contract costing.ppt

Upload: deepak3030ei

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Contract Costing.ppt

    1/12

    1

    CONTRACT

    COSTING

  • 7/27/2019 Contract Costing.ppt

    2/12

    2

    Is generally applied to contractors who undertakeconstructional work and engineering work like roads, dams,

    buildings, canals railway lines etc.

    Contract Costing defined:

    Contract costing is defined as that form of specific order costing

    where in work is carried out in accordance with customers

    special requirement and each order is of long duration

  • 7/27/2019 Contract Costing.ppt

    3/12

    3

    Features of Contract Costing:

    Contd.

    Contract work is performed on the basis of agreement

    between the contractor and contractee. Contract generally takes more than one year (long

    period) for completion.

    For cost calculation and profits single contract is the cost

    unit. Working place is contract site not the factory generally.

    For completing the contract some parts of the work or

    job may be assigned to specialist known as sub

    contractor.

    If contractor fails to complete the work in time penalties

    may be imposed by the contractee for delay.

  • 7/27/2019 Contract Costing.ppt

    4/12

    4

    Plant may be purchased or hired especially for thecontract

    Employed by undertakings engaged in building,

    road & bridge construction, ship building, etc.

    Work carried out at site and not in factory

    premises

    Payments made based on stages of completion and

    depends on Architects Certificate

    May contain Escalation Clause and Penalty Clause

  • 7/27/2019 Contract Costing.ppt

    5/12

    5

    Concepts relating to Contract Accounts:Contractor:

    Contractee:

    Contract Price:

    Work certified:

    Part of the total contract price which is has been

    completed and approved by the architect

    Value for which the contract is undertaken

    Person on whose behalf the task is being done

    Person who undertakes the task of doing the job

  • 7/27/2019 Contract Costing.ppt

    6/12

    Material

    1. Material unutilized carried forward.2. Transfer of material from one contract toanother.

    3. Profit & loss on sell of material transferred toP&L account.

    Debit Credit

    1. Material required 1. Material returned

    2. Sale of material

    3. Unutilized Material

    4. Material stolen or

    destroyed

  • 7/27/2019 Contract Costing.ppt

    7/12

    Wages

    1. Directly allocated to the contract.

    2. Contract account Debit - Accrued &

    outstanding wages.

    Expenses

    1. Other than material & wages.2. E.g. architects/consultants fees,

    electricity, insurance.

  • 7/27/2019 Contract Costing.ppt

    8/12

  • 7/27/2019 Contract Costing.ppt

    9/129

    Concepts relating.

    Uncertified Work:

    Cash Paid:

    Retention Money:

    Part of the work certified that is held back by theContractee

    Part of the work certified that is paid by the Contractee

    Part of the task done but not approved by the

    architect of the Contractee

  • 7/27/2019 Contract Costing.ppt

    10/1210

    Notional Profit:Difference between the value of work certified anduncertified less the cost of work done to date

    Estimated Profit:

    Contract PriceLess Total cost already incurred

    Excess of the contract price over the estimated total

    cost of the contract

    Less Estimated additional cost required to complete

    the contract

    Value of work certifiedAdd Value of work not yet certified

    Less Cost of work to date

  • 7/27/2019 Contract Costing.ppt

    11/1211

    Profit on Incomplete Contracts:

    No profit or Loss be accounted for

    Notional Profit X 1/3 X Cash received--------------------

    Work Certified

    (b) When work certified is 25 % or more but less than50%

    (a) When work certified is less than 25% complete

  • 7/27/2019 Contract Costing.ppt

    12/1212

    Profit on Incomplete Contracts:

    Notional Profit X 2/3 X Cash received--------------------

    Work Certified

    (d) When the contractor estimates the profit:

    (c) When work certified is the 50% or more but less

    than 90%

    Estimated Profit X Work Certified---------------------

    Contract Price