contract account
DESCRIPTION
contract accountTRANSCRIPT
A firm of contractors undertook three contracts on 1st April 2013, 1st Oct. 2013 & 1st Jan. 2014, On 31st March 2014, when their accounts were made up, the position was as follows:-IIIIII
Rs.Rs.Rs.
Contract Price8,00,0002,50,0002,50,000
Materials1,44,00058,00020,000
Wages Paid2,20,0001,12,40014,000
Direct Expenses Paid10,4003,6001,400
Plant40,00016,00012,000
Materials at Site at the end8,0004,0002,000
Wages Outstanding6,8003,6001,600
Work Certified50%64%14.40%
Cash Received75%75%75%
Work Uncertified12,0008,0002,100
Direct Expenses Prepaid1,200400200
The plants were installed on the respective dates of the contract and depreciation is to be provided at 10% p.a. Prepare Contract Account.