construction standards and concrete specifications

92
Construction Standards and Concrete Specifications for the City of En .glewood, Colorado

Upload: others

Post on 01-Oct-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Standards and Concrete Specifications

Construction Standards and

Concrete Specifications for the

City of En.glewood, Colorado

Page 2: Construction Standards and Concrete Specifications
Page 3: Construction Standards and Concrete Specifications

CONCRETE STANDARDS

AND

CONCRETE SPECIF/CATIONS

MANUAL

CITY OF ENGLEWOOD, COLORADO

DEPARTMENT OF PUBLIC WORKS

APRIL, 2011

Page 4: Construction Standards and Concrete Specifications
Page 5: Construction Standards and Concrete Specifications

TABLE OF CONTENTS

Permits

Special Provisions

Portland Cement Concrete

Placing and Finishing Concrete

Construction Standards

Section

1

2

4

5

A

Page 6: Construction Standards and Concrete Specifications
Page 7: Construction Standards and Concrete Specifications

ATTENTION CONCRETE CONTRACTORS

In the past, Englewood contractors have been required to saw the asphalt 12 inches from the lipline to allow adequate space for concrete forms and proper asphalt patching. This may no longer be required where the asphalt edge is in good condition and is maintained during removal and replacement of the curb and gutter, and thus providing an acceptable finishing edge for the new concrete. The City inspector will make this determination. In the event the asphalt line is in poor condition, or a good line cannot be maintained, the City will assess a four dollar ($6.90) per linear foot charge, and the contractor will be required to saw cut the asphalt 12 inches from the lipline. Prior to patching, it shall be the responsibility of the contractor to clean this area for patching to avoid an additional four dollar ($6.90) per linear foot charge.

If the sawed edge is damaged after removal of the forms, a new saw cut will be necessary to maintain a straight edge.

Barricades are to remain in place to protect the concrete as well as the asphalt edge. The City will patch the asphalt as soon as the concrete has cured sufficiently, generally within five to seven days.

Rick Kahm, Director Department of Public Works

08/2013

Page 8: Construction Standards and Concrete Specifications
Page 9: Construction Standards and Concrete Specifications

STREET CUT PERMIT ISSUED IN CONJUNCTION WITH THIS CONCRETE PERMIT (if applicable)

DATE: August 30, 2013

JOBSITE ADDRESS:

I Start Date:

Daythne~

0 L.F. Vertical Curb & Gutter

0 L.F. Sidewalk - Width:

0 L.F. Curbwalk - Type:

0 L.F. Curbcut - Approved By:

Other:

Estimated Value of Work $ 0.00

Special Conditions/Notes:

City of Englewood, Colorado Department of Public Works

PUBLIC RIGHT-OF-WAY

CONCRETE PERMIT

~ LICENSE EXPIAl:S:

Completion Date:

Permit Fee

Asphalt Patch

Re-Inspection Fee

Work w/o Permit

$ 0.00 + AC 1400 As halt

Permit No.

Note: See following page for additional permit information.

FEES: $100.00 $ 0.00

$6.90 I SF $ 0.00

$50.00

Double Fee $ 0.00

$ 0.00 = $ 0.00 AC 1500 TOTAL FEES Concrete

All work is to be done with permission of Property Owner.

Contractor Initial

All work is to be done in accordance with approved plans.

Contractor Initial

I/We agree to call (303) 762-2500 for inspection of forms at least four (4) hours prior to placement of concrete. I/We shall comply with permit requirements and all specifications of the City of Englewood, and will place construction signing in accordance with the M.U.T.C.D.

CITY APPROVAL:

Contractor Signature Director of Public Works

Prepared by:

Accepted/Date Inspector Rejected/Date Inspector Special Conditions

SEE REVERSE FOR GENERAL REQUIREMENTS

J

Page 10: Construction Standards and Concrete Specifications

City of Englewood Department of Public Works

GENERAL REQUIREMENTS Concrete Permits

1. This permit authorizes Concrete work only in the public right-of-way. In no event does this permit authorize work of any kind, even work of a temporary nature, outside of the public right-of-way.

2. This permit does not alleviate the requirement for other necessary permits such as COOT permits, Building Permits, or Excavation Permits.

3. A copy of this permit shall be kept on site while work is in progress and shall be available upon request to Police, Code Enforcement, or City representatives.

4. Work started without a permit is subject to double fee.

5. In the event that an inspection fails, the contractor shall be charged an additional $50.00 for each inspection necessary until such time as the City inspector approves. Engineering Services will mail billing for failed inspections.

6. Expansion joints are required in all locations where private sidewalk or driveways abut to City right-of-way concrete.

7. Concrete replacement must be done within five (5) working days after removal of said concrete.

8. Concrete mix design shall be 4000 psi or 5000 psi with Fiber Mesh or as directed by City Engineer.

9. If damage occurs to underground facilities, contractor must immediately notify Facilities operator (i.e. gas, water, telecommunications, etc.). If the presence of flammable, toxic or corrosive gas exists, contractor must immediately notify the Facilities operator and call 911, then take immediate action to protect the public and nearby properties.

10. When necessary to remove asphalt, the contractor shall cut (min 1 ft wide) and remove asphalt, and prepare cut for City crews to patch.

11 . The Contractor shall provide proper barricades to allow pedestrian and vehicle traffic to navigate the area safely.

12. Upon written notice to the contractor, this permit may be revoked or suspended by the City for: A. Major deviation from the approved plans, except for field changes authorized by the City. B. Failure to comply with any special conditions of this permit. C. Violation of any provision of the Englewood Municipal Code or other City ordinance or state law relating to the work. D. Determination of any condition, or performance of any act, constituting or causing a condition endangering life or

damage to public or private property.

13. State law requires that you contact the following agencies at least two (2) business days prior to the start of excavation: Utility Notification Center of Colorado 1 (800) 922-1987 City of Englewood - Traffic Division (303) 762-2512 City of Englewood - Utility Department (303) 762-2635

14. Contractor must provide advance written notification to all businesses for right-of-way construction work that may intefere with public parking or access to those businesses.

Page 11: Construction Standards and Concrete Specifications

SECTION 2

SPECIAL PROVISIONS

Paragraph Title

2.1 Insurance Limits

2.2 Concrete Removal

2.3 Obstructions

2.4 Maintenance of Traffic and Drainage

2.5 Final Acceptance

2.6 Water

2.7 Tamping

2.8 Waste Disposal Areas

2.9 Barricades and Barricading

2.10 Backfilling, Backsloping, Asphalt Patching, Final Cleanup

2.11 Construction Permits

2.12 use of Fly Ash

2.13 Contractor's Guarantee

2.14 Stop Boxes and Meter Pits

2.15 Opening to Traffic

2.16 Sawing Asphalt

2.17 Utility Locates

2.18 Fire Hydrant Policy

2.19 Handicap Ramps

2.20 Spalling Concrete

2.21 Concrete Markings

2.22 Sawing Concrete

2.23 Concrete Alley and Cross-pans

2.24 Fiber Mesh

~

2-1

2-1

2-1

2-1

2-1

2-1

2-1

2-1

2-2

2-2

2 - 2

2-2

2-2

2-2

2-2

2-2

2-2

2-3

2-3

2-3

2-3

2 - 3

2-3

2 - 3

Page 12: Construction Standards and Concrete Specifications
Page 13: Construction Standards and Concrete Specifications

SECTION 2

SPECIAL PROVISIONS

2.1 Insurance Limits. The Contractor shall carry throughout the life of the contract, the insurance called for in the General Contract Conditions in minimum limits as follows:

Public Liability Public Liability Property Damage

Automotive Liability Public Liability Property Damage

Minimum Limits $1,000,000 $1,000,000

Minimum Limits $1,000,000 $1,000,000

2.2 Concrete Removal. Concrete removal shall not precede concrete placement by more than two (2) days. Each removal shall be barricaded, per MUTCD, for the protection of the public. If this time frame is not being followed, the engineer can direct all removals to stop until this situation is corrected. No time extensions or extra cost associated with the stoppage will be granted.

2.3 Obstructions. No extra payment shall be considered or allowed for removal or protection of any obstruction which can be seen by a visual inspection, nor shall any payment be made for extra work involved in the protection or the repair of damage to any underground service, the presence of which can be ascertained by inspection of appropriate maps of the utility companies or the City, or by proper inquiry with the utility companies, the City and the property owners.

2 .4 Maintenance of Traffic and Drainage. During the progress of the work, the Contractor shall provide free access to fire hydrants, water and gas valves; gutters and water-ways must be kept open or other suitable provisions made for the removal of storm water. The Contractor shall build and maintain temporary driveways, bridges and crossings, such as in the opinion of the Engineer as necessary to reasonably accommodate the public. In the event of the Contractor's failure to comply with the foregoing provisions, the City may without notice, cause the same to be done and deduct the cost of such work from any money due, or to become, due, the Contractor under this Contract. Performance of such work by the City shall serve in nowise to release the Contractor from his general or particular liability for the safety of the public or the work.

2.5 Final Acceptance. Upon written request of the Contractor, the City will give final acceptance of logical areas of the Program as they are completed to the satisfaction of the Engineer.

2.6 Water. Water may be obtained by the Contractor from municipal fire hydrants designated by the Utilities Director for the City. The Contractor shall be responsible for negotiating a flat fee to be paid to the Utilities Department for the water to be used on the Program. The Contractor shall be liable for any damage to fire hydrants and adjacent property resulting from the use of the hydrants. Any damage so incurred shall be repaired by the City at the expense of the Contractor.

At the direction of the Engineer, water shall be furnished to insure the compaction of the subgrade, select material and gravel base course and shall be included in the unit bid price for the various units requiring water by the Engineer.

2.7 Tamping. To insure proper compaction of the subgrade, select material, and gravel base course, tamping shall be as directed by the Engineer and shall be included in the unit bid price for the various units requiring tamping by the Engineer. Jumping-jack and plate tampers must be on site at all times during sub grade preparations.

2 - 1

Page 14: Construction Standards and Concrete Specifications

2.8 Waste Disposal Areas. The disposal of all waste material such as broken concrete, pavement, trees, roots, rocks, pipe and excess earth material, shall be the sole responsibility of the contractor.

2.9 Barricades and Barricading. At the end of each workday, it shall be the responsibility of the Contractor to check each job site and insure proper barricading is in place. Barricades will not be removed from each job site until the hazard has been removed. All barricades and traffic control devices must have working lights when in service.

2.10 Backfilling, Backsloping, Asphalt Patching, Final Cleanup. Wherever the installation requires backfilling or backsloping, the top six (6) inches shall be top soil. The backfilling, backsloping, asphalt patching, and final cleanup shall be completed within 3 days of concrete pour. If this time frame is not being followed, the engineer can direct all other work to stop until this situation is corrected . No time extensions or extra cost associated with the stoppage will be granted. No work shall be paid for until all backfilling, backsloping, asphalt patching and final cleanup is complete.

2 . 11 Construction Permits. All construction permits necessary for this project shall be the responsibility of the Contractor to acquire f rom the City of Englewood, 1000 Englewood Parkway, or the Colorado Department of Transportation.

2.12 use of Fly Ash. Refer to Section 4, 4.04

2.13 Contractor's Guarantee. The Contractor shall guarantee that the paving shall remain in good order and repair for a period of two (2) years from all causes arising from defective workmanship and materials, and to make all repairs arising from said causes during such period without further compensation, and shall guarantee the concrete curbs, gutters and sidewalks against defective workmanship and materials, and shall keep the same in good order and repair without further compensation for a period of two (2) years from and after completion and acceptance thereof by the City. The determination of the necessity for the repair or replacement of said paving, curbs and sidewalks or any portion thereof, shall rest entirely with the Engineer whose decision upon the matter shall be final and obligatory upon the Contractor.

2.14 Stop Boxes and Meter Pits. All stop boxes and meter pits located in the sidewalk, driveway or any finished surface will be at finished grade, level and in good condition by the end of the project. All lids will be free of cement or finished material on top and sides. Any adjustment to stop boxes or meter pits will be completed by the Contractor.

2.15 Opening to Traffic. Concrete shall not be opened to traffic for a period of at least seven (7) days after the last concrete has been placed, or for a longer period of time if the Engineer considers it necessary. If a 5000 psi mix is used, traffic may be opened after three days. It shall be the obligation of the contractor to maintain suitable barricades for this purpose.

2.16 Sawing Asphalt at Lip Line. The City is requiring that you saw cut a minimum of twelve(12) inches away from the lip and the asphalt removed. After pulling your forms, clean the area so that it is ready for patching. If the sawed edge is damaged after pulling of the forms, make sure the damaged area is squared out.

Barricades are to be left to protect the fresh concrete as well as the asphalt edge. The contractor is responsible for patching these areas with a minimum of three (3) inches of asphalt or as directed by the Engineer. 2) No payment will be made for sawing and patching when excess damage to adjacent asphalt is caused by carelessness or negligence of the Contractor as determined by the Engineer.

2.17 Utility Locations. It is the Contractor's responsibility to contact Utility Notification Center of Colorado (Ph . 1-800-922-1987); and City Traffic Division (Ph. 303-762-2514) for all utility locates prior to construction.

2 - 2

Page 15: Construction Standards and Concrete Specifications

2.18 Fire Hydrant Policy. Hydrant use is strictly regulated by the Englewood Utilities Department. Their hydrant policy shall govern all hydrant use. The Contractor shall be responsible for obtaining these regulations and paying any associated use fees.

2.19 eurb Ramps. This item shall include all material, labor and any incidental work to construct a curb ramp (Bid Item #133). All ramps shall be constructed per enclosed revised CDOT Detail 608-1. Detectable warning surface color shall be Brick Red manufactured by Pavestone or an approved equal. An area of up to 56 SF of 6" thick walk and 14.0 LF of 8" thick curb and gutter shall be included in the unit price for each curb ramp.

2.20 Spalling Concrete. The Contractor guarantees all concrete against spalling for two (2) years from the date of acceptance. (Note: It is the City's contention that concrete that spalls is due to materials and/or workmanship if placed between April 1 and October 15; additionally, if placed between October 16 and March 31, the Contractor assumes responsibility knowing the concrete may be exposed to chemical deicers that may also affect the finish of the concrete.)

2.21 Concrete Markings. All concrete removals are marked with a pink dot in the Center of the stone, or arrows at both ends of removal. If removal is in question, contact the Inspector on the job.

2.22 Sawing Concrete. Concrete sawing will be paid for only as marked by the Engineer. Any concrete sawing by the Contractor for his convenience shall be at the Contractor's expense.

2.23 Concrete Alleys. Entrances and cross-Pans. All concrete placed in alleys and cross-pans or directed by the engineer shall have fiber mesh, placed 8" thick, and use an 5000 psi mix with fiber mesh.

2.24 Fiber Mesh. All items defined in 2.30 shall have~,, fiber mesh and it shall be added to the mix at a rate of l~ lbs. per cubic yard.

2 - 3

Page 16: Construction Standards and Concrete Specifications
Page 17: Construction Standards and Concrete Specifications

Paragraph

4.01

4.02

4.03

4.04

4.05

4.06

4.07

4.08

4.09

INDEX

SECTION 4

PORTLAND CEMENT CONCRETE

Title

General

Materials

Storage of Materials

Concrete Mixture Requirements

Proportioning of Materials

Batching Plant

Mixing Concrete

Protection

Testing

Page

4-1

4-1

4-2

4-3

4-4

4-4

4 - 5

4-6

4-6

Page 18: Construction Standards and Concrete Specifications
Page 19: Construction Standards and Concrete Specifications

SECTION 4

PORTLAND CEMENT CONCRETE

4.01 General. Portland Type I / II cement, air entrained, concrete shall consist of Portland Cement, mineral aggregates (both fine and coarse) , water, and any specified admixtures mixed in accordance with the requirements of these specifications and as directed by the Engineer.

All materials, methods of preparation, and construction shall conform to the requirements of these specifications.

4.02 Materials.

A. Cement . Portland Cement shall conform to the "Standard Specifications for Portland Cement" (A.A.S . H.T.O. Designation: M-85) and shall be Type I / II or shall be air entraining Portland Cement conforming to A . A.S.H.T . O. Designation: M-85, Type I / IIA.

B. Fine Aggregate . Fine aggregate shall be composed of clean, hard, durable uncoated particles of stone, free of lumps of clay, alkali, soft or flaky materials, loam and organic matter, well graded from coarse to fine and conforming to the following requirements:

1. Gradation:

Sieve Size 3/8" No. 4 No. 16 No. 50 No. 100

2. Deleterious Substances.

Clay lumps

% Passing 100 95-100 45-80 10-30 2-10

Material finer than No. 200 sieve Material floating on a liquid having a

specific gravity of 1.95

Max. % of Weight 1. 0 3.0

0.5

. 3. Organic Impurities. All fine aggregates shall be free from injurious amounts of organic impurities and producing a color darker than the standard shall be rejected unless they pass the following mortar strength test.

4. Mortar Strength. Fine aggregate shall be of such quality that when made into a mortar and tested in accordance with the "Standard Method of Test of Measuring Mortar-Making Properties of Fine Aggregate" (A.A.S.H . T . O. Designation: T 71), the mortar shall develop a compressive strength at seven (7) and twenty-eight (28 ) days of not less then ninety-five (95) per cent of that developed by the mortar specified in that method as the basis for comparison .

5 . soundness. When tested in accordance with the "Tentative Method of Test of Soundness of Aggregates by Use of Sodium Sulfate: (A.A.S.H.T.O. Designation: T 104), the weighted average loss in five (5) cycles shall not exceed ten (10) per cent.

6. Fineness Modulus. Fine aggregates shall have a fineness modulus between 2.50 and 2 . 90 .

4 - 1

Page 20: Construction Standards and Concrete Specifications

C. Coarse Aggregate. Coarse aggregate shall consist of crushed stone or gravel having hard, strong, durable pieces, free from adherent coating and conforming to the following specifications:

1 . Gradation. Coarse aggregate shall be well graded between the following limits:

Sieve l" 3/4" 3/8" No. 4 No. 8

% Passing 100 95-100 20-55 0-10 0-5

2. Deleterious Substances. The maximum amount of any one of the deleterious substances given below shall not exceed the following percentage by weight:

Material finer than No. 200 sieve Shale Chert Coal Clay lumps Soft fragments Material floating on a liquid having a specific

gravity of 1.95

Max. % of Weight 1.50 1. 0 1. 0 1. 0 0.25 3.00

1.0

The maximum amount of any combination of the deleterious substances listed in the foregoing shall not exceed three (3) per cent by weight.

3. Abrasion. When tested in accordance with "Standard Method Test for Abrasion of Coarse Aggregate by Use of the Los Angeles Machine" (A . A.S.H.T.O. Designation: T 96), all weighted average loss in five (500) revolutions shall not exceed forty (40) per cent.

D. Water. When used in concrete shall be clean, clear, free from oil, acid, alkali, vegetable matter or other substance injurious to the finished concrete.

E. Air-Entraining Admixture. The Contractor may elect to use a regular Portland Cement with the addition of an air-entraining admixture. Air-entraining admixtures shall conform to the requirements of A.A.S.H.T.O. Designation: M 154.

4.03 Storage of Materials.

A. Cement. Cement may be shipped from pre-tested and approved bins at the mill. The cement shall be well protected from rain and moisture, and any cement damaged by moisture or which fails to meet any of the specified requirements shall be rejected and removed from the work. Cement stored by the Contractor for a period longer than sixty (60) different brands, types, or from different mills shall be stored separately.

B. Aggregate. Aggregates shall be handled and stored at the site in such a manner as to avoid a separation of the coarse and fine particles and contamination be foreign materials. Sites for stockpiles shall be prepared and maintained in such manner as to prevent the mixing of deleterious materials with the aggregate. The Contractor shall deposit material in stockpiles at the batching plant site until the moisture content becomes uniform. Stockpiles shall be built in layers

4 - 2

Page 21: Construction Standards and Concrete Specifications

not to exceed five (5) feet in height, and each layer shall be completed before beginning the next one.

Coning or building up stockpiles by depositing the materials in one place will not be permitted.

4.04 Concrete Mixture Requirements. The concrete mixture shall meet the following requirements:

TABLE OF CONCRETE REQUIREMENTS f'c 4000 psi

Property Portland Cement Class F fly ash Water-cement ratio Entrained air Slump

Fine aggregate Coarse aggregate

7 day 28 day

Type I/II or Type I / IIA lbs/c.y % replacement by weight

per cent inches

Aggregate Proportions Per Sack of Cement

lbs. lbs.

Minimum Compressive Strength

psi psi

TABLE OF CONCRETE REQUIREMENTS f'c 5000 psi

Property Portland Cement Class F fly ash Water-cement ratio Entrained air Slump

Fine aggregate Coarse aggregate

7 day 28 day

Type I/II or Type I /I IA % replacement by weight

per cent inches

Aggregate Proportions Per Sack of Cement

lbs. lbs.

Minimum Compressive Strength

psi psi

Min . 564

5 2

150 300

2400 4000

Min. 615

5 2

150 300

3000 5000

Max .

30 .45 8 4

230 380

Max. 720 30 .40 8 4

230 380

Concrete shall be uniformly plastic, cohesive, and workable. Workable concrete is defined as concrete which can be placed without honeycomb and without voids in the surface. Workability shall be obtained without producing a condition such that free water appears on the surface when finished. The consistency of the mix shall be that required for the specified conditions and methods of placement; however, the previously determined maximum water cement ratio shall not be exceeded.

The properties of the concrete mixture will be determined by the Engineer to insure compliance with these specifications. Modifications will be made in the material proportions as are necessary to provide a satisfactory concrete mixture.

4-3

Page 22: Construction Standards and Concrete Specifications

4.05 Proportioning of Materials.

A. Mixed Proportions. The actual proportions of all materials entering into the concrete mixture shall be determined by the Contractor within the limits set forth above and shall be submitted to the Engineer for approval prior to the placement of any concrete. The proportions shall be changed whenever necessary to maintain the workability, strength and standard of quality required for the concrete covered by these specifications, and to meet the varying conditions encountered during the construction. The fine aggregate and coarse aggregate shall be measured separately for each batch of concrete. The cement shall be in contact with the aggregate no longer than forty-five (45) minutes before being deposited in the mixer.

B. Measurement. The Contractor shall provide the equipment necessary to measure and control the amount of each material in each batch of concrete . All aggregates shall be mechanically batched and measured by weight. Bulk cement shall be weighted, but cement in unopened bags as packed by the manufacturer may be used without weighing. If bag­cement is used, batches shall be proportioned so that fractional bags will not be required. One bag of Portland cement will be considered as ninety-four (94) pounds. Mixing water and air-entraining admixtures may be measured by volume or by weight. One gallon of water will be considered to weigh 8.33 pounds.

4.06 Batching Plant .

A. General. Separate bins or compartments shall be provided for the different sizes of aggregates to be batched and for bulk cements when used. The compartments shall be of ample size and so constructed that the materials will be kept separated under all working conditions. The plant shall be capable of ready adjustment to compensate for the varying moisture contents of the aggregates, and to change the weights of the materials being batched.

B. Weighing of Materials. Aggregates may be weighed in separate weigh­batchers with individual scales, or cumulatively in one weigh-batcher on one scale . Bulk cement shall be weighted on a separate scale in a separate weigh-batcher. Water may be measured by weight or by volume .

The plant shall be arranged so as to facilitate the inspection of all operations at all times. Weighing of materials from the batching equipment shall be within the following limits of accuracy:

Material Cement

Per Cent 1

Water 1 Aggregate 2 Air-Entraining Admixture 3

C. Water-Batcher. A suitable water-measuring device shall be provided that will be capable of measuring the mixing water within the specified requirements for each batch. The mechanism for delivering water to the mixers shall be such that leakage will not occur when the valves are closed. The filling and discharge valves for the water­batcher shall be so interlocked that the discharge valve cannot be opened before the filling valve is full closed.

D. Dispenser. A suitable device for measuring and dispensing the air­entraining admixture shall be provided. The device shall be capable of ready adjustment to permit varying the quantity of admixture to be batched . The dispenser for air-entraining admixtures shall be so designed as to permit discharge into the water-discharge lines . The air-entraining admixture shall be discharged simultaneously with discharge of the water into the batch. The entire batch of air-

4-4

Page 23: Construction Standards and Concrete Specifications

entraining admixture shall be discharged prior to the completion of the water discharge cycle.

E. Scales. The scales for weighing aggregates and cement may be of either the beam type or the springless-dial type. They shall be accurate at all loads within the specifications previously stated. A sufficient number of standard fifty (SO) pound weights for calibrating and testing scales shall be furnished by the Contractor for each and testing scales shall be furnished by the Contractor for each plant. All exposed fulcrums, devices and similar working parts of scales shall be kept clean. When beam-type scales are used, provisions shall be made for indicating to the operator that the required load in the weighing hopper is being approached; the device shall indicate at least the last two hundred (200) pounds of load. The weighing equipment shall be arrange so that when operating the bin gates, the operator stands in such a position that the weighing beam or dial is in full view and he can conveniently shovel material from the weighing hopper. A port or other opening for removing an overload of any one of the several materials from the weighing hopper. A port or other opening for removing an overload of any one of the several materials from the weighing hopper shall be provided. There shall be enough clearance at the top to the weighing hopper to permit the scale operator to shovel material out of the weighing hopper. Weighing hoppers shall be constructed so as to eliminate accumulations of tare materials and to discharge fully.

On beam-type scales, at least that part of the total load which is a fraction of 100 pounds shall be indicted on a graduated beam.

Scales shall be protected from air currents that may affect the accuracy of weighing. The scales shall be kept level and in adjustment at all times . Scales for weighing bulk cement in a closed compartment shall be equipped with an independent tare beam, and the scale shall be balanced to the tare before weighing and after discharging each batch of cement. In the case of a springless-dial type of scale, the indicator shall register zero before charging the weighing hopper and after the cement is discharged.

F. Protection. Weighing, indicating, and control equipment shall be protected against exposure to dust and weather.

G. Batch Trucks . When the aggregates are delivered to the mixer in trucks, each batch shall be in a separate compartment of the capacity required by the Engineer. Suitable covers shall be provided for the batch compartments of the trucks to protect the cement from the wind. All trucks, truck bodies, bulkheads and compartments used in proportioning an transporting to the mixer of concrete materials shall be so designed and operated to insure the charging of the mixer, batch by batch, with the proper amounts of each materials without overspillage, intermixing of batches or wastage. Any units which, in the opinion of the Engineer, do not operate satisfactorily, shall be removed from the work until properly rebuilt and corrected.

4.07 Mixing Concrete. Mixing of concrete shall conform to one of the two following methods:

A. Mixer on Project. The mixing machine used shall be of an approved type known as batch mixer and of a design having a suitable device for automatically measuring the proper amount of water accurately to one­half (~) of one (1) percent and for automatically timing each batch of concrete so that all materials will be mixed together for the minimum time required. If the timing device becomes broken or fails to operate, the Contractor will be permitted to continue for the balance of the day and for one additional day without the timing device while

4-5

Page 24: Construction Standards and Concrete Specifications

the same is being repaired providing that each batch of concrete is mixed not less than two (2) minutes.

All of the materials for each batch of concrete, including the water, shall be mixed not less than one and one-half (l~) minutes after all of the materials are in the mixer, which shall revolve at the speed for which it is designed but not less than fourteen (14), or more than twenty (20) revolutions per minute. If, in the opinion of the Engineer, a thorough mixing of the concrete is not obtained during this period of time, a sufficient number of additional revolutions at the same rate shall be given to assure thorough mixing.

The inside of the mixer drum shall be kept free from hardened concrete . No materials for a batch of concrete shall be placed in the mixer until all of the previous batch has been discharged therefrom. Water shall be added at the time the materials are being run into the mixer.

B. Central-Mixed. Shrink-Mixed or Transit-Mixed Concrete . Central-mixed, shrink-mixed or transit-mixed concrete shall be mixed and transported to the site of the work in accordance with "Standard Specifications for Ready-mixed Concrete" (A.A.S.H.T.O. Designation: Ml57) with the following restrictions:

1. Cement Content. Delivery tickets shall show the batch weight per cubic yard for each load.

2. Time of Delivery. Concrete must be delivered and discharged from the truck mixer or agitator truck within a period of ninety (90) minutes after introduction of the water to the cement and aggregate or of the cement to the aggregate. Delivery tickets shall have the time clearly shown thereon, the original or a copy thereof to be furnished the Inspector on the work before the concrete is discharged.

3. Type of Delivery Equipment . Concrete shall be delivered in truck mixers or agitator trucks (trucks providing mechanical agitation by revolving drums or revolving blade in stationary drum) operated, after time required for thorough mixing of the concrete, at the speed designated by the manufacturer as agitating speed. Delivery of the central-mixed concrete shall not be made in non­agitating equipment without securing the prior written approval of the Engineer of the type of equipment to be used and method of operation.

4. Retempering of Concrete. Retempering of concrete which has partially hardened by remixing either with or without the addition of water will not be permitted.

4.08 Protection. It shall be the responsibility of the Contractor to protect from damage all freshly poured concrete regardless of the location or type of structure for a minimum period of seven (7) days or for such longer period as the Engineer may direct. Any concrete which is damaged shall be repaired to the satisfaction of the Engineer prior to acceptance of the completed work.

4.09 Testing. Test cylinders six (6) inches in diameter and twelve (12) inches in length shall be made as directed by the Engineer. Samples of concrete shall be taken in accordance with the "Standard Method of Sampling Fresh Concrete" (A.A.S.H.T.O. Designation: T 141). Test cylinders shall be made in accordance with "Standard Method of Making and Curing Concrete Compression and Flexure Test Specimens in the Field" (A.A.S . H.T.O. Designation: T 23), shall be properly identified as to location which concrete was placed and shall, as directed by the Engineer, be sent to the Laboratory for testing. Test shall be made in accordance with "Standard Method of Test for Compressive Strength of Molded Concrete Cylinders" (A.A.S.H.T.O . Designation: T 22).

4 - 6

Page 25: Construction Standards and Concrete Specifications

Cylinders shall be tested at the age of seven (7) days, at the age of twenty­eight (28) days, and the remaining cylinders held for later testing if considered necessary by the Engineer. The expense of testing the cylinders shall be borne by the City.

4-7

Page 26: Construction Standards and Concrete Specifications
Page 27: Construction Standards and Concrete Specifications

SECTION 5

PLACING AND FINISHING CONCRETE

Paragraph Title

5.01 General

5.02 Reinforcing Steel

5.03 Structural Concrete

5.04 Curb and Gutter, Curbwalk, Sidewalks, Driveways and Cross Pans

5. 05 Curing

5.06 Cold Weather Concreting

5.07 Hot Weather Concreting

5.08 Opening to Traffic

5.09 Measurement and Payment

5-1

5-1

5-1

5-3

5-4

5-4

5-5

5-5

5-5

Page 28: Construction Standards and Concrete Specifications
Page 29: Construction Standards and Concrete Specifications

SECTION 5

PLACING AND FINISHING CONCRETE

5.01 General. The placing and finishing of concrete as described in this section, shall include all forming, placing, reinforcing, finishing and curing.

5.02 Reinforcing Steel. Reinforcing bars shall conform to the Standard Specification for Billet Steel Bars for Concrete Reinforcement (A .A.S .H.T.O. Designation: M 31), shall be "Intermediate Grade", and shall be of the sizes and shapes indicated on the plans.

Wire fabric shall conform to the Standard Specifications for Welded Steel Wire Fabric for Concrete Reinforcement (A . A.S.H.T.O. Designation: M 55 ), and the size shall be 6" by 6" by #10/#10 gage.

5.03 Structural Concrete.

A. Forming. The forms shall be tight and constructed in a workmanlike manner, and shall be of such dimensions and so constructed as to remain rigid and unyielding under the load of wet concrete. The lumber used shall be sound and free from loose knots. The form work shall be so constructed as to permit easy removal without injuring the concrete. Lumber once used in forms shall be cleaned before being used again. Before depositing concrete, the forms shall be thoroughly wetted and cooled, and the space to be occupied by the concrete cleared of shavings, sticks of wood or other debris. Use an approved type of form clamps and ties for all forms. Form ties in walls shall be cut off back of surface of wall.

Whenever concrete is to be left exposed, the forms shall be given special attention and all splinters, defects, loose knots, etc., shall be removed. Chamfer all exposed edges of concrete one (1) inch unless otherwise directed.

Unless otherwise authorized, the form lumber which is in contact with all exposed concrete surfaces shall be plywood or shall be faced with an approved type of composition board. All joints in such plywood or facing material shall be carefully matched to prevent the forming of irregularities in the concrete surface.

The term "exposed concrete surfaces" applies to above ground outside faces of structures.

Approved type metal forms may be used. Battered, bent, or twisted forms which will affect the alignment or appearance of the finished concrete shall not be used.

Openings shall be left at the bottom of the wall forms so they may be cleaned out after the forms have been washed. The time for removal of the form work shall depend on the weather conditions and shall be subject to the approval of the Engineer.

Forms for exposed surfaces shall be coated with oil before reinforcement is placed. The oil shall be a mineral base oil which will not discolor or interfere with the finish of the concrete. Surplus oil on form surfaces and any oil on reinforcement shall be removed before concrete is placed. Forms for interior surfaces and for exterior surfaces not exposed to view may be thoroughly wet with water in lieu of oiling immediately before placement of concrete, except that the freezing weather, oiling will be mandatory.

5-1

Page 30: Construction Standards and Concrete Specifications

B. Placing Reinforcing Steel. Reinforcing steel delivered or stored along the site of the work shall be neatly piled on blocks or timbers in such a way as to keep it off the ground.

Before being placed, all steel shall be thoroughly cleaned of mill rust, scale and of grease or other coatings that will destroy the bond.

Reinforcement shall be carefully placed exactly as indicated on the plans. Bars shall not be bent or straightened in a manner that will injure the material.

Bars shall be accurately and rigidly secured in position by use of such approved metal clips, spacers, bar supports, or hy-chairs as may be necessary. Should it be necessary to supply extra reinforcing bars for the purpose of supporting the mat of reinforcement and tying it together, such bars shall be furnished at the expense of the Contractor.

Splices shall not be made at point of maximum stress and where made, bars shall be lapped at least forty (40) times their least diameter.

Reinforcement shall be secured in position, inspected and approved before placing of concrete.

C. Placing Structural Concrete. The Contractor shall give notice sufficiently in advance of placing concrete to permit proper inspection of forms and reinforcement by the Engineer. Concrete shall be as specified in Section 4.

After the completion of the mixing, the concrete shall be rapidly conveyed to and deposited in the forms. The concrete shall be deposited in such a manner as will prevent the separation of the ingredients and permit the most thorough compacting. It shall be compacted by spading or by a mechanical vibrator until the ingredients have settled in the proper place and the surplus water is forced to the surface. Form vibrators shall be used only with the specific approval of the Engineer.

The concrete shall be placed in such manner as to prevent excessive crawling and segregation of the aggregate.

Location of all construction joints must be as approved by the Engineer. Such joints shall be roughened, rabbeted horizontally and grouted with cement, before joining new concrete to old. Construction dowels shall be placed as directed by the Engineer in both reinforced and non-reinforced work.

Before pouring new concrete on top of concrete which has set, the surface shall be thoroughly cleaned of foreign matter and laitance of scum, drenched and slushed with neat cement.

D. Finished. All exposed formed concrete surfaces exclusive of any surfaces below the water line or below the line of backfill, and exclusive of curbs and walks, will be given the surface finish described as follows:

As soon as the concrete has set sufficiently to permit it, the surface shall be thoroughly wet with a brush and rubbed with a No. 16 carborundum stone or an abrasive of equal quality, bringing the surface to a paste. The rubbing shall be continued sufficiently to remove all form marks and projections producing a smooth, dense surface without pots or irregularities. The material which, in the above process, has been ground to a paste shall be carefully spread or brushed uniformly over the entire surface and permitted to reset. The

5 - 2

Page 31: Construction Standards and Concrete Specifications

final finish shall be obtained by thoroughly rubbing with a No. 30 carborundum stone or an abrasive of equal quality. This rubbing shall continue until the entire surface is of a smooth texture and uniform in color.

5 . 04 Curb and Gutter, Curbwalk, Sidewalks, Driveways and Cross Pans.

A. Preparation of Subgrade. All subgrade upon which concrete is to be placed shall be thoroughly compacted and moistened . Concrete shall be placed only when the subgrade is moist and not when it is too wet or dry.

B. Forms. Metal or wooden forms may be used. They shall be free from warp, of sufficient strength to resist springing out of shape. Forms shall be cleaned of all mortar and dirt and oiled before they are used . They shall be set to the established line and grade, being well staked, braced, or otherwise held in place . Forms shall remain in place at least twelve (12) hours after concrete has been placed against them or for a longer period if so directed by the Engineer.

Maximum deviation of the top surface shall not exceed one-eighth ( 1/a ) inch in ten (10) feet or the inside face not more than one-quarter (~) inch in ten (10) feet . The method of connections between sections shall be such that the joint thus formed is tight and free from movement in any direction. Approved flexible forms shall be used for construction where the radius is one hundred fifty (150) feet or less.

C . Placing Concrete. After the inspector has approved the forms and subgrade, then concrete shall be deposited on the subgrade to the required depth and width in successive batches and in a continuous operation. The concrete shall be placed as uniformly as possible to minimize the amount of spreading necessary. While being placed, the concrete shall be spaded and/or vibrated with suitable tools to prevent the formation of voids or honeycomb .

Wire fabric shall be placed at a point three (3) inches below the surface of a cross pan and squared-out return . The fabric shall be fully supported on precast mortar blocks prior to placing the concrete.

1. Expansion Joints. Expansion joints shall be provided in accordance with the thickness and other dimensions indicated on the plans or as directed by the Engineer. The joint filler shall extend the full depth and width of the concrete and shall be set vertical with the tip edge flush with the finish surface of the concrete. Preformed expansion joint filler conforming to the requirements of A.A.S.H . T.O. Specification M 213-74 or latest revision shall be used.

Expansion joints shall be provided at the following locations and shall be in place prior to the placing of concrete:

a. Between back of sidewalk and driveway slab or service walk.

b. Between new concrete and existing masonry buildings. c . As shown on the plans. d. As directed by the Engineer.

D. Finishing. Finishing shall be done with a screed or mule designed to give proper shape to the section as detailed. Final finish shall be applied by a float or other means approved by the Engineer. The final texture desired may be obtained by lightly brooming the surface, edge

5-3

Page 32: Construction Standards and Concrete Specifications

to edge, to produce a slightly roughened finish at the discretion of the Engineer. Particular care shall be used to finish gutter flow line to a true uniform grade. Any pockets which will pond any appreciable amounts of water shall be removed by grinding . No water shall be added to the concrete surface to facilitate finishing.

1. Edging. Before final finishing is completed and before the concrete has taken its initial set, all edges in contact with the forms shall be tooled with an edger having three-eighth (3/0 ) inch radius.

2 . Jointing. Transverse joints shall be placed at maximum intervals of ten (10) feet. To control random cracking, the joints shall be formed, sawed or tooled to a minimum depth of one-quarter (~) of the total thickness. If divider plates are used, the maximum depth of plates shall not be greater than one-half (~) the total thickness. The joints shall be finished with a jointer having a width no greater than five-sixteenth (s/16) inch and a depth of not less than three-quarter (~) inch. A maximum joint width at the finished surface shall be no greater than five-sixteenth (s/16 ) inch.

Tool joints shall be spaced as follows:

a. Not more than ten (10) feet nor less than five (5) feet apart in curb and gutter and curbwalk.

b. Not more than six (6) feet nor less than four (4) feet apart in sidewalk.

c. In driveways one or two joints equally spaced as applicable .

d. As directed by the Engineer.

3. Marking. All sidewalks, curb, gutters and driveways shall have the name of the Contractor and the year of construction impressed therein, using block letters one (1) inch high and three-eighth (3/ 0) inch deep. One impression shall be made in each driveway. Impressions shall be made in sidewalks, curbs, gutters at each end of the construction, or at one hundred (100) foot intervals and at each extension to curbing.

5.05 Curing. Concrete shall be cured by protecting it against moisture loss, rapid temperature change, from rain, flowing water and mechanical injury for a period of not less than five (5) days after placement.

It shall be the Contractor's responsibility to protect from the elements and traffic, and if neglected the Engineer shall direct that the necessary protective measures be taken at the expense of the Contractor, and no further pouring will be permitted.

A. Moist Curing. Moist curing shall be accompli s hed after initial set by covering with wet burlap, cotton mats, or other approved fabric used singly or in combination. Curing mats shall be kept continuously wet and in intimate contact with the concrete for the duration of the mo ist cure.

B. Waterproof Paper and Polyethylene Sheets. The surface of the concrete shall be thoroughly moistened with a fine spray of water and then covered after initial set with the waterproof paper or sheeting. Paper or sheeting shall cover the entire width and edges shall be lapped at least twelve (12 ) inches to insure complete cov erage. Paper or sheeting shall be adequately weighted to prevent displacement or billowing due to wind. (•sheet Materials for Curing Concrete", A.A.S.H.T.O. Des ignation: M 171-70.)

5 -4

Page 33: Construction Standards and Concrete Specifications

C. Liquid Membrane Curing Compound. Only white pigmented membrane curing compound shall be used (PROTEX Promulsion 50AW or equivalent ) and shall be applied immediately after the water sheen has left the finished concrete. The compound shall be applied at a rate of one gallon per 200 square feet .

5.06 Cold Weather Concreting. Except by specific written authorization, concreting shall cease when descending air temperature in the shade and away from artificial heat falls below 40 degrees Fahrenheit. It shall not be resumed until the ascending air temperature in the shade and away from artificial heat rises to 35 degrees Fahrenheit.

When concrete is permitted during cold weather, the temperature of the mix shall be not less than 60 degrees Fahrenheit or more than 80 degrees Fahrenheit at the time of placing. Aggregates or water or both may be heated, but the water shall not be hotter than 175 degrees Fahrenheit and aggregates shall not be used which are hotter than 150 degrees Fahrenheit. Before concreting is started, remove ice, snow and frost.

When concrete is being placed in cold weather and temperature may be expected to drop below 35 degrees Fahrenheit, a supply of straw, insulated curing blankets, or other suitable material shall be provided along the line of work.

At any time when the air temperature may be expected to reach the freezing point during the day or night, the materials so provided shall be spread over the concrete to a sufficient depth to prevent freezing of the concrete . Concrete shall be protected from freezing temperatures until it is at least five (5) days old. Concrete injured by frost action shall be removed and replaced at the Contractor's expense.

5.07 Hot Weather Concreting. Except by written authorization, concrete placing shall cease if the temperature of the plastic concrete cannot be maintained at 90 degrees or lower. To facilitate the placement of concrete in hot weather, the aggregates or water or both may be cooled.

5.08 Opening to Traffic. Concrete shall not be opened to traffic for a period of at least seven (7) days after the last concrete has been placed or for a longer period of time if the Engineer considers it necessary. It shall be the obligation of the Contractor to maintain suitable barricades for this purpose.

5.09 Measurement and Payment.

A. Payment of structural concrete shall be included in the contract unit price of the applicable item such as "Construct Catch Basin Inlet", etc.

B. Measurement and payment for concrete items shall be made on the following basis:

Vertical curb and gutter Per lineal Curbwalk Per lineal 8" Concrete alley paving Per square Concrete sidewalks and driveways Per square Cross pans Per square Handicap Ramps (Sec. 2 .19) Per each

foot foot yard foot foot

or other items as set forth in the Proposal Form and shall be full payment for excavating, backfilling, the finishing and compacting of subgrade, furnishing, placing, finishing and curing of the concrete, reinforcing and other materials, and all incidentals connected therewith.

5-5

Page 34: Construction Standards and Concrete Specifications

Concrete alley paving shall be paid by the square foot . Alley excavation will be paid at the unit bid pr~ce for concrete alley paving.

5 - 6

Page 35: Construction Standards and Concrete Specifications

CITY OF ENGLEWOOD COLORADO

CONSTRUCTION STANDARDS AND

CONCRETE STANDARDS

Department of Public Works Engineering Division

DRAWN BY: R.A.K

REVISED BY: D.A.C

SCALE

AS SHOWN

DATE 8/25/75

REVISED 4/22/97

2/ 1/2008

Page 36: Construction Standards and Concrete Specifications
Page 37: Construction Standards and Concrete Specifications

DETAIL NO.

E-1 E-2 E-3 E-4 E-5 E- 6 E-7 E-8 E-9 E- 10 E-11 E-12 E-13 E-14 E-15 E-16 E-17 E-18 E-19 E-20 E-21 E-22

TABLE OF CONTENTS

TITLE

TABLE OF CONTENTS INDEX lYPICAL PAVEMENT SECTIONS lYPE I CURBWALK 2' -8" lYPE II CURBWALK 3'-11" VERTICAL CURB & GUTIER SECTION VIEW VERTICAL CURB & GUTIER PLAN VIEW CROSSPAN SECTION AND PIPE ENCASEMENT SIDEWALK DRAIN SQUARED OUT RETURN W/TRANSITION CURB RAMPS 4' SPECIAL INDUSTRIAL V-PAN VERTICAL CURB & GUTIER WITH 5'-0" LIP lYPICAL HAMMERHEAD CUL-DE-SAC SECTION OF SLOPE BACK VERTICAL CURB & GUTIER lYPICAL CONCRETE ALLEY PATCH SECTION lYPICAL CONCRETE HEADER CUL-DE-DAC WITH ATIACHED SIDEWALK CURB RAMPS CONCRETE PAVEMENT JOINT CONCRETE PAVEMENT JOINT ENGINEER TITLE BLOCK

FILE NUMBER

CCDT01.dwg CCDT02.dwg CCDT03.dwg CCOT04.dwg CCDT05.dwg CCDT06.dwg CCDT07.dwg CCDT08.dwg CCDT09.dwg CCDT10.dwg CCOT011.dwg CCDT012.dwg CCDT013.dwg CCDT014.dwg CCDT015.dwg CCDTO 1 6.dwg CCDT017.dwg CCDT018.dwg CCDT019.dwg CCDT020.dwg CCDT021 .dwg CCDT022.dwg

I DETAIL NO. E-1

Page 38: Construction Standards and Concrete Specifications
Page 39: Construction Standards and Concrete Specifications

INDEX

PROFILES

NORTH OR EAST PROPERTY LINE

WEST OR SOUTH PROPERTY LINE

WEST OR SOUTH FLOW LINE

NORTH OR EAST FLOW LINE

POWER POLE

TELEPHONE POLE

POWER & TELEPHONE POLE

STREET LIGHT

WATER VALVE

FIRE HYDRANT

STOP SIGN

WARNING SIGN

INFORMATION SIGN

MAIL BOX

HEDGE

BRUSHES

TREE

EVERGREEN TREE

MANHOLE

EXISTING CONCRETE

CONCRETE TO BE PLACED

CONCRETE TO BE REMOVED AND REPLACED

LAND LINE

CENTER LINE

DITCH SHOWING FLOW DIRECTION

GAS LINE SHOWING SIZE

WATER LINE SHOWING SIZE

SANITARY SEWER SHOWING FLOW & SIZE

STORM SEWER SHOWING FLOW & SIZE

FIBER OPTIC

FENCE (ALL)

RAILROAD

ti

-e--0--{)--

g ® 'O 0 0 0 • M.5

c=:J c=:J 014·

* •

-G 4•

-w ~:

-ss a•

-sT 2!"

-FO-FO-

)( )(

11111111111111

I DETAIL NO. E-2

Page 40: Construction Standards and Concrete Specifications
Page 41: Construction Standards and Concrete Specifications

-: ... -"'

DEPTH OF PAVEMENT AND BASE COURSE AS SPECIFIED

ON PLANS

DEPTH OF PAVEMENT AND BASE COURSE AS SPECIFIED

ON PLANS

CROWN IS CONSTANT ABOVE STRAIGHT LINE FROM LIP TO LIP

MINIMUM CROSSFALL = 1.53 MAXIMUM CROSSFALL = 3.03

SECTION I 32' PAVEMENT

CROWN IS CONSTANT ABOVE STRAIGHT LINE FROM LIP TO LIP

MINIMUM CROSSFALL = 1.53 MAXIMUM CROSSFALL = 3.03

SECTION II 40' PAVEMENT

_r 3 1/2" AVG

J~--, / 14' -0" AVG

' ' VARIES ----E-D-GE--il

5000 psi CONCRETE W/FIBER MESH ALLEY

STANDARD ALLEY SECTION

Fl

TYPICAL PAVEMENT SECTIONS

PAVEMENT 1 /8" TO 3/8" ABOVE LIP

PAVEMENT 1 /8" TO 3/8" ABOVE LIP

NOTE: SLOPE FROM EDGE OF ALLEY TO fl

NOTE: EDGES OF ALLEY MAY VARY FROM STANDARD

DETAIL NO. E-3

Page 42: Construction Standards and Concrete Specifications
Page 43: Construction Standards and Concrete Specifications

EXPANSION JOINT SHALL BE PLACED AT EXISTING CONCRETE

MIN.

MAX VARIES

CONCRETE DEPTH 6" MINIMUM

CONTROL JOINTS AS DIRECTED

SLOPE SLOPE

1-5/8" MAX. BUMPER STRIP (OPT)

ALLEY & DRIVEWAY - PLAN VIEW

AS DIRECTED

NOT MORE THAN 2: 1

SW

,o .. I

SECTION OF 4"

5'-3"

2'-0"

2'-5"

CURBWALK

2'- 0"

MIN.

IX)

' If) NN

~ 1===::::::::s;:i=::::::~2~

NOTE.

5000 psi CONCRETE W/FIBER MESH

ONLY PERMIITED WHERE INKIND CURBWALK I IS BEING REMOVED AND REPLACED

2'-3"

SECTION OF DRIVEWAY ' ~ If)

N 2'-0"

2' -3"

SECTION OF ALLEY

TYPE I CURBWALK 2' -8"

BACK OF WALK

TOP OF CURB

FLOW LINE

GUTIER LIP

DETAIL NO. E- 4

Page 44: Construction Standards and Concrete Specifications
Page 45: Construction Standards and Concrete Specifications

MAX VARIES

CONCRETE DEPTH 6" MINIMUM

CONTROL JOINT AS DIRECTED

SLOPE ' '

1 -5/8" MAX BUMPER STRIP (OPT)

5'

SLOPE

EXPANSION JOINT SHALL BE LACED AT EXISTING CONCRETE

, ,,

5'

BACK OF WALK

TOP OF CURB

FLOW LINE

MIN. MIN. GUTIER LIP

ALLEY & DRIVEWAY - PLAN VIEW

AS DIRECTED

NOT MORE THAN 2:1

' v

I

x ~ _::.L

BW

6'-6"

2'-0"

N

10" 2'-.3"

SECTION OF 4" CURBWALK

SECTION OF DRIVEWAY

6'-6"

2·-0·

N

"N

~Ir-:--:-~.- --:-:--~~-. ==-:-i I

r---~2~· -.3_.. ----.I ---t BW 5000 psi CONCRETE W/FIBER MESH

SECTION OF ALLEY

TYPE II CURBWALK 3' -11 " DETAIL NO. E-5

Page 46: Construction Standards and Concrete Specifications
Page 47: Construction Standards and Concrete Specifications

AS DIRECTED 4'-0"

NOTE: VERTICAL CURB & GUTIER WITH ADJACENT WALK MAY BE POURED MONOLITHIC.

1" R : v lO

SLOPE 1/4" PER FT 1 1/2" R N

NOT MORE THAN 2:1

: 0 I

D 6" i-_2_·-0_ .. -l

SECTION OF VERTICAL CURB & GUTIER

NOTE: 1-5/8" BUMPER USED IN TYPE "B" INDUSTRIAL VARIES 6"

·<X)L I SLOPE 1/4" PER FT I

~,cBW~·-~· .. s.~. ~:·· ~==~TT1 TYPE "8"' INDUSTRIAL (CONTINUOUS DRIVEWAY SECTION)

_j 6" 1--_2_· -_o_" _ _. <X)

SECTION OF ALLEY & DRIVEWAY

--------,---~Lr· __ VARIES __ FT . 1 •· r N

~ SLOPE 1/4" PER I I "

BW

5000 psi CONCRETE W/FIBER MESH

SECTION OF DEPRESSED ALLEY

N a: 0

' <D

NOTE: 1-5/8" BUMPER USED WHEN VERTICAL CURB & GUTIER AND SIDEWALK ARE NOT MONOLITHIC PERTAINS TO STANDARD DRIVEWAYS & ALLEYS ALSO IN TYPE "B" INDUSTRIAL.

VERTICAL CURB & GUTIER

DETAIL NO. E-6

Page 48: Construction Standards and Concrete Specifications
Page 49: Construction Standards and Concrete Specifications

' ,. ,,

·, -----6'-Q" MIN.

......

'

•' '· ' .,,

. ' .

------6'-0" MIN.

EXPANSION JOINT SHALL BE I PLACED AT EXISTING CONCRETE

V ..... l 'I Vl'\'-11... ""''-' 11 I V , .. .. , ............... MAX. VARIES I I

I I I

CONTROL JOINTY

~ SLOPE AS DIRECTED '

/ SLOPE

'

'

·,. . ...-.

~

6'-Q" MIN

ALLEY & DRIVEWAY WITH ADJACENT WALK

EXPANSION JOINT SHALL BE I PLACED AT EXISTING CONCRETE

......... .. ..., , ......... \... ""''-' , , , .... '"" '"""'""' '"' I

MAX. VARIES I I I I

CONTROL JOINTY ' AS DIRECTED

/ .• '

' ' I""- SLOPE SLOPE

ALLEY & DRIVEWAY WITH SET BACK WALK

VERTICAL CURB & GUTTER PLAN VIEW

' . ~

6'-Q" MIN.

BACK OF WALK

B BACK OF CURI

FLOW LINE

GUTIER LIP

BACK OF WALK

EDGE OF WALK

- -

B BACK OF CURI

FLOW LINE

GUTIER LIP

DETAIL NO. E- 7

Page 50: Construction Standards and Concrete Specifications
Page 51: Construction Standards and Concrete Specifications

5000 psi CONCRETE W/FIBER MESH

3'-0" OR 4'-0" 3'-0" OR 4'-0"

CROSSPAN SECTION

0 I

6"

1" R

1 1/2" R

1'-0"

1'-6"

l

I

SECTION OF MEDIAN CURB & GUTIER

' N

DETAIL NO. E-8

Page 52: Construction Standards and Concrete Specifications
Page 53: Construction Standards and Concrete Specifications

AREA GRADED TO

SIDEWALK CHASE

#3 BAR 6" LONG WELDED TO ANGLE 3 a· IRON AT 12" O.C.

ISOMETRIC VIEW N.T.S.

NON-SLIP RAISED PATIERN STEEL TREAD 1 /2" PLATE

PLATE 1 /2" BEHIND

1 /2"x 1" FLATHEAD MACH. SCREW BRASS OR ELECTRO-GALVANIZED FINISH, 2' 0.C.

8"

EACH SIDE ( 1 /2" ANCHOR BOLT MAY -----"t~;=::'.:::=i=:;;i;:;r:==::=;~--ANGLE IRON TO BE BE USED) ------- DRILLED AND THREADED

TO ALLOW SCREW

' ..,.

SECTION A-A N.T.S.

-- CONCRETE TO BE DRILLED TO ALLOW FOR SCREW

SIDEWALK DRAIN DCTAIL NO. E- 9

Page 54: Construction Standards and Concrete Specifications
Page 55: Construction Standards and Concrete Specifications

17'-Q"

1· ~[ - --- --- ...........

..........

0 I

-:..-

' "' I 0 -

RADIUS POINT

ALL CONCRETE SHALL BE 5000 PSI WITH FIBER MESH

ALL RAMPS SHALL NOT EXCEED 12: 1 SLOPE

NOTE: ALL RETURNS SHALL BE RAMPED

UNLESS OTHERWISE INDICATED ON THE PLAN OR AS DIRECTED BY THE ENGINEER. UNLESS OTHERWISE INDICATED ON THE

6' OR 8 ' :1 -:..-

CONTROL JOINTS Ct: 0

ON RADIAL LINES ;.,, (o

Ct: 0

"' it>

x P.I. PL

2'-0"

\ \

~ \ \ 0

I

' \ --\ \ \

WALK VC&G

I I I I I \ I \ I

2' -8" 2' -0" TRANSITION TO

TYPE I CURBWALK

3'-11" 2'-0" TRANSITIONTO

7" TYPE II CURBWALK

SQUARED OUT RETURN W/ TRANSITION ' DETAIL NO. E-10

Page 56: Construction Standards and Concrete Specifications
Page 57: Construction Standards and Concrete Specifications

ATTIOfD 'llALIC

{'

.D:'.EL.1

VAAIES

filLI

CITY OF ENGLEWOOD 1000 DQ£llOOO P-Y D«UllOOO. co 80110 Alone: (J03) 7&2-2SOO F/ok (J03) l'8J-Q9J

TYPE 3A (6' RAMP) JYPE 38 (8' RAMP)

.......

Sll'NW!D

"'°'

File Information

OIPN!l\IDIT Of PIBJC WCR1<S OAAllll BY: Miil

°'"'""9 Fit - COlTIJl 1.DllC OAl!; 01/:JJ/04

-- 2002 Is.."" Unb; i:..,.

JYPE ZA (6' RAMP) TYPE 28 (8' RAMP)

.liE.Li

Proiect Detail Revised 0o1r. I Ccnlmtn11:

GENERAL NOTES

1. RAMP N«> WING SI.OPES SHM..l. NOT BE STtIPOI TlWI 12: 1; Oo.IENSIOHS SHOWN SHM..l. BE MOOIF1!D. AS llECESSARI'. TO MEET THIS REO\J1AEMENT.

2. ALL CONCR[T[ SHM..l. BE ~ PSI WITH FIBER MESH

J NORMAi. GUTTUI n.aw UNE AHO PROn.E SHM..l. 8C IWHTAIHED THROUGH THE -Nl£A.

4 tr POSSIBlL DRAINIGE STRUCl\IRES SHM..l. NOT BE PVCED IN UHE WITH RAMPS. LOCATIOH Of THE RAMP SHAU. TAKE PRECEDENCE OVER LOCATIOH Of THE DRAINAGE STRUCTURC. EXCCPT WHERE CXtSTINC STRUCT\JR£S Nt£ 9ElNC unuzm IN nt[ NEW CONSTRUCTION

5. THE rn>E Of RAMP SHAU BE AS SHOWN OH THE PROJECT P1.NIS IN GENERM... THE RAMPS ARE IHTDIOED TO BE USED AS FOU.OWS.

TYPE 1 RAMP IS FOR USE IN AREAS WHCRE THE SIOEWAU< IS SET BACK "'°" THE STREET. AHO WHEELCHAIR ACCESS nlOM THE SIDE Of THE -IS HOT Ll<ELY TO OCCUR BECAIJSC THE N'PllON:tl -.a. IS CCMREO 11'1' LAWN OR CRA'ln.. OR ~ OBSTllUCT10N IS Pfl£SlHT. m'£ 1 ~ BE USED AHIWH£R£ IN THE Bl.OCI<.

TYPE 2 RAMP IS FOR GOeM.. USE AT INTERSECTlONS. ESPECWJ.Y WHERE ~ ARE ALLOWED TO CROSS ow;()NAl.LY.

TYPE 3 RAMP IS FOR USE WHERE THE SIDCWAU< EX!(NOS TO THE CURB OR ~ BE EASILY TlWISIT10N!D TO PERlofT WHEil.CIWR Al::CESS TO THE RAMP FROM THE SIDE. rn>E J ~ BE USED AtffllliERE IN THE BLOC!<. AS WELL AS AT INTERSECTIOHS, AS ~ ALTERNATE TO m'£ 2.

TYPE 4 RAMP IS FOR USE WHERE WHEil..CHAIR ACaSS ~ OCCUR rROM ONLY Oii[ SIDE.

TYPE 5 RAMP IS FOR USE WHERE ~ EXISTING SIOEWAU<, INCWDING THE CURB, IS u:ss TlWI e FT ~o WIOENING IS NOT msmu:.

~ CONCRETE RAMP AHO WING SUAf"ACES SllAl.I. BE TEX1\JR!D WITH A l.11£ BROOMED SURFACE ONLY. 111 OE'TECTMLL WARft9rtC PAVERS

WITH A TRUNCATED DOME SURFACE.

CJ

Issued By:

CRASS OR CRA\lfl. AREA .trulCOIT TO RAMP, WING OR WAU< THAT IS HOT APPROPRIATE FOR WHEil.CIWR TIWTlC

/),. - DESIGN FOR BACK Of WAU< HEAR RAMP -.a. WILL 8C AS SHOWN OH P1.NIS OR AS OIRECT!D

1-.l"'J', 'd'c 'Id · • I DrnCIAll.E -~IMJIS

SlfC) F1llNW1CM

fllRC

SECTION A-A

DETAIL NO. E-11 CURB RAMPS

Page 58: Construction Standards and Concrete Specifications
Page 59: Construction Standards and Concrete Specifications

SIDE CROSS SECTION VIEW OF DETECTABLE WARNING. WELL. CURB. AND GUTIER

r:- GUml!QB

I r . - • TRAHSlllON

Fl I

DmCT.llll.E W-.G Will MJ CUR8 Nl!A

DETAIL FOR TYPES 1 AND 3 CURB RAMPS

P.J. • PERMISSIBlE JOINT Willi EPOXY-COl<TED DEFORMED NO. 4 f1'( HI IN. BARS CONFORMING TO MSKTO M 2&4 AT 18 IN. SPACING.

Fl

P/IRT CE PNIT CE TlllC OR TlllC OR

I °';9 I "'™ CE RMI' I °';9 I A

•'"'1 ••I

g•

38"

GENERAL NOTES

1. THE OETECTABLE WARNINGS SIW.1. BE INSTAU£D AT SIOEWAU</STREET TRANSITlOHS. THEY SHAU. BE MADE IN PAVER FORM Willi A TRUNCATED OOME SURFACE. THE OOMES SIW.1. BE Pl.ACED IN A SQUARE GRtO.

2. THE TOP Of' THE ORAllW:E WEEP HOLE SIW.1. BE LOCATED AT THE LOWEST POINT Of THE OETECTABLE WARNINC WELL

3. AU. OETECTAllLE WARNING AREAS SIW.1. START A MINIMUM Of 8 INCHES FROM THE Fl.OW UNE Of' THE CURB ANO NOT BE MORE THAN A IAAXIMUM Of 11 INCHES FROM NlY POINT ON THE Fl.OW UNE Of THE CURB. AU. OETECTABU WARNING AAr>S stw.L BE 24 INCHES IH lING1H N¥J COYER THE COMPLETE WIOTH Of THE RAMP AREA ONLY.

g• 1111. 10 CUR8 now UHE (sa NOTE 3)-

t 1' I 'j : I •• I' '. 1 I [ : .. 4. THE OETECTABLE WARNING AREA SHALL BE INCl.UOEO

IN THE COST Of THE CONCRETE CURB RAMP.

~. RAMP SLOPES S1W.1. NOT BE STEEPER THAN 12:1. THE OETECTABL! WARNING ANO WEU AREA SLOPES SHALL NOT BE STEEPER THAN 20: 1.

'llEEP HOI! WEEP HOI! A

PLAN VIEW OF DETECTABLE WARNING AND WELL

(PAVERS NOT DRAWN TO SCALE)

M 1llP ~ CE M 1RllOJ[J) D011ES SlWL BE ~ 10 Ml CE 11£ &\St ~

I I I . . .. ~

I-

&-'\'\l)~:;!'s:?'!'' 1· . , DmCT~WNMNC SHAU. BE EOUM. IN

--· • _,. .. 90™ DIRECTIONS. ELEVATION YIEW PLAN VIEW

DETAIL FOR TYPE 2 CURB RAMP DOME AND DETECTABLE WARNING DETAILS

SECTION A-A

10 BE P<XJR£D llOIO.JlllCAU. Y

-CURB NI) GUmll TYP£ : g• WIDTH CE DmCTAl!l.E WAANllG Nil RAMP r

WIDTH CE Wt«: CURB MJ GUmll TYP£ :I:--

now lH ( WIDTH CE Ill«>

'> 12:1 12:1 now

I (• . . . - r DOME (M>.) PA'ID!S (M>.) - -. . .. . . I . .. . I I . , . ) .. . . . . . . . .

lH

. . . • 2· . . ~. !· I'-' '' 'I.'''' 1'.' '\.}',, "'' ''' •· I • . 2· • . . . . . . .. . ' ) . . . . T Tf l .. . • w .. 4 I • · •;.. IM. llRAlllll:( mr ~ 1 •· . I. ~ . .

T~2•· I ,. I I S" I 2•·~T '

_, FABllX:

FRONT SECTION VIEW OF DETECTABLE WARNING, WELL. CURB, AND GUTIER

{' CITY OF ENGLEWOOD 1000 ENGUllOOO p-y ENGUWOOO, CO ll0110 Phone: (JOJ) 762-~ FAX: (303) 783-!ll!IJ

File Information

DEP/IRTMENI CE PUil.iC llORICS I DRAllN lff: 1B.

llnloing 11o - CCD11l19.dwg I Gt.re 2/'l0/!>4

ktl1d vnon: 2002 I Saa NI. I ~ Ei'!lioh

Dote I ~ CURB RAMPS Proiect Detail Revised DETAIL NO. E-1 lA

Issued By:

Page 60: Construction Standards and Concrete Specifications
Page 61: Construction Standards and Concrete Specifications

2'-0"

2"

6" ors"[ SIDE B SIDE A

FIBER MESH

CROSS SECTION

4'-o"

SIDE A

PLAN VIEW

4' SPECIAL INDUSTRIAL V-PAN

DETAIL NO. E-12

Page 62: Construction Standards and Concrete Specifications
Page 63: Construction Standards and Concrete Specifications

~ I ,. I ~I ~I ~I 5

• O'

' ,,., I

\..

5000 PSI CONCRETE W/FIBER MESH

VERTICAL CURB & GUTIER WITH 5' -0" PAN

I

~ .~

' N ........

,,.,

r DETAIL NO. E-13

Page 64: Construction Standards and Concrete Specifications
Page 65: Construction Standards and Concrete Specifications

r 36'

L

10'

SIDEWALK

FL

R5'

"----I- 1 0.

TYPICAL HAMMERHEAD CUL-DE-SAC

116'

DETAIL NO. E-14

Page 66: Construction Standards and Concrete Specifications
Page 67: Construction Standards and Concrete Specifications

NOTE: ONLY PERMITTED WHERE INKIND CURBWALK I IS BEING REMOVED AND REPLACED.

2' MIN. TO 3' (VARIES) AVE. = 3'- 0"

SLOPE 1/4" PER n

6" ' 4.

v ........ n n

1'-6"

. N ........

N

-:r SLOPE BACK CURB & GUTIER WITH SIDEWALK

6" • 4" ' 1°-6"

'v ;:;.. n

' N ........

~I

3

SECTION OF SLOPE BACK CURB & GUTIER

DETAIL NO. E-15

Page 68: Construction Standards and Concrete Specifications
Page 69: Construction Standards and Concrete Specifications

1--------3'-6"---------J

A--1--~

~SAW EDGES MIN 3" DEPTH

,__ ___ _J

A ----+----_____,

PLAN

~~--/_,_2 .. _. ~I ,o____LJ_'~~~1_==r~ DOWEL & PIN 7 . J W/ #4 REBAR 18 .. O.C. 5000 psi

CONCRETE W/ FIBER MESH

~.COMPACT SUBGRADE (95% PROCTOR) STANDARD

SECTION A-A

TYPICAL CONCRETE ALLEY PATCH SECTION

I DETAIL NO. E-16

Page 70: Construction Standards and Concrete Specifications
Page 71: Construction Standards and Concrete Specifications

. H .. .. ·: - ~ ---.--- ..----. ---,---

to I

SIDEWALK

TYPICAL CONCRETE HEADER

I DETAIL NO. E-17

Page 72: Construction Standards and Concrete Specifications
Page 73: Construction Standards and Concrete Specifications

20' MIN. DRIVE LANE WIDTH

6' ATIACHED WALK

IRRIGATED LANDSCAPED ISLANDS

W/ 1' SPILL CURB

4' TRANSPORTATION /UTILITY EASEMENT _,_.........,.,____.

/R~60' Pl 6 - 9'X 18' PARKING SPACES

R=50' FL {MIN.)

j

R=15' FL (MIN.)

R=20' FL (MIN.) *ALL OTHER DIMENSIONS

ARE THE SAME

~FC~~L=_j 54'

ROW

CUL-DE-SAC WITH ATIACHED SIDEWALK

~

~FC~~L_:_j 54'

ROW

NOTE: 1. LANDSCAPING REQUIRED IN PARKING

ISLANDS IF SIDEWALK IS ATIACHED.

DETAIL NO. E-18

Page 74: Construction Standards and Concrete Specifications
Page 75: Construction Standards and Concrete Specifications

{'

I

SHOW)fJI

~~1f \112'

© © -, SHOW)fJI . DOWEL BAR DETAIL

FOR @ JOINT WITH 14 ft. AND 12 ft. LANES

A ~A L= =-1 _J ~7 HORl2.

L_ TRAFFIC I TRANSIAOON ~ FLOW

HORl2. Sl(E1f

PLAN VIEW ~ HOlllZ. TIW<SVillCH.

»ID HORIZ. SICIW TOUJINICCS

~~Sl(Elf 1- . =--~~ '

rT/2

d·= ~ T IS PAVEMENT THICKNESS FROM Pl.ANS

SECTION A-A SECTION A-A SHOWING ~ llllDWa: SHOW'HG "°"1CAI. SKEW lOlEJWICE

DETAILS ILLUSTRATING DOWEL PLACEMENT TOLERANCES SEE SU8S£C1lOll 412.1J(B)2 FOR loUOW(I) TOl£1WK:C V.Al.IJES.

File Information

GENERAL NOTES I. 1ltS ST.IHOolRD PINI DOCS NOT Aff'I. Y 10 lltll CXlHCR£lt OiERIAYS {WlllU!ll'l'N:). 2. l.OCAlt (!) JOlll AT A © JOlll OR A _., Of 2 FtEI F1IUI A © JOlll.

J. 1ltS JOlll LAYOUT IS INTElllED 10 BE usm IQ A ST.IHOolRD FOR 11£ JOlll LAYOUT FOR 11£ PRO.(CT. F T1£ CONIRACTOR PRCIPOSES - '1IOll 1ltS STANIWll> OR T1£ Pl!OJCCT !I'S UIMlW. OR IRR£.GUNt CXlllllllCNS NOT aMJE> IOD4, 11£ CONTR.IC1l)lt SIWJ.. PllfPMC A PA'IDEIT JOlll LAYOUT FOR lffflfNN.. Ill' 11£ lllCNill 14 FOOT SLABS SIWl. BC COllSll!UC'ltD ONLY 'MOE ICilClll.1tl) ON 11£ PLAHS.

4. WHEN A CllllTllUOUS 11\DlH 1:6 PA'>tMENT IS PQJ!£D WUR THAN 40 FtEI, T1£ JOtlT NEAAEST 11£ COOUU£ SIWl. BE All OOID (JlJ Jttll.

5. ON 4 .Jc!NE CMl€I> llCHMYS, 11£ 2 \ME DllECOOIW. PilMllDIT IKJ BOTH SHOUUDS SIWJ.. BE Pl.laD Will! w lOllCIT\.'OIW. SlllED CONIR,ICTION .-is.

l ON V-.C 11\DlH sues, lHE 2 FOOT OR 4 FOOT Diil Of SUB 11\DlH DIWENSION llAY V>Rf ti NHS.

7. (!') TO BE usm WHEN TIWflC lJK IS lallD SIJ'M.'.lll.Y OR FOR TN'ERS OR SPEED QWICE LAHES. N..ltRK\lM ~ JttlT l.OCATlONS AT SPEED OWIGl: lJK llAY BE usm F ll'f'llCM» •

Project Detoil Revised

JOINT LEGEND

.... --©-­

-----©­CID

- CONTRM:'l10N lOllCIT\.'OIW. CONSTRUC'TXlll

~--tt©-++©+-~ ---(!)--~

CITY OF ENGLElfOOD DETAIL NO. E-19 Dote: I c.mn.u

CONCRETE PAVEMENT JOINT CIO'NmlEllT Of PUllUC WORKS Dl!AWN Ill': Niil 1000 D«ll'fllOOO PNl.Kl/AY D«UllOCO, co 80110 - (JOO) 712-2500 FAX: (JOO) 7U-689J

°""""l Fie - 0JCCfC20.DIC

- Vwlion: 2002 I - * Mlt: 00./2l/04 lWb: £r9joll Issued By:

Page 76: Construction Standards and Concrete Specifications
Page 77: Construction Standards and Concrete Specifications

{'

JOINT NOT R(OUIR£D F CURB ANO CllITTR IS POUlED IOIOUTltCloU.Y Willi AOJICENT !»IE.

F PAVDIENT IS lllP

JOINT LEGEND

----181-------<G)i---

--+-0-+-+-+-0+-- ----0--------0-----~~~~ ...... ·~~·~~~~

SHOllS NTEGRM. CURB

*

EXPNISK)N

lRAHSVERSC CONTRN:OON

l.OllGll\OIW. OR lRAHSVERSC CONSTl!IJCTION

l.OllGll\OIW. CONTRN:OON

L.ONCl1\JOllW. CONSTl!IJCTION

GENERAL NOTES I. 1llS ST.lllllRO ()()(S NOT N'Pt.Y TO ~ CONCR£l[ CMl!lAYS ('MTETOPl'llG~ 2. 111S 1'IPICAl JOINT LAYOUT IS IN1DllED TO BE USED ~ A STNIWlll FOR 111: JOINT LAYOUT FOR 111: PROJECT. F 111:

CONTRl.cTOR PROPOSES V-TlONS FROM THS STNllW!D OR 1llE PROJECT HAS IKJSlW. OR llREGUINI rotlll110NS NOT C(MR[I) HCD, T1£ CONTRACTOR SllAll. PREPNIE A PMllOIT JOINT LAYOUT FOR >l'f'R<NN.. BY' THE OICNIR.

l. l.OllGll\OIW. JOlllS S11A1.1. caNCllE WITH LINE llolRKllGS 'MEI POSSllE, >HJ ~ llAXllJll SP.-aNG Of 12.5 FT. ( IS FT. PD!11mD WITH llOllOUlltC CUR9 >HJ CllITTR).

4. COllSlRUCT lRAHSVERSC JOlllS PCRl'OIOICUM TO T1£ COO"EJU€ Of PMllDIT ANO OODCl llfl(M)GH T1£ CURB OR CURB >HJ CllITTR.

* 5. PUa I /l ll 1111. EXPNISDI JOINT FUDI Ill Ttf' 5 Ill. Of CURB JOINT AT !ll1!RSEtllON REl1Jl!N AAOIJS POllTS.

a. T1£ CONTRACTOR SIWl. lN.£SS OTl£RW!SE SIOIN ON 111: PlNIS, srucr >HJ USE A BOii) BREAICD! AT ill£lS, loWflOl.ES ANO Siii.Ni SIZE STRUCTURES. SMN..LEll STRUCT\JRES SUCH ~ VN..VE AND llONUllOIT BO)([S SIWl. NOT RfQUllE A BONO lll!E.IKO!.

7. lRAHSVERSC JOlllS SllAll. BE 1.0CAlm AT T1£ CDllU! Of CIRCULAR llNtlOUS ANO N.ClS. NO lRAHSVERSC JOINT SllAll. PASS WllltN 4 FT. Of A IWtru.

a. WllRE A !.DNGllOOWL JOINT WOUlD PASS LESS TIWI 1 FT. FROM A CAST-IN PAVDIDIT IWKllE OR SllllAR sac S1llUCT\ft, A 1'IPICAl 2 fl. RADIN.. JOllT, ~ SHOWN Ill 111: llClAl.S, SllAll. BE USED.

DOllEl.ED lRAHSVERSC CONTRN:OON 9. 1.0CATE(!).alT [email protected] OR 2 fl. WIN FROM©

*

10. 'MEI A CON11NUOUS WIDTH AT PAVEllDIT IS POUlED WllER TIWI 40 FT, THC JOINT N£ARCST 111: COO"EJU€ SlW.l. BE AN lMED@ JOINT.

ROUIDtlG Of NIGl.E BY FORMING OR SlffORll PAvtlC PCRllSSHl.E.

{

Pl MNAM 12' MAX., CONC. fi" TltcK OR LESS

U' MAX., COHC. C1IER 6" 1HCK

CUR8 !lll£T

!llTEGRM. CURB

BOXOOT

F PAVDIENT IS lllP

_l 12-5' lllX.

I

TYPICAL CURBED PAVEMENT JOINT LAYOUT

CITY OF ENGLEWOOD 1000 D«llWOOO P.IRl<WAY D«llWOOO, co 80110 - (J03) 762-~ f.lk (JOl) 783-689l

File Information

DEPNmlOIT Of P\JllJC WORKS I ORAllN BY: Ill.

11nrw1n9 n. - OJCC111021.DWC I D1JE: 03/22/1>4

Acod Vinion: 2002 I Scolo: NA Units: £"9lioh

Project Detail Revised

CONCRETE PAVEMENT JOINT Doto: I eommo..to:

DETAIL NO. E-20

Issued By:

Page 78: Construction Standards and Concrete Specifications
Page 79: Construction Standards and Concrete Specifications

ITT 7/8"

40• • ~47

~ (39 7/8" )

37 7/8"

23 1/8"

@SECTION 1 1

~

I

21·

23 1(8" 123" )

~· ·

~

PLAN - FRAME

~

_.A.

_.A.

J PLAN - GRATE

SECTION

_.A. 40•

(39 7/8"') 39 7/8"

37 '!/8"

(Ji) SECTION

1/16" TAPER

GENERAL NOTES:

~ w-- @DETAIL 1 1

1. CAST IRON SH.t.U. CONF"ORM TO MSHTO M105/AST\A A48, CLASS 358, MINIMUM. 2. CASTINGS SH.t.U. COMPLY WITH MSHTO MJOS-89 FOR CASTING PROOF LOADING (DESIGNED FOR MSHTO HS-20 LOADING). 3. SEE CITY Of ENGLEWOOO DETAIL AND TECHNICAi. SPECIFICATIONS, ANO OTHER RELATED STANDARD DETAIL ORAWINGS.

1 •

It> 39

11/2"

@SECTION 1 1

Gjj) SECTION ~ 47 5/8"

I I

~ ~ 9 --- --- - -- --- --... 5/8"x3" HEX-HEAD BOLTS w/HEX NlJT

;-1

' ' AND WASHER (EACH SIDE). : II

- J 112·

38" l 3;4•

[ ,.

39 112·

I 10 ·___A

I

n~----------- 3~· - -------------tf ~-4. CASTINGS SH.t.U. BE MANUFACT\.IRED WITH SPECIAL LETTERING IN THE CURB HEAD THAT PROHIBITS OOMPING. (I.E.: NO OOMPING DRAINS TO RIVER)

@SECTION

{' CITY OF ENGLElfOOD 1000 ENCl!'tlOOO PNl.OAY ENCl!'tlOOO, co 80110 Phone: (JOJ) 712-2!i00 f~ (JOJ) 783--&893

File Information

DIPN!TllDIT Of PUllUC WOAKS I DRAIN Erl: Niil

DniWig fill - f"C04-oo1Adog I [)0.1[: 01/12/04

.lcod - 2002 I Scolo: NA ~&.glioll

Doto: I Commonb:

Pro iect Detail Revised DETAIL NO. D-1 TYPE 16

INLET GRATE AND FRAME DETAllB

Page 80: Construction Standards and Concrete Specifications
Page 81: Construction Standards and Concrete Specifications

'i.

TOP 0 ICK Of

~ UP Of7:

CONCRETE GllllER

BACK Of SIOEWAU<

f4'S 0 12· (IWC.) E.W. (lYP.)

I <'Ill lo::::: l .... __ I I I TOP Of CURB

1·-·· LN' (lYP.)

~'i.

2' _A

GUTTUl

I I ---1 I I . d I· . e=RCP Pl'EI 2' I I . ~CONCRETE ~

2'

UP OF C0NCMTt GUTTD!

12·

G.

sa STANOMD DETAll FOR FIWolE. CRATE .. AD.IUSTA&.E CURB BOX DETMS.

8" -CURB BOX TO BC CAST WITH SPECW. l.CITER9ICl lKAT PROHIBITS OWPING

O<PANSION JOfltf SID£WAIJ(

2" CL (T'tP.)

---~~---- 1·-0!112·

111 ,. ·1 4 '<tl!llCAl WALL ;#; !!&~

i!['.~'1.,;:;:=.;;.::;...:.._=_;;;i.__"f:;t=='hl---,,, BM (MCI< WAU)

• JXP!CAI. ygmcAL CURB f: G\JITTR I !YP!CAl CURBWAU< ..

PLAN VIEW

@SECTION

TOP Of CURB

' r I , Wm.:i.:a,:;;JJ~f-- f '~1:=--2'

TIWISITlON

1 1/2· CL (lYP.)

OEPTli VARl£S a·-o· w.x. a·

SUITAlllE SUEICRADC (SEE NOTE 10) @SECTION

2' TIWISITlON

Y•lMllQIQ'~ T•rmitr'tOmClrl.o..•ounut T • 5• re» ~ am aunDt • SIDlWAUC ...,.,,.,..~( Q.['.Ol110N"ll>CIWtl\. Q.['.OITOI (->!S2 .

COMB. CURB. GUTTER ac SIOEWAU<

f4'S 0 12· (IWC.) E.W. (lYP.)

B...cKFlU. AROUND STRUCTURE TO BE HNI() TAMPED IN 5• urn.

GDIRAI. NOTES:

REBAA PlACEMOIT @DETAIL AROUND CONNECTOR , 1

1. FOR PA'nlDIT PIR'OSES, ll!T STI!UCTIMES SIW.1. JiSO IQOOE 2'-0" QJR8 & GUITER 11WiSl110N S£CTIOll AT 00! DC> or ll!T P\JJS SllElW.IC S£CTIOllS WllR£ R(glJll(I> BOIN) ll!T S1'RUCTlff AHO 1RIHS!OON S(COONS.

2. FUlOR SUlPE ~y BE PQ.!!ED llONOU!ltC Willi llAS£. l. Sc • SUlPE or CONNECTllR • ll Mii. 4. IH!SS O!llJ!WIS£ SPECf'ED ON THE ORMM;S OR OMl!lllSE N'PRCMD, JU f 16 ll!TS SHIU

BE CONSlRUClDl ll1H AH AOJUS!All! Cl ClRll SOX. s. D£S1CN C0101D1S FOR ll!T .11..1.CMS IE'IHS or rr (IWC.). FOR ll!TS 110RE nw. a rm "

!IO'!H. Sl()P DRAfl!NCS AHO D£SICN -~ SIW.1. BE suamm FOR -... 6. JU RDf'ORCN: S1m. S1W.1. BE ASTll, A-615. CRAllE 60 DU'ORIE) IW!S. DW«lIR or llEl«l

M£ASURED ON THE llSU or T1£ llAA SHIU BE A _.., or 6 BAA OIAMEIDl

File lnformotion Project Detail Revised

11·

p

mDDETAIL CONNECTOR OVTl.£T 1 , (()p'fi()NA()

CONTRACTOR TO NOTCH at BLOCK OUT AAOUNO PIPE OPENING />M> FORM SMOOTH RADIUS AAOUNO PIPE WITH NON SHRINK CROUT.

11·

7. SlD'S SHIU BE PROIUD MO ll!T ll0'1lt !XaIDS S-6" AHO SHIU BE " K:J::J:llSlNa. 1ll1ll MSlflO 11199

! CONCRETE SIW.1. WM: A 211 MY CXlMFRESSNE S1RDIC1H or 4000 PSI. 9. NO FORM WOl!K SHIU REll!IN INSllE S1'RUCTlff lHN COllP\£lL 10. Sl.8-CRADE SIW.1. BE <MREXCA~m> AHO BIOCFlUD 111H N'PRCMD BEDOINC ~TERIAI.

COMPICm> PER THE CITY or ENCl£WOOO SPECRATIOllS. 11. SP\JCllG or REH"ORaNC S1m. SHIU BC PDUITtD Oll.Y WllR[ D£lM.ED IN llRM!llll;S. 12. ll!T WIUS SIW.1. BE FORllED BOTH INSllE AHO OU!'SllE. CASlllG or SUWAl1S M:AllST

fNl1li IS NOT PERlilml>. 11 LEAN OOHCRrn: Fll TO BE ( c • 2000 PSI.

{' CITY OF ENGLEWOOD

1000 ENCl£WOOO PNOAY ENCl.£WOOO, co 80110 - (JOl) 712-2500 F~ (JOl) 7U-e893

DEJIMmlDIT or P\JllJC WORKS I llRAWN ll't: ta.

0nw4ng no - rco.-oooA.dllg I Mn:: OJ/04/04

Oat« I ~ SINGLE TYPE 16 OPEN THROAT INLET ADJUSTABLE CURB BOX

DETAIL NO. D-2

Ar:ad - 2002 I Scale: NA I \WI: £nglioll Issued By:

Page 82: Construction Standards and Concrete Specifications
Page 83: Construction Standards and Concrete Specifications

5•

~ ~ .----------rbl\j ITT 21·

23 1(6" (23" ')

7/6" '1"

40• • (39 7/6" ) ~ _.. ~I l=:~=n=~=u=~u==l _..

40· (39 7/8"")

39 7/6" 37 1/8"

37 7/6"

23 1/6"

21· 23"

@SECTION 1 1

GENERAL NOTES:

• _..

PLAN - FRAME

J PLAN - GRATE @SECTION

NO, 16 INLET GRATE & FRAME

~.

B>~ r 1/6·~· ::j '~'"AA> 8>1/l~TAPER 1/2" RAD.

112~ 1 5/6~~ 2 1 2·

~ ~

,.

1. CAST IRON StW.1. CONFORM TO MSKTO M105/ASTM A~6. CLASS 358, MINIMUM. 2. CASTINGS StW.1. COMPLY WITH MSKTO M306-69 FOR CASTING PROOF LCW>INC (DESIGNED FOR MSKTO HS-20 LOADING) J . S£E CITY OF ENGLEWOOO DETAIL AND TECHNICAL SPECIFICATlONS, NlD OTHER RELATED STNlDAAO DETAIL DRAWINGS.

File lnformotion Proiect Detoil Revised

·~ [>I~

B> 39

11/2"

@SECTION 1 1

~ ~

{' CITY OF ENGLEWOOD Dair. I c:o.nr-a: TYPE 13 1000 D«llWOOO p-y D«llWOOO. co 80110 - (JOJ) 7$2-2300 f/IX: (JOJ) Jel-6893

DIJ'N!IMOIT r1f PUil.iC llORICS I DRA11t1 !Ir: Niil

°'"*'I f'lll - Ftl04-005.ll'"l I °"re OJ/04/04

-- 2002 I - NA I IMlib: £nglioll

GRATE AND FRAME DETAIIS

I I

G£) DETAIL 1 1

DETAIL NO. D-5

Page 84: Construction Standards and Concrete Specifications
Page 85: Construction Standards and Concrete Specifications

.A._B"

. · ;. ~-~ i .. :-

DEPTH VARIES 4' -6" STD. 6° -o· MAX

3• (m>.)

~ !.~EXPANSION JOltlT --- '4'S 0 12" (MAX.~

E.W. (m'.)

1·-11· •-4f 1 1/2" CL (m'.)

~RCPPIPE

...... ~

PLAN

@SECTION

-; .. ~·~. ,.

1'-4" lN' (m'.)

&.CKFlll AROUND STRUCTURE TO BE HAND TAMPERED IN 6" UFTS (&.CKfll METHOD B)

1/2" CL

UP OF CONCRrrE GUTTER

1 1/2" CL (m'.)

1' -4" lN' (m'.)

CONTRACTOR TO NOTCH .t BLOCK OVT AROUND PIPE OPENING AND FORM SMOOTH RADIUS WITH NON-SHRINK CROUT.

2 - f4 • J'-9"0 45•

0

2'-6"

- f4'sf"045

@SECTION

1e·1

SUITABLE SUBCRAOE (SEE NOTE 10) REBAR REPLACEMENT PREFERRED OPTIONAL

(A\ SECTION \ill7

DETAIL INLET WALL PENETRATION (1YP)

CONNECTOR PIPE ~DETAIL END TREATMENT (TYP.) 1 1

GOO.II. l«lTtS: 1. FOR PAYMENT ~ llt£T S1RUC1URES SHolU. Al.SO tlClUOE 2' -o· CUR8 t GUTTER 11!NISll10N

SECTIOH AT OCH 00 Of tt£T PllJS SIOEWAlJC S£Cm(5 wtm RCCURD 8EltlC) tt£T STRUCME Ml T1WISITlON SECTlOllS.

2. F\.OOR SlllPE llAY BE P01HD llONOUTltC Wl1lt 6'S£. l. Sc • SlllPE Of COIKC10R • 1:1: lfi 4. UllUSS 01lDWISE SPECflD ON Tit: ORA111NGS OR cmEnllSE N'l'RIMD, 1U 1'IPE lJ llt£TS SHo1U.

BE CONSlRUCllll WITH NI AOJJSl'Nll.E c.L CUR8 BOX. 5. OCSICN OONOOlONS FOR tt£T M.1.D11S DEl'1HS Of 6' (llAX.~ FOR llt£TS MORE lHAH 6 raT IN

OO'lll. SHOP ORA1llNGS Al() DESIGN AIW.'ISIS SHAU. BE SUlllTTEO rOR N'f'f«NN... 6. 1U R£J.fORCllG STm. SHolU. BE ASTM. A-81S, CRMlC 60 OUORllED 8IRS. DllollCTtll Of BEND

llCASIRD ON Tit: lllSU Of Tit: IWI SHAU. BE A -.., Of 8 IWI llWilCTl'.ll.

7. STU'S SIWJ. BE PR(M)fD lMH lll£T DEPTH EXCEEDS J'-6" NIO SIW.I. BE IN ACCORIWICC Willi MSHlD 11199

8. ca«:RE1I SIW.I. HA'IE A 28 ~ COlff£SSM sm:NClH Of 4000 PSI. 9. l«l rORllWORK SHAU. ~ llSll£ ~ lMH CCll'!.El'E. 10. Sl8-QWlE SIW.I. BE CMR EXCAVmD Al«l EW:ICflUD Wl1lt N'l'RIMD llEOOINC; llAlERlll.

CO!ol'ICT(l) PER T1£ CITY Of EllGl£'tlOOO SPEalCAlXlNS. 11. SPIJC1NG Of R£HORCllG STm. SHolU. BE PERlllTED 011.Y ~ OETMfll IN ORAlllNGS. 12. N.E1 WAU.S SHAU. BE FORl«D BOTH lllSU NfJ OUTSU. CASTNl Of SUWAU.S .IGfflST

EAl!lll IS NOT PERllTTED. 1 J. L£AN CONCRm ru 10 B£ r• • 2000 PSI.

CITY OF ENGLElfOOD File Information Proiect Detail Revised

{' 1000 EllGl£'tlOOO PNfl<WAY OIGIDIOOD, CO 80110 - (303)762-~ r~ (JOJ) 783-611113

DCPN!lllOIT Of PUIUC llOlllCS I DfWIN B't: ta.

Drowing Flo - ~ I MT{; 03/10/04

k»d - 2002 I Sc* NA ~£n911ioh

Dole: I Conwnonto:

Issued By:

SINGLE TYPE 13 INLET

1 1/2" CL (m'.)

1'-4" lN' ('M'.)

1'-6"

HOftllri.n-Al.-J,•.:..4• BAR lN'

(TYP.)

#4 TYPICAL CORNER

c:r DETAIL REBAR PLACEMENT

CONC. Fill

. T\IRN BAA INTO Pl»IE Of CURB BOX BEAM.

I• CURB BOX BEAM

DETAIL ANCHOR BAR (1YP.)

DETAIL NO. D-6

Page 86: Construction Standards and Concrete Specifications
Page 87: Construction Standards and Concrete Specifications

1- I B _J TYPICAL PLAN VIEW CUITER ---!---------- NET PAY lD«:TH J'

12·

r-1~~ CUl.,. ol()S...I 406 S-o.c. JI g•OL

1------.r-r-----+---ru1ro.c.

----t-- 1&'-r -------1

{'

SECTION A-A REGULAR INLET ~ c--, o-f-i c--,

r- w ..... ,....- 502 ----h.- S02

L-15' I I

D 11

' rS04tl-

I . •!o

rJ :-----.'----....;~-.....;;~,+1 413

!---'--,,~~~ lu ~~~~~~a·

T I I

o_J c _J 2:._i D

SECTION A-A INLET W!TH PROP BOX-H>S'

CITY OF ENGLElrOOD 1000 DIClEWOOO PlllKWAY DICILWOOO. co eo110 - (JOJ) 762-2500 f/IX; (JOJ) 7U-689J

File Information

DEPNITllOll CK PU8UC llllRICS I DRAllN BY: Ill.

Onnrlng Flo-. ~""9 I °"![; 02/r19/D4

koc1 - 2002 I Scoll: HI. I Unila: £ngWi

S02

l 403 4(

j

* f1lR t.D«;1H CHAlDI THDI 5 n. Pl!CNIJE .1CctSS Ar BOTH DIDS.

AaJlDW. IWHU Riil JKJ CIMR R£DUl!£D 111£11 l•10' OR llORE. M RfMllAC!JEIT 11111 .ICIXlRlllG.Y.

* MIIT SIW'E CK llllllMI. lllARIER alllB Nf> CUTTER IOC.

10·1~ ~ 'JY.

'f -=r=-- J"x3"1~ PLA1£

CURB FACE ASSEMBLY

PUC( DfT1AC ASSOa.Y - PW!Nl Clltla![1[.

~

~~-"--i-----~'- / -'--412

--l=----1 __ 1 _____ _

H11 11·o.e.

SECTIONS C-C & D-D (OOTTID lllllS 111£ II SEC1llM ~)

Standard Plan Revised

-CU1'8flC£~ * lHll A 1YPC R

NET IS USCI 111111 MOUNTAll..E tum Nf> MTEI. 5 n. T1W1S1T10N SHoU. BC COHS111UC1tD. TIWISITlONSHoll.llEPHD f1lR IS CURii JKJ GUT1Ul llOUllTHll!

MOUNT MU alllB fl({

CURii Nf) QJT1!l!

lRANSffiON CURB

• - f1lR A 1·~· PNI SW'[ r PIR n.

t~·. 4•...,,··-------i

;. 1 ~Sl.DPE-1·m.· .H ~11 C!F .... C""ut::l. , ' 2 R IJ. :z:::.. ~ l---PFT-11--=-- !01

r 1\'PICM. WM.I.

. ...,,. 413

J" CUl

I a· llllll FL

402 11• o.c.

SECTION B-B TYPICAL ENO VIEW

NOTE: 1W1W RtlG a CCMR. STAl10N POINT JKJ OW\Dll PIPE SHoU. BC 1.0CATEll IJ 11£ SAlol£ 00 CK 11£ NET.

NET SID'S REC'D. f1lR JU H >_J'-1•

4(11 .......

DETAIL NO. D-9 Date: ~

TYPE R CURB INLET

Issued By:

Page 88: Construction Standards and Concrete Specifications
Page 89: Construction Standards and Concrete Specifications

IA la 10·-o-~

~«AJ!i

1 [-=~H ~ ~1i 4•

I

LA' La INLET WITH Q!TCH PAYING

~ AS3lQit.llD '"" DIC[ llCl.U00>11MtoSTorMM£1

HU. Pf:CES

4 2 2

10;1 - ' , -\ IUlllll.lllllllH__.;

r-.viON or C011CC110N DntH C*U

STEEL GRATE OUANTffiES

DESCRFTION l.DIClll ~·Fl 7u;s..; S4 • 7.7 BEAM 40 7.70 103 3'h" x y,• Fl.AT 28'¥11 :ua 13

3 • v ... FlAT 28"" ~ 12

TOTAi. 128 L8S.

c

ams : CU.10!!

1115 IXIEllllON lo BC SiililN ON !'LINS.

Le

.... aJNalll[l[:

JINDSl\lllOllCllCl.UOO>ll ----~ 11< toST or~ams CU.'iElll \l)¥Jlll~ ~-lfll'- 2'-0-

··~·

SUll'[ Ml DntH PtlMNQ (llJIFtllal>) (RmMl£S 1.1 cu. 'tO.)

N11U 1011C - ON~ I'll'{

SECTION B-B

INLET ON GRADE SECTION C-C (FLOW FROM ONE DIRECTION)

INLET CONNECTED TO A CROSS CULVERT

.fl.61::1

ELEVATION CONCRETE INLET

.. I

•T GRAJ[

1i m STALLATION

GRATE IN NOTES .PEIAll. GENERAL

1. CONCll£lt SMJ. 11\YE A 2ll Ml' COIAeSllE S11ID«mf or 4000 PSI. M£I 111.Y I( CASI II f'IAC( Olt l'lllrASI.

2. 111J1Fa1CtC 111tS SHIU. 1t: ll'OICY coom IHl llEnJ!llD. JINDSHIU.tMA-...211.~

l. aJID[1[ SUll'[ Ml Dl10t - SHIU. <XNlllll 10 alOI lffDFDl10N5. llEWORallDfT FOii aJID[1[ SUll'[ P-. SHIU. It: 6 X I - Wl.4 X Wl .4 Olt 6 X 6 - W2.1 X W2.I .

4. SJllUC11llW. srm. RlR Gl!A1tS Ml GRA1I llSWlAllON - SHIU BC lltL'IHIZED

$. M o.osm ll£Slt M£I GMll:S SHIU. BC USU> ON It!. Tl?C C Mm \K£SS STANDIRD ll£Slt GM1tS Mf. Sf(l:lfE) ON Tit: P\ANS.

I. SID'S SIWL BC rtlCli'DID llHlll IUT IXIEllllON Y DamS 3 n.-e IL Ml SllU BC II Ja:1:/llfJ#Cf. ll1lt M9flO M 1a.

T - CONCll£lt SUll'[ IHl mtH PtlMNQ WU BC RBlUROJ llHlll SllJIN ON !'LINS.

H r4" O.J ~

"S-0- 1.0 eo "S-1" 1.2 Ill 4'-0- 1.l 101 I 4•-e• 1.4 118 2 ,·~· u 122 2

''-'" 1.7 137 2 r-o- u 142 3 r-e· I.I 1'8 3 T-4" u 113 3 T4" 2l 179 • r~ 1.l 184 r-e· 2.4 '" ··~· 2.5 2()(1

r-e" 2.1 220 10'~ 11 2la 11'- I" 14 2'1

• INCUJO(S VOWtlE OCCUPIED rr PftS.

BAR UST FOR H=2' -6" AND BENDING DIAGRAM -rlBo. ICI. lDCIH

401 2 2'-T r-11· 401 I 'il 11'-T 402 3 15'~

Li VINCll£J6CIXIEllllON

l"flllltlCHl'1NC11£16C orYllKH£ 2'4".

·EH ID laJ Oii[ 11111 RlR tlCH FOOT

I ,~3n• ' /.

INCll£J6CorYllKH£2'-I".

IUllRSlOllC l,'i0

1M.QllOlt

11>1> - l'F£S AS llm.mlm. 4Cll llRS WU BC trAlll.l.Y ~ ,_ tlCH ano. II CA5lS or SllDIUl l'F{.

1115 IMllSION lO I( -ON P\ANS.

ND

INLET CONNECTED TO A SKEWED CROSS CULVERT

lllDWI DntH -SI.OP( 112 • l'Ot " lllX. 11.0K 112· Pllt n. -

.,. •• CONCll£lt SUll'E JINDDntHr

~

..

··~ 4'-0-

SECTION A-A

INLET AT BOTIOM OF VERTICAL CURVE

54 • 7.7 llt'llS

Ol'D SIDI

r:~

·11· SECTION P-D

File Information CITY OF ENGLEWOOD Proiect Detail Revised

{' Dote: I eonw-

1000 DIGl1WOOO p-y OIGtE'MlOO, co 80110 - (303) 762-2'00 rAX: (303) 783-61193

DEPN!TllOIT or PIJllJC llllRKS

Drawing lilt Name: fGOH!ll.dwg

-- 2002 Scalo: NI.

DIWIN Ill': Ill.

Mlt: 02/~/04

l)1it>: c..,.

l/4"

CLOSE MESH GRATE USC RlR M.1. Tift C Mm

TYPE C INLET

Issued By:

SlDI DETM. II 3 'f2 • 1 1/4 flA1S SAllC 16 II STANDIRD M£I 4»>.lE.

DETAIL NO. D-10

Page 90: Construction Standards and Concrete Specifications

~ I ,•

Page 91: Construction Standards and Concrete Specifications

{'

STORM CONNECTOR PIPE CLOSURE DETAIL

(T~ BE USED ONLY WHERE NECESSARY AND AS AUTHORIZED BY THE ENGINEER]

#4 0 12"

l/2 (TYP ) -:--F.-=t I . ~ f~~cP~~~E E~isro~AL~~o~~CASE

MINUMUM "'MENSIONS

'v,~~»'f>'l'" /4 0 12"

3 14 CIRCULAR TIES

CUT NO ') Lllff

VERTICAL SECTION 5·

~[M1N1

CUT NO 2 LINE 0

CUT N0.1 LI MIN

D L 15· 12· 1s· 12" 21· 12"

TRENCH SUBGRAOE

CUT NO. 1. SAW THE TUBE AT AN ANGLE OF A/2 V.1TH THE TRANSVERSE PIJ.NE. REVFRSE ONE SECTION AND TAPE BOTH SECTIONS TOGETHER FOR~ING THE DEFLECTION ANGLE A.

CUT NO. 2: SAW THE TUBE LONGITUDINALL~ RH•OVING A STRIP 3.14 (D0 ·D) lt>CHES WIDE ON THE SIDE OPPISIT[ THE OPEN JOINT. BEND THE ENDS or THE CUT TOGETHER AND INSERT THE TUBE IN THE PIPE.

DETAIL "A" SONO-TUBE. OR EQUAL, INTERIOR FORM

CITY OF ENGLEWOOD File Information

T 5• 5• 5•

DD'NmlElll r1F PUllUC WlllllCS I DIWIN Ill': 111. 1000 ENGlDfOOO p-y ENCIDIOOO, CO 80110 Phonr. (JOJ) 762-~ FAX: (JOJ) 7a3-e89J

Orooir1g Flt - F004-016Adoq I MTr: rt1./l'IJ/04

kod Venion: 2002 I Scdo: w. I .- £ngWi

GENERAL NOTES

1 A CONCRETE COUAR IS REQUIRED WHERE THE CHANGE IN GRAD£ EXCEEDS 0. l 0 OF A FOOT PER FOOT

2. GAP LIMITS CAN NOT EXCEED MANUFACTURrRS TOLERANCES

3 CONCRETE COUAR SHALL NOT BE USED FOR A SIZE CHANGE ON THE MAIN LINE.

4 WHERE REINFORCING IS REQUIRED THE DIA~ffiR OF TH[ CIRCULAR TIES SHALL BE D+(2X WALL THICKNESS)+ T.

5. REINFORCING SHALL BE USED WHERE THE SPACES BE!WEEN THE EXTREME OUTER ENDS IS 2 1 /2" OR LARGER.

6. PIPE SPACE BETWEEN NO. OF

CIRCUIJ.R TIES·

DIAMCTER EXTREME OUTER ENDS CIRCULAR TIES 21• OR LESS 2 112·

WHERE THE SPACE BETWEEN PIPE LONGITUDINAL ENDS EXCEEDS 2 1 /2", THE NUMBER or CIRCULAR TIES SHALL BE INCREASED TO MAINTAIN AN APPROXIMATE SPACING OF 6" OC.

7. AN INTERIOR FORM Of UNSEAlED SONO-TUBE OR EQUAL SHALL Bf USED TO PROVIDE A SMOOTH INTERIOR JOINT. THE PAPER FORM MAY BE LEFT IN PlJ\CE (SEE OCTAiL A)

8. THIS DETAIL APPLIES "ONLY- TO PIPE 21· DWAETER OR LESS

Project Detail Revised c.mn...ts: CONCRETE ENCASMENT CLOSURE

OF RIGID CONDUITS

Issued By:

3

DETAIL NO. D-16

Page 92: Construction Standards and Concrete Specifications