CONSTRUCTION MANUAL
STANDARD DRAWINGS AND GENERAL TECHNICAL SPECIFICATIONS
IRVINE RANCH WATER DISTRICT
CONSTRUCTION MANUAL
FOR THE CONSTRUCTION OF WATER, SEWER AND RECYCLED WATER FACILITIES
Kevin L. Burton, Executive Director of Engineering and Water Quality
JANUARY 2017
TABLE OF CONTENTSStandard Drawings
NUMBER DESCRIPTION DATE
W-1 1" Copper Service January 2017
W-2 2" Copper Service January 2017
W-3 1" or 2" Service Connection for PVC, Steel, ACP and DIP January 2017
W-4 1" or 2" Service Manifold January 2017
W-5 3", 4", 6", 8" and 10" Meter Assembly January 2017
W-6 Double Check Backflow Assembly, 3" and Larger January 2017
W-7 Reduced Pressure Principle Backflow Assembly January 2017
W-8 Fire Hydrant January 2017
W-9 Recycled Water Wharf Head Hydrant January 2017
W-10 Water Sample Station January 2017
W-11 1" or 2" Air Release and Vacuum Relief January 2017
W-12 Temporary Flush-out Assembly January 2017
W-13 Flush-out Assembly January 2017
W-14 Blow off / Bottom Drain Assembly January 2017
W-15 Pressure Regulating Station (PRV) January 2017
W-16 Thrust Block January 2017
W-17 Water Trench January 2017
W-18 Water and Sewer Separation Standards January 2017
W-19 Cut-in Tee for PVC, DIP and ACP Mains January 2017
W-20 Mortar Lined and Coated Steel Pipe Joints January 2017
W-21 Steel Casing for Water Pipe January 2017
W-22 Valve Box January 2017
W-23 Valve Stem Extension January 2017
W-24 Pipe Support January 2017
S-1 Manhole January 2017
S-2 Drop Manhole January 2017
S-3 Sewer Lateral January 2017
S-4 Cut-in Wye Connection January 2017
S-5 Terminal Cleanout January 2017
S-6 Sewer Trench January 2017
S-7 Steel Casing for Sewer Pipe January 2017
CP-1 Two Wire Test Station January 2017
CP-2
CP-3 Casing Test Station January 2017
CP-4 Insulator Test Station January 2017
CP-5 Cathodic Protection Rectifier and Shunt Panel January 2017
CP-6 Test Box, Wiring, and Identification Tags January 2017
CP-7 Test Station Locations January 2017
CP-8 Alumino-Thermic (CAD) Welding January 2017
CP-9 Bonding for Pipe Joints and Fittings January 2017
CP-10 Insulating Joints January 2017
G-1 Removable Guard Post January 2017
G-2 Utility Marker January 2017
G-3 Access Gate January 2017
G-4 Retaining Wall January 2017
G-5 Vault Ladder January 2017
G-6 Vault Sumps January 2017
G-7 Vault Vent January 2017
G-8 2-1/2" < Wall Penetration < 4" January 2017
G-9 Wall Penetration 4" January 2017
G-10 Concrete Slope Anchors January 2017
Water
Sewer
Cathodic Protection
General
TABLE OF CONTENTSWater Standard Drawings
NUMBER DESCRIPTION DATE
W-1 1" Copper Service Jan 2017
W-2 2" Copper Service Jan 2017
W-3 1" or 2" Service Connection for PVC, Steel, ACP and DIP Jan 2017
W-4 1" or 2" Service Manifold Jan 2017
W-5 3", 4", 6", 8" and 10" Meter Assembly Jan 2017
W-6 Double Check Backflow Assembly, 3" and Larger Jan 2017
W-7 Reduced Pressure Principle Backflow Assembly Jan 2017
W-8 Fire Hydrant Jan 2017
W-9 Recycled Water Wharf Head Hydrant Jan 2017
W-10 Water Sample Station Jan 2017
W-11 1" or 2" Air Release and Vacuum Relief Jan 2017
W-12 Temporary Flush-out Assembly Jan 2017
W-13 Flush-out Assembly Jan 2017
W-14 Blow off / Bottom Drain Assembly Jan 2017
W-15 Pressure Regulating Station (PRV) Jan 2017
W-16 Thrust Block Jan 2017
W-17 Water Trench Jan 2017
W-18 Water and Sewer Separation Standards Jan 2017
W-19 Cut-in Tee for PVC, DIP and ACP Mains Jan 2017
W-20 Mortar Lined and Coated Steel Pipe Joints Jan 2017
W-21 Steel Casing for Water Pipe Jan 2017
W-22 Valve Box Jan 2017
W-23 Valve Stem Extension Jan 2017
W-24 Pipe Support Jan 2017
TABLE OF CONTENTSSewer Standard Drawings
NUMBER DESCRIPTION DATE
S-1 Manhole Jan 2017
S-2 Drop Manhole Jan 2017
S-3 Sewer Lateral Jan 2017
S-4 Cut-in Wye Connection Jan 2017
S-5 Terminal Cleanout Jan 2017
S-6 Sewer Trench Jan 2017
S-7 Steel Casing for Sewer Pipe Jan 2017
TABLE OF CONTENTS Cathodic Protection Standard Drawings
NUMBER DESCRIPTION DATE
CP-1 Two Wire Test Station Jan 2017
CP-2
CP-3 Casing Test Station Jan 2017
CP-4 Insulator Test Station Jan 2017
CP-5 Cathodic Protection Rectifier and Shunt Panel Jan 2017
CP-6 Test Box, Wiring, and Identification Tags Jan 2017
CP-7 Test Station Locations Jan 2017
CP-8 Alumino-Thermic (CAD) Welding Jan 2017
CP-9 Bonding for Pipe Joints and Fittings Jan 2017
CP-10 Insulating Joints Jan 2017
TABLE OF CONTENTS General Standard Drawings
NUMBER DESCRIPTION DATE
G-1 Removable Guard Post Jan 2017
G-2 Utility Marker Jan 2017
G-3 Access Gate Jan 2017
G-4 Retaining Wall Jan 2017
G-5 Vault Ladder Jan 2017
G-6 Vault Sumps Jan 2017
G-7 Vault Vent Jan 2017
G-8 2-1/2" < Wall Penetration < 4" Jan 2017
G-9 Wall Penetration 4" Jan 2017
G-10 Concrete Slope Anchors Jan 2017
TABLE OF CONTENTSGeneral Technical Specifications
Revised 1/2/2017 1
SECTION DESCRIPTION DATE01045 Existing Facilities 1/2/201702100 Clearing and Preparation 4/1/201002201 Earthwork and Grading 6/16/201502220 Structure Earthwork 4/1/201002223 Trenching, Backfilling, and Compacting 6/16/201502315 Jacked Casing 1/2/201702316 Open Trench Casing 1/2/201702528 Concrete Curbs, Gutters, and Sidewalks 4/1/201002578 Pavement Removal and Replacement 1/2/201702701 Installation of Gravity Sewer Pipelines 1/2/201702710 Vitrified Clay Pipe for Gravity Sewers 4/1/201002715 PVC Pipe and Fittings for Gravity Sewers 1/2/201503100 Concrete Formwork 12/9/200403201 Concrete Reinforcement 7/8/200803260 Concrete Joints and Waterstops 1/4/201603300 Concrete 1/2/201403345 Concrete Finishing, Curing, and Waterproofing 1/2/201503461 Precast Concrete Manholes and Bases 1/2/201703462 Precast Concrete Vaults and Meter Boxes 1/4/201605120 Structural Steel and Miscellaneous Metalwork 1/4/201609900 Painting and Coating 1/2/201715040 Interior Inspection for Cement-Mortar Lined Steel Pipe 1/2/201715041 Chlorination of Water Mains, Wells and Reservoirs 1/2/201715042 Hydrostatic Testing of Pressure Pipelines 1/2/201715043 Leakage and Infiltration Testing 6/16/201515051 Installation of Pressure Pipelines 1/2/201715053 Carbon Steel Pipe and Fittings 1/2/201715056 Ductile-Iron Pipe and Fittings 1/2/201715057 Copper Pipe and Fittings 1/2/201715064 PVC Pressure Pipe and Fittings 1/2/201715076 Cement-Mortar Lined and Coated Steel Pipe 1/2/201715089 Combination Air Release and Vacuum Relief Valves 1/2/201415100 Manual Valves 1/2/201715112 Backflow Preventers 1/2/201715120 Hydraulically Controlled Diaphragm-Actuated Valves 1/2/201715139 Hydrants 1/4/201615150 Meters 1/4/2016
TABLE OF CONTENTSGeneral Technical Specifications
Revised 1/2/2017 2
SECTION DESCRIPTION DATE15151 Facilities Identification 1/2/201715162 Flexible Pipe Couplings and Expansion Joints 1/2/201716010 General Electrical Requirements 1/4/201616051 Miscellaneous Electrical Devices 2/15/200516110 Raceways, Pull Boxes, and Fittings 7/23/201216120 Conductors and Cables 1/4/201616135 Cabinets and Enclosures 12/21/200416140 Switches and Receptacles 1/4/201616150 Electric Motors 3/5/201216155 Low-Voltage Motor Control 5/20/201316160 Panelboards 1/4/201616400 Service and Distribution 1/24/200516418 Variable Frequency Drives Below 100 HP 12/28/200416443 Low-Voltage Switchboards 1/21/200516450 Grounding 1/4/201616460 Transformers 1/4/201616500 Lighting 12/21/200416620 Manual Transfer Switch 1/21/200516625 Automatic Transfer Switch 1/24/200516640 Cathodic Protection and Joint Bonding 1/2/201716650 Telemetry Cable System 1/24/200516700 Telephone Utility Equipment 12/21/200416950 Electrical Testing 12/21/200417000 General Instrumentation Control Requirements 1/4/201617110 Identification Tags 2/26/200517200 Miscellaneous Instrumentation Equipment 1/2/201717300 PLCs and Programmable Operator Interfaces 1/2/201717350 Telemetry and Control Systems Communications Equipment 7/23/201217360 Fiber-Optic Data Transmission System 2/27/200517500 Uninterruptible Power Supply 1/4/2016
EXISTING FACILITIES 01045 - 1 Revised 01/02/2017
SECTION 01045: EXISTING FACILITIES PART 1 - GENERAL A. Description This section includes requirements for connection to and abandonment of existing water
and sewer facilities. B. Related Work Specified Elsewhere
1. Trenching, Backfilling, and Compacting: 02223
2. Chlorination of Water Mains, Wells and Reservoirs: 15041
3. Hydrostatic Testing of Pressure Pipelines: 15042
4. Leakage and Infiltration Testing: 15043
5. Manual Valves: 15100 C. Location The Contractor shall be responsible for determining in advance of constructing the
improvements the location of all existing pipelines to which connections are to be made. PART 2 - MATERIALS All materials used in making the connection or removing the facility from service shall conform to the applicable sections of the technical specifications. PART 3 - EXECUTION A. Connection to Existing Waterlines
1. Notification: The Contractor shall give the District a minimum of four (4) working days notice before the time of any proposed shutdown of existing mains or services.
2. Notice to Proceed: Connections shall be made only in the presence of the District
Representative