construction update september 2018 · movement around this structure is the key focus when work...
TRANSCRIPT
UP
DA
TE S
EP
T 2
01
8
Construction Update September 2018
Construction of the South East Flows Restoration Project (SEFRP) continued through August 2018. Drainage flows and
wet ground conditions have placed a temporary hold on works until late spring 2018 when the remaining 5 of the 85
structures will be completed as well as finishing works along the entire drain corridor.
With sufficient rainfall accumulating in the Blackford
catchment over the recent winter months, a trial diversion of
water into the newly completed SEFRP channel commenced
on Tuesday 4 September 2018. It involves closure of the gates
on the new Blackford regulator which is situated just
downstream of the new channel, so that water is pushed back
upstream enabling water to flow north into the new flowpath.
Flow releases are continuing and vary between 150 to
250 ML/day along the drain corridor. It is successfully
demonstrating the operational capabilities of the new
flow path and flows will continue to be monitored over
the coming weeks (Note 1ML = 1 megalitre = 1 million
litres).
Landholders are making a significant contribution in this trial, by
actively monitoring flows through their properties and reporting
their observations to project staff.
Localised water diversion into the Yeulba and Taratap Swamps
allowed 800ha of en route wetlands to be filled this year, and will
provide optimal waterbird habitat over the coming seasons for
locally breeding species such as ducks and swans, and migratory
visitors like Latham’s Snipe and Sharp-tailed Sandpiper.
Localised diversion into the Tilley Swamp Watercourse took place in
late July to assist with construction works in the main Tilley Swamp
Drain.
Trial water diversion into the new flowpath
Trial operation of the Blackford Regulator commenced on 4
September 2018.
Tilley Swamp Drain adjacent to Tilley Swamp
UP
DA
TE M
ON
TH
2016
The new regulating structure at the northern end of Morella Basin is reaching completion and passage for native fish
movement around this structure is the key focus when work resumes in late spring 2018.
Installing passage for native fish movement around the
upgraded Salt Creek outlet has progressed and due to
high water levels in the Coorong South Lagoon, works will
be completed in late 2018 as water levels allow. Recent
flows out of Salt Creek were required as part of the
construction program.
A section of the 2km Ngrugie Ngoppun Walk on the
northern side of Salt Creek remains closed during
construction to uphold public safety. No campgrounds or
other access within the Coorong National Park is
affected by this closure and further information is
available on the National Parks SA webpage.
Landholders continue to assist construction activities and are sincerely thanked for their cooperation and flexibility.
Cultural Heritage monitoring by the South East Aboriginal Focus Group and the Ngarrindjeri Regional Authority has
assisted on ground works.
The South East Flows Restoration Project is part of the
Coorong, Lower Lakes and Murray Mouth Recovery Project
funded by the Australian Government and the South
Australian Government’s Murray Futures Program.
For more information
Natural Resources South East
South East Flows Restoration Project
www.naturalresources.sa.gov.au/southeast/projects/se-flows
Significant progress has been made
on the new regulating structure at
the northern end of Morella Basin.
Progress from July – Sept (L – R).
Construction to complete the new outlet structure and fish
passage at Salt Creek will resume when water levels allow.