consulting engineer mt. pleasant, michigan 48853 · the lags must be identified immediately and...

85
Subject: Project*: Disk *'s: Monitoring Report #1 Ralph J. Stephenson, P.E., P.C. Consulting Engineer 323 Hiawatha Drive Mt. Pleasant, Michigan 48853 (517) 7722537 March 15,1992 First Colony Life Insurance Building Remodeling Lynchburg, Virginia 91:37 283 &304 Dates of monitoring: March 3 and 4, 1992 (wd's 299 and 300) Monitored from: , Sht #LL - issue #3, dated December 3, 1991 (wd 236) Sht #1-79 - issue #3, dated December 3, 1991 (wd 236) Sht #3-79/68 ne - issue #3, dated December 3, 1991 (wd 236) Sheet #T-79 - issue #3, dated December 3, 1991 (wd 236) Sheet #2-79/68 - issue #3, dated December 3, 1991 (wd 236) Sheet #1-68 - issue #3, dated December 3, 1991 (wd 236) Sheet #T-68 - issue #3, dated December 3, 1991 (wd 236) Start and move in dates from Issue *3 network models: • Lower level started in December, 1991 completed 01/09/92 (wd 262) • 1-79 started in December, 1991 to be complete 04/10/92 (wd 328) • 3-79/68 ne started 12/03/91 (wd 236) to be complete 04/22/92 (wd 336) • T-79 started 01/13/92 (wd 263) to be complete 05/13/92 (wd 351) .2-79/68 started in December, 1991 to be complete 05/18/92 (wd 354) • 1-68 start 05/19/92 (wd 354) to be complete 10/22/92 (wd 464) • T-68 start 10/23/92 (wd 464) to be complete 04/02/93 (wd 577) • 3-68 e no issue #3 diagram prepared 1

Upload: others

Post on 24-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

Subject:

Project*:

Disk *'s:

Monitoring Report #1

Ralph J. Stephenson, P.E., P.C. Consulting Engineer 323 Hiawatha Drive Mt. Pleasant, Michigan 48853 (517) 7722537 March 15,1992

First Colony Life Insurance Building Remodeling Lynchburg, Virginia

91:37

283 &304

Dates of monitoring: March 3 and 4, 1992 (wd's 299 and 300)

Monitored from: ,

Sht #LL - issue #3, dated December 3, 1991 (wd 236) Sht #1-79 - issue #3, dated December 3, 1991 (wd 236) Sht #3-79/68 ne - issue #3, dated December 3, 1991 (wd 236) Sheet #T-79 - issue #3, dated December 3, 1991 (wd 236) Sheet #2-79/68 - issue #3, dated December 3, 1991 (wd 236) Sheet #1-68 - issue #3, dated December 3, 1991 (wd 236) Sheet #T-68 - issue #3, dated December 3, 1991 (wd 236)

Start and move in dates from Issue *3 network models:

• Lower level started in December, 1991 completed 01/09/92 (wd 262)

• 1-79 started in December, 1991 to be complete 04/10/92 (wd 328)

• 3-79/68 ne started 12/03/91 (wd 236) to be complete 04/22/92 (wd 336)

• T -79 started 01/13/92 (wd 263) to be complete 05/13/92 (wd 351)

.2-79/68 started in December, 1991 to be complete 05/18/92 (wd 354)

• 1-68 start 05/19/92 (wd 354) to be complete 10/22/92 (wd 464)

• T -68 start 10/23/92 (wd 464) to be complete 04/02/93 (wd 577)

• 3-68 e no issue #3 diagram prepared

1

Page 2: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

/ Ralph]. Stephenson, P.E., P.e. Consulting Engineer 323 Hiawatha Drive Mt. Pleasant, Michigan 48853 (517) 772 2537 March 15, 1992

Start and move in dates from updated Issue #4 network models:

• Lower level • 1-79

• 3-79/68 ne

• T-79

• 2-79/68

• 1-68

• T-68

• 3-68 e

Actions taken:

work completed. 1st Colony moved in on 01/08/92 (261) started in December, 1991 to be complete 06/09/92 (wd 369)

started 12/03/91 (wd 236) to be complete OS/29/92 (wd 362)

started 01/13/92 (wd 263) to be complete 04/20/92 (wd 334)

started in December, 1991 to be complete 06/17/92 (375)

start 06/09/92 (wd 368) to be complete 11/11/92 (wd 478)

start 11/12/92 (wd 478) to be complete 04/22/93 (wd 591)

start 03/03/92 (wd 299) to be complete - 06/08/92 (wd 368)

• Inspected project with Mr. Steve Greene and Mr. Phil Jamerson • Reviewed current project status relative to areas not yet in work • Updated network models for areas

1-79 3-79/68 ne T-79 2-79/68 1-68 T- 68 3-68 e

• Prepared monitoring report

Summary

The main purpose of this session was to monitor the project, evaluate current

2

Page 3: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

RalphJ. Stephenson, P.E., P.C. Consulting Engineer 323 Hiawatha Drive Mt. Pleasant, Michigan 48853 (517) 7722537 March IS, 1992

status and update the network plans as required.

Work at the lower level (LL) was completed on January 8,1992 (wd 261), one day ahead of the scheduled completion of January 9,1992 (wd 262).

Currently four areas are in work. They are the 1979 addition 1st level (1-79), the 1979/1968 non executive (ne) addition 3rd level (3-79/68 ne), the 1979 addition Terrace Level (T-79), and the 1979/1968 addition 2nd level (2-79/68).

Level 1-79 interior rough work is nearly complete except for above floor sheet metal work and some above floor electrical and fire protection work. The new Issue #4 target date for completion of move into the 1-79 area is the pm of June 9, 1992 (wd 369).

Level 3-79 / 68 ne interior rough and finish work has been completed to where new ceiling work, finish painting and carpet could proceed. The new Issue #4 target date for move into the 3-79/68 area is the pm of May 29, 1992 (wd 362).

Work at the T -79 level has proceeded through most of the bulk rough work and the floor is now ready for finish painting, installation of carpet and completion of following interior finish work. The new Issue #4 target date for completion of move into the T-79 area is the pm of Apri120, 1992 (wd 334).

At the level 2-79/68 addition most rough interior work and some interior finish work is complete, and finish painting and carpet could start soon. This will be followed by remaining interior finish operations. The new Issue #4 target date for move into the 2-79/68 area is the pm of June 17,1992 (wd 375).

As of the am of March 23,1992 (wd 313) Mr. Jamerson estimates the approximate ahead or behind position at each area measured against the Issue #3 networks, dated December 3,1992 (wd 236) as follows. These are projected lags based on progress expectations for the next few weeks.

First Level-1979 addition (1-79) Third Level-1979/68 addition (3-79/68 ne) Terrace Level- 1979 addition (T-79) Second Level - 1979/68 addition (2-79/68)

20 working day lag 25 working day lag 15 working days ahead 10 working day lag

The updating of the networks to Issue #4, dated March 3, 1992 (wd 299) incorporated the revised sequencing and times into the network. The new starting dates as established for remaining areas are listed in tabulation and narrative above.

3

Page 4: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

/ Ralph]. Stephenson, P.E., P.e. Consulting Engineer 323 Hiawatha Drive Mt. Pleasant, Michigan 48853 (517) 772 2537 March 15, 1992

Mr. Greene, Mr. Jamerson and I prepared a full set of updated or new network models for the entire project. These were reviewed at our meetings and finish printed copies left with Mr. Greene and Mr. Jamerson for their use and distribution. The updated data appears to be achievable. However these revised plans of action must be accompanied by continuous expediting of approvals and deliveries of critical materials. If additional lags are experienced, the causes for the lags must be identified immediately and corrections made if the project is to be completed as desired.

I suggest close front end procurement attention be given the 3-68 e area for the executive offices. This will be a critical area for predictable reoccupation.

I also recommend that the project be monitored again in from 11/2 to 3 months to insure that the plan of work is being followed and to assist to pick up any deteriorating trends in project progress. Continuous monitoring and analysis efforts should be maintained by the project team agains t the issue #4 networks.

I shall be in touch with Mr. Greene shortly to determine needed, the timing of the next major monitoring and 'If, d

4

Page 5: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

122/81

122/81

3-78/68 0 JLaLI2 3/3112

1- t4 UPDATING - 03103112

313/82

3rd Floor 79/68 non executive (3-79/68 ne) Interior work

Location Early start

Duration Eany finish

3-78/68 1 ~ 3/41111

003-SELECT NUMBER OF TEST

PILES TO BE USED & LOCATION - 1

(_urnpl_)

3/4/81 3/4/111

Late start Late finish

ACTIVITY KEY

Activity number Activity description Activity estimated duration in elapsed working days

4 3/61112

022-APPROVE NEW HVAC DESIGN &

PRICE - 4

13/02 1'2

3~/68 1 3/31112 313/12

04S-PREPARE NEW PA DESIGN & ISSUE

FOR COSTING - 1

4/81112

BalDed "lIy;ty Numbe"

01710040 046 047 048 049

045 050

LAN 017 !IAN 108

3-711/68 0 3/31112 3/31112

3/11/11

3-711/68 4 3-78168 3/11/112 3/12/112 3/131112

067-COMPLETE On-COMP INSTALL INSTALL ABOVE NEW CEILING

CEILING DUCTWORK DIFFUSERS. LIGHTS.

AT 3-7OI68NE - 4 t-------I:~~~7N:ti:C.J~R;S t-----T-------------

318/82 3112/n

3-711/68 1 314/112 3141112

046-APPROVE NEW PA DESIGN AND

PRICE - 1

AT 3-79168NE - 4

3/13112 3118192

3-711/68 2 315/112 3/6/112

06&-INSTALL NEW ABOVE CEILING

CONDUIT & WIRING

I-____ -IFOR POWER. VOICE &

DATA. PUBLIC ADDRESS SYSTEM &

4/81112 41 182 4/10/12

SPEAKERS AT 3-7Il168NE - 2

41131112

3-7111G8 0 3/6/112 3/6/112

41 141IR,-1-4-111-2----

1 3131112

072-INSTALL NEW ACOUSTIC CEILING

SUSPENSION & GRID AT 3-79168NE - 1

3/6112 192

Page 6: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3·711/68 0

3-7t/1I8 15 3/31t2 3/231t2

01l3-REPAINT DEMONTABLE

PARTITIONS AT 3-7Q/IleNE - 15

3/101112

3/18/112 3/181112

-------------------------3-1-,-II/..;IIR/111/112

3· 711/68 3/4/112

4 3/111112

080-INSTALL DOORS .. HARDWARE AT

3·711111eNE • 4

3-711/68 3110/112

4 3113/112

083-COMP FINISH PAINTING AND

APPLYING VINYL

OM· INSTALL NEW CARPET AT

3-711111eNE • 8

3·711/88 5 3/3/12 31t/1l2

008-PREPARE .. SUBMIT HARDWARE

SCHEDULE· 5

/

1141112

3-711168 0 ~ 313182

4 192

3-711168 0 3/61112 3161112

4/14/112 4/14/112

OO2-T/R TO ISSUE 14 " UPDATING • 031031112

4114/112 414/112

10 ~ 3·711/68 4/13/112 ~/14/112 12

4/211/02

087-1NSTALL O!lO-CLEAN EXISTING DEMOUNTABLE CEILING GRID .. PARTITIONS .. INSTALL NEW

3·711/68 4/30/112

3 5/41112

101·BALANCE HVAC SYSTEMS AT

3-7Q/IleNE - MAY WALL COVERING AT DOORS AT 3-7II/118NE ACOUSTIC TILES AT HAVE TO BALANCE

3·7!1168NE 4

3/0112 3112192 3113192 311aroZ 311 1112 3130~3131/112 3·7t/68 3/3/112

II ""'~'711/118 3/10/1l~/16/112 4 31U/1I2

311

082·ROUGH IN CONDUIT FOR

TOMBSTONES .. SEAL HOlES AT

3-7!l/1I8NE • 6

';J;;,.' .:,/ = ":,,, 002-TIR TO ISSUE 14 002·T/R TO ISSUE 14 UPDATING - 03103102 UPDATING - 03103102

311l/Vi/! 3111/92

O85-TRIM OUT NEW ELECTRICAL .. LIFE SAFETY SYSTEMS AT 3-711168NE· 4

412m..,-------z7T

3·7111118 0 JllLI2 3131112

086-TIR TO NOTIFY PUBLIC .. OTHER

AGENCIES OF DATE OF TESTING LIFE

SAFETY SYSTEMS AT 2-711188 - ?

- 10

411 1112

3·711/68NE • 12

4/14102

3·711/68 3/311112

4129192

8 4/111112

088-lNSTALL VOICE, DATA .. POWER

TOMBSTONES AT 3-7Q/88NE - 8

412.rn.T"'-----ml!l2

3·711/88 3120/112 31201 2

08I1-cONDUCT LIFE SAFETY TESTS AND APPROVE SYSTEMS

AT 3-7Q/68NE - 1

5 102

WITH OTHER AREAS OF BUILDING· 3

4130/112

3-711168 4/111112

515111

5/4192

15/112

Page 7: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3-70188 31101112

OOII-REVIEW ... APPROVE

HARDWARE SCHEDULE ...

5 31181112

SUBMIT TEMPLATES TO HM FABRICATOR -

II

3-711168 31171112

10 31301112

012-FAB ... DELIVER HARDWARE - 10

412 1112 4/Z 1112 4128/92 511 1112

3-711168 2! /

3131112 3141112/

023-RE-KEY LOCK CYLINDERS

NECESSARY FOR

----I OWNER'S NEEDS - 2

412J11S12 41271112

3-711168 5 5/51112 51111112

lOZ-FINAL CLEAN ...

5151 2

/

MOVE OUT OF 3-7!l1lI8NE - II

51111112

3-711188 5112112

103-0WNER

2 51131112

PREPARE ... ISSUE PUNCH LIST FOR

3-711188NE - 2

5/1: 1112 5/1 1112

3-711168 112lIZ.

o 3131112

104-TIR TO APPLY FOR CERllFICATE OCCUPANCY AT

3-70/S8NE

511 5/112 5115102

3-711188 511"'112

• 511111112

101i-CONTRACTOR CORRECT PUNCH

LIsT ITEIiS ... OWNER ACCEPT AREA AT

3-71l188NE - •

5/141112 5 HI n

3-70168 3131112

3 '- 3-711168 315102 ~1201Q2 5

5127102 3-U168 51281112

2 51211/112

106-APPlY FOR ... RECEIVE

CERllF1CA TE OF OCCUPANCY FOR

3-70188NE - 3

5/15182 5/111/112

Issue #1 • Odober 9, 19!H Issue #2 - October 22, 1991 Issue #3 - December 3, 1991 Issue #3 • monilored 03103192 Issue #4 - Marcb 3, 1!l92 i4sbt#3·79/68 be

disk 304

107-FCL INSTALL 10ll-FCL MOVE INTO OFFICE FURNITURE 3-711168NE AREA - 2

AT 3-711168NE • 5

51201112 5/271112 6126/112

3rd HOOT 79/68 non executive (3-79/68 ne) Interior work

5129

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchbun:. Yireinja

H. J. Construction Joint Venture Lynchburg, Virginia 24506

Ralph J. Stephenson PE PE Consulting Engineer 323 Hiawolha Drive MI. Pleasant, Michigan 4885 3 ph 517 772 2537

/112

Sheet 3-79/68ne

Page 8: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

122/91

122/91

Terrace 79 (T-79) Interior work T·n 0 0

313192 3131112 313192 3131f12

T·lI 2 31111112 3112/112

021·RE·KEY LOCK CYLINDERS

NECESSARY FOR OWNER'S NEEDS • 2

."ff-11-2-111-2--------------------------31-1-2-,flHI12/f12

.;J:, ."\,, ,;;;:, •• " ,,;;:, ~,;J:, 3~~~~----~d

6 ./ T·79 3110192/ 3111192

045·PREPARE NEW 046-APPROVE NEW 072·COIIP INSTl PA DESIGN" ISSUE PA DESIGN AND NEW ABOVE ClG

FOR COSnNG • 1 PRICE • 1 CONDUIT " WIRING FOR POWER, VOICE ,.

~-----~ DATA, PUBLIC

312knr...-----"1"m.

ADDRESS" SPEAKERS AT T-7l1 •

5 312.!-nr,..-------.".,"*'/1I2 31

Ole·PREPARE " .,

SUBMIT HARDWARE SCHEDULE· 6

1 ,,.'" ~I 192

4 3/6192

~T.7l1 3/301112

3 4/1/112

077-CO S AL NEW CEILING

DIFFUSERS. LIGHTS. SMOKE DETECTORS. SPRINKLER HEADS

AT T·7fI· 4

31

T-n 0 T·n 4 ~ T-7l1 /,

3111 31692

lllLii 3131112 3/3192 3/6192 ~lfl192 5 3113192

T·711 31161112

10/ 312719

DOl·TIR ISSU 14 076-CO FIN H UPDATING· MARCH PAINTING AND

3, 1.2 APPLYING VINYL

I------i WALL ;.~~:R!NG AT 1-___ -1

313/12 313 2 3/3192 3 92 319 92

oel·INS AL DEMOUNTABLE PARTITIONS"

1------1 DOORS AT T·7\I • 10

3116192 31 7/112

~;;J:2 3IZ9X;Q;:2

2 3110192

T·7\l 31111112

1 31111112

....... -0,..7-1"'.CO=M""p""L--:e"'T"'E,...... .... INSTALL ABove

CEILING DUCTWORK AT T·7l1· 2

3/5/112 3161112

070-TRIM OUT NEW ELECTRICAL " LIFE SAFETY SYSTEMS

AT T·7fI· 2

41 1102 41

T·7l1 lliLll

O8O·TlR TO NOTIFY PUBLIC ,. OTHER

AGENCIES OF DATE OF TESTING LIFE

SAFETY SYSTEMS AT T·7f1 • ?

4131l1z

082·CONDUCT LIFE SAFETY TESTS AND APPROVE SYSTEIIS

AT T-711 • 1

IlI2 413 1112 41 192

083·CLEAN EXISTING CEILING GRID " INSTALL NEW

ACOUSTIC nlES AT T·7f1 • 3

3 1112 4/1/112

OOll·REVIEW " APPROVE

HARDWARE SCHEDULE· 5

312 II,.", 'II; 1112

T·79 4/2192

2 4/3/92

064·BAlANCE HVAC SYSTEMS AT T-79 • 0

MAY HAVE TO BALANCE WITH

OTHER AREAS OF BUILDING· 2

4/2 !92 4/: 1112

T·79 0 31111112 11 11/112

416111 41 &/lI2

Page 9: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T ·711 8 T 711 31181112 31271112 4181112 4181112

OI2-FAB .. DELIVER 086·0WNER HARDWARE· 8 PREPARE .. ISSUE

PUNCH LIST FOR T·711 • I -

312 '/V2 41 102 41 'VOl 4 1112

T·70 2/T'711 416102 417102 1llLU

o 313/112

085-FINAL CLEAN .. MOVE OUT OF T·70·

2

41

087·TIR TO APPLY FOR CERTIFICATE

OCCUPANCY AT T·711

8/112 4/8102

Location Early start

Duration Early finish

T·711 1llLU

1 313102

GOa·SELECT NUMBER OF TEST

PILES TO BE USED ..

313'112

LOCATION· 1 (example)

3t: 1112

• Activity numbgr • Activity description

Activity estimated duration in elapsed working days

Late start la1e finish

ACTIVITY KEY

T 711 2 41111112 4110111 2

G8a-CONTRACTOR CORRECT PUNCH

LIST ITEMS .. OWNER ACCEPT AREA AT

T·70 • 2

4111'112 411 }J:

T·711 3131112

3' T·711 315/112 "113102

I 4/13/02

T·711 4/141112

5 4/201112

T·70 4120/112

a 4/201112

O8!I-APPL Y FOR .. " OIlO-FCL INSTALL IOt·FCL MOVE INTO 100-E TIR TO SET RECEIVE

CERTIACATE OF OCCUPANCY FOR •

T·70·3

4/8f02 4/1 1112

Reseryed Activity Numbers

017 to 040 041 046 042 047 043 046 044 049 045 050

Ian 001 han 101

OFACE FURNITURE .. VENDING MACHINES

411 1112

AT T·711 • I

4/1 192 4/141.,,,

Issue #1 . October 9, 1"1 Issue #2 - October 22, 1991 Issue #3 • December 3, 1991 Issue #3 - monitored 03/03/92 I.,.u< #4 - Marcb 3, 1"2 i4sbt#T-79 disk 304

T·7Q AREA· 5 LATE AN ISH OF

41" 102 4/211i2

Terrace 79 (T-79) Interior work.

ACTIVITY

4/2 I 02

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchburg, Virginia

H. J. Construction Joint Venture Lynchburg, Virginia 24506

Ralph I. Stephenson PE PE Consulting Engineer 323 Hiawatha Drive ML Pleasant, Michigan 48853 ph 517772 2537

Sheet T-79

Page 10: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

12ZIIIl

122/01

2nd Floor 79/68 (2-79/68) Interior work

311

3116/112

1-711 4 3131112 3/611)2

APPROVE NEW HVAC DESIGN " PRICE - 4

1 3131112

045-PREPARE NEW PA DESIGN .. ISSUE

FOR COSTING - 1

2-781118 II 3/31112 3/10/112

006-PREPARE .. SUBMIT HARDWARE

SCHEDULE - II

4/2.m['lJ""-----'7Er4i /82

/ 2-711/68

13/02 3

3/1S/112

072-COMP INSTALL ABOVE CEILING FIRE

ALARM ROUGH WIRING AT ~7W88 -

3

tWZ at17/02

088- N CONDUIT FOR

TOMBSTONES "

8 3/25/112

SEAL HOLES AT

2-711/68 3/31112

2-711168 - 8

08o-COUP FINISH PAINTING AND

APPLYING VINYL

2-7t/68 5 3/11/112 3/17/112

008-REVIEW .. APPROVE

HARDWARE SCHEDULE - 5'

~c~~-----yr,I~'/1l2

2-711/11~ 6 3/6/11Z' ~'3/112

083-COMP INSTALL ............ NEW CEILING

DIFFUSERS, LIGHTS, SMOKE DETECTORS .. SPRINKLER HEADS

AT 2-711/88 - I>

311 I .. " \alz j 112

\ WALL COVERING AT 1-______________ _

2-7W88 - 4

knr"..-----.....".,j....!25IOZ

2-70/68 6 3/11/112 3116/112

073--COMPLETE INSTALL ABOVE

CEILING DUCTWORK AT 2-711188 - I>

311.m~----",m/02

1-711 1 3/4/112 314/02

046-APPROVE NEW PA DESIGN AND

PRICE - 1

2-711168 4 3/5102 311 0/112

074-COMP INSTL NEW ABOVE CLG

CONDUIT .. WIRING

I-___ -.;FOR POWER, VOICE .. '---__ _

DATA, PUBLIC r ADDRESS SYSTEM ..

4/141 2 414/82

SPEAKERS AT 2-711188 - 4

4/15~/;;;1I"--------'...,.n.

Page 11: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3117/112

5/12/11

2·711/68 ,/

3/11112 3/1 21112

01B-RE-KEY TO SUIT OWNER - 2

511/92

112/112

2·711/68 3/111112

4 3/12/112

2·711/68 4/111112

8 4/201112

101· TRill OUT NEW ELECTRICAL & LFE SAFETY SYSTEIIS

AT 2·79168· 4

10a·INSTAll DEMOUNTABLE PARTITIONS &

DOORS AT 2·79168 -8

11/112 4/20/112

711/68 1 13/112 3113/112

10S..cONDUCT LIFE SAFETY TESTS AND APPROVE SYSTEMS

AT 2-79168 • 1

3/26/11 48 2 51 1 f4/l>1I"'2,..------S.m.14/112

2·711168 0 ~'711/68 mru 313/112~/lI/n 4/20/11

l02-TIR TO NOTIFY l04-1NSTALL VOICE, PUBLIC & OTHER DATA & POWER

AGENCIES OF DATE TOMBSTONES AT OF TESTING LIFE 2·711/68 - 8

SAFETY SYSTEMS AT 2-79168 • ?

5/14/112 5/14/112 S/5'1I2

2-711168 4/211112

15 5/111112

lOS·CLEAN EXISTING CEILING GRID & INSTALL NEW

ACOUSTIC TILES AT 2-711/68 • 15

~""j S/11102

2-711/68 5112/112

3 5/14/112

10r·BALANCE HVAC SYSTEMS AT 2-7V168

• 0 MAY HAVE TO BALANCE WITH

OTHER AREAS OF BUILDING· 3

5/12/112 5/14/112

2·7\1/68 4/20/112

5/15/11 1151112

2-78/68 8 3118/112 31271112

012·FAB & DELIVER HARDWARE - 8

5/1 'v,.

2-711/68 5/15/112

"",,.,/112

5 5121/112

lOa-FiNAL CLEAN & MOVE OUT OF

2·711/68 • 5

5/15/92 5/21102

2-711/68 mru

o 3/31112

110-T/R TO APPLY FOR CERTIFICATE OCCUPANCY AT

2-711/68

5/2.m"..------rm.1 2~

2·78168 5/22/11-2

101l-0WNER

2 5/26/112

PREPARE & ISSUE PUNCH LIST FOR

2-79168 - 2 -

5/22/112 S/26/112

Page 12: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

, 2-71168 3 ,313182 315182

" 112-APPLY FOR & RECEIVE

CERTIACATE OF OCCUPANCY FOR

2-78168 - 3

5128/92 6111112

2-711168 4 5127182 6111112

~~~~R;~~~~ LIST ITEIIS & OWNER

ACCEPT AREA AT - 2-78168 - 4

51271n D/1/1l2

RcS!!rud Adlvity Numbers

017 to 040 041 046 042 047 043 048 044 049 045 050

LAN 001 HAN 115

2-78168 6121112

10 6115182

1,3-FCL INSTALL OFACE FURNITURE

AT 2-711168 - 10

Location Early start

6115192

Duration Early finish

2-71l168 61161112

6116192

Activity number Activity desc ription

• Activrty estimated duration in elapsed working days

Late start Lat .. finish

ACTIVITY KEY

2 61171112

61171112

2-711168 6117192

o 61 171112

1~iE T~~~~ ':,~T ACTIVITY

6117192 6117182

Issue #1 - Oclober 9, 1991 Issue #l - October 22, 1991 Issue #3 - December 3, 19'1 Issue #3 - mObitored 03/03192 Issue #4 - Marell 3, 1992 145111#2-79/68 disk 304

2nd Floor 79/68 (2-79/68) Interior work

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchbura. Vin~inia

H. J. Constroction Joint Venture Lynchburg. Virginia 24506

Ralph J. Stephenson PE ffi Consulting Engineer 323 Hiawatha Drive Mt Pleasalll. Michigan 48853 ph 517 772 2537

Sheet 2-79/68

Page 13: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

122191

122191

1st Floor 68 (1-68) Interior work

Page 14: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1·18 15 6/111/112 7/7/92

082·REPAINT DEMONTABLE

PARTITIONS AT HIS ·15

1I/3/uz 11/24/112

1·68 3 7/30192 8/3192

OIl6-INSTALL ABOVE CEILING FIRE ALARM

ROUGH WIRING AT 1-$8 • 3

811 IV'"' al'" 1112

/

Page 15: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1·68 0 813182 813102

812410HIUI02

\

1·68 8110102

076-LAYOUT DEMOUNTABLE

5 8125102

PARTITIONS AT 1-68 ·5

182 811182

1·68 0 111101112 0110182

1·68 8126182

8 014102

078·DRILL HOLES FOR

POKETHROUGHS AT 1·68 • 8

11121112 11114102

T·68 11181112

1·68 0 l..IIlZ.2lJ!l 1 0122182

FROM 080 • FINAL CLEAN & MOVE OUT

OF 1-68 • PM 10121182

1012·1mi------!!I2182

1·88 717182

o 7171e2

INSTALL CABLE TRAYS ABOVE

CEILING OF T-I18 • 8

1112 1112 10111

Page 16: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1·68 101221112

2 101231112

-1012

101"()WNER PREPARE .. ISSUE PUNCH LIST FOR

1-68 - 2

~1!/2 lUI: 31112

o 3131112

lQ2.TIR TO APPLY FOR CERTIFICATE

OCCUPANCY AT 1-68 - ?

111 219« 11121112

1·68 101261112

5 101301112

103·CONTRACTOR CORRECT PUNCH

LIST ITEMS .. OWNER ACCEPT AREA AT

1-68 - 5

1012 j/II;Z

1-68 3131112

101: 0711 2

o "- 1-68 3131112 ~11121112 5

1116192

I04-APPlY FOR .. .....

RECEIVE CERTIFICATE OF

OCCUPANCY FOR 1-68 - ?

11121112 11121i2 111

105-FCL INSTALL OFFICE FURNITURE

AT 1-68 - 5

1112 1116192

1-68 5 10171112 10113192

88- N EXISTING CEILING GRID .. INSTAll NEW

1-68 1119102

3 111111112

106~iA ~a.:8E I~TO

11111192 11/111112

1-68 2 101lMII2 10115192

08ll-BALANCE HVAC SYSTEMS AT 1-68 • 2

~ _________ .....l", _________________ -I ACOUS,r.:; ~I~ES AT 1------1

1-68 111257112

Oas-INSTAlL DEMOUNTABLE

PARTITIONS AT 1-68 - 8

hr------nr'1l102

10113192 101141!!2 10115192

1-68 11111192

o 111111112

1~;E I:NI1~ ~~I

11111/112

1-&8 101161112

ACTIVITY

11/11 1112

10/21192

1-68 10121102

o 101211!!2

101- 0 PREPARE .. ISSUE PUNCH lIST FOR

1-68

101211112 101211112

Page 17: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

Note: Phase 2 sla rts after Phase 1 at9a~ occupied on p~

1-68 5 610102 6115102

OS2-REMOVE • 1-68 6115/112 STORE EXISnNG

DEMOUNTABLE PARTITIONS AS

REQUIRED AT 1-68 - 1----------; 5 713019

o 6/151112

301112

1-68 6125182

4 6130/92

1-68 5 111102 7/8192 O56-OWNER 05!)'()WNER ABATE

IDENTIFY LOCATION ASBESTOS MASTIC OF ASBESTOS ON DUCTWORK AS

MASTIC ON REQUIRED AT 1-68 DUCTWORK AT 1-68 -1-----; 5

.J.::, .,::.:~,~-::, \",/:,1I;5'~"':"'2------6"'lrlI3"'~::: 711~:-------7~8192

053-SALVAG .....,-~Om5!15r"1_m:r.0~V:r.E!!"""-'IA 067-REMOVE STORE EXISnNG EXISnNG CEILING EXISTING ABOVE

LIGHTS, DIFFUSERS, GRID. nLE AS CEILING VOICE,

J.-'::.-__ -IS~:~~E:~T~M~~iR 1-_____ -; REQUIRED. AT 1-68 - ~~J.~~~ ;~:R4

619192

7/1

REQUIRED AT 1-68 -8

OS4-REMOVE

61 18/112

10 6122192

EXISnNG DRY WALL • MASONRY

PARTITIONS AS REQUIRED AT 1-68 -

10

6,,,,, 712i1IU

611919 6124192

'\ 058-REMOVE

EXISTING CARPET AT 1-68 0 1-68 - 5 6/3(1192 6130102

8161i1 8161112

7130192 815192

Page 18: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3 7113/82

oeO·ReMove ABOVE CEILING DUCTWORK

AS REQUIRED AT 1-68 • 3

1·118 7/1~/t12 • 7/21/82

1·68 7/22/82

063-PAIIT INSTALL 065-COMP INSTALL ABOVE CEILING ABOVE CEILING

ROUGH FIRE ROUGH FIRE PROTEcnON PIPING PROTECTION PIPING

1------1 AT 1-68 - 6 1-------1 AT l-GB - 6

/11'11"" 71 1112 7/1~IVZ

1·68 II 7/0/U 7/15102

OB1-CLEAN EXISTING ABOVE CEILING

DUCTWORK WITH

({ 1/82 7/2 IV" fl. 192", 1·68 II

7/30/112 8/51112

oe7-lNSTALL ABOVE CEILING DUCTWORK

AT 1-68 • II

IN WALL ITEMS INCLUDE

• BLOCKING • CONDUIT • FRAMES • PIPING

1-68 ~ 1·68 5 / 8/6/112 8/11182 8112/82 811818

oell-lNSTALl METAL 07o-HANG .. FINISH STUDS .. IN WALL NEW DRY WALL AT WORK FOR WALLS STRUCT TO STRUCT

VACUUM CLeANING AT 1-68·5 r-------------------------------------------------------------i 1-_______ -tS~~~D~':,G S~~ t--------t PARTITIO~~ AT 1-68 1-__ _

AT 1-68 • ~

8 111112 8/,.m~-------:8rni,8/112

Page 19: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1-68 3 81111/112 8/211112

071-A LY FIRST COAT OF PAINT TO

DRY WALL

1-$8 8 8131102 lII101ll2

074·INSTALL NEW CEILING DIFFUSERS.

LIGHTS. SMOKE DETECTORS.

SPRINKLER HEADS & SPEAKERS AT1·68 •

8

114..-.r------;,m11l2

1-G8\. 5 / 8/24102 8128/liZ

072-INSTALL NEW ACOUSTIC CEILING

SUSPENSION & GRID

1-68 5 8131112 lIl4I02

070-INSTALL DOORS .. HARDWARE AT

1..$8 - 5

1·118 5 018112 11114112

0II1-COMP FINISH PAINTING AND

APPL YING VINYL I-------t WALL ~a:~R!NG AT 1-__ _

41!12 /8

8/~'1~:2 !l1~1I2/ OlIO-PART APPLY FINISH PAINT &

VINYL WALL SURFACES AT 1..$8 •

-----; 3 ~----~ AT 1..$8 - 5 COVERING AT 1..$8 -

~---------------------------------------~ 3

811 m-----"'I"!I"

Page 20: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

48 81' .f',cS/12 1112~11I2

082·INSTALL NEW CARPET AT 1-58 • 8

~68 11121f1l2

8 10161112

086-INSTALL VOICE, DATA & POWER

TOMBSTONES AT 1-58 • 8

1·68 0 1016/112 1016/112

10116111 10116/112

1I11 m-----""'lI'1'I'l , 1·68

"-11115/112 3

111171112 1·68

111181112 '.'/

1I/1~11I2 0$3-TRIM OUT NEW O$7-CONDUCT liFE ELECTRICAL & lIFE SAFETY TESTS AND SAFETY SYSTEMS APPROVE SYSTEMS

AT 1-$8·3 AT 1-58 • 1

10 11;t.11I2 101141112 1011 51112 101151

1·61/ 0/ all£iZ 3/3111

082·TIR TO NOTIFY PUBLIC & OTHER

AGENCIES OF DATE OF TESTING liFE

SAFETY SYSTEMS AT 1-58· 7

10/15112 10/151112

Location Early start

Duration Early finish

1 101221111

03·SELECT NUMBER OF TEST PILES TO

BE USED & LOCATION· 1

(example)

• Activity number • Activity description • Activity estimated duration

in elapsed wOrking days

Late starl Late finish

ACTIVITY KEY

112

Reserved Activitv Numbm

017 to 040 041 046 042 047 043 048 044 049 045 050

LAN 001 HANW7

1·68 1016/112

101161t 10/161112

Issllr #1 • not isslled Issllo #2 • Ottober 12, 1991 Issue #3 • December 3, 1991 Issue #4 • Marcb 3, 1992 i4sbllll·/i8 int work disk #304

1st Boor 68 (1-68)

NET,,~~:tA. W?::vvf:L FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchbure. Yireinia

H. J. Construction Joint Venture Lynchburg, Virginia 24506

Ralph 1. Stephenson PE PH Consulting Engineer 323 Hiawatha Drive MI. Pleasant, Michigan 48853 ph 517 772 2531

Sheet #1-68

Page 21: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

122101

122101

Terrace 68 (T-68) Interior work

Page 22: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T·68 15 11/111H12 12/10/92

062·REPAINT DEMONTABLE

PARTIl10NS AT T·68 • 15

2/16/113 3/5/113

T·68 3 12/30/92 1/4/93

GGG-INSTALL ABOVE CEILING FIRE ALARM

ROUGH WIRING AT T-68 - 3

21: /113

d

Page 23: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T·68 4LZW

o 4/2/113

FROM 00 • FINAL CLEAN • MOVE OUT

OF T·60 • PM 04101/113

412 la 41./93

T·68 0 12/10/82 12/10/112

-----------------------------------------------------------------------------------------------------------------------------------------------3-1-8-/1I~/8/113

T·68 0 1141113 1141113

~31113

\

T·6e .1.ZWl1

o 12/3/111

on·T/R TO START LAYOUT PARmlONS

AT T-68·

5/11" 2/5/03

T·68 12/3/111

076·LAYOUT DEMOUNTABLE

5 12/11/111

PARTInONS AT HIe ·5

2/5 rn 2/11/113

T·68 0 2/1111113 211111113

1811/3

8 T·68 12/10181 12/111/01 12/20/111

078·DRILL HOLES INSTALL CABLE FOR TRAY. WIRING

POKETHROUGHS AT ABOVE CEILING AT 1-68 • 8 LL·3

2/12/11;0 21231113 31121113 al16

Page 24: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T-68 4/2/Q3

2 4/5/03

101-OWNER PREPARE & ISSUE PUNCH LIST FOR

T-68 - 2 -

4/2 '113 4/5/93

T·68 l.2Ql1l

o 12/3101

102· TIR TO APPLY FOR CERTIFICATE

OCCUPANCY AT T·68 - ?

411 1113 4/13/03

T-68 4/G/Q3

5 4112/03

t03·CONTRACTOR CORRECT PUNCH

LIST ITEMS .. OWNER ACCEPT AREA AT

T-68 - 5

4/6 , .. ~ T-68

12/3/91

41 llf:

o 3, T-68

12/3/01 ~/13/03 " 4110/03

104-... PPLY FOR & " RECEIVE

CERTIFICATE OF OCCUPANCY FOR

T-68 • ?

4/1 1183 4/13193 4/1

O~iLF~~~~~~E AT T-68 • 5

1113 4119/113

T·68 5 3/18/03 3/24103

088- N ING CEILING ORID .. INST"'ll NEW

T·68 4/20/03

3 4122/03

1 UIi-.... L IIIOVE INTO

4/20/93

T·1Ie 3125/03

AREA T-68 3

4/22/93

...... .-________ -"~-----------------_I ... COUS;: :';ES AT 1-------1

OS5-INSTALl DEMOUNTABLE

PARTITIONS AT T-68 - 8

3124/93 31251 3/26/93

T·6a 4122/83

o 4/22/83

107-E TIR TO SET L ... TE FINIS H OF

41221113

T-68 3/20/03

... CTIVITY

4122 193

4/11113

T-68 4/1183

4/11113

o 4/1/93

4/1/93

Page 25: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T·Ga II 11 It 2/1/2 11118/112

T·G8 12/1/112

4 12/41112

052·REMOVE .. STORE EXISTING

DEMOUNTABLE T-e8

11/18/112

R::J!~~~o:~ :1. f---------; II 12130192

° 111181112

12/30/112

Phase 2 area 1-68 is 111 7 1 3 02 1

056-OWNER IDENTIFY LOCATION

OF ASBESTOS MASTIC ON

DUCTWORK AT T-68 -4

21 1112 121 4192

Note: Phase 3 starts after \

occupied on PM 11/11192 /. "-.. /

~ 1111°2111 1l;;:~112 llI:3/1/2 "llI2:~1I2 l1I311HI2 li;'~:2 051-TI", TO OWNER Osa·SALVA ... ", '" "-"O=5':"5.'IlR:!E':IM~O~V'I!'E-""'-A.,\\ 057·REMOVE

4 12141112

MAKE AREA T-68 STORE EXISTING EXISTING CEILING EXISTING ABOVE AVAILABLE FOR LIGHTS. DIFFUSERS. GRID .. TILE AS CEILING VOICE,

PHASE 3 SPEAKERS .. OTHER REQUIRED AT T-68 • DATA AND POWER REMODELING WORK· CEILING ITEMS AS 1-------1 4 1----' ..... \--,-1 WIRING AT T-6II· 4

PM 11/11/112 REQUIRED AT T-611 • 8

T-68 12/7/112

ASBESTOS MASTIC ON DUCTWORK AS

REQUIRED AT T-66 5

"" -

121 1112 121111112

1111 1112 11/121112 111121112 111231112 111241112 11/30H'2 12/31f"~ 116/113

",:".~ ~T'G8 11112/112

OM-REMOVE

10 111251112

EXISTING DRY WALL

~, 11127/112

OR-REMOVE EXISTING CARPET AT T·n 0

.. MASONRY T-68 - II 1214102 12141112 PARTITIONS AS

REQUIRED AT T-68 • 10 1/7/g tl71!!3

121 15/112 121211/112 1213 01112 116103

Page 26: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3 12116102

~~i.':~:O:~~~ AS REQUIRED AT

T-88 • 3

!T14JVZ /12 1'lJ16/92

T·&8 4 121141112 12117182

on·CLEAN EXISTING ABOVE CEILING

DUCTWORK WITH VACUUM CLEANING

AT T-88 • 5

T·68 12117"2

4 121221t2

063-PART INSTALL ABOVE CEILING

ROUGH FIRE PROTEC1l0N PIPING

ATT-68·4

12/1 7/IJ7. 121: 2192

T·88 12123102

06::~: C~~:;L ROUGH FIRE

PROTECTION PIPING AT T-68·4

1212 3/87. 121. 871

U, T-66

"121301112 5

116183

067-1NSTALL ABOVE CEILING DUCTWORK

AT T-88 - 5

IN WALL WORK ITEMS INCLUDE

BLOCKING CONDUIT FRAMES PIPING

T·68 II T·68 5 1171113 1110193 11201113 11261113

0611-INSTALL METAL 07()'HANG .. FINISH STUDS .. IN WALL NEW DRY WALL AT WORK FOR WALLS STRUCT TO STRUCT

I--------IS~~~D~~Q S~~T I-____ -IPARTITIO~~ AT T-66I-__ _

AT T-68 - 11

1213'!m1'll"'-----';"1 ~11I3 1 1 103

T·68 0 ___________________________________________________________________________________________ 1_2_1_41_1I~2141112

117103 1171113

Page 27: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

T.S8 5 1/27/03 2/2103

011·APPL Y FIRST COAT OF PAINT TO

DRY WALL

T·Se 5 2/3/03 2/0/0

072·INSTALL NEW ACOUSTIC CEILING

SUSPENSION & GRID

T·S8 8 2/10/83 2/18183

074·INSTALL NEW CEILING DIFFUSERS,

LIGHTS, SIIOKE DETECTORS,

SPRINKLER HEADS & SPEAKERS AT T·68 •

8

/

l.em;-------u<-!,/03

T·S8 2/10/83

5 2/1S/83

ON·INSTALL DOORS & HARDWARE AT

T-68 • 5

T·S8 2/17183

5 2/23/83

081oCOIiP FINISH PAINTING AND

APPL YING VINYL WALL COVERING AT

1------; T.68 • 5 1------

2/1mT----....,~1 103 ./ 17 13",

2/~'0~:3 2/1~m/ 08O-PART APPLY FINISH PAINT &

VINYL WALL ___ -tSURFACESS AT T-68 .1-___ --1 AT T-68 • 5 1------------------------------------1 COVERING3 AT T-68 •

1/27m""""-----'IfTII/03 2/3mr-----"""II~/·03 2/1.mr.------......,.i1 103

Page 28: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

,:88 81' 2124fi3 3111"/113

_INSTAll NEW CARPET AT T ..... 8

"­T·68 3/8/03

8 31171113

086·IHSTALL VOICE, DATA. POWER

TOMBSTONES AT T-68 • 8

T·1I8 31171113

3/2919

311 193 /'

3 21261113

T·G8 3/11113 3/1~n/'

103 312

T·G8 0 / .12l.Ui1 12/31111

OM-TIR TO NOTIFY PUBLIC • OTHER

AGENCIES OF DATE OF TESTING LIFE

SAFETY SYSTEMS

3126lw~

Location Early start

AT T .... ·?

al 6/03

Duration Early finish

T·G8 1 1JIlULt1 10122101

03·SELECT NUMBER

087oCONDUCT LIFE SAFETY TESTS AND APPROVE SYSTEMS

ATT-68·1

OF TEST PilES TO BE USED.

• Activity n ... mber • Activity de.cription

103

o 31171113

1211103

LOCAnON·l (example, • Activity eSlimated duration

in elapsed working days Reserved Activity Numbers

10122101 10122101

Late start Late finish

ACTIVITY KEY

017 to 040 041 046 042 047 043 048 044 049 045 050

LAN 001 HAN 107

T·1I8 3117113

31211111 129193

Issue #1 • lIot Issued (""ue #2 • October 22, 1991 Issue #3 • December 3, 1991 Issue $4 • Marcls 3. 1992 13shl#T·68 illt work disk #283

H. J. Construction Joint Venture Lynchburg. Virginia 24506

Ralph J. Stepbenson FE PE Consulting Engineer 323 Hiawatha Drive Mi. Pleasant, Micbigan 48853 ph 517 772 2537

Sheet T-68

Page 29: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

122/81

122/81

3rd Floor 68 executive (3-68 e) Interior work

3-868 3/3/82

4 3/8/82

054-COMP PATCH AT EXISTING T STATS,

TOMBSTONES & OTHER FLOOR

MOUNTED DEVICES AS REQUIRED AT

3-78/8 - 4

4/;:L'

3-68e 3/3/82

00 A &

4/:L 102

5 3/0/02

SUBMIT HARDWARE SCHEDULE - 5

3-68e 5 3/1 0/82 3/16/02

GOO-REVI W & APPROVE

HARDWARE

3-68e 3/17/82

10 3/30/82

01 -,. & ELIVER HARDWARE - 10

t--------1sUB~~~E~~~:L:TES 1------1

3/3/82

3/9/82

TO HM FABRICATOR -5

3/10/02

3-68e 3/13/82

3/16/82

4 3/18/82

042-PREPARE & SUBMIT FIRE

PROTECTION SHOP DRAWINGS FOR 3 -

68 E - 4

182 3/1 382 3/18/82

~-::; .,:,/:~:, '''~" 1-..,0"'1"'8'"'-CO=M=PL'"'E"'T .. E,........ 018-APPROVE NEW

PREPARE & ISSUE HVAC DESIGN & ARCH, MECH, ELECT PRICE - 4

& FURNITURE LAYOUT WORKING

DRAWINGS - 8

3/3m~---"'T"lI"I'l'" 3/1,m...------=li /92

5 3/18/82

060-INSTALL METAL

3/17/92 3/30/82

3-68e 3/18/82

015-REVIEW & APPROVE FIRE

10 4/1182

PROTECTION SHOP DRAWINGS - 10

3/18/82 4/1182

3-68e 3 3/1 8/82 3/23/82

MARK ASBESTOS DEMOLITION AREAS

& REMOVE ASBESTOS DUCT INSULATION AS

REQUIRED - 3

..-k: ...... -----....,..,..n4/82

3-68e 3/20/82

5 3/26/82

DEMOLISH EXISTG CEILING, WALLS &

FLOOR COVERINGS AS REQD AT EXEC

AREA - 4

STUDS & IN WALL WORK FOR WALLS EXTENDING FROM

1-----, STRUCT TO STRUCT 1--------1

070-HANG & ANISH NEW DRY WALL AT

STRUCT TO STRUCT PARTITIONS AT 3-

68 E - 5 AT 3 - 68 E - 5

3/16~/ft82;;--------'1'7/'-!'1 8/82 3/23/82 3/27/82 3/3 182 4/3/82

3-66e 4/2/82

2 4/3/82

SP~I~-~Lir:I:~;~M DESIGN TO

MECHANICAL CONTRACTOR FOR

FIRE ALARM CONTACT POINTS - 2

4/2/92 4/3/82

3-68e 4/6/82

2 4/7/82

066-INSTALL ABOVE CEILING FIRE ALARM ROUGH WIRING AT 3

- 68 E - 2 -

4/8/82 4/9/82

" 3-68e 3 3/24/82 3/26/82

061-REMOVE ABOVE CEILING DUCTWORK AS REQUIRED AT 3 -

68 E - 3

3-68e 4/6T82

4 4/8/82

INSTALL ABOVE CEILING SPRINKLER ROUGH IN PIPING - 4

3/25l-nr..--------.""'b-.82 4/6'\ozoor-------m

~~;~~:2 41~82// ~06~2~-~C~LE~A~N~E~X~IS~T~I~N~G'~

ABOVE CEILING DUCTWORK WITH

VACUUM CLEANING AT 3 - 68 E - 5

3/30/82 41 182

Page 30: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3-688 0 3/6/92 3/6/92

--------------------------------------------------------------------------------------------------------4-1-2-9/~9~/29/92

3-688 --,,473/82 ~ '""'06=S"""'-I=-=N=S=TA""L'"'L""'-:N"'E=W""""""

ABOVE CEILING DUCTWORK AT 3-

68 E - 5

4 192

3-688 4 3/27/92 4/1192

071-APPLY FIRST COAT OF PAINT TO

DRY WALL SURFACES AT 3-

68 E - 4

41

68. 0 3/3/82

TIR TO START OF WORK AT EXECUTIVE

AREA - 03103182

4/20/92 4/20/92

3-688 S 4/1 0/92 4/16/92

072-INS ALL NEW ACOUSTIC CEILING

SUSPENSION & GRID AT 3 - 68 E - S

3-688 0 3/3/82 3/3/92

045-PREPARE NEW PA DESIGN & ISSUE

FOR COSTING - 4

4120/92 4/20/112

3-688 5 4/17192 4/23/92

074-INSTALL NEW CEILING DIFFUSERS,

LIGHTS, SMOKE DETECTORS,

SPRINKLER HEADS AT 3 - 68 E - 5

,... ~ 3/3/92 3/6

046-APPROVE NEW PA DESIGN AND

PRICE - 4

4/20/92

3-68. S 3/9/92 3/131 92

068-INSTALL NEW ABOVE CEILING

CONDUIT & WIRING FOR PUBLIC

'\ ADDRESS SYSTEM & SPEAKERS AT 3 - 68

E - S

4/24/92 4/30/92

~ .. 5 4/24{92 4/30/92

OlIO-INSTALL NEW ACOUSTIC TILES AT

3-68E-5

2,,4/24/92 4/30/92

3-68. 4 117/92 4/22/82

5/7/92

3-680 4 4/23/92 4/28/92

3-680 5 4/29/92 5/5192

o 3/13/92

073-T/R TO PROVIDE FURNITURE LAYOUT

- MARCH 13, 1992

3/92 41 192

OBO-INSTALL DOORS & HARDWARE AT 3-

68 E - 4

083-COMP FINISH PAINTING AND

APPLYING VINYL

084-INSTALL NEW CARPET AT 3 - 68 E -

1-________ -1 WAL; ~:EER~N: AT 1------------------------------------4

4/22/92 4/2 192

4 ~688 411m2 4/22/9(" 3~2~/92 6

3/30/92

081-CONT(1)083-APPLY FINISH PAINT

& VINYL WALL COVERING AT 3 - 68

E-4

079-DRILL HOLES

~11"'"----"""'lr'7'lll/92 4/1

3-688 3/13/92

076-LAY OUT TOMBSTONES AT

68 EE- 6

4/3/92

.,:,/ 3 -

4/10 192

FOR POKE THROUGHS AT 3 - 68

E - 6

IY2 4/2' 192

4/29/92 5/5192

3-688 3/31/92 /

3-68. 4/7/~ 4/29/92

4 5/4/92

082-ROUGH IN CONDUIT FOR

TOMBSTONES & SEAL HOLES AT 3-

68 E - 6

4/21/Y2 4/281 92

085-TRIM OUT NEW ELECTRICAL & LIFE SAFETY SYSTEMS

3-68. .uaw.

AT 3·68 E - 4

086-T/R TO NOTIFY PUBLIC & OTHER

AGENCIES OF DATE OF TESTING LIFE

SAFETY SYSTEMS AT 2-79168 - ?

5/12/92 5/12/92

Page 31: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

3·IISe 5/1182

:I 515/02

101·BALANCE HVAC SYSTEMS AT :I - 68

E - MAY HAVE TO BALANCE WITH

OTHER AREAS OF BUILDING·3

5/8/0 5/12/82

5/6102

3·118. 1 5/5/02 16102

5/1

/

080-CONDUCT LIFE SAFETY TESTS AND APPROVE SYSTEMS

AT 3 - 68 E-1

3·68. 5 5/13/02 5/10/02

102..fINAL CLEAN & MOVE OUT OF 3· 68

E-5

51 102

Location Earty start

3·6S. 5/20/02

2 5/21/02

1_ #1. 1 /I; 3 • not used Issue #4 - MardI 3, 1992 145111#3-68 3e int work disk 304

3·68. 4 5/22/02 SI28/02

10S-CONTRACTOR CORRECT PUNCH

LIST ITEMS & OWNER

iDS-OWNER PREPARE & ISSUE

PUNCH LIST FOR 3· 68 E - 2 ACCEPT AREA AT 3-

1-------1 68 E ·4

5/20182 5/21/82 6/22102 5/28/92

300 Floor 68 executive (3-68 e) Interior work

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchburg, Virginia

H. 1. Construction Joint Venture Lynchburg, Virginia 24506

Ralph J. Stephenson PE PE Consulting Engineer 323 Hiawatha Drive Mi. Pleasant. Michigan 48853 phSl7 772 2537

Sheet 3-68 e

3·6S8 1illn

o 313102

3-6e8 3 , 3·6S. 5 313102 3/5/02 'i120/02 6/41112

3·688 2

104·T/R TO APPLY i0G-APPLY FOR & 107·FCL INSTALL FOR CERTIFICATE RECEIVE OFFICE FURNITURE

OCCUPANCY AT 3· CERTIFICATE OF AT 3 - 68 E - 5

5126/112

Duration Early finish

68 E t--___ -ioCCUP::~Y.~OR 3 -I-----i

5/26/02 5/26b/"'0..------S"'/"..!.28/112 5/20/112 6/41112

6/6112 6/8/112

106·FCL MOVE INTO 3 - 68 E AREA· 2

6/51 2 6/8/02

3·68. 1 1illn 313102

03-SELECT NUMBER OF TEST PILES TO

3131112

BE USED & LOCATION - 1

(exampl.)

3/3/02

• Activity number • Activity description

Activity estimated duration in elapsed working days

Late start Late finish

ACTIVITY KEY

Reurycd Aetiyjty Npmhcn

017 1<>040 046 047 048 049

045 OSO

LAN 017 HAN 108

Page 32: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1/01

!lOl

lst Floor 79 (1-79) Interior work

1-7!I ~

o 31310

042-TIR TO ISSUE 14 V' UPDATING - 03I03/!l2

043-AIIEND FIRE PROTECTION SHOP

311 2/112 :s11

DRAWINGS TO INCLUDE CODE

COIIPLIANCE FOR ATRIUII - 1

'.2 3117/,,2 31171U

~ 1-711 ~/3I112 5

3111/112

044-IIAKE PENETRATIONS

THROUGH ARTIFICIAL SLATE

PANELS (ASBESTOS?) - 5

31 1 If.</ all IU

1-70 3131112

1 3/3/112

412

04S-PREPARE NEW PA DESIGN .. ISSUE

FOR COSTING - 1

!I Vii! 4/20/112

1-711 3/3/02

4 316/!12

APPROVE NEW HVAC DESIGN .. PRICE • 4

1-711 3141112

1 3141112

046-APPROVE NEW PA DESIGN AND

PRICE 1

4/21/02 4/" 11112

1-70 al2§l.U

o 3/26/Q2

TIR TO START OF INSTALLATION OF

ELEC ROUGH IN FOR TOIIBSTONES -

03/26/02 ??

3/2 1112 '3/2 1112

1-711 ). .aL3LU 31~~

042-TIR TO ISSUE 14 UPDATING - 031031112

067-INSTALL NEW ABOVE CEILING

CONDUIT .. WIRING FOR POWER. VOICE ..

DATA. PUBLIC ADDRESS SYSTEM .. SPEAKERS AT 1-711 -

5

41221112 '41281

1·7\1 '\

n

3/111112 3112/!l2

1-------------------; AT H!I -4 c£;j:~~~=RK \

01S-REVIEW .. APPROVE FIRE

PROTECTION SHOP DRAWINGS - 1

3118192 31181

3120111 51n

1·711 3151112

2 316102

D16·DISTRIBUTE SPRINKLER SYSTEM

DESIGN TO IIECH CONTRACTOR FOR

FIRE ALARII CONTACT POINTS - 2

3/111/02 312 1112

~~' •• '. 1·70

"'3110102 5

3/16/n -.....

047-COMPLETE INSTALL ROUGH IN

FOR SPRINKLER PIPING· 5

3/1 IViI! :Sf 102

~ 1·711 31111112 31111112

\ 068-INSTALL ABOVE CEILING FIRE ALARM

ROUGH WIRING AT 1·7\1 • 3

3/231!12 3/25/8

Page 33: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1·711 3131112

4 3161112

D78-COMP FINISH PAINTING AND

APPLYING VINYL WALL COVERING AT - 1·711 - 4

\121112 "''' 1102

1-711 3101112

2 3110182

081·TRIM OUT NEW ELECTRICAL & LIFE SAFETY SYSTEMS

AT 1·711·2

1·711 5 4181112 41141112

OM·INSTALL VOICE, DATA & POWER

TOMBSTONES AT 1-711 - 5

1·711 0 41141112 41141112

51151112 51151112

51,10 511 "'Ii' 1-711 • '" "',.n ' ''',''/, •

3131112 ~ill1112 3111/112 1Lal12 313112 ;::=;:08=2=-."'TI;;:R"-;;;'TO=-=N"'0"'n"'FY='" 08S-CONDUCT LIFE 042-TIR TO ISSUE IN

PUBLIC & OTHER SAFETY TESTS AND UPDATING - 031031112 AGENCIES OF DATE APPROVE SYSTEMS

1·70 3131112

1-711 0 41141112 41141112

018-RE·KEY LOCK CYLINDERS

NECESSARY FOR OF TESTING LIFE AT 1·711 • 1

SAFETY SYSTEMS AT 1·711

1-________________ -; OWNER'S NEEDS· 2

\126!-:1::':!l2::------=~ ~

048·RESOLVE REVISIONS TO

CARPET COLORS • 0 (USED TO SHOW ES r-------I

& EF)

4 120102

070·INSTAlL NEW CEILING DIFFUSERS,

LIGHTS, SMOKE DETECTORS &

SPRINKLER HEADS AT 1-711 • 4

312,milr-------,'I7'rllI02

1·711 4181112

15 41281112

on·INSTAll DEMOUNTABLE PARTITIONS &

DOORS AT 1-711 • 1$ t------I

4171112 4181{12 412 1112

1·111 3111/112

41211111

4,~k~--------.,,~'1I2

~~3;:2 6 3110/02

Q06-PREPARE & SUBMIT HARDWARE

SCHEDULE· 6

412 31112 41301112

10 5112/112

086·CLEAN EXISTING CEILING GRID a. INSTALL NEW

ACOUSTIC TILES AT

5161112

1·111 3111/112

DOlI-REVIEW & APPROVE

HARDWARE SCHEDULE &

II 31171Q2

SUBMIT TEMPLATES TO HM FABRICATOR·

5

5111112 Sl71112

1·70 2 5113102 5114/02

087·BALANCE HVAC SYSTEMS AT 1·10 • 0

MAY HAVE TO BALANCE WITH

1-10 • 10 t-------I OTHER AREAS OF BUILDING·2

412m-----"""I!~1:t,102 511m-----"""I!SmI1l2

Page 34: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

10 3/31/Q2

012·FAB ., DELIVER HARDWARE - 10

5/8/112

1-7. 5 5/15/112 5/21/t2

Oaa.FINAL CLEAN ., MOVE OUT OF I·N •

5

S/15~or-----""""'I/Q2

o 313/112

OIIO-T/R TO APPLY FOR CERTIFICATE

OCCUPANCY AT T'711 • ?

5/281112 51 8/02

2 5/26/82

0811"()WNER PREPARE., ISSUE PUNCH LIST FOR

1·N • 2

S/2.lor.or------r"d,'1I2

Ba,n. "dM'! Ngmbm

018'0040 050

LAN 001 HAN lOS

1·711 3 3/3/112 3/5/112

l02-APPLY FOR & RECEIVE

CERTIFICATE OF OCCUPANCY FOR

1-711 • 3

51281112

1·711 5/27/82 " 6/1/112

101-CONTRACTOR CORRECT PUNCH

LIST ITEMS ., OWNER ACCEPT AREA AT

I-N - "

5/27mor-----"""IITI,I'12

Issue #1 • Od;)ber 9, 1"1 Issue #2 - <ktober 22, 1')'1 Issue #3 December J, 1991 l_e #3 - mOllltored 03103192 Issue #4 - March 3, 1992 14sht#1-79 disk 304

" 6/5/112 103-FCL INSTALL

OFFICE FURNITURE AT 1-711 - "

6/2·mr------"""II7II·!l2

1-711 6/8ft2

1st Floor 79 (1-79) lnterior work

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchburg, Virginia

H. J. Construction Joint Venture Lynchburg, Virginia 24506

Ralph J. Stephenson PE PE CODSulting Engineer 323 Hiawatha Drive MI. Pleasant, Michigan 4885 3 pb 517 772 2537

Location Early start

Duration Early finish

1-711 1.2LWi1

o 10/22ftl

• Achvtty number

Sheet #1-79

03-SELECT NUMBER OF TEST PILES TO

BE USED ., LOCATION - 1

(examplo)

• Activity doscription

10122/11t

Late start

• Activity estimated duration in elapsed working days

101221111

Late finish

ACTIVITY KEY

2 6/t/1l2

o 6/t11l2

104-FCL MOVE INTO I-N AREA· 2

10S-E TIR TO SET LATE FINISH OF

ACTIVITY

Page 35: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

@!iV

Mr. Steve Greene, Assistant Vice President First Colony Life Insurance Company PO Box 1280 700 Main Street Lynchburg, V A 24505

Ralph J. Stephenson PE PC Consulting Engineer

October 25, 1991

Re: Issue ##2 network models of existing building renovation - First Colony Office Building, Lynchburg, Virginia - rjs project 91:37

Dear Steve:

Enclosed are seven network models of the various geographic areas to be remodeled in the existing building renovation. All are labeled issue #2, dated October 22, 1991 and were updated from the issue #1 networks prepared in our October 7th and 8th, 1991 sessions.

Included are the following:

• Sheet LL - issue 2, dated October 22, 1991 - move in date - pm January 7, 1992

• Sheet 3 - 79179 tie - issue 2, dated October 22, 1991 - move in date - pm March 30, 1992

• Sheet T - 79 - issue 2, dated October 22, 1991 - move in date - pm April 8, 1992

• Sheet 1 - 79 - issue 2, dated October 22,1991 - move in date - pm April 15, 1992

• Sheet 2 - 79168 - issue 2, dated October 22, 1991 - move in date - pm May 7, 1992

• Sheet 1 - 68 - issue 2, dated October 22, 1991 - move in date - pm October 27,1992

• Sheet T - 79 - issue 2, dated October 22, 1991 - move in date - pm April 21, 1993

These networks have been left unassembled as we discussed on the phone the other day. However I

have stapled a small key plan to each set of diagrams and the paste up process should be relatively

simple.

Once you have all had a chance to go through the diagrams in detail I'm certain there will be some

revisions and additions. The total project end date seems to be considerably later than I should think

it would be on a project of this type. However I have taken the material sent to me and converted it

1

kL2-

Page 36: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

Ralph J. Stephenson PE PC Consulting Engineer

October 25, 1991

as well as possible to what is considered to be the desired sequence of work. It would be well to

carefully review the dates, logic and durations with your construction team before officially issuing

the diagrams.

Notice the summary network model is not included. After trying to accommodate some of the partial

moves and intermediate dates in the summary plan, I decided to wait until we meet again to

complete this network model to insure accuracy.

If you do need the summary sooner I can construct it from the detailed diagrams already prepared.

However I would prefer to complete it with you, Phil and Don.

If there are any questions please call or write.

Enclosures: Network models Sincerely yours,

Ralph J. Stephenson, P. E.

2

Page 37: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

2/91

2101

o I 01el9 I 10/819 I

OWNER .. CONTRACTOR RESOLVE STATUS OF

19 FIRE ALARM SVSTEI'1

II fl Sill I 11/25191

.wDlJJ. 10~IlI/WDI91 10I~191

10

T /I TO OCTOIER O. PREPARE It. SlllMIT 1991 SIf.'P DRAWIIIGS FOR

EARL'!' DELlIlERIES

101819 ~0I1I191 10111191

o 1018191 I 0181 Il I

PREPARE .. Sl.llMIT HOLLOW !'lET Al SH:lP

ORAWII'GS

91 II/Mil

0 \ I 018l1l I 1 O/elO I

PREPARE .. SUBl'tIT HARDWARE SCH£OULE

1018191

l0/3I/1l1 101311111

11125101

o 10/8/91

11125101

° 10/11191 10111191

REVIEW .. APPRtlYE SHOP DRAWINGS FOR

EARL'!' DEL IIIERIES

o 1018l1l1 10181111

FAe& DEllYEREARL'I' o:wSTRUCT'lON ITEMS

o 1018101 1018191

E TlRTO SET LA,TE FINISH OF ACTI .... ITY

10/11/91 10111191 10 91 10 III 10181111 1018191

10/8/1l' o

1018191

RFtlIEW It. APPROY[ HOUOW"ETAlSIf.'P

DRAWII'GS

11/8101 1118191

10/8191

FAII& DELIVER HOUOW"ETAl

o 1018191

FRAtES & DOORS

11~1I91 NOI

\10 0

10/elOI IOI8l01/IONIlI 10NIII

RFtlIEW .. APPROYE FAIS&DELIVER HARDWARE SCHEDl.l.[ HARDWARE .. SUDMIT TEI'1PLATES

TO KI1 FABRICATOR

1018191 1018l1l1 91

10Ie/91

1018191

o ION91

PREPARE & SUBttIT FIRE PRIITECTIOII SHOP

DRAWINGS

10131 III I 013111l I

Page 38: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 10f8191 10f8191

II/Z$l9H I/Z$l9 I

101e/91 DISTRIIIUT£

o 10f8191

SPRINKLER SY$TEM DESIINTO

H£CIiANltAL OJIf'I'RACTOR FOR FI RE

ALARM CQIIIT' ACT PDINrS

o 1019191 10191111

REPAIIIIT' DEI1CWT' ABLE PARTITIONS AT U - 0

121191111

.....

12/191111

o 10/W9I

PART INSTAU NJ(N[ CEILIN& FIRE ALARM

ROJGH WIRINI AT I.L-0

~ 11/25191 II f25111 1 11/25191 1If25191"-....

1018191 10~91/'0/23191 10/~1I~0I2 ... 419."..:,..I-:-=~~~1~0I~iIl191 ~IO/:29l91 10~91 REVIEW r. N'f'fl(NE ;':'P"=NlT--III-"-ST.;A-U-NJ(N"""-'""[;;,I COtf> IIiST ALL AIIOYE Cll'tP INSTAU N!J(NE

FIRE PROTECTION StlllP CEILING AOLGH FIfI£ CEILINS ROUI8 FIRE CElLINI FIIIE ALARM

101S1 II

DU,WINlS PROTECTION PIPING AT PROTECTION PIPIIIi AT AOLGH WlltlNI AT U -

IOl3l1lH 10131 91 /'

U-O LL-3 2

10 1/111

" 10/31191 11 4191

\ 1112=519 I 1112t1191

Page 39: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

Q

1019/91 1019/91

---------------------------------------------------------------------------------------------------------------------------------12-,-1-9/~9~2/1~91

101lOl91 o 10130191

1212191 Q

1212191 PART INSTALL NEW CElLI .... DIFFUSERS,

LIGHTS. St10ICE CETECT'ORS.

SPRIN<lER HEADS &. SPLUERSAT LL - 0

121 12191/ 12112191

1~91

1213191

1 211 1al'91

121:191/ V COI'IP INSf IU.L NEW

C£ILlNG OIFf'U9ERS, L IOHTS, SNOKE

DErECTORS. ~INI(LER HEADS &. Sf£AkERS AT lL - 5

1211219, WIISI9

Q

1219191

12/19.191

~

o 1212191 12/219 I

INSTll1lLLWDRK AT LL

12(10191 /'

-0

Page 40: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 12J3I1QI 12/311111 121311111

1 12131/; I

FROI1 FINAl CUAH &. OWNER PRePARE &. MOVE OUT OF LL - AI'! ISSUE I"lIIICW UST FOR

12131181 U -1

1213111i11 121311111 121311111 12131191

1121111 o

112191

i IR TO APPLY FOR CERrIFICATE

OCCUPANCY AT

1/6192 1/6192

112/92 :2

113192

CDII'TIiACTlR CORRECT PIMCH LIST ITEI'1S ... OWNER ACCIiFT' AREA

AT LL - 2

112192

1/2191

APPLY FOR .. RECEIVE CER'TIFICAiE OF OCClPANC¥ FOR

1/6192 Tl. I 6192

", 1

1I6I1I2

FCL INIT;.u. VErI)ING nACHINES I/I,T LL - I

1/6192

12/19/91

116192

5 12/26191

1 111192

FCL I1D'o'E INIl) LL (111£1/1,-1

117/92

o 12/26191 12/26191

a..EAN EXISTING 1WAIIa: HVAC CEILING GRID &. S\'STi1'lS Ai U - 0

IIiSTALL fEW HAY HAVE 10 kANa:

E TIR iO SET LATE FINISH OF ACTIVITY

111192

o 12/26191 121261111

CONDUCT BAS TEST AT Ll - 0

-------------------:::...:~-----------------_tACOUSTIC TILES AT UI--_--IWITHOTI£I MEASOF ..... ___ -I - 5 BUILDING

12118191

INSTALL 0E11C1lffUBU PAR'TlTlcrtS Ai LL - 0

12/19191 12/111191

'"

1226191 12/27/91 12 27191 1212791 12127111

Page 41: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

121!719 I :2

12/3<1/91

FIliAl. ClEAN" HOVE OUT OF LL -:2

7" 12 3<1/91

Page 42: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

10

o IIVgl I/V91

D 1/2191 1/2191

o 1019191 1019191

REltOVE &. STORIE ElCISTIII&

DErt::urr ABLE PMTITIO'IS AS

REQJIREDAT U·O

1019191

IIMl91

o 1019.191

.IINIII

\

10/9191 '" 10114191 OWNER IDEHTIFY

UX'ATIa.OF ASBESTOS HASTIC 011 DUClwtRK AT LL - '"

1019191

10":'91/'01919 I

10/9191

rO~gl"101W91 91 \ 10191

\0 ./' 10(9J9~ 10(9J91

,~

10114191

'" 10"4191 Till "TO OWNER I"IAKt

AREA A .... AIUd!LE FCR RfJ10DEl.Ir«! WORt( •

10108191

.... "'91 I D19/9 I 10~

S ..... VAIIE& STORE ElUSTINB LI8IfTS,

DIFFUSERS, SPEAKERS &. an-EII CEILINB

"EltS M. R£QUIRED tilT LL ·0

1/91 1019/91

o '0/9191

RfJ1I1VE ElIISTIM& T STATS, TOtt:'JSTllNES'&' DTHERFLOOR rtQUIITED

..... 1IfJ10 .... DISTIllS "\ REltO'IE ElCISTING

CEILINB BRIDt. TILE ABDYE tElLING VOICE, AS REQJlRm AT LL - (I DATA All) POWER

""IRIN! ~T LL - '"

10/'1/" 10r~gl

1019111' REIOVE EKISTIr.B OR\' WALL.&.rt~ PART'ITICRS ... S

\" ... " 11119191

\ 2 10/919".. IOflO/91

REltO'IE ElCISTING CARPET" AT LL - 2

DEVICES M. REQUIREO 1-------1 ATU-O

R~IR£I)AT U ·0 1-----;

III il91

10115191 ......... ,. 7\ ASBESTOS HASTIC ON

OUCTWOI<:!< AS REQUIR£D-5

10I1S/91 10121191

1111"" 1116191 11(6191 11/10191 Ilnl91

~''{1 "" "';;'" CONPL.ETE COtiTRIX:T I1ISC I1ASONliIV ITB'lS

ATU -5

II/HIt" III:l :vg,,,

Page 43: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

10t.l2J01 101;''.,111/ RD'IDYE IIDOYE

CEILI.a DUC'T~ AS REOJIRID AT LL - 2

/101:1 5]9 I 1012819 I

10122/01 10I:iv91~10129l91 11';'01

CUNI OIISTIIIG INSTALl. NEW A80YE A80YECEILII'f> CEILING ELECTRICAL

tu:TWBRIC WITH CA8LE TRAY .AT LL - S

o 11/<4191

PART INSTALL NEW Ir«NE CEILlI'f>

DUCTWORIC AT LL - 0

3 11(7/91

COHPUTE IIIST ALL AlltNE CEILlI'f>

DIJC'I'W(R( AT LL - 3 ----I VACWn a.EAHII'f> AT 1------1

LL ·S

11/4'9' I INIal Ii/SIIII 1115191 11(7/01

" 0 ~ '11'41111 11/<4191 1115191 11111191

10/281111 I o 129J II 1

PART INSTALL IInI COHP INSrAU. IIEW Ir«NE CEILlI'f> ASOIIE CEILING

CQlDJIT 6. WIRIII6 FOR CON)UIT 6. WIII .. a FOR ---~.-------------------------IPOfIER. VDICE6.D4TA 1------1 POWER. VOICE6.D4TA I---~:---____________________ _

NO PU!LIC AOORESS #IR> PUlLIC ADDRESS

II

o .;':"':':"::'-.lo-__ ~I.;;;O/;...;101I1I

PARr IHSTALL METAL STUDS6. III WALL ..... FORWALLS EtrrEliDING FROM

STRUCT TO STRUtT AT LL -0

91 1118191

"'-

IN WAU ITEMS INCLUDE

-BlOCKING -CONDUIT • FRAl'ES • PIPING

o 10/10191 10/10191

;';"';:'PUI.t"-"-HA-Jl6""'6.-""FI""N~ISH~ HEW DR" WALL AT STRUCT TO STRUCT

SYST£M AT LL - 0 SVSTEtI AT - :I

1I/2OJ91 11/20191 11120/91 11126191

6 111819 I It 1151111

COMP IHST ALL METAL STUDS 6. III WALL WOIiIK FOR WALLS EXTEIIDING FROM

STRUCT TO STRUtT AT LL -6

1118191 " 15191

" 111111191 11122191

CDMP HAilS &. FINISH IIEW DRY WALL AT

PUl.tITI~ATLL-O~----------------------------------_____________________________ ~ STRUtT TO STRUCT PARTITIONS - S

11(11119 I I 1/11119 I 11/111191

~ 0 0 U/11JOI 10117191 10/17/9~·0/17J91

~~---------------------------------------------------------------------------------------~ 1112510 I 11125191 1I/~0 I 1I/:r.s191

Page 44: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

2/2791

11125/91 1 1126/91

APPt.'t FIRST COAT OF PA-IIIT TO DRY WALL SURfACES AT LL - 2

11(26/91

1212191

12/2/91 o

12/2191

CO"'" NISI' ALL NET IoL STUDS ... III WALL WtRC FOR WALLS EmHDl1'G FROM

STRUC'T TO CEILIIIG AT U -0

-'" 213191 1213191

12/2/91

PART IIIST ALI. I'1ETAL PART IWCB &. FINISH Sl'UDS &. III WIoU NEW DRY WALL AT WORI( FOR WALLS STRUI:T TO CEILlN8 EXTEHOII'G FROM 1-_____ --IPARTIlICJiS AT LL - 0

Sl'RUC'T'TO CEILIII8 II.T LL -0

12~/91 12 1213 91 1213191

3/ 12/2191

12/2191

1212191 0/

12/2/91 1213191 5

12191"

121:

CO,... HAilS&' FINISH INSTAU DOORS &. IIEW "RV WALL AT HARDWARE AT LL - 5

STRUI:T TO CEILlII8 PARTITICWS AT U - 0 -

:191 1213/91 1213/91 1219111

~ 0 1212191 12/21"""'-

PART APPL't FIIIISH V PAINT &. YIIWI. WAt.L COVERIIIS ATlL - 0

12/10/91 12/1Oi91

Page 45: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

""U/l0191 .'" COrP mUSK , ... ltrTllS

-,~ '" 12113191 12/16191

/ lUI

IMST AlL NEW CARPET /III) APPUIIS YINYL 101 U. ~3 WAlL ONERIII& - '"

l:l/n/ill 121t6l1l1 12118191 )/91

'" 2 12/171ti1l 12/t6JIII

TRII'1 OUT MEW ELECTlUCAL .. LIFE

SAFETY S'I'STEMS "T U. - 2

121231 91 12/24191

o 12/18191

IMSTM.~ WIt(, D"TIo So POWEll TOI'BSTONES

AT LL - 0 12/18191

12/21/91

12127/91 121211111 ,/ 12/1e/91 12I1e/91

CIIMDUCT LIfe SAF£T'f TESTS AICl APPROYt

SYSTEMS AT U. - 1

12126191 121': res..-91

0 12/let91

12/27191

112191 1/~91/ /

T IR TO NOTIFY PlI!I.IC .. OTHER A&EMCIES a: DATi Of' T£STIIS LIFt SAFETY S'I'STEMS "T

LL -7

12/261111 12/26191

(edllstert Dlfttlon Eerlll tlllith

I ~ 11/15190

03-sELECT IIUt1llER OF TiST PILES TO Be

USED &. LOCATIOII - 1 (1IlIIIIftPI~

11115190

• ACtlvltv IWl"*er • ACtlvltv dlKr1ptlan • ACtlvltv eaUmeted dntlen

In 11",,881:1 WllI'klnll dIU'

"'.alert Lete tlnl.h

.6&g,RI

• 7 I"ftI!I 6tiIbRJ "'1l1l'i __ ·1·~9.1~1 t ~Lll.llt wm <lilt 203

12/18/111 I

12/27/91 I 2/27191

NETWQRI( MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION LynchbUCI. Virainia

B. J. Coutruotl.oA Jotm VeAta:r. L,.~ Vil'~. 24506

Ralph J. S\.ephenlcm PE PE ConsultJnQ EngIneer 323 HIawatha ~ MI.. P1eesent. N1c1'Ilim 48653 ph 517 n2 2537

Sheet #LL

Page 46: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

191

191

il 7-79

o 10/0191 1018191

OWNER & CONTItIoCTOR R£SIl..YE STATUS or

79 FIRE ALARM SVSTm

215192

1018191 10~(I~ OWNER RESa'iE a8 ELEVATOR REtALL

SVSTEl'I DESISN 101819 I

21'51(12

o 1018191

215192

~~ 92 215192

~ 10~1/ 10111191 1~191 1018191 ° 1018191

1(1

T IR TO OCTOBER 8, PREPARE" SUIll'tIT 19'1 SHOP DRAWIII6S FOR

EARl" DELI'iERIES

10181(11 1018191 1018191

~ 1018191

o 1018191

PREPARE &. Sl81IT HOLLOW METAL SHOP

ORAWII'GS

12 215192

0 \ 10/0191 10181(11

PREPARE &. Sl811T HARDWARE StHItU.E

1018191

1120/92 1/20192

REVIEW &. APPROVE SHOP CQAW1"GS FOR

EAIL" DELIVERIES

10111191 8/91

1018191 o

1018111

REVIEW r. o\PPROY£ HOLLOWI'IETAL SHOP

DRAWII'GS

2(5)92 2151(12

101Ell91

REVIEW IS. AI'F'1mYE HMDWAR£ SCHEDt.lE " SUI MIT TB1PLATES TO.., rAIIRICATOR

0

IOlEll91 1018191

o 1018191 lOlEll91

FASa. IIELIYEREARLY awsnaJeTlON ITEt1S

101eJ91 o

1018191 E TlR TO SET LATE

FINISH or ACTIVITY

91 10/0191 101eJ11 10f81(l1

1018191

rAS&DELIVER HOLLOW M£TAL

o ION91

FRAMES & DOORS

~r.: '92

1018191

\21": 92

FAil & DELIVER HARDWARE

1018191

1018191

(I

1018191 1018l!U

PREPARE & SUl!lttIT fiRE PROT£CT11Jt SHOP

DRAWINGS

92

Page 47: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 1018191 1018/91

-------------------~--~9~~92

o 1018/9 I 1018/91

DISTlUIIUTE SPRINKLETC S'r'STE11

DESI&IITO nEOfANICAL

ctWT'RACTOR FIR FIRE ALARI1 CCIfT ACT

POINTS

e 1219191 12/18191

REPAINT DEI'DfTAI.lLE PARTITIONS AT T-79

-II

o 1I1~2\ 111519

PART INSTAll A!IOYE CEILlN& FIRE ALARI"!

RCU3H WIRIN& AT T-79 - 0

:2

:-::-.

1018191

215192 215192 215192 21519~

10~91/'110J92 1/1:"9/'/16192 112~J92 ~1I22192 112!,9:Z r.P::-:AI!T-=-=INSt=A:7Ll:-:":;lJ(N::-:::-:':'"[ -t r-COtt,---,-P-INST--A-Ll-;lJ(N--E.... r-COtt===P"':':INST=A~Ll:-:-:I>I!tCN=-::E:-1 REVIEW S. APPROVE

FIRE PROTECTION SHOP DRAWINGS

92

CEILING fn.ClH FIRE CEILING fn.ClH FIRE CEILIII8 FIRE ALARI"! PROTECTION PIPING AT PROTECTION PIPING AT RW6H WIRIH& AT

T-7g-4 T-79-4 T-7!1-3

1/2lI92 1/:24192 1119192

" \

Page 48: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 12/u5l9 1 12/1e191

-------------------------------------------------------------------------------------------------------------------3-/~--9~(~92

o 11.24192 1/24192

2f20192 <4

2/25192 PART INSTALL NEW CEILING DIFFUSERS.

LlMS, SI10KE mECT'O!S.

SPRlflKLER II:AOS& SPEAKERS AT T-19-

<I

31 'e 92 / 5/11/92

~

o 312192 3/2192

3/1el92q-"-e/-'-2---------------

21l!619:2 3J2V V 2119192

I)

2(19192 COif" INn,t,LL NEW CEILlII6 OIFFlJSERS,

LIGHTS. SNOKE DErECTDRS,

SPRINKLER HEADS ... SPEAKERSAT T-N-

<4 $11219:2 3,111

INSTLMILL~AT T-19-0

Page 49: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 3/21/92 3121192

1 3/21/g2

FRIl'1 FINAL CLEAN" MOVE OLIT Of T-79 -

1.1103127/92

7/92 3/21/92

OWNER PREPARE &. ISSUE PUfIICtI LIST FOR

T-79 - I

3/21/fJ2 3/21192

I/:2Igl o

112191 T IR TO APPLY FOR

CERTIFICATE OCCUPANCY AT T-79

41 1/92 411/92

3130/92 2

3131192

COIITRACTOR CORRECl PUNCH LIST ITE/'1S &. OWNER ACCEPT AREA

ATT-79-2

3130192 31311

1/2191

APPLY FOR&'RECEtVE CERTIFICATE OF

OCCUPANCY FOR - T19

411192 471192

INSTALL DEI10UIIT ABLE PARTITIONS&. DOORS

ATT-7'.'I-IO

3 17/92

- .... 1

4111!il2 fClINSTALL OFFICE

FURHITURE & V£IIDIMl I'IACHlflES AT T - 79 - 1

41:2192 1

41:21112 FCL I"IOVE INTO T-19

AREA-I

411/92 411192 41:2192 41211]2

2 3118192

3 3/20192 3123J92 3/24{92

CLEAN EXISTI"B eALAlCCE HV~ CEILING GRID&. S'lSTEttS AT T-79 - 0 IIIST ALL flEW MAY HAVE TO IW.ANCE

4121!il2 o

412/92 ET/RTOSETLATE FINISH OF ACTIVITY

41:211]2 41:

o S/24{92 3/2419:2

CDNOUCT BAS TEST AT T-79 - 0

ACOUSTIC TILES AT I---~ WITH OTIER AREAS OF f------1 T-79 -3 SUILDINJ- 2

'3 20192 31 92 '3 24{92 31 92 3/2519:2

Page 50: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1125192 2

"S126I92

FINAL ClEAN & !'lOVE OI1l'OFT-79-2

Page 51: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

L,' ! 7-71

5 4 12Ngi 12/6191 12I:Bf91 12/27J .. 12130191

IIE110'IE &. S'I'l:Jl:E OWNER lCEKTIF¥ OWNER ABATE [)IISTINS 0 I..OCATICfi IF ASBESTOS "ASTIC OM

DEtnM'"ABLE 12/6191 1216191 A!lBESTOSI'IASTIC OM DUCTWORK AS PWlrITlCftS AS IllCTWORK AT T~?1iI - 1-----IREOUIRED AT T-?9 - 51-_ ......

REQUIREb AT T-?g - 5 113OJ92 1130192 ,

" " " " \"" ",."" .L2£.1lIJ.. 12/~J9I/'2t21gl 12/~9I"'1219191 I 2J!.g 1/,':U231gl 12ri.t91

12 III 116192

12

I,)

1/2191 1/2191

o 1/2/91 1/2191

TIR70 OWNER t'lAJ(£ SA\.VAGEISo STORE REI'1OYE [)IISTlN' IIE110VE [)lISTING AIlEA A .... AILAILE FCR [JUSTING lIGHTS, CEILING GIIIO ISo TILE ABOVE CEILlM6 \IOICE.. REI1OD£lING WORK· DIFtI..ISERS, SPEAK£RS Na REQUIIiID AT T19 - DATA N.:J POWER

12101(91 &.anERCEILlN& 3 WlRINGATT-J9- 3 r----------------fTEI1S Na REQUIRED AT

91 12I2I9~2t21gl

12t2111

T-?9 -5

12/6191

2 1213191

1219191 I 2f1019 1

10 12/419 I 12/17/g1

REI10VE [)lIST INS T REt«:NE elUSTING DR'r' ST' ATS, TOI'8STCN:S &. WAll &. rt~

\

"\ 1~1J92

4 1:l/le/gl 121:2l191

lEI10VE [)lISTING CARPET AT 1 -701 - 4

O£'llIO!S Na REQUIRED 1-------1 REQUIRED /l.T T-?1iI - 1------1

\

OTHER F~ 1'I0UHTEO PNn"ITIIW> AS

ATT-79- 2 10

1/141g2 1/15192 1/16192 I/29Jg2

\ 12t21gl

e 12111191

REI'D\'E LIEBERT t.nfTS ATT-79- B

1/17/92

12/12191 5

1211&'91

REI1INE ACCESS F~ AT T-19- 5

92 2 "'92

1130192

o 12/:2319 I 12/23191

CCliPLETE CXJmll:IX:T I1ISC t'lASOMR't fTEI1S

ATT-19- 0

2 92

Page 52: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

Ihl92 I~~/ A£I'IMA8OVE

CEILING DI£TWORK AS REQUIRED -'T T-79 - 3:

I hili 2

11161,

1/1:'92 ~1/17/92 5 Ir2:3I92

<4 214192

1116192 1117/02 I r2:3192 1124102

~1/23I92 1129192

o 1/23192

CQ'1PLETE IIISTALL A.flOVE CEILlN6

ou::TWDRK AT T-79 -

"

InoI02

1124ID2

14I!il2 , s...

113OI!il2 PAIIT INSTALLICW CQ'1P INSrALLIIEW

N!KNE CE ILING A.flOVE CEILIN6 CtII)UIT &. WIRIIIGI'OR aNlUlT" ""'RIII6 FM

----\------------------------1 POWER. VOICE&.tI4TA 1-----1 POWER. VDIa:&.fMTAI---~----------------------_ Nfl) P\A.IC ADORESS ItR> PU.l.IC ADDRESS

o 12/231!i11

PARTIIISTALLMETAL STUDS&' III WALL WOAK FOR WALLS ElCT£IIDII'tG FROM

STRUer TO STRUCT AT T-79-0

IN WAll ITEMS INCLUDE

-IlOClCING -OONIIUIT

SYSTEM AT T-19 - 0 S'lS"TEtI AT T-1!I - ~

213192 2/3/92 2/3192 217/92

o 214192

COMP IIIST ALL METAL STUDS &. III WALL WOAK FOR WALLS EkTEIIDING FROM

STRUer TO STRUCT AT T-79- 0

• fRAltES 215192 2/51~ • PlPING

O

2/5192,

12/:2319 I 12r2:31!11 ~/4I92

215192

PART HAllEi &. FINISH · ..... .;:;C~OMP"!'!!"'!HA .... II ... Ei-&.-F-INI-S.:::H:..;; ~~~~ ~~~~

STRUCTTO S"IRUCT STRUCTTO STRUCT PARTITlOIIS ATT-19 -l--------------------------------------------IPARTITIDNS ~TT-711-

o 0

.2 02 215102 215102

"'0 ItlSllll 12123191 12/231110' 12123191

~r-------------------------------------------------------------------2115192 215192 215192 215192

Page 53: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

215m /IFP\.'1 FIRST COAl OF P""IIT TO 01'1 WAlL

SURfACESAl T-l9-3

217/92

2119192

2119/92 o

2/19192 tDI'P INSTALLNETAL

STUDS &. IN WALL WIRIC FOR WAUS EXT£NDlfG FAon

STRUCl TO CEILIIiS AT r-79 - 0

~/92 2/20192

2/19/92 PART INSTAlL METAL PART HANS &. FINISH

STUDS &. IN WAU NEW DRY WALL AT WORk FOI WAUS STRUCTTO CElLINI EXTENDING FRDI1 J-_____ ~PARTITIDIIS AT T-n-

STRIICT TD CEILINS AT 0 T-79-0

21 92 2 1:0/92 2/20 92 2 1:0/92

e/ 2119192

2 19/92

0/ 211g192 2119192 2/19/92

o 21191'2

tDI'P HAilS &. FINISH INSTAU DOORS&' NEW DRr WALL AT HARDWARE AT T -79 -STRun TO CEIUNS 0

ARTITIOIIS ATT-79- f---0

l21:li92 2/20192 2120/92 21201'2

" o 21191.2/ 2119/92

PART APPlV fiNISH PAINT &. VINYL WAU COVERlfG AT T-l9-

o

2120/92 2120/'2

Page 54: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

.. 2/25192 ~20/92

" CO!1P FINISH P"IIfTINS /IN) APPLYIN3 VINYL WAU COYERINS AT

T-79 -4

2/26192 ., IIIST Alll'EW CARPET

ATT-N- 5

/20192 2/2S192 2/26192 313192

~ 2/26192

2 2/'Z1192

TRII'! OIrT"E."fII ELECTRICAL &. LIFE

SAFETYSVSTD1S AT T-79 -2

o 313192

I"STAlL VOla, DATA eo. POWEI! TOtIISTOIES

ATT-N-O

21:28192

CIJlOOCT LIFE SAFm TESTS All) APPROVE SVSTD1S AT T-79 - 1

3n0J92 3/23192 312~92 3/24192

1/2191 I/~I/ Tlno IIIJTIFY I'lB..IC .. OTHER A&DCIESCE DATE or TEST' .... LIFE SAmy SVSTD1S AT

LL -1

3/24192 3/24192

lilly start DUI'Itlon Eer1y'llIl ....

I ~ 11/15190

03-5E1.ECT HUMBER or TEST PILES TO BE

USED &. LOCATIO" - 1 (Illampll>

11114190 1111:1t90

• Ac:tlylty numDer • Ac:tlylty daIcr1ptlon • Ac:tlylty IIIItlmalAd drntlon

In .1.se., Wlll1<lngdlllll

LaIA 'Inlth

~crl'"'

0 313192 313192

311:5192 311:5192

[ .... ] • ()::tQbar •• 1991 ! 18tI~ -79-1 II:lt 109IJJ'k 4tat 203

./ 313192 3 /3/92

3/25/92 3 11:5192

NETWORK MODEL POR PIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchbura. Virainia

H. J. Co:ubuetioa Joird VlH\tUt L~ ViI'PI 24506

Ralph J. Stephenson PE PE CoI:lsuIUng ~ 323 Hlewatha Drtve MI.. Pleesant, MIchlitm 46853 ph. 5177722537

Sheet T-79-1

Page 55: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

· "

"

2/111

2/111

.1MIlI..I. TIl! 10 Ot'TOBER EI.

11191

o IOte19 I 10181111

OWNER '" ccwrRAt'TOI RESII..VE STATUS OF

79 FIRE ALARM SVSTErI

','2' ',:~~' OWNER RE'SCLVE 6B ELEVATOR RECALL

Slr'STErI DESISN ION91

12110191

12110111

/)

10/8191

1211()J0 I

o o I01B191 loJB191 1 ()JB191

PREPARE & SUBMIT SH(F DRAWINEiS Fa!!

ENI1.¥ DELIVERIES

REVIE'lI' 6. APPROVE SID' CfttoWIN&S FOR

EARl.. ¥ DEL IVERIES

10 1018l1l~0/8/111 1018191

o 1018191

1018191 1 8191

(I

1018111 1018J1I1

PREPARE & SU!II"IIT HOlLOW METAL SID'

DRAWl rES

29/91 11/29i1l1

\ 0 10181111

PREPARE & SUf!ttIT HAAOWARE SCHEDllE

11lI8I1I1 INIEW r. APPRQY[

HOlLOW METAL SID' DU.WIIIGS

11f29J01 II(: 9191

10NDI

RNIE .... & N'AI.'OY[ HMDWARE SCIEDll.E r. SUIMIT TErlPLATES

TO HM FIIDRICIITDR

0

10NlI 1018111

/)

1018111 I 10NtI

FAa&. IIELIVERURt.¥ CCRml1.CTION ITEttS

o 1018/91 1018191

E TIR TO SET L .. TE FINISH OF ACTIVIT"!'

III 1018111 10 10181111

1018191

FAil & DELIVEI HOlLOW METAL

., ION91

FRAtES & DOORS

II/.U/IiI

1018191

29i91 ,\"0 FAB&DELIVER

KAROWARE

ION91

I Ol8lg I

o I 018J1I I ION"

PfiEPARE & SlBfIT FIRE PRIrTECTIDH SKOP

DIAWING8

11/1 91 I I 141111

Page 56: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 101el91 IOIS/9'

12/10l9H 211019 1

IOlS/91 o

IOtel91

DISTRIBUTE SPRINKlER SYSTEM

DESISNTO I1ECHANICAL

CCIII'I'RACTDR ~ FIlii ALARI'I COIIIT ACT

POINTS

IS 10/14191 II/V91

REPAINT DE/'OVTABLE PARTITI!HI AT 3-79J6I1NE- 15

1129J92

(I

I I tel 9 I

PART INSTALL N!J(1tI[

tElLING fiRE ALARM RIUlH WIRING AT

3-79/68NE - 0

12/10/91 12/10191 12110191~

10f&/91

12/10191

1I~91/ 1l18J91 "; 0/

litelil 11111/91 I ,,::Vgl "'"/1Qf91 -, 4 11/22191

RE\IIEW'~E PART INSTALl N!J(1tI[ COIfP INSTALl N!J(1tI[ COIfP INSTALL N!lt:NE FIRE PROTECTIDN SHIP CEILI~ IiOlGH FIRE CEILI~ ROOOHFlliE CEILING FIRE ALARM

DRAWIIIGS PROT'ECTICII P IPlNii AT PROTECTICII PIPINii AT RIl.I'3H WIIi! 1MB AT 3-79JRME - 0 3-79J68NE - 6 3-79168NE - 4

1111 "91 11/14191 1111 "'lill 11/14191 11/14191 II 12 VII 12/1~91 12713191 \.

Page 57: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

11;'22191 o 11/22/91

12123191 '" 12127/91 PART INSTAll"EW CEILtI'fl DiffUSERS.

LIGHTS, St'D(E DETECTORS,

SPRIN<LER foEADS &. SPEAICERSAT

3-79168N£ - 4

112191 o

1/2191

TIR TO START LA'" OUT TD'tllSTOMES - ?

1211 91111 12119/111

112191 i!>

1/11/91

lit.'" OUT 10l'llSnNS O\T l-1II/6e1'E- e.

1:2'1 ~gl 12127/91

o 11'3;192 1 flIII2

o 11/1/91 11/1/111

1/30/9RI3OJI2

~ 1/10/91

i!> 1/17/1'

DRIU HOLES ~ P'(ft THROUGHS O\T 3-79/68"E- &

12/ )/91 ",nl

\ 2/13.lI12q:.....(-1'$1-11-2---------------

12130/91 1J3~ cotP INSTALL NEW CEILlH8 DIFfUSERS.

LtaHTS, Sl'tOICE DmnORS.

SPRINKLER HEADS & SPEAKERS .. T

l-jlg/6eIIE - AI 217m. 121112

I/l/92 o

1,t:'$I!Z!

INSTL t1IU WCIIJ( AT 3-79168"£- 0

1/10/92 /

Page 58: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 3/12102 3/12192

:2 3/13192

FRQtt FINAL CLEAN t-HOVE OUT OF 2-70168

- An 03/1211112

3/1 :2192 3/12192

t/U!1I91 6

1125191 aDUSH I" COfCIUrr Fat TIlt'BmJ'ES & SEAL

IO.ES Al 3-79168NE­iI

lIe 92 1/1SlD:!

"

OWNER PREPIIR£ & ISSUE FUIICH LIST FDa

3-7916"'E - 2

3/121512 3113192

1/2101 o

1/2191

ll'R TO APPL't' Fat CERTIFICATE

UCCUPMC'f {l.r 3-79/l1f1NE

3/1 7/92 3/17/02

5/16192

CONTRACTOR CORA£CT PUNCH LIST rrms .. OWNER ACCEPT AREA

AT 3-79/i58NE -",

5116192 31191

112191

APPLY Fat & RECEIVE CERTIFICATE OF OCCUPANCY FOR 3-7916f1NE - 3

5/17192 3/19/92

1130192

1 /'

INST ALL DEMOlIITAISLE PARTITIONS .. DODaS AT 3-791i58NE - 10

92 2 12192

-, S

3/26192 FCLINSTALL OFFICE

Fl.RNrrURE' AT !-791I5BNE' - 5

3(21 V92 3/26192

2/13192 12

2/28192

C1.£AN ElIISTIN6 CEILINGGRID& IIISlALLNEW

ACDUS'lICTILES AT '-7916I1NE' - 12

:2 W92

3I'D192 FCL I'IOVE IIITO

:2 3130/92

3-791I5BN£ MEA - :2

3/'0192

S/2I92

3/30/92

3 3/4192

8Al..AMCE HYAC S'fSI'Et1S AT

3-7916"'E - flAY HAVE TO 8Al..AMCE

WITH O'nER AREAS OF IIIILDING - 3

$1 92 3/4192

3130192 o

3130192 ET/InO SEI" LATE FINISH OF ACTI .... I"

3IW92 3

3/4192 CONDUCT 8AS TEST AT

3179168NE - 0

3 92 3/S1112

/

Page 59: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

5 315192 3/11/92

FIN ..... CLEANS. tINE OUT rE 3-NJI58NE - 5

3/11192

Page 60: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

10

o 1/2111 11219 I

D 1/2191 1/2191

1019191 3

10/11191 REI1DYE .. STORE

ElIISTIN6 DEI"IOI.JNT ABLE

PWITIONS AS REQUIRED AT

'-791Ii8H[ - 3

lOllS/III,

10":', 1/.019191 T/RTD DWfER t1AKE !W.VAGE& STDRE

AREA " .... "ILAIILE F'tR ElCISTIN6 LIGHTS, REI100ELllia WCR( AT DIFfU!lERS. SPEAKERS

'-7916INE- &. OTl£R CEllINa 10/091Q1 ITEt1S AS REQUIRED II.r

3-7911i811E -1

.., "91 I 019J9 I 101' V91 10/17/91

~ e 10/18191 1019191

REtIOVE & PII.TCH E1USTIN6T STATS.

TDI'IISTONES .. OTHER FUlOR I'IDUIITED

DEVICES "5 REQUIRED "T 3-19/66I'E - e

\I;' \4191 11/13191

10/11191 o 10111191

10122/91 (,

10'2919' D'ftNiR IDENTIFY

LOCATION OF ASIIESTOS I1ASTIC DII

101'JOl91 OWNER ABATE

DUCTW(RC AT 1-----1

ASBESTOS I1I1.STIC DN DUCTWORK AS REQUIRlDAT

3-79/611NE - 5 11/19191 11/19191 3-79IMIIE -"

",

1011

\ ,,~, 10121191/.0/22/91

10(29191

:5 10/24191 "",,"

REND"'" EXIST'ING "\ REI1DYfl ElUST'IN& CEIL INa allD& TILE AIIOVE CEllIN6 VOICE,

...s REQUIRED "T O"TA AND POWER 3-7916INE-2 WIRIN6 AT 3-7IJ/158'E

\U4M' -3

et91 10121191 1216191

\ 10/21191

:5 10123191 10/24191

7 11/1191

REtmE EIC 1ST I 116 DRY REMOVE ElIISTINB WALL &. HMaIR'# CARPET AT 3-79I1511NE PoUn"lTICRi AS -1

RIXJJIRED AT 3-79115111[ - 3

11114191 II/lelt! "/19/91 1If.l 191

91 1I~91

'" 0 ". !!1I91 11/1191 C01PLETE COIISTAUCT Mise nASONRY ITEI1S

"T 3-19/661'E-0

12111)191 12110191 .....

Page 61: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

II/!;U// IlEl'l=O~VE~AI!fI1tI~:::-E-""'"

.flLlIIS DIX:'TWORk AS IIEQUIRED AT

3-79/68I1E - 3

/11/11 91 11113191

o 11/15191 11/&lF9",,!' ~~=~~1.;.;1I...;~9'~11{1!5I9'

Cl£M [XlsrlllS INSTtlU flEW ABOVE NDlE CEILItG CEILItG ELECTIlICAL

tu:TWORIC WITII C,I8.E TRIo ... AT ---4 '1ACUUI1 ClEAMItG AT 3-79J6IIME - 0

3-79/68I1E - 8

11/151111 11/1811i11 11/18111

11/1819' .-

111:21191

PAIIT INSTALL HEW Iil!JCNE CE ILING DUCTWOI!K AT 3-79168I1E - "

11/1810 I 11/211111

4 11122191 I I 127111 I

a»'IPLETE IIiST ALL A.IIO\IE CEILING DUCTWORK AT 3-79J68ME - '"

11/22101 111211111

~1I/15191 III~III 11/l8I1a! II~O_,\I PAIIT INSTALL MEW CCI1P INSTAU IIEW

Iil!JCNE CEILING MJt:NE CEILING IX'OJn &. WIRIIIS FOR CXlNXJIT &. WIIIIIIS FOR

------l'r-------------------------lPOWER. VOICE&. DAT" 1----; POWER VDICE&.DAToI.I---~------------------------

o 1111191 11I1I1I1

PARTIIISTALLMETAL STUDS&. III WALL WORI( FOil WALLS EXTEIIDlftG FIIOI1

STRUCT TO STRUCT /f,T 3-79/6IME - 0

11129191 11129/111 ,. IN WAU ITEMS INCLlIlE

- 8l0CXlNG -CONDUIT -FRAIES • PIPING

1111191 f)

1111191

Pili((" .... IIS &. FINISH MEW DRf WALL AT

STRUCT TO STRUCT PIII(("ITIQNSAT 3-7916111£ - 0

S":t~~~~::6~£ ::s, ~~~~:'Ra~ \ -0 -5

12111f91 121' III 1219191 12/13191

3 11/29I1iI1 121311i11

Cal'lPlMSTALLMETAL STUDS&. III WALL w.:IIK FOR WALLS EKTEIIDING FROI1

STRUCT TO STRUCT AT FJ9IallllE - :5

11/:29191 1213191

"""121410 I .-

1219191 .. ? COI'IP .... IIS &. FINIS.

MEW DRY WALL AT STRUCT TO STRUCT

P /f,RT IlIIJIS AT 3-1916811£ - "

~ 0 "'''01 ''''/II ",.", 7 11/1/9t::Jr'_/I_'_9_' ___________________________________________________________ 1 1_1_' __ /9C::J I/V91

12/10191 1211019, 12110191 12t1Of91

Page 62: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

12/10191

./'~' 12113/91

APPlYFIRSTCOAT OF P;'IIIT TO DRV WAlL

5l.RFACES AT 3-79/68I'tE - 4

12/HI/91

12/25191 3

12/20191

COMPINSTAlLNETAL STUDS .. IN WAll WORk FDa WAllS EmNOlfG FRO"

STRUCT TO CEILI.S AT 3-191681'1E- 3

12121/91 lIit92/ 1/6192 r=D»P==~~~m~"~F~IH~I:~~ ~~~~~.

NEW DIY WAlL AT STRUCT TO CEILINB

PARrITIONS AT 3-19I68NE - 5

1 3/92 1/6192

""1/6192

/12/:23/91 12120191 12 21 91

12/:0.,91/ 121:201r-::-9..;..1 ___ --..;.1.;;..2f..;;;:O,:.;t191/

119192

12120191

PART IMSTAllI'1ETAL PARr ~6&'FI"'I9H STUDS&. 1M WAll MEW DRY WAlL AT WORk FOR WAllS STRUCT TO CElLINI EmIllIHG FROM PARrIlIl::WS AT

STRUCT TO CEILING AT 3-79168NE - 0 3-79/68ME - 0

12/:23191 12 12121 91 12 27/91

5/ 12/20191

12 91

........ -=PARr':':~A~P=Pl:-:y:-:F:::IN=,SH::"!"".,..,oI PAIIIT .. VINYL WAll

tov£RIN6AT 3-7916.E - 4

116/92 119192

Page 63: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

.. " IIlSlIJZ I I 161IJ2 "

10 ./ 1129192" 1/W92

e 2/10192

.Iff" fiNISH PAIlfTINB INSTAlL NEW CARPET Nl) APPLYI"" YI",L AT 3-?IJ/68IIE - 10 WAU COllER1NB AT

- 3-""".1E-4

1/1S102 1/16102 1129192

'" 1/16102 4

I12l1IJ2

rz

TRII'IOUT NEW ELECTRiCAl ... LIFE

SAFETY SYSTEMS AT 3-""".1E-4

'192 313192

TlRTO IIITIF' RiLle .. OTHER: A8DICIES ~ DATE OFTESTINB LIFE SAFETY SYSTEMS AT

2-19J61J-1'

S/~ 112 3141IJ2

Dantlon £enU flnlSr.

I 11114190 11J15/90

03--sELECT NUI1I!ER OF TEST PILES TO eE

USED&. LOCATlDN - 1 (1IIIIInple)

11/14190 11/15190

• ,t,ctl" ltu IM'IIIIr • A.ctMtu dllCl"lpthlfl • A.ctl\lltu Mtlm ..... d dll"lthlfl

In .I .... a wl'lI1Clftg dill.

LI18 flnlsr.

Amy"1

INSTALL VOICE, DATA .. powe. TOI"l!lS'l"O\ES

AT r?IJ/68'>E - e

2t:l:4IIJ2

I/W92

CONDUCT LIFE wm TESTS AND N"f!1R(1tIE

S 'l'STE1'IS AT 3-79JDIJ"E - I

3/41D2 3/419 2

0 2/1OJIJ2 211Q1IJ2

3f5JIJ2 31S/IJ2

III'IIt .. J - 0c:I:DtI4Ir 9. J99 J i 1Sbt'"',-79168M IS wm: 0lIl:2'3

0 2110192

/ 1101IJ2

315192 3 15/92

IaWrior 'WOrt for 8I.'H 3 -19168 BOA ItDCIIltiw (JII!>

NETWORfC MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFFICE ADDITION Lynchbur8. Virainia

B. J. CoMb:uotioa JoiD.t V.atur. L~ Vi.:nlime 24506

Ralph J. St.ephenson :FE PI ConsuJting~ 323 HIawatha Drtve Nt. P1easant.~ 46653 ph. 5177722537

Sheet 3-79/6Sne

Page 64: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

C!D 2(91 /-7r 2/91

10

1018191 o

1018191

DwrER .. COIIT'RACTDR RESOLVE STATUS DF

19 FIREALARI1 SVSTEI1

:z ::~: OWI'ER RESQ.\IE 88 ELEVATOR RECALL

SYSTEI1 DESISN 1018191

1120/92

f'

/1/2"92

10:.,91. .... '/ 1011191

1120192 a

1018191 IOIB191

1/20102

o 10/B191 1018191

o I OlBlg I

T IA TO oaOlER El. V· PREPARE & SUII'IIT REVIEW .. APPROIIE FM.'I t. DEl.I't,IER EARl.. '" 1001

IlIl9I

9HfP MAWlfI6S FeR StU' DRAWIN&S lUi c:aenu::TIDNITEI1S EARl. Y DELIVERIES EAII. 'I' DEL 1IIEIIIES

\'\~018l91 101.191 1018191 1011/91 1018191 10/'01'91 10111111

~ o 101819 I 1018191

PREPME .. SUlII"IIT HDUOW METAL 9HfP

OR"WIIIDS

1125I!il2 I/23JliI2

\ o 10NGI 10l8lDI

PREPME .. SUlII"IIT HARDWARE SCHEDU.E

o 1018191 10/8/91

REVIEW. APPROVE HOLLDW"[TAl 5KF

OR"WlfES

loIe/91 o

101el11

FAil .. IlEtiVER HDLLOW"ETAl

FRAtES .. IlCJCJ1S

1I23JliI2 1123/112 I 92 1f2S192

10/MI 1~91/loIe/91 REVIEW & N'PROYE

HMDW_ SCHEDtU FAB&IlElIVER

HNI>'WME

o 101el11

" SUBI1IT TEI1PLA TES 1-------1 TO.., FAlRICATOR 1------1

117/92

10/8/91

o 1010/91

117192

1018191 101el1i1 loIe/liIl 1018191

o loIe/91 101el91

PREPARE & SlI!I'IIT FIRE PROTECTION SHOP

DIlAWIMlS

111/92 I 192

o 1018191

ET/RTOSETU.TE FINISH OF AalvrN

1018/91 10 IeIIII

Page 65: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o I 0te/9 I 1018191

-----------I-/~---O~/~n

10181111 o

101el91

DISTWIBllTE SPRINKLER S¥$TE11

DESI6MTO I'IEJ:HAMICAL

ccrm:u.CTDR FlJl fifE ALAII1 CCM"AtT

PDINTS

1219191 e

12/1e191

REPAINT DEI'Ofl"AlBLE PARTITIOIIS ... T 1-79 -

B

2 13192

o 112192

PAIRT INSTAll. III!J(NE CElLINI FIRE ALARI1 ROlGI WIRINII ~T

1-79 - 0

":20192 I t.2CV92 1(2()I92

1018191 1'~91/'2'27191 1':92/'15192 1~92 1I1~92 REVIEW" I>i'ffll.CNE PAlrTINSTAll. M!!tNE OO1P INSTAll. III!J(NE OO1P INSTALL /ll!Jl:NE

FII'i£ PRIFTECTIIlII SHIP CEIL!!. RCUlHFIRE CEILING RCUlHFIf1.E CEILlN& FIRE AlLARI1 D''''WIIDS PROTECTIl»! PIPING At PROTECTION PIPINS AiT ~ WIRIN& ... T 1-79

1-79-4 1-79-4 1---------4 -3 1--------------------------

I /92 IflQ192

" "13192 1116192

\ 92 92

Page 66: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o 1113/92 1/13/92

- ,_,I '\"

1/231112 4

11%8192 PART lET ALL NEW CEILING DIFFUSERS.

LIGHTS, StUE DIETECTtlRS,

SPIiIIM<1£R lEADS&. SPEAKERS 'T '-'19 -"

21 2lVII2/ 212 "'12

11219' o

1121111

T/RTO START LAV OUT T(J1E1STOIES - ?

112 4192 1124192

If2JIII :$

1141111

L'V OUT 10teSTQfES AT 1-19- 3

11.2 "92 1126192

o 213192 2(3192

o 12/,.,/111 12/,efll'

2"419~/14192

Inl91

~ :$

119191 DRIU IllLES F1:R POkE THI!.O.JIJiS AT 1-19 - :5

1129192 1131

:5~92~-(~-9-2-------------------------------

1129/92 2J3~ V ItlOI92

o 113OJ12

COHP INST Al..L NEW CEILlII6 DIFFUSERS,

liGHt'S, StlOICE DETECTORS,

~INICLER HEADS & SPEAKERS AT l-n-4

312192 315192

INSTl t1IUwaIC AT 1-711-0

2~ 92 /'

Page 67: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

(I 2 3131102 3131102 ..... 1192

FROtt FINAL CUM & NOVE OUT Dr 1-711 -

AN 03131182

1192 3131192

1110191 '" 1115191 RO ... H IN aIIIlUli Fat TIltlllSTCN:S &. SEtIIL HDLES"'T 1-711 - 4

!IJ 92

OWNER PREPARE &. ISSUE PUIICH LIST FDR

1-79 - 2

3131/02

1/21111

..... 1192

o 112191

i IR TO APPLY f(J!

CERTIFICATE OCCUPN«:Y AT T-?9

192 413192

4 417/92

COIITRN:11Ii! CXRIECT PI.KH LIST (TEns &. OWNER ACCEPT" AREA

AT 1-79- 4

417/9 412192

";'.~" 112191 4

..... ,3192 ' .....

2 411 ..... 92 ..... ,!S192 4Il!S192

(I

..--,5191 APPLY Fa! & RECeiVE

CElITlFICAiE CI' OCClPANC'tFOR 1-79

-3

411 92 41"

11 ..... 92

INSTALL DEI1CUIIT ABLE PARrIilOE:& DOORS

ATI-N-IS

211 92 ./

/92

ra. INSTALL DFFICE ra. I1JI.IE IIITO 1-?9 FURMITlRE AT 1-79 - AIIE"'-2

418192

3/6192

4

""13192 411 ..... 92

312:)/92

...,,5192

2 3/23192

Il.tAl ElIISTIN& BALANCE HV~ CSL~GRID&' SY5TEtlS "'T 1-711- (I

list tllLL lEW NAY HAVE TO BALANCE

E T IR TO SET LAn: m.'SH OF ACTIVlrl

4/15/92 411 5191

5/W9::! CONDUCT lAS TEST AT

,-711-0

ACOUstiC TILES AT t------I\tIITHOTtER ARfASCI'I------1 1-711- 10 ItUILD~- 2

92 3/19192 2 :5 92 512 92

/

Page 68: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

rl24192 5

3130192

FIM .... CLEAN &. t'IIVE OUT OF 1-113 - 5

3130192

Page 69: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1-11

12

o 11219 I 1/;219 I

CJ 112191 111191

TIR TO OWNER 11111([ AREA AYAILABLE FCR REI'IXELINB WCfiI( AT

1-""'- 10(09191

r:. 91 12f ygl

1212191

12/

RD10VE &. snRE ElIISTIIB

OEI'O..M"ABLE PMTITICWS AS

REqUIRED ATI-79 - 5

SALVABE & STORE ElIISTINB LIBHTS,

DIFFUSERS, SPEAICERS &. OIlER CEILINB

ITD1S AS I<£QUII<£D .. r 1-79 - 3

Lt91 1210191

~ 5 12/619 121219 I I

I<£If)YE & P .. TCH ElIISTIIB T ST ~TS.

TOI'Im'"CNS &. OllER FL.OI:R MOUNTED

DEVICES IJ.SI<£QUIRED AT 1-""'- 5

III 92 1(141'92

....

121'

12/61'91

1/15192

o 12N91

REtlOIE ElIISTING CEILlNB BIIO& TILE

AS REQUIRED ~r 1-79 - I

V9 I 12f

w

"\ ~91

I 21619 I I o

2(619 I

REIf)YE EICISTlm DR'I' WALL &. MoIr.SOIR'I PIJ.RTITICWS AS

REQUIRED "T 1-79 - 0

111 "92 1115192

12/10191 4

12(1:sJ9 I 12/16/91

\~ I

111

OwrER IIlENTIFf OWNER ABATt LCCATICW (F ASBESTOS MASTIC ON

ASBESTOS l"IoISTlC ON DUCTW(JIJ( AS DOCTWDRK .. r 1-79 - 1------1 REQUIRED .. r 1-79 - 5

4

12(1:sJ9 I

5 12(16191

RD101E ElIlSTINB .. BOlE CEILIM& Io'OICE.

DATA IIIC POWER WIRIMlAT 1-79 - 5

'2

I,

1/15192

6 12(16191

RD10VE ElIISTINB CARPET AT 1-79 - 6

"'92 112219

12/16 91 12 91

~"".'" .... o

12114191

C01PLETE o:rena.cT MISC MASONR ... ITD1S

AT 1-""'- 0

1/2 '192

Page 70: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

113I9~

1~92 ~116I92

\

5 1/10192

'--""!CUAII:":"::"~DI=IST=IN~i--' INSTALL NEW AIM I>I!!£NE alLIMl alLIMl ELE.CTRICltL

Dt.J:TWORIC WITH CAlLE. TRAY AT 1-19-__ ..... YAtoo" ClEANINl AT 1------1 5

\ ..

1116192 PART INSTAll IIEW

N!II:NE CEILING DUCTWORK AT 1-79-

4

4 1122/92

ta'1PlETE INSTAlL AlKNE CEILING

DUCTWORIC AT 1-79-

'\ 1-19-11

t2t.23/9 I 113102 1/10102 1/13/92 1116192 1117192 1122/92 1/61112

\

~1/10I92 1/1:'92 1/13192 1~2 CCMlUIT 6. WIRINS FeR a:roJIT 6. WIRINS FOR

.... PART INSTAll NEW ta'1P INSTAll NEW ""

\

N!II:NE aiLING "-!ICNE CEILING

------It------------------------IPOWER. vOla 6. OATAt-----i POWER. VOla&DATA I-----~------------------------

o 12/16191 12/16191

PART IIiSTILL METAL STUDS 6. III WAll W(Jik FOI WAllS EXTEIIDlnG FROM

STRUCT TO STRUCT II.T 1-79- 0

IfZ :t92 If23I92

'",-

.N WALllllMS INCLUDE

-1Lt:Ja:ING -COHIUIT -FRAnES -PIPING

12(16191 o

12I16J91 PART HIlliS 6. FINISH

HEW DR' WALL AT STRUCT TO STRUC'T

PARTITIOIIS AT 1-7'il-0

NIC PlIIlIC ADORm ~ PUl.IC ADDRESS SVSTEM AT 1-1'9 - Q S't'STEn AT 1-79-:5

1/16192 ,,, 1/92 1/16/92 1122/92

o 1/22192

CDrP IIiSTILL METAL STUDS 6. III WALL WORK FOR WALLS ElCTEIIDlnG FROM

STRUCT TO STRUCT AT 1-19- 0

IfW92 IIW92

"'-1/22J92 <>

1122I9z,. to .... HAilS &. FINISH 7

lEW DRIf WALL AT STRuer TO STRUCT

PARTITIONS O\T 1-'79 -0

~ 0 ''''''' II..," " .. '" 7 IVl619t==J_2_/l_61_9_' ___________________________________________________________ 1_2/_1_61 __ 9[::]2/16191

V'23I92 IIal92 11aI92 1/23/92

Page 71: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

. /..," 1/22192 1122/92

/ItIIPl't FIRST COAT OF p~lIrr TO DIY WAll

SURFACES AT 1-70-

112:519:2

I 23/92

3/ ',23192 1130192 1131192

COrP .. Sf ALL METAL COrP HAIII&. FINISH SlUDS &. .. WALl IIEW DRY WALL AT \ftIIII( FOR WAllS STRUtT TO CEllIlIG

INSTAll DO HARDWARE AT I­

I EmllOlMi FRaM 1------IPloRTtnOIlS AT 1-711 -1-___ -1

STROCT TO CEllI.S AT :s 1-19-3

11221112 1/22192 PART INSTALL METAL PART HAIlS &. FINISH

STUOS &. III WAll NEW DRY WALL AT WOf!I( FOR WAllS STRUtT TO CElLINI ElCTEII)IIIll FROM t-------IPARTITI€*S AT 1-79 -

STRUCT TO CEllfllS AT 0 1-79- 0

'2 1/23192 1120192 2

112 1131192

~ 1/30/92

PART APPLY FIIII&I PAIIIT &. VIN'I'l WALL COVERIIill AT 1-79-

o

2/3/92 2/11'92

Page 72: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

-

.. "-216192 217192 ,Ji

.Q/'P FINISH P"IIfTIr,e INST ALL IIIW CARPET Nf:} APPL1111G '~I""L AT 1-79- 5 WALL CaWRIr,e Ai

1-71 -.II

216192 217/92 2113192

~217192 Tllitt Otrr "EW

2 2/10/92

ELECTRICAl.. & LIFE SIom'!' S'¥STEr1S "'T

1-19 - 2

S 2/2OJ92

I"STALL \IOICE,DUII .. POWEll TOI18STONES

AT 1-70-5

5(17/92

2111192 COfiOUCT LIFE SAFETY TWI'S All) APPROVE SYST£l'IS AT 1-79-1

3/19192 3/20192 3/23112 3/23192

11219 I I/:'J.I/ Till iO IIOTIF' Ft.ft.IC & OTHER.t.II£l11CI£S(F DATE OF TESTING LIFE SIom'!' S'¥STEr1S AT

1-19 -7

3/23J1iI2 3123192

!iIIr1y atart .",Uon EIIr111 tlnl"

1 11/14190 I 11 1 5t90

03-5eLECT IIUttlE. ElF TEST PILES TO ££

USED & LOCATlOII- 1 (1OlIlI'lIplel

11/14190 1 1115190

• Hotly'ty .... nelf' • Hotlylty dllCMPtldn • Hotlylty "tlrnfltAld Ilretlen

In 11.,,12 wll1elng IlIIIII

Ldl ,Inllh

A':II,".

0 2I2OJ12 2t201!12

5124192 3124192

~ -I • 0I:t.t::iC0W 9. 1991 USll~F79 iIlt 'WOJl .sa: 2113

0 / 2120/92 2 120192

3124192 :5 124192

Iaterior 'WIDl'k for arM 1-19

NETWORK. MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFfICE ADDITION Lynchbufa. Virginia

B. J. CouhuotiO:D Joint veata::n L~ V'u ..... 24506

Ralph J.~FEPE CoasulI.tni ~ 323 Hlewathl.lriv& MI.. P.Ieasent. MIchiaIn 48653 ph ;177722537

Sheet #1-79

Page 73: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

,

2/91

2191

10

o 10/el91 10tefgl

DWYEII &. Ol\I1llJoCTOR ReSOL .... E STAlIIS OF

19 FIIIE ALAR" $'ISTEM

:z :~.~: O\IINEII IIESCL 'Al lie ELEYAl'Q'i: ReCALL " ION9I $'ISTEI1 Del6M I ON9 I

1;17/92 o

1018191

PIIEPARE " SUBMIT SJo«IP I)RAWIM6S f(R

EARLY tELI'AlIIIE5

!II~0I8191

1018191

1011J191

o 1018191

PREPN;£ &. S1..8'fIT HOLLOW "£rAL SH:P

DRAWI1'IiS

II 17/92

1018191

1/17/92

o 1018191

Re ... IN &IoPPIIM SIO' ORAWIII6S f(R

EARl.. Y DELI'o'EIIIES

10/8191

ION9I

1018191

o 10181111

R[\/IEW" ~E HOllOW I1ETAL SIO'

DIIAWIFG

o 10tefgl 10tef91

FII8& DELIVEREtUII!{ ~IDMITEttS

o 1018101 10t81gl

E TIl! TO srr LATe FINISH OF ACTI .... I"

10 91 1018111 10 91 10181111

o 10I8I9I I O/ao'g I

F .. e&.tELI..,.R HOllOW I1ETAl

f'R4I'ES &. OOCRS

\Ir~ 92 I(JID2 I(JI02 1(JI92 113 92

\ 0 0 I OI8lDI/. OI8Ig I 10/ao'91 1018191 1018191

92

IO/ao'91 PREPARE &. S1..8'fIT

HARDWARE StHo:u..E

ION91

o 101B/91

121121111

liN lEW & AfPII.'O'IIE HMD'fIARE SCI£DU..E .. SUBnIT TEMPLATES

TO tIM FABRICATOII

1018191 IGI8I!iII 1018191 I 8/ao'9 1

o I OI8Ig I I O/ao'll I

PREPARE &. SlEiI1IT FiRe PRIITOCTIDM SHOP

DRAWIN3S

12/1 91 12 12191

Page 74: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o IOle/gl 1018/91

-----------I-n-7-'9H 117/92

DISTRIIIUTE 5FRIIIKLER S\'$TIt1

OESI611TO nECHAlllCAL

c:cr.rrRACTDR FeR FIRE ALAI!t1 COIITIoCT

POINTS

10114191

REPAINT DEI'1(WTAllLE PARTITIONS AT 2-791118 - 13

3 1219191

PART INSTAlL ABOVE CEILING FIRE ALARM IItlUGH WIRING AT

2-79/68 -3

1117/92 1117192 1121J9~

lotll/91

1117192

18I:'91/.11'2IJJ91 6/

1214191 1215/91 12f~2191 ~12/13191 :5 12(17/91

"" "-. C01P INSTALl.I«NE REVIEW & I>I'fI'RtNE PART INSTAll. I«NE C01P INSTAll. ABOVE FIRE PRDTECTIOII SHOP aiLlt.G fO.JlH FIRE alLlN8 ROIJ3H FIRE CEILINB FIRE ALARM

DRAWINGS PAOTECTICW PIPIN8 AT PROTECTIOII PIPING AT RO.JeH WIRIMB AT 2-791611-6 2-7Q/6E1- 6 2-791611- :5

RI12/91 12/12191 12/12191 12119191 12/20191 121: 019 I lIZ ~!il2 '(24192 \ \

..

/

/

Page 75: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

o '17191 12117/91

\" 2f3J92

6 2/101112

PAII1INSTALl NEW CEILING DIF'FUSDI!S,

LIGHTS, SI'QE 1ETtt:rCRS.

SPRIJlQ.ER HEA.tIS & SPEAlCIRS oIIT 2-70/6e

-6

112191 o

112/91

T/RTO STMT LAY OIlT TQ'IBSTOIES - ?

192 tmlft

112.1111

LollY DUT 'OmsnHS Ar 2-79161- 1\

Im/92 213/92

o 2/161112 2118/92

o 11/1/91 1 I filII

31919RI9Ig2

~ 1/10/91

r. 1/111.1

DRILL HOLES f'(R Pa:E THROWHS Ar 2-N11S!

-6

21'4 92 2'11

3f1~9~-tl-~-9-2------------------------------

2.11:/ COI1P INSTALl NEW CElliNS DIFFUSERS,

LIGHTS, SI10ICE DETECTORS,

SPRINKLER HEADS & SPU.':ERS Ar 2-791611

-6

2/11192 D

2/111.2 INSTL I1ILLW(RI(Ar

2-791611-0

2/1 1192

/

Page 76: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

412

o 41211Q2 4121/92

FIIOtI FINAL CU ..... & I10VE OUT OF 2-19168

- N'I 04121/92

1192 4121192

OWNER PREPARE ... ISSUE PI.N:M LIST FOR

2-791615 - 2

4121192

1121111

04122192

o 112191

T/IHOAPPL¥ FCR C£RfIFICATE

accuPMCY AT 2-19tee

1192 ~2

CONTRACTOR CORRECT PUNCH LIST ITEMS & OWNER ACCEPT AREA

AT 2-711168 - ..

41f31!12 412fJJ~

112191

APfI\. Y FOR & RECEIVE CERTIFICATE OF OCCtJPANCYFDR

2-79/68 - 3

412 "92 412e192

...: S

5NIl2 f'CI. IIIST ALL OFF ICE

FUl:NlTURE AT 2-19/68 - 5

41211/92 515192

3119192

I1EAII DISTINS CEILING GRID ...

IIISTALLfEW

15 .atel92

5/6192 f'CI. I'OYE INTO

2-19168 AREA - 2

5/6192

419/92

517/92

3 411S192

I!W.ANCE HV~ SYSTEMS AT 2-711/68

- 0 I1AY HAVE TO

517/92 o

517/92

U/RTO SET LATE FINISH OF ACTIVITY

517 92 5171 92

4113/112 o

4113.192 CONDUCT BAS TEST AT

2-79-68 -0

----~----------------------------------~~--------------------------------------~ ACOUSTICTWESAT 1-----1 BALANCE WITH OTHER 1-----1 AREAS OF BUILDt,. -

8 Vl8191 1/29/91

ROUSH IN cuc)uIT FOR TOI18STONES & SEAL

HOLES AT 2-N/68 - iii

~12192 2/21/112

~

3/!i1192 IIIST ALL DEI10UIIT ABLE PARTITIOIIIS & DOORS

AT 2-7!i1/68 - e

92 3 18192

2-79168- 15 3

2 41992 1S/92 411 92

Page 77: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

5 "'14192 oU2(N'92

FINAL ru..".& mYE DIlT DF 2-7D/e8 - 5

"'1 V92

/

Page 78: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

10

o 112/91 1/2/511

o 112/91 112/91

101'9J91 3

10111lgi

RmOIlE .. STORE EXIST IllS

OEMOUNT AILE PotRTlTllIftS AS

REQUIRED AT 2-79168 -3

1011 91

~/ 10191'1 101'9J91

TIR TO OWNER /'lAKE SAlVASE&. STORE AREA AVAlLA8LE FCR £lUSTING LlGIfTS, REtt:IlE1.IIIG WCfI:I( AT DIFFUSERS, SPEAKERS 2-79/~ - 10lOQigi &. onER CEILING

ITDtS AS REQUIRED AT 2-79/61 - 10

I'~gl lONg I 10/W91 lOll 2191

~ 101'9J91

10 10122191

REItOVE &. PATCH ElIISTIIIGT STATS,

lOteSTONES .. OTHER FLOOR MQUIfTEI)

DEVICES AS /ll£QUIRED AT 2-751/68 - 10

12 r.:~1 12113191

....

10/11191

121 I 1S/9 I

o 10111191

REttDVE EXISTING CEILING BRII> &. TILE

AS REQUIRED AT

iif

\

I O(Xllg I 6

II/6Igl

IIWNER IOENTIFf L.CCA TICft Il'

ASflESTOSI'I#STIC 011 DUCTw.:R<: AT 2-191&8 -6

91 1116t91

II 1118/91

REl'tOVE DISTIllS ABOVE CEILlIIS VOICE.

DATA IIIf'J POWER

Iln/91 OWNER ABATE '"

ASBESTOS "UriC ON DUCTWOIIJ( AS

REQUIRED AT 2-71l1ee -8

IIn/91 Il/le/91

2-70161 - 5 WIRIIIB AT 2-79/~-

\n 8

10~ Sl91 1M 91'91 !l2 1/14192

10123/91 :2

101':24191

REItOVE EXISTING DRY WALL" "ASONR'f PARTITIONS AS

REQUIRED AT 2-79/68 -2

12/1 WIll 12117/91

\ 10125191

10 Iln/91

IIEl'tOVE DISTIIIB CARPET AT 2-191611 -

10

12/1 51'91 1(2/92-..

~llnl91 Ilhl!ili .... COttPLETE a.sTRI.CT MISC I1ASDHR'I' ITEl'tS

AT 2-19168 - 0

I/2H/92

~. ,

Page 79: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

RD1DII'E MOYE CEILINB DUCTWCWlK AS REQUIRE!) ",T 2--1D/ee

-s

I MilO I

10 12/19191

IHST AU. NEW A80\1E CElLINI ELEtTRIt'AL

CAIU 11UY AT 2-791611 -10

6 1213OJ!il1

PART INSTAll !lEW N!JtNE CEILING DUCT\tORI( AT 2-79168 -6

12~V91 6

118192

CCI'1PLET£ INSTAlL I4DIE CEILING DUCT\tORI( AT 2-791611- 6

12/6101 12119191 12120JIIII I 2130JIJ 1 12~1 It 118I!il2

~1212011i11 4 12/261111 12/:27J!il1

, " 1/219

PART INSTALL !lEW CCI'1P INSTALL NEW N!JtNE CEILING N!JtNE CEILING

ctrQJlT &. WIRING FOR OJIP.JIT 40. WIRING FOR -----'r-------------------------IPOWER. "OICE&'~TA i------IfIO'IIIER.. "OICE&.I),IITAI---~------------------------

:3 1118111 1 '/l2l1il1

PART'MSTALLNETAL STUIIS&.IIIWAll \tORI( FOR WALLS EICTEMIIING fRIIM

STRUCT TO STRUtT AT 2-791811 -3

92 '('1192

IN WAU ITEMS INCLUDE

• BlOCKING -CONDUIT • FRAItES • PIPING

4 '" 11/13/91 I II 18I!iI I

PARr HIIIG&. FINISH IIEW DR' WALL AT IiTRUtT TO STRUCT

PARrITIONS AT 2-W68-4

IteJIiI2 1I1~1iI2

~ o IInl91 IInl91

Nfl PI.Il.IC ADDRESS Nt) PlIl.IC ADDRESS S¥STEM AT 2-7911'111 - S'l'STEt'l AT 2-19It11 -

4 4

1I1S/92 1120192 11:21192 f(2<4I92

:3 1~!iI 1/1~92

COMP'"&TAl.LNETAL STUDS&. 'M WALL wa;IK FOil WALLS EICTEMIIIII$ FROM

IiTRUCT TO &TIIUtT AT 2-7911111 -:I

1~1iI2

COI"P HANG &. FINIS. NEW DRV WAU. AT

STRUCT TO STRUCT PARTITICNSAT

2-79168 -4

1114/92

~-------------------------------------------------------------------------1121)/92 1120192

,/'

Page 80: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

1120/92 ItI'f'l Y FIRST COAT Of' PAIIIT TO DRY WAlL

SlR'ACES AT 1-19/68 - 5

1131192 PARTINSTAllHETAl

STUDS & IN WAlL \IIOIIk FOR WALLS EXTENDING FROt1

STRUCT TO CEiliNG AT 2-70/68- 0

2 92 2

5/ 1131/92

I 1/92

:s 2115/92

CO .... INSTAll METAL STUDS &. III WALL WORK FOR WALLS EmllDlfG FROI'I

STRUCT TO CEILlII6 AT 2-79/68 - 3

1/31/92 PART lIANG & FINISH

NEW DRY WAlL AT STRUCT TO CElLINI

PARTrTlONS AT 2-79168 - 0

21&192 26192

4/ 216192 2111192 2/12192

2 2/1S1P2

CO .... HAilS & FINISH NEW IIR' WAll AT

STRUCT TO CEILING PAIlI"IT IONS AT

2-70168 - <4

92

INSTALL DOORS & HARDWARE AT 2-79168·2

11/92 2114/92

" 2112192

PART APPLY FINISH PAINT & VINYL WALL

COVERtNS AT 2-701611 - <4

2/1 92 2/17/92

Page 81: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

.. " 10 ./ ~2118192 -, 21211112 21241!12 :5/eJ9~ 319192 ;;r-

., 3118112

COt'P FINISH P,t,IHTINB INST ALL NEW CARPET INST ..... L YOICE, D~TA /IN) APPLYINO VINYL AT 2-79168 - 10 .. POWU TOI"8STONES WIoU COYERING AT AT 2-7W68 - 8

2-79168 - 4

0 3118192 :$/18112

41141'92 41140'92

18192 2121/92 21241D2 :SleJ92 4I2J92 4113/92

/' "" 2/241112 ~./ TRII'I OUT NEW

ElECTRICAL" LIfE SAFETY S'l'STEl"IS ~T

2-79168 - 4

192 4110192

112191 T IR TO NlJTIFf FUI!l.IC I), aTHER A&ENCIES '* D,t,TE OF TESTINB LIFE SAmy S'l'STEl"IS ~T

2-79168 -,

4113/112 4113/92

terly start DlAtlan Elrty flnlan

I 11115190

03-SELECT NUt'llER OF TEST PILES TO til

USED 3. LOC,t,TIOII- 1 (exlllll'lpl.)

11114190 11115190

• tIoI:;tlYltli rulNlt' • tIoI:;tlvlty dllCr1l1t1an • tIoI:;U ... lty 118Umllted dlll'llUOn

In .II111NG WIRing d'll_

Lete stllrt LIIte tlnl,h

As;n Ylt I

CONDUCT LIFE SAFm TESTS 10110 ~E SVSTEMS ,t,T 2-7!11e8

- I

"1 '192 <41131

, 9 aM Ac#dI';J .......

92

[tmt·l-~ t 1991 j II1IP2 -79/68 tilt 'III'OR. 4B1: :ld3

0 3/18192 :5

/ 118192

4114192 41141'92

IatKior wr:lr for vee 2-? 9/6 8

NETWORK MODEL FOR FIRST COLONY LIFE INSURANCE COMPANY OFfICE ADDITION Lynebbura. Vireinia

B. J. Co:ub:atio:a Joint V.Atun L~"" Vu'" 24,06

Ralph J. Stephenson FE PE ConsuJl.inS~ 323 HleWlUvl Jrtve MI.. Pleasant, MIchtIIn 4:6653 ph 5171722537

Page 82: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

.. -tIA-.

PHASE 1 TinD START OF

REI'O'.)ELlII6 ElUSTllI1 D WING - Fa. REI100EL

-W16101

FWoSE 1 'lAC ATE L'IotR LEVEL, I an ADDrTlCW AT

TERRACE .... 1ST FL. ENTIRE 2110 n &.

ENTIRE lRD n DCfPT EIlECUTIYE AREA

PHASE 1

OWNER REt'D'VE HIP.ZMtOJS

";'TERIAL$AT REAR

PHASE 1

E T IR TO SET LATE FINISH OF ACTIVITV

ST ;'11 &. LD'II'I:R LEVEL /----004

PHASE 1

PART IlEI1Il.ISH REaD ¥lUilCAT LOWER

LEYEL-158

PHASE 1

PART IlEI1Il.ISH REaD WORK AT 1ST FL 1079

ADDITION

PHASE 1

CIJI1> DEI1Il.ISIi REaD WORK AT La"""R LEVEL

PHASE 1 CIJI1> DEI1l.ISH REaD 'IotORK AT lSTFL lD70

ADO IT 1011

PHASE 1 r:R~EI'IOOEl=-==--L:-:OW~ER~L£\I~D..'" TO TEt'IPORAR'I' LOUIIIE

AREA

PHASE 1 REMODEL 1ST n 111

Page 83: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

IMASE 1 PHASE I PHASE I PHASE I PHAIIE 1

fCI. Kl\I£ IHTO TEI'IP DEI"IIl..ISH REDO WORK REHODEL TERRACE Kl\I£ LUNCH ROil'! ET/RTO SET LIlUNGE FR\l'I TERRACE AT TERRACE LE\IEL-19 LEVEl.-79 FROM LOWER LEVEL TO COMPLETION DATE 0' LEVEL 197'i ADDITION REnOOELED TERRACE UJNCH RIXI1I'1OVE

LEVEL - 1919 ADDITION

5E I PHASE I PHASE I

COtA.ETE ALL I1DYE CENTRAL fiLES ET IR TO SET LATE TEIRACE LEVEL FROM TERRACE LEVEL FINISH IJ'" CENTRAL

IIB1ODELINl4T In9 AT 11I6111i1E1"1lDELED FILE MOYE AOOTION AREA TO NEW TERRACE

LEVEL - 1919 ADDITION

Page 84: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

D

rill TO DCT 7. 1001

"-PHASE I PHAS[ 1 PHASE 1 PART DEI'IOLISH REQD WORK AT ENTIRE 2ND

FL

CDI'F' DEI'IOLISH REQD WORK AT EICTIRE 211D

Fl

REl"IOOEL ENTIRE :2M) Fl

PHASE I PHASE I

PARI' DEI1OI.ISH REQD CDI'F' DEI'IOLISH REQD REMODEL 3-68" 3·79 WORK Ar ~68 &. 3-79 WORK AT ~68 &. ~ 79 AREAS EtaP'T FIR EXCEPT fIR EkECUTIV£ EXCEPT FIR EICECUTI\'E EXECUTIVE SUITE AREA

AREA 1------1 AREA 1------4

PHASE 2

PREPARE" ISSUE EXECUTIVE SUITE DESIIIIDRAWIN6S

PWtSE2

EXECUTIYE GRn.P VACATE :SRD Fl fi8

AD[QUATE FtJI CHANGEI-____ -I ORDER

ORDER. DETAIL. APPROVE, FAB &

DELIYER LOMB LEAD

AIIS[2

ORDER &. DELIVER EARLY MATERIALS FOR

EXECUTIVE SUITE REl'IOOElINS AOEQUA TE

TO ElE61N WtJlK

PHASE 2 OEI'I(I.ISHREQD

EXISTINS W!H( AT 3RD FL 68 ElI£C11f lYE I-____ ~ AREA

rrEl"l9AREXECUTWEr-________________________________________ ~

SUITE REIfQOELlMB

Page 85: Consulting Engineer Mt. Pleasant, Michigan 48853 · the lags must be identified immediately and corrections made if the project is to be completed as desired. I suggest close front

PIIAIE 1 MOllE POLICY HOI.DER ~V'CESFRDn tSTFL 68 TO MIRE 2M> fL -

MSE 1 MOllE CLAlnS.

PRDDlI:T SUPPORT. EMPLOYEE P\..ANS ...

ANNUITIES III'TO REl'1ODELED H8 ...

3-19 SPACE EICCPT FOR EIlEC AREA

MSE2 REMODEl EXECUTIVE AREAS AT liD FL 68

Totl' noet time ElIrly $\1I"t

PHASE 1

PHASE 2

1IB100B.. 1ST FL M TO NEW INIlESTrElI'T

ACCOUNT'I«>

PHASE 1

ET IR TO SET IXHI' I'IOVE INTO lllO FL 6fI

SPACEn,NJS EIlECUTI'oIE AIlEA

PHASE 2

FCL EIlECUTIVE Sf AFF MOllE IIITO RErDl:ELED

3RDFL 68

DunnIon Early lint, ..

03-5£LECT N\JI1I!lER OF TEST PILES TO II! • Activity 1'.,lIntlll"

~S£2 tIM M:COUHI"IH

FAOI'lTiRRACE 611TO REKJDEUD ENTIRE

ISTFL

PllASE2

E TIl TO SET LATE FIIiSH Of e:xa:urIYE DCQlPAICY OF 3RO FL

r-----I 68

USED&' LOCATION - t (llCIImple)

• Actlvll.\l dlSCl'1pllan • Actlvll.\l88l1mOUld dlnlUan

III 'I~ w0l'1dll9 deys

otl ot6 ot2 ot7 ot3 ote ()oH 0t9 ot:) ~o

PHASE :s REr100B.. YACATED EVLlCO ItOIIE F10I OFF

TERRACE 68 TO lEW SITE INTO RB'tOOB..£D EVLICO tERRM:l 6fI

J\ kI~: ",I f;:' ",",,, .. f <"/'l

'j;."" ';.

,

r:.'~1

r C HEIWOK:~ODEL FOR FIRSI COLONY LIFE INSURANCE

l8IIu4t"l - Octo1*' 7, 1991 IltIIV8l tCia ..., ~ p1al1 I'IIG. zez

COMPANY OFFICE ADDITION Lyncbbufa. Virginia

H. J. ColwtLuutioA Joiat v.atun Ly~ Vi.rstI.aia at506

Ralph J. S\ephenson P£ PE Ca:IsuJLtng ~ 323 H:IIrwa1ha Ik'tve Nt. P.IeIsant.. Mi.Ghi&Jen 4:ee 53 ph 511 T72 2537

Sheet #s1