construction - b.c. homepage - province of british columbia · construction performance ... 26...
TRANSCRIPT
CONSTRUCTION
PERFORMANCE SIMULATION OF PROPOSED CHANGES TO THE 2015 EDITION OF THE
NATIONAL ENERGY CODE FOR BUILDINGS (NECB), RELATIVE TO THE 2011 EDITION OF
THE NECB Steve Cornick, Aziz Laouadi and Iain Macdonald, 5
th June 2015
81
PERFORMANCE SIMULATION OF PROPOSED CHANGES TO THE 2015 EDITION OF THE NATIONAL ENERGY CODE FOR BUILDINGS (NECB), RELATIVE TO THE 2011 EDITION OF
THE NECB
Author Iain Macdonald, PhD
Approved Trevor Nightingale, PhD Program Leader HPB Program, NRC Construction
Report No: A1-006606-01.1
Report Date: 5th June 2015
Contract No: A1-006606-01
Agreement date: 15th March 2015
Program: HPB
65 pages
Copy no. 1 of 1 copy
83
A1-006606-01 final report
PERFORMANCE SIMULATION OF PROPOSED CHANGES TO THE 2015 EDITION OF
THE NATIONAL ENERGY CODE FOR BUILDINGS (NECB), RELATIVE TO THE 2011
EDITION OF THE NECB
Steve Cornick, Aziz Laouadi and Iain Macdonald
National Research Council Canada
Ottawa ON K1A 0R6 Canada
A Report for Canadian Codes Center
2015-06-05
85
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report i
PERFORMANCE SIMULATION OF PROPOSED CHANGES TO THE 2015 EDITION OF THE
NATIONAL ENERGY CODE FOR BUILDINGS (NECB), RELATIVE TO THE 2011 EDITION
OF THE NECB
Steve Cornick, Aziz Laoudi and Iain Macdonald
Executive Summary
This report details the simulation study undertaken to estimate energy savings resulting from code
changes between the 2011 and 2015 editions of the National Energy Code for Buildings (NECB).
The study focussed on the four most common building types in Canada (large office, midrise
apartment, strip mall and secondary school) and examined performance across all climate zones.
Archetype models representing the four building types were supplied and the NRCan authored
software CanQuest was used as the basis of the analysis.
The supplied models from previously reported results were not fully documented (a report
summarising the main inputs and results obtained was available) and CanQuest has not been
officially released (the study used beta version v1.0b1r2937). The supplied models were created with
an older version of CanQuest and required manual updating of the input files (i.e. editing of files
outside of CanQuest).
It was not possible to replicate the previously reported results across all climate zones with the
current beta version of the software and the supplied models. This resulted in changes to the
modelling approach – essentially each archetype was modelled in one climate zone and from these
results savings estimated in the other zones.
The overall results for each archetype are as follows:
Zone 4
Zone 5
Zone 6
Zone 7a
Zone 7b
Zone 8
Energy
Consumption
(kWh/m2)
‘11 ‘13 ‘15 ‘11 ‘13 ‘15 ‘11 ‘13 ‘15 ‘11 ‘13 ‘15 ‘11 ‘13 ‘15 ‘11 ‘13 ‘15
Large Office 144 123 121 168 133 132 176 139 138 165 140 139 163 145 143 172 154 152
Large MURB n/a 137 133 n/a 167 163 n/a 170 166 n/a 173 168 n/a 178 172 n/a 203 197
Strip Mall 270 186 182 318 228 224 368 263 259 388 284 280 441 315 311 549 385 381
Secondary
School 209 152 150 251 183 181 276 194 192 263 203 202 288 214 213 327 247 245
In the above Table “’11” refers to the report commissioned for NRCC and gives the 2011 estimates
[1], “’13” gives the results from the previous report commissioned on NECB 2015 modelling work
[2], and “’15” gives the results from the work commissioned for this report. Note the 2011 study did
not contain energy consumption figures for the Large MURB archetype.
In conducting this work the authors made several observations on CanQuest. Overall the authors
believe that this will be a useful tool for code compliance work: the modelling process is
streamlined, parametric options can be explored and (once enabled) the compliance report should
provide a clear summary of the modelling results. Several ‘bugs’ exist within the tool at present,
notably conversions between metric and US IP units (the underlying simulation tool requires the use
of US IP units). Of particular note: the parametric run interface asks for metric values but converts
these to metric when closing the screen (i.e. the underlying code is expecting a number in US IP
units and converting it unnecessarily); on examining the input files the conversion from liters to US
gallons uses the conversion to imperial gallons (4.2 instead of 3.8), this will overestimate water
use/energy associated with water draws.
86
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report ii
For future studies the more general purpose simulation tool EnergyPlus is recommended over
CanQuest. The constrained interface for CanQuest is not suitable for modelling ‘what if’ studies for
energy code development as its focus is on code compliance with existing codes (most of this
functionality is enabled ‘behind the scenes’ and is not transparent to the user). Recent developments
around EnergyPlus have enabled the automatic creation of large numbers of ‘archetype’ models,
enabling a more comprehensive examination of proposed code changes. For example, the orientation
and FDWR (fenestration and door to wall ratio) can be parameterised and thus changes to wall R-
values or daylighting control, for example, can be examined for a range of buildings. This analysis
would provide a more targeted approach to code enhancement.
87
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report iii
Acknowledgements
This investigation is part of the NRC Construction project “PERFORMANCE SIMULATION OF
PROPOSED CHANGES TO THE 2015 EDITION OF THE NATIONAL ENERGY CODE FOR
BUILDINGS (NECB), RELATIVE TO THE 2011 EDITION OF THE NECB”, NRC Project # A1-
006606-1, supported by the Canadian Codes Center. The authors are grateful to Elisabeth Girgis
from NRC, and to members of the TG-CC steering committee for their assistance. Frédéric Genest’s
help was invaluable in resolving the pumping power requirements.
The authors would also like to thank Heather Knudsen for reviewing the report. Your comments
provided us with valuable insights.
88
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report iv
Table of Contents
1 Introduction ..................................................................................................................................... 1
1.1 Background .............................................................................................................................. 1
1.2 Objectives ................................................................................................................................ 1
2 Modelling Approach ....................................................................................................................... 2
2.1 Adopted approach .................................................................................................................... 2
3 Code Change Summary .................................................................................................................. 3
3.1 Hot water discharge rates ......................................................................................................... 3
3.2 Pipe and Duct Insulation .......................................................................................................... 3
3.3 Lighting Power and Controls ................................................................................................... 3
3.4 Pumping power ........................................................................................................................ 3
4 Models............................................................................................................................................. 4
4.1 Large Office ............................................................................................................................. 4
4.1.1 Model Description ................................................................................................................. 4
4.1.2 Model Verification ................................................................................................................. 6
4.1.3 Modelled code changes .......................................................................................................... 7
4.1.4 Results from Individual Changes ........................................................................................... 8
4.2 Large MURB ......................................................................................................................... 10
4.2.1 Model Description ............................................................................................................... 10
4.2.2 Model Verification ............................................................................................................... 12
4.2.3 Modelled code changes ........................................................................................................ 13
4.2.4 Results from Individual Changes ......................................................................................... 14
4.3 Strip Mall ............................................................................................................................... 18
4.3.1 Model Description ............................................................................................................... 18
4.3.2 Model Verification ............................................................................................................... 20
4.3.3 Modelled code changes ........................................................................................................ 21
4.3.4 Results from Individual Changes ......................................................................................... 22
4.4 Secondary School ................................................................................................................... 23
4.4.1 Model Description ............................................................................................................... 23
4.4.2 Model Verification ............................................................................................................... 25
4.4.3 Modelled code changes ........................................................................................................ 26
4.4.4 Results from Individual Changes ......................................................................................... 27
5 Overall Savings ............................................................................................................................. 31
5.1 Large Office ........................................................................................................................... 32
89
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report v
5.2 Large MURB ......................................................................................................................... 33
5.3 Strip Mall ............................................................................................................................... 34
5.4 Secondary School ................................................................................................................... 35
6 References ..................................................................................................................................... 36
A.1 Effect of proposed changes in water draw ................................................................................ 37
A.1.1 Large Office Building Archetype ....................................................................................... 37
A.1.2 Small Strip Mall Building Archetype ................................................................................. 39
A.1.3 Large Multi-Unit Residential Building Archetype ............................................................. 39
A.1.4 Secondary School Building Archetype ............................................................................... 41
A.2 Effect of proposed changes in pipe insulation ........................................................................... 43
A.3 Effect of proposed changes in lighting power density .............................................................. 44
A.3.1 Large Office Building Archetype ....................................................................................... 44
A.3.2 Small Strip Mall Building Archetype ................................................................................. 47
A.3.3 Large Multi-Unit Residential Building Archetype ............................................................. 50
A.3.4 Secondary School Archetype .............................................................................................. 53
A.4 Effect of proposed changes in limits to pumping power ........................................................... 55
A.4.1 Large Office Building Archetype ....................................................................................... 56
A.4.2 Small Strip Mall Building Archetype ................................................................................. 59
A.4.3 Large Multi-Unit Residential Building Archetype ............................................................. 59
A.4.4 Secondary School Archetype .............................................................................................. 64
90
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 1
1 Introduction
1.1 Background
The Standing Committee on Energy Efficiency in Buildings (SCEEB) along with its associated task
groups, have reviewed and revised the requirements of the National Energy Code of Canada for
Buildings (NECB) 2011, to create the 2015 edition of the NECB which is scheduled for publication
in late 2015. As part of the revisions made to the 2011 edition of the NECB are performance
improvements to the prescriptive requirements in Part 3 (Building Envelope), Part 4 (Lighting), Part
5 (Heating, Ventilation, and Air-Conditioning (HVAC) Systems), and Part 6 (Service Water Heating
(SWH) Systems).
SCEEB is seeking assistance in determining, based on energy modeling, the percent energy
efficiency improvement the NECB 2011 compared with the NECB 2015.
1.2 Objectives
The objective of this study was to compare the energy consumption of buildings built according to
the NECB 2011 to that of buildings built according to the NECB 2015, through energy simulation.
The percentage difference in energy consumption will be determined for the entire building and for
each building component, namely; HVAC, SHW, lighting, and the envelope losses (heating season)
and energy gain (cooling season).
The simulations were based on the archetype buildings supplied by the Canadian Codes Center
(CCC). The four building archetypes modeled were: midrise apartment, large office, strip mall and
secondary school. Collectively these building types represent 85-90% of constructed floor area in
Canada (NRCan data). Simulation results for each of the 6 Canadian climate zones below were
generated.
Table 1: Heating Degree-Days (HDD*) of Building Location, Celsius degree-days.
Zone 4 Zone 5 Zone 6 Zone 7A Zone 7B Zone 8
HDD <3000 3000 to 3999 4000 to 4999 5000 to 5999 6000 to 6999 ≥ 7000
Representative
city/climate
(HDD for city)
Victoria
(2650)
Windsor
(3400)
Montreal/Dorval
(4400)
Edmonton
(5120)
Fort
McMurray
(6250)
Yellowknife
(8170)
* – HDD values taken from Table C-2 NBC 2010
91
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 2
2 Modelling Approach
Models for the four archetypes were supplied by the CCC to enable a consistent modelling approach
with previous studies. The proposed modelling plan was to:
1. Simulate the supplied models with the current version of CanQuest and confirm that the
results were the same as previously reported [2].
2. Update the models to incorporate the 2011-2015 code changes [3] that had not been included
in the previous study.
3. Extract results and summarise predicted energy savings.
On attempting to simulate the supplied models with the current version of CanQuest it quickly
became apparent that a different modelling approach would be required. As clearly stated by the
CanQuest developers, there is no model version control between beta versions of the software. The
supplied models had been created with an older version of CanQuest than is currently available –
practically speaking this meant that the models could not be loaded into the current version.
In addition to the model/software version incompatibility, there was incomplete documentation
describing the modelling approach and assumptions made when the supplied models were created.
The modelling report [2] contained a high level summary of the model inputs and results from the
simulations. There was no explicit linkage between this information and the models provided,
making use of the models difficult. For instance there is a single strip mall model but six office
models; naming conventions were not followed resulting in different naming schemes being
employed between and within archetypes. This resulted in confusion about what exactly was
contained in each model and considerable time was spent trying to resolve issues with the supplied
models.
2.1 Adopted approach
To overcome the difficulties faced due to the model/software version incompatibility, an updated
approach was adopted in consultation with the CCC:
1. Identify one archetype model for each building type (i.e. for a single climate zone).
2. Update the model inputs to agree with code requirements as described in the documentation
provided (this was equivalent to the NECB 2015 changes included in the previous study).
3. Verify that the output from CanQuest was equivalent to that previously published [2].
4. Apply the new code changes to the model and calculate predicted energy savings.
5. Based on these results, extrapolate performance to the remaining climate zones.
The modelling approach is detailed in 0where the relationships between the code changes and EUIs
are developed.
92
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 3
3 Code Change Summary
The tables in the following sections summarise the additional (over the previous report) modelled
code changes between NECB 2011 and 2015 [3].
3.1 Hot water discharge rates
NECB 2011 NECB 2015
6.2.6 Specifies rates for showers (9.5
L/min) and faucets in lavatories (8.3
L/min).
6.2.6 Showers (7.6 L/min); Lavatory faucets (5.7 L/min).
(source – PCF 829 in NECB package
2014_public_review_2014-09-11 -.pdf)
3.2 Pipe and Duct Insulation
NECB 2011 NECB 2015
Table 6.2.3.1 specifies minimum thickness
depending on space and pipe diameter.
PCF 638 – insulation thicknesses increased.
3.3 Lighting Power and Controls
NECB 2011 NECB 2015
4.2 and 4.3 – pretty
much all of each
section
8.4.3.3 adds lux levels to table A-8.4.3.3.(1)A permit modelling of lighting controls.
(source – PCF 839 in NECB package 2014_public_review_2014-09-11 -.pdf)
8.4.4.6 updated to account for occupancy. (source – PCF 839 in NECB package
2014_public_review_2014-09-11 -.pdf)
Changes to 4.2 mentioned in PCF but no changes listed in supplied docs.
3.4 Pumping power
NECB 2011 NECB 2015
8.4.4.15
describes how to
model pumps –
use same
efficiency in
both models.
PCF 582 – limits places on pumping power depending on system and thermal loads:
[5.2.6.3.] ---Pumping Power Demand
[1] --)The combined pumping power demand required by the motors of all the pumps of a
given hydronic system shall not exceed:
[a] --)14 Wmotor power per kWthermal-peak for cooling systems,
[b] --)4.5 Wmotor power per kWthermal-peak for heating systems,
[c] --)12 Wmotor power per kWthermal-peak for heat rejection systems, and
[d] --)22 Wmotor power per kWthermal-peak for water-source heat pumps systems.
Where:
kWthermal-peak is the peak thermal demand of the space at design conditions
Wmotor power is the combined power of the pump motors.
93
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 4
4 Models
4.1 Large Office
4.1.1 Model Description
The supplied model “Large Office slab fixed z5.pd2” was used as the basis for the analysis. The
model was updated as shown in the table below. Note that for consistency with previous reports, the
same table layout has been used. The ‘Supplied Model’ column is reproduced directly from [2] and
only items that have been changed are described in the ‘Updates/changes’ column.
Item Code Section Supplied Model Updates/changes
Schedules
NECB Schedule MNECB-97 A-Office Occup
Sched
MNECB-97 A-Office Lights
Sched
MNECB-97 A-Office Recept
Sched
MNECB-97 A-Office HotWtr
Sched
MNECB-97 A-Office Fans
Sched
MNECB-97 A-Office Heatng
Sched
MNECB-97 A-Office Coolng
Sched
M/NECB A Occup Sched
M/NECB A Lights Sched
M/NECB A Recept Sched
M/NECB A HotWtr Sched
M/NECB A Fans Sched
M/NECB A Heatng Sched
M/NECB A Coolng Sched
Electrical
Lighting Power
Density
4.2.1.6. 8.8 W/m2
Plug Load Density A-8.4.3.3. 7.5 W/m2
Air side HVAC system
Air Handling Unit 8.4.4.10 Packaged VAV system with
gas furnace, electric reheat and
DX cooling
Supply Fan and
Motor
8.4.4.19 1000 Pa 55% efficiency
Return Fan and
Motor
8.4.4.19 250 Pa 30% efficiency
Fan Performance Table 8.4.4.18 Between 7.5 and 25 kW curve
94
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 5
Curve
Outdoor air NBC Part 9,
9.32.3. for
MURBs and
ASHRAE 62.1 for
all others
0.5 L/s/m2
Air-to-Air Heat
Recovery
5.2.10.4 for
MURBS and
5.2.10.1 for all
others
None
Economiser
control
Table 6.5.1.1.3A
for restaurants and
arena, and section
5.2.2.8 A5.2.2.8
for all others
Dry bulb with high limit at 18
°C
Zonal Units VAV boxes
Zonal Units
Efficiency
N/A N/A
Zonal Units Fan
Power
N/A N/A
Cooling
Central Equipment DX cooling
Central Equipment
Efficiency
Table 5.2.12.1 COP 2.78
EIR without fans 0.2748
Performance curve Table 8.4.4.12 DX cooling NECB curve
Chilled water loop
pump
8.4.4.11 N/A
Cooling Tower 8.4.4.12 N/A
Cooling Tower
Fans
5.2.13 N/A
Condenser Water
Loop Pumps
N/A
Heating
Central Equipment 5.2.12.1 Furnace
Central Equipment Et 80% (Furnace)
95
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 6
Efficiency
Performance curve Table 8.4.4.22 A NECB furnace curve
Heating water
loop pumps
8.4.4.10 N/A
Motor efficiency CSA C390 N/A
Zone heating Electric baseboard
Domestic Hot water
Demand 2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
3.8 L/person/day
Efficiency Table 6.2.2.1 Heat Input Ratio = 1.25
Supply
temperature
2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
60 °C
Pump efficiency CSA C390 Premium
4.1.2 Model Verification
The updated model was verified against previously reported results. The following table shows the
results for the Large Office.
Zone 5
Energy Consumption (kWh/m2) Old New
Space Cool 16.8 15.4
Heat Reject 1.0 0.9
Space Heat 29.0 84.3
HP Supp. 0.0 0.0
Hot Water 3.8 3.62
Vent. Fans 17.6 15.5
96
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 7
Pumps & Aux 12.6 12.5
Ext Usage 0.0 0.0
Misc. Equip. 27.3 27.3
Task Lights 0.0 0.0
Area Light 25.1 25.1
Total 133.2 184.6
4.1.3 Modelled code changes
For the Large Office archetype, the following changes were modelled.
Hot water discharge rates
This code change was modelled by adjusting the total daily hot water draw in the CanQuest models.
The hot water draw was parameterized by varying the hot water consumption, L/person/day. The
reduction in shower draw from the 2011 NECB is 20%, whereas the reduction in faucet draw from
the 2011 NECB is 31%.
For the Large Office model this change was modelled by reducing the total daily hot water draw by
30% (representing mainly faucet draws).
Pipe and Duct Insulation
This change was not explicitly modelled in CanQuest. The approach taken was to estimate the total
length of pipework in the office archetype and to use the 50% saving factors from the PCF (i.e.
assuming half of the heat loss is useful energy to the building). These were then applied to the
existing CanQuest results.
The pipe length was estimated as twice the total height of the building plus the perimeter of the
building times the number of floors. The vertical pipes were assumed to be 2” and those servicing
the floor 1”, resulting in savings of 3 W/m and 1 W/m respectively.
Lighting Power and Controls
The LPD modelled in the previous report was equal to the NECB 2015. Therefore, no changes were
made to the LPD in the Large Office model.
The available version of CanQuest coupled with the lack of model documentation precluded any
modelling of daylight or other controls. These are non-trivial exercises and require a careful
approach regarding the assumptions used to generate the model. Therefore, daylighting and controls
were not modelled in the current study.
Pumping power
To model these changes a two stage process was used. The initial calculation was used to size the
equipment. From this calculation, the limit on pumping power was set according to the NECB 2015
requirements. For the office model it was discovered that these values were already being used.
Therefore, no changes were made to the Large Office model.
97
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 8
4.1.4 Results from Individual Changes
For clarity, only results that differ from the old model are shown in the ‘new’ column in the
following tables (i.e. empty cells represent data that does not change between old and new models).
Hot water discharge rates (Large Office)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 14.2 16.8 15.5 13.4 13.4 12.0
Heat Reject 0.5 1.0 0.8 0.5 0.5 0.4
Space Heat 22.1 29.0 35.4 39.3 43.2 52.1
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 3.8 2.7 3.8 2.7 4.0 2.9 4.3 3.1 4.4 3.2 4.9 3.5
Vent. Fans 17.4 17.6 17.5 17.8 18.2 19.2
Pumps & Aux 12.3 12.6 13.3 12.7 12.5 12.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.1 25.1 25.1 25.1 25.1 25.1
Total 122.7 121.6 133.2 132.1 138.9 137.8 140.4 139.2 144.6 143.4 153.5 152.1
Saving (%) 0.8 0.8 0.7 0.9 0.9 0.9
98
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 9
Pipe and Duct Insulation (Large Office)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 14.2 16.8 15.5 13.4 13.4 12.0
Heat Reject 0.5 1.0 0.8 0.5 0.5 0.4
Space Heat 22.1 21.9 29.0 28.8 35.4 35.2 39.3 39.0 43.2 43.0 52.1 51.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 3.8 3.8 4.0 4.3 4.4 4.9
Vent. Fans 17.4 17.6 17.5 17.8 18.2 19.2
Pumps & Aux 12.3 12.6 13.3 12.7 12.5 12.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.1 25.1 25.1 25.1 25.1 25.1
Total 122.7 122.4 133.2 133.0 138.9 138.7 140.4 140.1 144.6 144.4 153.5 153.2
Saving (%) 0.2 0.2 0.1 0.2 0.1 0.2
Lighting Power and Controls (Large Office)
No changes in results as the current NECB 2015 requirements were included in the supplied model.
Pumping power (Large Office)
No changes in results as the current NECB 2015 requirements were included in the supplied model.
99
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 10
4.2 Large MURB
4.2.1 Model Description
The supplied model “NECB Archetype-Large Murb-Windsor_2015.pd2” was used as the basis for
the analysis. The model was updated as shown in the table below. Note that for consistency with
previous reports, the same table layout has been used. The ‘Supplied Model’ column is reproduced
directly from [2] and only items that have been changed are described in the ‘Updates/changes’
column.
Item Code Section Supplied Model Updates/changes
Schedules
NECB Schedule MNECB-97 G-Multfam
Heatng Sched
MNECB-97 G-Multfam
Coolng Sched
M/NECB G Heatng Sched
M/NECB G Coolng Sched
Electrical
Lighting Power
Density
4.2.1.6. 3.93 W/m2 6.5 W/m
2 modelled for NECB
2011 and 5.5 W/m2 for NECB
2015
Plug Load Density A-8.4.3.3. 6 W/m2
Air side HVAC system
Air Handling Unit 8.4.4.10 System 4-Single-zone make-
up air system
Supply Fan and
Motor
8.4.4.19 640 Pa 40% efficiency
Return Fan and
Motor
8.4.4.19 No Return Fan
Fan Performance
Curve
Table 8.4.4.18 NA Constant Volume
Outdoor air NBC Part 9,
9.32.3. for
MURBs and
ASHRAE 62.1 for
all others
Overall 0.589 L/s/m2
0.3 L/s/m2 (Corridor) 748 L/s;
1 Bed=75 cfm; 2 Bed=85 cfm;
3 Bed=105 cfm
Air-to-Air Heat
Recovery
5.2.10.4 for
MURBS and
5.2.10.1 for all
others
minimum 50%-65% sensible
efficiency in zone 6, 7 and 8
Economiser Table 6.5.1.1.3A
for restaurants and
N/A
100
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 11
control arena, and section
5.2.2.8 A5.2.2.8
for all others
Zonal Units Water source heat pumps
Zonal Units
Efficiency
N/A COPc 3.28, COPh4.2
Zonal Units Fan
Power
N/A 0.0005 kW/L/s
Cooling
Central Equipment DX cooling
Central Equipment
Efficiency
Table 5.2.12.1 SEER 14
EIR without fans 0.2748
Performance curve Table 8.4.4.12 DX cooling NECB curve
Chilled water loop
pump
8.4.4.11 N/A
Cooling Tower 8.4.4.12 0.061 kWfan/kWcap
Cooling Tower
Fans
5.2.13 Centrifugal fan indirect-
contact evaporative cooling
towers
Condenser Water
Loop Pumps
22 Wmotor power per kWthermal-peak for
water-source heat pumps
systems.
Heating
Central Equipment 5.2.12.1 2 Boilers, 88-733 kW and
Furnace
Central Equipment
Efficiency
Et = 83% (Boilers),
Et = 80% (Furnaces)
Performance curve Table 8.4.4.22 A
NECB non-condensing and
NECB furnace curves
Heating water
loop pumps
8.4.4.10 N/A
Motor efficiency CSA C390 premium
Zone heating N/A
101
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 12
Domestic Hot water
Demand 2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
53 L/person/day
Efficiency Table 6.2.2.1 Heat Input Ratio = 1.25
Supply
temperature
2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
49 °C
Pump efficiency CSA C390 Premium
4.2.2 Model Verification
The updated model was verified against previously reported results. The following table shows the
results for the Large MURB.
Zone 5
Energy Consumption (kWh/m2) Old New
Space Cool 12.3 4.6
Heat Reject 0.6 0.3
Space Heat 58.5 57.2
HP Supp. 0.0 0.0
Hot Water 43.9 43.4
Vent. Fans 8.2 6.2
Pumps & Aux 8.3 6.9
Ext Usage 0.0 0.0
Misc. Equip. 25.8 0.0
Task Lights 0.0 0.0
Area Light 8.9 8.9
Total 166.7 127.3
102
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 13
4.2.3 Modelled code changes
Hot water discharge rates
This code change was modelled by adjusting the total daily hot water draw in the CanQuest models.
The hot water draw was parameterized by varying the hot water consumption, L/person/day. The
reduction in shower draw from the 2011 NECB is 20%, whereas the reduction in faucet draw from
the 2011 NECB is 31%.
For the large MURB model this change was modelled by reducing the total daily hot water draw by
25% (representing a combination of shower and faucet draws).
Pipe and Duct Insulation
This change was not explicitly modelled in CanQuest. The approach taken was to estimate the total
length of pipework in the office archetype and to use the 50% saving factors from the PCF (i.e.
assuming half of the heat loss is useful energy to the building). These were then applied to the
existing CanQuest results.
The pipe length was estimated as twice the total height of the building plus the perimeter of the
building times the number of floors. The vertical pipes were assumed to be 2” and those servicing
the floor 1” resulting in savings of 3 W/m and 1 W/m respectively.
Lighting Power and Controls
The LPD modelled in the previous report was less than that of the NECB 2015 (3.9 compared to 5.0
W/m2). Therefore, the LPD was increased from the value used previously. The LDP values were
determined using the building area method, 6.5 W/m2 for the 2011 NECB and 5.5 W/m
2 for the
proposed 2015 NECB. The authors were unable to find any mention of values used in the supplied
model, especially 3.9 W/m2 for the living areas and 7.1 W/m
2 for the common areas.
Pumping power
Pump sizing was not specified in the supplied models. A two stage process was used to model these
changes. The initial calculation was used to size the equipment, the boiler and chilled water loop. For
example for Zone 5 the capacity of the boiler was 172 kW. Using the proposed code change, 22
Wmotor per kW yielded a pump size of 3.79 kW. From this calculation the limit on pumping power
was set. This is the value used to compare with the Footprint results. Since the NECB is silent on
pump power the NECB 2011 comparison case was determine using the default setting in CanQuest
(i.e. auto-sized). The beta version of CanQuest used for this work uses ASHRAE 90.1 2010 to auto-
size the pumps. In some cases the auto-sized pumps were smaller than the proposed change.
103
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 14
4.2.4 Results from Individual Changes
For clarity, only results that differ from the old model are shown in the ‘new’ column in the
following tables (i.e. empty cells represent data that does not change between old and new models).
Hot water discharge rates (Large MURB)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.5 12.3 16.0 10.2 13.9 12.6
Heat Reject 0.1 0.6 0.5 0.3 0.4 0.4
Space Heat 41.5 58.5 39.8 42.2 40.0 59.5
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 43.3 36.9 43.9 37.5 47.0 40.1 50.7 43.3 52.5 44.8 58.8 50.2
Vent. Fans 7.2 8.2 24.6 26.0 26.8 27.7
Pumps & Aux 5.5 8.3 7.5 9.0 9.1 9.3
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 8.9 8.9 9.0 9.0 9.0 9.0
Total 136.8 130.4 166.7 160.1 170.3 163.3 173.2 165.8 177.5 169.8 203.1 193.5
Saving (%) 4.6 4.0 4.1 4.3 4.3 4.7
104
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 15
Pipe and Duct Insulation (Large MURB)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.5 12.3 16.0 10.2 13.9 12.6
Heat Reject 0.1 0.6 0.5 0.3 0.4 0.4
Space Heat 41.5 58.5 39.8 42.2 40.0 59.5
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 43.3 43.1 43.9 43.7 47.0 46.8 50.7 50.5 52.5 52.3 58.8 58.6
Vent. Fans 7.2 8.2 24.6 26.0 26.8 27.7
Pumps & Aux 5.5 8.3 7.5 9.0 9.1 9.3
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 8.9 8.9 9.0 9.0 9.0 9.0
Total 136.8 136.6 166.7 166.5 170.3 170.1 173.2 173.0 177.5 177.3 203.1 202.9
Saving (%) 0.1 0.1 0.1 0.1 0.1 0.1
105
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 16
Lighting Power and Controls (Large MURB)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 5.1 4.8 12.9 12.6 16.6 16.3 10.8 10.5 14.5 14.2 13.2 12.9
Heat Reject 0.1 0.6 0.5 0.3 0.4 0.4
Space Heat 39.3 40.2 56.3 57.2 37.6 38.5 40.0 40.9 37.8 38.7 57.3 58.2
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 43.3
43.9
47.0
50.7
52.5
58.8
Vent. Fans 7.3 7.3 8.3 8.3 24.7 24.7 26.1 26.1 26.9 26.9 27.8 27.8
Pumps & Aux 5.5 8.3 7.5 9.0 9.1 9.3
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 14.7 12.5 14.7 12.5 14.9 12.6 14.9 12.6 14.9 12.6 14.9 12.6
Total 136.8 139.4 166.7 169.1 170.3 172.9 173.2 175.9 177.5 180.2 203.1 204.8
Saving (%) -1.9 -1.4 -1.5 -1.6 -1.5 -0.8
106
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 17
Pumping power (Large MURB)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.5 12.3 16.0 10.2 13.9 12.6
Heat Reject 0.1 0.6 0.5 0.3 0.4 0.4
Space Heat 41.3 41.5 58.3 58.5 39.6 39.8 42.0 42.2 39.8 40.0 59.3 59.5
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 43.3
43.9
47.0
50.7
52.5
58.8
Vent. Fans 7.2 8.2 24.6 26.0 26.8 27.7
Pumps & Aux 5.8 5.5 8.6 8.3 7.8 7.5 9.3 9.0 9.4 9.1 8.6 8.3
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 8.9 8.9 9.0 9.0 9.0 9.0
Total 136.9 136.8 166.8 166.7 170.3 170.3 173.3 173.2 177.6 177.5 203.2 203.1
Saving (%) 0.1 0.1 0.0 0.1 0.1 0.1
107
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 18
4.3 Strip Mall
4.3.1 Model Description
The supplied model “Strip mall.pd2” was used as the basis for the analysis. The model was updated
as shown in the table below. Note that for consistency with previous reports the same table layout
has been used. The ‘Supplied Model’ column is reproduced directly from [2] and only items that
have been changed are described in the ‘Updates/changes’ column.
Item Code Section Supplied Model Updates/changes
Schedules
NECB Schedule Schedule C with Saturday
schedules used on Sundays
until 6pm
Electrical
Lighting Power
Density
4.2.1.6. 15.5 W/m2 15.1 W/m
2 modelled for NECB
2011 and 13.5 W/m2 for NECB
2015
Plug Load Density A-8.4.3.3. 2.5 W/m2
Air side HVAC system
Air Handling Unit 8.4.4.10 Dedicated Packaged constant
system with gas furnace and
DX cooling
Supply Fan and
Motor
8.4.4.19 640 Pa 40% efficiency
Return Fan and
Motor
8.4.4.19 No Return Fan
Fan Performance
Curve
Table 8.4.4.18 NA Constant Volume
Outdoor air NBC Part 9,
9.32.3. for
MURBs and
ASHRAE 62.1 for
all others
0.9 L/s/m2
Air-to-Air Heat
Recovery
5.2.10.4 for
MURBS and
5.2.10.1 for all
others
None
Economiser
control
Table 6.5.1.1.3A
for restaurants and
arena, and section
Dry bulb with high limit at
18˚C
108
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 19
5.2.2.8 A5.2.2.8
for all others
Zonal Units None
Zonal Units
Efficiency
N/A None
Zonal Units Fan
Power
N/A N/A
Cooling
Central Equipment DX Cooling
Central Equipment
Efficiency
Table 5.2.12.1 SEER 14
EIR without fans 0.1984
Performance curve Table 8.4.4.12 DX Cooling NECB Curve
Chilled water loop
pump
8.4.4.11 N/A
Cooling Tower 8.4.4.12 N/A
Cooling Tower
Fans
5.2.13 N/A
Condenser Water
Loop Pumps
N/A
Heating
Central Equipment 5.2.12.1 Furnace
Central Equipment
Efficiency
Et 80% Furnace
Performance curve Table 8.4.4.22 A
N/A
Heating water
loop pumps
8.4.4.10 N/A
Motor efficiency CSA C390 N/A
Zone heating N/A
Domestic Hot water
Demand 2011 ASHRAE N/A
109
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 20
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
Efficiency Table 6.2.2.1 N/A
Supply
temperature
2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
N/A
Pump efficiency CSA C390 N/A
4.3.2 Model Verification
The updated model was verified against previously reported results. The following table shows the
results for the Strip Mall.
Zone 5
Energy Consumption (kWh/m2) Old New
Space Cool 8.0 8.0
Heat Reject 0.0 0.0
Space Heat 122.9 123.0
HP Supp. 0.0 0.0
Hot Water 0.0 0.0
Vent. Fans 23.5 23.5
Pumps & Aux 1.0 1.0
Ext Usage 0.0 0.0
Misc. Equip. 10.0 10.0
Task Lights 0.0 0.0
Area Light 62.1 62.1
Total 227.5 227.6
110
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 21
4.3.3 Modelled code changes
Hot water discharge rates
The strip mall does not consider DHW draws. Therefore, no changes were modelled for hot water
discharge rates.
Pipe and Duct Insulation
The strip mall does not contain significant piping (all units are serviced by packaged equipment).
Therefore, no changes were modelled for pipe and duct insulation.
Lighting Power and Controls
The supplied model used the NECB 2011 LPD (15.1 W/m2) this was adjusted to the NECB 2015
value (13.5 W/m2).
Pumping power
There are no pumps in the Strip Mall archetype. Therefore, no changes were modelled.
111
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 22
4.3.4 Results from Individual Changes
For clarity, only results that differ from the old model are shown in the ‘new’ column in the
following tables (i.e. empty cells represent data that does not change between old and new models).
Hot water discharge rates (Strip Mall)
No change from previous results.
Pipe and Duct Insulation (Strip Mall)
No change from previous results.
Lighting Power and Controls (Strip Mall)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 1.5 1.1 8.0 7.6 5.5 5.1 2.2 1.8 2.9 2.5 1.5 1.1
Heat Reject 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 88.2 91.2 122.9 125.9 160.6 163.6 183.9 186.9 213.8 216.8 285.3 288.3
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 0.0 0.0 0.0 0.0 0.0 0.0
Vent. Fans 23.2 23.5 23.9 23.9 24.3 24.8
Pumps & Aux 1.1 1.0 1.1 1.4 1.4 1.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 10.0 10.0 10.0 10.0 10.0 10.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 62.1 55.6 62.1 55.6 62.1 55.6 62.1 55.6 62.1 55.6 62.1 55.6
Total 186.0 182.2 227.5 223.6 263.2 259.3 283.5 279.6 314.5 310.6 385.2 381.3
Saving (%) 2.0 1.7 1.5 1.4 1.2 1.0
Pumping power (Strip Mall)
No change from previous results.
112
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 23
4.4 Secondary School
4.4.1 Model Description
The supplied model “Secondary School NECB_1004_Zone5.pd2” was used as the basis for the
analysis. The model was updated as shown in the table below. Note that for consistency with
previous reports, the same table layout has been used. The ‘Supplied Model’ column is reproduced
directly from [2] and only items that have been changed are described in the ‘Updates/changes’
column.
Item Code Section Supplied Model Updates/changes
Schedules
NECB Schedule Schedule D with Saturday and
Sunday schedules used on
Monday-Sunday in July and
August
Electrical
Lighting Power
Density
4.2.1.6. 10.1 W/m2 10.7 W/m
2 modelled for NECB
2011 and 9.4 W/m2 for NECB
2015
Plug Load Density A-8.4.3.3. 2.8 W/m2
Air side HVAC system
Air Handling Unit 8.4.4.10 System 3 - Single Zone
Packaged Rooftop Unit with
baseboard heating
Supply Fan and
Motor
8.4.4.19 Backward inclined with inlet
vanes at 640Pa 40% efficiency
Return Fan and
Motor
8.4.4.19 No Return Fan
Fan Performance
Curve
Table 8.4.4.18 NA Constant Volume
Outdoor air NBC Part 9,
9.32.3. for
MURBs and
ASHRAE 62.1 for
all others
0.98 L/s/m2
Air-to-Air Heat Recovery 5.2.10.4 for
Air-to-Air Heat
Recovery
5.2.10.4 for
MURBS and
5.2.10.1 for all
others
50% sensible effectiveness for
zones 4, 5, 6, 7a, 7b, and 8 for
main AHUs; 50% sensible
effectiveness for zones 6, 7a,
7b, and 8 for gym's AHU
113
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 24
Economiser
control
Table 6.5.1.1.3A
for restaurants and
arena, and section
5.2.2.8 A5.2.2.8
for all others
Dry bulb with high limit at 18˚C
Zonal Units None
Zonal Units
Efficiency
N/A None
Zonal Units Fan
Power
N/A N/A
Cooling
Central Equipment DX cooling
Central Equipment
Efficiency
Table 5.2.12.1 EER 9.5 for main AHUs, EER
9.8–11 for gym, cafeteria, and
auditorium units
EIR without fans EIR 0.275 for main AHUs, EIR
0.225-0.262 for gym, cafeteria,
and auditorium units
Performance curve Table 8.4.4.12 DX cooling NECB curve
Chilled water loop
pump
8.4.4.11 N/A
Cooling Tower 8.4.4.12 N/A
Cooling Tower
Fans
5.2.13 N/A
Condenser Water
Loop Pumps
N/A
Heating
Central Equipment 5.2.12.1 Boilers at 88-733 kW and
Furnaces
Central Equipment
Efficiency
Et = 83% (Boilers), Et = 80%
(Furnaces)
Performance curve Table 8.4.4.22 A
NECB non-condensing and
NECB furnace curves
Heating water
loop pumps
8.4.4.10 Constant speed, 4.5 Wmotor
power per kWthermal-peak
114
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 25
Motor efficiency CSA C390 Premium
Zone heating Hydronic baseboard
Domestic Hot water
Demand 2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
2.3 L/person/day
Efficiency Table 6.2.2.1 Heat Input Ratio = 1.25
Supply
temperature
2011 ASHRAE
HANDBOOK-
HVAC
Application Table
8 for MURBs/LTC
and Table 7 for all
others
60°C
Pump efficiency CSA C390 Premium
4.4.2 Model Verification
The updated model was verified against previously reported results. The following table shows the
results for the Secondary School. Note that Zone 4 was used for comparison in this case.
Zone 4
Energy Consumption (kWh/m2) Old New
Space Cool 4.1 4.0
Heat Reject 0.0 0.0
Space Heat 53.5 52.8
HP Supp. 0.0 0.0
Hot Water 8.8 8.7
Vent. Fans 24.2 24.2
Pumps & Aux 2.6 2.6
Ext Usage 0.0 0.0
115
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 26
Misc. Equip. 7.0 7.0
Task Lights 0.0 0.0
Area Light 25.4 25.4
Kitchen 26 26
Total 151.6 150.7
4.4.3 Modelled code changes
Hot water discharge rates
This code change was modelled by adjusting the total daily hot water draw in the CanQuest models.
The hot water draw was parameterized by varying the hot water consumption, L/person/day. The
reduction in shower draw from the 2011 NECB is 20%, whereas the reduction in faucet draw from
the 2011 NECB is 31%.
For the secondary school model this change was modelled by reducing the total daily hot water draw
by 25% (representing a combination of shower and faucet draws).
Pipe and Duct Insulation
This change was not explicitly modelled in CanQuest. The approach taken was to estimate the total
length of pipework in the office archetype and to use the 50% saving factors from the PCF (i.e.
assuming half of the heat loss is useful energy to the building). These were then applied to the
existing CanQuest results.
The pipe length was estimated as twice the total height of the building plus the perimeter of the
building times the number of floors. The vertical pipes were assumed to be 2” and those servicing
the floor 1” resulting in savings of 3 W/m and 1 W/m respectively.
Lighting Power and Controls
The supplied model used the NECB 2011 LPD (10.7 W/m2) this was adjusted to the NECB 2015
value (9.4 W/m2).
Pumping power
A two stage process was used to model these changes. The initial calculation was used to size the
equipment, the boiler. For example for Zone 4 the capacity of the boiler was 1740 kW. Using the
proposed code change, 4.5 Wmotor per kW yielded a pump size of 7.83 kW. From this calculation
the limit on pumping power was set. The Footprint model pump size for Zone 4 was 5.18 kW. The
Footprint pump sizing and the NECB 2015 were used for comparison.
116
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 27
4.4.4 Results from Individual Changes
For clarity, only results that differ from the old model are shown in the ‘new’ column in the
following tables (i.e. empty cells represent data that does not change between old and new models).
Hot water discharge rates (Secondary School)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.1 7.5 6.0 4.2 4.7 3.5
Heat Reject 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 53.5 77.1 86.1 94.4
102.9
130.2
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 8.8 6.4 9.0 6.5 9.5 6.9 10.1 7.3 10.4 7.6 11.6 8.4
Vent. Fans 24.2 24.3 25.3 25.5 25.6 25.5
Pumps & Aux 2.6 3.3 3.3 3.5 3.5 3.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.4 28.4 31.0 32.9 34.8 40.0
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Total 151.6 149.2 182.5 180.0 193.6 191.0 203.0 200.2 214.4 211.5 246.6 243.5
Saving (%) 1.6 1.4 1.4 1.4 1.4 1.3
117
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 28
Pipe and Duct Insulation (Secondary School)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.1 7.5 6.0 4.2 4.7 3.5
Heat Reject 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 53.5 77.1 86.1 94.4
102.9
130.2
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 8.8 8.6 9.0 8.8 9.5 9.3 10.1 9.9 10.4 10.2 11.6 11.4
Vent. Fans 24.2 24.3 25.3 25.5 25.6 25.5
Pumps & Aux 2.6 3.3 3.3 3.5 3.5 3.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.4 28.4 31.0 32.9 34.8 40.0
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Total 151.6 151.4 182.5 182.3 193.6 193.4 203.0 202.8 214.4 214.2 246.6 246.4
Saving (%) 0.1 0.1 0.1 0.1 0.1 0.1
118
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 29
Lighting Power and Controls (Secondary School)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.1 4.0 7.5 7.4 6.0 5.9 4.2 4.1 4.7 4.6 3.5 3.4
Heat Reject 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 53.5 55.0 77.1 78.6 86.1 87.6 94.4 95.9 102.9 104.4 130.2 131.7
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 8.8 9.0 9.5 10.1 10.4 11.6
Vent. Fans 24.2 24.1 24.3 24.2 25.3 25.2 25.5 25.4 25.6 25.5 25.5 25.4
Pumps & Aux 2.6 3.3 3.3 3.5 3.5 3.5
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.4 23.5 25.4 23.5 25.4 23.5 25.4 23.5 25.4 23.5 25.4 23.5
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Total 151.6 151.0 182.5 181.9 193.6 193.0 203.0 202.4 214.4 213.8 246.6 246.1
Saving (%) 0.4 0.3 0.3 0.3 0.3 0.2
119
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 30
Pumping power (Secondary School)
Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Energy Consumption (kWh/m2) Old New Old New Old New Old New Old New Old New
Space Cool 4.1 7.5 6.0 4.2 4.7 3.5
Heat Reject 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 53.5 52.6 77.1 76.2 86.1 85.2 94.4 93.5 102.9 102 130.2 129.3
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Hot Water 8.8 9.0 9.5 10.1 10.4 11.6
Vent. Fans 24.2 24.3 25.3 25.5 25.6 25.5
Pumps & Aux 2.6 3.4 3.3 4.1 3.3 4.1 3.5 4.3 3.5 4.3 3.5 4.3
Ext Usage 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Area Light 25.4 25.4 25.4 25.4 25.4 25.4
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Total 151.6 151.6 182.5 182.6 193.6 193.7 203.0 203.6 214.4 214.5 246.6 246.6
Saving (%) 0.1 0.0 0.0 0.0 0.0 0.0
120
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 31
5 Overall Savings
The combined savings were calculated for each building type assuming the principle of
superposition holds. The ‘2013 Report’ results are from the previous modelling work carried out for
the NECB 2015 changes [2] and the ‘2015 NRCC’ are the combined savings from the current work.
The values in the ‘2011 NECB’ columns were taken from the May 2010 report prepared for NRCC
[1].
121
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 32
5.1 Large Office
Zone 4
Zone 5
Zone 6
Zone 7a
Zone 7b
Zone 8
Energy
Consumption
(kWh/m2)
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
Space Cool 8.2 14.2 15.3 16.8 12.5 15.5 7.3 13.4 7 13.4 4.6 12
Heat Reject 10.1 0.5 14 1 15.5 0.8 10.4 0.5 9.4 0.5 8.4 0.4
Space Heat 28.2 22.1 21.8 38.9 29 28.8 48.3 35.4 35.2 48.1 39.3 39 47.8 43.2 43 59.9 52.1 51.8
HP Supp. n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Hot Water 7.7 3.8 2.7 7.8 3.8 2.7 8.3 4 2.9 8.8 4.3 3.1 9 4.4 3.2 8.4 4.9 3.5
Vent. Fans 8.6 17.4 10.2 17.6 9.5 17.5 9.5 17.8 9 18.2 8.4 19.2
Pumps & Aux 5.2 12.3 6.1 12.6 6.3 13.3 5 12.7 4.9 12.5 4.3 12.5
Ext Usage n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Misc. Equip. 35.1 27.3 35.1 27.3 35.1 27.3 35.1 27.3 27.3 35.1 27.3
Task Lights n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Area Light 40.3 25.1 40.3 25.1 40.3 25.1 40.3 25.1 40.3 25.1 40.3 25.1
Total 143.5 122.7 121.3 167.7 133.2 131.9 175.7 138.9 137.6 164.6 140.4 138.9 162.6 144.6 143.2 171.7 153.5 151.8
Saving (%) 1.1 1 0.9 1.1 1 1.1
122
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 33
5.2 Large MURB
Zone 4
Zone 5
Zone 6
Zone 7a
Zone 7b
Zone 8
Energy
Consumption
(kWh/m2)
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
Space Cool n/a 4.5 4.8 n/a 12.3 12.6 n/a 16 16.3 n/a 10.2 10.5 n/a 13.9 14.2 n/a 12.6 12.9
Heat Reject n/a 0.1 n/a 0.6 n/a 0.5 n/a 0.3 n/a 0.4 n/a 0.4
Space Heat n/a 41.4 40.4 n/a 58.4 57.4 n/a 39.8 38.6 n/a 42.2 41 n/a 40 38.8 n/a 59.4 58.4
HP Supp. n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Hot Water n/a 43.3 36.7 n/a 43.9 37.3 n/a 47 39.9 n/a 50.7 43.1 n/a 52.5 44.6 n/a 58.8 50
Vent. Fans n/a 7.2 7.3 n/a 8.2 8.3 n/a 24.6 24.7 n/a 26 26.1 n/a 26.8 26.9 n/a 27.7 27.8
Pumps & Aux n/a 5.6 5.3 n/a 8.4 8.1 n/a 7.6 7.3 n/a 9.1 8.8 n/a 9.2 8.9 n/a 9.1 8.8
Ext Usage n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Misc. Equip. n/a 25.8 25.8 n/a 25.8 25.8 n/a 25.8 25.8 n/a 25.8 25.8 n/a 25.8 25.8 n/a 25.8 25.8
Task Lights n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Area Light n/a 8.9 12.5 n/a 8.9 12.5 n/a 9 12.6 n/a 9 12.6 n/a 9 12.6 n/a 9 12.6
Total n/a 136.9 132.8 n/a 166.8 162.5 n/a 170.3 165.7 n/a 173.3 168.2 n/a 177.6 172.2 n/a 203.2 196.7
Saving (%) 3 2.6 2.7 2.9 3 3.2
123
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 34
5.3 Strip Mall
Zone 4
Zone 5
Zone 6
Zone 7a
Zone 7b
Zone 8
Energy
Consumption
(kWh/m2)
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
NECB 2011
2013 Report
2015 NRCC
Space Cool 5.1 1.5 1.1 21.5 8 7.6 15 5.5 5.1 5.6 2.2 1.8 7/0 2.9 2.5 3.3 1.5 1.1
Heat Reject 0 0 0 0 0 0 0 0 0 0 0 0
Space Heat 147.7 88.2 91.2 177.5 122.9 125.9 233.6 160.6 163.6 255.1 183.9 186.9 312.6 213.8 216.8 423.8 285.3 288.3
HP Supp. n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Hot Water 18.4 0 18.5 0 19.5 0 20.8 0 21.4 21.4 0 25.2 0
Vent. Fans 29.4 23.2 31.8 23.5 30.5 23.9 27.3 23.9 31.4 24.3 28 24.8
Pumps & Aux 0 1.1 0 1 0 1.1 0 1.4 0 1.4 0 1.5
Ext Usage n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Misc. Equip. 9.8 10 9.8 10 9.8 10 9.8 10 9.8 10 9.8 10
Task Lights n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Area Light 59.2 62.1 55.6 59.2 62.1 55.6 59.2 62.1 55.6 59.2 62.1 55.6 59.2 62.1 55.6 59.2 62.1 55.6
Total 269.6 186 182.2 318.3 227.5 223.6 367.7 263.2 259.3 387.9 283.5 279.6 441.3 314.5 310.6 549.3 385.2 381.3
Saving (%) 2 1.7 1.5 1.4 1.2 1
124
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 35
5.4 Secondary School
Secondary
School
Zone 4
Zone 5
Zone 6
Zone 7a
Zone 7b
Zone 8
Energy
Consumption (kWh/m2)
NECB
2011
2013
Report
2015
NRCC
NECB
2011
2013
Report
2015
NRCC
NECB
2011
2013
Report
2015
NRCC
NECB
2011
2013
Report
2015
NRCC
NECB
2011
2013
Report
2015
NRCC
NECB
2011
2013
Report
2015
NRCC
Space Cool 8.9 4.1 3.9 17.2 7.5 7.3 14.6 6 5.8 9.2 4.2 4 9.6 4.7 4.5 7.1 3.5 3.3
Heat Reject 5.7 0 11.5 0 12.1 0 7.5 0 7.3 0 5.8 0 0
Space Heat 72.5 53.5 55.6 93.1 77.1 79.2 118.2 86.1 88.2 115.8 94.4 96.5 139 102.9 105 178.9 130.2 132.3
HP Supp. n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Hot Water 38.8 8.8 8.6 39.3 9 8.8 41.5 9.5 9.3 44.2 10.1 9.9 45.4 10.4 10.2 51.2 11.6 11.4
Vent. Fans 11.7 24.2 24 12.9 24.3 24.1 12.5 25.3 25.1 11.9 25.5 25.3 12.1 25.6 25.4 10.6 25.5 25.3
Pumps & Aux 25 2.6 3.4 30.5 3.3 4.1 30.8 3.3 27.6 3.5 4.3 28.3 3.5 4.3 26.7 3.5 4.3
Ext Usage n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Misc. Equip. 15.2 7 15.2 7 15.2 7 15.2 7 15.2 7 15.2 7
Task Lights n/a 0 n/a 0 n/a 0 n/a 0 n/a 0 n/a 0
Area Light 31.2 25.4 21.6 31.2 28.4 22.4 31.2 31 23 31.2 32.9 23.5 31.2 34.8 24 31.2 40 25.2
Kitchen n/a 26 n/a 28.9 n/a 31 n/a 32.9 n/a 34.8 n/a 40
Total 209 151.6 150.1 250.8 182.5 181 276.2 193.6 192.1 262.6 203 201.5 288.0 214.3 212.8 326.6 246.6 245.2
Saving (%) 1 0.8 0.8 0.7 0.7 0.6
125
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 36
6 References
1. Caneta Research Inc., 2010. “Performance Simulation of Proposed Changes to NECB
Relative to MNECB and ASHRAE 90.1-2007 Final Report” May 2010.
2. Footprint, 2013. “Energy Modelling Report. Modelling of the National Energy Code for
Buildings 2015” Final report, revision 2.
3. NECB. “Technical Changes by Code Section”
http://web.archive.org/web/20140320150029/http:/www.nationalcodes.nrc.gc.ca/eng/public_
review/2013/necb_technical.php. Accessed multiple times between 1/Feb/2015 and
7/May/2015
126
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 37
Appendix A Modelling details
The following sections provide a different view on the modelling undertaken in support of this
project. The information is included in the hope that the relationships generated may be useful in
guiding future code developments. The sections are presented by code change then building type
rather than the building type, code change format used in the main section of the report.
A.1 Effect of proposed changes in water draw
Modelling approach: The objective is to update total daily hot water draw in the CanQuest archetype
models. The hot water draw will be parameterized by varying the hot water consumption,
l/person/day. The reduction in shower draw from the 2011 NECB is 20% whereas the reduction in
faucet draw from the 2011 NECB is 31%.
A.1.1 Large Office Building Archetype
For the large office archetype the per person daily draw was varied by +/- 30%. It was assumed that
the majority of draws are from faucets. This corresponds to the change in faucet discharge rates from
8.3 to 5.7 L/min for lavatory faucets. The baseline draw was obtained from the archetype models
provided. The only change in energy use was in the gas consumption used for hot water heating (and
correspondingly the total gas use). The change was linear; a given change in draw produces a given
change in gas consumption. Thus,
EUI = original EUI * (1 - Water draw * factor)
Component Factor R2
Hot water 0.940 1
Total 0.940 1
Factor, [ekWh/m2/y]/[L/person/day]
Water draw
Description Hot water Total
4.55 Baseline 4.29 85.3
3.185 -30% 3.01 84.0
5.915 30% 5.58 86.6
EUI, ekWh/m3/y
Water draw, L/person/day
127
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 38
Baseline ekWh/m2/y Draw 4.55 L/person/day
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 3.8 3.8 4.0 4.3 4.4 4.9
Total 122.6 133.2 138.8 140.4 144.6 153.5
Reduced ekWh/m2/y Draw 3.19 L/person/day
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 2.7 2.7 2.9 3.1 3.2 3.5
Total 121.6 132.1 137.8 139.2 143.4 152.1
Percent Change in EUI
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water -28.2 28.2 28.2 28.2 28.2 28.2
Total -0.79 -0.80 -0.74 -0.86 -0.86 -0.90
In summary, for a 30% reduction in water draw there is a maximum decrease in total EUI of
0.90%. The reduction in hot water heating is 28%, presumably representing the decrease in
hot water consumption corrected for the efficiency of the system.
Large Office Building: Percent change in EUIs for a 30% reduction in hot water draw, from
4.55 (2011 NECB) to 3.19 (2015 NECB) L/person/day.
128
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 39
A.1.2 Small Strip Mall Building Archetype
A reduction in hot water draw was not considered for the strip mall archetype. The amount of
energy used for domestic hot water for this type of building was considered to be negligible;
consequently changes in EUI were not estimated.
Percent Change in EUI
Strip Mall Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water n/a n/a n/a n/a n/a n/a
Total 0 0 0 0 0 0
A.1.3 Large Multi-Unit Residential Building Archetype
For the large MURB archetype the per person daily draw was varied by +/- 25%. It was assumed that
the mix of draws from faucets and showers averaged to a total reduction in hot draws of 25%. The
baseline draw was obtained from the archetype models provided. The only change in energy use
was in the gas consumption used for hot water heating (and correspondingly the total gas use).
Component Factor R2
Hot water 0.587 1
Total 0.587 1
Factor, [ekWh/m2/y]/[l/person/day]
Water draw
Description Hot water Total
59.1 Baseline 34.7 107
44.3 -25% 26.0 98.1
73.9 25% 43.3 115
EUI, ekWh/m3/y
Water draw, l/person/day
129
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 40
Baseline ekWh/m2/y Draw 59.1 L/person/day
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 43.3 43.9 47.0 50.7 52.5 58.8
Total 136.8 166.7 170.3 173.2 177.5 203.1
Reduced ekWh/m2/y Draw 44.3 L/person/day
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 36.9 37.5 40.1 43.3 44.8 50.2
Total 130.4 160.1 163.3 165.8 169.8 193.5
Percent Change in EUI
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water -14.7 -14.7 -14.7 -14.7 -14.7 -14.7
Total -4.64 -3.98 -4.11 -4.29 -4.34 -4.74
In summary, for a 25% reduction in water draw there is a maximum decrease in total EUI of
4.2%. The reduction in hot water heating is 13%.
Large Multi-Unit Residential Building: Percent change in EUIs for a 25% reduction in hot
water draw, from 59.1 (2011 NECB) to 44.3 (2015 NECB) l/person/day
130
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 41
A.1.4 Secondary School Building Archetype
For the secondary school archetype the per person daily draw was varied by +/- 25%. It was assumed
that the mix of draws from faucets and showers averaged to a total reduction in hot draws of 25%.
The baseline draw was obtained from the archetype models provide by Footprint [2]. The only
change in energy use was in the gas consumption used for hot water heating (and correspondingly
the total gas use).
Component Factor R2
Hot water 1.11 0.9719
Total 1.11 0.9719
Factor, [ekWh/m2/y]/[L/person/day]
Baseline ekWh/m2/y Draw 8.18 L/person/day
Secondary
School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 8.8 9.0 9.5 10.1 10.5 11.6
Total 151.6 182.5 193.6 203.0 214.4 246.6
Reduced ekWh/m2/y Draw 6.14 L/person/day
Secondary
School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water 6.4 6.5 6.9 7.3 7.6 8.4
Total 149.2 180.0 191.0 200.2 211.5 243.5
Percent Change in EUI
Secondary School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Hot Water -27.8 -27.8 -27.8 -27.8 -27.8 -27.8
Total -1.61 -1.37 -1.36 -1.38 -1.36 -1.26
Water draw
Description Hot water Total
8.18 Baseline 8.74 125
6.14 -25% 7.28 123
10.2 25% 11.9 128
EUI, ekWh/m3/y
Water draw, L/person/day
131
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 42
In summary, for a 25% reduction in water draw there is a maximum decrease in total EUI of
1.6%. The reduction in hot water heating is 28%.
Secondary School: Percent change in EUIs for a 25% reduction in hot water draw, from 8.18
(2011 NECB) to 6.14 (2015 NECB) L/person/day.
132
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 43
A.2 Effect of proposed changes in pipe insulation
Piping heat losses are not explicitly modelled in the archetype CanQuest models. To estimate the
effect on the overall building energy intensity the data provided in the PCF was used. Two tables
were presented in the PCF and it was decided to use the savings in the 50% table (as some of the
heat lost from piping will provide useful energy to the building as pipework is inside the thermal
envelope). A detailed model was not possible within the scope of this project as pipe runs,
enclosures and terminal devises would need to be explicitly modelled to capture the underlying
physics. However, the approach used is expected to provide a usable estimate of the savings
potential.
Floor plate Riser
perimeter+ 2*height
Archetype Length Width
Floor-
Floor
height #Floors
Saving
(W/m)
Saving
(W/m) Saving (W)
Saving
(kWh/year)
Saving
(kWh/m2/
year)
Office 36.6 36.6 3.9 10 1 3 380.4 3332.3 0.25
MURB 34.1 34.1 3 10 1 3 316.4 2771.7 0.24
School 202.5 202.5 4 1 1 3 834 7305.8 0.18
Strip Mall 36.6 36.6 3.9 1 0 0 0 0 0
In all cases the accumulated savings are less than 1 kWh/m2/year. To accumulate significant savings
would require an order of magnitude more piping in each building.
133
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 44
A.3 Effect of proposed changes in lighting power density
Modelling approach: Due to difficulties in duplicating the original modelling work the following
approach was taken for estimating the effect of changes in lighting loads.
1. The EUI results taken from [2] were assumed to be the baseline for the different archetypes
in the different zones.
2. For lighting power density studies the Zone 5 location, Windsor, was used for analysis. The
Windsor area has the highest number of cooling degree days (CDD10 and CDD18) in
Canada (ASHRAE 2013 Handbook – Fundamentals).
3. For each Zone 5 archetype three different LPDs were modelled. The 1997 MNECB LPDs
were used, as were the 2011 NECB values. The third LPD was the proposed 2015 change.
4. A linear relationship between the space heating and cooling EUI as well as the fan EUI was
derived expressing the change in EUI (ekWh/m2/y) given a unit change in LPD (W/m
2).
5. The change in heating, cooling, and fan energies for a given change in LPD was calculated
by modifying the original EUI results [2]. The change in total EUI was then calculated by
summing the various component EUIs.
A.3.1 Large Office Building Archetype
LPD Description Heating Cooling Fans
8.83 2015 value 89.1 9.87 3.66
9.7 2011 value 87.5 10.0 3.761
11.84 1.1 W/ft2 83.6 10.4 4.01
LPD, lighting power density, W/m2
Heating, Space heating EUI, ekWh/m2/y [*]
Cooling, Space cooling EUI, ekWh/m2/y [†]
Fan, Fans usage EUI, ekWh/m2/y;
Component Factor R2
Heating -1.84 1
Cooling 0.171 1
Fan 0.118 0.9998
Factor, [ekWh/m2/y]/[W/m
2]
* Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
† Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by
103 then dividing the result by the building area.
134
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 45
Thus,
EUI = original EUI + LPD * factor
2011 Levels ekWh/m2/y LPD 9.7 W/m
2
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 27.6 27.6 27.6 27.6 27.6 27.6
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps &
Aux. 12.3 12.6 13.3 12.7 12.5 12.5
Vent. Fans 17.5 17.7 17.6 17.9 18.3 19.3
Hot Water 3.8 3.8 4.0 4.3 4.4 4.9
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 20.5 27.4 33.8 37.7 41.6 50.5
Heat Reject. 0.5 1.0 0.8 0.5 0.5 0.4
Space Cool 14.3 16.9 15.6 13.5 13.5 12.1
Total 121.4 131.9 137.6 139.1 143.3 152.2
2015 Proposed Changes
‡ ekWh/m
2/y LPD 8.83 W/m
2
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 25.1 25.1 25.1 25.1 25.1 25.1
Task Lights 0 0 0 0 0 0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Ext. Usage 0 0 0 0 0 0
Pumps & Aux. 12.3 12.6 13.3 12.7 12.5 12.5
Vent. Fans 17.4 17.6 17.5 17.8 18.2 19.2
Hot Water 3.8 3.8 4 4.3 4.4 4.9
HP Supp. 0 0 0 0 0 0
Space Heat 22.1 29 35.4 39.3 43.2 52.1
Heat Reject. 0.5 1 0.8 0.5 0.5 0.4
Space Cool 14.2 16.8 15.5 13.4 13.4 12
Total 122.6 133.2 138.8 140.4 144.6 153.5
‡ This table is taken from the original EUI results.
135
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 46
Percent Change in EUI
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights -8.97 -8.97 -8.97 -8.97 -8.97 -8.97
Vent. Fans -0.59 -0.58 -0.58 -0.57 -0.56 -0.53
Space Heat 7.80 5.84 4.73 4.24 3.85 3.17
Space Cool -1.03 -0.88 -0.95 -1.10 -1.10 -1.22
Total -0.99 -0.84 -0.87 -0.79 -0.77 -0.73
In summary, for a 9% reduction in LPD there is a maximum decrease in total EUI of 1%.
The reduction in cooling loads is offset by an increase in heating loads due to the reduction
of internal gains. In fact the net change in space conditioning energy (heating, cooling, and
fans) is increased by 2-3%. The total decrease in EUI is attributable to a decrease in lighting
power. Also noteworthy is that for this case the equipment loads are equal to the lighting
loads, hence the reduction in internal gains is actually 5%.
Large Office Building: Percent change in EUIs for a 10% reduction LPD, from 9.7 (2011
NECB) to 8.8 (2015 NECB) W/m2
136
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 47
A.3.2 Small Strip Mall Building Archetype
LPD Description Heating Cooling Fans
13.5 2015 Value 108 7.32 10.5
15.07 2011 value 105 7.77 10.5
6.5 50% 2015 value 121 5.58 10.3
LPD, lighting power density, W/m2
Heating, Space heating EUI, ekWh/m2/y [§]
Cooling, Space cooling EUI, ekWh/m2/y [**]
Fans, Fan usage EUI, ekWh/m2/y;
Component Factor R2
Heating -1.90 1
Cooling 0.262 0.9998
Fan 0.019 0.9981
Factor, [ekWh/m2/y]/[W/m
2]
2011 Levels††
ekWh/m2/y LPD 15.1 W/m
2
Strip Mall Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 62.1 62.1 62.1 62.1 62.1 62.1
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 10.0 10.0 10.0 10.0 10.0 10.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps &
Aux. 1.1 1.0 1.1 1.4 1.4 1.5
Vent. Fans 23.2 23.5 23.9 23.9 24.3 24.8
Hot Water 0.0 0.0 0.0 0.0 0.0 0.0
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
§ Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
** Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by
103 then dividing the result by the building area.
†† This table is taken from the original EUI results.
137
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 48
Space Heat 88.2 122.9 160.6 183.9 213.8 285.3
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 1.5 8.0 5.5 2.2 2.9 1.5
Total 186.0 227.5 263.2 283.5 314.5 385.2
2015 Proposed Changes ekWh/m2/y LPD 13.5 W/m
2
Strip Mall Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 55.6 55.6 55.6 55.6 55.6 55.6
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 10.0 10.0 10.0 10.0 10.0 10.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 1.1 1.0 1.1 1.4 1.4 1.5
Vent. Fans 23.2 23.5 23.9 23.9 24.3 24.8
Hot Water 0.0 0.0 0.0 0.0 0.0 0.0
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 91.2 125.9 163.6 186.9 216.8 288.3
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 1.1 7.6 5.1 1.8 2.5 1.1
Total 182.2 223.6 259.3 279.6 310.6 381.3
Percent Change in EUI
Strip Mall Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights -10.4 -10.4 -10.4 -10.4 -10.4 -10.4
Vent. Fans -0.13 -0.13 -0.13 -0.13 -0.12 -0.12
Space Heat 3.38 2.43 1.86 1.62 1.40 1.05
Space Cool -27.4 -5.13 -7.47 -18.7 -14.2 -27.4
Total -2.06 -1.73 -1.49 -1.38 -1.25 -1.02
In summary, for a 10% reduction in LPD there is a maximum decrease in total EUI of 2%.
The reduction in cooling loads is offset by an increase in heating loads due to the reduction
of internal gains. In fact the net change in space conditioning energy (heating, cooling, and
fans) is increased by 1-2%. The total decrease in EUI is attributable to a decrease in lighting
power.
138
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 49
Strip Mall: Percent change in EUIs for a 10% reduction LPD, from 15.1 (2011 NECB) to
13.5 (2015 NECB) W/m2
139
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 50
A.3.3 Large Multi-Unit Residential Building Archetype
LPD Description Heating Cooling Fans
5.5 2015 Value 100 4.85 6.33
6.5 2011 value 99.5 5.06 6.37
3.9 Existing model 101 4.605 6.28
LPD, lighting power density, W/m2
Heating, Space heating EUI, ekWh/m2/y [‡‡]
Cooling, Space cooling EUI, ekWh/m2/y [§§]
Fans, Fan usage EUI, ekWh/m2/y;
Component Factor R2
Heating -0.688 0.9671
Cooling 0.179 0.9944
Fan 0.037 0.9999
Factor, [ekWh/m2/y]/[W/m
2]
2011 Levels ekWh/m2/y LPD 6.5 W/m
2
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 14.7 14.7 14.9 14.9 14.9 14.9
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps &
Aux.
5.5 8.3 7.5 9.0 9.1 8.3
Vent. Fans 7.3 8.3 24.7 26.1 26.9 27.8
Hot Water 43.3 43.9 47.0 50.7 52.5 58.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 39.3 56.3 37.6 40.0 37.8 57.3
Heat Reject. 0.1 0.6 0.5 0.3 0.4 0.4
Space Cool 5.1 12.9 16.6 10.8 14.5 13.2
Total 141.1 170.8 174.6 177.6 181.9 206.5
‡‡ Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by 10
6 then by
0.0029307107, then dividing the result by the building area.
§§ Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by 10
3 then
dividing the result by the building area.
140
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 51
2015 Proposed Changes ekWh/m2/y LPD 5.5 W/m
2
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 12.5 12.5 12.6 12.6 12.6 12.6
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 5.5 8.3 7.5 9.0 9.1 8.3
Vent. Fans 7.3 8.3 24.7 26.1 26.9 27.8
Hot Water 43.3 43.9 47.0 50.7 52.5 58.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 40.2 57.2 38.5 40.9 38.7 58.2
Heat Reject. 0.1 0.6 0.5 0.3 0.4 0.4
Space Cool 4.8 12.6 16.3 10.5 14.2 12.9
Total 139.4 169.1 172.9 175.9 180.2 204.8
Percent Change in EUI
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights -15.4 -15.4 -15.4 -15.4 -15.4 -15.4
Vent. Fans -0.60 -0.53 -0.18 -0.17 -0.16 -0.16
Space Heat 2.15 1.50 2.25 2.11 2.24 1.48
Space Cool -4.30 -1.69 -1.31 -2.02 -1.50 -1.65
Total -1.19 -0.98 -0.98 -0.96 -0.94 -0.83
In summary, for a 15% reduction in LPD there is a maximum decrease in total EUI of 1.2%.
The reduction in cooling loads is offset by an increase in heating loads due to the reduction
of internal gains. In fact the net change in space conditioning energy (heating, cooling, and
fans) is increased by 1%. The total decrease in EUI is attributable to a decrease in lighting
power. Also noteworthy is that for this case the equipment load is double the lighting load,
hence the large reduction in LPD produces little change in total EUI.
141
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 52
Large MURB: Percent change in EUIs for a 15% reduction LPD, from 6.5 (2011 NECB) to
5.5 (2015 NECB) W/m2.
142
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 53
A.3.4 Secondary School Archetype
LPD Description Heating Cooling Fans
9.4 2015 Value 61.4 3.614 23.9
10.7 2011 value 58.9 3.84 24.1
5.38 0.5 W/ft2 69.3 3.094 23.4
LPD, lighting power density, W/m2
Heating, Space heating EUI, ekWh/m2/y [***]
Cooling, Space cooling EUI, ekWh/m2/y [†††]
Fans = Fans usage EUI, ekWh/m2/y;
Component Factor R2
Heating -1.94 0.9999
Cooling 0.137 0.9951
Fan 0.129 0.9998
Factor, [ekWh/m2/y]/[W/m2]
2011 Levels ekWh/m2/y LPD 10.7 W/m2
Secondary School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Kitchen 26 28.9 31 32.9 34.8 40
Area Lights 26.7 26.7 26.7 26.7 26.7 26.7
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 2.6 3.3 3.3 3.5 3.5 3.5
Vent. Fans 24.3 24.4 25.4 25.6 25.7 25.6
Hot Water 8.8 9.0 9.5 10.1 10.5 11.6
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 52.5 76.1 85.1 93.4 101.9 129.2
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 4.2 7.6 6.1 4.3 4.8 3.6
Total 152.0 182.9 194.0 203.4 214.8 247.1
*** Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
††† Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by
103 then dividing the result by the building area.
143
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 54
2015 Proposed Changes ekWh/m2/y LPD 9.4 W/m2
Secondary School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Kitchen 26 28.9 31 32.9 34.8 40
Area Lights 23.5 23.5 23.5 23.5 23.5 23.5
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 2.6 3.3 3.3 3.5 3.5 3.5
Vent. Fans 24.1 24.2 25.2 25.4 25.5 25.4
Hot Water 8.8 9.0 9.5 10.1 10.5 11.6
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 55.0 78.6 87.6 95.9 104.4 131.7
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 4.0 7.4 5.9 4.1 4.6 3.4
Total 151.0 181.9 193.0 202.4 213.8 246.1
Percent Change in EUI
Secondary School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights -12.2 -12.2 -12.2 -12.2 -12.2 -12.2
Vent. Fans -0.69 -0.69 -0.66 -0.66 -0.65 -0.66
Space Heat 4.81 3.32 2.97 2.70 2.48 1.95
Space Cool -4.26 -2.35 -2.93 -4.16 -3.72 -4.98
Total -0.70 -0.58 -0.55 -0.53 -0.50 -0.43
In summary, for a 12% reduction in LPD there is a maximum decrease in total EUI of
0.70%. The reduction in cooling loads is offset by an increase in heating loads due to the
reduction of internal gains. In fact the net change in space conditioning energy (heating,
cooling, and fans) is increased by 3%. The total decrease in EUI is attributable to a decrease
in lighting power. Also noteworthy is that for this case the equipment load is double the
lighting load, hence the large reduction in LPD produces little change in total EUI.
144
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 55
Secondary School: Percent change in EUI’s for a 12% reduction LPD, from 10.7 (2011
NECB) to 9.4 (2015 NECB) W/m2.
A.4 Effect of proposed changes in limits to pumping power
Modelling approach: The following approach was taken for estimating the effect of changes in
pumping power.
1. The EUI results taken from [2] were assumed to be the baseline for the different archetypes
in the different zones. The proposed limits to pumping power were incorporated into the
models, specifically the proposed new Sentence 5.2.6.3.1 clauses through d.
a. 14 Wmotor power per kWthermal-peak for cooling systems,
b. 4.5 Wmotor power per kWthermal-peak for heating systems,
c. 12 Wmotor power per kWthermal-peak for heat rejection systems, and
d. 22 Wmotor power per kWthermal-peak for water-source heat pumps systems.
2. The pumping power values for the report [2] were calculating by applying the above limits to
the installed capacity of boilers, chillers, and cooling towers. For example, the installed
capacity of the boilers (two) for the large office archetype model located in Windsor is 3.74
mBtu/h, which translates into a pumping power limit of 4.94 kW for the hot water loop. The
installed capacity was estimated from a preliminary loads calculation.
3. For each Zone 5 archetype four different pumping power criteria were modelling. The
proposed 2015 restrictions were used, as were one-half and twice the 2015 limits. In the
fourth case the pumping power values were auto-sized by the software. The auto-sized
values were considered to be the NECB 2011 baseline (i.e. there were no restrictions in the
2011 code).
145
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 56
4. Linear relationships between various EUIs were derived expressing the change in EUI
(ekWh/m2/y) given a unit change in pumping power (kW).
5. The change in EUI for a given change in pumping power was calculated by modifying the
original EUI results [2]. The change in total EUI was then calculated by summing the
various component EUIs.
A.4.1 Large Office Building Archetype
Pumping Power Description Heating Cooling Heat Reject. Pumps
39.04 2015 value 57.9 14.9 1.29 10.3
19.52 50% NECB 58.7 14.4 1.26 5.46
78.08 200% NECB 56.8 15.8 1.33 17.8
50.43 CanQuest auto-size 58.6 15.2 1.30 11.6
Total Pumping power of all pumps covered by 5.2.6.3.1 , kW
Heating, Space heating EUI, ekWh/m2/y [‡‡‡]
Cooling, Space cooling EUI, ekWh/m2/y [§§§]
Heat rejection, ekWh/m2/y
Total Pump energy, ekWh/m2/y;
Component Factor R2
Heating -0.032 0.9967
Cooling 0.024 0.9955
Heat rejection 0.001 0.9908
Pump energy 0.208 0.9914
Factor, [ekWh/m2/y]/kW
Thus,
EUI = original EUI + Pump power * factor
‡‡‡ Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
§§§ Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by
103 then dividing the result by the building area.
146
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 57
Auto sized
Archetype ekWh/m2/y
Pump energy 50.4 kW for
Z5
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 25.1 25.1 25.1 25.1 25.1 25.1
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 15.0 15.7 15.1 14.9 14.9 15.0
Vent. Fans 17.6 17.5 17.8 18.2 19.2 17.6
Hot Water 3.8 4.0 4.3 4.4 4.9 3.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 28.6 35.0 38.9 42.8 51.7 28.6
Heat Reject. 1.0 0.8 0.5 0.5 0.4 1.0
Space Cool 17.1 15.8 13.7 13.7 12.3 17.1
Total 135.5 141.2 142.7 146.9 155.8 135.5
2015 Proposed Changes ekWh/m2/y
Pump energy 39.0 kW for Z5
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 25.1 25.1 25.1 25.1 25.1 25.1
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 27.3 27.3 27.3 27.3 27.3 27.3
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 12.3 12.6 13.3 12.7 12.5 12.5
Vent. Fans 17.4 17.6 17.5 17.8 18.2 19.2
Hot Water 3.8 3.8 4.0 4.3 4.4 4.9
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 22.1 29.0 35.4 39.3 43.2 52.1
Heat Reject. 0.5 1.0 0.8 0.5 0.5 0.4
Space Cool 14.2 16.8 15.5 13.4 13.4 12.0
Total 122.6 133.2 138.8 140.4 144.6 153.5
147
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 58
Percent Change in EUI
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Pumps & Aux. -16.2 -15.9 -15.2 -15.8 -16.0 -16.0
Space Heat 1.69 1.28 1.05 0.94 0.86 0.71
Heat Reject. -2.80 -1.42 -1.77 -2.80 -2.80 -3.48
Space Cool -1.89 -1.61 -1.74 -2.01 -2.01 -2.23
Total -1.92 -1.70 -1.70 -1.61 -1.57 -1.48
In summary, for a 23% reduction in pumping power in Zone 5 there is a decrease in total
EUI of 1.7%. The reduction in cooling loads is offset by an increase in heating loads due to
the reduction of internal gains. The maximum decrease in energy is predicted to be in Zone
4, around 1.9% of the 2011 EUI.
Large Office Building: Percent change in EUI’s for a reduction pumping power, 2011
NECB auto-sized to 2015 NECB proposed limits.
148
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 59
A.4.2 Small Strip Mall Building Archetype
A reduction in pumping power was not considered for the strip mall archetype. The HVAC system
in each store was a packaged roof-top unit with natural gas fired heating and DX cooling, providing
constant volume ventilation to the space. Consequently there were no primary circulation loops
defined.
Percent Change in EUI
Strip Mall Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Pumping power n/a n/a n/a n/a n/a n/a
Total 0 0 0 0 0 0
A.4.3 Large Multi-Unit Residential Building Archetype
In determining the pumping power for the water loop heat pump pump (WHLP Pump) the
pump was sized according the capacity of the heating portion (the boilers). The WLHP
provides both heat and cooling to the residential units. The logic for this was that the pump
should be oversized or right sized for heating and undersized for cooling (i.e. the pump
should run flat out for cooling applications).
Pumping Power Description Heating Pumps
3.79 2015 value 20.4 2.31
7.58 200% NECB 19.7 3.59
11.4 300% NECB 19.0 4.69
4.89 CanQuest auto-size 20.2 2.70
Total Pumping power of all pumps covered by 5.2.6.3.1 , kW
Heating, Space heating EUI, ekWh/m2/y [****]
Cooling, Space cooling EUI, ekWh/m2/y [††††]
Heat rejection, ekWh/m2/y
Total Pump energy, ekWh/m2/y;
Component Factor R2
Heating -0.181 0.9976
Pump energy 0.314 0.9982
Factor, [ekWh/m2/y]/[W/m
2]
**** Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
†††† Other EUIs are calculated from the CanQuest output (in kWh x 10
3) by multiplying the result by
103 then dividing the result by the building area.
149
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 60
Auto-sized archetype ekWh/m2/y
Pump energy 4.69 kW for
Z5
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 8.9 8.9 9.0 9.0 9.0 9.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 5.8 8.6 7.8 9.3 9.4 8.6
Vent. Fans 7.2 8.2 24.6 26.0 26.8 27.7
Hot Water 43.3 43.9 47.0 50.7 52.5 58.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 41.3 58.3 39.6 42.0 39.8 59.3
Heat Reject. 0.1 0.6 0.5 0.3 0.4 0.4
Space Cool 4.5 12.3 16.0 10.2 13.9 12.6
Total 136.9 166.6 170.3 173.3 177.6 202.2
2015 Proposed Changes ekWh/m2/y
Pump energy 3.79 kW for
Z5
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Area Lights 8.9 8.9 9.0 9.0 9.0 9.0
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 25.8 25.8 25.8 25.8 25.8 25.8
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 5.5 8.3 7.5 9.0 9.1 8.3
Vent. Fans 7.2 8.2 24.6 26.0 26.8 27.7
Hot Water 43.3 43.9 47.0 50.7 52.5 58.8
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 41.5 58.5 39.8 42.2 40.0 59.5
Heat Reject. 0.1 0.6 0.5 0.3 0.4 0.4
Space Cool 4.5 12.3 16.0 10.2 13.9 12.6
Total 136.8 166.8 170.3 173.2 177.5 203.2
150
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 61
Percent Change in EUI
Large MURB Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Pumps & Aux. -4.87 -3.28 -3.62 -3.03 -3.00 -3.28
Space Heat 0.39 0.28 0.41 0.39 0.41 0.27
Total -0.09 -0.07 -0.01 -0.07 -0.07 -0.06
In summary, for a 19% reduction in pumping power in Zone 5 there is a decrease in total
EUI of 0.1%. Pumping energy represents a small part of the overall EUI, 4 to 5% of the
energy use.
Large MURB: Percent change in EUIs for a reduction pumping power, 2011 NECB auto-
sized to 2015 NECB proposed limits.
151
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 62
Secondary School Archetype: (note Zone 4 was used as the base zone)
Pumping Power Description Heating Pumps
5.18 Footprint[2] at 4.686
kW] value 52.8 2.61
2.59 50% Footprint 53.9 1.69
10.4 200% Footprint 51.2 4.07
3.65 CanQuest auto-size 53.4 2.09
Total Pumping power of all pumps covered by 5.2.6.3.1 , kW
Heating, Space heating EUI, ekWh/m2/y [‡‡‡‡]
Pump energy, ekWh/m2/y;
Component Factor R2
Heating -0.338 0.9930
Pump energy 0.303 0.9968
Factor, [ekWh/m2/y]/kW
NECB Proposed ekWh/m2/y
Pump energy 7.83 kW for
Z4
Secondary school Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Area Lights 25.4 25.4 25.4 25.4 25.4 25.4
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 3.4 4.1 4.1 4.3 4.3 4.3
Vent. Fans 24.2 24.3 25.3 25.5 25.6 25.5
Hot Water 8.8 9.0 9.5 10.1 10.5 11.6
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 52.6 76.2 85.2 93.5 102.0 129.3
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 4.1 7.5 6.0 4.2 4.7 3.5
Total 151.7 182.6 193.7 203.1 214.5 246.6
‡‡‡‡ Space heating is calculated from the CanQuest output (in Btu x 10
6) by multiplying the result by
106 then by 0.0029307107, then dividing the result by the building area.
152
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 63
2015 Footprint Results ekWh/m2/y Pump energy 5.18 for Z4
Secondary School Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Kitchen 26.0 28.9 31.0 32.9 34.8 40.0
Area Lights 25.4 25.4 25.4 25.4 25.4 25.4
Task Lights 0.0 0.0 0.0 0.0 0.0 0.0
Misc. Equip. 7.0 7.0 7.0 7.0 7.0 7.0
Ext. Usage 0.0 0.0 0.0 0.0 0.0 0.0
Pumps & Aux. 2.6 3.3 3.3 3.5 3.5 3.5
Vent. Fans 24.2 24.3 25.3 25.5 25.6 25.5
Hot Water 8.8 9.0 9.5 10.1 10.5 11.6
HP Supp. 0.0 0.0 0.0 0.0 0.0 0.0
Space Heat 53.5 77.1 86.1 94.4 102.9 130.2
Heat Reject. 0.0 0.0 0.0 0.0 0.0 0.0
Space Cool 4.1 7.5 6.0 4.2 4.7 3.5
Total 151.6 182.5 193.6 203.0 214.4 246.6
Percent Change in EUI
Large Office Zone 4 Zone 5 Zone 6 Zone 7a Zone 7b Zone 8
Pumps & Aux. 31.3 24.6 23.2 23.2 23.2 23.2
Space Heat -1.70 -1.18 -1.06 -0.96 -0.88 -0.70
Total -0.06 -0.05 -0.05 -0.05 -0.04 -0.00
The results for the secondary school are atypical. First, the pump power limit in the
proposed NEB 2015 is higher than the Footprint report results by 34%. Consequently the
change in pumping EUI is positive. Second, the increased pumping energy reduces the space
heating EUI by about 1.7%. There was no change in cooling since the HW pumps should
not be running when the AC is operating. The end result of the increase in pumping power is
to decrease the total EUI by at most 0.06%.
153
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 64
Secondary school: Percent change in EUIs for an increase in pumping power from Footprint
results to 2015 NECB proposed limits.
A.4.4 Secondary School Archetype
Modelling approach: The following approach was taken for estimating the effect of changes in
pumping power.
1. The EUI results taken from “ENERGY MODELLING REPORT MODELLING OF THE
NATIONAL ENERGY CODE FOR BUILDINGS 2015 FINAL REPORT-REVISION 2”
[§§§§] were assumed to be the baseline for the different archetypes in the different zones.
The proposed limits to pumping power were incorporated into the models, specifically the
proposed new Sentence 5.2.6.3.1 clauses through d.
a. 14 Wmotor power per kWthermal-peak for cooling systems,
b. 4.5 Wmotor power per kWthermal-peak for heating systems,
c. 12 Wmotor power per kWthermal-peak for heat rejection systems, and
d. 22 Wmotor power per kWthermal-peak for water-source heat pumps systems.
2. The pumping power values for the report [2] were calculating by applying the above limits to
the installed capacity of boilers, chillers, and cooling towers. For example, the installed
capacity of the boilers (two) for the large office archetype model located in Windsor is 3.74
mBtu/h, which translates into a pumping power limit of 4.94 kW for the hot water loop. The
installed capacity was estimated from a preliminary loads calculation.
§§§§ “ENERGY MODELLING REPORT MODELLING OF THE NATIONAL ENERGY CODE
FOR BUILDINGS 2015 FINAL REPORT-REVISION 2”
154
Simulation study of Energy Savings between NECB 2011 and NECB 2015
A1-006606-01 final report 65
3. For each Zone 5 archetype four different pumping power criteria were modelled. The
exception here was the secondary school archetype where Zone 4 was used (there was little
to no space heating when the other zones were run). The proposed 2015 restrictions were
used, as were one-half and twice the 2015 limits. In the fourth case the pumping power
values were auto-sized by the software. The auto-sized values were considered to be the
NECB 2011 baseline (i.e. there were no restrictions in the 2011 code).
4. Linear relationships between various EUIs were derived expressing the change in EUI
(ekWh/m2/y) given a unit change in total pumping power (kW).
5. The change in EUI for a given change in total pumping power was calculated by modifying
the original EUI results [2]. The change in total EUI was then calculated by summing the
various component EUIs.
155