contents 1. introduction 3 - southern regional power …
TRANSCRIPT
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 1
CONTENTS
1. INTRODUCTION ............................................................................................................................................... 3
2. CONFIRMATION OF THE MINUTES OF THE 32nd TCC & 33rd SRPC MEETINGS .............................................. 3
3. SUPPORT OF RE GENERATORS FOR REACTIVE COMPENSATION .................................................................... 3
4. RAMP RATES ................................................................................................................................................... 4
5. PROCUREMENT OF POC SOFTWARE FOR DISCOMS ....................................................................................... 5
6. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION ................................................................................ 5
7. MONITORING OF SCHEMES FUNDED FROM PSDF ......................................................................................... 5
8. TRANSMISSION CHARGES / SHARING RELATED ISSUES ................................................................................. 6
9. OPTIMUM HARNESSING OF RE IN SOUTHERN REGION ............................................................................... 10
10. ISSUES WITH OA CONSUMERS ..................................................................................................................... 12
11. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT
(PROTECTION) AMENDMENT RULES, 2015 .................................................................................................. 12
12. COAL ISSUES.................................................................................................................................................. 14
13. STATUS OF DC/GENERATION IN ISGS ........................................................................................................... 15
14. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY ..................................................................... 16
15. TTC/ATC ........................................................................................................................................................ 18
16. ISSUE OF PREVAILING OVER VOLTAGES IN SR GRID ..................................................................................... 19
17. ISSUES IN RESPECT OF NPCIL ........................................................................................................................ 20
18. UPCOMING TRANSMISSION SYSTEM ........................................................................................................... 23
19. SCHEDULING OF MACHKUND AND TB DAM ................................................................................................ 31
20. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP ................................................................ 31
21. NEW PROJECTS OF STATE SECTOR & IPP ...................................................................................................... 33
22. REVIEW OF ULDC / SCADA/COMMUNICATION ............................................................................................ 34
23. URTDSM (PMU) PROJECT IN SOUTHERN REGION ........................................................................................ 36
24. EMERGENCY RESTORATION SYSTEM (ERS) .................................................................................................. 36
25. ADOPTION OF UNIFORM PROCEDURE TO PREPARE MERIT ORDER DESPATCH LIST ................................... 37
26. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR .............................................................. 37
27. NON-AVAILING OF OCC APPROVED SHUTDOWN ......................................................................................... 42
28. STATUS OF PHASE-I AND PHASE-II OF PROTECTION AUDIT RECOMMENDATIONS ..................................... 44
29. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM (PMS) FOR
SOUTHERN REGION ...................................................................................................................................... 46
30. COMPLIANCE STATUS OF NEW PROTECTION AUDIT RECOMMENDATIONS ................................................ 46
31. AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE TRANSMISSION LINES OF
SOUTHERN REGION ...................................................................................................................................... 47
32. REVIEW MEETING ON COMPLIANCE OF PCSC RECOMMENDATIONS .......................................................... 48
33. COMMERCIAL COMMITTEE ISSUES .............................................................................................................. 48
34. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION .............................................................................. 51
35. COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 – IN RESPECT OF
LVRT AND OTHER PROVISIONS OF CEA/CERC REGULATIONS ...................................................................... 61
36. GRID OPERATION .......................................................................................................................................... 62
37. REIMBURSEMENT OF SRPC EXPENDITURE ................................................................................................... 67
38. OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE .................................................................... 67
39. RSD & TECHNICAL MINIMUM ....................................................................................................................... 67
40. FREQUENT REVISION OF OUAGE PLAN BY ISG STATIONS ............................................................................ 68
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 2
41. COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF RENEWABLE ENERGY
SOURCES ....................................................................................................................................................... 68
42. SCHEDULING OF ANANTHAPURAMU ULTRA MEGA SOLAR PARK & RAMAGUNDAM SOLAR
PROJECT ........................................................................................................................................................ 69
43. GRID STUDY COMMITTEE (GSC) MEETINGS ON PACKAGE-A & PACKAGE-B ....................................... 70
44. OVR GRADING OF 400 KV AND 765 KV TRANSMISSION LINES OF SOUTHERN REGION ............................... 71
45. COMPLIANCE OF CERC (COMMUNICATION SYSTEM FOR INTER-STATE TRANSMISSION OF
ELECTRICITY), REGULATIONS 2017 ............................................................................................................... 71
46. SPECIAL MEETING ON THE TRIPPINGS OF POLES - 1 & 2 AT HVDC GAJUWAKA SS OF POWERGRID
(SRTS-I) – REG ............................................................................................................................................... 71
47. SPECIAL MEETING ON THE PENDING PROTECTION ISSUES OF PUDUCHERRY SUBSTATIONS...................... 72
48. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK ............. 72
49. PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS ....................................................... 73
50. ROSTER FOR HOSTING THE SRPC MEETINGS ................................................................................................ 73
51. DATE & VENUE OF THE NEXT MEETING OF SRPC ......................................................................................... 73
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 3
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
AGENDA FOR THE 33rd
TCC & 34th
SRPC MEETINGS TO BE HELD ON 10
th &
11th
AUGUST 2018 AT COIMBATORE
1. INTRODUCTION
The 33rd
Meeting of the Technical Coordination Committee of SRPC & 34th
Meeting of
the Southern Regional Power Committee (SRPC) would be held on 10th
& 11th
August
2018 respectively at Coimbatore.
These Meetings would be kindly hosted by SRTS-II, PGCIL.
2. CONFIRMATION OF THE MINUTES OF THE 32nd
TCC & 33rd
SRPC
MEETINGS
2.1 Minutes of the 33rd
Meeting of SRPC held on 17th
February 2018 at Puducherry had
been circulated vide letter dated 13th
April 2018.
2.2 Minutes of the 32nd
Meeting of TCC held on 16th
February 2018 at Puducherry had been
circulated vide letter dated 27th
March 2018.
2.3 Minutes of the Meetings may kindly be confirmed.
3. SUPPORT OF RE GENERATORS FOR REACTIVE COMPENSATION
3.1 In earlier Meetings the following had been noted:
Solar / Wind generators have controllable reactive injection / absorption capability,
which is not getting fully utilized on account of PPA provisions / penalties.
It had been suggested that SLDCs / STUs may approach their Regulator for flexible set
points as per direction of SLDCs.
In the 32nd
Meeting, TCC had opined that details could be shared by states and the
matter could be examined to arrive at some commonality in SR.
Subsequently, the following was noted:
In the Meeting held at Chennai on 28th
April 2018, NIWE had explained that support
from RE generators for MVAR interchange was very much possible.
SRPC vide letter dated 24th
May 2018 (Annexure-I) had circulated a Note regarding
MVAR power restrictions/support from RE generators. It was felt that suitable
incentives /penal rates may need to be in place for RE generators for their contribution,
in the interest of smooth grid operation.
It was noted that reactive support was essential from grid operation / reliability
perspective and the same was needed to be internally discussed by SLDC / TRANSCO
/ DISCOMs / Commercial sections and then the matter could be taken up with RE
generators.
All states had been requested to furnish their comments in this regard so as to help in
arriving at a consensus on this subject in Southern Region and to take the matter
further.
KSEBL had informed that RE generators are not being penalized (charges suspended)
for injection or absorption of MVAR, in case the same is as per instruction of SLDC.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 4
In the Special Meeting conducted on 09.07.2018 to discuss pending issues in respect of
Karnataka, KPTCL had informed that a Sub Committee has been agreed to be
constituted to review these aspects.
3.2 SRPC vide letter dated 24.05.2018 (Annexure-II) had taken up the issue of reactive power
support by the generating stations including RE with Hon’ble CERC. It was brought to
kind attention that reactive accounting for generators needs to be carried out so as to instill
desired grid discipline.
3.3 In day to day operations it was seen for instance that 400 kV lines connected to 400 kV
Uravakonda S/S are tripping frequently on account of persisting high voltage. Voltages at
400 kV Uravakonda S/S and 400 kV Jammalmadugu S/S are persistently very high. There
were two instances of complete outage of 400 kV Uravakonda S/S and 400 kV
Jammalmadugu S/S during the month of June 2018. This matter was also discussed in the
75th
Meeting of Protection Sub Committee held on 28th
June 2018. It was proposed to
constitute a Group of Officers from SRLDC, SRPC and States who would visit major RE
nodes facing high voltage scenario and suggest any improvement in the Operating
Procedure
4. RAMP RATES
4.1 As can be kindly appreciated, Ramp up and ramp down rates are assuming significance
with higher level of RE penetration, sudden changes in load, sudden PX schedules etc.
Details of ramp rates of RRAS stations are enclosed at Annexure-III.
Regulation 7(4) of CEA (Technical Standard for Construction of Electrical Plant and
Electrical Lines states, ‘the design shall cover adequate provision for quick start up and
loading of the unit to full load at a fast rate. The unit shall have minimum rate of loading
or unloading of 3 % per minute above the control load (i.e. 50 % MCR)’.
4.2 This issue had been discussed in the Meetings of OCC wherein NTPC had pointed out that
for different make of machines; even same capacity units may be having different
parameters. Further, even for the same make of machines, the year of manufacturing also
mattered. It was noted that Kudgi, NTPL and NTECL generating units had had come after
2010. In case any issue is being faced by generators in adhering to the Regulations, they
may need to kindly approach CEA/Regulators. NTPC, NLC, NTPL and NTECL had
agreed to discuss this matter with their engineering division so as to try to improve the
ramp percentages.
4.3 ISG stations under RRAS have started giving at least a ramp of 0.5 %/minute which was
implemented from 16.06.2018. This had resulted in an increase in ramp of around 262
MW/block. SRPC vide letter dated 03.07.2018 (Annexure-IV) had taken up the issue of
providing ramps in the range of 1% to 1.5 % /minute with NTPC, Ramagundam.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 5
4.4 SLDCs may also need to kindly ensure enhanced ramp rates from state generators. All
generating units irrespective of control area jurisdiction/ownership need to contribute with
higher ramp rates.
5. PROCUREMENT OF POC SOFTWARE FOR DISCOMS
5.1 TANGEDCO vide letter dated 24.05.2018/22.06.2018 had informed that in the 4th
Meeting
of the Task Force on ‘Review of PoC in ISTS’, it had been decided that PoC software may
be purchased at RPC level for states (extract copy enclosed as Annexure-V) SRPC vide
letter dated 04.06.2018 had informed TANGEDCO that this matter regarding procurement
of software at RPC level would be taken up in the next Meeting of SRPC. In the 38th
Meeting of Commercial Sub Committee held on 29th
June 2018, it was agreed that the
matter would be discussed in the ensuing Meetings of TCC and SRPC.
5.2 IIT Mumbai is the developer of the PoC software identified by Hon’ble Commission.
Preliminary discussions have taken place with IIT Mumbai in this regard. It is learnt that
the cost for 10 licenses would be around Rs 35 lakhs per year. The way forward in this
regard may kindly be deliberated.
6. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION
6.1 In line with the decision taken in the 30th
Meeting of SRPC, Terms of Reference (TOR)
were finalized after consultation with stakeholders in the Subcommittee/Special Meetings.
The objective was to have a Study/Report on the TOR, by means of engaging a Consultant.
Constituent states of SRPC had agreed to share the financial commitment equally.
6.2 Subsequently, Chairperson, SRPC vide letter dated 12.12.2017 addressed to MNRE had
proposed that certain specific studies could be initiated under IGEN – GEC Project being
implemented by GIZ in India on behalf of the German Federal Ministry of Economic
Cooperation and Development (BMZ).
6.3 Based on further discussion with M/s GIZ, the TOR was refined and the following scope
was agreed:
Control Reserve Dimensioning for States in Southern Region
Ancillary Services from RE and controlling RE generation during grid contingency
6.4 Further, M/s GIZ vide mail dated 03.07.2018 have informed that they had commenced the
procurement process. As they have to go for competitive tendering, it could take about 3
months before they can sign the contract with the Consultant.
7. MONITORING OF SCHEMES FUNDED FROM PSDF
7.1 In the 7th
Meeting of NPC held on 08.09.2017, RPCs had been further requested to
examine implementation of PSDF funded schemes in OCC & TCC Meetings and intimate
NPC about any bottlenecks.
7.2 In the 6th
Meeting of the Monitoring Group of PSDF held on 05th
January 2018 at Kochi,
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 6
it was observed that the overall progress was not very satisfactory. It had been
emphasized in that Meeting that better utilization was highly essential, especially since
progress was also being monitored by MoP.
Overall status of schemes in SR as on 30th
June 2018 is given below, please:
Sl.
No.
State/Entity Receive
d
Sanction
ed
Under
approval
Input
sought
Not
eligible
Grant
sanctioned
Disbursed
1 AP 8 3 4 0 1 295.2 29.55
2 Karnataka 7 3 2 2 0 205.06 26.85
3 Kerala 7 6 0 0 1 581.8 164.28
4 TN 15 4 2 9 0 459.39 41.03
5 Telangana 12 5 2 4 1 247.72 49.93
6 Puducherry 2 2 0 0 0 13.19 0.95
7 PGCIL, SR 1 1 0 0 0 378.04 37.80
8 SRPC 2 2 0 0 0 30.59 19.01
8. TRANSMISSION CHARGES / SHARING RELATED ISSUES
8.1 The issue of Transmission charges / sharing was discussed in the 38th
Meeting of
Commercial Sub Committee held on 29th
June 2018. Based on the deliberations in the
CCM, Chairperson, SRPC vide letter dated 03.07.2018 (Annexure-VI) had taken up the
following issues with Chairperson, CERC:
a) Determination of Relinquishment Charges
Early resolution of Stranded Capacity and relinquishment charges which are already
under kind consideration of Hon’ble Commission in Petition No 92/MP/2015 would
help relieve financial stress on DICs
b) Transmission charges related with RE projects
Issues involved in implementation of policy regarding waiver of transmission
charges for solar evacuation under POC mechanism had earlier been taken up vide
letter dated 23.08.2017. This issue had been referred to the Task Force.
c) Recovery of Transmission Charges for delay in commissioning of SPDs
It was noted that there was some time gap between issuance of provisional Tariff
Order and Final Tariff Order. During this interim period, charges are being
recovered through POC mechanism from existing DICs, thus causing upfront
financial burden.
8.2 TANGEDCO vide letter dated 02.07.2018 (Annexure-VII) had raised the following
issues:
a) Issues associates with sharing of transmission charges by IPPs
It had been pointed out that Hon’ble CERC in every tariff order directs to recover
transmission charges as per provisions of Sharing Regulation. Clause (5) of
Regulation 8 of the Sharing Regulations stipulates as under:-
“(5) Where the Approved Withdrawal or Approval Injection in case of a DIC is not
materializing either partly or fully for any reason whatsoever the concerned DIC
shall be obliged to pay the transmission charges allocated under these regulations:
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 7
Provided that in case the commissioning of a generating station or unit thereof is
delayed, the generator shall be liable to pay Withdrawal Charges corresponding to
its Long term Access from the date the Long Term Access granted by CTU becomes
effective. The Withdrawal Charges shall be at the average withdrawal rate of the
rate of the target region:
In the referred case the defaulting DICs are the IPPs. Hence, implementing agency
(NLDC) being responsible to implement the tariff orders and make PoC
computation is accountable to make the following points clear to the DICs for the
benefit of all concerned:
i. Whether the entire LTA quantum of the IPPs is considered for the purpose
of PoC calculation?
ii. Whether any clarification is obtained from Hon’ble Commission with regard
to difficulties in implementing orders related to the above IPPs?
iii. Any specific observation and comments of the validation committee on the
difficulties in implementing the orders.
iv. Details of assets / LTA quantum to be considered for bilateral billing
furnished to SRPC.
Implementing Agency (NLDC) / CTU are kindly requested to present their views.
b) Issues associated with transmission charges to be recovered from entities procuring
RE power and not qualified for waiver of transmission charges
MoP in its Order dated 13.02.2018 had communicated waiver of inter-state
transmission charges and losses on transmission of the electricity generated from solar
and wind sources of energy under para 6.4 (6) of the revised Tariff Policy, 2016. It had
been stated that in supersession of earlier Order dated 30th
September, 2016 and Order
dated 14th
June, 2017, it is notified that –
For generation projects based on solar and wind resources, no interstate
transmission charges and losses will be levied on transmission of the electricity
through the inter-state transmission system for sale of power by such projects
commissioned till 31st March 2022.
Provided that the above waiver will be available for a period of 25 years from the
date of commissioning till 31st March 2022.
Provided further that the above waiver will be available for solar and wind projects
entering into PPAs with all entities, including Distribution Companies for sale of
power from solar and wind power projects for compliance of their renewable
purchase obligation.
Provided further that the above waiver will be allowed only to those solar and wind
projects that are awarded through competitive bidding process in accordance with
the guidelines issued by Central Government.
This Order, irrespective of the purchasing entity, shall be applied prospectively ie from the
date of issue of Order.
CTU/NLDC are kindly requested to elucidate on how the same is being implemented.
c) Issues associated with recovery of transmission charges in respect of ultra mega
solar project at NP Kunta, Ananthapuram District, Andhra Pradesh
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 8
TANGEDCO has stated that direction of Hon’ble Commission in Order dated
30.06.2016 in respect of Petition No.26/TT/2016 should have been compiled by CTU
and the IA. Relevant portion of the order is extracted below:
51…………………….Accordingly the transmission tariff for the instant assets from
the date of commercial operation till the commissioning of solar generation shall be
borne by Andhra Pradesh Solar Power Corporation Pvt Ltd in line with the
Commission’s order dated 06.05.2015 in Petition No.29/MP/2015. The relevant
portion of the order is extracted hereunder:-
‘33…………….that transmission charges for delay in commissioning of solar power
generators are required to be paid by such solar generators/SPPD on the same line
as the liability for payment by the thermal and hydro generating stations in
accordance with the Central Electricity Regulatory Commission (Terms and
Conditions of Tariff) Regulations, 2014…………….’
Subsequently, Hon’ble CERC in Petition No. 133/TT/2017 in the matter of Approval of
transmission tariff for ±100 MVAR STATCOM at NP Kunta Pooling Station under
“Transmission System for Ultra Mega Solar Park in Anantapur District, Andhra
Pradesh-Part A (Phase-I)…….” had passed Order dated 29.06.2018 wherein the
following was stated :
60. The Commission observed that as per the minutes of the 38th
SCM held on7.3.2015,
the CTU was to obtain clarification on the eligibility for LTA, connectivity, issue of
multiple injections, whether the sub-station which is in the premises of the solar park
should be under the scope of park developer or in STU/CTU and whether LTA should
be applied by actual generation developers who may sign PPA with AP DISCOMS or
the APSPCL and directed the petitioner to submit action taken and the clarifications
received.
61. In response, the petitioner vide affidavit dated 12.12.2017 has submitted that as per
CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in
Inter-State Transmission and related matters) Regulations, 2009 any company
authorized by the central government as Solar Power park developer (SPPD) can
apply for Connectivity/Long Term Access (LTA) in ISTS. MNRE vide its letter
dated3.6.2015 authorized APSPCL as a SPPD to apply for connectivity/LTA in ISTS for
its NP Kunta Solar Park (1500 MW). As regards multiple injections, the petitioner
submitted that according to the Statement of Reasons to the above said regulations, in a
solar power park there may be multiple generation developers who may be injecting at
various points within the solar park and ultimately inject at interface with ISTS.
Hence, it will be treated as single injection at the interface point with ISTS. On the
issue of whether the sub-station within the solar park should be under the scope of park
developer or STU/CTU, the petitioner submitted that as per the Government of India
(MNRE) letter dated 12.12.2014, the responsibility of setting up a sub-station near
solar park will lie with the CTU or the STU taking into consideration the technical and
commercial requirement stipulated by the State and Central Commission.
62. TANGEDCO has submitted that in case of State specific solar projects there are no
identified beneficiaries outside the host State and there is no inter-State flow of power
as there is no firmed-up beneficiary outside the State. Further, the regulations do not
permit the socialization of the PoC charges among the beneficiaries of ISTS.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 9
TANGEDCO has submitted that it has raised the issue of ambiguous procedure for
implementation of the waiver of the transmission charges for the solar and wind power
under PoC mechanism.
63. TANGEDCO has submitted that the CERC (sharing of inter-State Transmission
Charges and Losses) Regulations, 2010 (2010 Sharing Regulations) did not account for
solar power injections into grid due to the capacity limitations and dispersal at
distribution level. As per the SOR of the 2010 Tariff Regulations, the 2010 sharing
Regulations facilitate solar based generation by allowing zero transmission access
charge for use of ISTS and allocating no transmission loss to solar based generation.
Solar power generators shall be benefited in event of use of the ISTS. Since such
generation would normally be connected at 33 kV, the power generated by such
generators would most likely be absorbed locally. This would cause no / minimal use of
400 kV ISTS network and might also lead to reduction of losses in the 400 kV network
by obviating the need for power from distant generators. TANGEDCO has submitted
that in contrast to the SOR, the present scenario is different as the solar power has
attained grid parity and the capacity is of the order of 1000 MW and above. This
peculiar situation necessitates revisiting the methodology for determining the PoC
charges and the Sharing Regulation. The sharing Regulations in the present form will
only pass on financial burden on account of the inefficiencies/inaccuracies in allocating
the charges on to the existing DICs irrespective of whether they are beneficial user or
not. TANGEDCO is in no way connected with the sharing of the transmission charges
since it is neither the beneficiary of the State specific solar project nor using the
transmission lines. The power generated and consumed within the State of Andhra
Pradesh does not entitle levy of transmission charges on TANGEDCO and hence the
claim of the petitioner is not maintainable.
64. In response, the petitioner in its rejoinder dated 28.12.2017 has submitted that
Ministry of Power, Govt. of India vide its letter No. 11/64/2014-PG dated 8.1.2015
while dealing with the evacuation of power from nine solar parks (7020 MW capacity)
being set up in seven States including Andhra Pradesh Solar Ultra Mega Park observed
that the transmission line connecting solar parks to ISTS are to be declared part of ISTS
and PGCIL is assigned to take up construction of transmission line including pooling
station from solar generating parks on compressed time schedule basis. Further, the
issue of implementation of the transmission line for connecting the Solar Power Parks
to the ISTS was discussed in the 38th meeting of the Standing Committee on Power
System Planning of Southern Region held on 7.3.2015 and it was agreed that the
proposal was technically in order and could be firmed up subject to resolving the
regulatory issues. The scheme was technically validated in the 38th
SCM and at Para
21.21 of the 38th
SCM following submissions were made with respect to scheme and
STATCOM. The scheme was also deliberated in 27th meeting of SRPC held on
12.05.2015 in presence of all Southern region constituents. The Commission in order
dated 6.8.2015 in Petition No. 29/MP/2015 accorded the regulatory approval for
execution of the instant transmission. The petitioner has submitted that the sharing of
transmission charges for Solar Park at Ananthpur district, Andhra Pradesh has already
been decided by the Commission wherein it was held that billing, collection and
disbursement of transmission charges shall be governed by the 2010 Sharing
Regulations.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 10
65. TANGEDCO has submitted that it has filed an appeal against the Commission’s
order dated 16.5.2016 in Petition No.26/TT/2016 before the Hon’ble Appellate
Tribunal for Electricity and it is pending disposal.
66. We have considered the submissions of the petitioner and TANGEDCO. We are not
able to agree with TANGEDCO that waiver of ISTS charges for solar and wind
generation is not in order. We are of the view that the waiver of transmission charges
for solar and wind generation is as per provisions of Sharing Regulations 2010 and is
in line with government policy to encourage renewable energy in the country.
Therefore, the billing, collection and disbursement of the transmission charges
approved for the instant asset shall be governed by the provisions of CERC (Sharing of
Inter-State Transmission Charges and Losses) Regulations, 2010, as amended from
time to time, as provided in Regulation 43 of the 2014 Tariff Regulations, subject to the
outcome of the Appeal filed by TANGEDCO before APTEL.
8.3 These issues were discussed in the 38th
CC Meeting held on 29.06.2018, wherein PGCIL
had explained that the relinquishment was being allowed as per the prevailing CERC
Regulations. Further the relinquishment charges were to be determined as per the final
order of CERC in Petition No 92/MP/2014. The same would be passed on to the existing
DICs as and when the charges are determined and received. CTU is diligently following
the regulations/CERC Orders from time to time.
8.4 SRPC vide letter dated 04.07.2018 (Annexure-VIII) had taken up the issue with CTU. It
was pointed out transmission charges for delay in commissioning of solar power
generators are required to be paid by such solar generators/SPPD on the same lines as
liability for payment by thermal and hydro generating stations. Implementing Agency
(NLDC) / CTU are kindly requested to furnish their views on the matter.
9. OPTIMUM HARNESSING OF RE IN SOUTHERN REGION
9.1 Follow up of MoP/SRZC meeting
9.1.1 In earlier SRPC Meetings Tamil Nadu had been requested to kindly sign the Overarching
Agreement. SRPC vide letter dated 24.01.2018 had requested Chairperson, TNEB that
necessary directions may kindly be arranged be given to TANGEDCO for signing this
Overarching Agreement. In the 33rd
Meeting of SRPC, TANTRANSCO had stated that
before the next SRPC Meeting, the Overarching Agreement was likely to be signed for
Banking/Swap option.
9.1.2 MoP vide letter dated 18.06.2018 (Annexure-IX) had sought update in respect of
‘Optimum harnessing of renewable energy available in Southern States without
endangering the security’ as noted in the 10th
Meeting of the Standing Committee of
Southern Zonal Council held on 28.11.2017 at Bengaluru. It had been recorded,
‘Government of Tamil Nadu stated that balancing of demand can be made with mutual
agreement among member States to (i) Standalone export: By which power could be
transferred from surplus State to deficit State without any obligation to return the power;
and (ii) Banking/Swapping of Power to deficit States on ‘Give and Take mode’,
returnable to installments at a mutually agreed quantum, duration and time. It was
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 11
stated that TN is also considering signing an agreement after considering the issue of
pricing’.
9.1.3 SRPC Secretariat vide letter dated 27.06.2018 had furnished the update to GM Division,
CEA wherein it was noted that the Overarching Agreement had been utilized as follows:
Date Seller Buyer MW and duration
28.02.2018 Karnataka Kerala 150 MW – 2.5 hrs
01.03.2018 Karnataka Kerala 200 MW – 04 hrs
21.05.2018 Karnataka Andhra Pradesh 300 MW – 03 hrs
9.1.4 MS, SRPC vide letter dated 27.06.2018 (Annexure-X) to Chairman, TNEB had
requested to kindly consider signing the Overarching Agreement so as to avail
opportunities in real time operation
9.1.5 The following had been noted in the earlier Meetings with regard to implementation of
SAMAST:
APTRANSCO had informed that they had prepared a Report and submitted it to
Hon’ble CERC and to NLDC for funding.
TSTRANSCO had informed that DPR for Rs. 87 Crores had been submitted.
TANTRANSCO had informed that PO had been placed on 13.12.2017; and the
project was likely to be completed by 25.05.2018.
KPTCL had informed that they had placed Order for meters which are adjustable to
0-60 minutes. DPR for Rs. 43.3 Crores had been submitted on 08.12.2017.
NPC had stated that as per ToR, the need for 5 minute scheduling was to be
examined. The same was needed to be simulated and validated w.r.t. 15-Minute
scheduling before recommending the same to FOR. It needs to be ascertained
whether there would be huge variation between 3 blocks of 5 minutes wrt 15 minute
block, for the new scheme to be in place with operational / economic justification,
without AGC in place. Pros and cons of the two options were not highlighted in the
draft report. NPC also informed that the SAMAST schemes are being considered
favorably for enhanced approvals, (50 % for communication and >50 % for other
project aspects).
9.2 Pump Storage Plants
9.2.1 The following is the status of upcoming Pump Storage Plants in SR please:
State PSP Scheme Status
Andhra Pradesh Upper Sileru (1000 MW) DPR being prepared
Tamil Nadu Kundah (4x125 = 500 MW) 42nd
SCPSPSR : 2020-21
Sillahalla-I (4x250 = 1000
MW)
42nd
SCPSPSR : 2023
onwards
Sillahalla-II (4x250 = 1000
MW)
4 projects on existing sites
Karnataka Sharavathy (2000 MW) PFR submitted to MoEF
Varahi
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 12
Kerala Sholayar-I (810 MW) Survey and investigation
(S&I)/implementation could
not be taken up for want of
forest clearance
Sholayar-II (390 MW)
Poringalkuthu(80 MW)
10. ISSUES WITH OA CONSUMERS
10.1 In the OCC Meetings, it was noted that certain OA consumers are directly approaching
Power Exchange for short duration of time when PX rates are less while during other times
they were availing power from DISCOMs.
10.2 During last year KSEBL had suspended NOC of such consumers but these consumers had
approached KERC and High Court with the prayer that NOC cannot be rejected on account
of lower demand. High Court had directed KERC to give a solution and Commission had
stated that NOC can be rejected only if there are transmission constraints.
10.3 OCC forum had noted that the following modalities / procedure for granting OA to
consumers in states like Gujarat, Rajasthan and Himachal Pradesh are in vogue:
OA is granted on RTC basis and not for just a few blocks during the day.
Once consent is granted for OA, the consumers have to compulsorily purchase
through OA.
For taking consent for OA for any particular day, the application has to be filed by
consumers two days in advance. For availing OA for the whole month, the
consumers have to file the O.A. application by 15th of the previous month.
Such conditions have helped DISCOMs to assess the demand supply in a more
efficient manner.
It was suggested that best practices of different states could be studied for further
finalizing a procedure / guideline which could be implemented in states after due
approval of the SERCs.
11. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER
ENVIRONMENT (PROTECTION) AMENDMENT RULES, 2015
11.1 Revised water consumption and emission norms for existing as well as new thermal units
(to be installed from 01.01.2017 onwards) as per Environment (Protection) Amendment
Rules, 2015 had been notified by Ministry of Environment, Forest & Climate Change
(MOEF & CC) (Gazette Notification dated 07.12.2015). MOEF guidelines had classified
thermal generators into three categories with different norms. The three classes were -
prior to 31st December 2003, 1
st Jan 2004 to 31
st December 2016 and beyond 1
st January
2017. Existing as well as new plants were required to meet standards by the stipulated time
lines. Preparedness and action plan in order to comply with revised norms had been
discussed in SRPC as well as Subcommittee Meetings
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 13
11.2 The following had been noted in earlier Meetings:
SRPC had noted the requirements for necessary compliance.
Chairperson, SRPC vide letters dated 24th
May 2017 & 28th
August 2017 addressed to
Secretary-Power, MoP had brought to kind attention of MoP, the issue regarding
funding either from PSDF or any other fund to meet stipulated revised environmental
norms.
In view of the time bound nature and criticality Chairperson, SRPC vide letter dated
04.10.2017 had requested Chairperson, CERC that the concerns expressed by the
generators may kindly be arranged to be examined.
11.3 As discussed in the 33rd
Meeting of SRPC held on 17.02.2018, Chairperson, SRPC vide
letter dated 02.03.2018 (Annexure-XI) had requested MoP to bestow its kind attention on
the matter regarding funding; either from PSDF or any other fund, to meet the stipulated
revised environmental norms.
11.4 A Special Meeting had been convened at SRPC Bangalore on 23.02.2018 (Minutes
available on SRPC website) to discuss on incentive to thermal stations for early
installation of Pollution Control Equipment.
11.5 MoP vide letter dated 30.05.2018 (Annexure-XII) had finalized ‘Mechanism for
implementation of New Environment Norms for Thermal Power Plants (TPP) supplying
Power to distribution licensees under concluded long term and medium term Power
Purchase Agreement (PPA)’. In the Mechanism, it has been stated, ‘After considering all
aspects and with due regard to the need for safeguards against environmental hazards
and accordingly to ensure timely implementation of new environment norms, the Central
Government has declared that –
5.1 The MoEFCC Notification requiring compliance of Environment (Protection)
Amendment Rules, 2015 dated 7th
December, 2015 is of the nature of Change in Law
event except in following cases:
a) Power Purchase Agreements of such TPPs whose tariff is determined under Section
63 of the Electricity Act, 2003 having bid deadline on or after 7th
December 2015,
or
b) TPPs where such requirement of pollutions control system was mandated under the
environment clearance of the plant or envisaged otherwise before the notification of
amendment rules.
5.2 The additional cost implication due to installation or up-gradation of various emission
control systems and its operational cost to meet the new environment norms, after
award of bid or signing of PPA as the case may be, shall be considered for being
made pass through in tariff by Commission in accordance with the law.
5.3 The respective TPPs may approach the Appropriate Commission for approval of
additional capital expenditure and compensation for additional cost on account of
this Change in Law event in respect of the Power Purchase Agreement entered under
Section 62 or Section 63 of the Electricity Act, 2003
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 14
5.4 For the TPPs that are under the purview of the Central Commission, the Commission
shall develop appropriate regulatory mechanism to address the impact on tariff and
certainty in cost recovery on account of additional capital and operational cost, under
concluded long term and medium term PPAs for this purpose.
11.6 SRPC Secretariat vide letter dated 25.06.2018 (Annexure-XIII) had forwarded CEA
letter seeking updated information in respect of status of implementation of revised FGD
installation / ESP upgradation plan to comply with the new environment norms. Updated
information is to be communicated periodically (initial update was to be furnished by
30.06.2018). It was mentioned in the CEA letter that the report will be submitted to
Hon’ble Supreme Court every quarter.
12. COAL ISSUES
12.1 Number of thermal power stations in the Region had faced critical coal stock situation in
the past few months. The following had been noted in earlier Meetings:
Chairperson, SRPC vide letters dated 25th
September 2017 and 13th
November 2017
had taken up the issue regarding critical coal stock and availability of sufficient rakes
with Ministry of Power.
SRPC vide letter dated 22nd
November 2017 had raised energy security concerns
with Hon’ble CERC and requested that the matter regarding maintenance of low coal
stock by CGS station whose tariff is approved by Hon’ble Commission may kindly
be examined.
As agreed in the Secunderabad Meeting held on 21st December, Chairperson, SRPC
vide letter dated 28th
December 2017 had taken up the issue regarding ‘Consent of
original beneficiaries’ for diversion of coal with Chairperson, CEA.
CEA had informed that CEA and NTPC, with active help of Railways and Ministry
of Coal are developing an IT application which would help in monitoring of coal
stock available at each Railway siding, with daily receipts and dispatch of coal, rake
allocation for coal supply to generating stations. This along with stock, consumption
and receipt of coal at generating station as available in NPP Portal, would help in
effective monitoring of coal supply. This would help ensure that coal movement is
monitored from source to consumption.
APGENCO had requested for minimum 2 rakes/day at Balram siding. Moreover,
sufficient rakes were required at Talcher (3 rakes/day) and Ib (5 rakes/day) sidings to
improve the coal at Vijayawada TPS and Rayalaseema TPS which was less than 5
days on sustained basis. For Unit 6 at Rayalaseema (Stage IV) additional 2 rakes/day
were required for movement of raw coal from MCL for this purpose.
KPCL had informed that around 18 rakes/day would be required for FY 2018-19.
Additionally around 2-3 rakes were required for fly ash movement. KPCL had
requested to ensure adequate availability of valid rakes for movement of allocated
coal through ARR.
Logistic constraints between Sambalpur-Rayagada and the congestion between
Vizianagaram and Vizag were noted.
MCL had pointed out that Availability of BOXN rakes (in ECR and ECOR) for long
distance linkage power plants are to be improved. Availability of Box N rakes for
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 15
maximizing long distance linkage power plants is to be improved. Presently, Box N
rakes are not sufficient with Zonal Railways. Congestion in ECO Railways, for rakes
going to Paradip and through Sambalpur – Titlagarh route was affecting rake
materialization for plants located in Southern Region. Also BOB rakes need to be
allowed over long distance for power plants such as Simhadri and other plants with
BOB rakes unloading facilities. To Paradip port, BOBR rakes were being supplied,
and Gencos may need to avail RSR route also instead of All Rail Route to reduce
congestion. There had been no shortfall in offer by MCL while problem was mainly
with regard to availability of rakes by Railways. MCL had also requested Gencos for
clearing of the dues to MCL in a timely manner.
12.2 As agreed in 33rd
Meeting of SRPC, Chairperson, SRPC vide letter dated 20.02.2018
(Annexure-XIV) had taken up the concerns of SR Thermal generators with Chairman,
Railway Board.
12.3 MD, APGENCO vide letter dated 08.06.2018 (Annexure-XV) had taken up issues of
transportation of raw / washed coal from MCL to APGENCO power plants by ARR with
Railways. Daily requirement had been specified as 2 rakes/day from BBMT siding & 3.2
rakes/day for Dr NTTPS, 1.33 rakes/day for RTPP and 2 rakes/day for RTPP stage-4.
12.4 NTPL vide letter dated 31.05.2018 (Annexure-XVI) had requested CEA to review the
criteria of criticality for NTPL coal stock position as 20 days for critical and 9 days for
super critical so as to improve the allocation of coal companies and rakes by railways.
12.5 NTECL vide mail informed that around 233 MU had been lost (in DC Declaration) from
01.04.2018 to 21.05.2018) (Annexure-XVII) on account of fuel shortage.
12.6 SRLDC had prepared a link wherein details of coal need to be uploaded
(https://goo.gl/y3LL4n). This information has to be kindly furnished before 06:00 hours
every day (critical since information is shared with MoP).
12.7 APGENCO vide letter dated 5th
July 2018 ( Annexure-XVIII) have informed that they
are getting 2 to 3 grade slippages particularly in case of coal received from Manuguru
and Rudrampur mines for RTPP and Dr NTTPS thermal stations. This is despite constant
pursuance with SCCL and CIMFR.
13. STATUS OF DC/GENERATION IN ISGS
13.1 Issue regarding low DC/Generation at NLC TS-II Expansion and NTECL had been
deliberated in earlier Meetings of SRPC. Level of generation of some ISG stations is
given below please:
Station Feb-18 Mar-18 Apr-18 May-18 June-18
NTECL,
Vallur
DC % 67.19 72.63 98.18 80.23 64.43
PLF (on Actual)
%
56.43 62.88 85.91 97.57 48.87
NLC TS
II Exp
DC % 44.14 31.52 25.78 30.62 16.72
PLF (on Actual) 29.51 32.43 26.34 30.97 17.26
MAPS PLF (on Actual) 51.24 51.04 50.20 49.03 50.51
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 16
13.2 The following had been noted in earlier Meetings:
MS, SRPC had informed that the loss in DC wrt normative was 956/272/356 MW
during Nov 2017/Dec 2017/Jan 2018 respectively. While scheduling right is with the
beneficiary, DC being the prerogative of generator should not be less.
NLC had informed that some modification works through OEM had been planned and
full availability was expected during the first quarter of 2018-19.
NTPC & NLC had also requested for maximization of consent for trading.
It had been noted that Unit-III of NTECL which was out since 06.06.2017 had come back
on bars on 27th
February 2018.
14. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY
14.1 In the 29th
Meeting of SRPC it had been noted that in the matter of Roadmap to
operationalize Reserves in the country, Hon’ble CERC vide Order dated 13.10.2015 on
Petition No. 11/SM/2015 had directed as follows:
(b) The Commission reiterates the need for mandating Primary Reserves as well as
Automatic Generation Control (AGC) for enabling Secondary Reserves.
(i) All generating stations that are regional entities must plan to operationalize AGC
along with reliable telemetry and communication by 1st April, 2017.
(iii) The Central Commission advises the State Commissions to issue orders for intra-
state generators in line with this timeline as AGC is essential for reliable operation
of India’s large inter-connected grid.
(c) To start with, a regulated framework in line with the Ancillary Services Regulations
would need be evolved for identification and utilizing of spinning reserves and
implemented with effect from 1st April, 2016. This framework may continue till 31
st
March, 2017.
……………
(d) In the long term, however, a market based framework is required for efficient
provision of secondary reserves from all generators across the country. For this,
NLDC/POSOCO is directed to commission a detailed study through a consultant and
suggest a proposal to the Commission for implementation by 1st April, 2017, giving
due consideration to the experience gained in the implementation of Spinning
Reserves w.e.f. 1st April, 2016.
14.2 In earlier Meetings the following had been noted:
Hon’ble CERC in Petition No. 79/RC/2017 had passed Order dated 6th
December,
2017 in the matter of ‘Automatic Generation Control (AGC) pilot project’.
NLDC had informed that in respect of AGC at Simhadri, offer had been received
from M/s Siemens. They would convene a Meeting with NTPC on 20th
February and
then the Order would be placed with implementation schedule of 5 to 6 months.
Regarding AGC at NP Kunta, M/s USAID had agreed to take the AGC
implementation under GTG project. On 10.02.2018, after assessment it had been
concluded that AGC implementation at NP Kunta was feasible. AP utilities as well as
SERC were required to be consulted in this regard.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 17
14.3 A Meeting on AGC related issues was conducted at SRPC on 28th
March 2018 (MOM
available on SRPC website). The following highlights may kindly be noted:
Better Load Forecasting and RE framework (forecasting, scheduling & settlement)
would naturally result in lesser reserve requirement and needs to be pushed through
FOR.
Scheduling software for unit commitment, meeting the ramps (+)/(-), ramps of
generators, fast start up and shutdowns of generators, errors in load and RE forecast,
technical minimum, meeting peak demand, meeting minimum demand, net load, pump
operation etc is required for resource optimization and proper decision support.
Forum opined that there was a need for a Procedure to quantify Secondary/Tertiary
Reserves. Procedure should also include a Mechanism to monitor these reserves in real
time manner for replenishment of these reserves.
Sharing of these secondary/tertiary reserves, including those available with States,
could lead to optimization of reserve requirement. However, the mechanism of sharing
and associated cost needs further analysis and discussions.
While there was lot of focus on positive reserve, during large RE ingress, negative
reserve is also required. This needs to be covered prominently in the reserve ambit.
Secondary and tertiary reserves should always be available with system operator and
cannot be dynamic with URS availability (diminishing during peak hours) or with all
units are running in Technical Minimum (no negative reserve). Whether this could be
achieved through Market based reserve or through regulatory mandatory market needs
to be studied?
There needs to be a mechanism in place for sharing of secondary/tertiary reserves
available with the states. These reserves are to be made available with the system
operator.
Time bound implementation of ABT in the states is also necessary for AGC
(Secondary)/Tertiary Reserves to take off.
Forum (except NLDC/SRLDC) was of the view that Gate Closure already exists (30
minutes prior to the delivery) as per IEGC. This issue needs to be further examined.
Forum opined that proposed Bias Setting requires further review.
It was noted that in the Report on National Reference Frequency it has been
recommended that dead band of +/-0.03 Hz (ripple factor in IEGC) may be gradually
phased out as is being done in ERCOT Texas and Europe. Generators opined that this
dead band of +/-0.03 Hz (ripple factor in IEGC) may need to be retained.
For SCADA veracity it was noted that it was joint responsibility of all the entities to
take proactive and appropriate steps to ensure consistency in data. The issue needed
due attention it deserves being critical in grid operation. Entities need to have
dedicated team with 24x7 support specifically at SLDC/RLDC/NLDC/CTU/STU.
It was noted that Optical Fibre Connectivity could be assessed and action plan could be
finalized by CTU/STU.
There is a need to have AGC pilot projects in all the SLDCs. It was thus recommended
that each SLDC could have a AGC standalone infrastructure with one or two stations
wired for AGC as Pilot Project. This approach would enable faster implementation of
AGC upto the state level. This would ensure hands on experience at State Level at a
faster pace along-with the development of infrastructure facility at SLDCs.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 18
IEGC provision that the schedules should not exceed capacity on bar less Normative
Auxiliary Consumption needs to be implemented pan India for all generators- ISGS,
State generators, IPPs, MPPs etc.
Forum strongly advocated for AGC for RE generators also. There would be need for
both positive and negative reserves provision for RE also. There is need to have a well
laid down procedure including commercial settlement, which could also be a market
based mechanism.
14.4 In the OCC Meetings the following had been noted:
KPCL had informed that M/s Andritz for Varahi and M/s ABB for Sharavathy have
been identified for AGC implementation by USAID / PRDC for which KPCL had
given approval. This was expected to be completed by December 2018. Further, AGC
for 10 MW of Solar project at Sivasamudram was also under consideration.
Simhadri, NTPC had informed that the infrastructure readiness for AGC was likely to
be in place by August 2018.
A Workshop had been conducted on 15th
May 2018 at APSLDC by NLDC on AGC at
NP Kunta.
15. TTC/ATC
15.1 ATC/TTC computations by SLDCs
The following had been noted in earlier Meetings:
APSLDC had assured that the system would be in place before the next Meeting of
SRPC.
KAR-SLDC had informed that the converged case was being furnished, while details
of Nodal Officer would be furnished within a week.
The following is the status in this regard please:
State 5
months
LGB
Converged
PSSE Base
case
ATC/TTC
Computation
furnished to
SRLDC
ATC/TTC
Computation
posted on SLDC
website
Nodal
Officer
Status
Study
Group
AP Yes No No No No Yes
TS Yes Yes No No Yes Yes
KAR Yes Yes No No No Yes
TN Yes Yes Yes No Yes Yes
KER Yes Yes Yes No Yes Yes
The following had been noted in the Meetings of OCC:
APSLDC had constituted a Study Group. While one DE had been posted, supporting
staff was to be posted.
SRLDC had assured of cooperation in training of the officials in this regard.
15.2 Harmonization of Philosophy of Computation of Total Transfer Capability (TTC)
by POSOCO and CTU between ER-SR & WR-SR
In a Special Meeting convened by NPC on 23rd
October 2017, Members had agreed
for an approach for preparing base load flow case to compute TTC/ATC for the
purpose of operationalization and grant of MTOA.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 19
SRPC had requested NPC to similarly kindly finalize procedure for base case
preparation by POSOCO, in respect of STOA.
In line with the decision taken in the 32nd
TCC Meeting, SRPC Secretariat had taken
up the issue of finalizing the procedure for base case preparation by POSOCO in
respect of STOA with NPC vide letter dated 05th
March 2018 (Annexure-XIX).
15.3 TTC/ATC enhancement – Operational guidelines issued by NRCE
SRPC vide letters dated 13.11.2017 and 20.11.2017 had requested POSOCO to assess
possibility of TTC/ATC enhancement as per operational guideline for determination of
TTC, ATC and TRM for short term horizon (0-3 months) issued by NRCE, keeping in
view high demand (Jan-Apr), coal shortage conditions etc.
NPC vide letter dated 13th
March 2018 (Annexure-XX) had again taken up the issue
with CTU and requested that required details of terminal equipment may please be
furnished. It was observed that the same request had been conveyed to CTU vide NPC
letters dated 21.11.2017, 19.12.2017 and 16.02.2018.
In the 5th
Meeting of Grid Study Committee (GSC) held on 18.06.2018, Chairperson,
CEA had observed on increasing the TTC through dynamic loading of line, use of
HTLS etc.
CTU is kindly requested to furnish information sought by NLDC for TTC/ATC
enhancement as per operational guideline for determination of TTC, ATC and TRM
for short term horizon (0-3 months) issued by NRCE.
16. ISSUE OF PREVAILING OVER VOLTAGES IN SR GRID
16.1 Number of nodes in SR are facing high voltage problems. PGCIL had pointed out that
these over voltages lead to over stress on substation equipment including ICTs,
Reactors, CVTs, CTs etc. Life span of equipment is also affected adversely leading to
early failures.
16.2 In the Operational Feedback for the quarter (January-March 2018), POSOCO had
highlighted high voltage nodes (41 nodes at 400 kV & 765 kV). List of lines which
were opened by real time operators to control over voltage in the grid were also
displayed.
16.3 Details of nodes of high voltage coupled with MVAR injection during the period
February 2018 to June 2018 are given below please:
Nodes with MVAR injection during V > 103%
AP KAR TN TS
Nellore PG Nelamangala Tiruneveli Maheshwaram
Kurnool Mysore Alamathy Hyderabad
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 20
Vijayawada Karaikudi Malkaram
Gazuwaka Pugalur Gajwel
Chittoor Mehaboobnagar
Vemagiri Khammam
Warangal
Dichipally
16.4 The issue of prevailing high voltage at 400 kV Urvakonda and 400 kV Jammalmadugu
sub-stations was taken up with APSLDC vide SRPC letter dated 03.07.2018
(Annexure-XXI). As mentioned earlier, it had been stated that KSEBL had informed
that RE generators are not being penalized (charges suspended) on injection or
absorption of MVAR in case the same is as per SLDC instructions. It was suggested to
consider similar philosophy in AP system to contain the high voltage scenario.
17. ISSUES IN RESPECT OF NPCIL
The following are the issues in respect of NPCIL stations:
17.1 Balance dues from Beneficiaries
Issue of outstanding dues of Southern Region beneficiaries to NPCIL had been
discussed in the 33rd
Meeting of SRPC. All beneficiary states had assured of early
settlement of the dues. The issue was regularly followed up by NPCIL stations and
MS, SRPC and the same was further discussed in the 38th
Meeting of CC. Director (F),
NPCIL vide letter dated 31.05.2018 (Annexure-XXII) had expressed concern on
significant dues. Outstanding dues to NPCIL as discussed in 38th
CCM (29.06.2018)
are as follows:
Sl.
No.
Entity MAPS
as on
30.05.2
018
KGS
(as on 26.6.18-
excluding May
2018 energy bill)
KKNPP as on 27.06.2018
Bill
Amount
Delayed
payment
charges
1 TNEB 188 184.89+119.28 989.19 138.446
2 HESCOM
(Karnataka) 4 191.02+71.59 167.672 25.221
3 Telangana 9 150.31+5.49 23 6
4 GESCOM
(Karnataka) 2 56.18+4.76 65.1925 4.484
5 CESCORP
(Karnataka) 2 33.21+3.65 37.355 3.286
6 APTRANSCO 7 56.17+10.9 1.198 0.642
7 PED
(Puducherry) 3 13 20.71 1.886
17.2 Part load operation/Reserve shutdown/frequent changes in revival of KKNPP units
In the 32nd
Meeting of TCC, it was noted that with higher RE penetration, NPCIL units
need to offer some flexibility (seasonal, part load etc) which was need of the hour.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 21
SR constituents had suggested that only one unit of KKNPP could be in service during
July to September each year and refueling need to be planned accordingly.
SR constituents had also pointed out that during peak demand months (Feb to Apr)
both the units at KKNPP need to be in service. The 1,000 MW size of KKNPP units
has significant impact on the LGB and even affects the power market price also.
Frequent change in revival was completely distorting purchase planning and LGB of
the control area. TN being a major beneficiary was impacted by around 550 MW for
any delay in revival of the unit.
To achieve the above requirements, part load operation / reserve shutdown needs to be
contemplated by NPCIL.
Chairperson, SRPC vide letter dated 11.04.2018 (Annexure-XXIII) had taken up the
pertinent issues with CMD, NPCIL.
TANTRANSCO vide letter dated 11.06.2018 (Annexure-XXIV) had suggested that
either one of the units be in service till September 2018 end, while both units would
need to be available from October 2018.
Director (F), NPCIL vide letter dated 31.05.2018 (refer Annexure-XXII) had requested
that beneficiaries may surrender surplus power on long term basis so that MoP may be
approached by NPCIL for allocation of the same to other beneficiaries in need of the
same. Further, it had been pointed out that in view of the defaults in payments of more
than 6 months and in most cases 4 to 5 months, the entitlement of these beneficiaries
from Kudankulam power of NPCIL could be reduced to the extent of surplus power
available even if it is more than 15% enabling NPCIL to sell it to others for cash and
serve purpose of both energy consumers and producers.
17.3 BSD of KGS units
Kaiga 1 & 2 would inform the extended dates for BSD of Unit 1well in advance to
OCC/SLDC KPTCL for the states to plan their LGB in an economic and secure
manner.
Shutdown of Unit 1 would not be allowed during Jan to April 2019.
On similar lines Kaiga GS would in future not schedule BSD for any of its units during
Jan to April.
All units would be planned for BSD only during the period June to December each
year.
17.4 Black Start Mock Drill at Kaiga GS and MAPS
In the Meeting held on 22.06.2018, KGS had informed that Black Start Mock Drill
would be taken up during BSD of Unit-I, on similar lines to KKNPP.
MAPS Black Start Mock Drill to be carried out.
17.5 PSS tuning / SRT
In the Meeting held on 22.06.2018, Kaiga GS agreed for PSS Tuning of unit during
BSD of Unit 1 & III respectively.
MAPS Unit –II PSS tuning/SRT to be completed.
17.6 MVAR interchange by Kaiga GS units (Meeting held on 22.06.2018)
Kaiga GS units 1 & 2 would start absorbing MVAR as per Capability Curve above 225
kV while there would be no MVAR injection at voltages in the range 220-225 kV.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 22
Kaiga GS/NPCIL would take all steps to ensure commissioning of first 125 MVAR by
December 2019. Kaiga GS/NPCIL would also initiate tendering activities of second
125 MVAR reactor. The same needs to be confirmed along with detailed
commissioning plan in the 34th
Meeting of SRPC scheduled in August 2018.
During testing activities of generator 3 & 4 with respect to MVAR absorption, Kaiga
GS would also involve SRPC & SRLDC.
Kaiga GS would endeavor to support the grid within mandated provisions of
IEGC/CEA & CERC Regulations.
17.7 2x125 MVAR Reactor commissioning at Kaiga GS (meeting held on 22.06.2018)
Kaiga GS/NPCIL had informed that technical bids had been opened for the first 125
MVAR reactor on 20th
June 2018. The reactor was planned to be commissioned by
December 2019.
Kaiga GS/NPCIL had assured that bidding activities for second 125 MVAR reactor
would also be initiated.
As also discussed in the Special Meeting held 22.06.2018 held at Kaiga GS,
Chairperson, SRPC vide letter dated 26th
June 2018 (Annexure-XXV) had taken up
this issue with CMD, NPCIL
17.8 Other issues as noted in the Meeting held on 22.06.2018 and other Meetings
Kaiga GS/NPCIL agreed for providing Differential and REF protection through
different relays in ICT-1&2. This would be complied by December 2018 by procuring
additional relays.
LBB time setting for lines is 0.25 sec and for ICTs - 0.2 sec. Kaiga GS informed that
the settings had been reviewed and it has been decided to keep settings as 200 msec for
all. Approval letter from HQ had been received and the same would be completed
during Bus Shutdown at the time of BSD of Unit 1.
KGS agreed to disable sending of DT to remote ends upon 86 X operation for any line
protection operation at its 400 kV KGS, within one month.
KGS agreed to ensure time-synchronization of all protection relays with GPS in their
400 kV switchyard by December 2018.
KGS agreed to use stipulated formats for furnishing FIR and TR.
KGS agreed to include line backup protections in Main I & Main II within 2 months,
and configure DR’s & EL’s of Main I & II for recording all mandated protections.
Kaiga GS would extend support for insulator replacement works in Kaiga complex.
The works would be completed within 3-4 months since new work order had to be
placed.
SRPC & SRLDC had pointed out that as User it was responsibility of Kaiga GS to
ensure data availability to SRLDC. It was agreed that Kaiga GS would formally take
up RTU related issues with SR-II, PGCIL with a copy to SRLDC & SRPC. SRLDC
would endeavor to facilitate these works through SR-II; however onus of ensuring
SCADA compliance rested with Kaiga GS.
Kaiga GS agreed to extend the digital status under URTDSM within a month.
KKNPP had informed that rectification of the other reactor would be taken up in
April/May 2018 and was expected to be completed by December 2018.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 23
With regard to A/R implementation on MAPS lines, NPCIL had informed that
procurement of required line CVTs was under progress. Commissioning of CVTs and
A/R enabling on all the four 220 kV lines was targeted to be completed by September
2018. MAPS had informed that PO was released for procurement of the CVTs. A/R for
the lines would be implemented after receiving the CVTs.
18. UPCOMING TRANSMISSION SYSTEM
18.1 42nd
Standing Committee on PSPSR
Minutes of Meeting of 42nd
Meeting of Standing Committee on Power System Planning in
SR (meeting held on 27.04.2018) had been issued on 15th
June 2018 (available on CEA
web site).
18.2 Operationalization of LTA
In Petition No. 12/SM/2017 along-with I.A. No. 54/2017, in the ROP for date of hearing
15.05.2018 (Annexure-XXVI) it was noted, ‘….the representative of CTU further
submitted that there are certain regulatory issues in operationalization of LTA as under:
(a)Non-opening of LC ………..(b)Relinquishment en-masse (specially on HCPTC
corridor) ……….(c)Abandonment of Generation Project / Adverse Progress…. After
hearing the representative of CTU, the commission reserved orders in the petition.’
18.3 Upcoming inter-regional transmission schemes
18.3.1 Updated status is furnished below please:
S S.No. Transmission Element Remarks
a) WR-SR 6000 MW HVDC Bipole
Link [Raigarh (Chhatisgarh) -
Pugalur-Trichur (TN/KER)]
Apr’ 2020
32nd
TCC: 800 kV December 2018. 320 kV: September 2019.
CEA (May 2018): Work held up in Tamil Nadu due to severe ROW -
Critical. Huge forest involvement (432 Ha.) in WR portion incl. Wildlife
Sanctuary clearance. Critical.
320 kV: Feb 2020 - Progress affected due to severe ROW problem in Tamil
Nadu area.
b) 765 kV Angul - Srikakulam PS D/C
Corridor
Main corridor commissioned.
Other associated elements by July
2018.
32nd
TCC: PGCIL informed that Garividi- Srikakulam PS was expected by
May/ June 2018. AP informed that downstream system is ready.
OCC update: To be charged in July 2018.
c) Additional inter-Regional AC link for
import to Southern Region, i.e.,
Warora - Warangal - Hyderabad-
Kurnool 765 kV link
TBCB, PFCCL- BPC Transmission Licensee : Warora-
Kurnool Transmission Limited
(WKTL)
32nd
TCC: There was a Meeting held to consider preponing of Hyderabad-
Kurnool line. It was concluded that further study may be required before
concurring for this preponement. One more Meeting was to be held.
CEA (May 2018): Nov 2019.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 24
d) System strengthening within SR for
transmitting power beyond Vemagiri TBCB- RECTPCL-BPC
Project has been awarded to
PGCIL under TBCB, and was
expected by April 2019.
32nd
TCC:
Chilkaluripeta – Cuddapah line was stuck up for want of wild life (Tiger
Conservation Reserve) clearance. It requires forest clearance from
AP/TS/Central Govts. They had taken up the issue since Tiger
Conservation Reserve is yet not in public domain, they may not to be
obligated to take this clearance. There were AP lines also stuck up due to
the same issue. The line would come up in Q3 of 2018-19.
Cuddapah – Madhugiri Q2 of 2018 – 19.
POSOCO’s Operational feedback for the quarter January to March
2018
The import capability of Southern Region can only be increased after the
constraint on ICTs at Vemagiri (PG) is relieved. The commissioning of
following 765 kV outlets at Vemagiri(PG) need to be expedited in order to
relieve the constraint on Vemagiri ICTs:
a) 765 kV Vemagiri – Chilkaluripeta D/C
b) 765 kV Chilkaluripeta – Cudappah D/C
c) 400 kV Chilkaluripeta – Narasaropeta D/C
d) 400 kV Cudappah – Hindupur D/C
e) 400 kV Cudappah – Madhugiri
18.3.2 Updated detailed status of upcoming inter regional schemes is furnished at Annexure-
XXVII.
18.4 Pending transmission elements in WR and SR for proper utilization of 765 kV
Raichur- Sholapur line (Out of planned 18 elements)
18.4.1 Updated status of pending transmission elements in WR and SR for proper utilization of
765 kV Raichur - Sholapur lines (out of planned 18 elements) is furnished below please:
Sl.
No
Name of Transmission Element
1 400 kV Tumkur-Yelahanka D/C line ; PGCIL (132 Ckm)
32nd
TCC: Sep 2018; CEA (May 2018): Dec 2018; Severe ROW in Karnataka.
Balance work re-awarded in Dec'17. Work under progress.
2 400 kV Nelamangala-Hoody LILO at kV Yelahanka ; PGCIL (20 Ckm)
CEA (May 2018): Charged on 22.03.2018 and COD from 01.04.2018
3 220 kV Tumkur – Antharasana Halli D/C ;KPTCL; LOA placed on 18.03.15 with
18 months completion schedule
32nd
TCC: March 2018
Special Meeting (09.07.2018) : KIADB has to procure and hand over the land.
4 220 kV Tumkur (400 kV) S/S – 220 kV Tumkur S/S D/C; KPTCL; LOA placed
on 18.03.15 with 18 months completion schedule
32nd
TCC: March 2018
Special Meeting (09.07.2018): KADB has to procure and hand over the land.
5 220 kV Yelahanka (400/220 kV) S/S- 220 kV Yelahanka S/S D/C Cable;
KPTCL (11.75 Ckm)
Special Meeting (09.07.2018): End of August 2018.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 25
18.5 Status of important Transmission Systems
18.5.1 Updated status of associated links is furnished below please:
Transmission Elements
1 765 kV S/C Salem PS (Dharmapuri) - Madhugiri P S line (initially charged at
400 kV) ; 243.23 ckm; PGCIL
32nd
TCC: March 2018
CEA (May 2018): Sep 2018, Severe ROW in Karnataka. Obstruction is being
removed progressively with the help of Police protection.
Covered under PRAGATI.
2 Salem New – Madhugiri 765 kV S/C line; 219 ckm ; (PNMTCL) (A subsidiary of
PGCIL)
32nd
TCC: June 2018
CEA (May 2018): Sep 2018; Severe RoW issues being faced in Karnataka, issue
highlighted to PMO level.
3 Transmission evacuation system for HNPCL (1,040 MW) Power Plant
APTRANSCO ; 400 kV TM D/C Kamavarapukota – Vemagiri; 185 ckm
31st TCC: Alternate options being explored, would be taken up with the Standing
Committee.
4 Transmission System required for evacuation of power from Kudgi TPS (3x800
MW in Phase-I) of NTPC Limited
KPTCL : 220 kV D/C line to Vajramatti: June 2018, 220 kV D/C line to Basavana
Bagewadi, 220 kV D/C line to Bijapur
5 Transmission System for evacuation of power from Singareni Collieries
Generating Project (2 x 600 MW)
TSTRANSCO : STPP, Jaipur – Jagityal; 139 ckm
31st TCC: Nov 17
TSTRANSCO : Jagityal – Nirmal; 148 ckm
31st TCC : Line ready; Nirmal SS by Nov 2017
6 Damaracherla TPP Evacuation
TSTRANSCO: 400 kV Damacherla TPP – Choutuppal D/C : Sep 2018, 400 kV
Damacherla TPP – Dindi D/C : Sep 2018, 400 kV Damaracherla TPP – Jangaon
D/C : Sep 2018, 400 kV Damaracherla TPP – Maheswaram (TS) D/C : Sep 2018
7 Bhadradri TPP (Manuguru) (4x270 MW), TSGENCO
TSTRANSCO: 400 kV Julurupadu SS - Manuguru TPP D/C : 2018-19, 400 kV
Julurupadu (QM) - Suryapet S/S D/C : 2018-19, Julurupadu S/S 2x 315 MVA : Bus I
and Bus II charged on 23.12.2017
8 Kothagudem TPS St-VII (1x800), TSGENCO
TSTRANSCO : 400 kV D/C Julurupadu - KTPS (Stage-VII): -, 400 kV Julurupadu –
Jangaon D/C : - Jangaon SS: -
9 Transmission system of KPTCL for evacuation of power from Yermarus TPS
(2 x 800 MW)
KPTCL : Yermarus TPS - Bellary PS 400 kV D/C QM
Gulbarga 400/220 kV substation- 2 x 500 MVA, Yermarus TPS - Gulbarga 400 kV
D/C line (QM),
400 kV SS at Chikkanayakanahalli – 2 x 500 MVA (39th
SC) Alternate site at
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 26
Bindikere is under consideration. Land acquisition is under progress.- CEA (May
2018): Sep 2018
LILO of Nelamangala – Talaguppa 400 kV D/C at CN Halli, Termination of 400 kV
D/C of Hassan from Nelamangala – Talaguppa at CN Halli 400 kV, Bellary PS -
C.N.Hally 400 kV D/C line QM
De-link 400 kV S/C RTPS-BTPS-JSW-Guttur with JSW Bus
Additional JSW TPS – BPS 400 kV D/C (QM)
400 kV BTPS-Guttur D/C (QM)
10 Transmission System for Rayalaseema TPS (600 MW)
APTRANSCO: 400/220 kV, Kalikiri S/S – 2 x 315 MVA: 2018-19: PO is placed in
Nov-15. Site handed over on 23.06.2016
LILO of Rayalseema IV-Chittoor 400 kV D/C at Kalikiri: 2018-19
11 400 kV Somanahalli- Dharmapuri PS; 244 ckm; PGCIL
32nd
TCC: June 2018
CEA (May 2018): Sep 2018 - Severe ROW problem faced in Karnataka. With the
support of state Govt. ROW issues are being resolved.
12 400 kV Mangalore (UPCL ) -Kasargode-Kozhikode; TBCB
13 400 kV Edamon-Kochi; 286 ckm; PGCIL
Being monitored under PRAGATI.
32nd
TCC: May 2018
CEA (May 2018): Sep 2018 - Severe ROW problem (long pending). Problem being
addressed progressively as per latest Revised G.O. of 30.07.15 (compensation to be
done on land value, to be finalized by concerned DC with the support of State Govt.).
Works under progress. Site is getting police protection as per requirement from State
admn. Foundation works affected due to non-availability of aggregate. Matter has
been taken up Secy. level.
14 LILO of 230 kV Neyveli- - Bahour at Karaikal
32nd
TCC: April 2018
CEA (May 2018) : NLY- Karaikal – Aug 2018
15 400 kV Pavagada – Hiriyur D/C line; PGCIL
32nd
TCC: March 2018
CEA (May 2018): Dec 2018- Slow progress due to ROW problem.
16 400 kV Hiriyur – Mysore line; PGCIL
32nd
TCC: June 2018
CEA (May 2018) : Jan 2019 – severe ROW issues
42nd
SCPSPSR: to be expedited to relieve over loading of Nelamangala-Mysore 400
kV D/C line getting heavily loaded.
17 400 kV Pavagada – Devanahalli D/C line; (139.30 D/C and 13.20 M/C); PGCIL
32nd
TCC: December 2018
CEA (May 2018) : Jan 2019 – severe ROW issues
18 FSC at Pavagada; PGCIL
32nd
TCC: July 2019
18.6 Associated Transmission Evacuation Schemes in Tamil Nadu
Updated status of the following stations, evacuation schemes finalized in the 37th
SCPSPSR, which were modified in the following Standing Committee Meetings, is given
below please:
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 27
Generating Station Likely COD Evacuation Status
Ennore TPS Expansion – 1 x
660 MW
2019-20
Ennore SEZ (NCTPS Stage-
IV) – 2 x 660 MW
2018-19
NCTPS Stage III – 1 x 800
MW
2019-20 41st SCPSPSR: 2019
Ennore TPS Replacement – 1
x 660 MW
2019-20 41st SCPSPSR: 2020
SEPC (1x525) October 2018 41st SCPSPSR: Require
start up power for its
Auxiliaries by April 2018.
SEPC-Thennampatty
400/230/110 kV 41
st SCPSPSR : April
2018
SEPC- Ottapidaram 400kV
(Regular evacuation)
765/400 kV, 2 x 1500 MVA
Ariyalur SS
31.3.2019 Work awarded to M/s BHEL
on 31.03.2017.
765/400 kV, 3 x 1500 MVA
North Chennai PS (GIS) March 2020 Work awarded to M/s
Hyosung Corporation,
Korea on 21.03.18
765/400 kV, 2 x 1500 MVA
Coimbatore SS
2020-21 Administrative approval
accorded. Alternate land is
to be identified.
765 kV Ariyalur –
Thiruvalam (PG) CEA (May 2018): June
2018
Work awarded to M/s
Transrail. Works are
under progress
765 kV North Chennai PS -
Ariyalur CEA (May 2018): Sep
2019
Work under progress.
400 kV Ennore SEZ-North
Chennai PS CEA (May 2018): Sep
2018
Tender opened on
07.06.17. Price bid opened
and evaluation is under
process. Approval of
BLTC to recommend to
place before board.
400 kV Ennore SEZ- Ennore
to ETPS Expn CEA (May 2018): April
2019
400 kV ETPS Expn – North
Chennai PS CEA (May 2018): Sep
2018
Interconnection from
common point of SEZ –
ETPS Expn to NCTPS Stage-
II and LILO of NCTPS-II –
SV Chatram 400 kV MC
between location No.21 & 22
18.7 Status of Implementation of downstream network by State utilities associated with
ISTS substations of POWERGRID
Sl.
No
Name of
Substation
MVA
Capacity
220kV
Bays
Expected
Schedule of
Substation
Remarks
1 Tumkur
(Vasantnarsa
pur)
2 x 500 6 Commissioned Construction of downstream
T/L for 6 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR : 4 Nos 220kV downstream links i.e. Tumkur-
Anthranasahalli 220kV D/C line & Tumkur- Madhugiri-II 220kV D/C line expected
by Sep’18. Balance 2 Nos 220 kV downstream links yet to be taken up
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 28
2 Yelahanka 2 x 500 10 Commissioned Construction of downstream
T/L for 10 Nos (6 bays under
ISTS) 220 kV bays to be
expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream T/L cable to
Yelahanka DG plant expected by Jun’18. Balance 4 Nos 220 kVdownstream links yet
to be planned.
3 Bidadi 2 x 500 6 Commissioned Construction of downstream
T/L for 4 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream links i.e Bidadi –
Magadi 220 kV D/C line expected by Mar’19. 2 Nos 220kV downstream Link
Bidadi-Kumbalgodu expected by Mar’20.
4 Hiriyur 2 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220kV downstream links i.e. Hiriyur-
Hiriyur (KPTCL) 220 kV S/C line & for Hiriyur-Chitradurga 220 kV S/C line
expected by Mar’19.
5 Hassan 2 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream T/L i.e. LILO of
Hassan(KPTCL) – Nittur S/c expected by Mar’19.
6 Kolar 2 x 500 6 Commissioned Construction of downstream
T/L for 2 Nos 220 kV bays to
be expedited by KPTCL.
Deliberations in 42nd
SCPSPSR: 2 Nos 220 kV downstream links Kolar-Gollahalli
220kV D/C line expected by Mar’19.
7 Karaikudi 2 x 315 4 Commissioned Construction of downstream
T/L for 1 Nos 230 kV bay to
be expedited by
TANTRANSCO
Deliberations in 42nd
SCPSPSR: 1 Nos 230 kV downstream T/L Karaikudi –
Sembatty 220kV S/c line expected by May’18.
8 Hosur 3 x 315 6 Commissioned Construction of downstream
T/L for 2 Nos 230 kV bays to
be expedited by
TANTRANSCO
Deliberations in 42nd
SCPSPSR: 2 Nos 230 kV downstream T/L Hosur -Shoolagiri
220kV D/C line expected by Jul’18.
9 Kozhikode 2 × 315
+
1 x 500
4 Commissioned Construction of downstream
T/L for 1 Nos 220 kV bay to
be expedited by KSEBL
Deliberations in 42nd
SCPSPSR: 1 Nos 220 kV downstream T/L to
Kozhikode(KSEB) expected by Mar’19.
18.8 Operational Feedback
18.8.1 NLDC vide letter dated 30th
April 2018 (available on NLDC website) had highlighted
following transmission constraints as part of Operational Feedback for the quarter
January– March 2018, in respect of SR:
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 29
a) Impact on grid operation due to ferro-resonance
Outage of FSC leads to power order reduction in HVDC Gazuwaka block (s) because
high power order without series capacitive compensation at Jeypore causes low voltage
at Gazuwaka East bus.
Frequent repetition of this phenomenon may affect reliable system operation at Eastern
region and Southern region boundary, and may even cause equipment damage, if the
FSC bypass scheme fails to act in case of ferroresonance.
It is necessary to carry out necessary system improvements aimed at damping the
resonant condition.
HVDC links are critical to integrated power system operation, since operator is able to
gain flexibility in power system operation using HVDC links. It is necessary that
extensive studies are conducted in critical HVDC installations and in cases of
overcompensated AC lines to prevent any surprises in real-time operation.
Vide letter dated 09th
March 2018, NLDC with regard to frequent occurrence of
ferroresonant phenomenon involving Gazuwaka HVDC had communicated its concerns
to PGCIL.
b) Frequent tripping of Talcher-Kolar Bipole
S. o. Name of
Element
Tripping Restoration Remarks
Date Time Date Time
1 Pole 1 8-Jan-18 19:06 9-Jan-18 00:54 Series Reactor in R-Phase of Pole-
1 was burnt & faulty at Talcher.
2 Pole 1 9-Jan-18 07:50 9-Jan-18 09:04 Operation of Valve Cooling
Differential Protection at Talcher
end.
3 Pole 1 2-Mar-18 16:15 2-Mar-18 19:19 Clogging of the mechanical filter
of Pole-1 valve cooling system at
Talcher.
4 Pole 1 7-Mar-18 09:38 7-Mar-18 10:25 Tripped due to external protection
tripping command as reported by
Talcher end
5 Pole 1 17-Mar-18 15:12 17-Mar-
N18
21:07 DC line differential
protection operated
6 Pole 2 17-Mar-18 20:29 17-Mar-18 21:07 While deblocking Pole-1, Pole 2
went into ground return mode and
power flow got reduced to 150
MW.
HVDC Talcher-Kolar Related RVO operation_January to March 2018
1 Pole 1 17-Mar-18 14:20 Tripped Several transients were observed in
HVDC Talcher –Kolar
2 Pole 1 20-Mar-18 06:32 20-Mar-18 13:43 Due to heavy fog in
Gazuwaka area. Total 6 nos
Transients were observed in
approx 1 hour
3 Pole 2 20-Mar-18 06:20 20-Mar-18 13:52
NLDC had observed Transmission licensees are required to take adequate steps to prevent
undesired outages of HVDC link. There had been multiple pollution related trippings,
which warrant replacement of porcelain insulators with appropriate polymer or composite
insulators, which have better resistance to flashovers from prevailing higher pollution
levels. NLDC communication dated 21st March 2018 with regard to frequent trippings on
HVDC Talcher – Kolar bipole had been communicated to PGCIL.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 30
c) High flow on 400 kV KKNPP-Tirunelveli D/C line after commissioning of 400 kV
KKNPP-Tuticorin PS D/C line
In 42nd
SCPSPSR it was noted that, POSOCO had informed that POWERGRID had
commissioned above transmission system in 1st week of March 2018. But, with the
commissioning of 400 kV Kudankulam - Tuticorin PS D/c line (144 Km), more than 80 %
of power generated from KKNPP (with both units in service) is flowing on 400 kV
Kudankulam-Tirunelveli D/C section (72.5 km). It was further added that with more
generation at Coastal Energen and NTPL, there would be further uneven distribution of
flow on 400 kV KKNPP Tirunelveli and 400 kV KKNPP- Tuticorin PS sections.
Additionally commissioning of the new 400 kV lines connecting Tirunelveli wind station
to Tuticorin PS will further aggravate the situation. POSOCO had stated that there is a
need to review the evacuation transmission system from KKNPP.
After deliberations, this issue was referred for joint system study by CEA, CTU, POSOCO
and constituents of Southern Region. The proposal along with study results would be
discussed in next Meeting of Standing Committee.
d) Transmission Line constraints:
400 kV Nellore Pooling Station -Nellore D/C line
400 kV Gooty-Nelamangala line & 400 kV Gooty- Somanahalli line.
400 kV Udumalpet- Palakkad D/C line
31st TCC: KSEBL had stated that there was no constraint on this line. SRLDC
stated that they would examine the matter.
400 kV Hiriyur-Nelamangala D/C line
220 kV Bangalore Metro Network
Overloading of 230 kV Shoolagiri-Hosur (TN)-Yerrandahalli-Somanahalli S/C line
Constraints in Nagjheri PH evacuation
Constraints in Chennai 230 kV System
Overloaded 230 kV Lines in Tamil Nadu
220 kV Hyderabad Metro Network
e) ICT Constraints
765/400kV 2x1500 MVA Vemagiri ICTs
400/220 kV 2 x 315 MVA ICTs at Gazuwaka
41st SCPSPSR: After deliberations members agreed for an additional
400/220kV, 1x500 MVA ICT at Gazuwaka substation as ISTS.
400/220 kV 3 x 315 MVA ICTs at Vemagiri
41st SCPSPSR: APTRANSCO has to look into the issue and may plan
additional ICTs/ replacement of ICT by higher capacity.
400/220 kV 3 x 500 MVA ICTs at Nelamangala
400/220 kV 3 x 500 MVA ICTs at Somanahalli
400/220 kV 3 x 500 MVA ICTs at Hoody (In the special meeting held on
09.07.2018 to discuss pending issues in respect of Karnataka, KPTCL had
informed that with the commissioning of Yelahanka SS, the loading was likely to
come down)
400/220 kV 2 x 315 MVA ICTs at Guttur
400/220 kV 2 x 315 MVA ICTs at Hiriyur
400/220 kV 1 x 500 MVA + 1x315 MVA ICTs at Narendra
400/220 kV 2 x 315MVA ICTs at UPCL
400/220 kV 3 x 315MVA ICTs at Shankarapally
41st SCPSPSR: 1x 500MVA 400/220kV transformer (4th one) at Malkaram
S/S & Shankarpalli S/S approved
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 31
f) Other issues:
Vallur TPS (1500 MW) and NCTPS-II (1200 MW) generation is connected at 400 kV
Bus and No 230 kV path is available to give start up supply in case of Blackout. Hence
there is a need to provide 230 kV path.
National HVDC project of Lower Sileru-Barasoor line right of way has to be used for
New inter connection between SR & NEW Grids.
g) Overloading of 400kV Nellore PS- Nellore D/C lines
In the 32nd
TCC the following had been noted:
TCC had recommended for SPS, during tripping of one of the lines of NPS-Nellore.
TCC had recommended that provision of third ICT at NPS could be planned/studied as
a long-term measure. Other options could also be looked into by CTU as discussed in
earlier Meetings / suggested by POSOCO.
Subsequently, the SPS had been implemented by PGCIL.
In 42nd
SCPSPSR after deliberations, it had been agreed to bypass Nellore PS – Nellore
400 kV D/C (Quad) line and Nellore – Thiruvalam 400 kV D/c (Quad) line at Nellore (PG)
for making Nellore PS – Thiruvalam 400 kV D/c (Quad) line to control loading on Nellore
– Nellore PS 400kV lines and control of short circuit levels.
19. SCHEDULING OF MACHKUND AND TB DAM
The issue of non-scheduling of Machkund and TB Dam power by APSLDC to Telangana
from 11.06.2017 had been taken up with APTRANSCO vide letter dated 04.07.2018
(Annexure-XXVIII) by SRPC. In this regard, the letter dated 02.07.2018 received from
TSTRANSCO on the subject was also enclosed.
20. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP
20.1 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC,
NPCIL, and BHAVINI & UMPP is furnished below please:
Station Unit
Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning Remarks
NTPC
Kudgi TPS
Stage-I
III 800 August 2018 Unit-III: Trial operation
successfully completed
between 30.04.2018 to
02.05.2018. Hon’ble CERC
in Petition No.146/MP/2018
had extended the COD upto
31.08.2018.
Telangana STPP
Phase I
2 x 800 32nd
TCC:
U-I CoD May 2020
(Synchronization by
Mar 2020)
U-2 CoD Dec 2020
(Synchronization by
Sep 2020)
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 32
Pudimadaka AP 4 x 1000 52 Months from Zero
Date
85 % share to AP.
Zero date yet to be finalized.
AP had requested NTPC to
firm up the zero date at the
earliest.
31st TCC:
NTPC had informed that the domestic coal was yet to be tied up. Within
two months, the status would be communicated.
CTU informed that there was no connectivity / LTA application pending
with them.
NLC
New Thermal
Power Project
I 500 October 2018
II 500 December 2018
CEA (May 2018): LILO of Neyveli – Puducherry by July 2018, New
Neyveli TPP - Ariyalur (Villupuram) by July 2019.
SRTS-II vide letter dated 26.06.2018 (Annexure-XXIX) had stated that
the LILO of could not be terminated at NNTPS Switchyard due to non-
readiness of associated bays at NNTPS switchyard which are under the
scope of M/s NLC. The said LILO line has been charged by cross
jumpering at dead end tower in NNTPS switchyard.
TPS –II 2nd
Expn 1&
2
2 x 660 42nd
SCPSPSR:
Seeking connectivity for
1320 MW w.e.f. 01.04.2021
NPCIL
KKNPP 3 &
4
2 x 1000 32nd
TCC
U3: 2023
U4: 2024
41st SCPSPSR:
CTU informed that they had
not received any LTA
application from NPCIL for
Kudankulam - 3 & 4 units.
Any system strengthening
would be planned on receipt
of the LTA application based
on proper studies.
BHAVINI
Kalpakkam
(PFBR)
I 500 Synchronization by
2018-19
COD by 2018-19
32nd
TCC:
Kanchipuram SS – TANTRANSCO informed that the S/S would
come up by March 2018
UMPP
Krishnapatnam 3960
(6 x 660)
32nd
SRPC: CMD, APTRANSCO had informed that
several Meetings had been held with beneficiaries
and coastal UMPP. In the present scenario, the
usefulness of this project for beneficiaries was
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 33
limited. In the meeting it had been decided that since
the matter was pending before Delhi High Court, it
was appropriate to file a Petition for Expeditious
Hearing. However after seeking legal opinion, a
SLP before Hon’ble Supreme Court was
contemplated seeking directions to Delhi High Court
to kindly expedite and pass Orders at the earliest.
32nd
TCC: AP informed that after discussing with the beneficiaries, an
Expeditious Petition was contemplated before Hon’ble Delhi High Court
(before approaching Hon’ble Supreme Court). The petition was likely to
be heard in the month of March 2018.
Cheyyur 4000 New bids would be called
21. NEW PROJECTS OF STATE SECTOR & IPP
21.1 Updated status of new projects of State sector is furnished below please:
Sl
No
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Rayalaseema TPS ST-IV AP 1 x 600 2018-19
2 Dr. NTTPS, Vijayawada AP 1 x 800 June 2019
3 Krishnapatnam Stage II
(U3)
AP 1 x 800
4 Polaki AP 4000 (5 x
800 MW)
5 Edlapur KAR 1 x 800
6 North Chennai Stage III TN 1 x 800 2019-20
41st SCPSPSR: 2019
7 North Chennai Stage IV TN 2 x 800 Beyond 2019-20
8 Ennore TPS Exp TN 1 x 660 2018
9 Ennore replacement TN 1 x 660 41st SCPSPSR: 2020
10 Udangudi Stage I TN 2 x 660 2020-21
11 Uppur TPP (TBCB) TN 2 x 800 2019-20
12 Manuguru PPP Telangana 4 x 270 U1: March18
U2: June18
U3: Sep 18
U4: Dec 18
13 Kakatiya TPP Stage III Telangana 1 x 800 Not decided
14 Kothagudem TPS Phase
VII
Telangana 1 x 800 2018-19 (June-18)
15 Damaracherla (Yadadri) Telangana 5x800 U1 & 2 Nov 2020
U3 – 5 2021
21.2 Updated status of new projects of IPPs is furnished below please:
Sl
No.
Name of project Located
in
Capacity
in MW
Commissioning Schedule
/Remarks
1 Meenakshi PH-II AP 2 x 350 2018-19
Untied: 640 MW
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 34
2 East Coast Energy
Thermal
AP 2 x 660
2018-19
AP : 300 MW
3 Thermal Powertech
(TPCIL) Unit-III
AP 1 x 660
2017-18
5 Godhna TPP, Janjir –
Champa Dist,
Chhattisgarh
For
KAR
2 x 800 2017-18
22. REVIEW OF ULDC / SCADA/COMMUNICATION
22.1 Status of pending items is as follows:
Update as per Meeting on 13.03.2018 Status update
ICCP link failure/not stable
It was noted that respective Control Center would ensure that M/s GE take pro-active action to renew the licenses before the expiry
Updated communication network diagram to be submitted
by SR-I 03and SR-II to all SLDCs & SRLDC. Further any
changes done in the communication network needed to be
informed to all.
SR II had informed that
Necessary standby channels
are made available and
updated communication
network is ready.
Data outage after commissioning
Cross checking to be done with site daily values for newly
commissioned elements for a period of two week duration
from commissioning.
SR II : Complied and
SRLDC may check and
intimate any failures
RTU/SAS Maintenance/Upgradation
AMC need to be provided for all RTU/SAS gateways by
CTU/STU.
A life/functional assessment report and action plan by
PGCIL/ISGS on old RTUs would be prepared and
submitted to SRLDC/SRPC.
SR-II does not feel to have
AMC for SAS stations.
However, the conventional
RTUs, commissioned during
2001-02 are proposed to be
upgraded / replaced. The
offer obtained from GE for
upgradation and process to
be initiated
Backup Control Centre
Backup SCADA functionality testing frequency needs to
be done once in 6 months to ensure high availability of
data/preparedness to operate from Back up CC in event of
any contingency. Compliance report may be furnished to
SRLDC.
TN stated that communication network is being
strengthened to Backup CC. Once same is completed, TN
will do the testing.
PGCIL would be floating new combined Open Tender for
Backup SLDCs for AP (Tirupati), TS (Warangal) along-
with few other states.
Periodical testing was being
carried out by SRLDC and
KSEBL.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 35
ICCP with NTAMC
PGCIL had confirmed that due to cyber security concerns
data would not be extended to SRLDC from NTAMC
ICCP.
Functional requirement of the requisite data by SRLDC
would remain, which needed to be ensured by PGCIL.
SRLDC would furnish the list of telemetry points that have
to be extended to PGCIL within 10 days, and within 1
month PGCIL would come out with a detailed plan to be
completed within 6 months (October 2018)
SR II : Additional data
points have been received
from SRLDC and action is
being taken to extend the
inputs by Oct 2018
Modification of EMS package
TSTRANSCO had received estimate of Rs 47 lakhs and
the contract was being firmed up.
Sparing of Fibre in Central Sector Project
TANTRANSCO had again requested for sparing of fibre
in Central Sector Project.
SR-II stated that request for
sparing of fibre in new FO
links could be communicated
for consideration.
VC issues
TSTRANSCO Video Conference issue at TSSLDC. There
was disturbance in Video Conference at TS end when
connected to SRLDC.
TSSLDC and SRLDC were
requested to coordinate and
sort out the issue.
Puducherry would take up VC requirement in the financial
year 2017-18.
22.2 ICCP links had failed on 07.02.2018, 08.02.2018 and 23.02.2018. To address these
issues, an urgent Meeting was called on 13.03.2018 (MOM available at SRPC website).
Actionable points need to be complied by all the concerned entities. Further, a Special
Meeting with participation from M/s GE was also conducted on 23rd
May 2018 (MOM
available at SRPC website). The following was agreed in that Meeting:
Formal procedure to be followed during ICCP failure would be developed. Timely
renewal of the certificates would also be included in the procedure.
Procedure for database mismatch correction, duration of making changes and
validation of the same to be formulated and made part of procedure such that the
database between control centers are in sync and error logs are cleared in timely
manner.
SR-I & SR-II were requested to check all ICCP links for healthiness through ping
check and testers in consultation with SRLDC and constituents on a periodic basis.
It was pointed out that all states need to compute a parallel ISTS drawal on
different philosophy independent of points being used by SRLDC. This would
ensure consistent verification of the ISTS drawal and will be helpful during
contingencies. AP & TS informed that they were following such procedure and
independent ISTS drawal was being computed. Discrepancy needed to be informed
to SRLDC for early rectification.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 36
M/s GE had offered to conduct quarterly Meetings on AMC and other SCADA
related issues which could be conducted through VC or at a common site.
22.3 Signing of Agreement / MOU between Powergrid and Constituents for
replacement/upgradation of RTUs
With regard to replacement of S-900 RTUs in Northern Region, SRPC vide letter
dated 24.05.2018 (Annexure-XXX) had communicated its concerns to ED (LD &
C), PGCIL and requested that a review exercise on this matter may kindly be taken
up for Southern Region also.
SR-I & SR-II had clarified that CPU card was to be replaced to handle the present
communication requirements for various applications. Requirement of replacing
the CPU card for ISG stations could be covered in the scope of PGCIL works on
payment basis. ISG stations were requested to revert back on the issue.
Letter dated 15.06.2018 from PGCIL (LD&C) in this regard is given at Annexure-
XXXI, SR-II vide letter dated 27.06.2018 (Annexure-XXXII) had informed that it
was proposed to replace CPU card in all RTUs of POWERGRID stations (SR-II-13
no, SR-I-09 no) .The estimated cost per station is approximately Rs.6,51,000/-
(Supply: Rs.4,66,000/- & Services: Rs.1,85,000/-) excluding GST @18 %.
However, final price can be arrived only after due negotiations with M/s GE as per
standard procurement policy of POWERGRID.
23. URTDSM (PMU) PROJECT IN SOUTHERN REGION
23.1 URTDSM Phase-I project is nearing completion. The progress is being reviewed in the
Special Meeting/OCCM. A Special Meeting was conducted on 13.03.2018 to review the
progress. The updated status in this regard is furnished at Annexure-XXXIII.
23.2 Feedback on currently installed analytical applications (LSE, VADR, Supervised Zone-3
Distance protection) had been requested from the control centres. PGCIL had agreed to
form a web group of control centres, LD & C, IIT Mumbai etc to exchange information
and for better rectification.
23.3 PGCIL had requested all constituents to submit revised PMU requirement, if any, for
Phase-II considering availability of Wide Band nodes. APTRANSCO, TSTRANSCO &
KSEBL vide had submitted PMU requirement for Phase-II.
24. EMERGENCY RESTORATION SYSTEM (ERS)
24.1 Requirement of ERS had been outlined in MoP letter dated 05.12.2014. The status was
being monitored by Secretary (Security). Status update is given below please:
Transmission
Utility
Requirement as
per MoP
Existing Status/Remarks
APTRANSCO 3 2 ERS III would be taken up
through own funding
TSTRANSCO 1 Tender floated; would be
taken up for PSDF funding.
KPTCL 2 2
KSEBL 1 Tenders to be floated. Would
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 37
be taken up for PSDF
funding.
TANTRANSCO 2 As per Minutes of BLTC
held on 03.01.2017,
procurement is put on hold.
Would require PSDF
funding.
PED Nil Nil
PGCIL 4 (2 Nos.
Additional)
4 (SR I &
SR II is
having 2
no. Each)
765 kV ERS (one each for
SR-I and SR-II) Order
placed. Expected by January,
2019.
25. ADOPTION OF UNIFORM PROCEDURE TO PREPARE MERIT ORDER
DESPATCH LIST
In the Sub-committee Meetings it was noted that different methods are being followed by
states to prepare Merit Order Despatch List. It was therefore suggested that common
guidelines for preparation of Merit Order Dispatch List may be formulated for the benefit
of all.
This issue was discussed in 38th
Meeting of Commercial Sub Committee, wherein certain
issues such as ISTS loss, incentive, compensation, URS, billed MOD, ERC approved
MOD, EC computation for state vs central generators, flexibility in LTA/MTOA, MOD on
D-3 (non-availing of STOA) etc were discussed. It was agreed to discuss the nitty gritty of
the issue by a Sub Group. Subsequently, the matter could be taken up with CEA/NLDC,
being a policy issue involving all generators in the country.
26. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
26.1 Status of implementation of Bus / Line Reactors / Dynamic Compensation approved in the
Standing Committee / SRPC pending for commissioning by the SR constituents is
furnished below please:
Entity Bus Name Status REMARKS
KPTCL
Hoody Reactor erected on
platform.
2018-19
Nelamangala Reactor erected on
platform
2018-19
Entity Bus Name
Capacit
y in
MVAR
Approved
in Type Remarks
PGCIL Yelahanka 2x63 40
th SC Bus
Deferred as per 40th
SCPSPSR. When
Madhugiri line will come
it will be expedited.
Cuddapah 50 to 125 39th
SC Yet to be awarded
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 38
Kurnool 765
kV 2 x 240 42
nd SCPSPSR
Raichur 765
kV 2 x 240 42
nd SCPSPSR
Thiruvalam
765 kV 2 x 240 42
nd SCPSPSR
Pavagada 2 x 125 42nd
SCPSPSR
Nellore (PG) 2 x 50
42
nd SC
Line
to
Bus
Hosur 63 to 125 42nd
SC Bus
Madhugiri 63 to 125 42nd
SC Bus
Dharmapuri 125 42nd
SC Bus
Hiriyur 125 42nd
SC Bus
Pugalur 125 42nd
SC Bus
Pugalur
HVDC 2 x 125 42
nd SC Bus
APTRANSCO
Vemagiri 125
36th
SC
Bus December 2017 – LOA
issued on 18.06.2017
Kurnool 125 Bus December 2017 – LOA
issued on 18.06.2017
Kalpaka 125 Bus March 2018
Chittoor 125 39th
SC APERC approval awaited
Vijayawada 125 39th
SC
It was noted that a
separate reactor at
Vijayawada in scope of
AP had been identified.
The exact location could
be firmed up by
APTRANSCO.
Uravakonda 125 42nd
SC Bus
Uravakonda 80 42nd
SCPSPSR
Jammalmadu
gu 80 42
nd SCPSPSR
Sattenapalli 125 42nd
SCPSPSR
Rachagunneri 125 42nd
SC Bus
Hindupur 80 to 125 42nd
SC Bus
APGENCO
VTPS Stage
IV 125 39
th SC
APGENCO informed that
reactor enquiry was being
taken up.
It was noted that this
reactor was different from
the APTRANSCO reactor.
Polavram
HEP 2 x 125 42
nd SC Bus
KPTCL
Davanagere 125 39th
SC 41st SCPSPSR:
Requirement reaffirmed.
Special meeting
09.07.2018: Approved in
TCCM, estimate under
preparation.
Talaguppa 125 39th
SC
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 39
C N Halli 2 x 125 42nd
SC Bus
42nd
SCPSPSR: KPTCL
stated that they will send
their consent within 15
days of the meeting.
Jagalur 2 x 125 42nd
SC Bus
KPCL
Yeramarus 125 42nd
SC Bus
Bellary 2 x 125 42nd
SC Bus
KSEBL Wayanad 125 42nd
SC Bus
TANTRANSC
O
Almathy 125 39th
SC Specification under
process Manali 125 39
th SC
Kayathar 125 39th
SC
Kamuthi 2 x 80 42nd
SCPSPSR
Virudhnagar
(765 kV)
2 x 330 42nd
SC Bus
2 x 330 42nd
SC Line
Coimbatore
(765 kV) 2 x 240 42
nd SC Line
Kayathar 125 42nd
SC Bus
Kamuthi 125 42nd
SC Bus
Thappagundu 125 42nd
SC Bus
Kadaladi 125 42nd
SC Bus
Parali 125 42nd
SC Bus
Arni 2 x 125 42nd
SC Bus
Velalividu 125 42nd
SC Bus
TANTRANSC
O/
TANGEDCO
Mettur 125 39th
SC
To be diverted from
Palavadi and works to be
taken up.
TSTRANSCO
Mamidipally 125 36
th SC
Bus
Commissioned on
23.02.2018
Asupaka 80 42nd
SCPSPSR
Suryapet 125 42nd
SC Bus
42nd
SCPSPSR:
TSTRANSCO stated that
they will send their
consent within 15 days of
the meeting.
Raidurg 2 x 125 42nd
SC Bus
Kamalapuram 125 42nd
SC Bus
Narsapur 125 42nd
SC Bus
Maheshwara
m 125 42
nd SC Bus
Tippapur 125 42nd
SC Bus
Manikonda 125 42nd
SC Bus
Jangaon 125 42nd
SC Bus
Choutuppal 125 42nd
SC Bus
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 40
Yellampalli 125 42nd
SC Bus
TSTRANSCO/
TSGENCO Srisailam LB 125
39th
SC
42nd
SCPSPSR: CEA
Meeting (06.02.2018)- It
was decided that a team
comprising officers from
CEA, CTU and
TSTRANSCO would visit
SLBHES switchyard to
explore the feasibility to
accommodate the reactor
(125 MVAR).
NPCIL Kaiga 2 x 125
Bus
One reactor by December
2019.
For 2nd
reactor, NPCIL
will get in touch with
PGCIL.
UPCL
Udupi 2 x 125
39th
SC
41st SCPSPSR: It was
informed that the
requirement was assessed
based on system studies,
therefore, it was decided
that the decision taken in
39th
SC Meeting may be
implemented.
SRPC vide letter dated 09.07.2018 (Annexure-XXXIV) had taken up with
PCKL the issue of according approval since these reactors had been
approved by the Standing Committee and Karnataka SLDC had also
endorsed the urgent requirement.
NLC NLC TPS-II
2nd
Expansion 125
42nd
SC Bus
All entities are requested to kindly expedite reactor commissioning, especially since high
voltages are being observed on a sustained basis.
26.2 Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR) Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125 June 2019
Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125 32nd
TCC:
March
2019
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 41
26.3 Reactive Power Planning
26.3.1 Status of Capacitor installation in Transco/Discoms is given below please:
Utility Reactive Power Planning Voltage
level
Remarks
APTRANS
CO
Kadapa: 244.8 MVAR
Vijayawada: 122.4 MVAR
Visakhapatanam:158 MVAR
On 33
kV side
0 MVAR commissioned
0 MVAR commissioned
0 MVAR commissioned
APSPDCL 640 MVAR 2 MVAR commissioned
APEPDCL 276 MVAR 54 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:784
MVAR
12.1 kV 30 MVAR commissioned
Bagalkot Tr. Zone: 258.1
MVAR
12.1 kV 78.3 MVAR commissioned
Hassan Tr. Zone: 150.8
MVAR
43.5 MVAR commissioned
Mysore Tr. Zone: 60.9
MVAR
60.9 MVAR commissioned
Gulbarga Tr. Zone: 98.60
MVAR
Nil
Tumkur Tr. Zone: 281.3
MVAR
12.1 kV 46.4 MVAR commissioned.
34.8 MVAR EI approval
awaited.
TSNPDCL 288 x 2 MVAR
110 x 1 MVAR
259 x 2 MVAR
105 x 1 MVAR commissioned
TSSPDCL 204 x 2 MVAR
58 x 1 MVAR
Nil
KSEBL 360 MVAR 66 kV Works will be taken up after
approval. 11kV
TANGEDC
O
34 x 2.4 MVAR 11 kV
16 x 2.4 MVAR 22 kV 16 x 2.4 commissioned
59 x 2.4 MVAR 11 kV IPDS tender to be opened on
30.11.2017
19 x 2.4 MVAR 22 kV IPDS tender to be opened on
30.11.2017
13 x 2.4 MAVR 110 kV PO placed on M/s Shreem
Electric Limited.
53 x 2.4 MAVR 11/22
kV
RAPDRP tender to be floated
101 x 2.4 MAVR – Erode
Region
11/22
kV
Tender to be floated.
32 x 2.4 MAVR – Vellore
Region
11/22
kV
Tender to be floated.
82 x 2.4 MVAR -
Coimbatore Region
11 kV BLTC note for price bid opening
to be submitted
822 MVAR capacitors at
Distribution level had been
commissioned out of 931
MVAR capacitors planned.
Balance 109 MVAR to be
commissioned. However, for
further enhancement of Reactive
Power, Capacitor bank
provisions have to be arranged
by Planning / Transmission
wings.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 42
26.4 PSDF – Funding of the schemes of the state utilities for installation of capacitors
in the state network at transmission / distribution network
26.4.1 MS, Appraisal Committee & ED, NLDC vide letter dated 22.06.2016 had earlier
stated that the matter had been deliberated by the Appraisal Committee during the
Meeting held on 31.05.2016 wherein, it was decided that assessment of capacitor
requirement be carried out at regional level by engaging expert agency like CPRI.
After approval, SRPC vide letter dated 03.05.2017 had placed work order on CPRI for
carrying out the assessment studies for Southern region (except Karnataka).
26.4.2 Base case was modeled by SRLDC & SRPC and submitted to CPRI on 23rd
March
2017. CPRI study report was received on 20.12.2017. SRPC vide letter dated
28.12.2017 had submitted the same to NLDC for further needful action. SRPC vide
letter dated 16.01.2018 had also informed states that the CPRI Report has been
submitted to NLDC and requested them for further necessary action at their end.
26.4.3 Convener, TESG & Consultant, NLDC vide letter dated 21.05.2018 (Annexure-
XXXV) had furnished the extracts of the 38th
Meeting of TESG held on 26.02.2018
and requested for needful with regard to the observations. With respect to SR it had
been mentioned that the Capacitor Study Report submitted by SRPC prepared by
CPRI dealt only with transmission level (132 kV and 220 kV voltage level) whereas
requirement was also for distribution level (33 kV and 11 kV).
SRPC vide letter dated 29.05.2018 (Annexure-XXXVI) had submitted its reply in this
regard to Member Secretary, Appraisal Committee.
26.5 Low voltages observed in Bengaluru Area and Central/ North Kerala with
Udumalpet and Arasur areas
A study was undertaken and the following are the recommendations in this regard:
Low Voltage in Bangalore Area was due to heavy drawl of MVAR to the order of
about 1,000 MVAR. In the Special Meeting held on 09.07.2018, KPTCL had
informed that 784 MVAR capacitors were expected to be commissioned by
December 2018 (153 breakers were expected by Aug 2018). Further KPTCL
confirmed that they would discuss the issue with BESCOM and identify measures
to minimize the impact of MVAR drawal from ISTS grid. Low Voltage in Kozhikode was due to operational error in switching Capacitor.
KSEBL had assured that in future, while drawing through Kozhikode ICTs, they
would also factor the current voltage situation at Kozhikode Bus.
Low Voltage in other parts of Kerala was due to low short circuit levels.
Improvement in voltage would be possible with commissioning of 400 kV D/C from
Tirunelveli to Cochin. This issue was under deliberation with KSEBL.
Low voltage in Udumalpet and Arasur areas.
27. NON-AVAILING OF OCC APPROVED SHUTDOWN
27.1 In OCC Meetings, it had been noted with concern that at times, entities were not availing
OCC approved shut downs as per schedule. Details of availed outages against OCC
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 43
approved shut downs (furnished by SRLDC) are given below please:
27.2 It was noted that certain shutdown proposals were being made even on the day of the OCC
Meeting. Constituents were kindly requested to plan outages more diligently and increase
coordination with the field and project officials.
27.3 In the 141st Meeting of OCC, it had been agreed that mid review outages would be
approved only after confirmation from SLDCs of AP, KAR, KER, TN & TS. Proposals
would be posted on outage group and after confirmation of states; the approved shutdowns
would be uploaded on SRPC website.
27.4 Delay in restoration of transmission elements
Narendra ICT-II was taken out by SR-II, PGCIL on 05th
March 2018 during the peak
months. Approval of the Senior Management of Karnataka had not been taken for availing
this shutdown. KPTCL had expressed serious concern since a couple of disturbances
involving load loss of about 1,000-1,500 MW had occurred in that area and there was high
loading on the only available Narendra ICT. SR-II had restored the ICT on 14.04.2018,
though the approved date for revival was 31.03.2018.
Shutdown of 400 kV Neyveli-Puducherry line was also extended beyond the approved
dates (12.04.2018-22.04.2018) by PGCIL (revived on 29.04.2018). During such time,
Entity
Feb-18 Mar-18 Apr-18 May-18
Availed % with respect to the OCC
approved outages
AP TRANSCO 35 40 72 75
KPTCL 83 75 57 60
KPCL 100 - - -
KSEBL 100 100 100 100
TANTRANSCO 49 - 35 40
TSTRANSCO 56 100 64 70
PGCIL, SR1 96 100 64 68
PGCIL, SR2 45 75 33 80
NTPC 100 100 100 100
NLC 100 100 100 50
NTPL - - - -
NPCIL 33 0 - 100
PNMTL 0 - - -
CEPL 100 - - -
MTL 0 - - -
RSTCL 0 - - -
UPCL 0 - - -
MEPL - 0 - -
Total 53 66 54 64
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 44
Puducherry region as well as Cuddalore area in Tamil Nadu were operating under reduced
grid reliability.
It was noted in the OCC Meeting that for any reconfiguration etc, similar procedure as
adopted for new elements needs to be followed by all concerned entities.
A Meeting in this regard was also conducted with SR-II, PGCIL on 17th
April 2018. The
actionable points (applicable to all the concerned entities) had been communicated vide
letter dated 18.04.2018 (Annexure-XXXVII).
As noted in the earlier SRPC Meeting, PGCIL / Transmission licensee would endeavour to
deploy ERS for critical outages. Further, PGCIL was to furnish revival status 2-3 hours
prior to the scheduled time of revival.
28. STATUS OF PHASE-I AND PHASE-II OF PROTECTION AUDIT
RECOMMENDATIONS
28.1 With reference to the Petitions filed by KSEBL (88/MP/2016) and KPTCL (135/MP/2016)
seeking further time-extension for completing their respective Protection Audit
Recommendations (PAR), final Order of Hon’ble CERC disposing of the Petitions was issued
on 15.12.2016. In this Order, Hon’ble Commission, apart from granting last-chance time-
extensions to various SR-Constituents, had also directed SRPC to monitor the status of
completion of PAR regularly in PCSC Meetings and submit bi-monthly Report to the
Commission confirming completion of Phase-I and Phase-II of PAR of the Constituents of
Southern Region.
In this regard, based on the information furnished various Constituents, a summary table
showing compliance status of various SR-Constituents as on 14.06.2018 is given below
please:
Sl.
No.
Constituent
PAR (Phase-
I) Activities
PAR (Phase-
II) Activities
PAR (Ph-I &
Ph-II)
Compliance
(%)
Remarks
Stipulated
Completion
Date
Stipulated
Completion
Date
1 APGENCO
(Hydel) 31.12.2017 31.12.2017 66.66 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (5 in
no.) is 30.06.2018
2 APGENCO
(Thermal) 30.07.2017 --- 83.33 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (2 in
no.) is 31.08.2018.
3 APTRANS
CO 31.03.2017 --- 98.57 Based on the status
furnished, the lone
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 45
pending recomm-
endation is expected to
be completed by April
2018.
4 TSGENCO
(Hydel) 31.03.2017 31.03.2017 91.18 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (3 in
no.) is 30.09.2018.
5 TSTRANS
CO 31.03.2017 31.03.2017 89.77 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (9 in
no.) is 30.06.2018.
6 KPTCL 31.05.2017 31.05.2017 76.05 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (17 in
no.) is 31.07.2018.
7 TANGEDC
O 31.12.2017 31.12.2017 77.77 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (8 in
no.) is 30.09.2018.
8 TANTRANS
CO 31.12.2017 31.12.2017 58.33 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (55 in
no.) is 31.12.2018*.
9 KSEBL 30.11.2016 31.12.2017 97.40 Based on the status
furnished, timeline for
complying with the
remaining pending
recommendations (2 in
no.) is 31.08.2018.
10 NPCIL
(MAPS) 31.01.2017 --- 88.89 Based on the status
furnished, timeline for
complying with the
lone pending
recommendation is
September 2018. *TANTRANSCO has been asked to approach Hon’ble CERC to seek required time-extension.
28.2 It may kindly be noted that total compliance percentage of SR-Constituents in
completing Protection Audit Works as on 14.06.2018 stands at 84.65 %.
28.3 All above SR-Constituents are requested to kindly complete their respective pending
PAR at the earliest. IPP’s for whom there are pending PAR [viz., Spectrum PGL,
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 46
Konaseema GPL, APGPCL Vijjeswaram (Stage-I & Stage-II), & LANCO-Kondapalli
PL] are also requested to complete them at the earliest.
29. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT
SYSTEM (PMS) FOR SOUTHERN REGION
29.1 Based on the approval of SRPC in the 26th
Meeting held on 20th
December, 2014 at
Visakhapatnam, implementation of Protection Management System in Southern Region
[Web-based Management Software and Protection Setting Calculation Tool for Southern
Region] had been undertaken through PSDF funding. This project was awarded through open
bidding process to M/s PRDC Pvt. Ltd. (PRDC) on 09.08.2017. The execution period for the
Project is about 18 months from the date of placement of LoA (also called “Effective Date”),
and is followed by an Extended Technical Services period of 5 years.
29.2 Details of the project implementation including Milestone-wise status is given at
Annexure–XXXVIII for kind reference.
29.3 In this regard, a Protocol on implementing & using Protection Management System and
giving an integrated view of the project had also been circulated to all SR-Constituents vide
SRPC dated 20.04.2018. Data collection by physical field visits of the stations in Tamil
Nadu, Puducherry, Kerala and Telangana has been undertaken by PRDC. Even though this
process had been completed, all the data sought as per stipulated formats for modeling in
PMS has been pending from certain stations. In view of the time bound nature of the PMS
project, monthly review Meetings are being planned regarding submission of pending PMS
data to PRDC.
29.4 Automated Fault Analysis System (AFAS) envisaged under PMS project was successfully
implemented for the 400/230-110 KV Palavadi SS (Pilot station) and was put under service
with effect from 18th
April 2018.
29.5 All SR-Constituents (Genco’s/ Transco’s/ LDC’s/ ISGS Utilities/ ISTS Utilities/ IPP’s/
other Generators/ etc.) are requested to kindly extend full-fledged cooperation in terms of
furnishing required information/ data for setting up & maintaining protection database,
and ensure that PMS project is made operational by the targeted time-line of 9th
Feb 2019.
30. COMPLIANCE STATUS OF NEW PROTECTION AUDIT RECOMMENDATIONS
30.1 As part of GSC (Task-II) under Package-A, protection audit check of 15 stations was
carried out by M/s Tractebel Engineering (TE) in Southern Region during the period,
December, 2015– July, 2016, wherein certain recommendations were also given for each
of these stations for compliance.
30.2 Subsequently, protection audit of various stations in SR has also been regularly conducted
by SRPC teams in line with Order dated 27.04.2015 of Hon’ble CERC in respect of
APTRANSCO Petition No.95/MP/2015 dated 09.04.2015. Protection audit of 11 stations
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 47
was carried out during the period December, 2016 – July, 2018, wherein certain
recommendations were also given for each of these stations for compliance. Details of
stations audited during the period March, 2018 - June, 2018 are given below for kind
reference please:
30.3 Remarks given by the audit teams for the above stations are enclosed at Annexure – XXXIX
for perusal.
30.4 APTRANSCO, TSGENCO, TSTRANSCO, KPCL, KPTCL, KSEBL, TANTRANSCO,
Puducherry ED, NTPC (RSTPS), NPCIL (KGS), NLCIL, PGCIL (SR-I) & PGCIL (SR-II)
are requested to kindly take suitable action to comply with their respective pending
remarks.
31. AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE
TRANSMISSION LINES OF SOUTHERN REGION
31.1 It is common knowledge that majority of the faults that occur on transmission lines are of
transient nature. Hence, provision of Auto-Reclosure certainly helps not only in preventing
forced outage of the subject transmission line, but also in averting cascade trippings, in some
cases, of adjacent transmission lines due to consequent over-loading.
31.2 Further, the provision for Auto-Reclosure is also mandated by Regulation 43 (4) (c) of CEA
Technical Standards for Construction of Electrical Plants and Electric Lines, 2010, which has
force of law. Therefore, it is in the interest of grid security that all Constituents implement
auto-reclosure feature on all 220 kV & above transmission lines in their respective control
areas. Any exceptions in this regard need to be properly justified.
31.3 In this connection, the logics for implementing A/R have been clarified in various PCSC
Meetings. Implementation status is being monitored periodically in the Meetings of PCSC.
From the details furnished by various Constituents, it is noted that the main issues in
implementing A/R are the adopted conservative protection philosophies, lack of proper PLCC
communication, and breakers’ suitability/ supportability. It is brought to kind attention that if
there are no issues w.r.t. carrier communication and breakers’ supportability, concerned
Constituents shall make efforts to implement A/R immediately in their respective networks.
Where communication & breaker related issues stand in the way of implementing A/R,
concerned Constituents shall take steps to address them appropriately on priority basis, and
implement A/R in their respective networks in a phased manner at the earliest.
Sl. No. Name of the Station Audited Period of Protection
Audit
Composition of Audit
Team
1 400/ 220 kV Uravakonda SS
of APTRANSCO
5-6 April, 2018 SRPC, SRLDC &
PGCIL (SRTS-I)
2 400/ 230 – 110 kV Palavadi
SS of TANTRANSCO
14-15 May, 2018 SRPC, SRLDC &
PGCIL (SRTS-II)
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 48
31.4 All concerned Constituents [APGENCO (Hydro), APGENCO (Thermal), APTRANSCO,
TSGENCO (Thermal), TSGENCO (Hydro), TSTRANSCO, KPCL, KPTCL, KSEBL,
TANGEDCO, TANTRANSCO, NPCIL (KKNPP), NPCIL (MAPS), NLCIL, UPCL &
JSWEL] are therefore requested to kindly take action accordingly to implement A/R on their
lines.
31.5 Latest status of A/R implementation by SR-Constituents on their 220 kV & above
transmission lines in SR-grid and the action plan proposed for implementing A/R where it is
presently not in service is proposed to be reviewed in the 76th
Meeting of PCSC scheduled to
be conducted on 26th
July 2018. The details are enclosed at Annexure – XL for kind
reference.
32. REVIEW MEETING ON COMPLIANCE OF PCSC RECOMMENDATIONS
32.1 All trippings involving 220 kV & above system on account of mal-operation/ non-
operation of protection systems in place are regularly discussed in the monthly Meetings of
Protection Coordination Sub-Committee (PCSC) of SRPC with a view to identify the root
cause and scrutinize correctness of operation of protection systems put in place by the
concerned Constituents. In the process, appropriate measures required to be taken for
system improvement are also being suggested/ recommended for compliance by concerned
Constituents. These recommendations, communicated vide Minutes of the Meetings, are
also being monitored for compliance by the concerned Constituents.
32.2 In this regard, latest status of implementation of PCSC recommendations pertaining to
various SR-Constituents for necessary compliance is enclosed at Annexure – XLI.
33. COMMERCIAL COMMITTEE ISSUES
33.1 Following issues are brought to the kind attention of TCC/ SRPC:
Transmission Charges pertaining to Kudgi STPS
Chairperson, SRPC vide letter dated 22.03.2018 (Annexure-XLII) had taken up the
issue regarding changing of the LTA quantum from 2392.49 MW to 2262 MW with
CMD, PGCIL.
Vide letter dated 28.06.2018 (Annexure-XLIII) COO, (CTU-Plg), had requested
NTPC to furnish the following details;
a) How the LTA quantum of 2392.49 MW has been arrived at when LTA was
sought against the installed capacity of 2400 MW and
b) Computation of revised LTA
NTPC vide mail dated 03.07.2018 had informed that the information sought had
already been communicated vide mail dated 24.04.2018 and the same was again
forwarded.
URS Accounting
It was noted that the 5th
Amendment had been notified on 12th
April 2017 (wef
01.05.2017) which had clear provisions on power sold beneficiary-wise to market.
This information was not being communicated to SRPC which was leading to
erroneous URS computations. This had commercial implication on fixed charge
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 49
reapportionment, approved injection in RTA, fixed charge apportionment in
RRAS, computation of incentive charges, compensation calculation etc. This issue
had been discussed in the Special Meeting held on 29.01.2018.
NTPC/NLC were to furnish consent quantum details beneficiary wise, cleared
quantum details beneficiary wise in PX for the period from 01.05.2017 to
10.12.2017.
Change in URS allocation procedure during ramp violation
Whenever a state has surrendered power (URS) and the same is taken by some
other state, and when that power is returned and in cases of the ramp violations,
the violation quantum was being booked to the URS surrendering beneficiary. It
has been noted that the ramp violation needs to be booked to the causer. (whichever
beneficiary avails URS) Therefore the ramp violation quantum will be booked to
the causer.
It was agreed to implement the same in SR.
PPA wise DC to be furnished by the IPPs
SRPC had observed that in line with CERC Order dated 31.08.2017 in respect of
Petition No 28/MP/2016, PPA wise DC has to be furnished by all ISGS. SRLDC
vide letter dated 28.05.2018 (Annexure-XLIV) had requested all IPPs in SR to
furnish the PPA wise DC (as per the format attached with the letter).
Pending payments between WR& SR Constituents as on 16.03.2018 are as
follows:
State Receivable from Payable to
Entity Rs Entity Rs
Andhra Pradesh
/ Telangana
MPPMCL 1,21,76,270 MPPMCL Nil
Karnataka MPPMCL 13,27,208 GUVNL Nil
Kerala MPPMCL 1,21,47,260
CSPDCL 7,05,279
Tamil Nadu MPPMCL 1,17,17,268 CSPDCL 92,77,878
This matter was further discussed in the CCM (77th
) of WRPC held on 20.4.2018. As
decided in the CCM, one to one Meeting with MPPMCL and SR constituents (Andhra
Pradesh, Karnataka and Tamil Nadu) was held on 9.5.2018 at Jabalpur, to reconcile the
figures.
The status update after 38 CCM is as under:
Karnataka: Karnataka claimed an amount of Rs. 13,27,208/- towards power purchase.
MPPMCL had claimed Rs.26,38,440/- which was said to be paid by Karnataka to
PTC.
PCKL had informed that the matter was again taken up with MPPMCL on 27.6.2018
and the reply was awaited
Tamil Nadu: Tamil Nadu claimed an amount of Rs. 1,17,17,268/- towards power
purchase. MPPMCL had claimed Rs.32,93,935/- which was said to be paid by Tamil
Nadu to PTC. MP had agreed to verify the same within 15 days.
Andhra Pradesh: AP has claimed an amount of Rs. 1,21,76,270/- towards power
purchase for the period 03/97 to 12/2002, out of which, figures related to 2002 &
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 50
wheeling charges are reconciled. It was informed by MPPMCL that Andhra Pradesh
Power Co., vide letter no.387 dated 20.08.2010,had claimed net amount payable by
MP after adjustment of wheeling charges is Rs.66.32 Lakhs. MPPMCL had requested
APPCC to verify their claim.
MPPMCL has also submitted details of claimed of Rs.5.62 crores as receivable from
Andhra Pradesh for verification of its payments to Chhattisgarh. AP has agreed to provide
the same within 15 days.
Kerala: KSEBL had informed that they would take up the matter for an early Meeting
with GRIDCO
Payable amount to PGCIL (WRTS) by SR Constituents (as discussed in 38th
CCM)
Pending payments of NTECL
In the 38th
CCM (29.06.2018), NTECL had expressed grave concern on
pending payments by beneficiaries and dues were as follows:
Sl. No. Beneficiary
Outstanding dues for
more than 60 days as
on 25.06.2018
1 APPCC Rs. 73.01 Cr.
2 TSPCC Rs.93.43 Cr.
3 GESCOM Rs. 17.60 Cr.
4 HESCOM Rs. 69.71Cr.
5 CESCORP Rs. 7.38 Cr.
TANTRANCO vide letter dated 28.12.2017 had requested PCKL to clear the dues of
Rs. 26,49,88,513/- as per the decision taken in 123rd
SREB Meeting. In the 36th
CCM
held on 24.11.2017, KPTCL/PCKL had informed that needful would be done at the
earliest.
In the 33rd
SRPC meeting, MD, PCKL had kindly assured that the payment issues
with TANTRANSCO would be resolved before the next SRPC Meeting.
In the 38th
CCM ( 29.06.2018), PCKL informed that the payment was likely to be
processed in first week of July 2018
Constituent Amount to be
refunded (Rs.)
Status
AP & TSTRANSCO 17,34,898
Karnataka DISCOM's 18,36,027 Paid
KSEB l0, 17,023 Paid
TNEB 17,40,999
PED 3, 40,692 Paid
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 51
34. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
34.1 Automatic Demand Management Schemes
34.1.1 In line with clause 5.4.2 (d) of IEGC, Automatic Demand Management Scheme was
to have been provided by all constituents. Revised logic at 49.85 Hz, Min DSM
violation for 15 minutes had been implemented by all the States/UT.
34.1.2 Number of incidents satisfying the existing logic is given below please:
Month
Present settings as per IEGC
Frequency < 49.85 Hz for 15 Min. and OD = Min DSM limit
No of
instances
Meeting the
freq. limit
No of
instances
applicable to
states
No of instances applicable to states
AP Kar Ker TN TS
Feb-18 1 0 0 0 0 0 0
Mar-18 19 3 1 0 0 1 0
Apr-18 22 2 2 0 0 0 0
May-8 107 23 13 0 0 9 1
34.2 UFR and df/dt reliefs
34.2.1. Details of recommended, implemented, SCADA monitorable and actual relief being
realized are shown in the Table below:
State AP TS KAR KER TN PUD SR
Recommended MW A 2782 2965 3539 1173 4176 103 14738
Implemented MW B 2782 2978 3575 1427 4399 109 15270
% B/A 100 100 101 122 105 106 104
SCADA monitorable MW C 1650 2318 3575 1399 3790 100 12832
% C/B 59 78 100 98 86 92 84
Average Visible
Relief in Feb 2018 MW D 1592 1750 3232 1255 2779 77 10685
Wrt monitorable % D/C 96 75 90 90 73 77 83
Average Visible
Relief in Mar 2018 MW E 1633 2238 3205 1350 3416 79 11921
Wrt monitorable % E/C 99 97 90 96 90 79 93
Average Visible
Relief in Apr 2018 MW F 1436 1526 3001 1369 3463 86 10881
Wrt monitorable % F/C 87 66 84 98 91 86 85
Average Visible
Relief in May 2018 MW G 1564 1075 2173 1276 3030 91 9209
Wrt monitorable % G/C 95 46 61 91 80 91 72
34.2.2 In earlier Meetings, the following had been noted:
SCADA mapping was to be improved for AP, TS and TN.
Visible relief to be improved for Karnataka and Telangana.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 52
In the Special Meeting held on 09.07.2018 in respect of pending issues of Karnataka,
it was noted that on account of RE injection which was substantial, the direction of
power flow on some of the identified features had reversed and also in some feeders,
the net flow has been reduced considerably. SRPC vide letter dated 09.07.2018
(Annexure-XLV) had requested all states to review the identified feeders for UFR
and in case required, to have more number of radial feeders at lower voltage levels.
34.2.3 Review of UFR quantum and set points
NPC Secretariat vide letter dated 30.05.2018 (Annexure-XLVI) had furnished UFR
quantum to be adopted by SR in the current Grid Environment, which was to be
ratified by NPC. Further NPC secretariat had sought comments on retaining the same
set points (49.2 Hz, 49.0 Hz, 48.8 Hz & 48.6 Hz) or enhancing the set points by 0.2
Hz (49.4 Hz, 49.2 Hz, 49.0 Hz & 48.8 Hz).
KSEBL vide letter dated 20.06.2018 had stated that the existing set points can be
retained. TSTRANSCO vide letter dated 20.06.2018 had suggested that the revision of
set frequencies could be deliberated in the TCC meeting for arriving at consensus on
the issues. APTRANSCO vide letter dated 05.07.2018 had stated that they were
agreeable for increase in settings of 0.2 Hz. In the Special Meeting held on
09.07.2018, KPTCL had confirmed that they were agreeable for the increase in setting
of 0.2 Hz.
34.3 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units
34.3.1 RGMO response is being analyzed in the Meetings of OCC. SLDCs are also to
analyze RGMO instances posted by SRLDC for the generators in their control area
and initiate suitable action as per Order in respect of 84/MP/2015. Inadequate
Response needs to be taken up with SERC (Petition No.302/MP/2013).
34.3.2 Summary for Southern Region (state-wise details are given in Annexure-XLVII) is
given in the Table below please:
Hydro Thermal TOTAL
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
30.01.2018 (1250 MW loss at Koderma)
41 53 130% 669 159 24% 710 211 30%
23.04.2018 (3090 MW generation loss due to multiple trippings at Kotra (PG)
81 109 135% 1282 380 30% 1363 489 36%
34.3.3 As per 5th
Amendment to IEGC, gas stations above 50 MW Installed Capacity were
also to come under RGMO/FGMO Operation w.e.f. 1st October 2017. SLDCs (AP &
TN and NTPC (Kayamkulam) had been requested to kindly take necessary action to
comply with this Amendment.
34.3.4 All generators should keep a Margin for RGMO response while declaring DC in all
level ie at full load/partial load operation.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 53
34.3.5 FRC computations are also to be undertaken by the SLDCs in line with approved
methodology of CERC.
34.3.6 In the OCCM, it was pointed out that necessary checks / interlocks need to be in place
so as to ensure that RGMO margin is available in all the generators under SRLDC
control area. Regulation 5.2(h) of IEGC states, ‘…………….For the purpose of
ensuring primary response, RLDCs/SLDCs shall not schedule the generating station or
unit (s) thereof beyond ex bus generation corresponding to 100 % of the Installed
capacity of the generating station or unit (s) thereof.’
34.3.7 SRLDC vide letter dated 07.02.2018 (Annexure-XLVIII) had taken up the issue with
IPPs/MPPs. It was mentioned that generators may kindly ensure that the station
schedule considering all contracts shall not exceed the MW quantum of NOC given by
SRLDC for ensuring primary response as mandated in the Regulations.
34.3.8 SRLDC vide letter dated 29.05.2018 (Annexure-XLIX) had requested all the SLDCs
to furnish the list of all hydro stations and gas stations which are covered under
FGMO/RGMO response along with the status, clearly mentioning the CERC Order in
case exemption/extension is received from Commission.
34.4 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
Load Forecasting tool meeting the regulatory requirement was yet to be developed by
all utilities. The forecast was required for RRAS and Renewable Framework also.
States had been requested to break the state load into sub components like district
wise/substation wise while carrying out the forecasting incorporating weather
conditions etc.
34.5 Sudden Change in Demand/Frequency Excursion (Clause 5.2 (j) of the IEGC)
Necessary action is kindly sought in respect of demand and generation management as
well as power purchases, so that clause 5.2 (j) of IEGC Regulations is not violated.
34.6 Arranging of interruptible loads in four groups
As per IEGC, to maintain the frequency within stipulated band and also to ensure
network security, interruptible loads are to be arranged in four groups of loads. This
was for the purpose of scheduled power cuts/load shedding, loads for unscheduled load
shedding, loads to be shed through UF relays, df/dt relays and loads to be shed under
any SPS Scheme. These loads are to be grouped in such a manner that there was no
overlapping between different groups of loads.
Existing schemes were not meeting Regulatory requirement fully and further action was
required in this regard. Constituents are kindly requested to ensure necessary
compliance.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 54
34.7 PSS Tuning
5th
Meeting of PSS tuning was conducted on 26th
July 2017 and MoM is available at
SRPC website. PSS Study group had analyzed the Step Response Test Reports for the
generators which had furnished the reports and recommendations had been finalized. It
had been kindly requested that necessary action may be taken as finalized in the PSS
Meetings. SRT of following units had been analyzed in the PSS Meetings and necessary
action had to be taken as per Recommendations:
Entity Generating Stations/Units
APGENCO Rayalaseema TPS U1 to U5; VTPS U1 to U4 & U7; SDSPP U1&
U2 (Reports to be analyzed); Srisailam RB HEP U1 to U7; Lower
Sileru HEP U1
AP IPP HNPCL U1 & U2
TSGENCO Nagarjunasagar HEP U1 to U8; Srisailam LB HEP U1 to U6;
Kakatiya TPS U1 & U2; Kothagudem TPS U 7 & 8 (Report to be
analyzed) U10 & U11; Singareni Collieries U1 & U2 (Reports to
be analyzed)
KPCL Raichur TPS U1,2,3,5,6,7& 8; BTPS U1 to U3; Varahi UGPH
HEP U1 to U4; Nagjheri HEP U1 to U6 (U6 report to be
analyzed); Sharavathy HEP U1,2,3,4,5,6,7,9, 10 & 8 (Report to be
analyzed), Raichur TPS U4 (Report to be analyzed)
KAR IPPs UPCL U1 & U2; JSWEL U1 to U3
KSEBL
TANGEDCO MTPS-I U1 to U4 (U1 Report to be analyzed); NCTPS St-I U1 to
U3; Tuticorin TPS U1(Report to be analyzed) U2 to U5; NCTPS
St-II U1; Kadamparai HEP U1 & U2, Mettur-II (Report to be
analyzed).
TN IPPs
CGS NTPC- Ramagundam U7 & U4 (Report to be analyzed); NTPC-
Simhadri U1 to U4; NTPC-Talcher STPS St-II U3 to U6; NTECL-
Vallur TPS U1 to U3; NLC-Neyveli TPS II U4 to U7; NLC-
Neyveli TPS II U1 to U3; KGS U2 (Report to be analyzed);
NPCIL-KKNPP U1 & U2 (Report to be analyzed) ;NLC-Neyveli
TPS II Exp. U1 & U2; (NLC & TN JV) NTPL U1; NTPC-Kudgi
U1
ISTS connected IPPs TPCIL U1 & U2 (U2 Report to be analyzed); Coastal Energen U2;
IL & FS U1 & U2
For the following Units, PSS is to be tuned and SRT to be carried out / information not
available.
Entity Generating Stations/Units
APGENCO VTPS U5 & U6; Lower Sileru HEP U2 to U4
AP IPPs
TSGENCO
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 55
KPCL Yeramarus TPP
KAR IPPs JSWEL U4
KSEBL Idukki HEP U1 to U6
TANGEDCO NCTPS St-II U2; Kadamparai HEP U3 & U4
TN IPPs STCMS
CGS NTPC-Ramagundam U1, U2, U3, U5 to U6; NTPC-Kudgi U2;
NLC-Neyveli TPS I Exp. U1 & U2 (SRT reports not submitted);
NPCIL- KGS U1, U3 & U4 ( Full Report not submitted for U4);
NPCIL-MAPS U1 & U2;
ISTS connected IPPs Coastal Energen U1; Lanco Stage II & III; SGPL-Nellore; SEL
U1 to U4; MEL U1 & U4
Generators to kindly initiate necessary action on the recommendations finalized in the
PSS meetings. In the 5th Meeting of Grid Study Committee held on 18th June 2018, it
was decided that a Committee would be constituted for PSS tuning at national level.
34.8 Relocation of SPS schemes
A comprehensive report on the SPSs to be shifted to Raichur and SPSs being retained at
Kolar would be furnished by SR-I and SR-II to all the states/UT, SRPC and SRLDC.
States would also communicate the corresponding load to the mapped to the respective
SPSs. The location of new DTPCs would also be coordinated in this exercise.
34.9 Other Issues requiring kind attention of TCC / SRPC
Following issues which are being followed up in the Meetings of Sub-Committees of
SRPC also merit kind attention:
SR-II had requested shutdown of IL&FS-Nagipatnam D/C lines for LILO of
Neyveli-Bahoor at Karaikal. IL&FS had suggested alternative method like hot line
which would not require any generation outage at IL&FS. SRPC had requested SR-
II to consider hot line crossing since this would ensure generation continuity at
IL&FS and also ensure Karaikal regional drawal of Puducherry is accounted in the
monthly REA and other commercial account as planned.
On 13.02.2018 and 14.02.2018, there were sudden variations in the DC by
Simhadri. In the 141st OCC Meeting, it was noted that sudden intra-day DC
variations would be stopped by ISGS during coal deficit condition. Further, it was
noted that clause 6.4.16 of IEGC could be followed in letter and spirit,
‘……….During fuel shortage condition, in case of thermal stations, they may
specify minimum MW, maximum MW, MWh capability and declaration of fuel
shortage.’ OCC had noted that even during supercritical coal stock, fuel shortage
was not being declared by some of ISGS stations. OCC suggested that less than 3
days coal stock could qualify to be declared as fuel shortage condition. ISGS need to
ensure that in case average DC is less than Ex-bus (normative) over a day, then DC
would need to be maximized during 06:00 to 09:00 hours and also during 18:00 to
21:30 hours, while appropriately reducing DC during other hours.
CEA vide letter dated 16.02.2018 had informed that a Special Task Force had been
constituted under IGEF Sub-Group-1 for enhancing the flexible operation of
existing coal-fired power plants. The Committee had recommended implementation
of measures for 50 %, 40 % and 25 % minimum load in thermal power stations. The
measures for 50 % minimum load operation requires no investment or minimal
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 56
investment (Report is available on CEA website under TRM division).
Subsequently, a Meeting was held under the Chairmanship of Member (Thermal) on
08.02.2018. It was decided that 55% minimum load operation would be
implemented nationwide in first phase. Further, six units, including two units of
NTPC and one unit each from DVC, GSECL, APGENCO, MSPGCL, would be
taken up for 55 % minimum load operation in line with the CERC notification dated
06.04.2016 and 05.05.2017 (IEGC) (4th
amendments). Accordingly SRPC vide
letter dated 23.02.2018 had requested APGENCO to communicate the unit where
the 55 % minimum load operation would be implemented to CEA, New Delhi with
a copy to SRPC. In the 144th
OCCM, APTRANSCO informed that APGENCO had
agreed for any of the Rayalaseema unit for flexibility (CEA letter 16.02.2018).
APGENCO would be informing the same to CEA.
CEA vide letter dated 10.04.2018 had sought following data for the study (as
decided in the 3rd
meeting of the Committee)
Historic generation data of renewables (RES) on hourly basis and, if possible, at
15 minutes interval for a period of one year.
Location of installed capacity of all current renewable energy sources and
location of anticipated RES installations by 2022.
Generation data of renewables as received from SRLDC had already been submitted
to CEA. All states had been requested to kindly furnish location of installed capacity
of all current renewable energy sources and location of anticipated RES installations
by 2022.
CEA vide letter dated 13.04.2018 (Annexure-L) had informed regarding
registration of all existing and upcoming electricity generating units of the country
of capacity 0.5 MW and above under National Level Data Registry System
Issue regarding Kudgi DC being more than LGB target had been taken up by
Chairperson, SRPC with Chairperson, CERC vide letter dated 28.02.2018
(Annexure-LI).
KKNPP had closed both the 400 / 230 kV ICTs from 09.03.2018.
In the OCC Meeting, it had been agreed that availability certification of natural
inter-state lines and RPC certified intra-state lines would be carried out by SRPC.
Procedure for submitting the details had been circulated by SRLDC. All states were
to furnish the element wise outage data with availability computations duly vetted
by SLDC to SRLDC by second of every month as per procedure.
All states had been requested to furnish the element-wise outage details and
availability computation for natural ISTS lines and SRPC certified intra-state lines
(which have gone into POC mechanism) vetted by SLDC to SRLDC by 02nd
of
every month (for the previous month). The same has to be verified by SRLDC and
furnish to SRPC Secretariat to issue the availability certificate.
SPS on 400 kV Nellore-NPS line was agreed and implemented on 08.04.2018.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 57
TSTRANSCO vide letter dated 28.02.2018 (Annexure-LII) addressed to Hon’ble
CERC had taken up the issues of, revision of schedule of inter-state short term
transaction (presently 2 clear days), advance intimation by ISGS units revival and
reduction in processing time for contingency transaction in Energy Exchanges.
Ministry of Power vide Order dated 17.03.2017 had allocated 540 MW of power
from Ratnagiri Gas and Power Private Limited (RGPPL) to Indian Railways. 35
MW MoP allocations to Railways (Karnataka) from RGPPL was operational from
25.10.2017. 50 MW & 100 MW to TSTRANSCO & TANTRANSCO was to be
made operational.
SEIL request for enhancement of net exportable quantum from 1240 MW to 1254
MW was recommended by a group and noted in the 144th
Meeting of OCC.
In the OCC Meeting, it was reaffirmed that for shutdown of 400 kV bays (for 765
kV bays, NLDC approval was required) code would be exchanged with SRLDC,
though OCC approval would not be required.
KPTCL had been requested to study the high loading of 220 KV UPCL – Kemar
lines and take up reconfiguration works, if required.
Issue of frequent tripping of Konaje – Manjeswaram line on overload and the set
points were to be settled mutually between KSEBL and KPTCL.
CEA vide letter dated 04.05.2018 had sought data required for development
Geospatial Energy Map of India which is a part of initiative of Government of India,
Niti Aayog. Data in this regard may kindly be arranged to be furnished.
NIWE vide letter dated 09.05.208 had communicated that NIWE is in process of
carrying out Geo-Tagging/Online registry of wind turbines for maintaining a
centralized system of data base. SRPC was requested to revert back with
suggestions/clarifications, if any. SRPC vide letter dated 18.05.2018 had replied to
NIWE in this regard.
Allocation of 50 MW to Telangana (SCR) and 100 MW to Tamil Nadu (SR) from
RGGPL was to be operationalized.
It was agreed that OCC approval for taking A/R in non-auto mode would not be
taken. However, a code would be exchanged (instead of messages) with SRLDC /
NLDC.
In the OCC Meeting, SRLDC had informed that the following practices may be
adopted/continued in real time grid operation for keeping transmission lines in open
condition on account of over voltage with immediate effect:
a. Hand tripping of lines on account of O/V: The existing practice of issuing
real time code from Control Room for hand tripping a line due to over voltage
will be continued during hand tripping.
b. Lines tripping on O/V Protection: Real time code may be issued from
Control Room to continue to keep the line in open condition if over voltage
continues to persist in the system. As and when, system voltage becomes
conductive, real time code may be issued for taking the line into service.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 58
c. Lines already tripped due to fault excluding over voltage protection: After
attending the fault, when SLDC/POWERGRID/Other ISTS Licensee is
conveying its readiness, real time code may be issued to take the line into
service without delay. In case of system constraint or over voltage persisting in
the system, Real time code may be issued from Control Room to continue to
keep the line in open condition on account of over voltage conditions. The
remarks column of the respective line in the outage portal may be suitably
modified.
On the observation of NTPC Simhadri, a Study on loading of Simhadri-Kalpakka-
Gazuwaka power corridor was carried out by SRPC/SRLDC and discussed with
NTPC Simhadri. It was noted that the system was N-1 compliant. During the
outage of one of the lines of Simhadri-Kalpakka, other two lines loading was
expected to go up in the range of 600-650 MW which was within thermal loading
limits.
Vemagiri (PG) -Nunna (Vijayawada) SPS was disabled as recommended by
SRLDC and approved by OCC.
Mock tests to check the healthiness of KKNPP & Talcher-Kolar SPSs were carried
out on 21.05.2018 and for Raichur -Sholapur SPS on 22.05.2018. Identified issues
were being addressed.
SRLDC had furnished summary of MVAR testing and the pending observations
were to be closed by the respective entities and it is being reviewed in the OCC.
NLDC letter dated 15.06.2018 (Annexure-LIII) had furnished the status report and
expressed concern on multiple tower collapses.
TSSLDC vide letter dated 09.05.2018 (Annexure-LIV) had requested to clarify
whether state utilities and distribution utilities can be addressed to include suitable
clause in the connectivity conditions, that models figuring in the RLMM list are
added to the Grid. SRPC vide letter dated 28.05.2018 (Annexure-LV) had
informed that in the Guidelines issued by MNRE for development of Onshore Wind
Power Projects it had been mandated that no wind turbine model shall be allowed
for installation in the country until it has obtained type and quality certification.
MNRE has stipulated verification of complete certificates of the models etc which
needs to be carried out by the concerned procurement agency.
It was agreed that URS availing on D-1 day would be processed at 2000 hrs after the
PX transactions are cleared.
Power Number for SR states for the year 2018-19 (based on the actual consumption
and Maximum Demand figures during the year 2017-18) are AP: 301, TS: 328,
KAR: 355, KER: 129, TN:524, Pudu:13. (Total SR: 1,650)
In the 7th
Meeting of NPC held on 8th September 2017, NPC had emphasized the
need for having an accurate All India power system data base for carrying out
accurate power system studies for operational and planning horizons. POSOCO
was to prepare requires formats and circulate to all RPCs and in turn RPCs were to
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 59
obtain data from their constituents. It was noted that NLDC had furnished the
formats to NPC.
Further to the follow up by SRLDC and TSSLDC on DG set requirement to start
auxiliaries at Jurala for black start and reply dated 30.11.2017 of TSGENCO,
TSTRANSCO vide letter dated 17.03.2018 (Annexure-LVI) had advised
TSGENCO to take up the work in compliance of CEA Regulations.
SRPC vide letter dated 28.06.2018 (Annexure-LVII) had enclosed CEA letters
dated 26.06.2018, 20.06.2018 and 01.06.2018 informing about that newly developed
National Power Portal (NPP) which has replaced earlier established Information
Management System (IMS) in CEA. All entities have been kindly requested to enter
their relevant data in NPP (npp.gov.in)
In Petition No. 58/TT/2017 on tariff determination for transmission elements in SR ,
Hon’ble CERC in its Order dated 05.07.2018 had noted ‘The Commission during
the hearing of Petition No. 38/TT/2017 filed by the petitioner for approval of
transmission tariff from COD to 31.3.2019 for Assets (10 nos.) of ERSS IX Project
in Eastern Region on 18.1.2018 directed as under:-
“2. Since the petitioner has not submitted proper reply regarding requirement of
regional spares vis a vis their current availability, the Commission directed to
submit a proper reply. The Commission further directed to set up a Committee
consisting of representatives from PGCIL, NLDC and CEA under the Chairmanship
of the Chief(Engineering) of the Commission to assess the requirement of regional
spares including bus reactors, line reactors, ICTs, etc., present availability and
other related issues and submit a comprehensive report on the requirement of spare
bus reactors, line reactors, ICTs and related equipment in different regions of the
country to the Commission by 9.3.2018. The Commission also observed that final
tariff in the matter would be allowed only after consideration of the Report to be
submitted by the Chief (Engineering) of the Commission…….
we direct the Committee to finalize the report and submit the same to the
Commission within two months of this order.”
Based on the tariff orders issued by the SERCs/JERCs for FY 2017-18, the APPC at
the National level has been determined as Rs. 3.53/kWh by Hon’ble CERC in
Petition No 4/SM/2018 vide Order dated 21.06.2018.
In Petition No. 198/TT/2017 in the matter of ‘Determination of transmission tariff
for Asset-I: ±800 kV 3000 MW HVDC Pole-III and LILO of Bishwanath Chariali -
Agra HVDC line for parallel operation of the HVDC station at Alipurduar, Asset-
II: ±800 kV 3000 MW HVDC Pole-IV along with Earth electrode station and Earth
Electrode line at Alipurduar and Agra end….’, Hon’ble CERC in its Order dated
13.06.2018 had stated, ‘The AFC allowed in this order shall be applicable from the
date of commercial operation of the transmission system and the billing, collection
and disbursement of the transmission charges shall be governed by the provisions of
CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations,
2010, as amended from time to time. Further, the transmission charges allowed in
this order shall be subject to adjustment as per Regulation 7(7) of the 2014 Tariff
Regulations.’
In Petition No. 245/TT/2017 in the matter of ‘Approval of transmission tariff from
COD i.e. 1.12.2015 to 31.3.2019 for Gooty-Madhugiri 400 kV D/C line and 2x500
MVA transformers along with downstream bays at Madhugiri Sub-station upon
bifurcation of capital cost and hence transmission tariff as per directive of the
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 60
Commission vide order dated 18.7.2017 in Petition 54/RP/2016….’, Hon’ble CERC
in its Order dated 24.05.2018 had stated, ‘In response, the petitioner submitted that
KPTCL shall bear the tariff for the Gooty-Madhugiri 400 kV D/C transmission line
(Asset-I) from 1.12.2015 to 24.8.2016 and for 2 x 500 MVA transformers at
Madhugiri Sub-station along-with bays for downstream system (Assets-II, III, IV
and V) from the COD to the commissioning of the downstream assets in terms of
order dated 18.7.2017 in Petition 54/RP/2016. The transmission charges of Asset-I
shall be included in the PoC computation from 25.8.2016 i.e. from the date of
commissioning of 400 kV D/C Madhugiri-Bidadi Transmission Line (TBCB) and for
Assets II, III, IV and V from the date of commissioning of downstream assets.
Accordingly, transmission charges for assets II to V have been withdrawn from PoC
Pool and are being borne by KPTCL till commissioning of downstream assets.’
In Petition No. 3/TT/2018 in the matter of ‘Approval of transmission tariff from
COD to 31.3.2019 for “Bunching of Tirunelveli – Edamon section of the Tirunelveli
–Muvathapuza (Cochin) 400 kV quad D/C line initially (and temporarily) at 220 kV
with existing Tirunelveli – Edamon 400 kV twin D/C line (400 kV line charged at
220 kV) under Transmission System associated with Kudankulam Atomic Power
Project”….’, Hon’ble CERC in its Order dated 24.05.2018 had stated, ‘The
Commission directed the staff to request CEA to clarify whether bunching of the
Bunching of Tirunelveli-Edamon section of the Tirunelveli-Muvathapuza (Cochin)
400 kV quad D/C line initially (and temporarily) at 220 kV with existing Tirunelveli-
Edamon 400 kV twin D/C line (400 kV line charged at 220 kV) under Transmission
System associated with Kudankulam Atomic Power Project enhances power flow
between buses and POSCO to validate the reason for increase in 167 MW flow as
claimed by the petitioner within a month..’
In Review Petition No. 44/RP/2017 in Petition No. 103/MP/2017 along with I.A.
No. 74/2017, Hon’ble CERC in its Order dated 21.05.2018 had stated, ‘The Review
Petitioner had raised similar issue in Petition No. 229/RC/2015. The Commission in
its order dated 8.3.2018 in Petition No.229/RC/2015 has dealt with the issue as
under:
“52. CTU has expressed apprehension that if LTA is operationalized in the absence
of LC, the Petitioner would not be able to recover the transmission charges in the
event of default by the DICs. In our view, though there is provision in the BCD
Procedure for opening of LC one month prior to the effective date, LC is not a
condition precedent for operationalization of LTA. If LTA is not operationalized
pending opening of LCs, this will give perverse incentives to the DICs not to open
the LCs to avoid paying the transmission charges. There is therefore a need for
prescribing certain deterrent measures against the defaulting DICs. In our view, a
DIC who has been granted LTA but does not intend to open the LCs, he shall be
debarred from applying for medium term open access and short term open access.
As a result, the DIC in order to avail the medium term and short term open access
will be forced to make payment of LTA charges. Accordingly, we direct that if the
DIC fails to make payment of the transmission charges or open letter of credit at the
end of the month after operationalization of LTA, it shall be denied medium term
open access and short term open access till it makes payment of transmission
charges and open letter of credit.”
Therefore, non-payment of transmission charges and non-opening of LC under the
LTA shall result in the denial of MTOA or STOA.
8. The Commission in the impugned order has decided that opening of LC is not a
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 61
Condition precedent for operationalization of LTA which has also been reiterated in
the order dated 8.3.2018 in Petition No. 229/RC/2015. The Commission, in the said
order has held also that if a DIC who has been granted LTA but does not intend to
open the LCs, then he shall be debarred from applying for MTOA and STOA.
Accordingly, there is no error apparent in the impugned order...’
35. COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014
– IN RESPECT OF LVRT AND OTHER PROVISIONS OF CEA/CERC
REGULATIONS
35.1 Four Meetings had been conducted so far in compliance of Order of Hon’ble CERC
(Petition No.420/MP/2014) in respect of LVRT and other provisions of CEA/CERC
Regulations. Hon’ble Commission had specified time lines for a number of actionable
points for various entities.
35.2 Quarterly reports of SR constituents jointly validated by SRLDC & SRPC Secretariat are
being communicated to Hon’ble CERC with regard to monitoring of the installation and
performance of LVRT installed on existing WTGs as per the directives.
35.3 CEA had issued draft second amendment in CEA (Technical Standards for connectivity
to the Grid) Regulations. The final notification is awaited.
35.4 The following had been noted in earlier Meetings:
New wind and solar units need to comply with LVRT/HVRT provisions and
STU/SLDC was to ensure necessary compliance. Required mechanism needs to be in
place for this purpose. SLDCs were requested to approve connectivity to new
generators only on confirmation of availability of LVRT feature and other
CEA/CERC requirements.
Identification of optimal location for installing PMUs for LVRT analysis purposes.
Conducting capacity building workshop regarding forecasting and scheduling of RE.
35.5 MNRE had brought out OM dated 01.03.2018 (Annexure-LVIII) on compliance of
WTG models to applicable CEA Technical Standards for Connectivity to the Grid (as
amended from time to time) as stipulated in the MNRE Guidelines/procedure for Revised
List of Models and Manufacturers (RLMM). MS, SRPC vide letter dated 19.04.2018
(Annexure-LIX) had sought certain clarification wrt MNRE OM dated 01.03.2018.
Further, it had been requested that the second amendment to Connectivity Regulations
may please be arranged to be notified at an early date.
35.6 A Meeting to discuss the OM and other issues was held at NIWE, Chennai on 23rd
April
2018 and the minutes are available at SRPC website. The following was noted:
Status of LVRT testing facility
NIWE had informed that they were in the process of equipping themselves to test all
the provisions of CEA Regulations.
NIWE had informed that at present 21 models from 9 OEMs are having valid
Statement of Compliance (SoC)/Conformity Statement (CS) and figure in the RLMM
list. They are complying with the provisions of CEA Regulations.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 62
Comprehensive Indian Wind Turbine Certification Scheme was being prepared and it
would cover
Type Certification
Wind Farm Project Certification
Life Assessment of Wind Turbine – Failure Analysis, Safety Assessment, Residual
Life Assessment, Life Extension & Decommissioning Procedure.
35.7 Forum had felt that there was a need for enabling agency similar to NIWE to ensure
compliance of CEA Regulations for Solar generators since solar targets were significant
and the addition was rapid pace. Based on these recommendations, Chairperson, SRPC
vide letter dated 09.05.2018 (Annexure-LX) had taken up the issue of effective
implementation of provisions of CEA Regulations (including LVRT / HVRT) and other
security features by agencies like NISE (on similar lines of NIWE).
36. GRID OPERATION
36.1 Salient Achievements
Overarching Agreement was successfully implemented on 28.02.2018 between
Kerala and Karnataka.
Kudgi Unit-I was taken under RSD on 28.02.2018. This was for the first time that
any ISGS unit was taken under RSD in the region. This would pave way for further
RE integration.
KGS-1 is operating continuously since 13.05.2016 (770 days as on 22.06.2018). It
has surpassed the earlier record (among NPCIL stations) for longest continuous run
of 765 days set by RAPS-5. With this achievement, KGS-1 now stands second in
the world among Pressurized Heavy Water Reactors (PHWR) and fourth among all
nuclear power reactors in terms of continuous operation.
PLF of Kaiga GS was 97.77% for the year 2017-18.
NTPC Ramagundam received the Golden Peacock Award on Energy Efficiency
Management in 20th
World Congress on Environment Management and Climate
Change at New Delhi on 06.07.2018.
SEIL received the Golden Peacock Award for Environment Management for the
year 2018 in 20th
World Congress on Environment Management and Climate
Change at New Delhi on 06.07.2018. Renewable energy arm Sembcorp Green Infra
has also won Greentech Gold Award.
Kolar HVDC Station completed two years of ‘Zero Tripping’ & ‘Zero Forced
Outage’ as on 23.06.2106.As per CIGRE Reports, it is a World/Global Record.
Ramagundam Stage-I & II, Ramagundam Stage-III, Neyveli Stage-II and Neyveli
TS-I Expn. had achieved PAF of more than 90% during the year 2017-18.
Ramagundam Stage-III and Talcher-II had achieved PLFs of > 85% during the year
2017-18.
On initiative of SRPC secretariat, SR had got additional ramp of 262 MW/block
from ISG Stations.
36.2 Grid Highlights during February 2018
SR demand touched all time maximum of 45,325 MW.
MVAR testing of SEIL and SGPL completed on 02nd
& 03rd
March 2018.
Revised ADMS settings were adopted by Kerala and Telangana also.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 63
220/132 kV Gachibowli SS in Rangareddy district of existing 2 x 160 + 2 x 100
MVA was commissioned on 19.02.2018 with augmented capacity of 3 x 160 + 1 x
100 MVA by TSTRANSCO.
220/132 kV Minpur SS in Medak district of existing 2 x 160 + 1 x 100 MVA was
commissioned on 21.02.2018 with augmented capacity of 3 x 160 MVA by
TSTRANSCO.
125 MVAR reactor at 400 kV Mamidipally SS was commissioned on 23.02.2018 by
TSTRANSCO.
4.6 MW of wind (private), 0.004 MW of Solar (state), 0.002 MW of Solar (private)
and 1.3 MW of biomass was commissioned in AP. 36 MW of Solar (private) and 11
MW of other RE was commissioned in TS. 14 MW of Solar (private) and 6 MW of
mini hydro was commissioned in Kerala. 29.4 MW of Wind (private) and 500.875
MW Solar (private) were commissioned in Karnataka.
36.3 Grid Highlights during March 2018
SR Demand touched all time maximum demand of 47,210 MW
SR Consumption touched 1,080 MUs.
LILO of 220 kV ADR Palem – Bobbli D/C line from loc. No.43 to proposed 400 kV
SS to Garividi in Vizianagaram district of 2 Ckm was commissioned on 15.03.2018
by APTRANSCO.
220 kV D/C line from 400 kV SS Gani to 220 kV SS Somayajulapalli in Kurnool
district of 34.6 Ckm was commissioned on 31.03.2018 by APTRANSCO.
220 kV SS Gundala in Krishna Dist of Existing 3 x 50 MVA was commissioned on
25.03.2018 by APTRANSCO with augmented capacity of 1 x 80 + 2 x 50 MVA.
220 kV D/C line with Moose conductor from 220/132 kV Narketpally SS to Udaya
Samudram 220/11 kV SS in Nalgonda dist of 18.18 Ckm was commissioned on
31.03.2018 by TSTRANSCO.
220 kV Chandrayagutta in Rangareddy Dist of existing 2 x 160 + 2 x 100 MVA
was commissioned on 20.03.2018 by TSTRANSCO with augmented capacity of 3 x
160 + 1 x 100 MVA.
Nelamangala-Yelahanka (39.006 Km) OPGM Fibre communication link of Central
Sector was put into service for commercial operation w.e.f 28.03.2018 by SR-II,
PGCIL.
Hoody-Yelahanka LILO point of Nelamangala – Hoody, Hoody-HSR (KPTCL),
Peenya-NRS-Hebbal (KPTCL), Hoody-HAL (KPTCL), LILO of Pondy –
Sriperumbadur to SV Chatram (TANTRANSCO), LILO of Neyveli TS-II – Neyveli
TS-I to NNTPS, Salem(PG) – Salem (TNEB) and Sriperumbadur (PG) to
Sriperumbadur (TNEB) OPGM Fibre links (98.484 Km) were put under commercial
operation w.e.f 28.03.2018 by SR-II, PGCIL.
1x 125 MVAR 400kV Bus Reactor along with its associated bays and equipments at
Tumkur (Pavagada) pooling station were put under commercial operation w.e.f
00:00 hrs of 31st March 2018 by SR-II, PGCIL.
1 x 500 MVA 400/230kV ICT along with associated bays and equipment at
Tirunelveli 400/230 kV substation were put under Commercial Operation w.e.f
00:00 hrs of 31st March 2018 by SR-II, PGCIL.
LILO of 400 kV D/C Bellary-Tumkur (Vasantnarsapur) (Quad Moose) TL at
Tumkur (Pavagada) pooling station along with associated bays and equipments were
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 64
put under Commercial Operation w.e.f 00:00 hrs of 31st March 2018 by SR-II,
PGCIL.
1 x 500 MVA 400/230 kV ICT along with associated bays and equipment at
Karaikudi 400/230 kV substation were put under Commercial Operation w.e.f
00:00 hrs of 2nd
April 2018 by SR-II, PGCIL.
1 x 500 MVA 400/230 kV ICT along with associated bays and equipment at Arasur
400/230 kV substation were put under Commercial Operation w.e.f 00:00 hrs of
31st March 2018 by SR-II, PGCIL.
136.4 MW of wind (private) and 3 MW of Solar (private) was commissioned in AP.
27.5 MW of Solar (private) was commissioned in TS. 190.175 MW of Wind
(private) was commissioned in TN. 203.5 MW of Wind (private) and 909.3 MW
Solar (private) were commissioned in Karnataka.
36.4 Grid Highlights during April 2018
220 kV SS Parchur in Prakasam district of existing 3 x 100 MVA was
commissioned on 22.04.2018 by APTRANSCO with augmented capacity of 2 x
100 + 1 x 160 MVA.
220 kV D/C line from 400 kV Asupaka SS to 220 kV Aswaraopet SS in Khammam
dist of 40.282 Ckm was commissioned on 28.04.2018 by TSTRANSCO.
220/132 kV SS Aswaraopet (Upgradation of existing 132/33kV SS Aswaraopet) in
Khammam district with 100 (MVA) capacity was commissioned on 28.04.2018 by
TSTRANSCO.
220 kV Mandamari SS in Mancherial Dist of existing 2 x 100 MVA was
commissioned on 06.04.2018 by TSTRANSCO with augmented capacity of 3 x
100 MVA.
220 kV Chandrayanagutta SS in Rangareddy Dist of existing 3 x 160 + 1 x 100
MVA was commissioned on 09.04.2018 by TSTRANSCO with augmented
capacity of 4 x 160 MVA.
1 x 500 MVA 400/220 kV ICT along with bays and equipment at Kozhikode
400/220 kV Substation were put under commercial operation w.e.f 00:00 hrs of 3rd
April 2018 by SR-II, PGCIL.
1 x 500 MVA transformer at 400/220 kV Narendra substation (replacement of
existing 2nd
1 x 315 MVA 400/220kV transformer) was put under commercial
operation w.e.f 00:00 hrs of 16th
April 2018 by SR-II, PGCIL. It was informed that
the replaced 1 x 315 MVA transformer shall be utilized as a regional spare.
18 MW of wind (private) and 61.896 MW of Solar (private) was commissioned in
AP. 2.5 MW of Solar (private) was commissioned in TS. 22.5 MW of Wind
(private) was commissioned in TN. 4.5 MW of wind (private) and 58 MW of Solar
(private), was commissioned in Karnataka.
36.5 Grid Highlights during May 2018
187 MU of Wind generation recorded on 10.06.2018 in SR during this season.
220 kV S’/C line from Chakrayapeta to LILO point of 33/220 kV pooling SS in
Animala of 25.662 Ckm was commissioned on 19.05.2018 by APTRANSCO.
220 kV D/C line from Chakrayapeta to Talamanchipatnam in Kadapa dist of
174.396 Ckm was commissioned on 19.05.2018 by APTRANSCO.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 65
220 kV D/C line for making LILO of existing one circuit of 220 kV Vemagiri to
Undiline at proposed 220/132/33 kV SS Duvva in West Godavari district of 0.64
Ckm was commissioned on 27.05.2018 by APTRANSCO.
220/132/33 kV SS Duvva in West Godavari district with 116 MVA capacity was
commissioned on 27.05.2018 by APTRANSCO.
220/132/33 kV SS at Chakrayapeta in Kadapa district with 100 MVA capacity was
commissioned on 19.05.2018 by APTRANSCO.
220 kV SS Tekkali in Srikakulam district of existing 2x100 MVA was
commissioned on 16.05.2018 by APTRANSCO with augmented capacity of
3x100MVA.
400 kV Gajwel to Ramadugu I 129.529 Ckm was commissioned on 06.05.2018 by
TSTRANSCO.
400 kV Ramadugu to STPP I 67.909 Ckm was commissioned on 06.05.2018 by
TSTRANSCO.
400 kV KTS – VII to Julurupadu I 39.08 Ckm was commissioned on 19.05.2018
by TSTRANSCO.
400 kV KTS – VII to Julurupadu II 39.08 Ckm was commissioned on 19.05.2018
by TSTRANSCO
400/220 kV Gajwel SS in Siddipet district of existing 3 x 315 MVA was
commissioned on 03.05.2018 by TSTRANSCO with augmented capacity of 3 x
315 + 1 x 500 MVA.
220/132 kV SS Gunrock in Hyderabad District of existing 2 x 160 MVA was
commissioned on 24.05.2018 by TSTRANSCO with augmented capacity of 3 x
160 MVA.
220/132 kV LI SS Huzurabad in Karimnagar Dist of PTR I 100 MVA capacity was
commissioned on 14.05.2018 by TSTRANSCO.
LILO of 400kV S/c Nelamangala – Hoody Transmission Line, 2 x 500 MVA,
400/230kV ICT’s at new 400/220kV GIS Substation at Yelahanka with 1 x 63
MVAR 420 kV Bus Reactor, along with associated bays & equipments were put
on COD w.e.f 00:00 hrs of 1st April 2018 by SR-II.
2 x 400kV D/C (Quad) Tirunelveli (Tuticorin II) PS - Tuticorin PS, 2 x 500 MVA,
400/230 kV transformers, 2 x 125 MVAR 400kV Bus Reactors along with
associated bays & equipment were put under Commercial Operation w.e.f 00:00
hrs of 10th
June 2018 by SR II.
12 MW of wind(private) and 4.004 MW of Solar (private) was commissioned in
AP. 06 MW of solar (private) was commissioned in TS. 1.25 MW of solar (private)
was commissioned in Kerala. 50 MW of Solar (private) was commissioned in
Karnataka.
36.6 Demand Variation (Peak Vs Off-peak)
Issue regarding large variation between minimum and maximum demands has been
under the consideration of TCC/SRPC. Issue is also being discussed in the monthly
Meetings of OCC. Following was observed with regard to the period from Feburary
2018 to May 2018:
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 66
Description
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala
Tamil
Nadu Pudu
Southern
Region
February 2018
Highest 41.59 36.27 27.02 38.89 34.82 41.18 27.24
Date (Day) 02.02.2018
(Friday)
08.02.2018
(Thursday)
09.02.2018
(Friday)
05.02.2018
(Monday)
05.02.2018
(Monday)
05.02.2018
(Monday)
05.02.2018
(Monday)
Lowest 31.30 20.09 13.28 29.59 15.52 21.14 12.48
Date (Day) 10.02.2018
(Saturday)
25.02.2018
(Sunday)
25.02.2018
(Sunday)
24.02.2018
(Saturday)
25.02.2018
(Sunday)
11.02.2018
(Sunday)
25.02.2018
(Sunday)
Average 34.69 29.57 18.99 33.19 27.51 33.74 20.53
March 2018
Highest 35.05 45.69 29.40 37.66 30.14 42.13 23.39
Date (Day) 03.03.2018
(Saturday)
17.03.2018
(Saturday)
16.03.2018
(Friday)
31.03.2018
(Saturday)
19.03.2018
(Monday)
17.03.2018
(Saturday)
17.03.2018
(Saturday)
Lowest 22.24 11.38 11.48 25.04 9.27 19.41 9.17
Date (Day) 18.03.2018
(Sunday)
31.03.2018
(Saturday)
29.03.2018
(Thursday)
13.03.2018
(Tuesday)
25.03.2018
(Sunday)
28.03.2018
(Wednesday)
25.03.2018
(Sunday)
Average 28.40 19.99 17.27 30.56 21.29 29.40 15.14
April 2018
Highest 35.41 52.13 29.42 36.20 22.43 44.67 19.61
Date (Day) 24.04.2018
(Tuesday)
06.04.2018
(Friday)
22.04.2018
(Sunday)
04.04.2018
(Wednesday)
30.04.2018
(Monday)
25.04.2018
(Wednesday)
02.04.2018
(Monday)
Lowest 17.49 9.37 10.83 25.04 8.66 18.42 7.09
Date (Day) 29.04.2018
(Sunday)
15.04.2018
(Sunday)
14.04.2018
(Saturday)
13.04.2018
(Friday)
14.04.2018
(Saturday)
14.04.2018
(Saturday)
29.04.2018
(Sunday)
Average 25.19 21.22 17.99 30.32 14.52 27.55 13.67
May 2018
Highest 34.96 58.06 42.93 43.97 26.41 35.73 28.58
Date (Day) 01.05.2018
(Tuesday)
03.05.2018
(Thursday)
03.05.2018
(Thursday)
04.05.2018
(Friday)
29.05.2018
(Tuesday)
27.05.2018
(Sunday)
04.05.2018
(Friday)
Lowest 18.91 15.48 12.24 17.07 8.12 14.63 7.68
Date (Day) 05.05.2018
(Saturday)
24.05.2018
(Thursday)
01.05.2018
(Tuesday)
13.05.2018
(Sunday)
13.05.2018
(Sunday)
30.05.2018
(Wednesday)
06.05.2018
(Sunday)
Average 26.82 22.84 25.11 31.64 17.82 25.64 15.85
Note: Highest & lowest figures for the month have been computed based on the daily
values.
36.7 Frequency of Operation of Southern Grid
Frequency of operation of the Southern Grid for the period under review is furnished
below please:
Month
Percentage of time when frequency (Hz) was
Month
Avg.
freq.
Less
than
49.5
49.
to
49.
7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
February 2018 0.00 0.00 9.68 53.15 27.00 10.17 0.00 80.15 49.98
March 2018 0.00 0.00 12.99 55.23 23.95 7.82 0.01 79.18 49.97
April 2018 0.00 0.02 12.74 53.66 25.72 7.86 0.00 79.37 49.97
May 2018 0.00 0.22 22.29 48.41 21.44 7.64 0.00 69.85 49.95
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 67
During the period under review, caution / violation messages (Annexure-LXI) were
issued to the constituents by SRLDC. Matter regarding overdrawal at low frequency
by some of the constituents is being regularly deliberated in the OCC forum. Utilities
are requested to kindly adhere to the Regulations in this regard.
In the OCC Meetings, SRPC & SRLDC had pointed out that sustained violation of
reversal of sign was to be avoided for compliance of IEGC /DSM Regulations.
Regulation 6.4.6 of IEGC states ‘…………… Every regional entity shall ensure
reversal of sign of deviation from schedule at least once after every twelve time
blocks.’ Regulation 7(10) of DSM Regulations states, ‘In the event of sustained
deviation from schedule in one direction (positive or negative) by any regional
entity, such regional entity (buyer or seller) shall have to make sign of their
deviation from schedule changed, at least once, after every 12 time blocks.’
37. REIMBURSEMENT OF SRPC EXPENDITURE
Statement showing net amount payable by Member Utilities of SRPC for the year 2018 -19,
after adjustment of surplus/deficit for the previous period is furnished in Annexure-LXII.
Members are kindly requested to ensure payment, wherever due.
38. OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE
A Special Meeting was held at SLDC, KSEBL, Kalamassery on 13.04.2018 (MOM
enclosed at Annexure-LXIII). In the 143rd
OCC meeting, the forum had concluded that the
performance of hydro stations cannot be assessed by means of any standard formats. In view
of this, OCC had unanimously agreed to drop the matter regarding monthly performance
from the Agenda.
39. RSD & TECHNICAL MINIMUM
39.1 KSEBL and TSTRANSCO had raised certain issues in respect of scheduling during RSD of
one of the units at Kudgi. These issues were discussed in detail in the OCC and CC
Meetings. NLDC vide letter dated 06.04.2018 (Annexure-LXIV) had proposed discussion
on RSD procedure in each of the RPC as noted in the approved RSD procedure. In the OCC
Meeting, it was noted that NLDC had confirmed that the procedure being followed was in
line with the Regulations / Procedure. However, concerns of the states (TS/Kerala) would
be communicated to Hon’ble CERC as they had sought comments on the TM / RSD
procedure and Compensation Mechanism. States had also been requested to furnish their
views to NLDC on TM / RSD Procedure. SRPC vide letter dated 16.04.2018 (Annexure-
LXV) had furnished its comments to Hon’ble CERC. Subsequently, SRPC vide letter dated
05.07.2018 (Annexure-LXVI) had taken up the concerns of SR states on RSD procedure
with Director (MO), POSOCO.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 68
39.2 In the OCCM, NTPC, Kudgi had informed that the requirement of 35 hours to bring back
the Kudgi super critical unit from cold start under RSD would be taken up through
Corporate with NLDC / CERC.
40. FREQUENT REVISION OF OUAGE PLAN BY ISG STATIONS
NTPC/NTECL had revised the annual outage plan for the FY 2018-19 in the month of
April 2018 from the plan originally submitted. SRPC vide letter dated 16.04.2018
(Annexure-LXVII) had expressed concern about frequent changes in the annual outage
plan that had been well deliberated in the earlier OCC /TCC Meetings. Based on the outage
plan furnished by the generators and the MoP target, LGBR and the outage plan are
prepared. These inputs are also utilized by the states for their regulatory compliance,
purchase planning etc. The need for adhering to this Outage Plan was also highlighted.
41. COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF
RENEWABLE ENERGY SOURCES
41.1 CEA vide letter dated 12.04.2017 and 08.05.2017 (enclosing MoP letter dated 06.04.2017)
and in Special Meetings held on 28.06.2017 and 11.09.2017 had observed that it was
obligatory for all grid connected renewable generators to provide necessary facilities for
data communication and data storage and other parameters as may be stipulated. It had been
decided by CEA that respective states would submit weekly reports of data communication
status to CEA as well as to respective RPC / RLDC and NLDC. The issue had been further
discussed in the 4th
Meeting of LVRT / RE issues held on 25th
October 2017 at SRPC,
Bengaluru. (Minutes available on SRPC website). The following is updated status with
regard to availability of RE SCADA:
State SCADA availability as on
31.05.2018 Mapped I/C
Remarks
AP Wind: 3801.87/3965.87 MW (96.11%)
Solar: 2003/2209.78 MW (90.64%)
Total: 5662/6095.75 MW (94.15%)
Pending SCADA availability was for RE
connected distribution level and for which
action had been taken for compliance.
TS Wind: 100.8/100.8 MW (100%)
Solar: 3023/3257 MW (92.82%)
Total: 3123.8/3357.8 MW (93.03%)
Action for balance SCADA availability at
33 kV and below was being followed up
and notices had been issued.
KA Wind: 3504/3504 MW (100%)
Solar: 3079/3244 MW (94.91%)
Total: 6583/6748 MW (97.55%)
KE Wind: 16/59.3 MW (26.99%)
Solar: 71.18/90.858 MW (78.34%)
Total: 87.18/150.133 MW (58.07%)
TN Wind: 7988.96/8152 MW (98%)
Solar: 648/1918 MW (33.79%)
Total: 8636.96/10070 MW (85.77%)
Notices had been issued for SS under 10(1) for
SCADA availability. 100% SCADA availability
of wind was likely to be ensured by December
2017. TANTRANSCO (Communication) and
TANGEDCO (Metering) had jointly initiated
action for Solar SCADA availability and was
targeted to be completed by July 2018.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 69
41.2 A Meeting regarding “Furnishing Real Time/Daily Renewable Energy Generation Data”
was held at Jaipur, Rajasthan on 04-05-2018 under the Chairmanship of Member
(Planning), CEA (MOM is available at Annexure-LXVIII). In the Meeting, it was
decided that the status of the pooling stations having data communication would be
ascertained and the percentage of availability of communication link/system would be
monitored and reported on a weekly basis. States had agreed to follow the same.
41.3 In respect of REMC project (SRLDC, AP, Karnataka & TN) it had been noted that
sanction of GoI had been received during September 2017 and implementation schedule
was of 14 months. The effective date of contract is 29.01.2018 (Awarded to M/s
Chemtrols/OSI (JV), date of Award is 29.09.2017) with completion schedule of 14
months (29.03.2019). The following is the updated status (as on 05.07.2018):
a) Site survey of Control Centres is completed and the Control Centre buildings of
KPTCL & APTRANSCO are expected to be ready by October’ 18.
b) Database & display building is expected to be completed by August’ 18 for the
stations envisaged under the project (TN-140, AP-48, KAR-78 & SRLDC-5)
c) ICCP testing successfully completed with SCADA systems of RLDC & SLDCs for
the integration of RE stations reporting to existing SCADA systems.
d) Vendor is finalized for forecasting & scheduling services.
e) Engineering activities are in progress and expected to be completed by August’ 18.
f) Supplies (SCADA hardware & Software and Video projection displays) are
expected to resume from end October’ 18 and total commissioning is expected by
Jan’ 19.
g) Training programs on RE introduction, System administration, system software &
Historian & Application software are completed and course on RE forecasting &
scheduling is proposed in August’18.
42. SCHEDULING OF ANANTHAPURAMU ULTRA MEGA SOLAR PARK &
RAMAGUNDAM SOLAR PROJECT
42.1 In the Special Meetings held on 02.05.2018 and 08.05.2018, it was agreed that scheduling
of Ananthapuramu Ultra Mega Solar Park (1500 MW) would be carried out by SRLDC.
SRPC vide letter dated 10.05.2018 (Annexure-LXIX) had communicated the activities of
the SPDs and SPPD.
42.2 Further, to have clarity on issues, SRPC vide letter dated 25.05.2018 (Annexure-LXX)
had communicated the feedback on Procedure for implementation of the Framework on
forecasting, scheduling and in balance handling for Renewable Energy (RE) generating
stations including power parks based on wind and solar at inter-state level to Hon’ble
CERC.
42.3 In the Meeting held on 15.06.2018, it was agreed that the complete share of 10 MW of
Ramagundam Solar Power project would be availed by Telangana (including 6 MW
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 70
presently allocated to AP) along with 10 MW from unallocated power of coal based NTPC
stations of SR (MoM available on SRPC website). The same was implemented from
01.07.2018 after due concurrence from CEA.
43. GRID STUDY COMMITTEE (GSC) MEETINGS ON PACKAGE-A & PACKAGE-B
43.1 MoP (GoI) has constituted a "Task force on Power System Analysis under Contingencies"
in December 2012 as a follow up of the recommendations of Enquiry Committee under
Chairperson, CEA on Grid Disturbances of 2012 in Indian Grid. Terms of Reference
(TOR) was prepared by POWERGRID in consultation with CEA and POSOCO. The
works were undertaken in two separate packages:
Package-A: To review the status of implementation of recommendation of Enquiry
Committee on Grid Disturbance and Protection Audit: Awarded to M/s Tractebel
Engineering, Romania. The consultancy assignment for Package A comprised two Tasks as
follows:
Task - I: To study and review the status of implementation of recommendations of the
Enquiry Committee.
Task - II: To conduct on site Protection audit check of the works already carried out, for
10% (76 nos.) of 762 Substations across the country after grid failure of July 2012.
Package-B: To review transmission system transfer capability and review of operational and
long term planning: Awarded to M/s Powertech Lab Inc. (PLI), Canada. The consultancy
assignment for Package-B comprised six Tasks as follows:
Task-I: Examination and Recommendation of Methodology for Optimum Calculation of
Transfer Capability (TIC/ATC/TRM) in the Planning and the Operational Horizons.
Task -II: Calculation of Transfer Capability (TIC/ ATC/TRM) for entire country.
Task-III: Guidelines for developing and implementing System Protection Scheme (SPS)
and Islanding schemes and review existing schemes.
Task-IV: Operational Planning and Long term planning for secure and efficient operation
of the grid.
Task-V: Suitable suggestions in the Regulatory framework to ensure Secure and efficient
grid operation.
Task-VI: To review the tuning of all Power Electronic Devices (including FACTS and
HVDC) and suggest retuning of setting of these devices, as per report of Task Force.
43.2 Grid Study Committee (GSC), which was constituted to facilitate the consultant's study/
analysis, had so far held five Meetings.
43.3 GSC in their 4th meeting held on 16.01.2018 (minutes issued vide NPC letter dated
01.03.2018 were circulated to SR-Constituents along with the minutes of PCSC-72 meeting
had accepted the following Reports:
Report of the Consultant M/s Tractebel Engineering on Task I & II under Package A.
Report of the Consultant M/s Powertech Labs Inc. on Task I, II & III under Package B.
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 71
43.4 GSC in the 5th
Meeting held on 18.06.2018 (minutes issued vide NPC letter dated 26.06.2018
would be circulated to SR-Constituents along with the minutes of PCSC-75 meeting) had
accepted the following report:
Report of the Consultant M/s Powertech Labs Inc. on Task IV, V & VI under Package B.
43.5 As decided in the GSC-5 meeting, an action plan for implementation of various
recommendations for all Tasks under Package-A & Package-B is under finalization by
CEA in consultation with CTU & POSOCO. After finalization, the same would be made
available to SR-Constituents for appropriate action, please.
44. OVR GRADING OF 400 KV AND 765 KV TRANSMISSION LINES OF SOUTHERN
REGION
44.1 In the past one year, a number of new 400 kV and 765 kV transmission lines have been added
to SR-Grid in addition to reconfiguration (including LILO) works of the existing 400 kV and
765 kV transmission lines. In this regard, a comprehensive exercise of OVR grading for
400 kV and 765 kV transmission lines of Southern Region (existing as on March, 2017) had
been carried out. New OVR Gradings proposed to be adopted for these lines (along with
study results) had been circulated to all Constituents for modifications/ omissions/ comments.
After duly incorporating Constituents' comments, final OVR gradings to be adopted for 400
kV and 765 kV lines in the Southern Region had been issued vide SRPC letter dated
01.05.2018 for implementation with immediate effect. Above OVR gradings had also been
kept in SRPC Website for easy reference.
45. COMPLIANCE OF CERC (COMMUNICATION SYSTEM FOR INTER-STATE
TRANSMISSION OF ELECTRICITY), REGULATIONS 2017
45.1 A Special Meeting was held on 08th
May 2018 at SRPC, Bengaluru (Minutes available on
SRPC website) on compliance of CERC (Communication System for inter-State
Transmission of Electricity) Regulations, 2017 which had come into force w.e.f.
01.07.2017. There were two activities assigned for RPCs - periodic auditing of
communication system and ensuring cyber security third party audits. Audit procedure
(Annexure-LXXI) had been finalized in that Meeting and the same is put up for kind
approval of the TCC/SRPC. All the entities had agreed for annual periodicity (FY) for
Cyber Security Audit. Further on the request of the constituents, a guiding Code for Cyber
Security audit has been prepared in consultation with the stake holders and circulated to all
the constituents.
46. SPECIAL MEETING ON THE TRIPPINGS OF POLES - 1 & 2 AT HVDC
GAJUWAKA SS OF POWERGRID (SRTS-I) – REG
46.1 A Special Meeting was held on 02nd
April, 2018 at RHQ POWERGRID (SRTS-I), Hyderabad
to deliberate on all outstanding issues involved in the recent HVDC Gazuwaka Pole trippings
- esp. two categories of trippings that occurred in the past one year - viz., Pole-1 trippings on
A.C. auxiliary supply failure and Pole-2 trippings on ferro-resonance detection. The
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 72
following issues were discussed in the Meeting:
Deliberations on HVDC Pole trippings in the past one year
Resolution of Issues w.r.t. Pole-1 Trippings (ALSTOM make)
Resolution of Issues w.r.t. Pole-2 Trippings (ABB make)
Compliance of Protection Audit Recommendations (PAR) pertaining to Gajuwaka
(HVDC & HVAC) Substation
46.2 The issue had also been raised in the Operational Feedback (Jan-Mar 2018) by POSOCO .
46.3 The Minutes of the Meeting were circulated vide SRPC letter dated 11.04.2018. PGCIL
(SRTS-I) is requested to kindly take appropriate action w.r.t. measures identified for
resolving issues w.r.t. Pole-1 & Pole-2 trippings.
47. SPECIAL MEETING ON THE PENDING PROTECTION ISSUES OF
PUDUCHERRY SUBSTATIONS
47.1 A Special Meeting is proposed to be held on 20th
July, 2018 at Puducherry ED HQ to
deliberate on all outstanding protection issues involving Puducherry substations. The
following issues are proposed to be discussed in that Meeting:
Root-cause Analysis of the Villianur GD’s on 30.05.2018, 05.06.2018 & 15.06.2018
Review of status of implementation of Protection Audit Recommendations of Villianur and
Bahour Substations.
Review of compliance status of the recommendations given in the Special Meeting held
on 3rd
January, 2017 w.r.t. Neyveli Grid Disturbance on 25.11.2016.
48. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH
TRANSMISSION NETWORK
48.1 In the earlier Meetings it was noted that some RE schemes are getting modified at times
while some are getting dropped also. TCC had suggested that the RE Projects/evacuation
schemes may kindly be reviewed and updated status communicated. It was observed that
timely progress on these schemes needs to be communicated to SRPC Secretariat, being a
critical issue monitored by various bodies.
48.2 Transmission scheme for Wind Energy Zones (WEZs) in Southern Region
In the 42nd
SCPSPSR, representative of POWERGRID stated that Govt of India has set an
target for 175GW renewable capacity by 2022, out of which 60 GW is envisaged to be set
up through wind power projects. In view of the wind capacity expansion plan as well as
connectivity applications received in ISTS for wind capacity & SECI bids, it is expected
that wind capacity may cross the milestone of 60 GW in next 3-4 years. SECI has already
bid 6,050 MW ISTS connected wind bids (awarded-4,050 MW) and planning to bid
10,000 MW in FY18-19. Therefore, there is a requirement of development of ISTS
infrastructure in wind rich pockets. To identify actual developable wind potential by 2022,
several rounds of discussions were held with MNRE & other stakeholders. Further, wind
energy zones along with projected capacity in each WEZ, which may come up by 2022 in
wind resource rich states were prioritized. Accordingly, five WEZs viz. Koppal (2,500
Agenda for the 33rd TCC & 34th SRPC Meetings to be held on 10 &11.08.2018 Page 73
MW) in Karnataka, Kurnool (3,000 MW) in Andhra Pradesh, Karur (2,500 MW) in Tamil
Nadu, Dwarka (2,000 MW) in Gujarat and Osmanabad (2,000 MW) in Maharashtra were
identified for which ISTS substation/infrastructure was decided to be developed/made
available.
After deliberations, it was decided that due to large scale integration of renewable
generation in SR, detailed study considering the proposals of renewable rich states of SR
and CTU need to be carried out. The results of the study would be discussed in joint study
meeting.
49. PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS
49.1 Insulator tracking had been observed in Transmission lines and Substations located in the
coastal and polluted areas. SRPC vide letter dated 05th
May 2016 had communicated to
the concerned in this regard. Transmission Lines and Substations in the most vulnerable
terrain, coastal and polluted areas were to be categorized for monitoring to ensure that
Patrolling and Maintenance is being carried out as per Patrolling guidelines.
49.2 Concerned entities need to kindly initiate/continue necessary steps to ensure that
Patrolling and Maintenance is carried out regularly as per the Patrolling Guidelines.
50. ROSTER FOR HOSTING THE SRPC MEETINGS
As per the roster the SRPC meetings are to be hosted in the following sequence:
(1) UPCL (2) JSWEL (3) NPCIL (4) SGPL
51. DATE & VENUE OF THE NEXT MEETING OF SRPC
*********