Page 1: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

C e n t r a l H e a t i n g P l a n t E x p a n s i o n

Boston CollegeArchitectural Development Presentation January 19, 2018

Page 2: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

I. Existing Central Heating Plant

II. Central Heating Plant Upgrade and Purpose

III. Site Plan

IV. Exterior Development

I. Elevations

II. Renderings

III. Proposed Materials

V. Floor Plans

Contents

Page 3: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Existing Central Heating Plant• Provides steam to approximately 2.4M sqft

• Peak steam load – 100,000 lbs/hr (observed winter 2015)

• (3) existing boilers in CHP– (2) are 37 years old, the 3rd is 50 years old

– Installed capacity = 100,000 lbs/hr

– Firm capacity = 62,000 lbs/hr (assumes largest boiler is out of service)

Page 4: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Existing Central Heating Plant• Building Condition

– Original construction – 1948– Aged masonry (stack and building facades)– Non-seismic resistant design– Life-safety limitations (fire protection, FA, ADA compliance)– Non-compliant elect. infrastructure and insufficient E-power– Service Building FCI – 0.65

Page 5: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Central Heating Plant Upgrade & Purpose

• Increase firm capacity to meet peak load – long-term firm capacity = 120,000 lbs/hr

• Improve steam distribution reliability

• Defer replacement of existing boilers

• Accommodate Master Plan timeline & uncertainties

• Upgrade building’s electrical infrastructure

Page 6: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Site Plan

Page 7: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Exterior Development

Page 8: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Existing View from Conte Circle

Page 9: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed East Elevation

Page 10: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed East Elevation – Alternate Brick Penthouse

Page 11: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

11 | CANNONDESIGN - Boston College Recreation Center

Proposed Bi-Folding Doors

Page 12: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

View from Conte Circle – without trees

Page 13: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Alternate Brick Penthouse

Page 14: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

View from Conte Circle

Page 15: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed West Elevation

Page 16: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed West Elevation – Alternate Brick Penthouse

Page 17: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

View from Higgins Hall

Page 18: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

View from Higgins Hall – Alternate Brick Penthouse

Page 19: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed North Elevation

Page 20: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

View from the Conte Forum Campus Walk

Page 21: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Existing and Proposed Stacks

Page 22: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed Stack Design Options

Tapered Pilastered Stepped

Page 23: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Tapered(Basis of Design)

Page 24: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Pilastered Alternate

Page 25: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Pilastered Alternatewith Ornament

Page 26: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Stepped Alternate

Page 27: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Proposed Materials – Brick and Cast Stone

Brick to Match Existing Cast Stone to Match Existing

Page 28: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

CHP AdditionExisting Campus Buildings

Proposed Materials – Metal Panels and Frames

Conte Frm. Higgins Hall Service Bldg. Stokes Hall St. Mary’s Hall

Page 29: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

IntroductionFloor Plans

Page 30: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Level 1

9 Existing Boiler Plant

9 New Boiler Plant

9 Fuel Tank Enclosure

Floor Plans

Page 31: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Level 2- Mezzanine

9 Open to Existing Boiler Plant

9 Open to New Boiler Plant

9 Open to Fuel Tank Enclosure

9 Existing Utility Tunnel

9 Existing Boiler Plant Electrical Room

9 Office

9 Existing Tel/Data Hub

Floor Plans

Page 32: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Floor Plans

Level 3

9 Existing Service Building

9 New Boiler Plant Addition

9 New Exhaust Stack

9 Fuel Tank Enclosure

Page 33: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Floor Plans

Level 4

9 Existing Service Building

9 New Boiler Plant Addition

9 New Exhaust Stack

9 New Fuel Tank Enclosure

Page 34: Construction Documents Technologist (CDT) Study Series · Existing Central Heating Plant • Provides steam to approximately 2.4M sqft • Peak steam load –100,000 lbs/hr (observed

Floor Plans

Level 5

9 Existing Service Building

9 New Boiler Plant Addition

9 New Exhaust Stack

9 New Fuel Tank Enclosure