contract costing.ppt
TRANSCRIPT
-
7/27/2019 Contract Costing.ppt
1/12
1
CONTRACT
COSTING
-
7/27/2019 Contract Costing.ppt
2/12
2
Is generally applied to contractors who undertakeconstructional work and engineering work like roads, dams,
buildings, canals railway lines etc.
Contract Costing defined:
Contract costing is defined as that form of specific order costing
where in work is carried out in accordance with customers
special requirement and each order is of long duration
-
7/27/2019 Contract Costing.ppt
3/12
3
Features of Contract Costing:
Contd.
Contract work is performed on the basis of agreement
between the contractor and contractee. Contract generally takes more than one year (long
period) for completion.
For cost calculation and profits single contract is the cost
unit. Working place is contract site not the factory generally.
For completing the contract some parts of the work or
job may be assigned to specialist known as sub
contractor.
If contractor fails to complete the work in time penalties
may be imposed by the contractee for delay.
-
7/27/2019 Contract Costing.ppt
4/12
4
Plant may be purchased or hired especially for thecontract
Employed by undertakings engaged in building,
road & bridge construction, ship building, etc.
Work carried out at site and not in factory
premises
Payments made based on stages of completion and
depends on Architects Certificate
May contain Escalation Clause and Penalty Clause
-
7/27/2019 Contract Costing.ppt
5/12
5
Concepts relating to Contract Accounts:Contractor:
Contractee:
Contract Price:
Work certified:
Part of the total contract price which is has been
completed and approved by the architect
Value for which the contract is undertaken
Person on whose behalf the task is being done
Person who undertakes the task of doing the job
-
7/27/2019 Contract Costing.ppt
6/12
Material
1. Material unutilized carried forward.2. Transfer of material from one contract toanother.
3. Profit & loss on sell of material transferred toP&L account.
Debit Credit
1. Material required 1. Material returned
2. Sale of material
3. Unutilized Material
4. Material stolen or
destroyed
-
7/27/2019 Contract Costing.ppt
7/12
Wages
1. Directly allocated to the contract.
2. Contract account Debit - Accrued &
outstanding wages.
Expenses
1. Other than material & wages.2. E.g. architects/consultants fees,
electricity, insurance.
-
7/27/2019 Contract Costing.ppt
8/12
-
7/27/2019 Contract Costing.ppt
9/129
Concepts relating.
Uncertified Work:
Cash Paid:
Retention Money:
Part of the work certified that is held back by theContractee
Part of the work certified that is paid by the Contractee
Part of the task done but not approved by the
architect of the Contractee
-
7/27/2019 Contract Costing.ppt
10/1210
Notional Profit:Difference between the value of work certified anduncertified less the cost of work done to date
Estimated Profit:
Contract PriceLess Total cost already incurred
Excess of the contract price over the estimated total
cost of the contract
Less Estimated additional cost required to complete
the contract
Value of work certifiedAdd Value of work not yet certified
Less Cost of work to date
-
7/27/2019 Contract Costing.ppt
11/1211
Profit on Incomplete Contracts:
No profit or Loss be accounted for
Notional Profit X 1/3 X Cash received--------------------
Work Certified
(b) When work certified is 25 % or more but less than50%
(a) When work certified is less than 25% complete
-
7/27/2019 Contract Costing.ppt
12/1212
Profit on Incomplete Contracts:
Notional Profit X 2/3 X Cash received--------------------
Work Certified
(d) When the contractor estimates the profit:
(c) When work certified is the 50% or more but less
than 90%
Estimated Profit X Work Certified---------------------
Contract Price