current Contract Time Including this Change Order .............................................. _______Calendar Days

Requested by: The Above Changes Are Approved:

Owner _________________________________ Engineer ______________________________

By ____________________________________ By ___________________________________

Date __________________________________ Date __________________________________

The Above Changes are Accepted:

Contractor _____________________________

By ____________________________________

Date __________________________________

3.9

Page 25: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

CERTIFICATE OF SUBSTANTIAL COMPLETION

To: ________________________________________________________________________________

Date of Substantial Completion _____________ Project Title ___________________________

Project or Specified Part Shall Include: ______________________________________

______________________________________ Project No. _____________________________

______________________________________ Location: ______________________________

______________________________________ Owner: _______________________________

______________________________________ Contractor: ____________________________

______________________________________ Contract For: ___________________________

______________________________________ Contract Date: __________________________

The Work performed under this contract has been inspected by authorized representatives of the Owner, Contractor, and Engineer-Architect, and the Project (or specified part of the Project, as indicated above) is hereby declared to be substantially completed on the above date.

_________________________________________________________

DEFINITION OF SUBSTANTIAL COMPLETION

The date of substantial completion of a project or specified area of a project is the date when the construction is sufficiently completed, in accordance with the contract documents, as modified by any change orders agreed to by the parties, so that the Owner can occupy or utilize the project or specified area of the project for the use for which it was intended. _________________________________________________________

A tentative list of items to be completed or corrected is appended hereto. This list may not be exhaustive, and the failure to include an item on it does not alter the responsibility of the Contractor to complete all the work in accordance with the contract documents.

Larson Design Group By _____________________________________ Engineer Authorized Representative Date

The Contractor accepts the above Certificate of Substantial Completion and agrees to complete and correct the items on the tentative list within the time indicated.

By _____________________________________ Contractor Authorized Representative Date

3.10

Page 26: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

The Owner accepts the project or specified area of the project as substantially complete and will assume full possession of the project or specified area of the project at ____________(time), on _______________________(date). The responsibility for heat, utilities, security, and insurance under the contract documents shall be as set forth under "Remarks" below.

By _____________________________________ Owner Authorized Representative Date

Remarks:

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

3.11

Page 27: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

CONSENT OF SURETY FOR FINAL PAYMENT

Project Name: Ralston Flood Mitigation Project Repairs

Project No.: 5713-013 Contract No.: __________________________

Type of Contract : _____________________________________________________________________

Amount of Contract : __________________________________________________________________

In accordance with the provisions of the above-named contract between the Owner and the Contractor, the following named surety:

___________________________________________________________________________________

___________________________________________________________________________________

on the Payment Bond of the following named Contractor:

___________________________________________________________________________________

___________________________________________________________________________________

hereby approves of final payment to the Contractor, and further agrees that said final payment to the Contractor shall not relieve the Surety Company named herein of any of its obligations to the following named Owner as set forth in said Surety Company's bond:

___________________________________________________________________________________

___________________________________________________________________________________

IN WITNESS WHEREOF, the Surety Company has hereunto set its hand and seal this ________ day of ______________________________, 20___.

____________________________________________ (Name of Surety Company)

____________________________________________ (Signature of Authorized Representative)

Title ________________________________________

(Affix Corporate Seal Here)

3.12

Page 28: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

AFFIDAVIT OF RELEASE OF LIENS

TO ALL WHOM IT MAY CONCERN:

WHEREAS, the undersigned has been employed by _________________________________________

to furnish labor and materials for _________________________________________________________

_______________________________________________________________________________ work,

under a contract _______________________________________________________________________

for the improvement of the property described as ____________________________________________

___________________________________________________________________________________

in the _____________________________________ of _____________________________________

County of _____________________________ , State of _____________________________________

of which __________________________ is the Owner.

NOW THEREFORE, this _______ day of _____________________________, 20___,

The undersigned, as the Contractor for the above-named Contract hereby certifies that to the best of his knowledge, information and belief, except as listed below, the Releases or Waivers of Lien attached hereto include the Contractor, all Subcontractors, all suppliers of materials and equipment, and all performers of work, labor or services, who have or may have liens against any property of the Owner arising in any manner out of the performance of the Contract referenced above.

EXCEPTIONS: (If none, write "None". If required by the Owner, the Contractor shall furnish bond satisfactory to the Owner for each exception).

___________________________________________________________________________________

___________________________________________________________________________________

ATTACHMENTS:

1. Contractor's Release or Waiver of Liens, conditional upon receipt of final payment.2. Separate Releases or Waivers of Liens for Subcontractors and material and equipment suppliers.

______________________________________ (SEAL) Contractor (Name of sole ownership, corporation or partnership)

______________________________________ (SEAL) (Signature of Authorized Representative)

(Affix Corporate Seal Here) Title: _______________________________________

3.13

Page 29: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PUNCH LIST

Project: Ralston Flood Mitigation Project Repairs No.: 5713-013

Location Date _____________

Inspection was conducted at the above project by ____________________________________________

at ____________________ o'clock on this date.

REPRESENTATION

CONTRACTOR-OWNER ENGINEER

Contractor _____________________________ Design ________________________________

Owner _________________________________ Staff Spec. _____________________________

__________________________________ Job Supervisor _________________________

The following items are to be corrected or completed to comply with the contract documents:

Type of Inspection Check Final 1 Yr. Guar. Guar.

No. Item

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

___________________________________________________________________________________

DISTRIBUTION: 1. Project Manager2. Contractor's Representative3. Resident Project Representative4. File

3.14

Page 30: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

GENERAL CONDITIONS

Definitions ................................................................................................................................................. 4.1 Additional Instructions & Detail Drawings ............................................................................................... 4.3 Schedules, Reports & Records .................................................................................................................. 4.3 Drawings & Specifications ........................................................................................................................ 4.3 Materials, Services & Facilities ................................................................................................................. 4.4 Inspection & Testing .................................................................................................................................. 4.4 Substitutions .............................................................................................................................................. 4.5 Patents ........................................................................................................................................................ 4.5 Surveys, Permits, Regulations ................................................................................................................... 4.6 Protection of Work, Property, Persons ...................................................................................................... 4.6 Supervision by Contractor ......................................................................................................................... 4.7 Changes in the Work .................................................................................................................................. 4.7 Changes in Contract Price ......................................................................................................................... 4.8 Time for Completion & Liquidated Damages ......................................................................................... 4.10 Correction of Work .................................................................................................................................. 4.11 Subsurface Conditions ............................................................................................................................. 4.11 Suspension of Work, Termination & Delay ............................................................................................ 4.11 Payments to Contractor ............................................................................................................................ 4.14 Acceptance of Final Payment as Release ................................................................................................ 4.15 Insurance .................................................................................................................................................. 4.15 Contract Security ..................................................................................................................................... 4.18 Assignments ............................................................................................................................................. 4.18 Indemnification ........................................................................................................................................ 4.18 Separate Contracts ................................................................................................................................... 4.19 Subcontracting ......................................................................................................................................... 4.19 Engineer's Authority ................................................................................................................................ 4.20 Land and Rights-of-Way .......................................................................................................................... 4.20 Guarantee ................................................................................................................................................. 4.21 Arbitration ................................................................................................................................................ 4.21 Taxes ........................................................................................................................................................ 4.21 Compliance .............................................................................................................................................. 4.21

Page 31: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

DEFINITIONS

1.1 Wherever used in the Contract Documents, the following terms shall have the meanings indicated which shall be applicable to both the singular and plural thereof:

1.2 ADDENDA - Written or graphic instruments issued prior to the receipt of bids which

modify or interpret the Contract Documents, Drawings, and Specifications, by additions, deletions, clarifications, or corrections.

1.3 BID - The offer or proposal of the bidder submitted on the prescribed form setting forth

the prices for the work to be performed. 1.4 BIDDER - Any person, firm, or corporation submitting a bid for the work. 1.5 BONDS - Bid, Performance, and Payment Bonds, and other instruments of security,

furnished by the contractor and his surety in accordance with the Contract Documents. 1.6 CHANGE ORDER - A written order to the contractor after the acceptance of the

Agreement has been signed authorizing an addition, deletion, or revision in the work within the general scope of the Contract Documents or authorizing an adjustment in the contract price or contract time.

1.7 CONTRACT DOCUMENTS - The contract, including Advertisement for Bids,

Information for Bidders, Bid, Bid Bond, Agreement, Payment Bond, Performance Bond, Notice of Award, Notice to Proceed, Change Order, Drawings, Specifications, and Addenda.

1.8 CONTRACT PRICE - The total monies payable to the contractor under the Terms and

Conditions of the Contract Documents. 1.9 CONTRACT TIME - The number of calendar days stated in the Contract Documents for

the completion of the work. 1.10 CONTRACTOR - The person, firm, or corporation named as such in the Contract

Documents. 1.11 DRAWINGS - The part of the Contract Documents which show the characteristics and

scope of the work to be performed and which have been prepared or approved by the Engineer.

1.12 ENGINEER - The person, firm, or corporation named as such in the Contract

Documents.

4.1

Page 32: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

1.13 FIELD ORDER - A written order effecting a change in the work not involving an adjustment in the Contract Price or an extension of the Contract time, issued by the Engineer to the Contractor during construction.

1.14 NOTICE OF AWARD - The written notice of the acceptance of the Bid from the Owner

to the successful bidder. 1.15 NOTICE TO PROCEED - Written communication issued by the Owner to the Contractor

authorizing him to proceed with the work and establishing the date of commencement of the work.

1.16 OWNER - A public or quasi-public body or authority, corporation, association,

partnership, or individual for whom the work is to be performed. 1.17 PROJECT - The undertaking to be performed as provided in the Contract Documents. 1.18 RESIDENT PROJECT REPRESENTATIVE - The authorized representative of the

Owner who is assigned to the project site or any part thereof. 1.19 SHOP DRAWINGS - All drawings, diagrams, illustrations, brochures, schedules, or

other data which are prepared by the Contractor, a subcontractor, manufacturer, supplier or distributor, which illustrate how specific portions of the work shall be fabricated or installed.

1.20 SPECIFICATIONS - A part of the Contract Documents consisting of written

descriptions of a technical nature of materials, equipment, construction systems, standards, and workmanship.

1.21 SUBCONTRACTOR - An individual, firm, or corporation having a direct contract with

the Contractor or with any other subcontractor for the performance of a part of the work at the site.

1.22 SUBSTANTIAL COMPLETION - That date, as certified by the Engineer when the

construction of the project or a specified part thereof is sufficiently completed, in accordance with the Contract Documents, so that the project or specified part can be utilized for the purposes for which it is intended.

1.23 SUPPLEMENTAL GENERAL CONDITIONS - Modifications to General Conditions

required by a federal agency for participation in the project and approved by the agency in writing prior to inclusion in the Contract Documents, or such requirements that may be imposed by applicable state laws.

1.24 SUPPLIER - Any person or organization who supplies materials or equipment for the

work, including that fabricated to a special design, but who does not perform labor at the site.

4.2

Page 33: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

1.25 WORK - All labor necessary to produce the construction required by the Contract

Documents, and all materials and equipment incorporated or to be incorporated in the project.

1.26 WRITTEN NOTICE - Any notice to any party of the Agreement relative to any part of

this Agreement in writing and considered delivered and the service thereof completed, when posted by certified or registered mail to the said party at his last given address, or delivered in person to said party or his authorized representative on the work.

2. ADDITIONAL INSTRUCTIONS & DETAIL DRAWINGS

2.1 The Contractor may be furnished additional instructions by the Owner or his

Representative, as necessary to carry out the work required by the Contract Documents.

3. SCHEDULES, REPORTS AND RECORDS 3.1 The Contractor shall submit to the Owner such schedule of quantities and costs, progress

schedules, payrolls, reports, estimates, records, and other data where applicable as are required by the Contract Documents for the work to be performed.

3.2 Prior to the first partial payment estimate, the Contractor shall submit construction

progress schedules showing the order in which he proposes to carry on the work, including dates at which he will start the various parts of the work, estimated date of completion of each part and, as applicable:

3.3 The Contractor shall also submit a schedule of payments that he anticipates he will earn

during the course of the work.

4. DRAWINGS & SPECIFICATIONS 4.1 The intent of the drawings and specifications is that the contractor shall furnish all labor,

materials, tools, equipment, and transportation necessary for the proper execution of the work in accordance with the Contract Documents and all incidental work necessary to complete the project in an acceptable manner, ready for use, occupancy or operation by the Owner.

4.2 Any discrepancies found between the drawings and specifications and site conditions or

any inconsistencies or ambiguities in the drawings or specifications shall be immediately reported to the OWNER or his representative, in writing, who shall promptly correct such inconsistencies or ambiguities in writing. Work done by the contractor after his discovery of such discrepancies, inconsistencies or ambiguities shall be done at the contractor's risk.

4.3

Page 34: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

5. MATERIALS, SERVICES & FACILITIES

5.1 It is understood that, except as otherwise specifically stated in the contract documents, the contractor shall provide and pay for all materials, labor, tools, equipment, water, light, power, transportation, supervision, temporary construction of any nature, and all other services and facilities of any nature whatsoever necessary to execute, complete, and deliver the work within the specified time.

5.2 Materials and equipment shall be so stored as to insure the preservation of their quality

and fitness for the work. Stored materials and equipment to be incorporated in the work shall be located so as to facilitate prompt inspection.

5.3 Manufactured articles, materials and equipment shall be applied, installed, connected,

erected, used, cleaned and conditioned as directed by the manufacturer. 5.4 Materials, supplies and equipment shall be in accordance with samples submitted by the

contractor and approved by the owner or his representative. 5.5 Materials, supplies or equipment to be incorporated into the work shall not be purchased

by the contractor or the subcontractor subject to a chattel mortgage or under a conditional sales contract or other agreement by which an interest is retained by the seller.

6. INSPECTION & TESTING

6.1 All materials and equipment used in the construction of the project shall be subject to adequate inspection and testing in accordance with generally accepted standards, as required and defined in the contract documents.

6.2 The owner shall provide all inspection and testing services not required by the contract

documents. 6.3 The contractor shall provide at his expense the testing and inspection services required

by the contract documents. 6.4 If the contract documents, laws, ordinances, rules, regulations or orders of any public

authority having jurisdiction require any work to specifically be inspected, tested, or approved by someone other than the contractor, the contractor will give the owner or his representative timely notice of readiness. The contractor will then furnish the owner or his representative the required certificates of inspection, testing or approval.

6.5 Inspections, tests or approvals by the owner or his representative or others shall not

relieve the contractor from his obligations to perform the work in accordance with the requirements of the contract documents.

4.4

Page 35: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

6.6 The owner or his representative will at all times have access to the work. In addition, authorized representatives and agents of any participating Federal or State agency shall be permitted to inspect all work, materials, payrolls, records of personnel, invoices of materials, and other relevant data and records. The contractor will provide proper facilities for such access and observation of the work and also for any inspection or testing thereof.

6.7 If any work is covered contrary to the written instructions of the owner or his

representative, it shall be uncovered for his observation and replaced at the contractor's expense.

6.8 If the owner or his representative considers it necessary or advisable that covered work

be inspected or tested by others, the contractor, at the owner or his representative's request, will uncover, expose or otherwise make available for observation, inspection or testing as the owner or his representative may require, that portion of the work in question, furnishing all necessary labor, materials, tools, and equipment. If it is found that such work is defective, the contractor will bear all the expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction. If, however, such work is not found to be defective, the contractor will be allowed an increase in the contract price or an extension of the contract time, or both, directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction and an appropriate change order shall be issued.

7. SUBSTITUTIONS

7.1 Whenever a material, article or piece of equipment is identified on the drawings or specifications by reference to brand name or catalog number, it shall be understood that this reference is for the purpose of defining the performance or other prominent requirements and that other products of equal capacities, quantity and function shall be considered. The contractor may recommend the substitution of any material, article, or piece of equipment of equal substance and function for those referred to in the contract documents by reference to brand name or catalog number, and if, in the opinion of the owner or his representative, such material, article, or piece of equipment is of equal substance and function to the specified, the owner or his representative may approve its substitution and use by the contractor. Any cost differential shall be deductible from the contract price and the contract documents shall be appropriately modified by change order. The contractor warrants that if substitutes are approved, no major changes in the function or general design of the project will result. Incidental charges or extra component parts required to accommodate the substitute will be made by the contractor without a change in the contract price or contract time.

8. PATENTS

8.1 The contractor shall pay all applicable royalties and license fees. He shall defend all

suits or claims for infringement of any patent rights and save the owner harmless from

4.5

Page 36: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

loss on account thereof, except that the owner shall be responsible for any such loss when a particular process, design, or the product of a particular manufacturer or manufacturers is specified; however, if the contractor has reason to believe that the design, process, or product specified is an infringement of a patent, he shall be responsible for such loss unless he promptly gives such information to the owner or his representative.

9. SURVEYS, PERMITS, REGULATIONS

9.1 The owner will furnish benchmarks and reference points. The contractor is responsible

for construction stakeout. This is incidental to mobilization. The contractor shall provide the owner and engineer with all layout information prior to the start of construction.

9.2 The contractor shall carefully preserve benchmarks and reference points and in case of

willful or careless destruction, he shall be charged with the resulting expense and shall be responsible for any mistakes that may be caused by their loss or disturbance.

9.3 Permits and licenses of a temporary nature necessary for the prosecution of the work

shall be secured and paid for by the contractor (the owner will secure PADEP General Permits as required). Permits, licenses and easements for permanent structures or permanent changes in existing facilities shall be secured and paid for by the owner, unless otherwise specified. The contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on the conduct of the work as drawn and at variance therewith, he shall promptly notify the owner or his representative in writing, and any necessary changes shall be adjusted as provided in Section 13, Changes in the Work.

10. PROTECTION OF WORK, PROPERTY AND PERSONS

10.1 The contractor will be responsible for initiating, maintaining and supervising all safety

precautions and programs in connection with the work. He will take all necessary precautions for the safety of, and will provide the necessary protection to prevent damage, injury or loss to all employees on the job and to other persons who may be affected thereby, all the work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and other property at the site or adjacent thereto, including trees, shrubs, lawn, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction.

10.2 The contractor will comply with all applicable laws, ordinances, rules, regulations and

orders of any public body having jurisdiction. He will erect and maintain, as required by the conditions and progress of the work, all necessary safeguards for safety and protection. He will notify owners of adjacent utilities when prosecution of the work may affect them. The contractor will remedy all damage, injury or loss to any property caused, directly or indirectly, in whole or in part, by the contractor, and subcontractor or anyone directly or indirectly employed by any of them or anyone for whose acts any of

4.6

Page 37: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

them be liable, except damage or loss attributable to the fault of the contract documents or to the acts or omissions of the owner or his representative or anyone employed by either of them or anyone for whose acts either of them may be liable, and not attributable, directly or indirectly, in whole or in part, to the fault or negligence of the contractor.

10.3 In emergencies affecting the safety of persons or the work or property at the site or

adjacent thereto, the contractor, without special instruction or authorization for the owner or his representative, shall act to prevent threatened damage, injury or loss. He will give the owner or his representative prompt written notice of any significant changes in the work or deviations from the contract documents caused thereby, and a change order shall thereupon be issued covering the charges and deviations involved.

11. SUPERVISION BY CONTRACTOR

11.1 The contractor will supervise and direct the work. He will be solely responsible for the

means, methods, techniques, sequences and procedures of construction. The contractor will employ and maintain on the work a qualified supervisor or superintendent who shall have been designated in writing by the contractor as the contractor's representative at the site. The supervisor shall have full authority to act on behalf of the contractor and all communications given to the supervisor shall be as binding as if given to the contractor. The supervisor shall be present on the site at all times as required to perform adequate supervision and coordination of the work.

12. CHANGES IN THE WORK

12.1 The owner may at any time, as the need arises, order changes within the scope of the

work without invalidating the Agreement. If such changes increase or decrease the amount due under the contract documents, or in the time required for performance of the work, an equitable adjustment shall be authorized by change order.

12.2 The owner or his representative, also, may at any time, by issuing a field order, make

changes in the details of the work. The contractor shall proceed with the performance of any changes in the work so ordered by the owner's representative, unless the contractor believes that such field order entitles him to a change in contract price or time, or both, in which event he shall give the owner or his representative written notice thereof within seven (7) days after the receipt of the ordered change. Thereafter the contractor shall document the basis for the change in contract price or time within thirty (30) days. The contractor shall not execute such changes pending the receipt of an executed change order or further instruction from the owner.

4.7

Page 38: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

13. CHANGES IN CONTRACT PRICE 13.1 The value of any change shall be determined by one or more of the following methods:

a. If applicable unit prices are contained in the Agreement (established as a result of a unit price bid, the owner may order the contractor to proceed with desired changes in the work, the value of such changes to be determined by the measured quantities involved and the applicable unit prices specified in the contract; provided that in case of a unit price contract the net value of all changes does not increase or decrease the original total amount shown in Agreement by more than twenty-five percent (25%).

b. By acceptance of agreed unit prices based on estimated cost plus overhead and

profit as applicable. c. By estimate of the actual cost of labor and materials plus overhead and profit,

cost to be determined as the work progresses. d. By actual cost of labor and materials plus overhead and profit, cost to be

determined as the work progresses. e. By estimate of the value as deductible from the approved detailed estimate.

13.2 Overhead shall be defined as an allowance to compensate for all costs, charges and expenses, direct or indirect, except for the actual cost of labor to include, but not be limited to insurance (other than as mentioned in Paragraph 157) bond or bonds, field and office supervisors and assistants above the level of foreman, use of small tools and minor equipment, incidental job burdens, general office expenses, etc.

13.3 Actual cost of labor and material shall be defined as the amount paid for the following

items, to the extent determined reasonable and necessary:

Item 1 - Cost of materials delivered to the job site for incorporation into the contract work. Item 2 - Wage paid to workmen and foreman and wage supplements paid to labor organizations in accordance with current labor agreements. Item 3 - Premiums or taxes paid by the contractor for workmen's compensation insurance, unemployment insurance, FICA tax and other payroll taxes as required by law, net of actual and anticipated refunds and rebates. Item 4 - Sales taxes paid as required by law.

4.8

Page 39: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

Item 5 - Allowance for use of construction equipment (exclusive of hand tools and minor equipment), as approved for use by the owner or his representative. The rate on self-owned equipment used for periods of under one week will be the Rental Rate Blue Book for Construction Equipment by Nelsen/Dataquest, Inc. published rate. Equipment used for periods of 5 consecutive days or more will be billed at a rate equal to 45% of the published monthly rate. Allowance for operating costs (fuel and maintenance) shall be the Blue Book rate. In the alternative, the owner or his representative may approve for reimbursement at a rate representing the allowable costs or ownership. Self-owned equipment is defined to include equipment rented from controlled or affiliated companies. Rented equipment will be paid for at the actual rental cost. Gasoline, oil and grease required for operation and maintenance will be paid for at the actual cost. When, in the opinion of the contractor, and as approved by the owner or his representative, suitable equipment is not available on the site, the moving of said equipment to and from the site will be paid for at actual cost.

13.4 Regardless of the method used to determine the value of any change, the contractor will be required to submit evidence satisfactory to the owner to substantiate each and every item that constitutes his proposal of the value of the change. The amounts allowed for overhead and profit shall not exceed the applicable percentages as established in the two following paragraphs.

13.5 If the work is done directly by the contractor, overhead in an amount of 10% may be

added if method (b), (c) or (d) is used, and to the cost of the labor and materials plus overhead there may be added 10% for profit. The percentages for overhead and profit may vary according to the nature, extent and complexity of the work involved, but in no case shall exceed the percentages set forth in this paragraph. No percentages for overhead and profit will be allowed on payroll taxes or on the premium portion of overtime pay.

13.6 If the work done by a subcontractor, subcontractor's overhead in the amount of 5% may

be added to cost of labor and materials if method (b), (c) or (d) is used and to the cost of labor and materials plus overhead there may be added 10% for the subcontractor's combined overhead and profit. No percentage for overhead and profit will be allowed on payroll taxes or on the premium portion of overtime pay.

13.7 In computing the value of a change order which involves additions and deductions of

work and the added work exceeds the omitted work, the contractor will be allowed to retain the overhead and profit on the amount which the omitted work exceeds the added work, except that no overhead and profit shall be retained on value of work determined by method (a).

13.9 The contractor may retain overhead and profit on a change order which involves

deduction only, except that no overhead and profit shall be considered on value of work determined by method (a).

4.9

Page 40: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

13.10 For overruns and underruns exceeding 25% of estimated quantities, the owner will review the unit price and negotiate a new price if appropriate.

13.11 Change orders will be issued for overruns and underruns which change a single quantity

by 25% or $25,000, or which cumulatively change the contract amount by both 25% and $25,000.

13.12 Any change order(s) which substantially alter(s) the scope and/or quantities of the

project from the bid amount shall require prior approval by the appropriate funding agency.

14. TIME FOR COMPLETION AND LIQUIDATED DAMAGES

14.1 The date of beginning and the time for completion of the work are essential conditions of the contract documents and the work embraced shall be commenced on a date specified in the Notice to Proceed.

14.2 The contractor will proceed with the work at such rate of progress to insure full

completion within the contract time. It is expressly understood and agreed, by and between the contractor and the owner, that the contract time for the completion of the work described herein is a reasonable time, taking into consideration the average climatic and economic conditions and other factors prevailing in the locality of the work.

14.3 If the contractor shall fail to complete the work within the contract time, or extension of

time granted by the owner, then the contractor will pay to the owner the amount for liquidated damages as specified in the bid for each calendar day that the contractor shall be in default after the time stipulated in the contract documents.

14.4 The contractor shall not be charged with liquidated damages or any excess cost when the

delay in completion of the work is due to the following, and the contractor has promptly given written notice of such delay to the owner or his representative.

14.4.1 To any performance, priority or allocation order duly issued by the owner. 14.4.2 To unforeseeable causes beyond the control and without the fault or negligence

of the contractor, including but not restricted to, acts of God, or of the public enemy, acts of the owner, acts of another contractor in the performance of a contract with the owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and abnormal and unforeseeable weather; and

14.4.3 To any delays of subcontractors occasioned by any of the causes specified in

paragraphs 14.4.1 and 14.4.2 of this article.

4.10

Page 41: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

15. CORRECTION OF WORK

15.1 The contractor shall promptly remove from the premises all work rejected by the owner or his representative for failure to comply with the contract documents, whether incorporated in the construction or not, and the contractor shall promptly replace and re-execute the work in accordance with the contract documents and without expense to the owner and shall bear the expense of making good all work of other contractors destroyed or damaged by such removal or replacement.

15.2 All removal and replacement work shall be done at the contractor's expense. If the

contractor does not take action to remove such rejected work within ten (10) days after receipt of written notice, the owner may remove such work and store the materials at the expense of the contractor.

16. SUBSURFACE CONDITIONS

16.1 The contractor shall promptly, and before such conditions are disturbed, except in the event of an emergency, notify the owner by written notice of:

16.1.1 Subsurface or latent physical conditions at the site differing materially from

those indicated in the contract documents; 16.1.2 The owner shall promptly investigate the conditions, and if he finds that such

conditions do so materially differ and cause an increase or decrease in the cost of, or in the time required for, performance of the work, an equitable adjustment shall be made and the contract documents shall be modified by a change order. Any claim of the contractor for adjustment hereunder shall not be allowed unless he has given the required written notice; provided that the owner may, if he determines the facts so justify, consider and adjust any such claims asserted before the date of final payment.

17. SUSPENSION OF WORK, TERMINATION AND DELAY

17.1 The owner may suspend the work or any portion thereof for a period of not more than

ninety days or such further time as agreed upon by the contractor, by written notice to the contractor and the owner or his representative which notice shall fix the date on which work shall be resumed. The contractor will be allowed an increase in the contract price or an extension of the contract time, or both, directly attributable to any suspension.

17.2 The owner may, without prejudice to any other right or remedy and after giving the

contractor and his surety a minimum of ten (10) days from delivery of a written notice, terminate the services of the contractor and take possession of the project and of all materials, equipment, tools, construction equipment and machinery thereon owned by the contractor, and finish the work by whatever method he may deem expedient if it is determined that the contractor has done one of the following:

4.11

Page 42: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

17.2.1 He is adjudged bankrupt or insolvent. 17.2.2 He makes a general assignment for the benefit of his creditors. 17.2.3 He or any of his property is appointed a trustee or receiver. 17.2.4 He files a petition to take advantage of any debtor's act. 17.2.5 He reorganizes under the bankruptcy or applicable laws. 17.2.6 He repeatedly fails to supply sufficient skilled workmen or suitable materials or

equipment. 17.2.7 He repeatedly fails to make promptly payments to subcontractors or for labor,

materials, or equipment. 17.2.8 He disregards laws, ordinances, rules, regulations or orders of any public body

having jurisdiction of the work. 17.2.9 He disregards the authority of the owner or his representative. 17.2.10 He otherwise violates any provision of the contract documents.

In such case the contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the contract price exceeds the direct and indirect costs of completing the project, including compensation for additional professional services, such excess shall be paid to the contractor. If such costs exceed such unpaid balances, the contractor will pay the difference to the owner. Such costs incurred by the owner will be determined by the owner or his representative and incorporated in a change order.

17.3 Where the contractor's services have been so terminated by the owner, said termination

shall not affect any right of the owner against the contractor then existing or which may thereafter accrue. Any retention or payment of monies by the owner due the contractor will not release the contractor from compliance with the contract documents.

17.4 After ten (10) days from delivery of a written notice to the contractor and the owner or

his representative, the owner may, without cause and without prejudice to any other right or remedy, elect to abandon the project and terminate the contract. In such case, the contractor shall be paid for all work executed and any expense sustained plus reasonable profit.

17.5 If, through no act or fault of the contractor, the work is suspended for a period of more

than ninety (90) days by the owner or under an order of court or other public authority,

4.12

Page 43: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

or the owner or his representative fails to act on any request for payment within thirty (30) days after it is submitted, or the owner fails to pay the contractor substantially the sum approved by the owner or his representative or awarded by arbitrators within thirty (30) days of its approval and presentation, then the contractor may, after ten (10) days from delivery of a written notice to the owner or his representative, terminate the contract and recover from the owner payment for all work executed and all expenses sustained. In addition and in lieu of terminating the contract, if the owner or his representative has failed to act on a request for payment or if the owner has failed to make any payment as aforesaid, the contractor may upon ten (10) days written notice to the owner and the owner or his representative stop the work until he has been paid all amounts then due, in which event and upon resumption of the work, change orders shall be issued for adjusting the contract price or extending the contract time or both to compensate for the costs and delays attributable to the stoppage of the work.

17.6 If the performance of all or any portion of the work is suspended, delayed, or interrupted

as a result of a failure of the owner or his representative to act within the time specified in the contract documents, or if no time is specified, within a reasonable time, an adjustment in the contract price or an extension of the contract time, or both, shall be made by change order to compensate the contractor for the costs and delays necessarily caused by the failure of the owner or his representative.

4.13

Page 44: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

18. PAYMENTS TO CONTRACTOR

18.1 At least ten (10) days before each progress payment falls due (but not more often than once a month), the contractor will submit to the owner or his representative a partial payment estimate filled out and signed by the contractor covering the work performed during the period covered by the partial payment estimate and supported by such data as the owner or his representative may reasonably require. If payment is requested on the basis of materials and equipment not incorporated in the work but delivered and suitably stored at or near the site, the partial payment estimate shall also be accompanied by such supporting data, satisfactory to the owner, as will establish the owner's title to the material and equipment and protect his interest therein, including applicable insurance. The owner or his representative will, within ten (10) days after receipt of each partial payment estimate, either indicate in writing his approval of payment and present the partial payment estimate to the owner, or return the partial payment estimate to the contractor indicating in writing his reasons for refusing to approve payment. In the latter case, the contractor may make the necessary corrections and resubmit the partial payment estimate. The owner will, within thirty (30) days of presentation to him of an approved partial payment estimate, pay the contractor a progress payment on the basis of the approved partial payment estimate. The owner shall retain ten percent (10%) of the amount of each payment until fifty percent of the work is completed. After that five percent of the amount of each payment shall be retained until final completion and acceptance of all work covered by the contract documents. On completion and acceptance by the owner of a part of the work on which the price is stated separately in the contract documents, payment may be made in full, including retained percentages, less authorized deductions.

18.2 The request for payment may also include an allowance for the cost of such major materials which are suitably stored whether at or near the site less ten percent (10%) of the amount.

18.3 Prior to substantial completion, the owner, with the concurrence of the contractor, may

use any completed or substantially completed portions of the work. Such use shall not constitute an acceptance of such portions of the work.

18.4 The owner shall have the right to enter the premises for the purpose of doing work not

covered by the contract documents. This provision shall not be construed as relieving the contractor of the sole responsibility for the care and protection of the work area, or the restoration of any damaged work except such as may be caused by agents or employees of the owner.

18.5 Upon completion and acceptance of the work, the owner or his representative shall issue

a certificate attached to the final payment request that the work has been accepted by him under the conditions of the contract documents. The entire balance found to be due the contractor, including the retained percentages, but except such sums as may be lawfully

4.14

Page 45: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

retained by the owner, shall be paid to the contractor within thirty (30) days of completion and acceptance of the work.

18.6 The contractor will indemnify and save the owner or the owner's agents harmless from

all claims growing out of the lawful demands of subcontractors, laborers, workmen, mechanics, materialmen, and furnishers of machinery and parts thereof, equipment, tools, and all supplies, incurred in the furtherance of the performance of the work. The contractor shall, at the owner's request, furnish satisfactory evidence that all obligations of the nature designated above have been paid, discharged, or waived. If the contractor fails to do so the owner may, after having notified the contractor, either pay unpaid bills or withhold from the contractor's unpaid compensation a sum of money deemed reasonable sufficient to pay any and all such lawful claims until satisfactory evidence is furnished that all liabilities have been fully discharged whereupon payment to the contractor shall be resumed, in accordance with the terms of the contract documents, but in no event shall the provisions of this sentence be construed to impose any obligations upon the owner to either the contractor, his surety, or any third party. In paying any unpaid bills of the contractor, any payment so made by the owner shall be considered as a payment made under the contract documents by the owner to the contractor and the owner shall not be liable to the contractor for any such payments made in good faith.

18.7 If the owner fails to make payment thirty (30) days after approval, in addition to other

remedies available to the contractor, there shall be added to each such payment interest at the maximum legal rate commencing on the first day after said payment is due and continuing until the payment is received by the contractor.

19. ACCEPTANCE OF FINAL PAYMENT AS A RELEASE

19.1 The acceptance by the contractor of final payment shall be and shall operate as a release to the owner of all claims and all liability to the contractor other than claims in stated amounts as may be specifically excepted by the contractor for all things done or furnished in connection with this work and for every act and neglect of the owner and others relating to or arising out of this work. Any payment, however, final or otherwise, shall not release the contractor or his sureties from any obligations under the contract documents or the Performance Bond and Payment Bonds.

20. INSURANCE

20.1 The contractor shall purchase and maintain such insurance as will protect him from claims set forth below which may arise out of or result from the contractor’s execution of the work, whether such execution be by himself or by a subcontractor or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable:

20.1.1 Claims under workmen’s compensation, disability benefit and other similar

employee benefit acts;

4.15

Page 46: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

20.1.2 Claims for damages because of bodily injury, occupational sickness or disease,

or death of his employees; 20.1.3 Claims for damages because of bodily injury, sickness or disease, or death of any

person other than his employees; 20.1.4 Claims for damages insured by usual personal injury liability coverage which are

sustained (1) by any person as a result of an offense directly or indirectly related to the employment of such person by the contractor, or (2) by another person; and

20.1.5 Claims for damages because of injury to or destruction of tangible property,

including loss of use resulting there from.

20.2 Certificates of insurance acceptable to the owner shall be filed with the owner prior to commencement of the work. These certificates shall contain a provision that coverage’s afforded under the policies will not be cancelled unless at least fifteen (15) days prior written notice has been given to the owner. Cancellation clauses that read “endeavor to …but failure to mail such notice…” are NOT acceptable and must be crossed out. The owner and engineer shall be named as additional insured in all policies for ongoing operations and completed operations.

20.3 The contractor shall procure and maintain, at his own expense, during the contract time,

liability insurance as hereinafter specified:

20.3.1 The contractor shall carry Commercial General Liability Insurance with limits of not less than $1,000,000 per occurrence and $2,000,000 aggregate. The insurance includes: Products/completed operations; blanket contractual liability – all written and oral contracts; premises and operation liability; explosion, collapse and underground personal injury; independent contractors; broadform property damage; severability of liability; fire damage legal liability – real property; incidental malpractice (including employees); non-owned watercraft; and automatic coverage for newly acquired entities.

20.3.2 The contractor shall carry, during the life of the Contract, Commercial

Automobile Liability Insurance – covering all owned, hired, leased and non-owned vehicles with a minimum limit of liability of $1,000,000 per occurrence.

20.3.3 The contractor shall maintain Umbrella and Excess Liability Coverage over

General Liability; Auto and Worker’s Compensation in the amount of $1,000,000.

20.3.4 The contractor shall procure and maintain, at his own expense, during the contract time, in accordance with the provisions of the laws of the state in which

4.16

Page 47: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

the work is performed, Workmen’s Compensation Insurance, including occupational disease provisions for all of the latter’s employees unless such employees are covered by the protection afforded by the contractor. In case any class of employees engaged in hazardous work under this contract at the site of the project is not protected under Workmen’s Compensation statue, the contractor shall provide, and shall cause each subcontractor to provide, adequate and suitable insurance for the protection of his employees not otherwise protected.

20.3.5 Unless otherwise indicated, the contractor shall secure, if applicable, “All Risk” type Builder’s Risk Insurance for work to be performed. Limit of coverage will correspond to the amount of the contract less any agreed to uninsurable portions of the Work, as approved by the Owner. The policy shall cover not less than the losses due to fire, explosion, hail, lightning, vandalism, malicious mischief, wind, collapse, riot, aircraft, and smoke during the contract time, and until the work is accepted by the owner. The policy shall name as the insured the contractor and the owner. In cases of projects involving utility lines or other work on which Builder’s Risk policies are normally not written, the Contractor will furnish an “all-Risk” Installation Floater which provides coverage for all materials stored or installed. Such insurance will provide coverage until said materials have been installed, tested and placed in operation by Owner. Such insurance may have a deductible clause, but the amount of deductible shall not exceed One Thousand Dollars ($1,000.00).

If Owner finds it necessary to occupy or use a portion of portions of the work prior to Substantial Completion of all the work, the insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be cancelled or permitted by lapse of account of any such partial use or occupancy.

20.3.6 When the work involves occupancy of railroad right of way, highway right of way, use of marine equipment or work in navigable waterways, or any other special hazard, adequate liability insurance shall be provided by the Contractor as required by the railroad or the regulatory agency or governmental body having jurisdiction over the work site(s). In the case of railroad protective insurance, the conditions of the License Agreement between the Owner and the railroad will be fully met by the Contractor’s insurance, with such special insurance certificates or “additional insureds” as may be required. In the case of occupancy of PennDOT right or way, the Contractor will furnish all certificates required by PennDOT, on the forms(s) prescribed by PennDOT.

4.17

Page 48: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

21 CONTRACT SECURITY

21.1 The contractor shall within ten (10) days after the receipt of the Notice of Award furnish the owner with a Performance Bond and a Payment Bond in penal sums equal to the amount of the contract price, conditioned upon the performance; by the contractor of all undertakings, covenants, terms, conditions and agreements of the contract documents, and upon the prompt payment by the contractor to all persons supplying labor and materials in the prosecution of the work provided by the contract documents. Such bonds shall be executed by the contractor and a corporate bonding company licensed to transact such business in the state in which the work is to be performed and named on the current list of "Surety Companies Acceptable on Federal Bonds" as published in the Treasury Department Circular Number 570. The expense of these bonds shall be borne by the contractor. If at any time a surety on any such BOND is declared a bankrupt or loses its right to do business in the state in which the work is to be performed or is removed from the list of Surety Companies accepted on Federal bonds, contractor shall within ten (10) days after notice from the owner to do so, substitute an acceptable bond (or bonds) in such form and sum and signed by such other surety or sureties as may be satisfactory to the owner. The premiums on such bond shall be paid by the contractor. No further payments shall be deemed due nor shall be made until the new surety or sureties shall have furnished an acceptable bond to the owner.

22. ASSIGNMENTS

22.1 Neither the contractor nor the owner shall sell, transfer, assign or otherwise dispose of the contract or any portion thereof, or of his right, title or interest therein, or his obligations thereunder, without written consent of the other party.

23. INDEMNIFICATION

23.1 The contractor will indemnify, defend, and hold harmless the owner and the engineer and their agents and employees from and against all claims, damages, losses and expenses including reasonable attorney's fees arising out of or resulting from the performance of the work, provided that any such claims, damages, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property including the loss of use resulting there from; and is caused in whole or in part by any negligent or willful act or omission of the contractor, or subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable.

23.2 In any and all claims against the owner or the engineer, or any of their agents or

employees, by an employee of the contractor, any subcontractor, anyone directly or indirectly employed by any of them, or anyone for whose acts any of them may be liable, the indemnification obligation shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the contractor or

4.18

Page 49: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

any subcontractor under workmen's compensation acts, disability benefit acts or other employee benefits acts.

23.3 The obligation of the contractor under this paragraph shall not extend to the liability of

the engineer, his agents or employees arising out of the preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, designs, or specifications.

24. SEPARATE CONTRACTS

24.1 The owner reserves the right to let other contracts in connection with the project. The contractor shall afford other contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work, and shall properly connect and coordinate his work with theirs. If the proper execution or results of any part of the contractor's work depends upon the work of any other contractor, the contractor shall inspect and promptly report to the engineer any defects in such work that render it unsuitable for such proper execution and results.

24.2 The owner may perform additional work related to the project by himself, or he may let

other contracts containing provisions similar to these. The contractor will afford the other contractors who are parties to such Contracts (or the owner, if he is performing the additional work himself), reasonable opportunity for the introduction and storage of materials and equipment and the execution of work, and shall properly connect and coordinate his work with theirs.

24.3 If the performance of additional work by other contractors or the owner is not noted in

the contract documents prior to the execution of the contract, written notice thereof shall be given to the contractor prior to starting any such additional work. If the contractor believes that the performance of such additional work by the owner or others involves him in additional expense or entitles him to an extension of the contract time, he may make a claim therefore as provided in Sections 14 and 15.

25. SUBCONTRACTING

25.1 The contractor may utilize the services of specialty subcontractors on those parts of the work which, under normal contracting practices, are performed by specialty subcontractors.

25.2 The contractor shall not award work to subcontractor(s), in excess of fifty (50%) percent

of the contract price, without prior written approval of the owner. 25.3 The contractor shall be fully responsible to the owner for the acts and omissions of his

subcontractors, and of persons either directly or indirectly employed by them, as he is for the acts and omissions of persons directly employed by him.

4.19

Page 50: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

25.4 The contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to bind subcontractors to the contractor by the terms of the contract documents insofar as applicable to the work of subcontractors and to give the contractor the same power as regards terminating any subcontract that the owner may exercise over the contractor under any provision of the contract documents.

25.5 Nothing contained in this contract shall create any contractual relation between any

subcontractor and the owner.

26. ENGINEER'S AUTHORITY

26.1 The engineer, when requested by the owner, shall act as the owner's representative during the construction period. He shall decide questions which may arise as to quality and acceptability of materials furnished and work performed. He shall interpret the intent of the contract documents in a fair and unbiased manner. The engineer will make visits to the site and determine if the work is proceeding in accordance with the contract documents.

26.2 The contractor will be held strictly to the intent of the contract documents in regard to

the quality of materials, workmanship and execution of the work. Inspections may be made at the factory or fabrication plant of the source of material supply.

26.3 The engineer will not be responsible for the construction means, controls, techniques,

sequences, procedures, or construction safety. 26.4 The engineer shall promptly make decisions relative to interpretation of the contract

documents. 27. LAND AND RIGHTS-OF-WAY

27.1 Prior to issuance of Notice to Proceed, the owner shall obtain all land and rights-of-way necessary for carrying out and for the completion of the work to be performed pursuant to the contract documents, unless otherwise mutually agreed.

27.2 The owner shall provide to the contractor information which delineates and describes the

lands owned and rights-of-way acquired. 27.3 The contractor shall provide at his own expense and without liability to the owner any

additional land and access thereto that the contractor may desire for temporary construction facilities, or for storage of materials.

4.20

Page 51: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

28. GUARANTEE

28.1 The contractor shall guarantee all materials and equipment furnished and work performed for a period of one (1) year from the date of substantial completion. The contractor warrants and guarantees for a period of one (1) year from the date of substantial completion of the system that the completed system is free from all defects due to faulty materials or workmanship and the contractor shall promptly make such corrections as may be necessary by reason of such defects including the repairs of any damage to other parts of the system resulting from such defects. The owner will give notice of observed defects with reasonable promptness. In the event that the contractor should fail to make such repairs, adjustments, or other work that may be made necessary by such defects, the owner may do so and charge the contractor the cost thereby incurred. The Performance Bond shall remain in full force and effect through the guarantee period.

29. ARBITRATION

29.1 All claims, disputes, and other matters in question arising out of, or relating to, the contract documents or the breach thereof, except for claims which have been waived by the making and acceptance of final payment as provided by Section 20, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgement may be entered upon it in any court having jurisdiction thereof.

29.2 Notice of the demand for arbitration shall be filed in writing with the other party to the

contract documents and with the American Arbitration Association, and a copy shall be filed with the engineer. Demand for arbitration shall in no event be made on any claim, dispute or other matter in question which would be barred by the applicable statute of limitations.

29.3 The contractor will carry on the work and maintain the progress schedule during any

arbitration proceedings, unless otherwise mutually agreed in writing.

30. TAXES

30.1 The contractor will pay all sales, consumer, use and other similar taxes required by the law of the place where the work is performed.

31. COMPLIANCE

The work proposed in this contract complies with all current Federal, State and Municipal Building codes, regulations and laws, to the best of the engineer's knowledge. Should the contractor find any non-compliance, he should follow the stipulations of General Conditions, Section 10.

4.21

Page 52: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT ITEMS Project Location Map ................................................................................................................................. 5.1 Reference to PennDOT .............................................................................................................................. 5.2 Construction Restrictions ........................................................................................................................... 5.3 Item 1 – Mobilization ................................................................................................................................. 5.4 Item 2 – Construction Access .................................................................................................................... 5.5 Item 3 – Sediment Deposit Removal ......................................................................................................... 5.7 Item 4 – Rock, Class R-7 ........................................................................................................................... 5.8 Item 5 – Diversion Dike System ................................................................................................................ 5.9 Item 6 – Mud Sill Cribbing ...................................................................................................................... 5.10

Page 53: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

Scale: 1 : 65,000

LOCATION MAP

6.80" WIDE X 9.15" HIGH

Ralston Flood Mitigation Project RepairsMcIntyre Township, Lycoming County, Pennsylvania

PROJECT LOCATION

5.1

Page 54: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

REFERENCE TO PENNDOT

All materials and workmanship to be in accordance with Standard Specifications of the Pennsylvania Department of Transportation, Publication 408 dated 2011, Change No. 7, and Supplements thereto unless otherwise noted or otherwise directed by the Specifications of this Project. Where applicable, all materials used shall be in the Pennsylvania Department of Transportation, Bulletin #15 - Approved Construction Materials. Supplemental Specifications or standard drawings listed or referred to in this proposal are available for purchase upon request from PennDOT Sales Store, P.O. Box 2730, Harrisburg, Pennsylvania, 17105 Telephone: (717) 787-5968.

5.2

Page 55: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

CONSTRUCTION RESTRICTIONS

Lycoming Creek is listed as “Approved Trout Waters” and as a “Stream Section that Supports Natural Reproduction of Trout” by the PA Fish and Boat Commission. Therefore, stream restrictions will be in place from March 1st to June 15th and from October 1st to December 31st.

The Contractor will be responsible for coordinating any waivers with the PA Fish and Boat Commission that they may need for the proposed project. Contact North Central Region, 1150 Spring Creek Road, Bellefonte, PA 16823, Phone (570) 359-5250 to coordinate waivers.

The Contractor is to conduct all work in strict accordance with the approved DEP/USACOE Standard Joint Permit.

Burning is not permitted on the project site.

Contact Daniel Ryan – PA Fish and Boat Commission (814-359-5140) a minimum of 14 days in advance of constructing Mud Sill Cribbing.

5.3

Page 56: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT ITEM 1 - MOBILIZATION

In accordance with Section 608 and as follows:

608.1 – DESCRIPTION. Add the following:

• A job office is not a requirement of the Contract.

608.4 – MEASUREMENT AND PAYMENT. Lump Sum.

Delete item (a) and (b) and add the following:

Payment will be made for the lump sum price bid for Mobilization at seventy five percent (75%) of the lump sum amount bid at the beginning of the project. The remaining twenty five percent (25%) will be paid to the Contractor at the completion of the project as specified after a site inspection by the Engineer. The following are also required to be furnished before final payment of this item:

• Certified Payroll Records*• Final DBE/WBE/MBE Payment amounts, if necessary• Material Slips, as required• Material Certifications, as required• Material Testing Results, as required• Any Right to Enter forms and property release forms from property owners, if necessary• Final Work Order documentation and Force Account documentation, if necessary

*Certified payrolls required for projects with contracts greater than or equal to $100,000.00.

5.4

Page 57: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT ITEM 2 – CONSTRUCTION ACCESS

DESCRIPTION - This work consists of construction access and all work associated with access to the work site and staging area including; removal and disposal of any debris from within the area of proposed Rock, Class R-7 and Mud Sill Cribbing, restoring the site to existing conditions, seeding and mulching and site cleanup. This item also includes basic erosion and sediment pollution control measures in accordance with the DEP Erosion and Sediment Pollution Control Best Management Practice (BMP) Manual dated March 31, 2012, in accordance with the Erosion Sediment Pollution Control Plan for this project and approved Standard Joint Permit as required. MATERIAL -

• Seeding and Soil Supplements, Formulas D, B & E – Section 804.2.

• Mulch, Straw –Section 805.2.

• Compost Filter Sock – Section 867.

• AASHTO No. 1 Coarse Aggregate – Section 703.2.

• Geotextile, Class 4, Type A – Section 735.

• Pumped Water Filter Bag – Section 855.

CONSTRUCTION - Site Access as follows: Access should be constructed with minimal impacts to the existing site conditions. The Contractor will gain access to the area of the proposed Rock, Class R-7 construction over an existing gravel driveway. A temporary access road is required over the area of the earthen berm beyond the gravel drive. Construct the temporary access road as shown on the Erosion and Sediment Pollution Control Plan. Any damage to the clay layer on top of the earthen berm shall be repaired at no additional cost to the Township. If the clay layer is damaged, immediately contact the Engineer for further instruction. Access to the area of sediment removal will be made over an existing access road. Crossing of Rock Run shall be made during low flow conditions over the existing streambed. No pipe crossing is required to access the sediment deposit. Cut all brush and vegetation required to be removed for access and staging flush with the ground. Do not grub brush and/or vegetation or excavate the existing ground within the limits of the temporary construction easements. Upon completion of the work, restore any areas disturbed by the Contractor’s method of operations to the pre-construction conditions to the satisfaction of the Owner. Seed disturbed areas as required according to the Erosion and Sediment Pollution Control plan. Remove all excess materials, tools, equipment and rubbish created or used during the Contractor’s method of operations from the project site.

5.5

Page 58: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

MEASUREMENT AND PAYMENT– Lump Sum. Payment will be made for the lump sum bid price of “Construction Access” upon completion of this work as specified after a site inspection by the Engineer. All labor, tools, equipment, materials, disposal of brush and any other costs associated with Construction Access is incidental to this item.

5.6

Page 59: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT ITEM 3 – SEDIMENT DEPOSIT REMOVAL DESCRIPTION – This work is the removal of the sediment deposit as indicated and as directed. This work includes all labor, material, tools and equipment necessary for removal and proper disposal of the sediment. Approximate Quantities:

Sediment Deposit Removal = 740 CY ± Above quantities are for information only and is to be checked and verified by contractor before ordering materials or beginning work.

CONSTRUCTION – Remove sediment deposits in the stream channel as indicated on the plan and properly dispose of outside the project area. Remove the sediment deposit to within 6 inches above the water surface elevation. Do not disturb the sediment below the elevation defined as 6” above the water surface elevation. Contractor will be responsible to provide documentation of the location of disposal.

MEASUREMENT AND PAYMENT – Lump Sum.

5.7

Page 60: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

PAYMENT ITEM 4 – ROCK, CLASS R-7 DESCRIPTION –In accordance with PennDOT Publication 408/2011, Section 205 and as follows: Approximate Quantities:

Rock, Class R-7 = 331 Tons ± Above quantities are for information only and is to be checked and verified by contractor before ordering materials or beginning work.

Provide rock of the class indicated meeting the requirements of Section 850.2(a) except as follows: Place rock by mechanical means, but do not end dump. Construct the R-7 Rock keyway, as shown on the Contract Drawings, prior to placing the mud sill cribbing structure. Provide Geotextile, Class 4, Type A meeting the requirements of Section 735. Provide Geotextile in all areas where Rock, Class R-7 comes in direct contact with existing ground. Construct Rock, Class R-7 in accordance with PennDOT Publication 408/2011, Section 850.3. MEASUREMENT AND PAYMENT – Ton. Payment will be made for excavation and placement of Rock, Class R-7, including construction of the R-7 Rock Keyway and in association with the Mud Sill Cribbing.

5.8

Page 61: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

ITEM 5 – DIVERSION DIKE SYSTEM

DESCRIPTION – This work consists of installing, maintaining and removing a diversion dike system to construct the Rock, Class R-7 and Mud Sill Cribbing along the west channel bank of Lycoming Creek in accordance with the Contract Drawings. MATERIAL– In accordance with applicable parts of PennDOT Pub 408/2011 and as follows:

• Sand Bags – provide sand bags in accordance with the DEP Erosion and Sediment Pollution Control Best Management Practice (BMP) Manual dated March 31, 2012.

• Polyethylene, 6 Mil – AASHTO - M171.

• Concrete Glare Screen – Precast barrier. In accordance with applicable parts of Section 714.

CONSTRUCTION– In accordance with applicable parts of PennDOT Publication 408/2011, in accordance with the DEP Erosion and Sediment Pollution Control Best Management Practice (BMP) Manual dated March 31, 2012 and as indicated on the Contract Drawings.

Install the Diversion Dike System along the western channel bank of Lycoming Creek for rock placement as shown on the Contract Drawings. Place precast barriers, sandbags and impervious material as required to divert all of the water around the work areas. Dewater the excavation areas as necessary to properly perform the work. Maintain the Diversion Dike System for the duration of the placement of the Rock, Class R-7 and Mud Sill Cribbing along the western channel bank of Lycoming Creek. The water diversion system may be reset as necessary to complete construction.

The Diversion Dike System is a regulated water obstruction and not an E&S control structure. Follow the requirements of the approved DEP/USACOE Standard Joint Permit for this project. Do not make changes to the design of this structure without specific approval from the PA DEP and the Lycoming County Conservation District.

If an alternate method or alternate Diversion Dike System is proposed by the contractor, the contractor is responsible to submit a copy of the proposed plan including the schedule of operations for review and approval by the engineer and to acquire the necessary approvals from the PA DEP and the Lycoming County Conservation District. Upon completion of the work, remove the Diversion Dike System and restore the streambed to pre-construction conditions.

MEASUREMENT AND PAYMENT– Lump Sum. Payment will be made for the lump sum bid price of “Diversion Dike System” upon completion of this work as specified after a site inspection by the Engineer. All labor, tools, equipment, materials, and any other costs associated with Diversion Dike System is incidental to this item.

5.9

Page 62: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

ITEM 6 – MUD SILL CRIBBING DESCRIPTION – This work is for the construction and installation of mud sill cribbing along the west channel bank of Lycoming Creek as indicated and directed. MATERIAL

• Sill Logs – Hemlock or Larch logs, 10 to 14 inches in diameter and 10 feet in length. • Wing Logs - Hemlock or Larch logs, 10 to 14 inches in diameter and 20 feet in length. • Front Logs – Hemlock or Larch logs, 10 to 14 in diameter and 12 feet in length. • Deflector Logs – Hemlock or Larch logs, 10 to 14 inches in diameter and 20 feet in length. • #5 rebar, 2’ length – PennDOT 408/2011, Section 1002. Use an 11/16” drill bit for anchor holes. • #5 rebar, 3’ length – PennDOT 408/2011, Section 1002. Use an 11/16” drill bit for anchor holes. • #5 rebar, 4’ length – PennDOT 408/2011, Section 1002. Use an 11/16” drill bit for anchor holes. • R-4 Rock – PennDOT 408/2011, Section 850 • Geotextile Class 4, Type A – PennDOT 408/2011, Section 735

CONSTRUCTION BANK COVER CRIBBING STRUCTURE – Estimated length of the structure is approximately 75 feet (not including wing logs) along the west channel bank of Lycoming Creek, as shown on the plans. The structure will begin at the downstream end of the existing rock protection and tie into the existing stream bank so that the structure does not protrude into Lycoming Creek beyond the existing toe of the channel bank. The structure will follow the existing stream bank and tie into the existing stream bank at the downstream end of the structure. PA Fish & Boat Commission personnel are to be on site for approving the structure location and to estimate normal water flow conditions for setting log heights. Contact Daniel Ryan – PA Fish and Boat Commission (814-359-5140) a minimum of 14 days in advance of operations to schedule and coordinate site approval. Excavation/placement for the sill logs: Each sill log should be 10 feet in length, as shown, and have a 10-14 inch diameter. Excavate seven trenches spaced approximately 11 feet apart and perpendicular to the stream flow. Each trench should be wide enough to accommodate two sill logs placed side by side with a ±2 ½” gap between them. Seven feet of the log should be anchored into the stream bank with 3 feet extending out into the water (measured at the end sill logs). Each log should sit level in the trench with about 2 to 4 inches of water flowing over them at normal flow condition. After each log is installed, 2 pieces of the four foot rebar, installed in pre-drilled holes, (spaced approximately two feet apart) should be used to anchor the stream bank end of each log. The R-4 rock should be placed gently on the bank end of each log until stable. Excavation/attach wing logs and deflector logs: A trench for the wing logs should be installed at a 30º angle to the flow with a minimum of 7 feet of the log anchored into the stream bank. Stabilize/back fill each trench using the same technique as the sill logs, using the four foot rebar stakes and rock. Attach the stream ends of the wing logs to the top of the upstream and downstream sill logs using two foot long, #5 rebar stakes in pre-drilled holes. Stakes should extend into the sill logs approximately 3/4 of the sill log diameter. Rebar stakes should be cut flush with the top of the wing logs. Leave enough room between the end of the wing log and the stake to enable an angle cut to be made when adjoining the front logs. Attach front logs: The bottom three front logs shall be attached directly to the sill logs using two foot rebar stakes in pre-drilled holes as shown on the plans. The rebar stakes should extend into the sill logs approximately 3/4 of the sill log diameter. The rebar stakes should be cut flush with the top of the front logs. The ends of the

5.10

Page 63: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

front logs should be abutted tip to tip or spliced using overlap joints. Angle cuts will be necessary where the front log attaches to the ends of the wing logs. The top front log should be placed in the V-notch of the bottom front logs, as shown on the plans. The top front logs should be attached to the underlying logs using three foot rebar stakes in pre-drilled holes. The rebar stakes should extend into the underlying logs approximately 3/4 of log diameter. Rock placement: Fill in the structure between the front logs and the stream bank with Rock, Class R-7 to lock in this material. Rock should be added to a height of approximately three to four feet above the water level or bankfull height. Final determination will be made in the field by the Fish and Boat Commission Representative and/or the Engineer. Fill in the triangle-gap of the wing logs with R-7 rock. Also add R-7 rock to the stream bank up to bank full height and where the wing logs enter the bank. See Payment Item 4 for information regarding Rock, Class R-7. Bank material: Grading of the upstream and downstream stream banks may be necessary. All disturbed areas shall be seeded and mulched as indicated on the Erosion and Sediment Pollution Control Plan. MEASUREMENT AND PAYMENT – Lump Sum. All labor, tools, equipment, materials and other costs associated with the completion of the mud sill cribbing is incidental to this item. Includes excavation as required. Payment for Rock, Class R-7 associated with this item will be made according to “Payment Item 4 – Rock, Class R-7”.

5.11

Page 64: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

SPECIAL CONDITIONS Work Area .................................................................................................................................................. 6.1 Existing Above Ground Utilities ............................................................................................................... 6.1 Existing Underground Utilities .................................................................................................................. 6.1 Bonding Company ..................................................................................................................................... 6.1 Contractor Verification .............................................................................................................................. 6.1 Engineer's Role During Construction ........................................................................................................ 6.1 Stream Restrictions .................................................................................................................................... 6.2 Wetlands.. .................................................................................................................................................. 6.2 Erosion and Sediment Pollution Control ................................................................................................... 6.2 Prevailing Wage Rates ............................................................................................................................... 6.2 DEP/USACOE Standard Joint Permit ....................................................................................................... 6.2

Page 65: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

SPECIAL CONDITIONS (Items Incidental to the Contract)

Work Area - The Contractor shall keep the area free from accumulations of waste material or rubbish caused by his employees or work. At the completion of the work he shall remove all rubbish from and about the premises and all tools, other equipment or apparatus, and surplus material. The construction site shall be left clean to the satisfaction of the "Inspector of Work". In all locations where private or public property is disturbed or destroyed due to the construction program, it shall be replaced in its original form at the Contractor's expense. Existing Above Ground Utilities - It shall be the responsibility of the Contractor to use all precautions to prevent damage to those utilities. Any utility damaged or destroyed by the Contractor shall be repaired or replaced at his expense in accordance with the requirements of the utility company involved. Existing Underground Utilities - The Contractor will contact all utilities which may have facilities in the project area in accordance with the provisions of Act No. 38. Any utility facilities damaged or destroyed by the Contractor shall be repaired or replaced at his expense in accordance with the requirements of the utility company involved. Bonding Company - The surety company (bonding company) for the performance bond must be listed on the Federal Register Circular 570. Contractor Verification - The Contractor is responsible for field verifying all of the dimensions and quantities shown on the contract drawings prior to the start of construction and purchasing material. Engineer's Role During Construction - It is understood that the Contractor is solely responsible for construction of the Project, and that the Owner, its Engineer, consultants, project managers and any of their officers, agents, employees, designees, and anyone acting on their behalf are not responsible for the acts or omissions of any contractor, subcontractor, or material supplier, for safety programs or enforcement, or for construction means, methods, techniques, sequences, and procedures employed by the Contractor, its agents, subcontractors, officers, employees or persons acting on their behalf. The Contractor shall be solely responsible for the construction means, methods, techniques, sequence or procedures for all safety precautions and programs in connection with the work, compliance with OSHA regulations, and for the acts or omissions of himself, all subcontractors, or any other persons performing any of the work or for the failure of any of them to carry out the work in accordance with the contract documents, statutes, laws, and ordinances, permits or regulations. Neither the Engineer, consultants, project managers, and any of their officers, agents, employees, designees, and anyone acting on their behalf have any responsibility for, or control of, the implementation of the client's safety program. Any program monitoring the performance of the work implementation of the client's safety program. Any program monitoring the performance of the work implemented by the Owner, its engineers, project managers, consultants or any of their designees shall not be deemed to be the exercise of control, or the right to control, of the Contractor's implementation of the means, methods, sequencing and oversight of the safety programs of the Contractor. This paragraph also applies to any initial submission of any Contractor safety program to the Owner, its Engineer, consultants, project managers and any of their officers, agents, employees, designees, or anyone acting on their behalf for review and suggested modifications. It is the express intent of this provision that the Contractor is solely responsible for job site safety of the work.

6.1

Page 66: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

Stream Restrictions – Lycoming Creek is listed as “Approved Trout Waters” and as a “Stream Section that Supports Natural Reproduction of Trout” by the PA Fish and Boat Commission. Therefore, stream restrictions will be in place from March 1st to June 15th and from October 1st to December 31st, unless the Contractor submits a request for a stream waiver to the PA Fish and Boat Commission. Wetlands –The Contractor shall not disturb any wetland areas. If the areas are disturbed, the Contractor is responsible for restoring the site as required at no cost to the County. Erosion and Sediment Pollution Control – The Contractor is to implement proper Erosion and Sediment Pollution Control measures in accordance with PA Code, Title 25, Chapter 102 Regulations, the DEP Erosion and Sediment Pollution Control Program Manual dated March, 2012, and the approved Erosion and Sedimentation Pollution Control Plan. Prevailing Wage Rates – Prevailing wage rates are required for contracts in excess of $100,000.00. DEP/USACOE Standard Joint Permit – The permit is currently under review. The approved DEP/USACOE Standard Joint Permit will be forwarded to the contractor.

6.2

Page 67: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

DEP/USACOE STANDARD JOINT PERMIT

The permit is currently under approval review. The approved DEP/USACOE Standard Joint Permit will be forwarded to the awarded contractor.

7.1

Page 68: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.1

Page 69: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.2

Page 70: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.3

Page 71: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.4

Page 72: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.5

Page 73: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.6

Page 74: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.7

Page 75: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.8

Page 76: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.9

Page 77: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.10

Page 78: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.11

Page 79: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.12

Page 80: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.13

Page 81: CONTRACT DOCUMENTS & TECHNICAL SPECIFICATIONSbidplans.larsondesigngroup.com/datafolder/R7qF81424706972n9UG8... · GENERAL CONDITIONS ... Sets of the CONSTRUCTION DRAWINGS and the

8.14