construction status - apr 2018 · construction status - apr 2018. puravankara limited, 130/1,...
TRANSCRIPT
Construction Status - Apr 2018
Puravankara Limited, 130/1, Ulsoor Road, Bangalore - 560 042,Call - 080 – 67724001, Email: [email protected]
Building-1 P.C.C. below footing and Footing casting in progress Building-2 (Parking -2) slab shuttering work in Progress
Building-3 (parking - 3) slab shuttering is in Progress Building-4 1st typical floor Slab shear wall Reinforcement is in progress
Building-5 1st typical floor Slab completed Building-6 parking slab-2 (Pour-2) Reinforcement work in progress for parking-3 slab and shuttering work for parking-3 in progress
Building-7 Parking-2 slab shuttering in progress Building-8 1st typical slab (Pour-2) Pour-1 ready for casting
Building-9 1st typical floor slab (Pour -2) shuttering and Reinforcement in progress Building-10 Earth Work Excavation completed
PURVA SILVERSANDSWORK PROGRESS REPORT - April '18
PURVA SILVERSANDS MARKETING PROGRESS REPORT -March 2018-(As On 30.04.2018)
S. No ACTIVITIESBuildings
1 2 3 4 5 6 7 8 9 10 11 12 13
1 Earth Work Excavation 100% 100% 100% 100% 100.00% 100% 100% 100% 100% 100% 100% 100% 100%
2 Plain Cement Concrete 60% 100% 100% 100% 100.00% 100% 100% 100% 100%
3 Raft/Footing Reinforcement 30% 100% 100% 100% 100.00% 100% 100% 100% 100%
4 Raft/Footing Concrete 30% 100% 100% 100% 100.00% 100% 100% 100% 100%
5 Plinth beam casting 100% 100% 100% 100.00% 100% 100% 100% 100%
6 Grade Slab Concreting
7 Column Concrete ( Plinth Top to -1st Parking Floor Slab ) 100% 100% 100% 100.00% 100% 100% 100% 100%
8 1st Level Parking Floor Slab Shuttering 50% 100% 100% 100.00% 100% 50% 100% 100%
9 1st Level Parking Floor Slab Reinforcement 100% 100% 100.00% 100% 100% 100%
10 1st Level Parking floor Slab Concrete 100% 100% 100.00% 100% 100% 100%
11 Column Concrete ( 1st Parking Floor Slab to 2nd parking slab) 100% 100% 100.00% 42% 100% 100%
12 2nd Level Parking Floor Slab Shuttering 80% 100% 100.00% 20% 100% 70%
13 2nd Level Parking Floor Slab Reinforcement 100% 100.00% 100% 60%
14 2nd Level Parking floor Slab Concrete 100% 100.00% 100% 50%
15 Column Concrete(2nd Parking Floor Slab to 3rd parking slab) 100% 100.00%
16 3rd Level Parking Floor Slab Shuttering 100% 100.00%
17 3rd Level Parking Floor Slab Reinforcement 100% 100.00%
18 3rd Level Parking floor Slab Concrete 100% 100.00%