construction noise study

30
Lichfield Southern Bypass - Final Phase Preliminary Construction Noise Study

Upload: others

Post on 20-May-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Construction Noise Study

Lichfield Southern Bypass - Final Phase Preliminary Construction Noise Study

Page 2: Construction Noise Study
Page 3: Construction Noise Study

Preliminary Construction Noise Study Lichfield Southern Bypass Phase 4 COSTCDM0014 /PEA Revision 0

October 2017

Page 4: Construction Noise Study

Document Control Sheet

Project Name: Lichfield Southern Bypass Phase 4

Project Number: COSTCDM0014

Report Title: Preliminary Construction Noise Study

Report Number: PEA

Issue Status/Amendment

Prepared Reviewed Approved

Rev 0 Name: Sunil Salpekar

Name: Richard Peers Name: Graham Brackstone

Signature:

Date: 23/10/2017

Signature:

Date:

Signature: Date:

Name: Name:

Name:

Signature: Date:

Signature: Date:

Signature: Date:

Name:

Name:

Name:

Signature: Date:

Signature: Date:

Signature: Date:

Name:

Name:

Name:

Signature: Date:

Signature: Date:

Signature: Date:

Richar

d Peers

Digitally signed

by Richard Peers

Date: 2017.10.26

16:17:11 +01'00'

Digitally signed by

Graham Brackstone

Date: 2017.10.27

14:05:21 +01'00'

Page 5: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - i - Issued: October 2017

Contents

1 Introduction ....................................................................................................... 3

1.1 Background ....................................................................................................... 3

1.2 Objectives ......................................................................................................... 3

2 Legislation and Guidelines ................................................................................. 4

2.1 General ............................................................................................................ 4

2.2 Temporary (construction) noise and vibration ...................................................... 5

3 Location ............................................................................................................. 7

3.1 Site Description ................................................................................................. 7

3.2 Location of sensitive receptors ............................................................................ 7

3.3 Noise Important Areas ....................................................................................... 8

4 Noise Scape ...................................................................................................... 10

4.1 Noise Maps ..................................................................................................... 10

4.2 Baseline Road Noise ........................................................................................ 10

4.3 Baseline Rail Noise .......................................................................................... 11

5 Construction Programme ................................................................................. 16

5.1 General .......................................................................................................... 16

5.2 January, February 2019 - Haul Road & compound construction ........................... 16

5.3 March - April 2019 – Piling platform and plateau construction .............................. 17

5.4 May, June 2019 - Piling and removal of piling platform ....................................... 17

5.5 July to December 2019 – Bridge Deck construction ............................................ 18

5.6 December 2019 – Roll Bridge Deck into position ................................................. 19

5.7 January 2020 – Plateau removal ....................................................................... 19

5.8 January 2020 – Railway Embankment Excavation ............................................... 19

5.9 January 2019 – Statutory Undertakers diversions ............................................... 20

5.10 February 2020 – Retaining wall, finishing works to bridge ................................... 20

5.11 March 2020 – Drainage, kerbing, surfacing and lighting ...................................... 20

6 Identification of potentially noisy activities ..................................................... 21

6.1 Assessment of the temporary effects of construction .......................................... 21

6.2 Key areas of potential noise impact ................................................................... 22

7 Noise Mitigation ............................................................................................... 23

7.1 Construction Environmental Management Plan (CEMP) ....................................... 23

Page 6: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - ii - Issued: October 2017

7.2 Detailed Construction Noise Assessment ............................................................ 23

7.3 General Noise mitigation .................................................................................. 23

8 Summary .......................................................................................................... 25

8.1 Further work ................................................................................................... 25

Table 1: Construction activities and predicted impacts ......................................................... 21

Page 7: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 3 - Issued: October 2017

1 Introduction

1.1 Background

To assist with the submission of a Planning Application for the railway bridge east of

Birmingham Road, Lichfield, Amey has been commissioned by Staffordshire County

Council to undertake a preliminary assessment into the potential noise impacts from the

construction of this phase of the proposed Lichfield Southern Bypass.

1.2 Objectives

The assessment aims to:

• Provide a description of the study area;

• Identify the location of sensitive receptors;

• Identify and provide an outline of the construction programme;

• Identify noisy activities;

• Highlight the risks posed by these activities;

• Provide an outline of possible mitigation measures.

Page 8: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 4 - Issued: October 2017

2 Legislation and Guidelines

2.1 General

National Planning Policy Framework

2.1.1 Paragraph 123 of the National Planning Policy Framework (NPPF) states that

planning policies and decisions should aim to:

· avoid noise from giving rise to significant adverse impacts on health and

quality of life as a result of new development;

· mitigate and reduce to a minimum other adverse impacts on health and

quality of life arising from noise from new development, including through

the use of conditions;

· recognise that development will often create some noise and existing

businesses wanting to develop in continuance of their business should not

have unreasonable restrictions put on them because of changes in nearby

land uses since they were established; and

· identify and protect areas of tranquillity which have remained relatively

undisturbed by noise and are prized for their recreational and amenity value

for this reason.

2.1.2 The Noise Policy Statement for England (NPSE) describes the effective management

and the control of environmental, neighbour and neighbourhood noise within the

context of Government policy on sustainable development. The main aims of the

policy statement are to:

· Avoid significant adverse impacts on health and quality of life.

· Mitigate and minimise adverse impacts on health and quality of life.

· Where possible, contribute to the improvement of health and quality of life.

2.1.3 The Planning Practice Guidance on Noise (PPG-N) to the NPPF provides more detail

on when noise may be a concern. It clarifies that the determination of noise effects

should include the effects during the construction phase wherever applicable.

Page 9: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 5 - Issued: October 2017

2.2 Temporary (construction) noise and vibration

Environmental Protection Act 1990

2.2.1 Under Part III of the Environmental Protection Act 1990, local authorities have a

duty to investigate noise complaints in relation to premises (including land and

buildings) and vehicles, machinery or equipment. The Noise and Statutory Nuisance

Act 1993 amended Part III of the Environmental Protection Act 1990, by placing

additional definitions in the list of statutory nuisances in Section 79 of the

Environmental Protection Act. The definitions relate to nuisance caused by

stationary vehicles, machinery and equipment on the street.

2.2.2 If a local authority’s Environmental Health Officer is satisfied that a complaint

amounts to a statutory nuisance, the authority must serve an abatement notice on

the person responsible or, in certain cases, the owner or occupier of the property.

The notice could require that the noise or nuisance be stopped altogether, the

sound level reduced, or limited to certain times of the day.

Control of Pollution Act 1974

2.2.3 The Control of Pollution Act 1974 (CoPA) Section 61 sets out the procedures for

obtaining ‘prior consent’ for construction works, including the agreement of noise

limits. Applications for ‘prior consent’ should be made to the relevant local authority

and should contain a method statement detailing how the works will be carried out

as well as a procedure to ensure noise is kept to a minimum.

2.2.4 Under Section 60 of the Act, the local authority serves the notice on the developer

to limit noise and vibration impacts (usually as a result of complaints being

received). These notices cannot be served if a Section 61 consent already exists (in

which case, prosecution is for breach of S61 rather than for breach of S60 notice).

Section 71 of the Act details the approved codes of practices used to minimise noise

and Section 72 defines best practicable means (BPM).

Page 10: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 6 - Issued: October 2017

The Control of Noise (Code of Practice for Construction and Open Sites)

(England) Order 2015

2.2.5 The Control of Noise Order 2015 approves BS 5228:2009+A1:2014 Part 1 Noise and

Part 2 Vibration (Ref. 8 and 9) for the purpose of giving guidance on appropriate

methods for minimising noise and vibration in relation to Section 71 of CoPA.

Page 11: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 7 - Issued: October 2017

3 Location

3.1 Site Description

3.1.1 The site is located to the east of the existing roundabout junction of the A5127

Birmingham Road and A461 Falkland Road and is split either side of the Cross City

railway line at approximately BNGR: SK115080. There is residential development to

the north west and north east of the site with arable land to the south.

3.1.2 The proposed scheme involves the construction of a road bridge through the

existing railway embankment with a new link to the existing Birmingham Road

roundabout. Future plans associated with a proposed housing development will

provide a new road to the east to form a new junction with London Road. A

temporary haul road will be used to access the site from London Road.

3.2 Location of sensitive receptors

3.2.1 The nearest sensitive receptors to the site are located on the west side of the

railway in Foxglove Close and on the east side in Shortbutts Close; the closest being

approximately 40 metres away.

3.2.2 As the works will require the construction of a temporary haul road, there are also a

number of receptors located within 100 metres of the route. These are homes

located in Sanders Way, Wordsworth Close, Shortbutts Lane and Marsh Lane.

There are no schools or hospitals within 500 metres of the works location.

Figure 1: Aerial view showing location of proposed works

Page 12: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 8 - Issued: October 2017

3.3 Noise Important Areas

3.3.1 A desk study search for Noise Action Planning Important Areas was undertaken on

the government website https://data.gov.uk/dataset/noise-action-planning-important-

areas-round-2-england1. The location of sensitive receptors was determined using

Google Instant Street View https://www.instantstreetview.com/ and the baseline road

traffic noise and rail traffic noise levels were was gained from Extrium interactive noise

map http://www.extrium.co.uk/noiseviewer.html

3.3.2 The proposed scheme has been identified as not being within a Noise Action

Planning Important Area (Figure 3).

Figure 2: Proposed working area (shown in the

brown box)

Page 13: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 9 - Issued: October 2017

Figure 3: Site location is identified as being away from the nearest

Noise Important Area (marked in red)

Site location

Page 14: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 10 - Issued: October 2017

4 Noise Scape

4.1 Noise Maps

4.1.1 In order to identify the existing noise climate, noise maps have been taken from

Extrium England Noise Map Viewer (http://www.extrium.co.uk/noiseviewer.html)

4.1.2 Noise levels for road and rail traffic are shown in Figures 4 to 7. The noise levels

were obtained from modelling on a 10 metre grid with a receptor height of 4 metres

above ground.

4.1.3 The maps show LAeq, day (16hr) and Lnight (8hr) levels. The LAeq, 16hr is the

annual average noise level for the 16 hour period between 07:00 and 23:00. Lnight

is the night time annual average noise level where night is defined as the period

from 23:00 to 07:00.

4.1.4 This data is a product of the strategic noise mapping exercise undertaken by Defra

in 2012 to meet the requirements of the Environmental Noise Directive (Directive

2002/49/EC) and the Environmental Noise (England) Regulations 2006 (as

amended).

4.2 Baseline Road Noise

4.2.1 The estimated LAeq, 16hr from road traffic (Figure 4) for dwellings on Foxglove

Close and Marsh Lane is 60.0 to 64.9 dB.

4.2.2 The estimated Lnight from road traffic (Figure 5) for the homes on Foxglove Close

and Marsh Lane is 50.0 to 54.9 dB.

4.2.3 The road noise level estimates for properties in Shortbutts Close and Wordsworth

Close are not available.

Page 15: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 11 - Issued: October 2017

4.3 Baseline Rail Noise

4.3.1 The estimated LAeq, 16h from rail traffic (Figure 6) for dwellings on Shortbutts

Close is 60.0 to 64.9 dB.

4.3.2 The estimated Lnight from rail traffic (Figure 7) for dwellings on Shortbutts Close is

50.0 to 54.9 dB.

4.3.3 Rail noise estimates for dwellings on Foxglove Close, Marsh Lane and Wordsworth

Close is not available.

Page 16: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 12 - Issued: October 2017

Figure 4: Road Traffic Noise LAeq,16h - the annual average noise level (in dB)

for the 16-hour period between 07:00-23:00.

Page 17: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 13 - Issued: October 2017

Figure 5: Road Traffic Noise Lnight - the annual average noise level (in dB) for

the period between 23:00-07:00.

Page 18: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 14 - Issued: October 2017

Figure 6: Rail Noise LAeq, 16h - the annual average noise level (in dB) for the

period between 07:00-23:00.

Page 19: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 15 - Issued: October 2017

Figure 7: Rail Noise Lnight - the annual average noise level (in dB) for the

period between 23:00-07:00.

Page 20: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 16 - Issued: October 2017

5 Construction Programme

5.1 General

5.1.1 The details below provide an indicative programme for the works highlighting where

potential noise impact could occur. Recommendations for mitigation measures are

also provided and it is the intention that the contractor will develop these measures

further to incorporate them into a Construction Environmental Management Plan

(CEMP) including the undertaking of a detailed construction noise assessment

5.2 January 2019 – Statutory Undertakers diversions

5.2.1 In advance of the main construction works, Statutory Undertakers diversions works

will be required. These works will be to the east of the site and be carried out

during the daytime period with an anticipated duration of 8 weeks.

5.2.2 The exact nature of the works has yet to be fully explored but is likely to involve

trench excavations and reinstatements which may have a noise impact on

properties on and near to London Road. The noise impact would be expected to be

minor.

5.3 January, February 2019 - Haul Road & compound construction

5.3.1 The planned works will involve the construction of a haul road accessed off London

Road leading to the east side of the railway embankment. This is to allow for the

future transport of materials to the main works site. The haul road works will

require excavation to a depth of around 450mm to enable the construction of a

stone based route. The estimated duration of these works is 8 weeks. The site

compound will require the erection of site offices and equipment storage buildings.

5.3.2 Works will be carried out during the daytime between the hours of 07:00 and 17:30

and have the potential for some noise disturbance. The main noise impact during

this phase will primarily be on the residents on Marsh Lane and Wordsworth Close.

Page 21: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 17 - Issued: October 2017

5.3.3 Construction of the haul road will require the use of HGVs, excavators, rollers and

other equipment. The contractor will need to ensure that the haul road is properly

constructed and maintained to ensure no uneven surface which could cause noise

and vibration impacts. Speed limits on site will be set to 10 mph so that noise from

construction vehicles is kept to a minimum.

5.3.4 The activities associated with the construction and use of the haul road, are

predicted to have a limited noise impact on nearby homes and residences during

the construction of the haul road and minor impact during the construction of the

compound. There may be some perceptible vibration associated with the

compaction of the haul road.

5.4 March - April 2019 – Piling platform and plateau construction

5.4.1 To facilitate the positioning of the new bridge deck, construction of temporary

plateaus and piling platforms on either side of the railway will be necessary. These

will be ramped and approximately 3 to 4 metres in height. Construction materials

will be brought on to site using the Birmingham Road access and the haul road with

the plateau construction requiring the use of excavators, rollers and HGVs. The

anticipated duration of the construction work is around 8 weeks.

5.4.2 Some noise from these activities is likely with the main impact being primarily

focussed on the properties closest to the compound in Foxglove Close and

Shortbutts Close. To minimise the noise impact, works will be carried out during

daytime hours only between 07:00 and 17:30. To further reduce the noise impact,

the 10 mph speed limit on the haul road will be enforced.

5.4.3 The noise impact from construction activities is predicted to be moderate at this

stage of the scheme.

5.5 May, June 2019 - Piling and removal of piling platform

5.5.1 Due to the nature of the works being close to the existing railway, the piling work

required for the new bridge will need to be carried out during a series of four

railway possessions. These are likely to be from around 22:00 on a Saturday

evening until 06:00 Sunday morning.

Page 22: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 18 - Issued: October 2017

5.5.2 The piling works will use continuous flight auger (CFA) system to drill into the

bedrock to a depth of between 10 to 17 metres. The construction will involve the

use of a piling rig, concrete pump and associated plant and equipment including

generators to provide power for task lighting.

5.5.3 The noise impact from the construction at this stage is expected to be significant for

dwellings in Foxglove Close and Shortbutts Close. To reduce the levels of noise at

nearby homes, temporary screens will need to be erected and the mitigation as

detailed in Section 5 be fully utilised.

5.5.4 It will be important for the contractor to liaise with homeowners and residents of

Foxglove Close and Shortbutts Close in order to fully identify the impacts from the

works, to seek feedback and to detail the mitigation methods to minimise the

impact as far as is practicable.

5.5.5 As the nature of the works and the phasing are critical in terms of timings, it is

important that the contractor liaises with the Lichfield District Council Environmental

Health Officer and it is recommended that a s61 Prior Consent Application under the

Control of Pollution Act 1974 is sought.

5.5.6 Upon completion of the piling, the platform will be removed with use of 360°

excavators and lorries. Works will be carried out during the daytime only.

5.6 July to December 2019 – Bridge Deck construction

5.6.1 The construction of the steel bridge deck and ballast walls will be carried out within

the compound area to the east side of the railway. Materials will be brought in via

the haul road and the works will generally be light construction and include welding

and bolting. Works will be carried out during the daytime only and anticipated to

take 24 weeks.

5.6.2 It is expected that the contractor will utilise the noise screening benefit of the

existing plateau where the works are carried out and the movement of HGVs and

other plant will be limited to reduce the noise at nearby homes.

Page 23: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 19 - Issued: October 2017

5.7 December 2019 – Roll Bridge Deck into position

5.7.1 In order to position the bridge deck and ballast walls in place, a rail possession is

required. This will be carried out over the three day Christmas period and it is likely

that works will be carried out during both the daytime and night time periods.

5.7.2 The positioning of the deck and ballast walls will be carried out using multi-axle

crawlers and two cranes. Generators are likely to be required in order to provide

lighting.

5.7.3 As construction noise has the potential for high impact on homes in Foxglove Close

and Shortbutts Close, temporary screens will be erected in order to mitigate noise.

5.7.4 The contractor will again be expected to liaise closely with residents and the

Lichfield District Council Environmental Health Officer and a s61 Prior Consent

Application under the Control of Pollution Act 1974 is recommended to be sought

due to the sensitive nature of the works.

5.8 January 2020 – Plateau removal

5.8.1 Following the bridge deck positioning, the two plateaus will require removal. This

will be limited to daytime operations only and require 360° excavators and lorries to

transport the material off site using the haul road and Birmingham Road. This stage

of the scheme is expected to take 2 weeks to complete.

5.8.2 As the plateaus are on either side of railway, the removal work will take place on

both sides simultaneously and the noise impact is likely to affect households located

on Foxglove Close, Shortbutts Close, Marsh Lane and Wordsworth Close.

5.8.3 Mitigation would include the adherence to the site speed limit of 10 mph, continued

maintenance of the haul road to ensure an even and smooth surface and general

measures such as avoidance of excessive engine revving and equipment left idling

when not in use.

5.9 January 2020 – Railway Embankment Excavation

Page 24: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 20 - Issued: October 2017

5.9.1 The excavation of the railway embankment to effectively create the underpass will

require 360° excavators and HGV lorries to remove the material via the haul road

and possibly the Birmingham Road. The anticipated duration for this stage of the

works is 2 weeks.

5.9.2 The impact will be similar to the plateau removal with householders in Foxglove

Close, Shortbutts Close, Marsh Lane and Wordsworth Close potentially affected.

Good site practice and management will be required to ensure the impact is

minimised.

5.9.3 Mitigation should include adherence to site speed limits and the maintenance of the

haul road to ensure no uneven sections.

5.10 February 2020 – Retaining wall, finishing works to bridge

5.10.1 The construction activity associated with the bridge finishing works would take place

during the daytime for around 12 weeks.

5.10.2 Works would involve some contiguous piling for the retaining walls and some

brickwork on both the east and west side of the railway. This could affect

households on Foxglove Close and Shortbutts Close. The works are predicted to

have a moderate impact with regards to construction noise. The contractors would

be expected to follow the mitigation guidance as set out in section 5.

5.11 March 2020 – Drainage, kerbing, surfacing and lighting

5.11.1 The final construction operations would be the finishing works and would take place

during the daytime for around 12 weeks.

5.11.2 The works will consist of activities primarily to the west of the site with low level

construction noise potentially affecting households in Foxglove Close and possibly

Shortbutts Close.

5.11.3 The contractor would be expected to carry out the works using best practice

measures detailed in Section 5 to minimise the potential impact on residents.

Page 25: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 21 - Issued: October 2017

6 Identification of potentially noisy activities

6.1 Assessment of the temporary effects of construction

6.1.1 Indicative construction activities for each phase of the scheme have been identified

and assigned an indictor with regard to the potential for noise impact.

6.1.2 These are minor, moderate or major. Minor is defined as unlikely to have any

adverse impact on people and major as likely to adversely affect people’s amenity

and require mitigation to minimise effect. Details are provided in Table 1 below:

Table 1: Construction activities and predicted impacts

Timescale Activity Impact Mitigation

January

2019

Statutory undertakers

diversions

Minor Construction activity restricted to 07:00-17:30

All relevant stakeholder s to be informed of works

January-

February

2019

Haul Road construction

Compound construction

Moderate

Minor

Construction activity restricted to 07:00-17:30

Adherence to site speed limit

Maintenance of haul road

Deliveries to arrive during daytime hours only, if

practical.

March-April

2019

Piling platform and plateau

construction

Moderate

Construction activity restricted to 07:00-17:30

Adherence to site speed limit

Maintenance of haul road

May-June

2019

Piling – CFA auger incl.

overnight works

Removal of piling platform

Major

Moderate

Construction activity restricted to 00:00–05:00

Temporary screens to be erected

Stakeholder liaison

July-

December

2019

Construction of steel

bridge deck and ballast

walls

Minor Construction activity restricted to 07:00-17:30

Adherence to site speed limit/restrict movement of

vehicles

Maintenance of haul road

December

2019

Roll bridge deck into

position and ballast walls

incl. overnight works

Major Construction activity restricted to 00:00–05:00

Temporary screens to be erected

Stakeholder liaison

January

2020

Plateau Removal Moderate Construction activity restricted to 07:00-17:30

Adherence to site speed limit

Maintenance of haul road

Page 26: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 22 - Issued: October 2017

Timescale Activity Impact Mitigation

January

2020

Embankment Excavation Moderate Construction activity restricted to 07:00-17:30

Adherence to site speed limit

Maintenance of haul road

February

2020

Retaining wall, finishing

works to bridge

Moderate Construction activity restricted to 07:00-17:30

Adherence to site speed limit

Maintenance of haul road

Deliveries to be to arrive during daytime hours only,

if practical.

March-May

2020

Drainage, kerbing,

surfacing and lighting

Minor Construction activity restricted to 07:00-17:30

All relevant stakeholder s to be informed of works

6.2 Key areas of potential noise impact

6.2.1 The preliminary noise assessment has identified the key activities that are required

to be carried out and the potential likelihood for noise impact. The report has

identified a number of areas where the potential is considered as significant and the

impact as major.

6.2.2 The contractor will be required to address these concerns and it is recommended

that a detailed noise impact report on these main concerns is carried out. The key

activities are:

i. Operation and use of the haul road.

ii. Piling works.

iii. Bridge deck and ballast wall positioning.

Page 27: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 23 - Issued: October 2017

7 Noise Mitigation

7.1 Construction Environmental Management Plan (CEMP)

7.1.1 The contractor, as part of general requirements, will be required to produce a

Construction Environmental Management Plan (CEMP) to outline how impacts on

the environment and the surrounding community during the scheme’s construction

will be avoided, minimised or mitigated.

7.1.2 As part of the CEMP, the contractor is responsible for producing and maintaining a

register of environmental impacts including noise. A Noise Management Plan will

form part of the CEMP and will detail specifically how the noise impact will be

identified, controlled and mitigated.

7.2 Detailed Construction Noise Assessment

7.2.1 As part of the Noise Management Plan, in order to assess the full environmental

noise impact, the contractor will be required to undertake a detailed construction

noise assessment in accordance with guidance from BS 5228-1:2009+A1:2014

‘Code of practice for noise and vibration control on construction and open sites –

Part 1 Noise’.

7.2.2 The assessment will focus on the key areas of potential noise impact as identified as

likely to have a major or significant effect in section 6.2. The contractor is expected

to comply with the requirements of the Lichfield District Council as laid down under

Sections 60 and 61 of the Control of Pollution Act 1974 as amended by the Control

of Pollution Amendment Act 1989. The contractor will be required to seek a S61

Prior Consent with Lichfield District Council for these works.

7.3 General Noise mitigation

7.3.1 The Contractor shall employ ‘the best practicable means’ as defined in the Control of

Pollution Act 1974 and amended by the Control of Pollution Amendment Act 1989,

to minimise noise and vibration from his operations. Further advice shall be utilised

in line with measures described in BS 5228-1:2009+A1:2014 ‘Code of Practice for

Noise and Vibration Control on Construction and Open Sites – Part 1 Noise and BS

5228-2:2009+A1:2014 ‘Code of practice for noise and vibration control on

Page 28: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 24 - Issued: October 2017

7.3.2 construction and open sites – Part 2: Vibration.

7.3.3 In the event that public complaints and noise measurements indicate that noise

levels have significantly risen at sensitive receptors, the Contractor would take all

reasonably practicable mitigation measures to reduce the noise impact and/or

prevent recurrence e.g. change the method of working, use mobile noise barriers.

7.3.4 Specific mitigation shall include:

· Audible reversing warning systems on mobile equipment and vehicles. When

reversing, mobile equipment and vehicles should travel in a direction away from

dwellings whenever possible.

· All compressors shall be sound reduced models fitted with properly lined and

sealed covers which shall be kept closed whenever the machines are in use.

· Equipment and machinery in intermittent use shall be shut down in intervening

periods of non-use or where this is impracticable they shall be throttled down to a

minimum.

· Unattended equipment outside normal working hours should, if possible, be

powered by electricity otherwise acoustic enclosures will be necessary to minimise

noise levels.

· Where possible, equipment with directional noise characteristics shall be

positioned to minimise noise at adjacent properties.

· Static machines shall be sited as far away as practicable from inhabited buildings

or other noise sensitive premises and/or behind temporary screens or enclosures.

· All vehicles and mechanical equipment used for the purpose of the works shall be

fitted with effective exhaust silencers and shall be maintained in good and

efficient working order.

Page 29: Construction Noise Study

Project Name Lichfield Southern Bypass Phase 4

Document Title Preliminary Construction Noise Study

Doc. Ref.:COSTCDM0014 /PEA Rev. 0 - 25 - Issued: October 2017

8 Summary

8.1 Additional commitments

8.1.1 The preliminary noise assessment has identified a number of aspects of the scheme

which may have a noise impact on nearby noise sensitive receptors.

8.1.2 The contractor will be required to carry out and commit to a number of

undertakings before any site works commence. These are:

· Detailed construction noise assessment

· Noise Management Plan detailing mitigation proposals as part of the CEMP

· Liaise with Lichfield District Council Environmental Health in order to

formulate s61 Prior Consent applications for key aspects of the scheme.

Page 30: Construction Noise Study

For more information please contact:

Connectivity Strategy Connected and Sustainable County Staffordshire County Council No. 1 Staffordshire Place Stafford ST16 2DH

Tel: 0300 111 8000 Email: [email protected]

If you would like this document in another language or format (e.g. large text), please contact us on 0300 111 8000 or email [email protected]