construction delaware river-site 6-pix by derrick 9-12-2009

49
Riprap covered with Erosion Control Blanket (ECB), & planted with native trees & shrubs through

Upload: eliora

Post on 13-Feb-2016

28 views

Category:

Documents


0 download

DESCRIPTION

Soil-choked Riprap covered with Erosion Control Blanket (ECB), & planted with native trees & shrubs through the ECB. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Soil-choked Riprap covered with Erosion

Control Blanket (ECB), & planted with native

trees & shrubs through the ECB

Page 2: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Riprap to top bank was soil-choked, seeded, covered with a 100% coir 700 grams/ sq. meter series Erosion Control Blanket

(ECB), & five species of container native trees & shrubs planted

through the ECB. Toe protection was LPSTP and Single Stone

Bendway Weirs.

Page 3: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Cutting coir blanket to length plus close-up. This is a 700 series (700 grams per sq. meter blanket. Heavy& tough. Traps soil & seed well,

sticks in dirt when wet, open weave, can be reseeded if needed

CONSTRUCTION DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Page 4: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

SITE 2-B: BANK STABILIZATION TO PROTECT A COUNTY OWNED

HIGHWAY, BUSHKILL, PA.DELAWARE WATER GAP

NATIONAL RECREATION AREA NATIONAL PARK SERVICE PROJECT CONSTRUCTED

SEPTEMBER 19-22, 2009

Page 5: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

PROBLEMS A severe attack angle caused by planform geometry

& a transverse bar that directs the flow of Bushkill Creek into the left descending bank just downstream of Site 2-A had eroded the left descending bank dangerously close to a county-maintained two lane highway. The project is 255 ft long. In places the stream was within 15 ft of the road. The bank was steep in this area with the high velocity thalweg immediately at the toe. In some areas a single row of mature trees attempted to hold the bank together, in other areas trees were absence or dead.

Page 6: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Aerial view of project area with

work limits delineated.

Courtesy of Ecological Restoration, Inc

Page 7: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

PRE-PROJECT PHOTOS by Dave Derrick Dec. 16, 2008

(HIGH WATER) & Sept 9, 2009

Page 8: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

HIGH WATER-Looking DS @ flow attack into Site 2-B.

PRE-PROJECT BUSHKILL CR-SITE 2-B PIX BY DERRICK 12-16-2008

Page 9: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking DS @ left bank (entire length of project)

PRE-PROJECT BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-9-2009

Page 10: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking DS @ left bank. Flow into upper end of project

PRE-PROJECT BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-9-2009

Page 11: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

THE PLAN

Page 12: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

SOLUTIONS (THE PLAN) The upstream section has 210 ft of Longitudinal Peaked

Stone Toe Protection (LPSTP), applied at a rate of 2 tons/ft as a resistive toe protection. Vines were planted to cover the LPSTP stone. Keyed into the LPSTP are 9 Single or Double Stone Bendway Weirs, spaced approx. 30 ft apart. The downstream 45 ft of the project has two Bendway Weirs & 7 Traffic Control Stones. Four keys anchor the entire project, with two keys designed as stairs for fisherman access. Above the entire length of LPSTP is a row of willow & dogwood poles (brush layer). The upstream 85 ft has riprap applied up to top bank, then soil-choked & encapsulated with a 100% coir, 700 grams/sq. meter Erosion Control Blanket (ECB). Five species of trees and shrubs were planted through the ECB. The downstream 125 ft of LPSTP has the single brush layer & about 2 ft of ECB encapsulated earth, with the mid & upper bank sloped & planted with dozens of rooted-stock trees & shrubs.

Page 13: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Courtesy of Ecological Restoration, Inc.

Soil-choked & planted riprap to top bank in pink area-85 ft wide

Page 14: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Courtesy of Ecological Restoration, Inc.

This is typical protection US & DS of the Soil-choked

Riprap protection

Page 15: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Cottonwood 30 in tree bands (small pots)

Sycamore 10 2 gallon fiber pots Silver Maple 10 2 gallon pots Red Oak 10 3 gallon pots Silky Dogwood 500 bare root Black Willow 250 bare root Ninebark 233 bare root Virginia Creeper 52 cuttings Rhododendron 25 3 gallon pots

PLANTS PLANTED Common Name # Size

Page 16: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION PHOTOS

by Dave Derrick, September 22, 2009

Page 17: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US @ large stone for Single & Double Stone Bendway Weirs. No room for construction!

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 18: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US @ completed LPSTP toe protection near DS end. Valuable trees untouched. Single Stone Bendway Weir

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 19: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US @ thalweg controlled by Bendway Weirs, note dead water near bank.

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 20: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

The local county road supervisor was worried that the section of bank that was impacted

the most by flow would erode (upper section of project), so in response to his concerns, a

blanket of riprap 85 ft wide was applied up to top bank (riprap applied above the LPSTP). Riprap was soil-choked, covered with a 100%

coir 700 grams/ sq. meter series Erosion Control Blanket (ECB), & five species of container native trees & shrubs planted

through the ECB

Page 21: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Bushkill Creek, Delaware Water Gap, PA

FIL

L

CUT

Slope bank. A balanced cut/fill in all sections. Backfill

anchors the ECB at toe.

Bendway Weir LPSTP

Live Siltation

Erosion Control Blanket

Page 22: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

85 ft wide blanket of riprap applied from LPSTP & Live

Siltation up to top of bank.

Bushkill Creek, Delaware Water Gap, PA

Page 23: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Soil-choke riprap to top of bank.

Bushkill Creek, Delaware Water Gap, PA

Page 24: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Seed all soil-choke soil.

Bushkill Creek, Delaware Water Gap, PA

Page 25: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Riprap to top bank, then soil-choked. Leah is spreading grass seed. The local road super was worried about the

impact zone eroding, so riprap to top bank.

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 26: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Bushkill Creek, Delaware Water Gap, PA

Install Erosion Control Blanket, dig key at top bank

to anchor ECB

Page 27: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US. Upper end of ECB tucked into key trench.

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 28: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US. Backfilling the uphill ECB anchor trench

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 29: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Looking US. Backfilling the uphill ECB anchor trench

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-22-2009

Page 30: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

Bushkill Creek, Delaware Water Gap, PA

Install rooted stock plants through ECB as appropriate

Page 31: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

PROJECT COMPLET

E

Page 32: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE

Photos by Derrick SEPT. 25, 2009

Page 33: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-Looking downhill @ the soil-choked riprap with Erosion Control Blanket cover & rooted plants

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Page 34: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-Looking at the ECB uphill key. ECB was trenched in, then backfilled with soil & stone.

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Page 35: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-Looking DS @ flow into Site 2-B. Upstream key & US end of project. Riprap area is covered by the tan Erosion Control Blanket.

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Page 36: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-LPSTP with Live Siltation, Single-Stone Bendway Weirs, ECB with riprap to top bank

with soil-choke & tree & shrub rooted-stock plantings

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Page 37: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-LPSTP with Live Siltation, Single-Stone Bendway Weirs, ECB with riprap to top bank

with soil-choke & tree & shrub rooted-stock plantings. Note dead water near bank due to Bendway Weirs

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Soil-Choked Riprap

Page 38: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

CONSTRUCTION COMPLETE-Looking @ the DS half of the project

CONSTRUCTION BUSHKILL CR-SITE 2-B PIX BY DERRICK 9-25-2009

Soil-Choked Riprap

Page 39: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

1 YEAR AFTER PROJECT

COMPLETION Photos by

Dave DerrickSEPT. 12, 2010

Page 40: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

1 YEAR LATER-Looking DS @ mid-project area. LPSTP, Bendway Weirs, Soil-Choked Riprap & many plantings

1 YEAR LATER-BUSHKILL CR-SITE 2-B - DERRICK 9-12-2010

Soil-Choked Riprap

Page 41: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

1 YEAR LATER-Looking US @ the transverse bar directing flow into the formerly eroding bank. Riprap with

soil choke encapsulated with ECB with plantings.

1 YEAR LATER-BUSHKILL CR-SITE 2-B - DERRICK 9-12-2010

Page 42: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

1 YEAR LATER-Looking @ section covered by full bank riprap, then soiled, seeded, & covered by Erosion Control Blanket (ECB)

1 YEAR LATER-BUSHKILL CR-SITE 2-B - DERRICK 9-12-2010

Page 43: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

14 MONTHS AFTER PROJECT

COMPLETIONHIGH WATERPhotos by Derrick

Nov. 4, 2010

Page 44: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

FROM UPSTREAM

TO DOWNSTREAM

Page 45: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

HIGH WATER-Looking @ the US end of Site 2-B. Soil-choked riprap. Water is redirected by the transverse bar toward the project (US arrows),

but then redirected again by the Bendway Weirs (SSBW), DS arrow.

14 MONTHS LATER-BUSHKILL CR-SITE 2-B - DERRICK 11-4-2010

Page 46: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

HIGH WATER-All of the bank in this picture is rip rapped to top bank, soil-choked, seeded, & covered with a 700 series, 100% coir, 100%

degradable, Erosion Control Blanket then container plants were installed.

14 MONTHS LATER-BUSHKILL CR-SITE 2-B - DERRICK 11-4-2010

Page 47: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

HIGH WATER-Close-up looking @ soil-choked riprap with Erosion Control Blanket & plantings.

14 MONTHS LATER-BUSHKILL CR-SITE 2-B - DERRICK 11-4-2010

Page 48: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

HIGH WATER-Close-up looking @ soil-choked riprap with Erosion Control Blanket & plantings.

14 MONTHS LATER-BUSHKILL CR-SITE 2-B - DERRICK 11-4-2010

Page 49: CONSTRUCTION  DELAWARE RIVER-SITE 6-PIX BY DERRICK 9-12-2009

PEYTON & CLEOPHUS READY TO DO SOME

COLD WEATHER MOWING