Construction Management Applications: Challenges in Developing Execution Plans
Presented by: Amlan Mukherjee
andNilufer Onder
Michigan Technological University
May 14, 2010 --- ICAPS, Toronto
![Page 2: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/2.jpg)
Construction Management Domain
● To build ... under constraints– Time
– Budget
– Site location
– Resources: equipment, labor, material
● To avoid or contain ... contingencies– Adverse weather
– Accidents
– Delivery problems
– Labor strikes
![Page 3: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/3.jpg)
Our objective
Provide automated project management support for
– Project execution
– What-if analysis
– Contingency planning
![Page 4: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/4.jpg)
Stages of Steel Project Management
Design decision to use steel
Participants● Owner● Architect● Structural engineer● General contractor● Construction manager● Design builder● Steel contractor● Steel fabricator● Steel erector● Lower tier subcontractors● Steel suppliers● Detailers
Design development
Develop contractdocuments Bidding
General contractaward
Steel contractexecution
Award lowertier subcontracts
Erect fabricatedsteel
Deliver fabricated steel
Fabricate steel
Shop drawingapproval
Prepare erection& shop drawings
Deliver material
Order steel
Shop drawingapproval
Deliver
![Page 5: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/5.jpg)
Stages of Steel Project Management (cont’d)
Participants● Owner● Architect● Structural engineer● General contractor● Construction manager● Design builder● Steel contractor● Steel fabricator● Steel erector● Lower tier subcontractors● Steel suppliers● Detailers
Steel contractexecution
Award lowertier subcontracts
Erect fabricatedsteel
Deliver fabricated steel
Fabricate steel
Shop drawingapproval
Prepare erection& shop drawings
Deliver material
Order steel
Shop drawingapproval
Deliver
![Page 6: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/6.jpg)
Structural Framing Plan
![Page 7: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/7.jpg)
Corner of the floor
![Page 8: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/8.jpg)
The schedule
![Page 9: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/9.jpg)
Contingencies – Planning error
![Page 10: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/10.jpg)
Contingencies – Productivity changes
![Page 11: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/11.jpg)
Contingencies – Material not delivered
![Page 12: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/12.jpg)
Contingencies – Space is a concern
![Page 13: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/13.jpg)
The big picture
![Page 14: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/14.jpg)
Current Abilities & Future Needs
● Current Abilities– Gantt charts, critical path method (CPM)
– Linear scheduling (Ioannou et al.)
– Simulation of operations (AbouRizk et al.)
– Virtual/Augmented reality (Martinez, Kamat et al.)
● Resource/resource to human/resource interactions:
– Decision-making at a system-level
– Constraint driven approaches
– Contingency planning
![Page 15: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/15.jpg)
Our system
● ICDMA (Interactive Construction Decision Making Aid)
● Can perform what-if analysis on As Planned Schedules (APSs) if provided with
– Tasks and dependencies
– Relevant constraints
– External events
– Relevant effects of events such as productivity
![Page 16: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/16.jpg)
ICDMA interface
![Page 17: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/17.jpg)
Temporal Network with Activities and Events (TONAE)
A1,B
A1,E
A4,B
A4,E
A2,B
A2,E
A3,B
T1
T2
T3
T4
T5
0
0
6
0
TNOW
Y2
1 1
1
1
E1,B
E1,E
0
1
![Page 18: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/18.jpg)
Monte Carlo Simulations
Ti T
i+2T
i+1
![Page 19: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/19.jpg)
Extend ICMDA with contingency planning
● When the execution deviates from the as-planned schedule (APS), automatically suggest alternatives
● Assumptions of automated planners– The domain information is represented in
PDDL format
– There is a single plan
– All planning activities are done “offline”
![Page 20: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/20.jpg)
Challenge 1: knowledge representation
● Knowledge: – Dispersed, multi-format
– Incomplete operationalization
● Need to represent:– The project plans and schedules
– Constraints
– Stochastic events
![Page 21: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/21.jpg)
Challenge 2: execution time deviations
● Need to consider:– Effects on the cost and the duration
– Constraints that are violated
– Soft constraints
● Show:– Various levels of detail
(HTN-style, macro-style)
– Different views to stakeholders
![Page 22: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/22.jpg)
Challenge 3: contingency responses
● Possible responses:– Do nothing (use contingency funds)
– Reschedule, reallocate
– Replan
● Available technologies– Plan generation
– Planning under uncertainty
– Planning with constraints
![Page 23: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/23.jpg)
Conclusion
● Construction management: knowledge-rich domain
● Challenge 1: knowledge representation to aid contingency responses
● Challenge 2: Understanding the contingencies● Challenge 3: Responding to contingencies
![Page 24: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/24.jpg)
Thank You!
AcknowledgmentsNSF #SES0624118
![Page 25: Construction Management Applications: Challenges in …nilufer/paper-files/onder-icaps10-pres.pdf · Construction Management Applications: Challenges in Developing Execution Plans](https://reader033.vdocuments.us/reader033/viewer/2022050107/5f45536620fb882c7d7022c9/html5/thumbnails/25.jpg)
Additional References
● Ansari, Alex. “Target Costing: When the Client Looks Under the Hood,” Constructor, p. 64, March/April 2010.
● Mrozowski, Tim, Matt Syal, and Syed Aqeel Kakakhel. “Construction Management of Steel Construction: Project Management Module,’’ Technical Report, American Institute of Steel Construction (AISC), 1999.