Integrity - Competence - ServiceIntegrity - Competence - Service
Consultant Selection2017
(LPA Manual, Section 2)
![Page 2: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/2.jpg)
Integrity - Competence - Service
MaineDOTContract Procurement Office
CPO is responsible for the development, implementation, and oversight of MaineDOT’s
contractual policies, procedures, and standards for non-construction contracts.
Contact Information: 207-624-3262 or www.maine.gov/mdot/cpo
3.28.17
2
![Page 3: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/3.jpg)
Integrity - Competence - Service
Consultant Procurement Process
Qualifications Based Selection (QBS) –
• The method used to select consultants who provide engineering and architectural services that will lead to a construction project.
• This is pursuant to Part 172 of Title 23 of the U.S. Code of Federal Regulations.
• Selection is based solely on their qualifications.
3.28.17
3
![Page 4: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/4.jpg)
Integrity - Competence - Service
Consultant Procurement Process
How do you begin?– Develop a detailed scope of work.
• This will be the basis for the consultants’ proposals.
– Generate an Independent Government Estimate. • This will assist in determining which consultant selection
method will be used.• It will be the basis for negotiations with the consultant. • A consultants may be hired to develop a gov’t estimate, but
those consultants cannot then submit proposals
3.28.17
4
![Page 5: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/5.jpg)
Integrity - Competence - Service
Independent Government Estimate
What goes into an Independent Gov’t Estimate?
• Tasks - based on Scope of Work
• The required Consultant positions
• Number of labor hours by task and position
• Direct salary by position
• Overhead rate (typically 160% to 180%)• Profit/Fee (typically ~ 8% to 10%)
• Direct expenses (travel, sub-consultants printing, etc.)
3.28.17
5
![Page 6: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/6.jpg)
Integrity - Competence - Service
Independent Government Estimate
6
3.28.17
![Page 7: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/7.jpg)
Integrity - Competence - Service
Consultant Salary Limits
• MaineDOT has determined that $50 per hour, up to $104,000 annually, is a “fair and reasonable” direct salary rate.
• Requirement for MaineDOT-funded projects.
• Approved waiver needed to exceed this rate.
• No limit on overhead, but rates must be supportable.
3.28.17
7
![Page 8: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/8.jpg)
Integrity - Competence - Service
Consultant Selection
Contract requirements should not be broken down into smaller components merely to avoid using the Brooks Act
selection method.
8
3.28.17
![Page 9: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/9.jpg)
Integrity - Competence - Service
Consultant Selection Methods
• Simplified selection process may be used for contracts, including modifications, that are <$25,000.
• Competitive selection process must be used for contracts, including modifications, >$25,000 and <$150,000.
• Brooks Act (publicly advertised) shall be used for contracts including modifications that are >$150,000.
3.28.17
9
![Page 10: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/10.jpg)
Integrity - Competence - Service
Consultant Selection Method
10
3.28.17
![Page 11: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/11.jpg)
Integrity - Competence - Service
Selection Process
REMINDERS:1. Obtain MaineDOT project manager’s approval when using the
Simplified Selection Process seeking proposal from a single, qualified consultant.
2. Following the technical proposal review:a) Rank consultantsb) Revise Government Estimate
3. Consultants must always sign the contract first.
4. Send a copy of the executed agreement to MaineDOT.
5. Document your process and retain records for your files.
3.28.17
11
![Page 12: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/12.jpg)
Integrity - Competence - Service
Payment Methods
• Burdened Hourly Rate (Fixed or Adjustable)
• Cost Plus Fixed Fee
• Commercial Rate (Hourly or Task)
• Lump Sum
3.28.17
12
![Page 13: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/13.jpg)
Integrity - Competence - Service
Actions that may risk your funding• Using lowest price as a selection method.
• Failing to comply with the Brooks Act, requiring competitive, qualifications-based selection.
• Starting work before executing a contract.
• Allowing extra work without an executed contract modification in place.
• Performing work past the contract expiration date.
• Exceeding the maximum amount of a contract without an executed modification in place.
3.28.17
13
![Page 14: Consultant Selection - Maine€¦ · – Generate an Independent Government Estimate. • This will assist in determining which consultant selection method will be used. • It will](https://reader035.vdocuments.us/reader035/viewer/2022071003/5fc09af09672554a2422172e/html5/thumbnails/14.jpg)
Integrity - Competence - Service
Consultant General Conditions
Engineering & architectural work on Locally Administered Projects are governed by MaineDOT’s Consultant General Conditions. They can be found on the CPO website: www.maine.gov/mdot/cpo
Key clauses:• Project Records• Consultant’s duties regarding sub-consultants• Flow down provisions for sub-contracts • Accuracy and redesign responsibility for errors and omissions• Electronic exchange of CADD data (format of work) • Progress Reports• Indemnification and insurance requirements • Default, termination, or suspension • Copyright and licenses• Conflict of interest• Federal Provisions