Construction Management Plan Page | 1

Construction Management Plan Cover Sheet:

Project Address: 1121 NE 45th Street, Seattle WA 98105

MUP # 3022052

Building Permit # 6490679

Applicant/Contractor: Howard S. Wright, a Balfour Beatty Company

Version – 1.0

Date: 12/21/2016

Page | 2

Table of Contents

1. Project Overview ......................................................................................................................... 3

1.1 Project address ............................................................................................................... 3

1.2 Site Development: .......................................................................................................... 3

2. Construction Communication ..................................................................................................... 3

2.1 Contact Person: .............................................................................................................. 3

2.2 Construction Notification List:........................................................................................ 3

2.3 Communication methods: .............................................................................................. 3

2.4 Notification timing & tracking: ....................................................................................... 5

2.5 Construction Project and Known Special Events in the Vicinity .................................... 5

3. Construction Noise and Sensitive Receivers ............................................................................... 5

3.1 Construction Hours......................................................................................................... 5

3.2 High noise-generating activities ..................................................................................... 6

3.3 Noise-sensitive receivers ................................................................................................ 6

3.4 Construction noise management ................................................................................... 7

4. Schedule ...................................................................................................................................... 8

4.1 Schedule ......................................................................................................................... 8

5. Off-site Construction Worker Parking ........................................................................................ 8

5.1 Location .......................................................................................................................... 8

6. Right of Way Use ......................................................................................................................... 9

6.1 SDOT Coordination ......................................................................................................... 9

6.2 Material management .................................................................................................... 9

6.3 Pedestrian mobility ........................................................................................................ 9

6.4 Street closures .............................................................................................................. 10

Attachment 1 Map of Nearby Parking Areas ............................................................................... 10

Attachment 2 Proposed Haul Routes........................................................................................... 10

Attachment 3 Site Logistics Plans ................................................................................................ 10

Page | 3

1. Project Overview

1.1 Project address: 1121 NE 45th St, Seattle WA 98105

1.2 Site Development:

The Washington State Employees Credit Union (WSECU) – 45th St. project is a 7-story, 66,695 sf

mixed use office building with three floors of below grade parking. WSECU will be building out

the 1st floor as their new branch location, along with a café and community room the second

floor will be built out to house the WSECU administrative team. Floors 3 through 7 will be

leasable shell and core spaces. The building is a structural steel building with a Brick and curtain

wall façade.

2. Construction Communication

2.1 Contact Person:

Primary contact to the jobsite should be through [email protected].

The following individuals may also be used as project contacts for Howard S. Wright (HSW):

- Superintendent – Jeff Kynaston

Cell Phone: (206) 206-321-5840

[email protected]

- Project Executive – Doug Schumacher

Cell Phone: (425) 765-1764

[email protected]

- Project Manager – Will Colby

Cell Phone: (206) 387-9006

[email protected]

2.2 Construction Notification List:

Parcel owners, neighbors, and area businesses that will receive direct notification of planned

and emergency construction activities will be the following:

• Marriott Residence Inn

• Sharetea

• CorePower Yoga

• QDOBA Mexican Eats

• Washington Federal

Page | 4

• Hotel Deca

• Shell

• University of Washington Tower

• WSECU

• 32 Good Reason – Family, Cosmetic & Implant Dentistry

• University District Building

• ATI Physical Therapy

• The District Lounge

• U District Family Dentistry – Andy Nelson

• The Collegiana – UW Medicine

In general, all affected parties will be notified within the range identified above.

Page | 5

2.3 Communication methods:

Howard S. Wright will provide an email notification monthly, at a minimum, summarizing the

upcoming activities and associated impacts. In the event of any unplanned, unusual or

disruptive activities required for the project, the Construction Point of Contact will make their

best effort to provide SDOT and the members of the Neighborhood Notification List with a

Construction Notification indicating nature of activity, location, and duration at least 10

business days prior to the start of activity. Activities that may require notification include

street/sidewalk closure, associated detours, oversize deliveries, excessive hauling, noise and

work hour variations, and utility interruptions.

2.4 Notification timing & tracking:

Contacts on the Construction Notification List will be notified of upcoming activities weekly via

email, in addition to the updates concerning unforeseen disruptive activities. Notice will also be

given to SDOT, when required, regarding street use and right of way impacts (a minimum of 10

business days prior to the start of these activities).

2.5 Construction Project and Known Special Events in the Vicinity

Construction Projects:

• Sound Transit – Completing 2020

Special Events:

• University District Street Fair – Occurs May 21st – 22nd, 2017

o This event occurs on the weekend and is several blocks away. Special care will be

taken so as not to schedule impactful work during this weekend.

3. Construction Noise and Sensitive Receivers

3.1 Construction Hours

The majority of construction activities will be limited to standard construction hours between 7

a.m. and 6 p.m. on non-holiday weekdays. Construction workers may arrive at the site prior to

standard start times; however, they will be instructed during their site orientation that loud

talking and noisy set-up activity will be prohibited prior to 7 a.m. on weekdays and 9 a.m. on

Saturdays, unless a noise variance has been coordinated with the City of Seattle. Work is not to

be performed on Sundays or construction observed holidays. Any equipment warm-up prior to

standard times or times coordinated through a noise variance with the City of Seattle will be

such as to limit disturbance to neighbors.

Page | 6

HSW anticipates that some evening and Saturday work will be required using smaller crews

between the hours of 6 p.m. and 10 p.m. on non-holiday weekdays and between 9 a.m. and 6

p.m. on Saturdays. Work performed at this time will generate smaller amounts of noise and will

fall within the limits of the City of Seattle noise ordinance. In addition:

I. Work that is scheduled to take place during evenings and Saturdays will help

significantly reduce the overall length of the schedule.

II. Work is not expected to occur on construction holidays, which are defined as: New

Year’s Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day, day after

Thanksgiving Day, and Christmas Day.

A Howard S. Wright (HSW) representative will be onsite at all times during construction

activities and will respond to any issues that may arise.

3.2 High noise-generating activities

Activities that will potentially generate unusual amounts of noise will be as follows:

• Demolition of existing structure

• Chipping, sawing and removal of site concrete and asphalt

• Drilling for installation of shoring system

• Shotcrete activities

• Crane setup & dismantle

• Structural steel erection

• Setup for concrete pouring operations

• Metal Stud Framing Operations

3.3 Noise-sensitive receivers

The following are noise-sensitive receivers:

• Marriott Residence Inn

• CorePower Yoga

• Hotel Deca

• 32 Good Reason – Family, Cosmetic & Implant Dentistry

• U District Family Dentistry – Andy Nelson

• The Collegiana – UW Medicine

Page | 7

3.4 Construction noise management

HSW will use the following techniques to minimize construction noise and vibration:

Timing Restrictions:

i. Most activities will be limited to standard construction hours, which are 7 a.m. to 6

p.m. on non-holiday weekdays.

ii. Impact types of equipment such as, pavement breakers, jackhammers, powder-

actuated tools and other impulse noise sources will only be used between 8 a.m.

and 5 p.m. weekdays and 9 a.m. and 5 p.m. on Saturday.

Noise Reduction Construction Technologies:

i. “Ambient Sensitive Broadband Alarms” for all equipment requiring alarms will be

used. These devices use a motion sensor to activate the back-up alarm; otherwise

the alarms operate at a much-reduced level.

ii. Back-up alarms will not be allowed to operate from 10 p.m. to 7 a.m. on weekdays

and 10 p.m. to 9 a.m. on Saturdays.

Process Modifications:

i. Reduce truck noise and audible backup alarms by using 12th Ave NE for trucking

activities. 12th Ave NE is the least busy of the streets bordering the jobsite.

ii. Loud talking or other miscellaneous noisy activities are prohibited before 7 a.m. and

after 10 p.m. on weekdays and before 9 a.m. and after 6 p.m. on Saturdays

iii. Concrete truck staging will be done off-site to minimize the impact of street-level

truck traffic. The location of a staging area will depend on awarded Subcontractor’s

coordinated staging plan with the Seattle Department of Transportation.

iv. Pre-fabrication of construction assemblies at off-site locations will minimize on-site

manpower and noisy activity. For staging locations and trucking routes, comment

(iii) above applies.

v. The concrete pumping station and concrete deliveries will be located on 12th Ave NE.

The material and personnel lift will also be located on 12th Ave NE.

vi. A compliance statement for this Construction Management Plan (CMP) will be

included in all subcontracts for this project. HSW is responsible for all subcontractor

adherence to this CMP.

vii. During demolition, excavation and construction, debris and exposed areas will be

sprinkled with water as necessary to control dust.

Page | 8

viii. To aid in maintaining air quality, electrically operated small tools will be used in

place of gas powered small tools wherever feasible. HSW will make every effort to

manage the work to avoid noise variances, and any street closures beyond those

described in other sections of this plan. However, as is typical for urban construction

projects, there will be times when such variances and additional street closures will

be required. Neighbors will be notified by email as describes previously in advance

of any work requiring noise variances, and street closures beyond those described

elsewhere in this plan.

4. Construction Milestones

4.1 Schedule

Construction Milestones:

Start Date – 04/03/2017

Project Duration – 15 Months

Projected Completion Date – 07/10/2018

Projected Milestone Completion Dates

• Site Grading & Demolition – 04/30/2017

• Excavation and Shoring – 7/15/2017

• Structural steel – 12/31/2017

• Project Completion – 07/10/2018

5. Off-site Construction Worker Parking

5.1 Location

a. Construction workers will be encouraged to park outside of downtown and use transit

service to the project. The site is near most major King County Metro bus routes as well as

routes operated by Sound Transit and Community Transit Bus information will be made

available to construction workers.

b. Employees, subcontractors, and vendors that do drive to the site will be obligated by

contract to park their cars at parking garages and lots surrounding the site. Carpooling and

other high-occupancy-vehicle modes of transportation will be encouraged. Parking on the

streets surrounding the site will be discouraged.

c. The peak number of construction workers anticipated on site will be between 80 and 100.

d. HSW will not be constructing any temporary parking areas during the project.

Page | 9

Attached is a map of parking lots in the area and the amount of parking in each area.

6. Right of Way Use

6.1 SDOT Coordination

All necessary coordination with SDOT will be accomplished prior to beginning work on

04/03/2017. HSW will coordinate with SDOT to develop appropriate plans for the various

phases of work.

6.2 Material management

• All material deliveries, soil export, and concrete pumping and delivery will be done from

12th Ave NE. This is the only street that will be reserved for these activities.

• The proposed haul route is attached to this document.

• Mobile cranes will be located on 12th Ave NE through foundation work. The tower crane

will be within the building footprint once it is erected.

• Man hoist/material hoist will be located on 12th Ave NE.

6.3 Pedestrian mobility

Sidewalk Closures:

• The West side 12th Ave NE sidewalk will be closed for the duration of the project both

day and Night.

• However, during evenings 5:00pm – 6:00am Howard S. Wright will open up the parking

lane for pedestrian mobility with the water-filled traffic barricades until the start of the

construction in the morning at 7:00am.

• The NE 45th Street sidewalk will remain open for the duration of the project both day

and night with a covered pedestrian walkway installed for public protection and crew

shacks above.

• The alley will be partially closed for West wall shoring and vertical element activities and

SCL duct bank protection. Howard S. Wright will have onsite flagging available for any

emergency traffic needs down this alley.

• The Alley will also be partially closed during structural steel erection, masonry and

glazing work on the West elevation.

Page | 10

• Access to existing curb ramps, landing area, and pedestrian access shall be maintained

for the duration of the project. Approved exceptions will be granted only for short term

utility or street improvement work.

6.4 Street closures

Street Closures:

• 12th Ave NE parking lane will be closed for the duration of the project.

• 12th Ave NE Southbound and Northbound traffic will be shifted East into the East

parking lane. This shift in traffic will be properly delineated with traffic cones, barricades

and signage. This street modification will occur during working days for activities such

as, Excavation, during concrete pouring operations, and major equipment and material

deliveries. (see attached site logistics plan for schematic)

• Construction flaggers and Police Officers as needed, will be utilized at the intersection of

12th Ave NE and NE 45th St. during Mass Excavation and concrete pour days.

• The alley to the west of the project site will be closed intermittently through the

duration of the project for utility installation, exterior envelope construction and

material/personnel staging.

Attachment 1 Map of Nearby Parking Areas

Attachment 2 Proposed Haul Routes

Attachment 3 Site Logistics Plans

Diamond Parking Lot(93 stalls)

Diamond Parking Lot(88 stalls)

University District ParkingAssoc. (65 stalls)

University District ParkingAssoc. (66 stalls)

WSECU Jobsite1121 NE 45th St.

Attachment 1 WSECU ­ 45th StreetMap of Nearby Parking Areas

Seattle Transit Stops

WSECU Jobsite

Nearby Parking Lots

Attachment 2 WSECU Proposed Haul & Delivery Route

From Northbound/Southbound I­5 to Jobsite: North/South I­5 take Exit to NE 50th St. Turn East off NE 50th St. to 12th Ave NE. Turn South 12th Ave NE through NE 45th St. Arrive at project loading zone

Exiting Jobsite to I­5 Northbound/Southbound:•Exit loading zone to NE 43rd St.•Turn west on NE 43rd St. to 11th Ave NE•Turn North on 11th Ave NE to NE 45th St. •Turn West on NE 45th St. to I­5 North/South on ramps.

WSECUJobsiteIncomingOutgoing

Project Dates: Site Grading & Demolition 04/03/2017 ­ 04/28/2017 Shoring & Excavation 05/02/2017 ­ 07/10/2017 Foundations & Structural Steel 06/26/2017 ­ 11/03/2017

WSECU Jobsite:1121 NE 45th St.

Page | 11

Attachment 2 Proposed Haul Route:

Project Address:

1121 NE 45th St.

Seattle WA, 98105

Project Description:

The Washington State Employees Credit Union (WSECU) – 45th St. project is a 7-story, 66,695 sf

mixed use office building with three floors of below grade parking. WSECU will be building out

the 1st floor as their new branch location, along with a café and community room the second

floor will be built out to house the WSECU administrative team. Floors 3 through 7 will be

leasable shell and core spaces. The building is a structural steel building with a Brick and curtain

wall façade.

From Northbound/Southbound I-5 to Jobsite:

• From Northbound/Southbound I-5 take Exit to NE 50th St.

• Turn East off NE 50th St. to 12th Ave NE.

• Turn South 12th Ave NE through NE 45th St. to project loading zone

Exiting Jobsite to I-5 Northbound/Southbound:

• Exit loading zone to NE 43rd St.

• Turn west on NE 43rd St. to 11th Ave NE

• Turn North on 11th Ave NE to NE 45th St.

• Turn West on NE 45th St. to I-5 Northbound/Southbound on ramps.

Haul Route Narrative:

Truck and Trailer combinations will be used for disposing of demolition debris and site clearing

Demolition of the existing foundations is scheduled to begin approximately 04/03/2107 and

end 04/28/2017. There will be about 3 trucks per day hauling the demolition debris.

Shoring & Mass excavation will follow, scheduled to begin approximately 05/02/2017 and end

07/10/2017. During this time, Approximately 17,500 CY of soil will be exported. 40 loads will be

exported daily at a frequency of 1 truck per 6-8 minutes. Trucks will be loaded on site from an

excavator, entering the site off of 12th Ave NE Southbound and exiting the site down 12th Ave

Page | 12

NE southbound. Flaggers will be utilized to facilitate trucks crossing 45th Ave NE into the loading

zone on 12th Ave NE. Construction loading/unloading will occur on hardscape to minimize risk

of tracking debris onto adjoining streets as well utilization of street sweepers throughout the

day as needed. The trucking operation will take place between the hours of 7:00 am and 6:00

pm.

Structural steel erection will occur on a continuous basis beginning approximately 08/01/2017

and ending 11/03/2017. It is anticipated that between 2 and 3 40’ flatbed semi delivery trucks

will be used a day during the peak of structural steel erection.

Concrete pumping activities will occur approximately once a week beginning roughly

09/01/2017 and ending 12/08/2017. It is anticipated that between 10 and 12 concrete mixer

trucks will be used to pour the concrete fill on metal deck at the peak of construction.

All deliveries will be received on 12th Ave NE Southbound lane. Street use permits will be in

place to adjust the 12th Ave. NE traffic lanes during working hours (7am to 6pm). Including

closing the west sidewalk and parking lane on 12th Ave. NE.

Onsite supervision will be in constant communication with all truck drivers to ensure proper

spacing is occurring during demolition, mass excavation, concrete pours, structural steel

erection and any misc. deliveries throughout the project life cycle.

The contractor acknowledges the following:

o Any changes to routing will need prior approval

o All oversize loads shall have separate approval for each movement

o No truck queuing or staging allowed at or in the vicinity of the job site, including I-5

o All necessary SDOT and DPD permits shall be in place prior to any trucking activity

o No compression brakes (“Jake Brakes”) shall be allowed

o All applicable traffic laws shall be adhered to as defined in Seattle Municipal Code

Title

NE 45TH ST

12TH

AVE

NE

ALL

EY

WSECU ­ 45TH ST1121 NE 45TH ST

SEATTLE, WA

STAGING AREA­SIDEWALK CLOSEDFULL TIME DAY/NIGHT

TEMP ELEC SERVICE ­ ON HOARDING PLATFORM

CREW SHACKS/SUB OFFICES­ ON HOARDING PLATFORM

PEDESTRIAN WALKWAY ­ BELOWHOARDING PLATFORM ­ ABOVE

MAINTAIN (VEHICLE) SIGHT LINES& HANDICAP ACCESS

Attachment 3

ALLEY WAY­ PERIODICALLY ALLEY WILL BE CLOSEDDUE TO CONSTRUCTION ACTIVITIES.BUT WILL REMAIN OPEN IN A REDCUEDSPACE DURING MOST DAYS.

WSECU ­45th StreetSite Logistics Plan:

Work Hours 7:00am ­ 5:00pmDemolition, Shoring, Excavation,

Structural Steel Installation, ConcretePumping.

Anticipated 04/06/2016 ­ 12/08/2016

Work Day Routing

Lane and Alley Closure

Southbound Traffic

Northbound Traffic

12TH AVE NORTH/PARKING LANE­12TH AVE NORTH BOUND LANEWILL BE DIVERTED TO THENORTHBOUND PARKING LANE OF12TH AVE. SIGNAGE AND LANEDELINEATION WILL BE PROVIDED.

LANE DELINEATION ANDCONES BETWEENCONSTRUCTION AREA ANDTRAFFIC.

PARKING LANE & SOUTHBOUND 12TH AVE ­PARKING LANE TO REMAIN CLOSEDDURING WORKING HOURS.­ 12TH AVE NE SOUTHBOUND LANE TO BECLOSED FOR CONSTRUCTION USE ONLYDIVERTING TRAFFIC TO OCCUR ONNORTHBOUND LANES.

12TH AVE SOUTH LANE­12TH AVE SOUTH BOUND LANEWILL BE DIVERTED TO THENORTHBOUND LANE OF 12TH AVE.

CONSTRUCTION FENCE

DURINGWORKING

HOURS

NE 45TH ST

12TH

AVE

NE

ALL

EY

WSECU ­ 45TH ST1121 NE 45TH ST

SEATTLE, WA

STAGING AREA­SIDEWALK CLOSEDFULL TIME DAY/NIGHT

TEMP ELEC SERVICE ­ ON HOARDING PLATFORM

CREW SHACKS/SUB OFFICES­ ON HOARDING PLATFORM

PEDESTRIAN WALKWAY ­ BELOWHOARDING PLATFORM ­ ABOVE

MAINTAIN (VEHICLE) SIGHT LINES& HANDICAP ACCESS

Attachment 3

PARKING LANE ­PARKING LANE USED FORPEDESTRIAN TRAFFIC AFTER HOURS

TRAFFIC LANES­12TH AVE NE SOUTHBOUND ANDNORTHBOUND LANES OPENED FORNORMAL USE AFTERCONSTRUCTION ACTIVITIES

ALLEY WAY­ PERIODICALLY WILL BE CLOSEDTHROUGHOUT THE PROJECT. NORMALOPERATION WILL ALLOW FOR USE AFTERCONSTRUCTION ACTIVIES HAVECOMPLETED FOR THE DAY.

WATER­FILLED BARRICADESW/FENCE AND LIGHT

CONSTRUCTION FENCE

WSECU ­45th StreetSite Logistics Plan:

After hours Hours 5:00pm ­ 6:00amDemolition, Shoring, Excavation,

Structural Steel Installation, ConcretePumping.

Anticipated 04/06/2016 ­ 12/08/2016

Night Day Routing

Alley Closure

Pedestrian Traffic Area