Construction Report /2012 Operations Division Denton Independent School District Prepared by: Paul Andress, Director of Operations Glen Martin, Construction Coordinator Rod Reeves, Facilities Coordinator Michael Elmore, SHW Architects Leesa Vardeman, VLK Architects

Upload: others

Post on 10-Mar-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Construction Report

5/22/2012

Operations Division

Denton Independent School

District

Prepared by:

Paul Andress, Director of Operations

Glen Martin, Construction Coordinator

Rod Reeves, Facilities Coordinator

Michael Elmore, SHW Architects

Leesa Vardeman, VLK Architects

Page 2: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 02

Ryan High School Track and Field

(2002 Bond Referendum)

Page 3: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Ryan High School - Track and Field Replacement (1133.00)

Ryan High School - Track and Field Replacement

Construction Progress

• Utility work is complete• Installed drainage beds for track and fi eld• New track is installed• Some of the new turf has been installed

Forecasted

• Complete new turf installation• Stripe new track• Regrade soil around retaining wall

The construction progress through April is 96% complete.

Page 4: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

2

05.09.2012

Ryan High School - Track and Field Replacement (1133.00)

North end of track

Northwest end of track

Northeast end of track

Page 5: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 05

Strickland Middle School

(2004 Bond Referendum)

Page 6: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Additions and Renovations to Strickland Middle School (2833.00),

Denton ISD

Strickland Middle School

Construction Progress

• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Music and casework cabinets are installed• Sound rooms are complete• Most of the new exterior doors and hardware is

installed

Forecasted

• Finishes including paint, fl ooring, and ceiling are in progress

• Will begin secured main entry and offi ce area once the school year has ended

• Will begin new lockers once the school year has ended

The construction progress through April is 82% complete.

Page 7: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

2

05.09.2012

Additions and Renovations to Strickland Middle School (2833.00),

Denton ISD

Northeast corner of building

Northeast corner of building

Northwest corner of the band hall

Page 8: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 06

McMath Middle School

(2004 Bond Referendum)

Page 9: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Additions and Renovations to McMath Middle School (2833.00),

Denton ISD

McMath Middle School

Construction Progress

• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Music and casework cabinets are installed• Sound rooms are complete

Forecasted

• Finishes including paint, fl ooring, and ceiling are in progress

• Begin renovations to the reception area including new desk

• Provide new secured vestibule

The construction progress through April is 86% complete.

Page 10: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

2

05.09.2012

Additions and Renovations to McMath Middle School (2833.00),

Denton ISD

Northwest corner of the band hall

South wall of the band hall

Southeast corner of the band hall

Page 11: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

3

05.09.2012

Additions and Renovations to McMath Middle School (2833.00),

Denton ISD

North wall of Band Hall

West exterior of Band Hall

North exterior wall of Band Hall

Page 12: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 12

Lee Elementary School

(2004 Bond Referendum)

Page 13: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Additions and Renovations to Lee Elementary School (2833.00),

Denton ISD

Lee Elementary School

Construction Progress

• Structural steel is complete• Masonry work is complete• Roofi ng is complete• Windows are installed• MEP overhead is complete• Ceramic tile work is complete• Geothermal well drilling has begun

• Forecasted

• To begin fi nishes including paint, fl ooring, and ceiling are in progress

• Casework to be fabricated and installed• Marker boards and tack boards to be installed

The construction progress through April is 72% complete.

Page 14: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

2

05.09.2012

Additions and Renovations to Lee Elementary School (2833.00),

Denton ISD

Drilling of geothermal wells

North wall of classroom addition

South wall

Page 15: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

3

05.09.2012

Additions and Renovations to Lee Elementary School (2833.00),

Denton ISD

Northwest corner

Rainwater collection cistern

Page 16: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 08

Evers Park Elementary School

(2007 Bond Referendum)

Page 17: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Additions and Renovations to Evers Park Elementary School (2834.00),

Denton ISD

Out for Proposal - April 12, 2012

Proposals Due - May 8, 2012

Proposed Board Approval - May 22, 2012

Begin Construction - June 4, 2012

Page 18: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 09

Ginnings Elementary School

(2007 Bond Referendum)

Page 19: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Ginnings Elementary School

05.09.12

Ginnings Elementary School

05.09.12

• This project is

currently in the

Construction

Document Phase.

• Complete contract

documents May 31.

• School board to

approve bids in June.

• Construction to start in

July.

Page 20: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 11

Houston Elementary School

(2007 Bond Referendum)

Page 21: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Houston Elementary School

05.09.12

Houston Elementary School

05.09.12

• This project is

currently in the

Construction

Document Phase.

• Complete contract

documents May 31.

• School Board to

approve bids in June.

• Construction to start in

July.

Page 22: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

Project – 52

Middle School #7

(2007 Bond Referendum)

Page 23: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

1

05.09.2012

Middle School No. 7 (2854.00), Denton ISD

Milestones• Construction bids were received• The School Board approved the project• The Contractor was given notice to proceed and begin construction• Construction fencing is being installed

Forecasted• Clearing site to prepare for construction• Utilities to begin• Foundation work to begin

The construction progress through April is 0% complete.

Page 24: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

2

05.09.2012

Middle School No. 7 (2854.00), Denton ISD

First Floor

Page 25: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

3

05.09.2012

Middle School No. 7 (2854.00), Denton ISD

Second Floor

Page 26: Construction Report · • Ceramic tile work is complete • Geothermal well drilling has begun • Forecasted • To begin fi nishes including paint, fl ooring, and ceiling are in

4

05.09.2012

Middle School No. 7 (2854.00), Denton ISD

North Elevation - Front Entry

Shady Shores Elevation